This document discusses the key considerations when drafting engineering, procurement, and construction (EPC) contracts. It outlines various types of construction contracts, including:
1. EPC contracts combine engineering, procurement, and construction aspects into a single contract, placing responsibility on the contractor.
2. Procurement contracts involve organizing the supply of materials, equipment, and machinery to project sites.
3. Construction contracts involve overseeing all construction activities, including labor organization and site management.
4. In EPC contracts, the contract structure is more complex as many parties are involved in project implementation. Drafting the contract carefully is important to allocate risks appropriately between parties.
Copyright:
Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online from Scribd
Conceiving and Drafting The Terms of Epc Contracts
This document discusses the key considerations when drafting engineering, procurement, and construction (EPC) contracts. It outlines various types of construction contracts, including:
1. EPC contracts combine engineering, procurement, and construction aspects into a single contract, placing responsibility on the contractor.
2. Procurement contracts involve organizing the supply of materials, equipment, and machinery to project sites.
3. Construction contracts involve overseeing all construction activities, including labor organization and site management.
4. In EPC contracts, the contract structure is more complex as many parties are involved in project implementation. Drafting the contract carefully is important to allocate risks appropriately between parties.
Original Title
Conceiving and Drafting the Terms of Epc Contracts
This document discusses the key considerations when drafting engineering, procurement, and construction (EPC) contracts. It outlines various types of construction contracts, including:
1. EPC contracts combine engineering, procurement, and construction aspects into a single contract, placing responsibility on the contractor.
2. Procurement contracts involve organizing the supply of materials, equipment, and machinery to project sites.
3. Construction contracts involve overseeing all construction activities, including labor organization and site management.
4. In EPC contracts, the contract structure is more complex as many parties are involved in project implementation. Drafting the contract carefully is important to allocate risks appropriately between parties.
Copyright:
Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online from Scribd
Download as pdf or txt
100%(2)100% found this document useful (2 votes)
1K views8 pages
Conceiving and Drafting The Terms of Epc Contracts
This document discusses the key considerations when drafting engineering, procurement, and construction (EPC) contracts. It outlines various types of construction contracts, including:
1. EPC contracts combine engineering, procurement, and construction aspects into a single contract, placing responsibility on the contractor.
2. Procurement contracts involve organizing the supply of materials, equipment, and machinery to project sites.
3. Construction contracts involve overseeing all construction activities, including labor organization and site management.
4. In EPC contracts, the contract structure is more complex as many parties are involved in project implementation. Drafting the contract carefully is important to allocate risks appropriately between parties.
Copyright:
Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online from Scribd
Download as pdf or txt
You are on page 1of 8
At a glance
Powered by AI
EPC contracts combine engineering, procurement and construction aspects into a single contract. Care must be taken to properly allocate risks between contracting parties.
EPC contracts involve a single contractor providing engineering, procurement and construction services for large infrastructure projects like power plants.
EPC contracts combine the construction, procurement and engineering aspects into one contract allowing projects to proceed in an overlapping manner.
Articles
Conceiving and Drafting the Terms of EPC Contracts
R. V. Seckar, FCS, ICSA (UK), Company Secretary, Chandra Group of Companies, Kakinada.
Engineering, Procurement and Construction Contract, commonly known as EPC
contract are common in the construction of large power plants, infrastructure projects and the like. While emphasising the care and caution to be taken while drafting the e-mail : term of such a contract, this article discusses elaborately the various other points to be [email protected] considered in such an exercise.
INTRODUCTION turnkey contracting basis. Under this contract, the FIDIC
Conditions of Turnkey or EPC Projects (famously known as The term EPC means Engineering, Procurement and the silver book) is designed to handle scenarios where bids are Construction contract. An EPC Contractor is engaged in the invited on an international basis. It has been specifically construction of large power plants, large industrial plants, giant designed for use in EPC and BOT contracts. However, law industrial infrastructure, power transmission and distribution, firms and big contractors will have their own in-house standard railways and in oil and gas industry. Some of the famous EPC EPC contract and for these parties, silver book may act as a contractors are ABB, L&T, Uhde India, Tata Projects Ltd, solid reference to update and review their in-house standard IRCON International Ltd, etc. Under an EPC contract, the forms. For those law firms and contractors, who do not have contractor offers all the engineering, procurement and standard EPC, contract forms may use the Silver Book for construction activities. In an EPC contract, the contractor will drafting their EPC contract terms. (Huse 2002:48). be held responsible for any defect in the construction, design or However, there are obvious tensions between a project company performance of the works. Moreover, in an EPC contract, both and a contractor where a turnkey EPC contract is used. The the design and construction are placed on the contractor along drafters of EPC contract has to pay special attention to the with a harsh standard of performance. Hence, the personnel allocation of project risks and with specific reference to the engaged in drafting of EPC contract have to pay special attention drafting of common terms in EPC contracts. Else, the to the allocation of project risks and with specific reference to contractor’s interest will be affected, and he may have to incur the drafting of common terms in EPC contracts. Else, the pecuniary losses. contractor’s interest will be affected, and he may have to incur pecuniary losses and implementation of the project may be ANALYSIS delayed. This article analyses the points to be taken into An EPC Contract is also known as the fast-track contract. It consideration while drafting the terms of international EPC combines three stages of construction contract under the ambit contract and allocation of risks in the EPC contract so that of one contract. It combines the construction, procurement interests of both the contracting parties are secured. and engineering aspects into one single contract. It facilitates In drafting the EPC contracts, legal practitioners may use the growth on a project to proceed on an overlapping basis standard form contracts as a basis for their contract document. than if the three stages have been taken over in series. These template or boiler contracts offer a familiar starting The “package deal” or “turnkey arrangement” or “design or point to lessen the drafting trouble and to make easy negotiation. build “, “cle-en-main” or “EPC” imposes the duty to construct FIDIC (The Federation Internationale des Ingenieurs Conseils) and design solely on the contractor. There is no standard of late released a new form of contract that can be used in explanation for each of these terms in the construction sector. design and construction of projects thereby employing the same The phrase ‘turnkey” connotes the most extreme structure of to the engineering,procurement and construction contract or placing the design and construction obligation on the Articles Conceiving and Drafting the Terms of EPC Contracts contractor, such that after completion, the employer will be of supplies, materials, equipments and machinery to the given the key to project to start the operation of the constructed project site. project. To organise financial functions such as reviewing of There are potential complex contractual structures in any BOT invoices, forecasting the cash needs and overseeing of (Build, Operate and Transfer) contract. In majority cases, the accounting records. BOT projects will employ either an EPC or a turnkey contract In a majority of contracts, often no separate procurement for the actual construction and design aspect of the contract. contract is employed especially in project financing and for Hence, a BOT is not a separate style of construction contracting the obvious reasons, a separate engineering contract is not but rather a technique of financing the project. In case of employed. Instead, the turnkey construction contract is made BOT contract, the lenders will have considerable sway on the to include all procurement work until the financial closure is condition of the underlying construction contract including successfully completed. (Hoffman 2008:170). the prerequisites that such a contract be on a turnkey basis or in the guise of an EPC contract. Construction Contract In BOT contract, the operation period between finishing and This contract oversees the complete construction activities of transfer also offers the transferee a chance to authenticate the the project. Thus, in a construction contract, the contractor quantity and quality of the productivity of the completed undertakes to offer all constructions – associated services project work. Accordingly, in a BOT contract, a contractor including organisation of labour, supervision of the may be obliged to give training of the transferee’s employees construction, management of tools, supplies, construction before the actual transfer of the project is completed thereby facilities, field engineering and site investigation. (Hoffman easing any possible tension that may arise in the contract. 2008:170). The contract provision should be drafted by taking into consideration the accelerated deterioration of the work at the EPC Contract time of transfer of the project. Thus, a transferee will be In an EPC contract, the contract structure will be much required to pay attention to maintain the operator’s incentive complicated as many participants are involved in the to maintain the workflow properly and to circumvent any implementation of the project. Thus, either an EPC or a BOT deterioration in the final phase of the contract just before the contract often is not as simple as its definition connotes. There transfer to the transferee. The operator may in an effort to may be large number of parties involved under complex save on costs and at the terminal phase of the operating period, contract structure. For instance, in a hydroelectric project, the the contractor may indulge in a slowdown in the maintenance concerned government has granted a concession to the project and operating expenditures resulting in accelerated worsening development company. This project development company of the work scenario. Thus, contract provision in some BOT has in turn entered into separate contracts for the construction contract is drafted in such a manner by placing the of the facility, its operation and maintenance during such responsibility on the operator to assume liability for defects concession phase and power purchase agreement (PPA) with for a shorter period subsequent to the transfer. an electrical supply utility. A consortium of contractors was assigned with the turnkey contract for the construction of the VARIOUS TYPES OF CONSTRUCTION facility. Again, each of the turnkey contractors was also an CONTRACTS equity stakeholder of the EPC contracting company as they will have to subscribe some portion of the equity of the project Procurement Contract development company. Further, one of the subsidiaries of the It provides for the methodical sourcing of work and supplies turnkey contractor was assigned the operation of the facility for a project. This contract includes stipulations that demand after the completion of the project. Thus, in an EPC or a BOT the architect or an engineer to perform the following functions: project the contract has to be drafted by taking into account To frame bidding guidelines for equipment, machinery this complex structure involved in a typical power plant and supplies. construction contract. Where a project is undertaken by a State or by a political entity, the EPC contractor assumes further To carry out an economic evaluation of the bids received; risks in that project as the project may be affected in future. A To arrange for export licenses and other governmental successor government gaining power, whether it be federal, permissions, which are essential for the import or export State or local may try to dishonour some part or whole part of Articles Conceiving and Drafting the Terms of EPC Contracts project contract entered into by the predecessor government. law by having recourse to its own international nature. An A best illustration of this type of action by a successor issue of confiscation will always look at in the background of government to modify or change an EPC contract entered applicable international law only irrespective of the fact of into by an earlier government is the Enron-Dabhol power the law preferred by the parties. project in India. In such cases, it is wise to incorporate Financial institutions and banks will make a further stipulation termination payments and termination provisions in an EPC while granting finance to the project as to offer them some contract in favour of Project Company. If the government certainty as to their financial risk. Thus, lenders may be placed failed to honour its legal commitments, then these damage with a significant amount of certainty if lump-sum bidding or payments will have to be made by the defaulting government if much risk is placed on the contractor for completion of the to the project company. It is sound to add a so-called statement project. of binding impact to other agreements or an implementation with the host nation. (Hoffman 2008:158). EPC CONTRACT (OLD EXAMPLE) Further it is prudent to add a waiver of sovereign immunity clause in the EPC contract if it is entered with a host nation’s Project Company government or with an entity owned by a host nation. For instance, in Texaco Overseas Oil Petroleum Co / California Asiatic Oil Co v. Libyan Arab Republic1, it was held that the Engineering Fabrication EPC Contractor government cannot employ its sovereignty to ignore obligations Contractor Contractor and cannot cancel the privileges of the contracting party who has executed its multiple duties under the contract through an Equipment internal order of the government. (Hoffman 2008:158). In Vendor case of sovereign immunity, a government may waive such immunity either through explicit or implicit actions. In Morgan EPC CONTRACT (NEW EXAMPLE) Guaranty Trust Co v. Republic of Palau, the Republic’s sovereign immunity was waived by the President of the Project Republic while entering into loan agreements with companies Company of U.S.A origin in respect of construction of power plants. Later, the financing company sued the Republic when it failed to make payment under a guarantee and defaulted on its Main payment obligations. It was held by the court that Republic Contractor was under obligation to reimburse the guarantors. According EPC to court, the President of the Republic by signing the agreement Engineering and by supporting the financing with the “full faith and credit Contractor of the Republic” has the obligation to honour the commitments made already. (Hoffman 2008:159). In Saudi Arabia v. Arabian Oil Co (Armco)2 , it was held by System Vendor Facrication EPC Contractor an International Arbitration tribunal that laws of Saudi Arabia Contractor had to be supplemented or construed by the general principles of law, by the practice and customs and usage in the oil business and by thoughts of untainted jurisprudence and the defendant’s Equipment rights could not be “protected in an authentic style by the Vendor legislation in force in Saudi Arabia.” In Mobil Oil Iran Inc v. Islamic Republic of Iran3 , as regards Source: (Wilpert & Fahlbruch 2002:214) the applicable law in a contract, the Iran-United States Claims Tribunal has often corroborated its stand on applicability of EPC, TURNKEY AND DESIGN – BID CONTRACT 1. 21 I.L.M 726,735-36. (1982). 2. 27 ILR 117 ,168 (1963). Dissimilarities exists between these contracts. Under an EPC 3. US CI Trib Rep 3, 64-65 (1987) contract, the contractor offers all the engineering, procurement Articles Conceiving and Drafting the Terms of EPC Contracts and construction. In a design-bid contract, the employer offers chief construction contracts becomes a confront and many the design, which often includes the description of materials contractors incur major pecuniary losses or attrition of expected to be used and other major construction parameters. Under a incomes since the most of the construction contractors are turnkey contract, it is the obligation of the contractor to supply bound by predetermined-priced EPC contracts where they have the final design of the project. to accept the risk of increases in both supplier and material costs. Thus, under EPC contract, the contractor will be held responsible for any defect in the construction, design or Devoid of a distinctly worded price appreciation provision performance of the works. The employer has to demonstrate that permits for a modification to the price of the contract due to what degree resultant damage was caused by defective to the occurrence of an unforeseen event or, an unforeseen design or by the faulty construction under a design-bid –build increase in the whole-sale prices of major construction related contract. (Huse 2002: ix). materials, a contractor may have to bear the unbearable pecuniary loss. Further, an EPC contractor may not get a relief Under EPC contract, both the design and construction are as, even if the contract has turned to be onerous, which will placed on the contractor along with a harsh standard of not normally be adequate legal stances for execution of the performance. The standard of performance applicable will contract to be exempted by the courts. (Kerur 2005). be contained in the contract or in the non-existence of any explicit provision, by the applicable law. Under the Silver Since, EPC contract is a fixed price or lump-sum price contract, Book, the standard is “fitness for purpose.” As laid down in unless the contract specifically provides for a price increase due to the occurrence of some modifications or events, it is English case law namely IBA v. EMI and BICC4 , a turnkey wise to add a price increase clause in the EPC contract to contractor is under strict liability to deliver the work ‘fit for safeguard the interest of the contractor against price volatility the purpose” for which it was constructed. (Huse 2002:18). in the near future. For instance, the courts in U.S.A hold parties To choose the best design and quality of work, in EPC contract, responsible for their contractual agreements. For instance, in the bidding process will be consisting of five stages; pre- Iowa Electric Light and Power Co v. Atlas Corp5 , the court feasibility, feasibility, bidding, evaluation of bids and award ordered that the uranium supplier had to honour his contractual of the contract and the negotiation. Such phased bidding will obligation to supply the uranium to the utility though the price help the employer to first evaluate the quality of the design at of the Uranium to the supplier had increased considerably first and then only the bid price. later. This case stresses the significance to include “price The fitness for purpose standard can be explained a stricter escalation clause” “in an EPC contract to safeguard against standard than a “professional “duty of care as it places onerous the incurring of financial loss due to price escalation in the on the contractor for any defect or failure of design to perform later date. Further, in an EPC contract, contractual provisions to the standards needed. can be included in the contract to pardon performance upon the happening of discussed events like price increases. In DRAFTING OF EPC CONTRACTS Eastern Airlines v. McDonnell Douglas Corp, the court held that the doctrine of force majeure clause will not be applicable While drafting EPC contacts one should give importance to where a future event was particularly mentioned in the the following aspects: contract. (Hoffman 2008:192). The Scope and Definition of the Works Since the contractor assumes overall control over the project, The scope of work has to be clearly drafted and requirement the employer may desire to restrict the capacity of the contractor of an employer should be drafted precisely to define the to obtain such increases. Generally, courts will insist that a liability of the contractor for design, construction and contractor must carry out the construction work at the rate agreed performance. especially in predetermined-priced EPC contracts, which assign risk and, which do not contain a precise clause permitting for Increase in the price modification in prices. In the present economic scenario, EPC contract’s tender prices are towering and service providers insist The real issue for suppliers and EPC contractors working in that if the project owners are ready to share more risk, then the current unpredictable materials price inflation scenario such they will get more competitive bids. For instance, EPC contract as cement, steel etc. is that forecasting, quoting and executing awarded by Dubai municipality are footed on FIDIC contract 4. (1980) , 14 BLR 1 5. 445 U.S 911 ( 1980) Articles Conceiving and Drafting the Terms of EPC Contracts stipulations but so far, do not mirror the suggestion by FIDIC performance tests are to be made before or after such that terms for modifications in bids for variations in cost should completion. Thus, under the customary design-bid-build be introduced where it might be unjust for a service provider to contract, the designer and construction contractor will be held assume the whole of the risk of increasing costs associated with liable for varied yardsticks of performance for the completion inflation. From the perspective of a project owner, the notion of the works. It is to be noted that designers in many countries of conveyancing a price-increase provision in a contract may are not needed to undertake for results, but rather method. It appear like issuing a blank cheque, albeit he might get profit is expected from them that they have higher supreme out of it. If the contract is allowing the contractor to charge his knowledge on the subject, competent enough and can finish rate on current prices and any real enhancement, rather than a the design with a rational magnitude of technical skill. For standard-price quotation with tentative eventualities, in such instance in Surf Realty Corp v. Standing6 , the U.S court held cases, the project owners might save some handsome money that the designer, while preparing the drawings and design, and may avoid any unwanted delay and overrun in the timely should exercise his ability and skill, taste and judgement construction of the project. rationally and without neglect. Thus, this principle needs a In any EPC contract, the terms should have a price-escalation professional duty of care. (Huse 2002: 18). provision which should recognise the exact materials regarded to be unstable and the prices per unit for such project materials Liability for Defects is to be charged at rates which prevailed at the time when the An EPC contract should include a provision as to decide the contract is completed. Normally, these provisions should period of time up to which the contractor will be held illustrate unambiguously that the project owner will be responsible for rectifying any defect that may occur in the responsible for any increase in price in those basic construction works. materials like cement, steel and the total price of contract to be augmented by a settled percentage to offset the loss due to price Consortium or a Joint Venture escalation. A rational provision will lay out periods of notice Where a contractor uses a consortium or a joint venture for for recognition of price augmentation and to shun disagreements the project, a specific provision will need to be included that at later dates, to audit and verify the category of documentation it is essential to elect a representative among consortium with demonstrating the price increase, the incident that activated such adequate decision-taking authority to facilitate interaction with a boost in price of contract, what is the proper assessment of the the employer. market price, what are the time periods covered and how frequent the increase in the contract price can be made. Other matters Onus for the design supplied by the employer Provisions relating to contractor’s duty to safety and protection, In an EPC contract, it should be wise to allocate the risk to adhere to local laws and regulations have to be drafted. pertaining to design supplied by the employer between the parties by way of specific provision. Allocation of Risk in EPC Contract In an EPC contract, the risk allocation will be made in the Employer Risks following manner. The project company will assume the An EPC contract has to specify the risks associated with the market risk and in a power project, the power purchaser will employer. accept the risk to a limited extent. The EPC contractor will assume the design, construction and commissioning risks. The Performance Guarantee risks arising out of operation and maintenance will be borne There should be provision in the EPC contract for the by the O& M contractor. The overall political risk like performance guarantee by the contractor by way of providing rebellion, war and delays by authorities will be borne by the bank guarantee or other guarantee or by way of retention respective government, mainly through concession agreement. money. It is recommended that the respective government should accept these political risks as they are the sole party who could Completion either influence or control it and can lessen its impacts. An EPC contract should contain a provision regarding the Provisions concerned with risk allocation have to be drafted so extent and nature of completion needed before the employer that it would reflect the language of the agreement and other takes over the works. It is to be ascertained whether any 6. 78 S.E .2d 901 at 907 (1953) Articles Conceiving and Drafting the Terms of EPC Contracts concession. Further, it has to take into account the considerations 7. In some scenarios, the owner and the contractor like identical language for extension of time and force majeure may agree to share losses and responsibilities equally events. Such back-to-back language minimises the extent of or jointly. Here, only to the degree of a gaps and vagueness between various agreements. proportionate share of negligence, each party would A dispute resolution clause in the EPC contract will not only agree to indemnify each other. Thus, by agreement save time but also cost and helps to find a fast solution to any or through a court or through a commercial issue between the parties. (Huse 2002: 48). arbitration, each party’s liability will be determined in case of loss due to negligence. There are four fundamental risk-of-loss methodologies that an owner can impose in his EPC contract. In the case of EPC hydro contracts, contractors are always reluctant to forward their bid unless they are short listed in a (a) Demand the EPC contractor to wholly responsible and prequalification bid due to expenses and time involved in this to totally indemnify the owner, all for all, possible losses. process. Minimal design particulars are offered by the project (b) Discharge the EPC contractor from indemnity and companies in the prequalification bid document. This will cast responsibility and to fully reimburse or indemnify the on the tenderer the onus of developing the design to the point owner for all damages or losses. where he can confidently submit a firm price. In hydro electric (c) Impose an overall ceiling limit on the EPC contractor’s EPC contract, more than four or more companies are to be responsibility and indemnify for selected or for all losses. involved in a consortium to offer the overall services to be provided, which habitually set hurdles to the bidding process. (d) Adjust or modify one or more of the approaches (Head 2000:5). In hydro electric projects, the management of mentioned in tune with the owner’s predestined risk risks due to flooding during construction of the project is management program. (Bramble & West 1999:105) effectively a commercial decision, thereby balancing the The other parameters are as follows : incremental expenses of augmented flood safeguard against 1. EPC contractor should be imposed with the the chances and outcomes of particular floods happening. This sufficient risk to motivate them to execute the is mainly a concern of risk allocation between the contractor, contract in a professional style. However, imposing the owner and the insurer and normally would not involve the of unreasonable or excessive risk will hinder host government. (Head 2000:19). For instance, in Turkey, innovation and maybe yield negative results. geological risk in a hydro project is passed to the contractor from the project company. This is an obvious departure from 2. Risk allocation should be footed on the profit or the usual contract EPC terms. When the availability of work return that the party espousing risks that may is very limited, some contractors dare to accept such risks, actually have anticipated from its participation in although it is highly debatable whether it is in either party’s the project. interest. In Philippine’s Casecnan power project, which 3. The extent of control over the risk to be distributed included about twenty-six kilometre tunnel and an underground must be taken into account in establishing a suitable power manufacturing unit, for which virtually no site allocation of responsibility. investigation was possible and the contractor undertook the 4. It should be seen that the party is having the ability whole risk of unpredictable ground scenarios within his fixed to cover the risk through insurance or by other price quote. However, he failed midway through the contract methods, which are a crucial element in risk and had to be replaced. Thus unforeseen risk may cost an allocation. ( Bramble and West 1999 :101) EPC contractor his job and his resources. 5. Full indemnity and responsibility are obtained from Likewise, in Malaysia’s Bakun hydroelectric project, an EPC EPC contractors by owners for all equipments and contractor made a lump sum price bidding with no price tools either owned or rented by the contractor used escalation for unforeseen risks. In that project, excavation of in the project site. tunnels disclosed weaker rock conditions than expected, needing 6. For all equipments and tools supplied or loaned by an addition of the steel liner. This is a common issue, but it the owner to the contractor, full responsibility is cannot be anticipated in advance and may materialise only during the construction stage and will have huge cost implications that placed on the EPC contractor for use in carrying cannot be borne by the contractor due to its magnitude, especially out the work and many owners contractly negate in a lump sum EPC contract where if there is any absence of such representation or fitness for such an equipment provision of price inflation for such an eventuality, the EPC and tool. Articles Conceiving and Drafting the Terms of EPC Contracts contractor may be able to restructure the cost effect by making reasons. Reading together with sub-clause 4.10, it imposes all some changes in design, but it may have an impact on the final obligations on the contractor for unforeseen site scenarios. Thus, quality of the project. Further, such design change may end in the contractor runs this risk despite whether the employer offered a debate over whether the proposed changes can be acceptable the information on the original site conditions or where the site under the contract. (Head 2000:57). conditions were, in fact, unpredictable. In fact, the aftermath In an EPC or turnkey project, competitive price bidding can of this clause is to make the contractor responsible for be made possible with certain kind of sharing of risks as unpredictable or conditions, which are wholly out of the control mentioned below. of a contractor. Thus, under Silver Book, the contractor has the EPC contract containing both a lump sum and re- responsibility to bear the risk associated with unforeseen site measurable portion and re-measurement is mainly conditions. In fact, sub-clause 4.12 of the Silver Book spells applicable to civil works and unexpected geological risks, out that there shall be no modification in the contract price to especially in case of flooding, weaker rock conditions take account of any unforeseen costs or difficulties. For instance, or other unforeseeable events. countries like Malaysia and Hong Kong allocate risk for differing conditions solely on the contractor in the government contracts. Restricting the re-measurable portion of contract; hence (Huse 2002:144). the owner undertakes lesser risk leaving the contractor to assume an unlimited risk. Sub-Contractor A stratum approach where the employer, insurance Though an EPC contractor is authorised to entrust the work company and the contractor bear some portion of risk in to sub-contractors, the Silver Book sub-clause 4.4 spells out a predefined order. some mandatory provisions with regard to sub-contractors. Cost overrun has to be shared on a predetermined The above sub-clause imposes the following : percentage basis. An EPC contractor cannot sub-contract the whole of the Specific geological associated risk in the construction is work to sub-contractors. to be passed on to the owner or the contractor but with It makes the EPC contractor liable for the activities of reimbursement of additional expenses to avoid what had his agents, sub-contractors and employees. happened in Casecnan power project and in Bakun hydroelectric project. Force Majeure Clauses Thus, an EPC contract may have risk-sharing formulas and in Due to the occurrence of an unexpected event, if performance case of any additional cost of risk due to happening of an becomes “impossible”, a party may be condoned from carrying unforeseen incident has to be met by sponsors of the project out a commitment under an EPC contract under the most legal through pumping in contingent equity, mainly to cater for the system. However, there exists many numbers of legal precedents possible cost overruns. (Head 2000:57). where courts were of the opinion that the doctrine of For instance, India was less successful in attracting private impossibility cannot be extended just because completion of finance for its hydropower projects, mainly due to some risk the contract will happen to be more costly than earlier expected. allocation, which is hazardous to any project contract. Hence, Majority of contractors are under the wrong impression that the it revised power policy to encourage private foreign investment availability of the force majeure clause will help them to succeed in its hydroelectric projects. The new pragmatic policies of in their claim. It is to be noted that a force majeure clause is the Indian government acknowledged the necessity to offer included into a contract as a way to safeguard parties if a section the private developer safeguard against wide varieties of natural of the contract could not be completed due to the occurrence of risk over which such contractor has no sway. Thus, for risk some extraordinary incidence, which falls outside the control arising out of an unforeseen natural predicament, EPC of the parties and which could not have been forbidden using contractor will not be held liable. This may encourage a large rational care. Force majeure clause can ordinarily be seen in all number of international bidders to participate in a contract the construction contracts but normally such provision is meant and may result in cost savings and timely completion of the to grant a contractor some extra period to complete the contract. project (Head 2000:62). Hence, whereas a force majeure clause may facilitate a contractor Ground Conditions some additional time to acquire materials that are in acute shortage, it is doubtful of help to him if he is compelled to bear Sub-clause 4.12 of the Silver Book acts as a reference for several much escalated prices of material than he formerly forecasted. Articles Conceiving and Drafting the Terms of EPC Contracts The reality is that judges normally do not incline to permit methodologically drafted EPC contract will pay special attention somebody to get away from an obligation under a contract under to the allocation of project risks and with specific reference to the pre-text of force majeure clause. (Kerur 2005). the drafting of common terms in EPC contracts. Else, the contractor’s interest will be affected, and he may have to incur CONCLUSION pecuniary losses. Thus, while drafting the terms of international Of late, FIDIC has released a new form of contract that can be EPC contract and allocation of risks in the EPC contract, serious considerations should be given while drafting of terms so that used with design and construction of projects employing interests of both the contracting parties are properly secured. engineering, procurement and construction contract or turnkey contracting. Under this contract, the FIDIC conditions of List of Reference turnkey or EPC projects (known as the silver book) are Bramble Barry B & West Joseph D. (1999). Design Build designed to handle scenarios where bids are invited on an Contracting Claims. Illinois: Aspen Publishers Online. international basis. It has been specifically designed for use in Head, Chris R. (2000). Financing of Private Power Projects. New EPC and BOT contracts. However, law firms and large York: World Bank Publications. contractors will have their own in-house standard EPC contract and for these parties silver book may act as a solid reference Hoffman Scott L. (2008). The Law and Business of International to update and review their in-house standard forms. For those Project Finance. Cambridge: Cambridge University Press. law firms and contractors, who do not have standard EPC, Huse, Joseph A. (2002). Understanding and negotiating turnkey contractor or firms may use the Silver Book for drafting their and EPC contracts. New York: Sweet & Maxwell. EPC contract terms. (Huse 2002: 48). Kerur Sachin [June 16 2005]. Sharing the Risks. (Online) available Thus, a legal draftsman has to use not only standard terms as from http://www1.fidic.org/resources/contracts/national/ mentioned in the silver book but also to use his experience to dubai_jun05.asp [accessed 30 October 2009). cover force majeure, price escalation, sovereign immunity, Wilpert Bernhard & Fahlbruch Babette. (2002). System Safety: unforeseen ground scenarios to safeguard the interest of the Challenges and Pitfalls of Intervention. New York: Emerald Group contracting parties. A well planned and conceived and Publishing.