This document discusses various ground improvement techniques, including mechanical, hydraulic, physical/chemical, and inclusion/confinement methods. It focuses on dewatering techniques, specifically sumps and ditches. Sumps and ditches involve collecting groundwater in excavated pits (sumps) and channels (ditches) and pumping it out. While economical for shallow excavations in permeable soils, this method is limited to lowering the water table up to 8 meters and risks slope instability in steep slopes or high heads. Deeper dewatering requires pre-drainage methods like deep wells, well points, eductors, or horizontal wells.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
86 views

Ground Improvement Techniques UNIT-1

This document discusses various ground improvement techniques, including mechanical, hydraulic, physical/chemical, and inclusion/confinement methods. It focuses on dewatering techniques, specifically sumps and ditches. Sumps and ditches involve collecting groundwater in excavated pits (sumps) and channels (ditches) and pumping it out. While economical for shallow excavations in permeable soils, this method is limited to lowering the water table up to 8 meters and risks slope instability in steep slopes or high heads. Deeper dewatering requires pre-drainage methods like deep wells, well points, eductors, or horizontal wells.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 23

GROUND IMPROVEMENT TECHNIQUES

UNIT-1
Introduction

Need for Engineering ground Improvement

When a project encounters difficult foundation conditions, possible alternate solutions are:

Avoid the particular site


Design the planned structure accordingly.

Use a soft foundation supported by piles, design a very stiff structure which is not damaged
by settlements

Remove and replace unsuitable soils.


Attempt to modify the existing ground

Classification of Ground modification Techniques:

4 Groups of Ground Improvement techniques

Mechanical Modification: Soil density is increased by the application of mechanical force,


including compaction of surface layers by static vibratory such as compact roller and plate
vibrators.

Hydraulic Modification:

Free pore water is forced out of soil via drains or wells.


Course grained soils; it is achieved by lowering the ground water level through
pumping from boreholes, or trenches.
In fine grained soils the long term application of external loads (preloading) or
electrical forces (electrometic stabilization)

Physical and chemical modification:

Stabilization by physical mixing adhesives with surface layers or columns of soil .Adhesive
includes natural soils industrial by-products or waste.

Materials or cementations or other chemicals which react with each other and/or the
ground.

When adhesives are injected via boreholes under pressure into voids within the ground or
between it and a structure the process is called grouting. Soil stabilization by heating and by
freezing the ground is considered thermal methods of modifications

Modification by inclusions and confinement:

Reinforcement by fibers, strips bars meshes and fabrics imparts tensile strength to a
constructed soil mass. In-situ reinforcement is achieved by nails and anchors. Stable earth
retaining structure can also be formed by confining soil with concrete, Steel, or fabric
elements.
Suitability, Feasibility and Desirability

The choice of a method of ground improvement for a particular object will depend on the
following factors.

Type and degree of improvement required


Type of soil , geological structure, seepage conditions
cost
Availability of equipment and materials and the quality of work required
Construction time available
Possible damage to adjacent structures or pollution of ground water resources
Durability of material involved ( as related to the expected life of structure for a
given environmental and stress conditions)
Toxicity or corrosivity of any chemical additives.
Reliability of method of analysis and design.
Feasibility of construction control and performance measurements If soil is moist,
freezing is applicable to all type of soil.

Dewatering
Dewatering involves controlling groundwater by pumping, to locally lower groundwater
levels in the vicinity of the excavation.

The application of sumps and ditches within an excavation is one of the elementary method
of dewatering employed in construction. The water entering these installed units can be
pumped out.

The general procedure of dewatering with sumps and ditches is depicted in the figure-1.

Fig.1. Dewatering Method by the Installation of Sumps and Ditches

The sump is located below the ground level of the excavation as shown in figure-1, at one or
more corners or the sides. The procedure involves the cutting of a small ditch around the
bottom of the excavation, that is falling towards the sump.
The sumps is the name given for the shallow pits that are dug along the periphery of the
excavation or the drainage area, which is named as ditches. Under the action of gravity, the
water from the slopes will flow to the sumps. The sumps collect the water and are later
pumped out.

Significant amount of seepage can result in raveling or sloughing or softening of the slope in
the lower part. The slump bottom may also be subjected to piping.
The above problems can be solved by the use of inverted filter that is of many layers. These
have coarser material in successive layers from the bottom of the sump pit to the upward
direction. This is a simple method used for dewatering shallow excavations that have coarse
grained soils or the soils that have permeability that is greater than 10-3 cm/sec.

Suitability of Sumps and Ditches for Dewatering of Excavations


If the construction demands for lowering the water table or the ground water head of the
area to a depth greater than 1 feet, the method of sumps and ditches is not suitable.

If sumps and ditches are employed for greater depth lowering, seepage will be prominent
that will result in the instability of the excavation slopes. This wrong decision will also bring
effects that are detrimental for the integrity of the foundation soils of the area.

In order to overcome the problems that arise due to minor raveling and to support the
collection of seepage water, it is recommended to employ filter blankets or drains in the
sump and ditch system installed.

Use of Sumps and Ditches in Cofferdams


In areas that are confined, the common method of excavation that is followed is the driving
of a sheet pile that is either wood or steel, below the subgrade elevation. Then the bracing
is installed and proceeds with the excavation of earth. Later the water that seeps into the
cofferdam area is pumped out.

The use of sumps and ditches in the dewatering of sheet excavation face the limitation
similar to that of open excavations. The formation of hydraulic heave at the bottom of the
excavation which is found to be very dangerous can be reduced by the driving of sheeting
into the impermeable strata that is underlying. This can help in the reduction of seepage
into the bottom of the excavation.

Those excavation carried out below the water table can be effectively conducted with the
help of sheeting and sump. This is merely dependent on the site conditions. The hydrostatic
pressure and toe support are the two factors that is to be considered important while
designing the sheeting and the bracing.

The construction process and the pumping out activities can be conducted smoothly by
covering the bottom of the excavation by means of a inverted sand and gravel filter blanket.

Advantages of Sumps and Ditches


The advantages of Sumps and Ditches are:

1. The method is widely used. It is appropriate for small depth lowering.


2. This method is found to be most economical one among dewatering systems while
considering the installation and the maintenance procedures
3. This method can be applied for most of the soil and rock conditions.
4. The site is mostly recommended where boulders or massive obstructions are met
within the ground.
5. The greatest depth up to which the water table can be lowered by this method is 8m

Disadvantages of Open Sump and Ditches


The disadvantages of this method are:

1. In areas where there is high heads or steep slopes, the method is not demanded.
This method will bring collapse of the slopes and cause dangerous problems
2. The use of sumps and ditches in open or timbered excavation will bring risk in the
stability of the base.

The simplest form of dewatering is sump pumping, where groundwater is allowed to enter
the excavation where it is then collected in a sump and pumped away by robust solids
handling pumps. Sump pumping can be effective in many circumstances, but seepage into
the excavation can create the risk of instability and other construction problems.

To prevent significant groundwater seepage into the excavation and to ensure stability of
excavation side slopes and base it may be necessary to lower groundwater levels in advance
of excavation. This is known as ‘pre-drainage’.

Pre-drainage methods include:

1. Deep wells
2. WellPoint’s
3. Eductors
4. Vacuum wells
5. Horizontal wells

Other specialist dewatering techniques are also sometimes used:

1. Relief wells
2. Artificial recharge
3. Siphon drains

The selection of the dewatering technique or techniques at a particular site or country will
depend on many factors. Groundwater Engineering’s team has decades of experience in
dewatering projects around the world, and we provide a complete design and installation
service to control your groundwater problems.

DEEP WELLS
A deep well system consists of an array of bored wells pumped by submersible pumps.
Pumping from each well lowers the groundwater level and creates a cone of depression or
drawdown around itself. Several wells acting in combination can lower groundwater level
over a wide area beneath an excavation. Because the technique does not operate on a
suction principle, large drawdowns can be achieved, limited only by the depth of the wells,
and the hydrogeological conditions.

The wells are generally sited just outside the area of proposed excavation, and are pumped
by electric submersible pumps near the base of each well. Water collection pipes, power
supply generators, electrical controls and monitoring systems are located at the surface.
This is shown in figure-1. Here the excavation can be pre*drained for the complete depth.

Fig.1: Deep Well Dewatering System


Working and Arrangement of Deep Well System
The deep wells arrangement for the purpose of dewatering is similar to that for commercial
water wells. These systems will make use of a screen that have a diameter of 6 to 4 inches
with lengths ranging up to 300 feet.

When such a system is installed, a filter is placed around the screen. This arrangement helps
to prevent the infiltration of the foundation materials into the well. The installation of filter
also helps to improve the yield.
In order to dewater small deep excavations, the deep well systems can be used in
conjunction with the deep wells. This is applied for related works of tunnels, caissons sunk,
shafts and the areas with fine grained sand or stratified soils that are pervious. In areas,
there are rock layer below the ground table this method work best.

An increase in hydraulic gradient to the well because of the use of vacuum creates a vacuum
within the surrounding. This phenomenon avoids seepage from the perched water into the
excavation.

The installation of deep well system incorporating vacuum is shown in figure-2. This type
requires adequate vacuum capacity to undergo the dewatering operation efficiently.

Fig.2. The use of deep well with vacuum systems to dewater a shaft over a stratified
ground material.
To have sufficient wetted area of intake in the aquifer, adequate well depth have to be
provided. This helps to produce yield and interactive drawdown. In most of the civil
engineering applications, a depth of 60m with a typical depth value of 20m is used.

For a limited distance say 1 to 2m, the well might penetrate an impermeable layer lying
below the pumped aquifer. This is to behave as sump for the fines. The pump must be
placed such a level in the well so that the water circulation helps it to remain cool.

The site layout decides the spacing of the wells. But most commonly, the spacing used is 10
to 30m. The deepening of the well creates drawdown in areas. Sometimes these might be
the areas where the wells cannot be sited.
Special care and precaution must be taken so that with increase in drawdown no kind of
settlement is happening to the adjacent buildings.

Groundwater Engineering provides complete deep well dewatering solutions:

Design of dewatering systems

Well drilling and installation

Pumping tests

Equipment sales and rental

Monitoring systems

On-site operation and maintenance


WELLPOINTS

Wellpoint dewatering is widely used for excavations of shallow depths, especially for
pipeline trench excavations. In appropriate ground conditions a wellpoint system can be
installed speedily and made operational rapidly. A typical wellpoint system consists of a
series of small diameters wells (known as wellpoints) connected via a header pipe, to the
suction side of a suitable wellpoint pump. The pump creates a vacuum in the header pipe,
drawing water up out of the ground. For long pipeline trenches, horizontal wellpoints may
be installed by special trenching machines.
Wellpoints are typically installed in lines or rings around the excavation, and are pumped by
diesel or electrically powered pumps, with associated header mains, water discharge pipes,
power supply generators, electrical controls and monitoring systems.

There are two types of well point system, namely single stage well point system and multi-
stage well point system. These systems are briefly described in the followings.

1. Single Stage Well Point system


2. Multistage Well Point system

Single Stage Well Point system – A well point consists of a pipe about 1 m long and 50 mm
in diameter. It has perforations, which are covered with a screen to prevent clogging in. At
the lower end, a jetting nozzle is provided. This nozzle also acts as a drive point. A ball valve
provided near the lower end allows the water to flow only in downward direction during
installation of the well point. A sketch of the well point is shown in Fig.1 below. A riser pipe
having the same diameter as the well point connects the well point at its bottom end. The
riser pipes are connected to a horizontal pipe, known as header pipe, at the ground level.
The header pipe is connected to a pumping unit. The well points are spaced every 0.6 to 1.5
The well points are installed to the required depth by jetting water through riser pipes in the
downward direction. Once installed pumping is started continuously till the excavation work
is completed.

Single stage well point system is used when the depth of excavation is less than 4.5 m. They
are effective in granular soils. By Single stage well point stage method the water table is
lowered by about 4.5m. This method is suitable to soils having coefficient of permeability
between 10-2 to 10-4 cm/sec.

Multistage Well Point system – These systems are used if excavation exceeds 4.5 m and
there is a chance of slope failure. The set up of the system is shown in Fig.2.In this system
the well points are installed in stages. In the first stage well points are installed to a depth of
around 4.5 and put into action till the water table is lowered by about 4.5 m. Then the area
is excavated up to this 4.5 m depth. After this second stages of well points are installed
within the area, which is excavated already. The water table is further lowered by another
4.5 m.
In this way the excavation is carried out till the excavation reaches to about 15 m. By well
point system method excavation greater than 15 m cannot be made.

Groundwater Engineering provides complete wellpoint dewatering solutions:

Design of dewatering systems

Wellpoint installation

Equipment sales and rental

Monitoring systems

On-site operation and maintenance

EDUCTORS

The eductor system (also known as the ejector system) is specialist technique used to
control pore water pressure in low permeability soils such as very silty sands, silts, or clays
with permeable fabric. Eductors are typically used to help stabilise the side slopes and base
of excavations in soils that would be difficult to dewater with wellpoints or deep wells.
Eductors have the advantage that they can allow vacuum-assisted drainage, to draw water
out of poorly draining fine-grained soils. The system works by circulating high pressure
water (from a tank and supply pumps at ground level) down the well to a small-diameter
nozzle and venturi located in the eductor in each well. This generates a vacuum of up to 9.5
m of water at the level of the eductor. The vacuum draws groundwater into the well from
where it is piped back to ground level via a return riser pipe and thence through the
reservoir tank back to the supply pump for recirculation.

Groundwater Engineering provides complete eductor dewatering solutions:

Design of dewatering systems

Well drilling and installation

Equipment sales and rental

Monitoring systems

On-site operation and maintenance


VACUUM WELLS
Vacuum wells are an adaptation of deep well systems. Each well in the system is pumped by
a submersible pumps, but a vacuum is also applied to each well via a vacuum pump located
at the surface. The application of a vacuum allows the wells to be more effective in reducing
pore water pressures in poorly draining fine grained soils. In appropriate ground conditions
vacuum wells can be a viable alternative to eductors.
Groundwater Engineering provides complete vacuum well dewatering solutions:

Design of dewatering systems


Well drilling and installation
Pumping tests
Equipment sales and rental
Monitoring systems
On-site operation and maintenance

HORIZONTAL WELLS

Horizontal wells for dewatering are of two principal types:


Horizontal drains installed by specialist trenching machines
Horizontally directionally drilled (HDD) wells.
Horizontal drains installed by specialist trenching machines

This technique uses a horizontal flexible perforated pipe, pumped by a wellpoint pump, to
lower groundwater levels. The perforated pipe is installed by a special trenching machine.
One end of the pipe is unperforated and is brought to the surface and connected to a
wellpoint suction pump. The method can be very effective for dewatering long pipeline
excavations.
Horizontally directionally drilled (HDD) wells

HDD wells are used where groundwater must be abstracted from beneath inaccessible areas
or from areas where the disruption associated with surface drilling is undesirable.
Applications for HDD wells include:
Installation of permanent dewatering systems beneath existing built up (urban)
environments.
Pumping for remediation of contaminated groundwater without the risks of cross-
contamination associated with vertical drilling
Dewatering for tunnel construction
Recharge wells to re-inject water as part of artificial recharge schemes.

Groundwater Engineering provides complete horizontal well dewatering solutions:


Design of dewatering systems
Well drilling and installation
Pumping tests
Equipment sales and rental
Monitoring systems
On-site operation and maintenance
Drains:

A Drain consists of filter, conduit and disposal system. A filter is necessary for
continued efficiency of the drain and to prevent seepage erosion. The collection of
water is done in the drain conduits. Normally the size of the conduit is 5 to 10 times
larger than its hydraulic dictate. The commercial pipes have perforations of diameter 8
to 9mm and are need of 12 to 15mm gravel filter.
Classification:

a. Open drains
b. Closed drains
c. Horizontal drains
d. Foundation drains
e. Blanket drains
f. Interceptor drains
Open drains

Drainage systems may be open or closed (subsurface), depending on the drainage


method.

In the open system, open channels are used as the regulating network, whereas in
the closed system, the regulating network is made up of closed collectors and has
underground drains and small channels.
In both systems, the main conducting and protective channels are open.

Open drainage systems are used for the initial drainage of marshes and forests and
sometimes also of hayfields and pastures.

Their drawbacks include a reduction in land available for cultivation, interference


with mechanized farming operations, and overgrowth with weeds and other types
of interference in the channels.

Closed drains
Closed drainage systems are technically more advanced and long lasting.

They do not have the shortcomings of open systems, and they offer great potential for
irrigation of drained lands during dry periods of the growing season.

For every 30m to 50m there must be openings to flush out the pipe. At 100m to 150m
intervals, the manholes must be provided at changes in direction along straight sections.

Such systems are built for intensive use of drained lands.


The Criterion For Selecting Of Fill Material Around Drains

The criteria for selecting material as suitable for use as fill shall be based on achieving
adequate strength, stiffness and permeability after compaction. These criteria shall take
account of the purpose of the fill and the requirements of any structure to be placed on it.

Suitable fill materials include most graded natural granular materials and
certain waste products such as selected colliery waste and pulverized fuel
ash. Some manufactured materials, such as light aggregate, can also be used
in some circumstances. Some cohesive materials may be suitable but require
particular care.
The following aspects shall be considered when selecting a fill material:
- grading;
- resistance to crushing;
- compactibility;
- plasticity;
- organic content;
- chemical aggressivity;
- pollution effects;
- solubility;
- susceptibility to volume changes (swelling clays and collapsible materials);
- the effect of frost;
- resistance to weathering;
- the effect of excavation, transportation and placement;
- the possibility of cementation occurring after placement (e.g. blast furnace slags).

If local materials are not suitable for use as fill in their natural state it may be
necessary to adopt one of the following procedures:

- adjust the water content;

- mix with cement, lime or other materials; - crush, sieve or wash;

- Protect with appropriate material; - use drainage layers.

When the selected material contains potentially aggressive or polluting chemicals,


adequate provisions shall be adopted to prevent these attacking structures or
services or polluting the groundwater. Such materials shall only be used in large
amounts in permanently monitored locations.
Blanket Drains
A drainage blanket is a very permeable layer of material. It can be used to remove
water from beneath pavement structures when applied as a permeable base or can
be used effectively to control groundwater from cut slopes and beneath fills.

In slope stability applications drainage blankets improve slope stability by preventing


a seepage surface from developing on the slope and by providing a buttressing
effect.

Drainage blankets are also used as an interface between embankment and soft
foundations to provide drainage during foundation consolidation.
Blanket drains often require a collection system and transverse pipe under drains
may be needed to outlet the blanket.
Horizontal Drains

Horizontal drains can be relatively inexpensive and effective in lowering


groundwater levels and relieving stresses on slopes, side hill fills and behind
retaining structures.
Their principle use is in slope stabilization applications.
A horizontal drain is a perforated or slotted pipe advanced into a slope with a
special auger typically at 5 degrees above horizontal. The last 10 ft of pipe
should be left imperforated to assure that water flows out.

Filter material or filter fabric should be used if clogging is expected. This can
greatly extend the life of the drain but is extremely difficult to install.

Horizontal drains should be designed by the Geotechnical Section. They are


commonly installed in fan-shaped arrays of several pipes emanating from a
common point.

Construction of horizontal drains can often be complicated depending on the


drilling capabilities and techniques used. Soil conditions and moisture can
affect stability of borings. Horizontal and vertical controls are essential to
ensure that the drains are installed as intended.
Regular maintenance and inspection of horizontal drain installations is critical
to ensure effectiveness. Horizontal drains can clog from precipitation of metals,
piping of fine particles and root penetration.

Clogged drains can sometimes be cleaned with high pressure water systems.
Drains installed in unstable soil slopes which continue to move after installation
can fail.
Underdrains

Deep underdrains can be used to lower groundwater levels in slopes and


intercept seepage before it can reach the slope face.
Interceptor drains are most effective when deep enough to intercept an
impervious layer below the surface. Although interceptor drains as deep as 30
feet have been constructed in Colorado, construction techniques and worker
safety should be considered before recommending an underdrain.

Often other drainage methods will need to be considered when subsurface


drainage is required at greater depths. If continued movement of the slope is
possible, perforated pipe in an underdrain is likely to rupture and fail.

Interconnected Belled Caisson Drains

Interconnected belled caisson drains are usually used to lower groundwater levels
on unstable slopes where depths restrict the use of underdrains.
A caisson drill rig is used to auger a line of large diameter holes. The bottom of
each hole is belled such that each hole is interconnected.

The belled caisson holes are filled with a coarse aggregate drainage material
immediately after drilling. This is done one caisson at a time until the drain is
complete.

Vertical and horizontal control is essential to ensure that continuity and positive
drainage is provided between adjacent bell sections.

Caisson drains are outlet with non-perforated pipe that is stubbed into the last caisson bell.
The outlet pipe is typically larger in diameter than underdrain outlet pipe because of the
large flow capacity of these drains. Interconnected belled caisson drains must be established
in material which is firm enough to support them; usually shales. The use of this method is
limited to those locations where this condition can be met.

Dewatering by electro osmosis


When an external electro motive force is applied across a soild liquid interface the
movable diffuse double layer is displaced tangentially with respect to the fixed layer.
This is electro osmosis.
As the surface of fine grained soil particles causes negative charge, the positive ions
in solution are attracted towards the soil particles and concentrate near the
surfaces.

Upon application of the electro motive force between two electrodes in a soil
medium the positive ions adjacent to the soil particles and the water molecules
attached to the ions are attracted to the cathode and are repelled by the anode.

The free water in the interior of the void spaces is carried along to the cathode by
viscous flow. By making the cathode a well, water can be collected in the well and
then pumped out.

SAFETY MEASURES

Only persons wearing rubber boots should be admitted into the neighbourhood of
the electrodes,
While working between anode and cathode neither the electrode nor the wiring
should be touched in such a manner that while one hand is on the electrode, the
other gets into contact with the ground or with the other electrode.
Where the excavation is carried out by machinery special attention has to be paid by
the operator to avoid the occurrence of short circuits.
GROUTING

Grout is a fluid form of concrete used to fill gaps. Grout is generally a mixture of water,
cement, and sand, and is employed in pressure grouting, embedding rebar in masonry walls,
connecting sections of pre-cast concrete, filling voids, and sealing joints such as those
between tiles.

Grouting is a high-cost treatment method and should be used where there is adequate
confinement to handle the injection pressures. The typical applications include control of
groundwater during construction, filling voids to prevent larger amounts of settlement, soil
strengthening, stabilization of loose sands, foundation underpinning, filling voids in
calcareous formations and strengthening soils for protection during excavation. Selection of
the most suitable method for stabilization will depend on the type of soil, degree of
improvement and depth and extent of treatment required. Another factor to consider is
whether the treatment is required for a new or existing structure.

Grouting especially with some chemical grouts may present risks to the public health and
environment that must be considered. Considerations for utilizing a treatment method
include energy use, maintenance costs, requirements for excavation and adequate
treatment performance. Environmental risks include mismanagement of surface and
groundwater drainage and incomplete treatment. Leachates and migration of contaminants
can contaminate subsoil, groundwater, water wells and nearby surface water unless
properly managed. There are several ground barrier methods used to control seepage,
which include slurry-trench cutoff walls and grout curtains.

The advantages of grouting include:

a. Can be performed on almost any ground condition


b. It doesn't induce vibration and can be controlled to avoid structural damages
c. Improvements to ground formations can be measured
d. Very useful for confined spaces and low headroom applications
e. Used for slab jacking to lift or level distorted foundations
f. Can be installed adjacent to existing walls.
g. Can be used to control seepage, groundwater flows and hazardous waste plumes

The primary Objectives of grouting ground formations are to:

a) Increase the strength and bearing capacity or the soil stability,

b) Reduce seepage and control groundwater during construction,

c) Form groundwater barriers and d) rehabilitate or reinforce structures.

The Different Investigation Methods Carried Out Before Grouting:


Drilling and direct inspection to accurately locate and determine local
conditions.
Taking coring samples for laboratory tests.
Drilling with drilling data recording to locate fissured zones, voids and the interface
between structure and surrounding ground
Borehole logging with BHTV Scanner examination (optical/seismic)
Non-destructive geophysical investigations (seismic resistivity)
Water testing (constant head or falling head tests conducted in borehole)
Underground flow & temperature measurements
Pumping test to assessment of initial hydraulic conditions.
The Applications Of Grouting
Grouting May Be Used In The Following Applications:
Filling Voids To Prevent Excessive Settlement
To Increase Allowable Pressure Of The Soil Both For New Structures And / Or
Additions To Existing Structures.
Control Of Groundwater Flow
Prevention of Loose - Loose to Medium Sand Densification under Adjacent
Structures (i.e. both for Vertical and Lateral Movements) Due To Adjacent
Excavations, Pile Driving Etc. Ground Movement Control during Tunnelling
Operations.
Soil Strengthening To Reduce Lateral Support Requirement.
Soil Strengthening To Increase Lateral and Vertical Resistance of Piles.
Stabilization of Loose Sands against Liquefaction.
Foundation Underpinning.
Slope Stabilization.
Volume Change Control Of Expansive Soils Through Pressure Injection Of Lime Slurry
(Only For Some Expansive Soils Not All)

The Systematic Representation Of Different Methods Of Grouting:


Different Grouting Materials

Grout Materials:

1. Suspensions: Small particles of solids are distributed in a liquid dispersion medium.


Example: cement and clay in water
2. Emulsions: A two phase system containing minute (colloidal) droplets of liquid in a
disperse phase.

Example: bitumen and water. Foams created by emulsifying a gas into the grout material,
which could be cement or an organic chemical. Foaming agents increase surface tension;
assist in forming bubbles by agitation.

3. Solutions: Liquid homogeneous molecular mixtures of two or more substances. Example:


sodium silicate, organic resins, and a wide variety of other so called chemical grouts.

Classification Of Grouting
Different Types Of Grouting

Types of Grouting
Penetration grouting or Permeation grouting
Displacement grouting
Compaction grouting
Grouting of Voids
Jet grouting
Electro grouting

Penetration grouting or Permeation grouting

This method describes the process of filling joints or fractures in rock or pore spaces
in soil with a grout without disturbing the formation

Displacement grouting
It is the injection of grout into a formation in such a manner as to move into the formation,
it may be controlled, as in compaction grouting or uncontrolled. As in high pressure soil or
rock grouting which leads to splitting of the ground, also called hydro fracture.
Compaction grouting
Grout mix is specifically designed so as not to permeate the soil voids or mix with the soil.
Instead, it displaces the soil into which it is injected.
Jet grouting
The high-pressure water or grout is used to physically disrupt the ground, in the process
modifying it and thereby improving it
Grouting of Voids

Using this process, grout is pumped under pressure into a void beneath a structure. The
cavity might have been caused by a water supply or drainage line break where the soils have
been washed away. It is ideal for situations during new construction or machine placement
where a void cannot be easily filled without extensive rip out. To account for proper travel
and strength qualities, the grout mix is custom-designed for each application.

Electro grouting
Electro grouting is a term used for promoting electrochemical hardening during electro
osmosis by adding chemicals, such as sodium silicate or calcium chloride, at the anode.
Under the influence of the electric field, these chemicals permeate the ground, flowing in
the direction of the cathode, while the anode becomes a grout injection pipe.

Compaction Grouting

Compaction grouting is a ground treatment technique that involves injection of a


thick-consistency soil-cement grout under pressure into the soil mass,
consolidating, and thereby densifying surrounding soils in place.
The injected grout mass occupies void space created by pressure-densification.
Pump pressure, as transmitted through low-mobility grout, produces compaction
by displacing soil at depth until resisted by the weight of overlying soils.
When injected into very dense soils or bedrock, compaction grout remains
somewhat confined, since the surrounding material is quite dense.
However, when injected into under-consolidated or poorly compacted soils, grout is
able to "push" these materials aside.
When grouting treatment is applied on a grid pattern, the result is improved
compaction of displaced soils and greater uniformity of the treated soil mass.
As a secondary benefit, the resulting grout columns add strength in the vertical axis,
as typical grout compressive strengths exceed those of the surrounding soils.
Compaction grouting applications include densification of foundation soils, raising
and relieving of structures and foundation elements, mitigation of liquefaction
potential, augmentation of pile capacity and pile repair, and densification of utility
trench backfill soils.

Permeation Grouting
Permeation grouting is a term used to describe a ground treatment method in which
grout is injected into a porous medium without disturbing its original structure.

In geotechnical engineering, this usually refers to the process of filling the pores and
joints in a soil and/or rock deposit to change its geotechnical properties.

Almost any grout material may use for permeation grouting, but there are distinct
limits on the grout mix used for specific types of soil or rock.

Applications are for enhanced foundation bearing value, improvement of excavation


character in sands and reduction of liquefaction potential.

The image shows a sample of permeation grouted sand from a project that
required steep-walled footing excavations in running sands.
The proposed excavation area was permeation grouted with a micro fine
cement slurry prior to cutting footing trenches, resulting in a significant
reduction in project cost. Unconfined compressive strength tests performed
confirmed the improvement
Particulate grouts are typically water-based slurries of cement, fly ash, lime or
other finely ground solids that undergo a hardening process with time.

These materials may be used to fill pores and joints in soil and rock, provided the
grout particles are small enough to be carried through the pore or joint openings.

A good rule of thumb is that the effective particle diameter in the grout
suspension should be less than the dimension of the pore or joint aperture
divided by 5.
Slurry grout mixes used for permeation grouting are designed primarily to
promote passage of the grout particles into the porous medium. The grain size of
the slurry is matched to the pore aperture and steps are taken to assure the grout
particles are properly dispersed in the grout.

To eliminate the effect of bleed on Portland cement grout, additives are used to hold
the cement grains in suspension at water to cement ratios that would otherwise be
quite unstable. The most common additive is a water suspension of bentonite. Even
small amounts of bentonite increase the inter particle forces dramatically and hold
the cement particles in suspension.
Permeation grouting is also known as Penetration grouting.

Displacement Grouting:
Displacement grouting is the injection of grout into a formation in such a manner as to
move the formation, it may be controlled, as in compaction grouting or uncontrolled, as in
high-pressure soil or rock grouting which leads to splitting of the ground, also called hydro
fracture.
Displacement grouting involves the use of grout to displace soil
Such displacement can fill voids, cap sinkholes, deal with poor soils and leave grout
mass in place.
Displacement grouting constitutes a method of introducing support elements into a
soil which cannot otherwise be modified readily.
Such grouting takes on a number of names such as pressure grouting,
cement grouting, slurry grouting, all of which are designations of both
grouting and grout.
The grouts involved in Displacement grouting range from compaction grout,
through low mobility non-cohesive grout, to thinner and less viscous materials.
Many are cement based because of low cost although ground rubber, walnut shells,
oyster shells, and many other available things have been used in grout, depending
on the problem.
Jet Grouting

Jet grouting is a technique where high-speed water jets emanating from a drill bit cut into
alluvial soils; as the drill bit is withdrawn, grout is pumped through horizontal nozzles and
mixes with or displaces the soil. The original foundation material is thus replaced with a
stronger and/or more impermeable grout-soil mixture. Jet grouting may be used to form
cut-off walls, do underpinning, or form deep foundations similar to grouted auger piles.

The high-pressure water or grout is used to physically disrupt the ground, in the
process modifying it and there by improving it.
Jet grouting blasts extremely high pressure fluids into the ground at ultra-high
velocities. The soil is broken up and mixed with the fluids to become one mass which
then hardens.
Depending on the application and soils to be treated, one of three variations is used:
the single fluid system (slurry grout jet), the double fluid system (slurry grout jet
surrounded by an air jet) and the triple fluid system (water jet surrounded by an air
jet, with a lower grout jet).
The jet grouting process constructs soil create panels, full columns or anything in
between (partial columns) with designed strength and permeability.
Jet grouting has been used to underpin existing foundations, construct excavation
support walls, and construct slabs to seal the bottom of planned excavations.
Jet grouting is effective across the widest range of soil types of any grouting system,
including silts and most clays. Because it is an erosion-based system, soil erodibility
plays a major role in predicting geometry, quality and production.
Cohesion less soils are typically more erodible by jet grouting than cohesive soils.
Since the geometry and physical properties of the soil create are engineered, the
properties of the soil create are readily and accurately predictable.
Jet grouting’s ability to construct soil create in confined spaces and around
subsurface obstructions such as utilities, provides a unique degree of design
Flexibility.
Indeed, in any situation requiring control of groundwater or excavation of unstable
soil (water-bearing or otherwise) jet grouting should be considered.
Stages in grouting flow

Grouting in stage may be in a descending or ascending direction.

In descending method, impregnation of the ground occurs in advance of the borehole,


which is advantageous in loose soil or rock.
In ascending technique, grouting follows drilling as a separate phase
Water pressure testing is possible immediately prior to grouting, allowing for a choice of the
most suitable grout type, pressure and quantity of grout for that particular stratum.

Following points to be taken care of:


Minimum wastage of grout.
Least damage to the ground.
Maximum gain in strength or reduction in seepage.

Grouting Techniques and controls

The hole is drilled and cased


A steel or plastic tube, slotted at regular intervals is inserted. The vertical slots are
covered with a rubber sleeve.
As the casing is withdrawn, the space between the sleeve tube and the borehole wall
is sealed with a cement-bentonite grout.
After the seal has set, the grouting tube is inserted grout exist between two packers
allowing injection through selected slots with increasing pressure, the rubber sleeve
bursts and grout flows into the soil.

With the sleeve tube technique, grouting can be repeated in the same hole using
different viscosity grout or different chemicals in a planned sequence.

Post Grout Test


Post Grouting of anchors can significantly improve the load carrying capacity of anchors in
cohesive soils by increasing the skin friction of the anchor grout body with the soil.

Post-grouting process is performed by the following stages:

Constructing bored pile with the nowadays commonly used technology is grout
spouting technology attached to the steel cage at least 2 bottom sealed steel pipe
D90, symmetry through the center, along the length of the pile, 10-20cm distance
from the bottom of pile
The bottom of the pile spouting grout structure; after installing steel cages
conducting concrete bored piles
Drilling the bottom hole of two D90 steel pipes to soil under the pile tip
Pumping high pressure water with 80-200 bar to wash bottom of the pile until
the ejected water is as fresh as pumped water

IMPORTANT QUESTIONS

1. What is dewatering? Explain its importance in civil engineering works.


2. List various well point dewatering systems and explain their suitability for different
soils.
3. What are the objectives of dewatering? What are the types of foundation drains?
4. Explain the electro osmosis method to control ground water in low permeable soil?
5. What is grouting? Explain in detail various field of applications of grouting.
6. Explain compaction grouting, penetration grouting and fracture grouting with neat
sketches.
7. What are the properties of the grout mixes: (i) Solutions such as water glass
(silicate). (ii) Emulsions such as chemical grout.
8. Explain the following grouting methods: (i) Compaction. (ii) Jet grouting.
9. Discuss briefly the important points to be considered in design of dewatering
system.
10. Discuss in detail with suitable examples the field conditions which necessitate
dewatering in soil.
11. What do you understand about soil stabilization by grouting? Explain in detail
various fields of applications of grouting.
(b) Describe the equipment used in the grouting technique
12. Discuss in details various well point techniques for dewatering soils.
Explain the criteria for the selection of a particular fill material around the drains.
13. Explain briefly various methods of grouting.