GP 03 19 01
GP 03 19 01
GP 03 19 01
Scope
1) [I] This Global Practice (GP) covers field erection, leak testing, flushing, and cleaning of piping
systems.
2) [I] An asterisk (*) indicates that additional information is required. If a job is contracted, this
additional information is specified in the Job Specification.
Refining/Chemicals, Downstream
For ExxonMobil Use Only Version 2.0.0
Imperial Oil
Table of Contents
1. Additional Requirements
* [I] The following Practices and Standards shall be used with this GP as specified by the Owner's
Engineer.
2. Erection
1) [R] Field routed small piping (NPS 11/2 [40 mm]) shall be supported in a manner that minimizes
excessive vibration and accommodates thermal expansion of terminal equipment.
2) [R] Temporary shipping braces, stops, or other protective devices for expansion joints shall not be
removed until installation is complete, including any required adjustments to tie-rods, etc.
1 2
Special Services
1 Per the applicable Code 1/32 in. (1 mm) maximum out of parallel alignment of flanges,
measured across any diameter.
2 Per the applicable Code 1/8 in. (3 mm) maximum translation of branches or
connections.
2) [R] Flange "makeup" shall be done without the use of gasket sealing compounds.
3) [R] All flange bolting shall be assembled with thread lubricating compound.
4) [R] Regarding flanged pipe joints of cement lined type valves, it may be necessary to grind the lining
at the pipe ends to avoid interference with the action of the valve disc (or plate). In this case, the
lining shall be taper ground and coated with epoxy cement.
5) [R] Flange "bolt-up" procedures shall be approved by the Owner’s Engineer.
The procedure shall require that flange alignment tolerances and driver to driven machine alignment
change tolerances be satisfied both with and without temporary strainers installed. Where these
criteria cannot be met, the Contractor and machinery vendor shall develop a suitable resolution, such
as installation of piping spools of different length to accommodate temporary strainers.
2) [R] The following considerations shall be addressed as part of final flange alignment and bolt up:
a) Prior to final flange alignment, all hydrostatic leak testing and line cleaning (including chemical
cleaning, hydroblasting, steam blowing, and rupture disk blow downs) shall be complete. The
system shall be clean and dry. Hydrotesting blinds shall be removed.
b) Permanent spring supports shall be locked in the "cold load" position during piping erection, leak
testing, piping alignment to machinery, and piping bolt up.
c) All fixed supports shall be checked with feeler gauges to ensure full contact with piping. All
guides shall be checked to verify that design piping movement is not restricted.
d) No unsupported piping shall be connected to the equipment nozzles.
e) For field-fabricated piping, the makeup of flanged or field welded joints shall be done
progressively towards the machinery (e.g. the last flange bolted shall be the flange to the
machinery).
f) If prefabricated piping sections are used, at least one weld shall be left near the nozzle flanges for
final fitting and alignment.
g) Piping shall be free of load-imposing temporary restraints that may cause "cold springing" of the
piping.
h) Local heating to correct minor misalignment is permitted on piping that does not require post
weld heat treatment. Piping shall be allowed to cool below 150F before bolt up.
i) Machined pins furnished with mating flanges shall be used to align flange boltholes during field
erection of mating piping.
j) Final alignment of the driver to driven machine(s) shall be achieved in accordance with the
required tolerances specified in the alignment procedure. This includes offsets for thermal
growth or movement of the casing prior to final pipe alignment and bolt up.
k) * Final piping alignment and driver to driven casing alignment or web deflection and movement
on bolt up shall be witnessed by the Owner's Engineer. Records of pipe flange misalignment
shall be provided for the following:
i) All special purpose equipment trains
ii) All reciprocating compressors over 200 bhp (150kW)
iii) All machinery bolted to flanges of NPS 10 and larger
iv) When specified by the Owner's Engineer
3) [R] Equipment nozzle and mating flange alignment tolerances shall be within the following maximum
permissible limits:
a) For steam turbines and compressors other than reciprocating types, 1/64 in. (0.4 mm) for all
alignment categories listed in Item b below.
b) For centrifugal pumps, reciprocating compressors and other rotating machinery, refer to Table 1.
4) [R] For liquid service, final adjustments of spring supports shall be performed with the piping full of
process liquid.
5) [R] After piping alignment is achieved for all machinery except reciprocating compressors, flange
bolt up shall be performed as follows:
a) Dial indicators shall be installed on brackets installed on coupling hubs or shafts to measure
vertical and horizontal movement of the driven machine(s) relative to the driver(s).
b) Starting with the largest flange size to be connected to any casing in the train, bolts and the gasket
shall be installed in the flange.
c) All bolts shall first be finger tightened. Then all bolts shall be tightened to approximately half the
required torque level. Next, bolts shall be tightened to an intermediate torque level, followed by
tightening to the full torque level required.
d) The maximum allowable vertical or horizontal movement of the shaft on the casing to which the
piping is bolted as measured relative to the adjacent shaft is 0.002 in. (0.05 mm).
e) If the shaft movement exceeds 0.002 in. (0.05 mm), all bolts in the flange shall be loosened, the
gasket shall be removed, corrections to the piping or supports shall be made, and the bolt up
procedure shall be repeated.
5) [R] Joints, including all welds and bonds, shall be left unprimed and unpainted for examination
during leak testing as follows:
a) * Joints located in environmentally sensitive areas, when specified by the Owner's Engineer
b) Joints located in buried piping systems
Record of Change
Version 1.0.0 Date: 07/01
Location Action Description
Initial Publish