Cost Estimate Breakdown For TTC and Rebuild Workshops
Cost Estimate Breakdown For TTC and Rebuild Workshops
a. Demolition works
Wall m3 56.70 - 1.10 - 2.50 141.75 85.00 12,048.75 195.00 11,056.50 - 407.50 23,105.25 2,310.53 25,415.78 5,083.16 537.90 30,498.93
Column m3 1,012.80 452.00 457,785.60 1.10 503,564.16 3.40 3,443.52 85.00 292,699.20 - - 786.20 796,263.36 79,626.34 875,889.70 175,177.94 1,037.78 1,051,067.64
Slab m3 35.00 452.00 15,820.00 1.10 17,402.00 3.40 119.00 85.00 10,115.00 - - 786.20 27,517.00 2,751.70 30,268.70 6,053.74 1,037.78 36,322.44
Sub - Total 473,605.60 520,966.16 3,704.27 314,862.95 11,056.50 - 846,885.61 84,688.56 931,574.17 186,314.83 1,117,889.01
b. Earthworks
Excavation m3 32.00 - 1.10 - 1.00 32.00 85.00 2,720.00 186.00 5,952.00 - 271.00 8,672.00 867.20 9,539.20 1,907.84 357.72 11,447.04
Gravel Bedding m3 56.70 - 1.10 - 2.50 141.75 85.00 12,048.75 195.00 11,056.50 - 407.50 23,105.25 2,310.53 25,415.78 5,083.16 537.90 30,498.93
Backfilling m3 1,012.80 452.00 457,785.60 1.10 503,564.16 3.40 3,443.52 85.00 292,699.20 - - 786.20 796,263.36 79,626.34 875,889.70 175,177.94 1,037.78 1,051,067.64
Sub - Total 457,785.60 503,564.16 3,617.27 307,467.95 17,008.50 - 828,040.61 82,804.06 910,844.67 182,168.93 1,093,013.61
c. Concrete Works
Concreting m3 36.60 - 1.10 - 2.00 73.20 85.00 6,222.00 70.00 2,562.00 - 240.00 8,784.00 878.40 9,662.40 1,932.48 316.80 11,594.88
Sub - Total - - 73.20 6,222.00 2,562.00 - 8,784.00 878.40 9,662.40 1,932.48 11,594.88
d. Rebar Works
Rebar Works m3 166.00 725.00 120,350.00 1.10 132,385.00 1.70 282.20 85.00 23,987.00 - - 942.00 156,372.00 15,637.20 172,009.20 34,401.84 1,243.44 206,411.04
Sub - Total 120,350.00 132,385.00 282.20 23,987.00 - - 156,372.00 15,637.20 172,009.20 34,401.84 206,411.04
e. Formworks
Formworks m3 35.10 725.00 25,447.50 1.10 27,992.25 1.70 59.67 85.00 5,071.95 - - 942.00 33,064.20 3,306.42 36,370.62 7,274.12 1,243.44 43,644.74
Sub - Total 25,447.50 27,992.25 59.67 5,071.95 - - 33,064.20 3,306.42 36,370.62 7,274.12 43,644.74
f. Masonry Works
Mansonry Works m3 35.10 - 1.10 - 1.89 66.34 85.00 5,638.82 - - 160.65 5,638.82 563.88 6,202.70 1,240.54 212.06 7,443.24
Sub - Total - - 66.34 5,638.82 - - 5,638.82 563.88 6,202.70 1,240.54 7,443.24
g. Structural Works
Structural Steel m2 820.00 100.00 82,000.00 1.10 90,200.00 0.25 205.00 85.00 17,425.00 - - 131.25 107,625.00 10,762.50 118,387.50 23,677.50 173.25 142,065.00
Sub - Total 82,000.00 90,200.00 205.00 17,425.00 - - 107,625.00 10,762.50 118,387.50 23,677.50 142,065.00
h. Carpentry Works
Carpentry Works m2 703.00 42.00 29,526.00 1.10 32,478.60 0.10 70.30 85.00 5,975.50 - - 54.70 38,454.10 3,845.41 42,299.51 8,459.90 72.20 50,759.41
Sub - Total 29,526.00 32,478.60 70.30 5,975.50 - - 38,454.10 3,845.41 42,299.51 8,459.90 50,759.41
i. Tiling Works
Tiling Works m3 56.70 - 1.10 - 2.50 141.75 85.00 12,048.75 195.00 11,056.50 - 407.50 23,105.25 2,310.53 25,415.78 5,083.16 537.90 30,498.93
Sub - Total - - 141.75 12,048.75 11,056.50 - 23,105.25 2,310.53 25,415.78 5,083.16 30,498.93
j. Plumbing & Sanitary Works
Plumbing & Sanitary Works m3 32.00 - 1.10 - 1.00 32.00 85.00 2,720.00 186.00 5,952.00 - 271.00 8,672.00 867.20 9,539.20 1,907.84 357.72 11,447.04
Sub - Total - - 32.00 2,720.00 5,952.00 - 8,672.00 867.20 9,539.20 1,907.84 11,447.04
k. Roofing
Roofing m3 36.60 - 1.10 - 2.00 73.20 85.00 6,222.00 70.00 2,562.00 - 240.00 8,784.00 878.40 9,662.40 1,932.48 316.80 11,594.88
Sub - Total - - 73.20 6,222.00 2,562.00 - 8,784.00 878.40 9,662.40 1,932.48 11,594.88
l. Painting/Finishing Works
Painting/Finishing Works m3 166.00 725.00 120,350.00 1.10 132,385.00 1.70 282.20 85.00 23,987.00 - - 942.00 156,372.00 15,637.20 172,009.20 34,401.84 1,243.44 206,411.04
Sub - Total 120,350.00 132,385.00 282.20 23,987.00 - - 156,372.00 15,637.20 172,009.20 34,401.84 206,411.04
m. Airconditioning Works
Airconditioning Works m3 35.10 725.00 25,447.50 1.10 27,992.25 1.70 59.67 85.00 5,071.95 - - 942.00 33,064.20 3,306.42 36,370.62 7,274.12 1,243.44 43,644.74
Sub - Total 25,447.50 27,992.25 59.67 5,071.95 - - 33,064.20 3,306.42 36,370.62 7,274.12 43,644.74
n. Electrical Works
i. Electrical Panel Boards m2 820.00 100.00 82,000.00 1.10 90,200.00 0.25 205.00 85.00 17,425.00 - - 131.25 107,625.00 10,762.50 118,387.50 23,677.50 173.25 142,065.00
ii. Lighting and Power System m2 703.00 42.00 29,526.00 1.10 32,478.60 0.10 70.30 85.00 5,975.50 - - 54.70 38,454.10 3,845.41 42,299.51 8,459.90 72.20 50,759.41
ii. Cable Layout m2 703.00 42.00 29,526.00 1.10 32,478.60 0.10 70.30 85.00 5,975.50 - - 54.70 38,454.10 3,845.41 42,299.51 8,459.90 72.20 50,759.41
iv. Grounding System m2 703.00 42.00 29,526.00 1.10 32,478.60 0.10 70.30 85.00 5,975.50 - - 54.70 38,454.10 3,845.41 42,299.51 8,459.90 72.20 50,759.41
v. Airconditioning System m3 56.70 - 1.10 - 2.50 141.75 85.00 12,048.75 195.00 11,056.50 - 407.50 23,105.25 2,310.53 25,415.78 5,083.16 537.90 30,498.93
Sub - Total 170,578.00 187,635.80 557.65 47,400.25 11,056.50 - 246,092.55 24,609.26 270,701.81 54,140.36 324,842.17
GRAND TOTAL 3,010,180.40 3,311,198.44 18,449.44 1,568,202.23 122,508.00 - 6,820,083.67 682,008.37 7,502,092.04 1,500,418.41 9,002,510.44
9,002,510.44
18,449.44 Manhour
1,844.94 Mandays
90.00 Days
20.50 Men
F. Detailed Breakdown
Safety Paraphernalia
Total 720,000.00
Project : MESCO Oxygen Plant VPSA4
Client : MESCO
Location : LIDE, Isabel, Leyte
Duration : 3 months (90 calendar days)
A. Revenue
Total Revenue - 26,000,000.00
B. Job Cost
Materials 14,907,972.00
Direct Labor - Php 450/day x 51 men 2,065,500.00
Total Job Costs 16,973,472.00
C. Overhead Expenses
Officers' salaries - Php 30,000/month x 5 men 450,000.00
Administrative wages Php 25,000/month x 5 men 375,000.00
Cook, Dishwasher, etc. Php 5,000/month x 3 men 45,000.00
Site Office 100,000.00
Barracks/Bunkhouse 100,000.00
Telephone & mobile phone 10,000.00
Design and drafting 120,000.00
Asbuilts and Permitting Documents 140,000.00
Insurances 780,000.00
PEZA Permit 123,000.00
Material Testing 623,000.00
Office supplies 30,000.00
Bank Charges 3,000.00
Tools & Equipment 960,000.00
Consumables 147,000.00
Safety Paraphernalias 162,650.00
Meals - Php 150/day x 44 men 594,000.00
Water and electricity 150,000.00
Mobilisation 720,000.00
Demobilisation 720,000.00
PROJECT SCHEDULE
DATE
Month June July August September October
Item ACTIVITY
Week No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Week Beginning
1 BUILDING WORKS
Earthworks
Formworks
Concrete Works
Rebar Works
Structural Steel Works
Masonry Works
Metal & Sheet Metal Works
Metal Door & Window Works
Plastering Works
Painting Works
Interior Finishing Work
Miscellaneous Work
2 MACHINE FOUNDATION & PIPE FOUNDATION
FSP Outside & Inside Building
Machine Concrete Foundation
Trench with Checkered Plate Cover
External Works
3 MECHANICAL & ELECTRICAL WORKS
Electrical Works
Mechanical Works
Prepared by: