Proposal Computer Replacement Aizad
Proposal Computer Replacement Aizad
Since 2007, our company had a problem with the computer, So i have been selected
to be the project Manager for the computer replacement plan ,
The PC replacement project is intended to replace all primary office
computers that are obsolete and do not meet the recommended minimum
standard. The minimum standard is determined by the Standard’s
Committee and is to be updated annually. With the help from deans and
department heads, new computer purchases will be deployed based on
division priorities. All primary computer support staff will work together to
minimize the university’s expense and be as efficient as possible during the
deployment..
Changes, New or Special needs: New computing needs may arise for a
computer or printer (an additional staff member, replace equipment before
its standard replacement cycle, or change from previous model). These
special needs must be identified and funded during the annual budget
approval process or approved by a Vice President
To address these issues all computers across the campus will be placed on a
regularly scheduled replacement cycle based upon our current information
technology standards. There are three separate processes to replace our existing
computer technology:
Phase I -
o Employee Computer Replacement Process
o Network switches in the wiring closets which support student
labs
Phase II -
o Classrooms/labs Computer Replacement Process
o Server Replacement Process
.
The goals of the technology replacement plan are to:
The Employee Replacement Process covers all faculty, staff, and administrative
computers, notebooks, and Macintosh workstations assigned to district employees.
It includes workstations for faculty, classified staff and administrators as well as
general use computers shared in an area or used by substitute or part-time
workers. Areas which are funded on a cost recovery basis, such as Community
Education or specific grants, may not be covered under this replacement plan.
This process calls for the replacement of all employee computers every five
years. To accomplish this goal, the campus has been divided geographically into five
equal parts, based on the number of employee computers in each area. Each year
new computers will be provided to all employee users in each of these designated
areas. PC’s for new positions will also be funded by this plan. During the first cycles
of this plan, if the new position will be located in an area that has yet to be fully
replaced, then a recycled computer will be made available.
To accomplish this goal a timetable and budget has been recommended, which
includes the prioritization for the areas. Individual machines that will be replaced are
detailed on thisworksheet . The process will start with Year 1 computers being
ordered around July 2010, so the installation disruption can occur during summer.
There will be approximately 200 new workstations installed each fiscal year under the
employee replacement process.
Request for Exceptions to the Computer Replacement Process
In some situations users may be required to run special software or perform unique
tasks as part of their assigned job duties, and may need a computer with more
memory, a faster processor, a larger monitor, or a larger hard disk than the one they
are using or will be assigned. Users in this situation may request that their
workstation be evaluated to determine an appropriate upgrade path. IT may
recommend additional memory, a larger hard drive, or possibly a newer
workstation. The user’s division/department may be required to fund these upgrades
if there are not adequate funds within the replacement budget.
While we expect that the majority of requests will come at the beginning of the fiscal
year, requests will be reviewed throughout the year to handle unforeseen changes in
job duties, etc.
The process calls for the replacement of PCs and Macintoshes every five years. To
accomplish this goal, the College has created a lab replacement schedule for the
academic computer labs. The schedule begins with the 2005-06 fiscal year and
details subsequent years including estimated costs. This timetable should be
reviewed by various constituency groups and provide any feedback as soon as
possible. Based on the feedback received, adjustments are made to ensure that
appropriate technology resources are available in each area.
Installation Process
PC Macintosh
Microsoft Windows 7 Mac 10.4.x Tiger
Office 2007 Safari
Internet Explorer 8 Office 2008
SharePoint Designer 2007 Entourage or Mail
McAfee Virus Scan Enterprise 8.x iTunes
Acrobat Reader 9.x Virus Scan 8.x
Microsoft Media Player 11.x Acrobat Reader 8.x
SARS Grid Microsoft Media Player 9.x
Quicktime 7.x iMovie 3.x
iTunes 9.x Quicktime 7.x
Windows Defender
Roxio Creator (DVD/CD)
Premier AT 10
Adobe Flash Player 10
Shockwave Player 11
Java 6 update X
VLC Player (DVD/CD)
RealPlayer SP 1.X
Learning Styles Inventory
FireFox 3.x
Latest OS Updates
The College has been divided geographically into five parts, based on the number of
employee computers in each area. The locations prioritization has been approved
by the Presidents' Cabinet. The implementation schedule below will be followed as
funding permits.
Priority
2 = Year 2 - Next
3 = Year 3
4 = Year 4
5 = Year 5
Budget recommendations:
Plan on spending $1275. per computer (not including tax).
Lecturer :