CC Road 2018-19

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 19

SPECIFICATION REPORT

Est Cost Rs 0.00 Lakhs

The above work is reprented by the Hon,ble MLC Sri PJ Chandrasekar rao for acccording administratively sanction
Accordingly the detailed estimate is prepared with following Provisions

Accordingly The Estimate is prepared with the following Provisions

1 Removal of unsuitable / Unserviceable soil including excavation, loading and disposal upto 1000 m lead but excluding compaction ground
supporting embankment subgrade replacement by suitable soil, which shall be paid separately as per Clause 303.5.2 as per Technical
Specification Clause 302.3.11 MORD / 301 MORTH

2 Supplying and filling of 2.36mm HBG Chips with initial lead in layers not exceeding 15 cm thick consolidatiing each deposited layer by
watering and rampping including cost and conveyance of water to work site and all operational incidental ,labour charges hire charges
and T & O Complete for finished item

3 Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as
per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine
aggregates conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum capacity and appropeiate weigh batcher using
approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 mictron thick polythene film, wedges,
steel plates including levelling the formwork as per drawing), spreading the concrete with sholvels, rakes, compacted using needle,
scareed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints,
applying debonding strips, primer, sealant, dowel bars, near approaches to bridge / culvert and construction joints, admixtures as
approved, curing of concrete slabs for 14- days, curing compound (where specified) and water finishing to lines and grade as per drawing
and Technical Specification Clause 1501 MORD.

4 Supplying and filling gravel in trenches , with initial lead in layers not exceeding 15 cm thick consolidatiing each deposited layer by
watering and rampping including cost and conveyance of water to work site and all operational incidental ,labour charges hire charges
and T & O Complete for finished item

5 Supplying and fixing of Mild steel dowel bar 25mm dia for Joint

6 Add 0.50% QC Charges

7 Add 5% VAT Charges

8 Add LS for U/S items of work

The Estimate is prepared with SSR 2011-12 and submitted for administrative sanction.

Asst. Engineer Dy Executive Engineer


PRISD Maheshwaram PRI SD Ibrahimpatanam
DETAILED CUM ABSTRACT ESTIMATE

Construction of Side Drain


Total 5.00
Sl.
Description of work No L B D Qty Rate/per Amount
no
1 2 3 4 5 6 7 8 9

1 Removal of unsuitable / Unserviceable soil including excavation, loading and disposal upto
1000 m lead but excluding compaction ground supporting embankment subgrade
replacement by suitable soil, which shall be paid separately as per Clause 303.5.2 as per
Technical Specification Clause 302.3.11 MORD / 301 MORTH

For Box Cutting 1 146.00 6.00 0.050 43.80 74.97 3284.00


cum / cum
2 Supplying and filling of 2.36mm HBG Chips with initial lead in layers not exceeding 15 cm
thick consolidatiing each deposited layer by watering and rampping including cost and
conveyance of water to work site and all operational incidental ,labour charges hire
charges and T & O Complete for finished item

Base 1 146.00 6.00 0.050 43.80 3105.02 136000.00


cum / cum
3 Plain Cement concrete (1:4:8) using 40 mm metal with concrete mixture. All work
upto plinth level. nominal mix (cement: fine aggregate: Coarse aggregate) using 40mm
size HBG (SS5) metal from approved quarry including cost and conveyance of all materials
like cement, sand, coarse aggregate, water etc. to site, including seigniorage charges,
Countryes & other taxes on all materials, all operational, incidental, and labor charges
such as mixing, laying and ramming concrete in layers in position not exceeding 15cm,
finishing top surface, curing concrete, etc., complete for finished item of work for
levelling Course

1 146.00 6.00 0.10 87.60 4249.32 372240.00


4 Construction of un-reinforced, dowel jointed at expansion and construction joint only,
plain cement concrete pavement, thickness as per design, over a prepared sub base, with
43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine
aggregates conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum
capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed
side formwork (steel channel, laying and fixing of 125 mictron thick polythene film,
wedges, steel plates including levelling the formwork as per drawing), spreading the
concrete with sholvels, rakes, compacted using needle, scareed and plate vibrators and
finished in continuous operation including provision of contraction and expansion,
construction joints, applying debonding strips, primer, sealant, dowel bars, near
approaches to bridge / culvert and construction joints, admixtures as approved, curing of
concrete slabs for 14- days, curing compound (where specified) and water finishing to
lines and grade as per drawing and Technical Specification Clause 1501 MORD.

1 146.00 6.00 0.10 87.60 8884.95 778322.00


cum / cum
5 Supplying and fixing of Mild steel dowel bar 25mm dia for Joint including all
labour charges etc complete 4.00 1790.70 7163.00
Nos / Joint
1293725.00
Total Rs 1293725.00
DETAILED CUM ABSTRACT ESTIMATE

0
Total 5.00
Sl.
Description of work No L B D Qty Rate/per Amount
no
1 2 3 4 5 6 7 8 9

1 Removal of unsuitable / Unserviceable soil including excavation, loading and disposal upto
1000 m lead but excluding compaction ground supporting embankment subgrade
replacement by suitable soil, which shall be paid separately as per Clause 303.5.2 as per
Technical Specification Clause 302.3.11 MORD / 301 MORTH

For Box Cutting 1 146.00 6.00 0.050 43.80 74.97 3284.00


cum / cum
2 Supplying and filling of 2.36mm HBG Chips with initial lead in layers not exceeding 15 cm
thick consolidatiing each deposited layer by watering and rampping including cost and
conveyance of water to work site and all operational incidental ,labour charges hire
charges and T & O Complete for finished item

Base 1 146.00 6.00 0.050 43.80 3105.02 136000.00


cum / cum
3 Plain Cement concrete (1:4:8) using 40 mm metal with concrete mixture. All work
upto plinth level. nominal mix (cement: fine aggregate: Coarse aggregate) using 40mm
size HBG (SS5) metal from approved quarry including cost and conveyance of all materials
like cement, sand, coarse aggregate, water etc. to site, including seigniorage charges,
Countryes & other taxes on all materials, all operational, incidental, and labor charges
such as mixing, laying and ramming concrete in layers in position not exceeding 15cm,
finishing top surface, curing concrete, etc., complete for finished item of work for
levelling Course

1 146.00 6.00 0.10 87.60 4249.32 372240.00


4 Construction of un-reinforced, dowel jointed at expansion and construction joint only,
plain cement concrete pavement, thickness as per design, over a prepared sub base, with
43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine
aggregates conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum
capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed
side formwork (steel channel, laying and fixing of 125 mictron thick polythene film,
wedges, steel plates including levelling the formwork as per drawing), spreading the
concrete with sholvels, rakes, compacted using needle, scareed and plate vibrators and
finished in continuous operation including provision of contraction and expansion,
construction joints, applying debonding strips, primer, sealant, dowel bars, near
approaches to bridge / culvert and construction joints, admixtures as approved, curing of
concrete slabs for 14- days, curing compound (where specified) and water finishing to
lines and grade as per drawing and Technical Specification Clause 1501 MORD.

1 146.00 6.00 0.10 87.60 8884.95 778322.00


cum / cum
5 Supplying and fixing of Mild steel dowel bar 25mm dia for Joint including all
labour charges etc complete 4.00 1790.70 7163.00
Nos / Joint
1293725.00
Total Rs 1293725.00
DETAILED CUM ABSTRACT ESTIMATE

0
Total 5.00
Sl.
Description of work No L B D Qty Rate/per Amount
no
1 2 3 4 5 6 7 8 9

1 Removal of unsuitable / Unserviceable soil including excavation, loading and disposal upto
1000 m lead but excluding compaction ground supporting embankment subgrade
replacement by suitable soil, which shall be paid separately as per Clause 303.5.2 as per
Technical Specification Clause 302.3.11 MORD / 301 MORTH

For Box Cutting 1 146.00 6.00 0.050 43.80 74.97 3284.00


cum / cum
2 Supplying and filling of 2.36mm HBG Chips with initial lead in layers not exceeding 15 cm
thick consolidatiing each deposited layer by watering and rampping including cost and
conveyance of water to work site and all operational incidental ,labour charges hire charges
and T & O Complete for finished item

Base 1 146.00 6.00 0.050 43.80 3105.02 136000.00


cum / cum
3 Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain
cement concrete pavement, thickness as per design, over a prepared sub base, with 43
grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine
aggregates conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum
capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed
side formwork (steel channel, laying and fixing of 125 mictron thick polythene film, wedges,
steel plates including levelling the formwork as per drawing), spreading the concrete with
sholvels, rakes, compacted using needle, scareed and plate vibrators and finished in
continuous operation including provision of contraction and expansion, construction joints,
applying debonding strips, primer, sealant, dowel bars, near approaches to bridge / culvert
and construction joints, admixtures as approved, curing of concrete slabs for 14- days,
curing compound (where specified) and water finishing to lines and grade as per drawing
and Technical Specification Clause 1501 MORD.

1 146.00 6.00 0.17 148.92 8884.95 1323147.00


cum / cum
4 Supplying and fixing of Mild steel dowel bar 25mm dia for Joint including all
labour charges etc complete 4.00 1790.70 7163.00
Nos / Joint
1466310.00
Total Rs 1466310.00
DETAILED CUM ABSTRACT ESTIMATE

0
Total 5.00
Sl.
Description of work No L B D Qty Rate/per Amount
no
1 2 3 4 5 6 7 8 9

1 Removal of unsuitable / Unserviceable soil including excavation, loading and disposal upto
1000 m lead but excluding compaction ground supporting embankment subgrade
replacement by suitable soil, which shall be paid separately as per Clause 303.5.2 as per
Technical Specification Clause 302.3.11 MORD / 301 MORTH

For Box Cutting 1 40.00 3.75 0.150 22.50 70.35 1583.00


cum / cum
2 Supplying and filling of 2.36mm HBG Chips with initial lead in layers not exceeding 15
cm thick consolidatiing each deposited layer by watering and rampping including cost and
conveyance of water to work site and all operational incidental ,labour charges hire
charges and T & O Complete for finished item

Base 1 40.00 3.75 0.050 7.50 926.60 6950.00


cum / cum
3 Construction of un-reinforced, dowel jointed at expansion and construction joint only,
plain cement concrete pavement, thickness as per design, over a prepared sub base, with
43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine
aggregates conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum
capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed
side formwork (steel channel, laying and fixing of 125 mictron thick polythene film,
wedges, steel plates including levelling the formwork as per drawing), spreading the
concrete with sholvels, rakes, compacted using needle, scareed and plate vibrators and
finished in continuous operation including provision of contraction and expansion,
construction joints, applying debonding strips, primer, sealant, dowel bars, near
approaches to bridge / culvert and construction joints, admixtures as approved, curing of
concrete slabs for 14- days, curing compound (where specified) and water finishing to
lines and grade as per drawing and Technical Specification Clause 1501 MORD.

1 40.00 3.75 0.17 25.50 6394.45 163058.00


cum / cum
4 Supplying and fixing of Mild steel dowel bar 25mm dia for Joint including all
labour charges etc complete
2 40 0.6 0.15 7.20 258.52 1861.00
Nos / Joint
173452.00
5 Add 0.50% QC Charges

6 Add 12% VAT Charges 20814.00

7 Add LS for U/S items of work

Total Rs 194266.00
305734.00
500000.00
Asst. Engineer Dy Executive Engineer
PRISD Maheshwaram PRI SD Ibrahimpatanam
Data Sheet

RATE ANALYSIS (ROAD WORK) - SSR 2018-19

Index
S.No. Description of item Unit Qty Rate Amount
Code

1 RBR- Removal of unsuitable / Unserviceable soil including excavation, loading and


EECD disposal upto 1000 m lead but excluding compaction ground supporting
-7 embankment subgrade replacement by suitable soil, which shall be paid
separately as per Clause 303.5.2 as per Technical Specification Clause 302.3.11
MORD / 301 MORTH

Unit = cum
Taking output = 360 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 2.08 425.00 884.00
Area allowences 0.40 884.00 353.60
b) Machinery
52 Excavator 0.90 cum bucket capacity @ 100 cum per hour 3.60 2967.90 10684.44
I&CAD hour

54 Tipper 5.5 cum capacity, 4 trips per hour hour 15.00 1004.40 15066.00
I&CAD

c&d) Overheads & Contractors Profit 0.00000 26988.04 0.00


Cost for 360 cum = a+b+c+d 26988.04
Rate per cum = (a+b+c+d)/360 Rs 74.97
Rate per Cum
2 5 i) a) Excavation in Cutting in Soil by manual
means with lead upto 50 m
Excavation for roadway in soil using manual
means for carrying of cut earth to embankment
site with initial lift of 3 mts and lead upto 50 m
as per Technical Specification Clause 302.3
MORD

Unit = cum
Taking output = 120 cum
a)  Labour
Mazdoor (Unskilled) day 46.80 425.00 19890.00
Area allowences 0.40 19890.00 7956.00
Cost of 120 cum = a+b+c 27846.00
Add seignorage charges day 120.00 0.00
Overheads & Contractors Profit 0.00000 27846.00 0.00
Rate per cum = (a+b+c)
27846.00
Sundries
0.00
Rate per cum = (a+b+c)/120 Rs
232.05

Page 6 of 19
Data Sheet

Index
S.No. Description of item Unit Qty Rate Amount
Code

3 BLD- Supplying and filling of 2.36mm HBG Chips with initial lead in layers not
CSTN- exceeding 15 cm thick consolidatiing each deposited layer by watering and
2-9 rampping including cost and conveyance of water to work site and all operational
incidental ,labour charges hire charges and T & O Complete for finished item

Unit : 1 cum
Taking output : 6 cum
a) Labour
Mazdoor ( Unskilled) No 0.31 425.00 131.75
Cost of 2.36mm HBG Chips Cum 6.00 3074.28 18445.68
Area allowences 0.40 131.75 52.70
Rate per 6 cum 18630.13
Overheads & Contractors Profit 0.00000 18630.13 0.00
18630.13
Rs 3105.02
Seignorage charges Cum 1.00 75.00 75.00

Rate per cum Rs 3180.02


4 Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain
cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade
cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates
conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum capacity and
appropeiate weigh batcher using approved mix design, laid in approved fixed side formwork (steel
channel, laying and fixing of 125 mictron thick polythene film, wedges, steel plates including
levelling the formwork as per drawing), spreading the concrete with sholvels, rakes, compacted
using needle, scareed and plate vibrators and finished in continuous operation including provision of
contraction and expansion, construction joints, applying debonding strips, primer, sealant, dowel
bars, near approaches to bridge / culvert and construction joints, admixtures as approved, curing of
concrete slabs for 14- days, curing compound (where specified) and water finishing to lines and
grade as per drawing and Technical Specification Clause 1501 MORD including overhead charges &
Contractors profit but excluding VAT.

,
Unit = cum
Taking output = 75cum (172.50 t)
(100x3.75 x 0.200)
a) Labour
Mason (1st class) day 5.00 470.00 2350.00
Mason (2nd class) day 5.00 450.00 2250.00
Mazdoor (unskilled) day 150.00 425.00 63750.00
Mazdoor(skilled) day 6.00 425.00 2550.00
Surveyor day 2.00 750.00 1500.00
Mazdoor (semi-skilled) day 6.00 425.00 2550.00
74950.00
Area allowences 0.40 74950.00 29980.00
(A) 104930.00
b) Machinery
Page 7 of 19
Data Sheet

Index
S.No. Description of item Unit Qty Rate Amount
Code

18 I&CAD Concrete mixer 0.28/0.40 cum capacity ( 6 Hour 36.00 534.30 19234.80
mixers) with weight batcher and suitable
capacity calibrated water tank
42 I&CAD Needle vibrator 60 mm Hour 9.00 216.70 1950.30
48 R&B Plate vibrator Hour 9.00 53.76 483.84
10 R&B Water tanker 6 Kl. Capacity Hour 5.00 698.88 3494.40
2 I&CAD Air compressor ( 1hour initial + 1 hour final) Hour 2.00 588.40 1176.80
(B) 26340.14
c) Material
(I) Crushed stone coarse aggregates, grading will be
as per clause 1501.2.4.1 (Table 1500.1) of
specifications @ 0.90 Cum/cum of concrete

20 mm Cum 44.55 3743.78 166785.39


10 mm Cum 22.95 3477.53 79809.31
(ii) Sand as per IS:383 and conforming to clause cum 33.75 3169.35 106965.56
1500.2.4.2. @ 0.45 cum of concrete
(iii) Cement @ 350 Kg/cum of concrete t 26.25 4816.45 126431.81
(iv) Polythene sheet 125 micron 412.50 17.00 7012.50
TBSC-Q.I- Plasticizer 0.5 per cent by weight of cement litre 122.00 78.00 9516.00
06

15 Curing compound (if used) @ 0.33 litre per sqm litre 131.25 119.00 15618.75

BMS- Maustic pads12.7mm thick as per IS:1838 sqm 6.25 568.00 3550.00
W.21 ( 29.40*3.75*.17/3 =6.25 ) for 1/3 depth only
sl
no
965
154& Water for curing kl 18.00 98.00
155
(C ) 515689.32
Total ( a + b + c ) 646959.46
(d) Form work @ 3% on (a+b+c) 19408.78
Cost for 75 cum = a+b+c+d 666368.24
Rate per Cum = (a+b+c+d+e)/75 8884.91
Overheads & Contractors Profit 0.00000 8884.91 0.00
8884.91
Add Sundries 0.04
Rs 8884.95
Add Seign Charges
Metal Cum 0.90 75.00 67.50

Sand Cum 0.45 90.00 40.50

Rate per cum Rs. 8992.95

Page 8 of 19
Data Sheet

Index
S.No. Description of item Unit Qty Rate Amount
Code

5 Supplying and fixing of Mild steel dowel bar


25mm dia of grade S 240.500 mm long 20 Nos. at
Joints including 5 percent wastage per 75 Cum

(4x20x0.500) + 5 per cent wastage = 42m @ 2.80 Kg 117.60 43079.65 5066.17


Kg per m = 117.6 kg.
Black smith for cutting of dowel bars including day 1.00 470.00 470.00
removal of bars, fabrications & fixing of dowel
bars per 75 Cum
Area allowences 0.40 470.00 188.00
271 Jute rope 12mm dia including 5 per cent m 90.00 8.30 747.00
wastage per
Polythene 75 Cum covering 2/3rd dowel bars
sheathing, No 483.00 1.00 483.00
(20x23) and tight fit including 5 per cent
wastage
6954.17
Form work @ 3% on (a+b+c) 208.63
Per 4 Joints 7162.79
Overheads & Contractors Profit 0.0000 7162.79 0.00
7162.79
Sundries 0.00
Rate Per Joint Rs 1790.70
6 BLD- Supplying and filling gravel in trenches , with initial lead in layers not exceeding
CSTN- 15 cm thick consolidatiing each deposited layer by watering and rampping
2-9 including cost and conveyance of water to work site and all operational incidental
,labour charges hire charges and T & O Complete for finished item

Unit : 1 cum
Taking output : 6 cum
a) Labour
Mazdoor ( Unskilled) No 0.31 425.00 131.75
Cost of Gravel Cum 6.00 238.66 1431.96
Area allowences 0.40 131.75 52.70
1616.41
Add 14% overhead charges, Contractor profit 0.0000
1616.41 0.00

Rate per 6 cum 1616.41


Rate per 1 cum Rs 269.40
Add Seign Charges
Gravel Cum 1.00 30.00 30.00

Rate per cum Rs 299.40


`

Asst. Engineer
PRISD Maheshwaram

Page 9 of 19
L E A D S T A T E M E N T 2018-19

Est Cost Rs

Total Cost
UnLoadin of the
Machine
Sl Roads SSR Lead in Lead charges
Deduct 13.615 %
Net Lead Blasting Seignorag g Charges Materials
Description in Material Name of the Quarry (As per SoR)
over head
charges Initial Cost Crushing (Excludin
No. Item Km charges Charges e Charges Excl
Charges
13.615% g Seign
OH Charges)

1 2 3 4 5 6 7 8 9 10 11 12 13 14

1 Cement As on 4750.00 66.45 4816.45

2 Fe-250Steel As on 43000.00 79.65 43079.65

3 Gravel Local 34 10.00 159.80 19.14 140.66 98.00 0.00 0.00 30.00 238.66

5 Selected earth Local 34 5.00 91.30 10.94 80.36 40.00 0.00 0.00 30.00 120.36

5 Sand for Blindage Local 36(c) 250.00 2941.80 352.52 2589.28 570.00 0.00 0.00 90.00 10.07 3169.35

6 Sand for concrete Karimnagar Vagu 36(B) 250.00 2941.80 352.52 2589.28 570.00 0.00 0.00 90.00 10.07 3169.35

7 2.36 and below Stone Dust Ankireddypally 35(B) 250.00 2941.80 352.52 2589.28 485.00 0.00 0.00 75.00 3074.28

8 10 mm HBG Chips-SS5 Ankireddypally 33(B) 250.00 2941.80 352.52 2589.28 657.00 164.25 67.00 75.00 3477.53

9 12 mm HBG Chips-SS5 Ankireddypally 33(C) 250.00 2941.80 352.52 2589.28 781.00 195.25 67.00 75.00 3632.53

10 20 mm HBG Metal-SS5 Ankireddypally 33(D) 250.00 2941.80 352.52 2589.28 870.00 217.50 67.00 75.00 3743.78

11 40 mm HBG Metal-SS5 Ankireddypally 33(F) 250.00 2941.80 352.52 2589.28 505.00 126.25 67.00 75.00 3287.53

12 40-45mmHBG M/C Metal Ankireddypally 33(G) 250.00 2941.80 352.52 2589.28 520.00 130.00 67.00 75.00 3306.28

13 25-27 mm HBG M/C Metal Ankireddypally 33(F) 250.00 2941.80 352.52 2589.28 790.00 197.50 67.00 75.00 3643.78

14 19-22 mm HBG M/C Metal Ankireddypally 33(E) 250.00 2941.80 352.52 2589.28 821.00 205.25 67.00 75.00 3682.53

15 12-14 mm HBG M/C Metal Ankireddypally 33(D) 250.00 2941.80 352.52 2589.28 700.00 175.00 67.00 75.00 3531.28

16 9.5-11.2 mm HBG M/C Metal Ankireddypally 33(C) 250.00 2941.80 352.52 2589.28 620.00 155.00 67.00 75.00 3431.28

17 5-7 mm HBG M/C Metal Ankireddypally 33(B) 250.00 2941.80 352.52 2589.28 485.00 121.25 67.00 75.00 3262.53

18 2.36-5 mm HBG M/C Metal Ankireddypally 33(A) 250.00 2941.80 352.52 2589.28 485.00 121.25 67.00 75.00 3262.53

19 2.36 and below Ankireddypally 35(b) 250.00 2941.80 352.52 2589.28 485.00 75.00 3074.28
12 Man mazdoor 425
13 Woman mazdoor 425
14 Semi skilled Mason/Electrician / 2nd Class Carpentor or Painter /Balck smith/Bar bender /Helper 450
15 Skilled Mason /1st Class Carpentor / Bllack Smith Muncipal allowance MA 40% 470
16 Allowance Over Heads OH 0.000%
17 Water 98.00 13.615
1) This is to certify that the proposed leads over and above initial 1kM
2) This is to certify that the proposed leads of the work is true and nearet to the best of my knowledge
3) This is to certified that the stone requires blasting
4) This is to certified that the proposed work is located with in the Muncipal limits of 12KM

Asst. Engineer
PRISD Maheshwaram
Lead charges 2018-19

Metal Gravel & Sand

SSR 2018-19 SSR 2018-19


Lead Rate Lead Rate
1 33.00 1 34.20
2 46.20 2 47.90
3 63.90 3 63.90
4 77.60 4 77.60
5 91.30 5 91.30
6 105.00 6 105.00
7 118.70 7 118.70
8 132.40 8 132.40
9 146.10 9 146.10
10 159.80 10 159.80
11 173.50 11 173.50
12 187.20 12 187.20
13 200.90 13 200.90
14 214.60 14 214.60
15 228.30 15 228.30
16 242.00 16 242.00
17 255.70 17 255.70
18 269.40 18 269.40
19 283.10 19 283.10
20 296.80 20 296.80
21 310.50 21 310.50
22 324.20 22 324.20
23 337.90 23 337.90
24 351.60 24 351.60
25 365.30 25 365.30
26 379.00 26 379.00
27 392.70 27 392.70
28 406.40 28 406.40
29 420.10 29 420.10
30 433.80 30 433.80
31 445.20 31 445.20
32 456.60 32 456.60
33 468.00 33 468.00
34 479.40 34 479.40
35 490.80 35 490.80
36 502.20 36 502.20
37 513.60 37 513.60
38 525.00 38 525.00
39 536.40 39 536.40
40 547.80 40 547.80
41 559.20 41 559.20
42 570.60 42 570.60
43 582.00 43 582.00
44 593.40 44 593.40
45 604.80 45 604.80
46 616.20 46 616.20
47 627.60 47 627.60
48 639.00 48 639.00
49 650.40 49 650.40
50 661.80 50 661.80
51 673.20 51 673.20
52 684.60 52 684.60
53 696.00 53 696.00
54 707.40 54 707.40
55 718.80 55 718.80
56 730.20 56 730.20
57 741.60 57 741.60
58 753.00 58 753.00
59 764.40 59 764.40
60 775.80 60 775.80
61 787.20 61 787.20
62 798.60 62 798.60
63 810.00 63 810.00
64 821.40 64 821.40
65 832.80 65 832.80
66 844.20 66 844.20
67 855.60 67 855.60
68 867.00 68 867.00
69 878.40 69 878.40
70 889.80 70 889.80
71 901.20 71 901.20
72 912.60 72 912.60
73 924.00 73 924.00
74 935.40 74 935.40
75 946.80 75 946.80
76 958.20 76 958.20
77 969.60 77 969.60
78 981.00 78 981.00
79 992.40 79 992.40
80 1003.80 80 1003.80
81 1015.20 81 1015.20
82 1026.60 82 1026.60
83 1038.00 83 1038.00
84 1049.40 84 1049.40
85 1060.80 85 1060.80
86 1072.20 86 1072.20
87 1083.60 87 1083.60
88 1095.00 88 1095.00
89 1106.40 89 1106.40
90 1117.80 90 1117.80
91 1129.20 91 1129.20
92 1140.60 92 1140.60
93 1152.00 93 1152.00
94 1163.40 94 1163.40
95 1174.80 95 1174.80
96 1186.20 96 1186.20
97 1197.60 97 1197.60
98 1209.00 98 1209.00
99 1220.40 99 1220.40
100 1231.80 100 1231.80
101 1243.20 101 1243.20
102 1254.60 102 1254.60
103 1266.00 103 1266.00
104 1277.40 104 1277.40
105 1288.80 105 1288.80
106 1300.20 106 1300.20
107 1311.60 107 1311.60
108 1323.00 108 1323.00
109 1334.40 109 1334.40
110 1345.80 110 1345.80
111 1357.20 111 1357.20
112 1368.60 112 1368.60
113 1380.00 113 1380.00
114 1391.40 114 1391.40
115 1402.80 115 1402.80
116 1414.20 116 1414.20
117 1425.60 117 1425.60
118 1437.00 118 1437.00
119 1448.40 119 1448.40
120 1459.80 120 1459.80
121 1471.20 121 1471.20
122 1482.60 122 1482.60
123 1494.00 123 1494.00
124 1505.40 124 1505.40
125 1516.80 125 1516.80
126 1528.20 126 1528.20
127 1539.60 127 1539.60
128 1551.00 128 1551.00
129 1562.40 129 1562.40
130 1573.80 130 1573.80
131 1585.20 131 1585.20
132 1596.60 132 1596.60
133 1608.00 133 1608.00
134 1619.40 134 1619.40
135 1630.80 135 1630.80
136 1642.20 136 1642.20
137 1653.60 137 1653.60
138 1665.00 138 1665.00
139 1676.40 139 1676.40
140 1687.80 140 1687.80
141 1699.20 141 1699.20
142 1710.60 142 1710.60
143 1722.00 143 1722.00
144 1733.40 144 1733.40
145 1744.80 145 1744.80
146 1756.20 146 1756.20
147 1767.60 147 1767.60
148 1779.00 148 1779.00
149 1790.40 149 1790.40
150 1801.80 150 1801.80
151 1813.20 151 1813.20
152 1824.60 152 1824.60
153 1836.00 153 1836.00
154 1847.40 154 1847.40
155 1858.80 155 1858.80
156 1870.20 156 1870.20
157 1881.60 157 1881.60
158 1893.00 158 1893.00
159 1904.40 159 1904.40
160 1915.80 160 1915.80
161 1927.20 161 1927.20
162 1938.60 162 1938.60
163 1950.00 163 1950.00
164 1961.40 164 1961.40
165 1972.80 165 1972.80
166 1984.20 166 1984.20
167 1995.60 167 1995.60
168 2007.00 168 2007.00
169 2018.40 169 2018.40
170 2029.80 170 2029.80
171 2041.20 171 2041.20
172 2052.60 172 2052.60
173 2064.00 173 2064.00
174 2075.40 174 2075.40
175 2086.80 175 2086.80
176 2098.20 176 2098.20
177 2109.60 177 2109.60
178 2121.00 178 2121.00
179 2132.40 179 2132.40
180 2143.80 180 2143.80
181 2155.20 181 2155.20
182 2166.60 182 2166.60
183 2178.00 183 2178.00
184 2189.40 184 2189.40
185 2200.80 185 2200.80
186 2212.20 186 2212.20
187 2223.60 187 2223.60
188 2235.00 188 2235.00
189 2246.40 189 2246.40
190 2257.80 190 2257.80
191 2269.20 191 2269.20
192 2280.60 192 2280.60
193 2292.00 193 2292.00
194 2303.40 194 2303.40
195 2314.80 195 2314.80
196 2326.20 196 2326.20
197 2337.60 197 2337.60
198 2349.00 198 2349.00
199 2360.40 199 2360.40
200 2371.80 200 2371.80
201 2383.20 201 2383.20
202 2394.60 202 2394.60
203 2406.00 203 2406.00
204 2417.40 204 2417.40
205 2428.80 205 2428.80
206 2440.20 206 2440.20
207 2451.60 207 2451.60
208 2463.00 208 2463.00
209 2474.40 209 2474.40
210 2485.80 210 2485.80
211 2497.20 211 2497.20
212 2508.60 212 2508.60
213 2520.00 213 2520.00
214 2531.40 214 2531.40
215 2542.80 215 2542.80
216 2554.20 216 2554.20
217 2565.60 217 2565.60
218 2577.00 218 2577.00
219 2588.40 219 2588.40
220 2599.80 220 2599.80
221 2611.20 221 2611.20
222 2622.60 222 2622.60
223 2634.00 223 2634.00
224 2645.40 224 2645.40
225 2656.80 225 2656.80
226 2668.20 226 2668.20
227 2679.60 227 2679.60
228 2691.00 228 2691.00
229 2702.40 229 2702.40
230 2713.80 230 2713.80
231 2725.20 231 2725.20
232 2736.60 232 2736.60
233 2748.00 233 2748.00
234 2759.40 234 2759.40
235 2770.80 235 2770.80
236 2782.20 236 2782.20
237 2793.60 237 2793.60
238 2805.00 238 2805.00
239 2816.40 239 2816.40
240 2827.80 240 2827.80
241 2839.20 241 2839.20
242 2850.60 242 2850.60
243 2862.00 243 2862.00
244 2873.40 244 2873.40
245 2884.80 245 2884.80
246 2896.20 246 2896.20
247 2907.60 247 2907.60
248 2919.00 248 2919.00
249 2930.40 249 2930.40
250 2941.80 250 2941.80
251 2953.20 251 2953.20
252 2964.60 252 2964.60
253 2976.00 253 2976.00
254 2987.40 254 2987.40
255 2998.80 255 2998.80
256 3010.20 256 3010.20
257 3021.60 257 3021.60
258 3033.00 258 3033.00
259 3044.40 259 3044.40
260 3055.80 260 3055.80
261 3067.20 261 3067.20
262 3078.60 262 3078.60
263 3090.00 263 3090.00
264 3101.40 264 3101.40
265 3112.80 265 3112.80
266 3124.20 266 3124.20
267 3135.60 267 3135.60
268 3147.00 268 3147.00
269 3158.40 269 3158.40
270 3169.80 270 3169.80
271 3181.20 271 3181.20
272 3192.60 272 3192.60
273 3204.00 273 3204.00
274 3215.40 274 3215.40
275 3226.80 275 3226.80
276 3238.20 276 3238.20
277 3249.60 277 3249.60
278 3261.00 278 3261.00
279 3272.40 279 3272.40
280 3283.80 280 3283.80
281 3295.20 281 3295.20
282 3306.60 282 3306.60
283 3318.00 283 3318.00
284 3329.40 284 3329.40
285 3340.80 285 3340.80
286 3352.20 286 3352.20
287 3363.60 287 3363.60
288 3375.00 288 3375.00
289 3386.40 289 3386.40
290 3397.80 290 3397.80
291 3409.20 291 3409.20
292 3420.60 292 3420.60
293 3432.00 293 3432.00
294 3443.40 294 3443.40
295 3454.80 295 3454.80
296 3466.20 296 3466.20
297 3477.60 297 3477.60
298 3489.00 298 3489.00
299 3500.40 299 3500.40
300 3511.80 300 3511.80
301 3523.20 301 3523.20

You might also like