Shear Retrofitting of RC Beams: February 2017
Shear Retrofitting of RC Beams: February 2017
net/publication/316093854
CITATIONS READS
0 472
4 authors, including:
P. Markandeya Raju
Maharaj Vijayaram Gajapati Raj College of Engineering
60 PUBLICATIONS 68 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by P. Markandeya Raju on 14 April 2017.
P.Markandeya Raju,
Professor of Civil Engineering, MVGR College of Engineering (A), Vizianagaram, AP
M.Pavan Kumar,
Asst. Professor of Civil Engineering, SVP Engineering College, Visakhapatnam, AP
Abstract: Studies on rehabilitation and retrofitting are gaining importance due to the
need for restoration of partially damaged structures due to wind load and earthquake.
This project presents an experimental investigation on retrofitting the capacity of
damaged RC beams. In this work retrofitting of shear deficient RCC beam using
diagonal stitching method will be studies. Nine beams of size 120mm x 210mm x
1500mm were cast. Out of this one control beam was used and remaining 8 beams are
categorized in to two sets of beams with each set containing 4 beams as shear deficient
beams. Out of these 8 beams, two beams were tested without retrofitting and remaining
six beams were shear deficient used for retrofitting. Control Beam designed for ultimate
shear & flexure was loaded up to ultimate load in the Loading frame (of capacity 1000
kN) using a Hydraulic jack of 500 kN capacity. Shear deficient beams were retrofitted
using diagonal stitching and cover concrete was bonded Nitto bond. Load deflection
behaviour of beams, retrofitted with different layers of stitched mat was compared. All
the beams were casted using M25 grade concrete and Fe500 steel. After the 28 days of
curing they were tested and kept safe for retrofitting. It was observed that stitching
method is effective in restoring the capacity of damaged beams. Among all the shear
retrofitting techniques, diagonal stitching is effective and easy to implement.
www.ijar.org.oin 86
International Journal of Academic Research
ISSN: 2348-7666; Vol.4, Issue-2 (1), February, 2017
Impact Factor: 4.535; Email: [email protected]
www.ijar.org.oin 87
International Journal of Academic Research
ISSN: 2348-7666; Vol.4, Issue-2 (1), February, 2017
Impact Factor: 4.535; Email: [email protected]
www.ijar.org.oin 88
International Journal of Academic Research
ISSN: 2348-7666; Vol.4, Issue-2 (1), February, 2017
Impact Factor: 4.535; Email: [email protected]
especially when estimating the shear and mixed followed by gradual addition of
strength. Therefore, in the present water and mixing. Before casting the
experimental program, all nine beams specimens, workability of the mixes was
were prepared so that the concrete found by Slump cone test. The specimens
strength was nearly the same are left in the moulds undisturbed at
(compressive strength of concrete cubes room temperature for about 24 hours
used to make the beams, after 28 days, after casting. The specimens are then
was in and around 30 MPa.) . The removed from the moulds and
specimens were cured under the same immediately transferred to the curing
conditions to reduce the variation in pond containing clean and fresh water
concrete strength. and cured for required period as per IS
516-1969.
Mix Proportions for M25 Grade
concrete: Mix design of M25 grade Shear Retrofitting Methodology
concrete was carried out in accordance
Shear-deficient RC beams are retrofitted
with IS 10262: 2009 and following mix
by using Diagonal Stitching (DS).
proportions for 1 m3 concrete were
Retrofitting is done by providing links
obtained .
across the possible shear crack position.
Cement 385 kg. Six specimens are retrofitted in two
series A & B (by providing links spaced
Water 197 litres.
equally across the possible diagonal crack
Coarse aggregate 1166 kg. line). The increased shear strength in
retrofitted beams vs. un retrofitted
Fine aggregate 714 kg.
(respective shear deficient control beams)
Preparation of Testing Specimens: beams shear strength and original control
Mixing of ingredients is done in pan beam (both flexure & shear) is
mixer of capacity 40 liters. The determined experimentally to assess the
cementitious materials are thoroughly shear increasing capacity of a beam by a
blended and then the aggregate is added given percentage.
Table 1: Details of No. of beams used with & with out retrofitting
No. of Vertical stirrups
Sl. Designation Without With
/Shear reinforcement
No. of Beams Retrofitting Retrofitting
spacing
C
1 11/144 1 ---
(Control)
2 A series 5/360 1 3
3 B series 8/205 1 3
www.ijar.org.oin 89
International Journal of Academic Research
ISSN: 2348-7666; Vol.4, Issue-2 (1), February, 2017
Impact Factor: 4.535; Email: [email protected]
Fig.1 Longitudinal and cross section details of Control beam with reinforcement
Diagonal Stitching (DS) Method Shear reinforcement links of 6mm
diameter are provided in holes of 8 mm
In this method, the beams are retrofitted
diameter and 50 mm deep. These are
with the help of additional reinforcement
provided at all possible shear crack path
to the shear deficient beams. In order to
lines on either side of beam faces as
resist shear along the crack, it is
shown in the figure. Beams are chipped
necessary to use diagonal stitching and
and the dust is removed completely and
concrete is stitched by 6mm dia steel rods
cleaned. The holes shall be cleaned with
diagonally along the possible crack path
compressed air and water jet to remove
with stitches of different lengths
all the dust etc. and then the shear links
(60,100,160mm) of u-shaped bends are
are fixed in the holes using CEBEX 100
used for retrofitting in shear that are
anchor grout material. The links are
embedded into up to specified depth .
made in ‘U’ shaped so that the horizontal
Holes are drilled on the shear deficient
portion is perpendicular to the crack and
beams and reinforcement links are
placed across the possible shear crack.
provided perpendicular to the possible
NITTO - bond (a chemical agent which is
shear crack up to a depth of 50 mm in to
used for the bonding between old and
the beam and an extra cover concrete is
new concrete) applied on the surface.
provided on two sides of reinforcement.
Over the diagonal shear links concrete
cover is maintained throughout the
beam.
www.ijar.org.oin 90
International Journal of Academic Research
ISSN: 2348-7666; Vol.4, Issue-2 (1), February, 2017
Impact Factor: 4.535; Email: [email protected]
120 S1
80 S2
40 S3
0 S4
0 1 2 3 4 5 6
DEFLECTION(mm)7 8 9 10
Fig.7 Load vs. deflection for Comparison of Control Beam with Beam Series-B:
www.ijar.org.oin 91
International Journal of Academic Research
ISSN: 2348-7666; Vol.4, Issue-2 (1), February, 2017
Impact Factor: 4.535; Email: [email protected]
Series-B
160
120 CONTROL
S5
LOAD (kN)
80 S6
S7
40 S8
0
0 1 2 3 4 5 6 7 8 9 10 11
DEFLECTION (mm)
www.ijar.org.oin 92
International Journal of Academic Research
ISSN: 2348-7666; Vol.4, Issue-2 (1), February, 2017
Impact Factor: 4.535; Email: [email protected]
www.ijar.org.oin 93