Precast Modular Block For Retaining Wall Systems
Precast Modular Block For Retaining Wall Systems
Field Installation
Best Practices Manual
TABLE OF CONTENTS
INTRODUCTION 3
DEFINITIONS 3
CONSTRUCTION RESPONSIBLILITES 4
Precast Retaining Wall Dealer
Engineer or Owner’s Representative
Contractor
SITE PREPARATION 5
EXCAVATION 5
FOUNDATION PREPARATION 6
CONSTRUCTION TOLERANCES 7
CLEANUP 7
TROUBLESHOOTING 7
REFERENCES 8
DEFINITIONS
backfill – earth or other material placed between a retaining wall manufacturer’s representative – a product representative able
and existing ground to replace material that has been previously to provide technical assistance to the contractor, engineer or
excavated. owner.
backfill soil -– either in-situ soils or borrow soil used to fill exca- OSHA – Occupational Safety and Health Administration
vated and over-excavated areas behind the wall system. These
soils shall be free of debris and deleterious material. owner –owner of the project or property, who is identified in the
project contract as being responsible for the payment for the
base course – first, or lowest, footing course to be installed; it work performed under the terms of the contract.
may be totally or partially buried.
Precast Modular Block (PMB) - wetcast modular retaining wall
base material – selected free-draining granular material of a block
planned thickness, compacted and leveled to support the base
course; in unusual applications, the base course may be a lean proof-rolling – several passes from a 10-ton smooth-drum vibra-
concrete as specified by the design engineer. tory roller or loaded tandem-axle truck used to compact subgrade
soils and/or indentify any soft or loose pockets that may require
borrow soil -– any soil imported from another location, typically removal and replacement, additional compaction, and/or further
offsite, to be used as backfill. investigation by the geotechnical engineer.
contractor – person or entity who undertakes responsibility of reinforced soil – compacted structural fill placed behind the PMB
the construction of the retaining wall. units to interact with the geogrid reinforcement; this area extends
from behind the PMB units to the tail end of the geogrid.
discing – to cultivate or break up soil using a harrow or plow that
turns and loosens soil with a series of discs retained soil – soil immediately behind the PMB units or gravel
fill in conventional gravity-wall systems or immediately behind the
drainage column – see gravel fill reinforced soil for mechanically stabilized PMB units.
engineer – owner’s designated organization or trained and shop drawings – graphics, usually in contract documents,
experienced individual with authoritative charge over engineering produced by the PMB supplier to show installation details for the
functions and responsibilities. contractor.
foundation soil – soil mass supporting the wall base. Founda- site contractor – organization responsible for the installation of
tion soil is typically undisturbed in-situ soils; these soils may be the wall system.
compacted to reduce settlement from base excavation work.
Proof-rolling may be required in order to obtain a firm, unyielding soil compaction – proper soil placement and consolidation
base for the wall. are essential to the successful performance of retaining wall
structures. Soils must be compacted in specified lifts to achieve
gravel fill – free-draining, coarse-grained aggregates placed either maximum soil shear strength and validate the design.
within the PMB unit cores and between their openings or directly
behind the units. Depth of gravel fill should be specified in the subbase soil – see foundation soil
contract documents. The gravel fill acts to facilitate drainage either
through the PMB units or behind them, depending on its place- subgrade soil – see foundation soil
ment, by accepting incidental water thereby relieving hydrostatic
pressures. Wall drainage should not be used for conveyance of swale – a depression or lower level in a stretch of flat land.
site runoff; adequate surface drainage structures above and be-
hind the wall should be provided within the site plan. wall base –- level surface either of gravel fill or lightweight con-
crete used to distribute the weight of the PMB units evenly over
leveling pad - see wall base the underlying subgrade.
EXCAVATION
wall base
Layout the location and length of the wall. If possible, always
start the wall base at the lowest elevation of the entire wall. construction
Excavate as required for installation of the retaining wall system. Construct the wall base to the lines and grades shown on the
Use caution not to over-excavate beyond the depth needed for the plans. The base may be constructed from lean concrete with a
foundation. minimum 28-day compressive strength of 3,000 psi concrete or
granular material. Construct base to the material and dimensions
Slope or shore excavation as necessary for safety and for confor- shown on the plans. Over-excavated areas shall be filled with ad-
mance with applicable OSHA requirements. ditional concrete or granular base material.
Compact the wall base to provide a hard and level surface to sup-
port the precast wall unit. Base material shall be compacted to
a minimum of 95 % of the maximum dry density (ASTM D698,
Standard Proctor).