SOCAR Construction

Download as pdf or txt
Download as pdf or txt
You are on page 1of 162

Moscow, Prechistenskaya Nab.

 No:17 | Tel :  +7 (499) 502 88 88 
54 Elif Hajıyev Street, Baku, AZ1060, Azerbaijan | Tel: (+99412) 521 07 80/81 | Fax: (+99412) 422 30 50
www.socarcons.com | [email protected]
INDEX

1. SOCAR Construction in Brief
2. Manpower
3. Machinery & Equipment
4. Project References
5. QA / QC Plan
6. HSE Plan
7. Winterization Plan

www.socarcons.com | [email protected]
SOCAR Construction in Brief

www.socarcons.com | [email protected]
SOCAR Construction in Brief

SINCE: 1949
SOCAR Oil and Gas Construction was founded on the base of
AzerDenizNeftInshaat founded on 31 October 1949 and
KhazarDenizNeftGazTikinti founded on 7 May 1979 to develop onshore and
offshore oil and gas fields.

www.socarcons.com | [email protected]
Main Activities

Construction and Modernization of:
‐ offshore jackets (10‐150m);
‐ offshore piers (0‐30m);
‐ ports and port facilities;
‐ offshore (up to 150m) and onshore oil‐ gas‐water pipelines in different diameters;
‐ offshore and onshore gas‐compressor stations;
‐ offshore and onshore oil terminals and other technological facilities;
‐ electric power supply system for fields;
‐ high‐voltage subsea cable lines
‐ high‐voltage cable and overhead power lines
‐ underground gas storages

www.socarcons.com | [email protected]
Other works

‐ Anticorrosion activities (blasting, painting etc.);
‐ Civil construction;
‐ Production of precast‐concrete items;
‐ Fabrication and installation of steel structures;
‐ Production of asphalt‐concrete;
‐ Asphalt‐concrete paving of main roads, streets and squares;
‐ Supply of all kind construction materials and equipment;
‐ Testing of welding joints by destructive and non‐destructive methods.

www.socarcons.com | [email protected]
CERTIFICATES

On 19 February 2002, Trust was honored


with TSE-ISO-EN 9001 - “Quality
Management System Certificate” by the
respective Commission of Turkey Standards
Institute (TSI) in Ankara .

On 25 December 2002, Trust was honored


with TSE-ISO-EN 14001 “Environmental
Management System Certificate” by the
respective Commission of Turkey Standards
Institute (TSI)in Ankara.

On 11 January 2005, Trust was honored


with TS-18001 -“Occupational Health and
Safety Management System Certificate” by
the respective Commission of Turkey
Standards Institute (TSI)in Ankara.

www.socarcons.com | [email protected]
Organization Chart

www.socarcons.com | [email protected]
SOCAR Construction Divisions

www.socarcons.com | [email protected]
SOCAR Construction Divisions

Construction and Installation Division (CID‐1) 

Performs installation of power lines and subsea cable lines, electrical equipment,
construction of electrical substations, capital construction and overhaul associated with
power supply, cathodic protection of pipeline and other structures, instrumentation
works.

Employees: 217
Location: Zykh yard

www.socarcons.com | [email protected]
SOCAR Construction Divisions

Construction and Installation Division (CID‐2) 

Construction of onshore (underground and aboveground) and offshore 
oil‐gas‐water pipelines.

Employees: 519
Location: Zykh yard/Garadagh

www.socarcons.com | [email protected]
SOCAR Construction Divisions

Construction and Installation Division (CID‐3) 

Performs fabrication and installation of offshore platforms, installation of hydraulic 
facilities, process pipelines, different equipment, dismantling of high capacity tanks, 
capital construction, overhaul and rehabilitation of stationary water jackets, oil‐field 
hydraulic and water cooling facilities, high pressure oil and gas pipelines, oil reservoirs, 
quay wall and finger piers.

Employees: 561
Location: Zykh yard

www.socarcons.com | [email protected]
SOCAR Construction Divisions

Construction and Installation Division (CID‐4)

Construction, repair and rehabilitation of compressor stations, high pressure oil and
gas pipelines, oil reservoirs, asphalt‐concrete paving, finger piers and pier‐side
platforms, stationary water jackets, support blocks and process systems at “Oil
Rocks” OGPD

Employees: 592
Location: Oil Rocks

www.socarcons.com | [email protected]
SOCAR Construction Divisions

Construction and Installation Division (CID‐5)

Performs construction and asphalt‐concrete paving of highways, streets and squares


at Oil Rocks, Chilov Island, Sangachal area and Absheron peninsula by asphalt‐
concrete facilities, as well as construction, repair and rehabilitation of residential
apartments for oil workers and other social units.
Asphalt Concrete Plants:
Sangachal – 80 tonne/hour
Hovsan – 45 tonne/hour
Employees: 507
Location: Hovsan

www.socarcons.com | [email protected]
SOCAR Construction Divisions

Construction and Installation Division (CID‐6)

Construction, repair and rehabilitation of compressor stations, high pressure oil and
gas pipelines, oil reservoirs, asphalt‐concrete paving, finger piers and pier‐side
platforms, stationary water jackets, support blocks and process systems at
“Absheronneft” OGPD.

Employees: 281
Location: Pirallahi

www.socarcons.com | [email protected]
SOCAR Construction Divisions

Construction and Installation Division (CID‐7)

Performs construction, repair and rehabilitation of compressor stations, high


pressure oil and gas pipelines, oil reservoirs, asphalt‐concrete paving, finger piers
and pier‐side platforms, stationary water jackets, support blocks and process
systems at OGPD named after N. Narimanov.

Employees: 313
Location: Sangachal

www.socarcons.com | [email protected]
SOCAR Construction Divisions

Specialized Repair and Construction Division (SPCD)

Performs vacuum painting, manual and mechanical anticorrosion activities of 
offshore platforms, piers, oil reservoirs, pressurized manifolds, subsea pipelines and 
onshore steel structures. Production yards are located at Oil Rocks area, Pirallahi and 
Chilov islands, Dubendi, Sangachal, Galmaz, Garadagh and Zykh production yard, 
Guneshli field.

Employees: 273
Location: Zykh yard

www.socarcons.com | [email protected]
SOCAR Construction Divisions

Precast Concrete Production Division (PCPD)

Produces all types of precast concrete items and ready‐mixed concrete required for 
offshore platforms, civil construction and other worksites based on awarded service 
contracts.

Employees: 178
Location: Zykh yard

www.socarcons.com | [email protected]
SOCAR Construction Divisions

Warehouse Management Division (WMD)

Performs  procurement, receiving, storage and distribution of materials and 
equipment required for construction, installation and production works carried out 
by Oil and Gas Construction Trust.
WMD of OGCT has Railway connection and necessary lifting infrastructure for loading 
and unloading materials and goods.

Closed area: 4.469 m2
Open area: 27.267 m2

Employees: 42
Location: Zykh yard

www.socarcons.com | [email protected]
SOCAR Construction Divisions

Representative office in Georgia (RG)

Functioning since 2006, performs installation of oil and gas pipelines and different 
hydraulic facilities and infrastructure projects in Georgia.

Employees: 60
Location: Georgia

www.socarcons.com | [email protected]
SOCAR Construction Divisions

Electrical laboratory is operating within Trust to provide: 

• Voltage  test of power networks,
• Voltage  test of cables,
• Grounding test of building and erections and etc.

www.socarcons.com | [email protected]
SOCAR Construction Divisions

Welding Technology, Destructive and Non‐destructive Test Division (WTDNTD)

WTDNTD consists of 630 m2 workshop and 400 m2 administrative building.

• WTDNTD applies automatic and semi‐automatic welding for the latest achievements 
of modern techniques and technologies and provide improvement of welders’ 
competence level.
• WTDNTD is involved in examining quality of welding joints by visual and physical 
methods (X‐Ray, ultrasonic, MPI and penetration test) which gives suitable 
references.
• WTDNTD prepares specifications of welding procedures (WPS) according to 
requirements of TS EN ISO/IEC 17025, international and other standards of physical 
and mechanical (fragility, bending, impact viscosity, hardness) testing based on 
project requirements.

Employees: 49
Location: Zykh yard

On 01 May 2008, OGCT was honored with TSE EN ISO/IEC 17024 -


“Welders’ Certification” by the respective Commission of TurkAK.

www.socarcons.com | [email protected]
SOCAR Construction Divisions ‐ Quality & HSE

Head of Division

Deputy

Certification Industrial Quality


HSE Ecology
and Audit Sanitary Control
Department Laboratory Department Department
Department

www.socarcons.com | [email protected]
Fabrication Yards

• Khatai warehouse/supply yard  ‐ 7.000 m2;


• Garadagh Yard  ‐ 16.000 m2;
• Pirsaat Yard ‐ 30.000 m2;
• Dubandi Yard  ‐ 30.000 m2;
• Hovsan Yard  ‐ 93.500 m2;
• Zykh Yard ‐ 317.000 m2. 

Main fabrication yard of Oil and Gas Construction Trust Zykh Fabrication Yard is located at the 
seaside. The base was built for line production of 14.000 ton support structures, various topside 
platform structures  including modules and structural elements of fixed offshore platforms to 
operate at water depth up to 140 meter.
The base is reliably provided with electric power from power supply system by means of dedicated  
6/0.4 kW substation with two transformers of 6/0.4 kW up to 1.000 kW each and branchy cable 
network in closed concrete cable channels. Zykh base has close guard perimeter.
The base has been also provided with fire protection system, waste‐water disposal and fresh water 
systems.

www.socarcons.com | [email protected]
Fabrication Yards

Zykh‐3 
Fabrication of various topside structures for offshore platforms

• Pier of 3.840 m2 area for loading and unloading heavy tonnage vessels, bridge‐port
• Welding and fitting workshop of 3.355 m2 area with 2 pcs bridge cranes of 50 and 12.5 ton capacity
• 990 m2 welding workshop with a 15 ton bridge crane intended to be used for welders’ trainings
• Closed workshop.  Workshop area is 780 m2
• 3 outdoor welding and fitting areas 4.200 m2 each with 50 ton gantries and welding stations
• Mechanical shop equipped with various metal‐working machines and two 10 ton bridge cranes
• Administrative building and amenity rooms (showers, changing rooms, toilets, etc.) with total area of 1.152 m2
• 6/0.4 kW Electric power substation
• Pumping plant (drainage station) 12 m2
• Railway branch
• Highway 

www.socarcons.com | [email protected]
Fabrication Yards

Zykh ‐4 
Fabrication and launching support structures

•Assembly and launch skids  (slip) allowing fabrication  of offshore  platform jacket
with bearing capacity of 50 tons/m2
•3 indoor 2 span assembly  and welding workshops fitted with a 50 ton capacity bridge
crane in every span. Total area is 3.456 m   
•Oxygen station producing 120 m3/hour of oxygen per hour with a filling dispenser
department allowing for filling of 15 bottles oxygen per hour
•6/0.4 kW Electric Power Substation

www.socarcons.com | [email protected]
2. Manpower

www.socarcons.com | [email protected]
Manpower Resources

WORKER SPECIALIZATION

Welders
Fitters
5% Electrical fitters
20%
Locksmith
Crane operators
34% Other construction workers
Other workers
1%
30%

5%

5%

www.socarcons.com | [email protected]
Manpower Resources

Item Staff category Number of staff


1 Management 426
2 Specialists 295
Other employees
3 30
(technical workers)
4 Workers 3106
TOTAL 3857

1 Welders 615
2 Fitters 944
3 Electrical fitters 163
4 Locksmith 144
5 Crane operators 26
6 Other construction workers 1065
7 Other workers 149
TOTAL WORKERS 3106

STAFF CATEGORY

11%
8%
Management

1%
Specialists

Other employees (technical
80% workers)
Workers

www.socarcons.com | [email protected]
3. Machinery & Equipment

www.socarcons.com | [email protected]
List of Machinery & Equipment

Description Qty. Description Qty.


MOBILE CRANES (<50 tons) 356 PILING MACHINES 16
MOBILE CRANES (>=50 tons & <100 tons) 43 BULLDOZERS 185
MOBILE CRANES (>=100 tons) 3 2608
PICK‐UPS
TRUCKS WITH CRANE 246
LOADERS 298
CRAWLER CRANES (<50 tons) 148 34
GRADERS
CRAWLER CRANES (>=50 tons & <100 tons) 38 CONCRETE BATCHING PLANTS 12
CRAWLER CRANES (300 tons) 20 ASPHALT PLANTS 26
CRAWLER CRANES (500 tons) 12 COMPRESSORS 69
DRILLING RIG (<50 tons) 522 TRACTORS 34
DRILLING RIG (>=50 tons & <100 tons) 334 FLATBED TRAILERS 254
DRILLING RIG (>=100 tons) 29 LOWBED TRAILERS 391
EXCAVATOR‐CRANE 80 OTHER TRAILERS 321
EXCAVATORS 545 BREAKERS 28
PIPE LAYER (<50 tons) 228 WELDING MACHINES 615
58 NDT EQUIPMENT 88
PIPE LAYER (>=50 tons & <=100 tons)
362 WORKSHOP MACHINES 455
MINIBUS
HEAT BLOWERS 608
CONCRETE PUMPS 211
MOBILE LABORATORIES 236
FORKLIFTS (MANLIFT/TELEPORTER) 62
MOBILE CONCRETE LABORATORY 143
BUS 1465
MOBILE  SEISMIC LABORATORY  12
CARS 1484
SUV 971
TRAILERS 1328
DUMP TRUCKS 825
MIXER TRUCKS 785
OTHER TRUCKS 713
COMPACTORS 152
VIBRATORS 54
WEIGHBRIDGE 533
FIRE EXTINGUISHER 243
STEAM UNIT 164
HOIST WASHING UNIT 155

www.socarcons.com | [email protected]
4. Project References

www.socarcons.com | [email protected]
Industrial References

www.socarcons.com | [email protected]
Omsk Refinery VDU/CDU ‐ Various Mechanical Erection Works
Omsk / Russia

www.socarcons.com | [email protected]
SOCAR Polymer – HDPE Plant & PP Plant & U&O Area
Baku / Azerbaijan

www.socarcons.com | [email protected]
SOCAR Polymer – HDPE Plant & PP Plant & U&O Area
Baku / Azerbaijan

www.socarcons.com | [email protected]
SOCAR Polymer – HDPE Plant & PP Plant & U&O Area
Baku / Azerbaijan

www.socarcons.com | [email protected]
South Caucasus Pipeline Expansion Project
Azerbaijan‐Georgia

www.socarcons.com | [email protected]
Western Route Project / Azerbaijan

www.socarcons.com | [email protected]
Sangachal Terminal Project / Azerbaijan

www.socarcons.com | [email protected]
Sangachal Terminal Project / Azerbaijan

www.socarcons.com | [email protected]
Production, Compression and Utilities Platform Project
Azerbaijan

www.socarcons.com | [email protected]
Production, Compression and Utilities Platform Project
Azerbaijan

www.socarcons.com | [email protected]
ATA Yard Facility / Azerbaijan

www.socarcons.com | [email protected]
Construction of Baku-Supsa Main Oil Pipeline
Project title (Western Route Export Pipeline) 20”, L=480km,
P=64bar
Customer AIOC
Contractor Azfen/Tekfen JV

Role in Contract Subcontractor

Handover date 1998

Connecting pipelines between “Azertrans” and


Project title “Sangachal” Terminals, 16” (L=11,5km) and 30”
(L=11.56km)
Customer “Azertrans” LTD
Contractor Oil and Gas Construction Trust

Role in Contract Contractor

Handover date 2005

www.socarcons.com | [email protected]
Project title 30” Georgian Gas Off take Pipeline (L=12.2km)

Customer BP, South Caucasus Pipelines Company (SCP)


Contractor Oil and Gas Construction Trust
Role in Contract Contractor
Handover date 2006

Rehabilitation works on Georgian Oil and Gas


Project title Corporation's North-South Gas Pipeline (48”,
L=4.5km)
Customer Millennium Challenge Georgian Fund
Contractor Oil and Gas Construction Trust
Role in Contract Contractor
Handover date 2007

www.socarcons.com | [email protected]
Rehabilitation works at Gardabany-Navtlugi site
Project title of “Saquramo-Red Bridge” Main Gas Pipeline
(28”, L=30.35km)
Customer Georgian Oil and Gas Corporation JSC
Contractor Oil and Gas Construction Trust
Role in Contract Contractor
Handover date 2007

Replacement of 48” Gas Pipeline (L=9.6km) and


28” Oil Pipeline (L=10.1km) under Construction of
Project title
“Takhtakorpu” Water Storage with Hydroelectric
Power Station Project

Ministry of Agriculture of Republic of the


Customer
Azerbaijan
Contractor Oil and Gas Construction Trust
Role in Contract Contractor
Handover date 2008

www.socarcons.com | [email protected]
Installation of medium pressure gas pipeline of
Project title
Kabali district of Lagodekhi district

Customer SOCAR Georgia Gas LLC

Contractor Oil and Gas Construction Trust

Role in Contract Contractor


Handover date 2010

Installation of medium-pressure gas lines in Algeti


Project title and Tazakand villages of Marneuli district (19,825
r/m)

Customer SOCAR Georgia Gas LLC

Contractor Oil and Gas Construction Trust

Role in Contract Contractor


Handover date 2011

www.socarcons.com | [email protected]
Installation of medium-pressure gas lines in Keshalo
Project title village of Marneuli district (700 consumers, 35,539
r/m)
Customer SOCAR Georgia Gas LLC

Contractor Oil and Gas Construction Trust


Role in Contract Contractor
Handover date June 2013

Installation of medium-pressure gas lines in Didi


Project title Muganlo village of Marneuli district (412
consumers, 16,394 r/m)
Customer SOCAR Georgia Gas LLC

Contractor Oil and Gas Construction Trust


Role in Contract Contractor
Handover date 2011

www.socarcons.com | [email protected]
LAM-C wellhead platform load-out, sea
fastening, transportation and installation work
Project title package
Caspian Sea - Turkmenistan

Customer Petroliam Nasional Berhad (PETRONAS)

Contractor Level Oil and Gas Corporation

Role in Contract Subcontractor


Handover date February 2012

Construction of 29 km Section of Gas Pipeline


Project title
Abasha-Senaki Project
Customer Georgian Oil and Gas Corporation JSC

Contractor Oil and Gas Construction Trust

Role in Contract Contractor


Handover date May 2013

www.socarcons.com | [email protected]
Rehabilitation of Kareli Water Supply System
Project title
Project
Customer Municipal Development Fund of Georgia
Contractor Oil and Gas Construction Trust
Role in Contract Contractor
Financing European Investment Bank
Handover date Ongoing

Rehabilitation of Telavi-Kurdgelauri Water


Project title
Supply System Project
Customer Municipal Development Fund of Georgia
Contractor Oil and Gas Construction Trust
Role in Contract Contractor
Financing European Investment Bank
Handover date Ongoing

www.socarcons.com | [email protected]
Project title Construction of Baku Shipyard Project

Customer Baku Shipyard LLC

Contractor Oil and Gas Construction Trust

Role in Contract EPCm Contractor

Handover date September 2013

www.socarcons.com | [email protected]
“Construction of ofshore Jacket (SWJ)#122 for
Project title
drilling of 3 production wells at “Bulla-Deniz” field”
Customer Azneft PU, named after N.Narimanov OGPD
Oil and Gas Construction Trust, Construction
Contractor Installation Board #8 (present Construction
Installation Board #3)
Handover date March, 2014
Purpose increase of production

www.socarcons.com | [email protected]
Construction of SWJ#112 for drilling of
Project title
10 production wells at “Chilov” field
Customer Azneft PU, 28th May OGPD
Oil and Gas Construction Trust,
Construction Installation Board #3
Contractor
(present Construction Installation
Board #2)
Handover
December, 2014
date
Construction of additional support
Purpose block to drill wells for oil-gas
production increase

Project Construction of SWJ #20 for drilling of


title 10 wells at “Western Absheron” field”
Customer Azneft PU, Absheronneft OGPD
Oil and Gas Construction Trust,
Construction Installation Board #3
Contractor
(present Construction Installation
Board #2)
Handover
July, 2014
date
Construction of an additional
Purpose supporting block to drill wells for oil-
gas production increase

“Installation of subsea oil-gas pipeline


between Deep Water Jacket
Project title
(DWJ)#29 and DWJ #14 at “Bulla-
Deniz” field”
Azneft PU, named after N.Narimanov
Customer
OGPD
Oil and Gas Construction Trust,
Contractor
Construction Installation Board #2
Handover
July, 2014
date
Installation of pipeline for
Purpose
transportation of produced oil

www.socarcons.com | [email protected]
"Installation of subsea oil pipelines
between Oil Collection Station
Project title
(OCS) #3 - OCS#1, OCS#1-Dashgil
OCS"
Azneft PU, named after
Customer
N.Narimanov OGPD
Oil and Gas Construction Trust,
Construction Installation Board #3
Contractor
(present Construction Installation
Board #2)
Handover
October, 2013
date
Ensure transportation of produced
Purpose oil and gas to the shore facilities
without loss

"Construction of SWJ#740 for drilling


Project title of 8 production wells at “Darvin
bankasi” field”
Customer Azneft PU, Absheronneft OGPD
Oil and Gas Construction Trust,
Construction Installation Board #8
Contractor
(present Construction Installation
Board #3)
Handover
October, 2013
date
Drilling of 8 wells to increase oil
Purpose
production

www.socarcons.com | [email protected]
“Construction of FOP #2150 for drilling of 12 production
Project title
wells at “Oil Rocks” field”
Customer Azneft PU, Oil Rocks OGPD
Oil and Gas Construction Trust, Construction Installation
Contractor
Board #8 (present Construction Installation Board #3)
Handover date August, 2013
Purpose increasing of oil and gas production

Construction of offshore platform #2585 for Oil Rocks


Project title
(complex II)
Customer Azneft PU, Oil Rocks OGPD
Oil and Gas Construction Trust, Construction Installation
Contractor
Board #4 (present Construction Installation Board #3)
Handover date September, 2012
Purpose Drilling of 12 wells to increase oil production

www.socarcons.com | [email protected]
Rehabilitation of new Cooling Tower of Ethylene-
Project title
Polyethylene Plant
Customer Azerikimya PU, Ethylene-Polyethylene Plant
Oil and Gas Construction Trust, Construction Installation
Contractor
Board #4 (present Construction Installation Board #3)
Handover date May, 2013
Ensure cooling of 21 m3 water per hour for EP-300 complex
Purpose
of Plant
“Construction of platform, support buildings and plants for
Project title New Gas Turbine Electric Station at Oil Rocks field ( I & II
Complex)”
Customer Azneft PU, Oil Rocks OGPD
Oil and Gas Construction Trust, Construction Installation
Contractor
Board #7 (present Construction Installation Board #4)
Handover date July, 2013
Purpose Power Supply of Oil Rock, Gunashli fields, and Chilov island

www.socarcons.com | [email protected]
Construction of hydro carbons collection and transportation systems,
Project title
and site modernization at OGPS#1, 2 and 5 of “Bibiheybat” OGPD
Customer Azneft PU, Bibiheybatneft OGPD
Oil and Gas Construction Trust, Construction Installation Board #8
Contractor
(present Construction Installation Board #3)
Handover
February, 2013
date
Site treatment from oil waste and construction of modern collection-
Purpose
transportation system

Rehabilitation of Galmaz Underground Gas Storage (I , II and IV


Project title
completion)
Customer Azneft PU, Gas Storage Operation Department
Oil and Gas Construction Trust, Construction Installation Board #5
Contractor
(present Construction Installation Board #4)
Handover
December, 2012
date
Ensure continuous gas supply to gas storages during gas supply
Purpose
season

www.socarcons.com | [email protected]
Construction of hydrocarbon
collection and transportation
Project
systems and site modernization at
title
OGPS#4 of “Bibiheybat” OGPD (I
complex completion)
Customer Azneft PU, Bibiheybatneft OGPD
Oil and Gas Construction Trust,
Construction Installation Board #5
Contractor
(present Construction Installation
Board #4)
Handover
February, 2011
date
Purpose Environmental protection

Installation of dry gas and naphta


pipelines between Baku Oil Refinery
plant named after Heydar Aliyev
Project title
and Ethylene-Polyethylene Plant of
“Azerikimya” PU (2 lines) (II
complex)
Baku Oil Refinery Plant named after
Customer
Heydar Aliyev
Oil and Gas Construction Trust,
Contractor
Construction Installation Board #2
Handover
December, 2011
date
Utilization of crude oil refinery
Purpose
wastes in chemical industry

Enlargement and rehabilitation of


Project title SWJ# 29 to drill exploration well #
90 at “Bulla Deniz” field
Azneft PU, named after
Customer
N.Narimanov OGPD
Oil and Gas Construction Trust,
Construction Installation Board #8
Contractor
(present Construction Installation
Board #3)
Handover
July, 2012
date
Enlargement and rehabilitation of
Purpose water jacket to increase gas
production

www.socarcons.com | [email protected]
Construction and Modernization of piers and offshore platforms

Number
Total
of Number of
# Name of project weight,
support wells
tonne
blocks
"Construction of offshore platform №1 for drilling 1
1 6 5.200 6
exploration and 5 production wells in "Umid" field"

“Construction of offshore platform №620 for drilling of


2 10 1.800 20
20 production wells in “Darwins Banka” field

"Construction of offshore platform №720 for drilling of


3 9 1.950 12
12 production wells in “Darwins Banka” field"

"Construction of offshore platform №2585 for drilling of


4 4 7.000 12
12 production wells in "Oil Rocks" field"

"Construction of offshore platform №122 for drilling of


5 10 2.600 3
3 production wells in “Bulla deniz” field"

"Construction of offshore platform №20 for drilling of 10


6 9 2.100 10
production wells in “West Absheron” field"
"Construction of Gas-Lift Compressor station in
7 2 11.500 N/A
"Guneshli" field"
"Construction of offshore platform №7 in “Guneshli”
8 1 28.000 20
field"

"Construction of offshore platform №6 for drilling of 4


9 11 4.500 4
production wells in “Bulla deniz” field"

"Construction of offshore platform №602A for drilling of


10 8 2.700 14
14 production wells in "Oil Rocks" field"

www.socarcons.com | [email protected]
Modernization of offshore platforms

Number of wells
Number of Total
# Name of project support weight,
blocks tonne initial additional

"Modernization and enlargement of


1 1 24 12
offshore platform №14 in "Guneshli" field" 8.600

"Modernization and enlargement of


2 1 16 8
offshore platform №11 in "Guneshli" field" 5.120

"Modernization and enlargement of


3 offshore platform №340 for drilling of 8 6 8 8
850
production wells in “Darwins Banka” field"

"Modernization and enlargement of


4 offshore platform №190 for drilling of 6 2 10 6
400
production wells in “Darwins Banka” field"

"Modernization and enlargement of


5 offshore platform №29 for drilling of 5 2 1
1.450
exploration well №90 in "Bulla deniz" field"

www.socarcons.com | [email protected]
150 MW combined Cycle Power Plant, Kayseri, Turkey

Project : Turn Key Power Plant Construction


Client : Zorlu Energy

55mw Combined Cycle Power Plant

Employer : Zorlu Enerji


Location : Sincan - Ankara

www.socarcons.com | [email protected]
Denizli Cement Plant Cogeneration Project

Employer : Denizli Cimento San. Tic. A.fi.


Location : Denizli -Kaklik
Project : Prokon Muhendislik
Scope : 24.000 m2

www.socarcons.com | [email protected]
Turkmenbashi Onshore Gas
L.M Packaging Plant
Terminal Project Fabrication Yard

Employer : Lawson Mardon


Location : Almaty - Kazaknstan
Main Contractor : Fintraco Construction

B.A.T. Factory

Employer : B.A.T
Location : Samarkand - Uzbekhstan
Main Contractor : John Laing-Alsim Alorko Construction J.V

www.socarcons.com | [email protected]
Turkmenbashi Onshore Gas
GREAT MAN ‐ MADE RIVER PROJECT
Terminal Project Fabrication Yard

Employer : GMRA -Libya, STTFA Const.Co.


Location : Sirte, Libya

SANGACHAL TERMINAL

Employer : AIOC - Azerbaijan International


Oil Company
Location : Baku, Azerbaijan
Contractor : AZFEN J.V

www.socarcons.com | [email protected]
Turkmenbashi Onshore Gas
SUPSA TERMINAL
Terminal Project Fabrication Yard

Employer : GPC Georgian Pipeline Company - Kvarner - John Brown


Location : Supsa, Georgia
Contractor : AZFEN J.V

SELAHUDDIN REFINERY

Employer : Techrip, La Defece, France.


Contractor : Gama A.fi., Turkey
Location : Baiji, Iraq

www.socarcons.com | [email protected]
Turkmenbashi Onshore Gas
MIDDLE ANATOLIA REFINERY
Terminal Project Fabrication Yard

Employer : Tupras
Location : Kırıkkale, Turkey
Contractor : Enkut Consortium

Plastic Recycling Plant

Employer : Yesilli Plastik Geri Donusum San. A.S.


Location : Izmit - Kocaeli
Project : Seyas Muhendislik

www.socarcons.com | [email protected]
Turkmenbashi Onshore Gas
Acrylic Production Plant
Terminal Project Fabrication Yard

Employer : Yalova Elyaf ve Iplik San. A.S.


Location : Yalova - Denizcalı

Turkmenbashi OnshoreSolvertas Plant
Gas
Terminal Project Fabrication Yard

Employer : Solvertas Teknik Depolama A.S.


Location : Izmit

www.socarcons.com | [email protected]
Tedjen Amonia and Urea Factory 

Location: Tecen - TURKMENISTAN


Contractor: GAP İnşaat Yatırım ve Dış Ticaret A.Ş.
Client: Ministry of Chemistry

Marble Factory 

Location: Ashgabat - TURKMENISTAN


Contractor: Bouyges Batiment Int.
Client: Turkmennebitgazgurluşık State Company

www.socarcons.com | [email protected]
PROCTOR & GAMBLE Plant, Borispol, Kiev, Ukrania

Proctor & Gamble
Turn Key Plant Construction

www.socarcons.com | [email protected]
Civil References

www.socarcons.com | [email protected]
Grand Hotel RADISSON S.A.S Hotel, Sofia, Bulgaria

www.socarcons.com | [email protected]
Radisson Hotel | Кiev / Ukraine

www.socarcons.com | [email protected]
Athenee Place HILTON | Budapest / Romania

www.socarcons.com | [email protected]
HOLIDAY INN | Katowice / Poland

www.socarcons.com | [email protected]
HILTON | Sofia / Bulgaria

www.socarcons.com | [email protected]
Grand LUBLIN | Lublin / Poland

Grand Hotel MARRIOTT | Budapest / Romania

www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
www.socarcons.com | [email protected]
5. QA‐QC Plan

www.socarcons.com | [email protected]
SOCAR CONSTRUCTION

QUALITY ASSURANCE SYSTEM

SOCAR CONSTRUCTION's Quality Assurance System is constructed around a set of


standard procedures embodied in:
• Quality Assurance in Engineering
• Quality Assurance / Quality Control Field Construction Manual

SOCAR CONSTRUCTION has built its reputation by providing high quality facilities
and services at reasonable cost. These high quality facilities and services result from
practices and procedures developed within the firm during its years of operation. The
SOCAR CONSTRUCTION Quantity Assurance Manuals document these practices
and procedures.

QUALITY PLAN
QUALITY ASSURANCE SYSTEM 1 / 23
QUALITY ASSURANCE IN ENGINEERING
TABLE OF CONTENTS

1. Issuance and Control


2. Authority for Quality Assurance Program Plan Revisions and Deviations
3. Method for Revision and Deviation
4. Quality Assurance Organization
a) Chief Executive and Chief Operating Officers
b) Project Manager
c) Quality Assurance Manager
d) Group Engineer Heads
e) Lead Engineers
f) Inspectors
5. Field Organization
a) Qualifications
b) Third Party Inspection
c) Auditing
d) Field Inspection
6. QA/QC Procurement
7. QC Source Inspection
8. Audits
a) Audit Selection
b) Audit Initiation
c) Audit
d) Record of Audit
e) Summary of Audits
9. Reporting Discrepancies
a) Discrepancy Reporting
b) Corrective Action
c) Closeout
d) Discrepancy Summary
10.QA/QC Schedule

QUALITY PLAN ________________________________________


QUALITY ASSURANCE SYSTEM 2 / 23
1. Issuance and Control

The responsibility for the issuance and accountability control of the program rests with the
Project Quality Assurance Manager. He will determine those organizational units performing
activities affecting quality; and shall provide accountable copies of the project personnel.

2. Authority for Quality Assurance Program Plan Revisions and Deviations

Revisions to, and deviations from, the Quality Assurance Program Plan are authorized when
recommended by the Quality Assurance Manager and approved in writing by the Project
Manager. A revision is defined as a permanent change to the Quality Assurance Program
Plan which is distributed by the Quality Assurance Manager in the form of printed
replacement pages. A Program Deviation is a temporary change to the QA Program Plan to
permit a particular function to be completed on a individual case basis.

3. Method for Revision and Deviation

A revision to, or a deviation from, the Quality Assurance Program Plan is issued by the
Quality Assurance Manager. Request for revision or deviation is initiated by any supervisory
personnel using the change request procedure or non-conformance procedure. The request is
forwarded by the initiator to the Quality Assurance Manager. Upon his preliminary approval
of the request, the following steps are taken:

a) The request will be circulated for review and comment to cognizant management and
technical personnel as determined by the Project Manager.

b) If upon completion of the comment and review phase, the revision or deviation request is
not approved, the request will be returned to the initiator starting the reasons for
disapproval.

c) If upon completion of the comment and review phase, the revision or deviation request is
not approved, the approved revision or deviation will be issued to all holders of the QA
Program Plan. When issued, revisions will be assigned a number and effective date.
When a revision is issued a new list of effective pages will be forwarded with the
revisions.

When issued, deviations will be assigned a number and given both an effective and
expiration date. Periodically, the Quality Assurance Manager will issue a summary list of
effective deviations.

4. Quality Assurance Organization

All persons and organizations performing quality assurance or quality control functions shall
have their duties and responsibilities established in writing. These persons or organizations
shall be given sufficient authority and organizational freedom to perform these activities free
from cost and schedule influences. The responsibilities for each party assigned to the project
are summarized below:

a) Chief Executive and Chief Operating Officers


Have final responsibility for the attainment of quality of the client's project. Reporting to
them is the manager of QA who is responsible for defining and implementing the
company’s Quality Assurance Program for the project. Also reporting to them is the

QUALITY PLAN ________________________________________


QUALITY ASSURANCE SYSTEM 3 / 23
project manager who is responsible for designing and building quality into each
individual project.

b) Project Manager
Responsibility for quality assurance on the project lies with the Project Manager. The
Project Manager, or his designee, reviews and initial drawings, requisitions and other
documents prior to their issue to assure that all procedures are followed. This function,
performed by the project team is independent of the quality assurance functions of the
Quality Assurance Manager.

c) Quality Assurance Manager


The Quality Assurance Manager is responsible for the continuing development,
implementation, management, surveillance and audit of the Project Quality Assurance
Program. This responsibility extends into all project activities including engineering,
design, procurement, manufacturing, construction, testing, assembly, erecting and
commissioning.

The Quality Assurance Manager will assure that the facilities are designed and built in
accordance with the client's specifications and the current, safe and industry accepted
codes and practices. This includes a full testing and inspection program to insure that the
product meets its specifications.
Main duties and responsibilities of the Quality Assurance Manager:

- Directs the development of the Project Quality Assurance Plan and implementing
procedures on the project.
- Directs the implementation of the Program and Procedures, including personnel
indoctrination and training, defines individual Quality Assurance responsibilities and
evaluates modifications to the Plan.
- Meets regularly with Group Heads and Lead Engineers of each discipline to discuss
quality related problems.
- Performs regular monitoring and surveillance of all Quality Assurance activities.
- Performs surveillance and audits of subcontractor's Quality Assurance activities.
- Reviews and approves sub contractor Quality Assurance / Quality Control Programs.
- Maintains liaison on QA matters with client and sub contractors.
- Has "stop work" authority as delegated by the Chief Executive and Project Manager.
- Reviews the Project Quality Assurance Plan on a regular basis with SOCAR
CONSTRUCTION management and the client.
- Reviews selected documents, such as drawings, requisitions, specifications, purchase
orders, procedures, certification programs etc. for conformance to QA standards.
- Provides technical direction and administrative guidance to inspection staff,
contractors, laboratories and projects.

d) Group Engineer Heads


The Group Heads are responsible for defining the quality aspects on the project. They
shall assign the respective duties to lead engineers.
The engineering Group Heads are responsible for checking the work produced in their
department for the project, and insuring it is satisfactory and complete.

e) Lead Engineers
Each discipline will assign a lead on the project to work closely with the Project Quality
Assurance Manager. His responsibilities will include the design and specification of the
product and supervision of the engineers and draftsmen. He will meet regularly with the

QUALITY PLAN ________________________________________


QUALITY ASSURANCE SYSTEM 4 / 23
Quality Assurance Manager to discuss Quality Assurance matters. He will provide
specialized personnel for QC vendor or field inspection at the request of the QA/QC
Manager.

f) Inspectors
Contract and internal inspection personnel shall be responsible for executing the Quality
Control Program in accordance with the Quality Assurance procedures, Company
Inspection Standards, Project Inspection Plan and project documentation. Third party
specialty Inspection and testing agencies will be used where necessary.

5. Field Organization

The main function of the field organization is to ensure a quality installation. The field
organization ensures that the quality engineered into the design drawings and specifications
is built into the facilities being constructed.
Sub contractors are contractually obligated to perform all work in accordance with the
drawings and specifications. On these projects they are also contractually obligated to have
an approved QA/QC program to ensure this quality.
The field organization, headed by the Construction Manager, will initiate appropriate
construction management, administrative and inspection procedures to verify that sub
contractors meet contractual obligations. Inspections are the primary method of measuring
the quality of work. All SOCAR CONSTRUCTION field supervisors' staff will monitor the
work to ensure conformance to specifications and drawings. The qualifications and
responsibilities of this group are as follows:

a) Qualifications
Field inspections of construction work will be conducted in accordance with the QA/QC
program. The group will have knowledge and experience in the following areas:
Earthwork
Concrete
Building Construction
Steel Structures
Piping manufacturing and erection
Equipment and Instruments

b) Third Party Inspection


The field QA/QC Superintendent will act as the primary interface with third party
inspectors. The field group will be responsible for the following:
Notify third parties for Inspections/ Tests
Review Results
Review Adequacy/ Quality of service provided

c) Auditing
The Quality Assurance Department will be responsible for auditing of activities such as
materials receiving and storage, record keeping, filling and other activities as directed by
the Construction Manager or Project Manager.

d) Field Inspection
Inspection of the construction work is the primary functions of the Field QA/QC
Superintendent. Inspections shall be in conformance with sub contract documents and the
SOCAR CONSTRUCTION QA/QC program.

QUALITY PLAN ________________________________________


QUALITY ASSURANCE SYSTEM 5 / 23
6. QA/QC Procurement

All the procurement documents and procedures prepared for or associated with the project
are subject to the QA/QC Program.
Procurement and material control commences with identification and control of requisitions,
inquiries and purchase orders and continues through expediting of materials and equipment,
through manufacture, shipment and receipt at site. This procedure defines the steps taken to
assure the proper execution of these activities and QA's role and responsibilities therein.

7. QC Source Inspection

Inspection is primarily a QC function. Inspections will be in accordance with the SOCAR


CONSTRUCTION inspection procedures.
The QA function is limited to analysis of feedback from inspectors to assure proper
procedures were followed.

8. Audits

a) Audit Selection
The QA manager will prepare a preliminary list of documents subject to the QA audits.
This list will be prepared using the following:
Engineering Requisition Report
Equipment List
Inspection Plan
Site QA/QC Inspection Matrix
Drawing Status Report
Flowchart
Schedule
This list and the percent of documents to be audited will be approved by the Project
Manager and will be reviewed by the client. This will have limited distribution.
Additional audits may be requested by the Project Manager or Quality Assurance
Manager as the need arises.
b) Audit Initiation
When work has progressed to a selected audit point, the Quality Assurance Manager or
his designee will request the Quality Control checker to make the documents used to
perform his checks available for audit. The check copy and checklist should be reviewed
immediately. Back-up documentation, which is not immediately available, should be
made available within four hours.
c) Audit
The Quality Assurance Manager or his designee shall check the documents supplied to
assure that all Quality Control functions were performed in accordance with the project
and SOCAR CONSTRUCTION Quality Control procedures.
The auditor will use the appropriate Quality Assurance checklist.
Normally work will not be on hold for an audit.
When the audit is complete all material will be returned to the senders.
d) Record of Audit
At the completion of each audit, the project Quality Assurance Manager shall issue a
Record of Audit report. This report shall document what was audited, what reference
material was used, what department is responsible for quality control and the findings of
the audit. Copies of the report shall be sent to the department head and the Project
Manager.

QUALITY PLAN ________________________________________


QUALITY ASSURANCE SYSTEM 6 / 23
e) Summary of Audits
The Quality Assurance Manager shall maintain a summary of all audits on the project.
This summary shall note the item audited, date, responsible department and the name and
date of additional reports filed as a result of the audit. Such reports as a discrepancy
report or memo shall be noted.

9. Reporting Discrepancies

Three ways are available for the Quality Assurance Manager to inform the Project Manager
of a problem. They are:
Memo
Discrepancy Method
Non Conformance Method
A memo is used when procedures were not followed, but no benefit can be gained by going
back and completing the overlooked procedure. Such a memo serves to inform those
involved the procedures were not followed in an effort to avoid similar occurrences in the
future.
A Discrepancy Report will be issued when corrective action is needed to complete a quality
control step that has been omitted or done inadequately. This report consists of three parts:
notification of the discrepancy, corrective action and closeout.
When a violation is severe and the quality of work is in serious question, a Nonconformance
Report will be used.

a) Discrepancy Reporting
The Quality Assurance Manager describes the discrepancy and sends the report to the
Project Manager for a recommendation of corrective action. Copies are also sent to the
responsible Group Head, the Responsible Manager, Chief Executive Officer and Chief
Operating Officer. Additional distribution is made at the discretion of the Quality
Assurance Manager.
b) Corrective Action
Upon notification of a discrepancy, the Project Manager develops a plan of corrective
action and returns a copy the report describing the recommended action to the Manger of
QA. The Quality Assurance Manager makes distribution of report again, including the
recommended corrective action to the same people who received the initial notification.

c) Closeout
When corrective action is completed, the Project Manager signs the Discrepancy Report
and returns it to the Quality Assurance Manager. The Quality Assurance Manager must
then assure himself that the corrective action was indeed taken and was effective. He then
reissues the report showing that it has been closed out.

d) Discrepancy Summary
The Quality Assurance Manager issues a summary of all discrepancies on each project
monthly. This summary shows a brief description of each discrepancy and shows what
corrective action is planned and whether or not it has been taken.

10. QA/QC Schedule

The QA/QC schedule is dictated by the Project Schedule. Using the Project Schedule and the
flowcharts, which show the QA/QC activities, project staff will be aware of the QA/QC
schedule. In general, the Quality Control functions are holding on the work. Quality
Assurance functions should be timely, but will not be hold points.

QUALITY PLAN ________________________________________


QUALITY ASSURANCE SYSTEM 7 / 23
QUALITY ASSURANCE / QUALITY CONTROL PROGRAM
(CONSTRUCTION)

TABLE OF CONTENTS

1. General
2. Field Monitoring and Program Administration
a) Earthwork and Sitework
b) Buildings and Structures
c) Structural Steel
d) Concrete
e) Equipment
f) Instruments
3. Quality Audits
4. Follow-up

QUALITY PLAN ________________________________________


QUALITY ASSURANCE SYSTEM 8 / 23
1. General

It is the SOCAR CONSTRUCTION’s stated policy to deliver a quality product, satisfying in


all respects the requirements of SOCAR CONSTRUCTION and the client. This policy
applies to both SOCAR CONSTRUCTION’s work, and work performed by its
subcontractors and is carried out through the application of sound engineering, procurement,
and construction methods. SOCAR CONSTRUCTION’s Quality Assurance / Quality
Control program provides a continuing review function to verify that the work is performed
in accordance with approved procedures and specifications. The key components of the
Construction Quality Assurance Program are:
Field Procedures
Field Monitoring and Program Administration
Quality Audits
Follow–up
Quality Assurance / Quality Control Field Procedures (QA/QC FP)
SOCAR CONSTRUCTION’s QA/QC FP provides a framework for our Quality Assurance /
Quality Control Program. It states Company Policy to be adhered to in our areas of operation
and provides guidance to, our project personnel so that their responsibilities and standards
for quality are clear and well defined. It also provides a mechanism to verify that the quality
conformance is inspected and documented, as required, to the manual standards.
The QA/QC FP outlines the areas of administration and project control to provide a
comprehensive, total-quality project. The QA/QC FP inspection forms included in the
manual serve as a guide for the inspection and documentation requirements for each area of
work. These procedures are further developed into detailed, working documents that are
project specific, based on the particular project specifications, contract requirements, local
jurisdictional authority requirements, and specific vendor recommendations. The procedures
and work methods in place cover the work nominally encountered in the construction of a
CB industrial plant.
SOCAR CONSTRUCTION’s QA/QC FP, assigned to each Construction Manager, offers
specific guidelines for accomplishing QA/QC activities. SOCAR CONSTRUCTION's
QA/QC FP is proprietary, and is intended for the sole use of SOCAR CONSTRUCTION.

2. Field Monitoring and Program Administration

The following summarizes the type of administrative and control functions considered for
each major work item associated with a standard industrial plant. Within each area is a
general discussion indicating the typical detail considered in developing the project specific
QA/QC FP.

a) Earthwork and Sitework


Quality Control methods for earthwork generally follow the recommendations of the
Geotechnical Report as conveyed in the drawings and specifications. Lines and grades are
verified by the survey team and inspection of the materials are carried out by the SOCAR
CONSTRUCTION field staff in conjunction with the Geotechnical Consultant. When
applicable, material testing of densities and other pertinent soil data are coordinated
through local testing firms. Excavation and backfill placement techniques are monitored
by the SOCAR CONSTRUCTION field staff and documented to ensure conformance to
the specifications and safety standards.

b) Buildings and Structures


All buildings are designed, fabricated, and built in accordance with the latest edition of
the applicable specifications, codes and standards. Building materials, equipment,

QUALITY PLAN ________________________________________


QUALITY ASSURANCE SYSTEM 9 / 23
systems and appurtenances are inspected upon receipt by the SOCAR CONSTRUCTION
field staff for conformance to specifications. Erection and installation of the material,
equipment, systems and appurtenances are performed in accordance with approved
drawings and manufacturer's recommendations.
Equipment and system tests are made and/or witnessed by the field staff on all installed
equipment and systems to verify that the building components meet the performance
criteria. Tests which may be included are HVAC, electrical, plumbing, communications
and fire protection and/or any other applicable system. Test results are witnessed, signed
off, and recorded.

c) Structural Steel
Structural steel materials are certified as meeting the required sizes and the grades prior
to fabrication. Steel fabrication plants are inspected and approved by SOCAR
CONSTRUCTION. Approved steel fabrication plants have Quality Control Program for
the fabrication and welding of structural steel in place. This Quality Control Program
addresses the welding procedures, production techniques, consumable control and
fabrication control required to produce steel structures to the project specifications.
Fabricated steel is erected in accordance with the approved erection drawings, and the
field staff verifies that the correct erection sequence, bolt up, plumbing and leveling of
the steel to the final steel structure is performed.

d) Concrete
The supply and placement of reinforced concrete are done in accordance with the
American Concrete Institute (ACI) and the project specifications. Local batch plants are
inspected for their ability to produce quality concrete in conformance with the project
specifications. Concrete suppliers are required to have demonstrated QCP in place for
producing consistent, quality concrete. The SOCAR CONSTRUCTION field staff
inspects placing techniques to ensure transportation, consolidation, and protection of the
concrete meets project requirements.
The SOCAR CONSTRUCTION field staff will ensure reinforcing steel is of proper size
and grade (for mill certificates) and is placed in accordance with the drawings.

e) Equipment
Equipment that is to be supplied and installed on the project is inspected upon receipt to
ensure it meets the requirements set forth in the equipment requisition and purchase
order. Where manufacturers design submissions are required, they are verified as
approved by the Engineer. Vendors are also requested to provide proper performance and
maintenance data. Equipment storage procedures are maintained in accordance with the
vendor requirements and recorded on Material Receiving Reports to verify the condition
and temporary maintenance requirements. Installation of equipment follows the Vendor's
suggested procedure, and the equipment is checked for level, alignment, and bolt down
prior to testing.
Equipment tests are made and/or witnessed on installed equipment by the SOCAR
CONSTRUCTION field staff to verify the component meets the performance criteria.
Test results, along with alignment and bolt-down data, are recorded on the appropriate
Quality Assurance document. Where engineer, Owner, or ASME Code representative
request witnessing, they are notified by the field staff. In the case of subcontracted
package work, the Subcontractor must demonstrate an equivalent Quality
Assurance/Quality Control Program prior to commencing the work.

f) Instruments

QUALITY PLAN ________________________________________


QUALITY ASSURANCE SYSTEM 10 / 23
Instrument equipment, materials and installation are in accordance with the Instrument
Society of America (ISA), or other recommended practices. Vendors of materials and
equipment provide design data or material reports for approval prior to the supplying
components to the project. Material receiving, storage and installation follow the vendor
recommendations and the project specifications. The SOCAR CONSTRUCTION field
staffs inspect material and equipment upon receipt and inspect instruments and control
systems during mounting, installation, calibration and testing. Direct systems test are
made and/or witnessed by the field staff, signed and recorded.

3. Quality Audits

Quality Audits provide an independent evaluation and check of the quality-related activities
and procedures used on SOCAR CONSTRUCTION projects. Audits are carried out on both
SOCAR CONSTRUCTION’s quality performance and on that of its sub contractors.

4. Follow-up

Follow-up is essential to verify that commitments to correct deficiencies are made, and that
the deficiencies are corrected. The Construction Manager provides initial follow up. Regular
quality audits supplement field control. Knowledgeable personnel are available to our site
staff from engineering department for quality problem solving during all stages of
construction. Success and safety are ensured by SOCAR CONSTRUCTION management's
commitment to a high quality project.

QUALITY PLAN ________________________________________


QUALITY ASSURANCE SYSTEM 11 / 23
QUALITY ASSURANCE / QUALITY CONTROL
FIELD CONSTRUCTION MANUAL

TABLE OF CONTENTS

A. GENERAL PLAN
1. Scope
2. Field Procedures Manual
3. Product Quality Audits
4. Follow-up
B. ADMINISTRATION AND IMPLEMENTATION
1. Scope
C. ORGANIZATION AND RESPONSIBILITIES
1. Scope
2. Responsibilities - General
3. Specific Responsibilities
D. CONTROL OF MATERIAL AND EQUIPMENT
1. Scope
2. Responsibility for Material and Equipment
3. Documentation and Coordination
E. INSPECTION
1. Scope
2. Inspection Prerequisites
F. TESTING AND NON-DESTRUCTIVE EXAMINATION
1. Scope
2. Organization and Responsibility
3. Construction Material Testing
4. Non-Destructive Examinations
5. Acceptance Testing
6. Documentation
G. CONTROL OF MEASURING AND TEST EQUIPMENT
1. Scope
2. Procedure
H. DOCUMENTATION
1. Scope
2. General
3. Responsibility
4. Procedure
5. Record Retention

QUALITY PLAN
QUALITY ASSURANCE SYSTEM 12 / 23
Section A

GENERAL PLAN

1. Scope

1.1. SOCAR CONSTRUCTION Construction Company's stated policy is to deliver a


quality product satisfying in all respects the requirements of SOCAR
CONSTRUCTION and the Client. This policy applies to both SOCAR
CONSTRUCTION's own Work and the Work performed by its subcontractors. This
policy is carried out through the application of sound engineering, procurement, and
construction methods. SOCAR CONSTRUCTION's Quality Control Program
provides a continuing review function to verify that the Work is carried out in
accordance with approved Procedures and Specifications The key components of the
Program are:

1.1.1. Field Procedures Manual Quality Control.


1.1.2. Quality Control Inspections.
1.1.3. Project Quality Audits Quality Assurance.
1.1.4. Follow-up on Inspections and Audits.

1.2. SOCAR CONSTRUCTION Construction Company's Quality Control System is


designed to conform to the Project requirements, SOCAR CONSTRUCTION and
Client Standards and Specifications, and Federal, State, and local Codes.

2. Field Procedures Manual

2.1. SOCAR CONSTRUCTION's Field Procedures Manual provides a framework for the
Quality Assurance / Quality Control Program. It states Company Policy to be
adhered to in our areas of operation. It provides guidance to our project personnel so
that their responsibilities and standards for quality are clear and well defined. It
provides a mechanism to verify that quality conformance is inspected and
documented, as required, to the Manual Standards.

2.2. Our Field Procedures Manual outlines the areas of administration and project control
to provide a comprehensive, total-quality project. The sample Field Procedure forms
included in the Manual outline, in general terms, the inspection and documentation
requirements for each area or Work. These procedures are further developed into
detailed, working documents that are Project specific, based on the particular Project
Specifications, Contract requirements, Local, State, and Federal Codes and
requirements, and specific Vendor recommendations.

3. Product Quality Audits

3.1. Quality Audits provide an independent evaluation and check of the quality-related
activities and procedures used on SOCAR CONSTRUCTION projects. Audits are
carried out on both SOCAR CONSTRUCTION's quality performance and on that of
its Subcontractors, Consultants, Vendors, and Suppliers to the extent deemed
necessary by SOCAR CONSTRUCTION.

3.2. Each audit concentrates on the degree to which the project meets both Client and
SOCAR CONSTRUCTION requirements, including any appropriate

QUALITY PLAN
QUALITY ASSURANCE SYSTEM 13 / 23
recommendations for the effective function of the operations, for example, to verify
that:

3.2.1. The Scope of Work is clearly and precisely defined.


3.2.2. The Project Team responsibilities are well defined and inclusive.
3.2.3. The Project Team is adequately staffed.
3.2.4. The Project Procedures are in place, and are being followed.
3.2.5. The Project Specifications are adequate, and Work is in compliance with
them.
3.2.6. Project Standards are available, and are being adhered to.
3.2.7. Project control systems are in place, and being effectively used.

4. Follow-up

Follow-up is essential to verify that commitments to correct deficiencies are made, and that
the deficiencies are corrected. The Construction Manager provides initial follow-up.
Regular quality audits supplement field control. Knowledgeable personnel are available to
our site staff from our Engineering Department for quality problem solving during all
stages of construction. Success and safety are ensured by SOCAR CONSTRUCTION
management's commitment to a high-quality project.

QUALITY PLAN
QUALITY ASSURANCE SYSTEM 14 / 23
Section B

ADMINISTRATION AND IMPLEMENTATION

1. Scope

1.1. The administration of the Quality Assurance / Quality Control Program shall be the
responsibility of the Resident Construction Manager.

1.2. The implementation of the Quality Assurance / Quality Control Program shall be by
the Resident Construction Manager or his designee.

1.3. The Resident Construction Manager will be located on the job site, and will have the
responsibility of establishing a satisfactory working relationship with the Project
Staff and Subcontractor representatives; recognizing that the initial responsibility for
performing quality Work rests with the Subcontractors and/or Superintendents and
Foremen. Functionally, the Quality Assurance / Quality Control Program will be
accomplished in the following manner:

1.3.1. Documentation: Provide records of all QA/QC Inspections, Audits, and other
functions performed.
1.3.2. Testing: Provide and interpret technical validations to comply with Contract
testing requirements.
1.3.3. Inspection: Provide onsite inspections to assure compliance with all
applicable Codes, Procedures, Specifications, and Standard practices.
1.3.4. Submittals: Submittals meeting the requirements of the Contract will be
submitted to the Owner, as required, in a timely manner.
1.3.5. Assistance: Provide, any necessary service to assist Construction efforts
(Specification and Code interpretation, technical assistance, etc.)

1.4. The Quality Assurance / Quality Control Program includes basic procedures to be
used by project personnel to perform the necessary inspections required to assure
compliance with all applicable documents. These procedures provide minimum
standard directions, but do not limit or exclude development of additional or revised
inspection practices. They are intended to be effective working tools that will be
modified to meet the changing requirements of the Project.

QUALITY PLAN
QUALITY ASSURANCE SYSTEM 15 / 23
Section C

ORGANIZATION AND RESPONSIBILITIES

1. Scope

1.1. This section outlines the organizational structure and responsibilities of SOCAR
CONSTRUCTION's Quality Assurance / Quality Control personnel.

2. Responsibilities - General

2.1. The accountability for all Quality Control activities is assigned to the Resident
Construction Manager who is located at the job site. He is fully responsible for
supervising the Quality Control functions and to ensure that proper control,
inspection, and documentation are performed.

2.2. The accountability for all Quality Assurance activities is assigned to the Head Office
Project Manager, or his designee in the field, if job size requires an onsite Quality
Assurance Manager. He is fully responsible for supervising the Quality Assurance
functions and to ensure that proper control, inspections, and documentation are
performed.

2.3. The prime responsibility for performing quality workmanship in all disciplinary
efforts rests with the Superintendents, Assistant Superintendents, and Foremen,
actually supervising the performance of the Work. The Construction Manager and
Project Manager are jointly charged with the responsibility for compliance with all
Plans, Specifications, applicable Codes, Standards, and Construction practices.

2.4. All Quality Assurance / Quality Control Inspections and Audits will be performed
with safety in mind, and shall report and, if necessary, stop all unsafe practices.

2.5. The Construction Manager is responsible for supervision of Quality Control Audits
and Inspections to see that the quality of Work is properly inspected and
documented. He will determine the quality requirements of the Project, and assume
an active role in the inspection of the Work.

2.6. The Construction Manager will advise, assist and fully cooperate with the Project
Team concerning the quality of the Work. In addition, he will coordinate with the
Project Manager and Engineering staff as to project workmanship to ensure that the
Quality Control Program is providing inspections consistent with the demands of the
Project. The Construction Manager will review conditions found to be
nonconforming, and investigate any recurrent problems. He shall initiate corrective
actions as required.

2.7. The Construction Manager is responsible or monitoring and reporting all


constructing activities and tests as they relate to adherence to Plans and
Specifications. He is fully responsible for establishing satisfactory working
relationships with the assigned Owner's Representatives. A summary of Quality
Control responsibilities is as follows:

2.7.1. Construction inspection, report writing, and submittal of all Quality Control
reports, notification of testing and test reports to the Project Manager, as
required;

QUALITY PLAN
QUALITY ASSURANCE SYSTEM 16 / 23
2.7.2. Surveillance of the Work performed by inspection personnel and testing
laboratories, ensuring that such Work is done in accordance with this criteria
and the Contract Documents;
2.7.3. Works jointly with the Project Manager to ensure compliance with all
technical provision, Drawings, and Codes. Informs the Project Manager in a
timely manner of any poor workmanship, deficiencies, discrepancies or
potential problems;
2.7.4. Maintains as-built Drawings, and keeps them up-to-date and marked up.

2.8. The Construction Manager will interface with craft supervision employees to assure
conformance with the Project Specifications. Specific attention shall be given to
startup of each construction activity to assure the Work is being performed in the
proper manner. Inspection, testing, and documentation of Work will be done in
accordance with the appropriate inspection plan developed for the job.

2.9. The Construction Manager will be responsible for establishing and maintaining a
filing system for the Quality Control documents. This activity will include the
collection, filing, storage, and maintenance of Quality Control records. Files will
include a copy of the latest revision of the Specifications. Files will be maintained on
Welding Procedure Qualifications, Non-destructive Examination, test results, and
copies and submittals necessary to assure the quality of the Project.

3. Specific Responsibilities

3.1. The Construction Manager is responsible for:

3.1.1. Providing not less than 24-hour notice to the Owner of onsite inspections or
tests such as:
3.1.1.1. Hydrostatic test, testing of electrical installation.
3.1.1.2. Ready for concrete pour.
3.1.1.3. Instrument loop check.
3.1.2. Dependant on the construction activities, the 24-hour notice may be waived
at the discretion of the Construction Manager at any time he deems it to be
beneficial to the schedule, or pending weather conditions.
3.1.3. The Project Manager shall furnish the Construction Manager with a copy of
all Purchase Orders and Subcontractors.
3.2. The Construction Manager is responsible for:
3.2.1. Providing not less than one (1) week notice to the Owner of offsite
inspections or tests such as:
3.2.1.1. Witness load testing of masonry units.
3.2.1.2. Inspect and witness periodic batching of concrete and asphalt.
3.2.1.3. Witness re-setting of safety valves, if required.
3.2.1.4. Inspect laboratory and witness test (chemical lubricant, etc.).
3.2.1.5. Analyze material (sharpy test, etc., if required).
3.2.2. Notification of Project, Manager's approval of all proposed changes to the
Quality Assurance / Quality Control Program.
3.2.3. Notification to Contractor of any approved chances to the Quality Assurance
/ Quality Control Program.
3.2.4. Assuring that all Inspectors and/or Contractor and/or Material Suppliers
prepare and submit inspection and test plans for prior approval.
3.2.5. To inventory and inspect all Owner and Contractor equipment and material,
including installation guides and/or Vendor data.
3.2.6. To certify that all materials installed (both Owner and Contractor-furnished)
meet or exceed the Specifications, Codes, and Standards.

QUALITY PLAN
QUALITY ASSURANCE SYSTEM 17 / 23
Section D

CONTROL OF MATERIAL AND EQUIPMENT

1. Scope

1.1. This section describes the systems for controlling of all Project materials and
equipment.

2. Responsibility for Material and Equipment

2.1. All material and equipment received shall be documented on Material Received
Reports and Daily Inspection Reports listing material received and condition of
material at time of delivery. Inspection shall be made by the Construction Manager,
as applicable, confirming adherence to Specification and purchasing definition.

2.2. The Construction Manager will assure that all material and equipment received shall
be handled in a manner as to ensure protection from physical damage.

2.3. The Construction Manager shall inspect, inventory, and otherwise account for all
Owner-furnished material and equipment prior to transfer of material to a
Construction Contractor in accordance with the approved Project schedule.

3. Documentation and Coordination

3.1. The Construction Manager shall accumulate and evaluate all Vendor data,
installation instructions, and operating procedure manuals.

3.2. The Construction Manager shall initiate notification to the Project Manager and the
Contractor of any and all deficiencies, omissions, location conditions, and/or
problems anticipated with Owner and Contractor furnished materials and equipment.

3.3. The Construction Manager shall coordinate all manufacturer representative


inspections, installation, startups, and checkout; and provide proper notification of
such to the Project Manager.

QUALITY PLAN
QUALITY ASSURANCE SYSTEM 18 / 23
Section E
INSPECTION
1. Scope
1.1. This Section establishes the requirements for monitoring and inspection of
construction activities.
2. Inspection Prerequisites
2.1. The inspection necessary for the successful field fabrication, construction, and
installation of the Work shall be determined by the Specifications and the
Construction Manager.
2.2. Prior to the start of a construction activity, the Construction Manager shall review
the field Quality Control Inspection Report to assure that instructions governing the
activity have been included.
2.3. Prior to implementing the specific requirements of the field Quality Control
inspection Report, the following conditions small be verified by the Construction
Manager:
2.3.1. By a review of the records, verify that the item to be used is identified and
has been previously accepted through receiving inspection.
2.3.2. Latest approved Design Drawings are available.
2.3.3. Where required, personnel and procedures have been qualified.
2.3.4. Equipment for special processes, if required, is available and conforms to
specified requirements.
2.4. Field Quality Control Inspection Report
2.4.1. Inspection reports shall be executed by the Construction Manager to verify
that necessary inspection has been completed.
2.4.2. The results of inspections shall be documented on an inspection report, or a
specially designed form, as stipulated herein.
2.4.3. All inspection reports shall be numbered consecutively by discipline, and
shall be used to document all phases of Work under the Contract.
2.4.4. Inspection reports must be filled out onsite each day, and for every
construction activity.
2.5. Processing
2.5.1. If the inspection indicates a satisfactory condition, the checklist or specially
designed form shall be processed in accordance with Section 2.6 of this
Manual.
2.5.2. If the inspection indicates an unsatisfactory condition, the reason shall be
stated in the "Remarks" block and be forwarded to the Project Manager for
action.
2.5.3. Unsatisfactory conditions, which cannot be resolved by the Construction
Manager, shall be reported to the Project Manager for resolution.
2.6. Closing and Distribution of Checklists
2.6.1. The Construction Manager shall review the checklist or special form for
completeness, and close it by signing and dating when it is returned without
unsatisfactory conditions, or after all the unsatisfactory conditions have been
re-inspected and indicated satisfactory.
2.6.2. Final distribution shall be the original checklist with attachments filed in the
Quality Control Record File.

QUALITY PLAN
QUALITY ASSURANCE SYSTEM 19 / 23
Section F

TESTING AND NON-DESTRUCTIVE EXAMINATION

1. Scope

1.1. This section establishes the requirements for control of testing and non-destructive
examinations.

2. Organization and Responsibility

2.1. Pre-qualified subcontractors whose personnel have been approved by the


Construction Manager shall perform all necessary non-destructive examinations and
testing.

2.2. The Construction Manager shall schedule and observe all testing and non-destructive
examination.

2.3. The Engineering Manager shall be notified by the Construction Manager of


schedules and test procedures prior to all testing to be done onsite, giving the
responsible Inspection Department time to prepare for monitoring of tests.

2.4. All Quality Assurance / Quality Control problems shall be handled by the
Construction Manager onsite.

2.5. When and if a conflict, exists between any documents and the Specifications, the
Specifications shall govern.

3. Construction Material Testing

3.1. Construction material testing shall be performed in accordance with the requirements
of the Design Documents, either by the Construction Manager or an approved
subcontracted testing laboratory.

4. Non-Destructive Examinations

4.1. Non-destructive examination shall be performed in accordance with the requirements


of the Design Documents, either by the Construction Manager or by an approved
subcontracted testing laboratory.

5. Acceptance Testing

5.1. Acceptance testing of structures, systems, and components (when required) shall be
performed to meet the requirements of the Design Documents. Any/all of the
required acceptance testing may be subcontracted.

6. Documentation

6.1. Results of construction material testing, non-destructive examination, and


acceptance testing shall be documented by field Quality Control Checklists or by
specially designed form, and shall be evaluated by the Construction Manager or his
designee.

QUALITY PLAN
QUALITY ASSURANCE SYSTEM 20 / 23
Section G

CONTROL OF MEASURING AND TEST EQUIPMENT

1. Scope

1.1. This section establishes the requirements for the control, calibration, and periodic
adjustment of measuring and test equipment used to verify conformance to
established requirements.

2. Procedure

2.1. Prior to initial use, measuring and test equipment shall be assigned a unique
identification number; calibrated, adjusted, and maintained in accordance with the
manufacturer's instructions.

2.2. If measuring and test equipment appears to be damaged or it is carelessly handled,


the equipment shall be re-calibrated prior to use.

2.3. The Construction Manager shall assure calibration of measuring and test equipment
by witnessing the calibration or review of the Calibration Test Report.

2.4. All reports shall be kept and filed onsite.

2.5. The Construction Manager shall establish areas for storage of measuring and test
equipment for field use.

QUALITY PLAN
QUALITY ASSURANCE SYSTEM 21 / 23
Section H

DOCUMENTATION

1. Scope

1.1. This section establishes the requirements regarding collection, storage, retention, and
transmittal of Quality Assurance / Quality Control documentation.

2. General

2.1. This section applies to all Work on the job site, and includes Quality Assurance /
Quality Control records and related documents initiated by Engineers, Contractors,
Subcontractors, and Suppliers.

3. Responsibility

3.1. The Construction Manager is responsible for the Quality Assurance / Quality Control
records on the Project. He shall assure that the records are prepared, collected,
retained, and transmitted in accordance with this section.

4. Procedure

4.1. Record Requirements

4.1.1. Quality Assurance / Quality Control procedures are to be followed as Work


is performed to assure documentary evidence of the quality of items and of
activities affecting quality. Records shall be consistent with applicable
Codes, Standards, Specifications, and Contract requirements.
4.1.2. Quality records shall include the results of inspections, tests, audits, reviews,
monitoring of construction activities, etc. Records shall also include related
data such as personnel, procedures, equipment qualifications, calibration
records, etc., and other documentation required by the Contract
Specifications.
4.1.3. Inspection and test records shall (as a minimum) note the date of
inspection/test, the inspector, type of inspection/test, results, and the action
taken regarding any deficiencies noted.
4.1.4. A Quality Record Checklist shall be prepared by the Construction Manager
to note those records required for the project activity. The Checklist shall be
reviewed with Owner's authorized representatives to assure that all records
required are listed. As records are received, they shall be reviewed by the
Construction Manager before filing to assure they are accurate and complete.
4.1.5. Quality records may include, but are not limited to, the following:
4.1.5.1. Quality Record Checklists
4.1.5.2. Receiving Records: Material Receiving Reports, shipping
records, material test reports, certificates of compliance, non-
destructive test reports, and test reports.
4.1.5.3. Equipment Manufacturer's Records: Drawings; diagrams;
equipment data sheets for pumps, motors, valves, etc.;
installation, operating, and maintenance instructions; inspection
reports.

QUALITY PLAN
QUALITY ASSURANCE SYSTEM 22 / 23
4.1.5.4. Non-destructive Examination Records: Procedure qualification,
personnel qualifications, NDE reports, and personnel interpreting
the test; laboratory and test reports.
4.1.5.5. Welding Records: Welding personnel and procedure
qualifications, test reports, and inspection reports.
4.1.5.6. Process and Final Inspection Reports: Including a Daily
Inspection Report of inspections conducted, onsite Suppliers
Shops, etc.; including general observances.
4.1.5.7. Contractor / Subcontractor Records: As required by the Contract
Specifications.
4.1.5.8. Test Records: Hydrostatic, Compaction, Electrical, Installation,
etc.
4.1.5.9. Calibration Records: Measuring and test equipment, including
NDE equipment, if applicable.
4.1.5.10. As-built Records: Drawings, Sketches, etc.
4.1.5.11. Warranty / Guarantee Records: Certificates and Letters.
4.1.6. The Records listed in the above paragraphs are not an all-inclusive list. The
Construction Manager shall review the Contract Specifications to determine
if additional records are required.
4.1.7. All Records shall be the original copy whenever possible. If originals are not
available, a legible copy, which can be reproduced, is accepted.

5. Record Retention

5.1. During construction activities, all quality records (including radiographic film) shall
be maintained in a safe and secure facility. Records shall be filed in such a manner
that they are identifiable and retrievable in a timely manner.

5.2. On completion of a specific construction activity, the Construction Manager shall


prepare a documentation package utilizing the Quality Record Checklist for
transmittal.

5.3. Transmittal of Documentation

5.3.1. Quality Assurance / Quality Control packages shall be transmitted to the


Owner's authorized representative in a timely manner.

5.4. Submittals
5.4.1. All job-related requirements shall be submitted to the Project Manager for
approval. All submittals shall be recorded on a Submittal Log Sheet.

QUALITY PLAN
QUALITY ASSURANCE SYSTEM 23 / 23
6. HSE Plan

www.socarcons.com | [email protected]
SOCAR CONSTRUCTION

HEALTH, SAFETY & ENVIRONMENT


PLAN

The part of the above-mentioned document which is in the attachment reflects SOCAR
CONSTRUCTION’s general policies and approach to HSE issues. The complete document
contains also the procedures listed therein.

Please note that in case of award of the contract, we shall prepare and submit to the
COMPANY for approval on HSE Plan which is generally in the same format but accommodating
also the specifics of the project and contractual and local HSE requirements.

1/15
HSE PLAN
Section 1

INTRODUCTION

1.1. Executive Summary

The main objective of this plan is to give a clear understanding for the basis of HSE management
and planning, and guidelines for the HSE aspects of the construction projects to SOCAR
CONSTRUCTION project management team. It is prepared on the basis of SOCAR
CONSTRUCTION HSE policy, objectives, targets and principles taking into account contract
objectives and targets, and specifies the requirements, relevant hazards involved in the project,
how to manage these hazards, organizational responsibilities, HSE equipment and procedures.

The plan will be reviewed together with the COMPANY and submitted for approval after
revising according to recommended revisions. Then, it will form the basis of monthly reviews of
performance.

To ensure full understanding of the plan by all SOCAR CONSTRUCTION senior, junior staff
and subcontractors, the revisions in the approved plan shall be incorporated into the Turkish
version discussed in detail with senior, junior staff and subcontractors and signed by staff and
subcontractors at the formal receipt for confirmation of understanding. All staff and
subcontractors are accountable for the requirements in this plan.

The execution of the plan requires continuous commitment of individuals at all levels within the
organization and project team shall aim to spend all necessary effort to meet the contract
objective and targets.

In order to give a good start to project, the action plan, which is a list of activities prior to start of
work with responsible persons and action date is provided.

Additional to the above action plan, an overall project HSE activities schedule is provided.

In line with the system described in this Site Specific HSE Plan, the action plan and HSE
activities schedule will be executed and followed up by HSE staff and project management team
without any comprimise.

2/15
Section 2

HSE MANAGEMENT

2.1. HSE Policy

SOCAR CONSTRUCTION policy statement will be visible on notice boards in work sites
reminding the workforce the objective of aiming to spend all necessary effort to:

• protect employees and other persons, which may be affected by the activities, from work
related injuries and illnesses
• avoid damage to property
• ensure to eliminate environmental pollution while conducting the activities.

2.2. Contract Objectives

The main HSE objective for the contract is to ensure all necessary efforts are spent for accident
prevention. In order to achieve this overall objective, CONTRACTOR will make the required
resource allocations to:

• Establish a basic level of HSE awareness in all labor including subcontractors


• Consolidate and further improve the HSE awareness and competance of SOCAR
CONSTRUCTION engineers and subcontractor supervisors
• Provide formal training on site about basic safety aspects and HSE concerns of the project
• Increase awareness of the staff for the hazards involved in the execution of the project
• Establish unsafe act/condition auditing as a normal everyday activity for SOCAR
CONSTRUCTION engineers & supervisors
• Establish HSE planning prior to start of jobs
• Ensure compliance with all applicable provisions of laws and regulations specified for the
contract.

2.3. Contract Targets

The HSE targets for the contract are:

• Dissemination of this plan prior to mobilization to site


• Complete 40 man-days of HSE training at supervisory level prior to start of the work
• Complete 100 man-days of HSE training of labor in the first days of construction start
• Monthly HSE meetings
• HSE audits every three months starting at the end of mobilization
• Quarterly emergency drills to measure contingency response capabilities
• Work completion with no fatality and no material damage to client & third parties and with
accident ratio of 0.5 (ie. 0.5 accidents for every 100,000 mhrs).

2.4. Contract HSE Plan

Site specific HSE plan will be submitted after award of the contract. The plan is concentrated on
activities regarding construction and prepared on the basis of:

1. Hazard assessment for construction activities

3/15
2. Identification of resource requirements for the contract (personnel, equipment, budget)
3. Developing preventive and protective measures for HSE critical activities
4. Preparation of contingency plans and emergency procedures
5. Preparation of specific construction procedures required.

The activities with action parties and target completion dates, which will be executed prior to start
of work are planned.

HSE activity schedule, addresses when the activities will be performed during the execution
phase including the mobilization audit, training, preparation of site specific HSE procedures,
training, tool box meetings supervision, unsafe act / condition auditing, HSE site audits drills.

2.5. Performance Monitoring

• Overall

The overall performance will be based on statistical analysis which gives the quantity and
frequency of the following against exposure hours:

Accidents / incidents
Fatalities
Lost time injuries
Medical treatment cases
First aid cases
Material damages
Near misses
Unsafe acts & conditions

Incidents and accidents would be reported immediately to line supervisors, project manager and
clients site responsible person. The line supervisor would fill in a report form with the details of
the involved people, the potential causes of incident and recommendations to prevent
reoccurrence (report form is given in relevant procedure).

The incident / accident will be discussed in detail at management level and the outcomes about
the causes and recommendation would be issued in written form on HSE boards and discussed in
HSE and toolbox meetings.

The HSE performance during the project based on statistics would also be reported every month
by HSE engineer and improvement areas would be discussed in meetings.

• Activity based

Additional to the actual overall performance, the activities foreseen in the HSE activity plan and
schedule will be checked monthly to record the progress. These sort of activities are:

Training
Preparatory works (for emergency procedures, fire plans etc.)
Meetings
Site audits
Unsafe act / condition auditing
Equipment checks and inspections
System & procedure application checks

4/15
Drills and exercises
Any other specific HSE activity

These are shown on an activity bar chart in HSE activity schedule, where planned and actual are
visible together.

2.6. Corrections & Revision

This Site Specific HSE Plan will be a live document. Therefore, the individuals has to show
continuous effort to improve the plan according to actual progress and findings in contract
execution. The corrections may result from:

• analyses of statistical performance indicators


• new requirements which are not foreseen initially
• accident / incident investigation (accident tree analysis)
• changes in scope, specifications or conditions

The management system, responsibilities, activity schedule, procedures and other relevant topics
may be subject to correction and revision.

The revisions are first drafted by the originator, checked by site HSE engineer, reviewed by
project manager and then approved by the COMPANY and issued for execution.

5/15
Section 3

HAZARD MANAGEMENT

3.1. Project Description

The project is described as the civil,mechanical , electrical and instrumentation works of plants in
Khabarovsk, RF. The works related with the project are:

• Piping Prefabrication and Erection,


• Equipment Erection Works

The scope of work and related construction activities in these projects involves a lot of
subactivities which shows a great variance in nature. The most common ones are:

Piping Prefabrications , spool manufacturing,


Equipment Erections

3.2. Hazard Identification

The types of hazards encountered in this project related directly with construction activities are:

• falling into excavated pits and trenches


• crushing / asphyxiation due to collapse of excavations
• being hit by falling objects
• being crushed by plant equipment / vehicles
• being crushed by rolling pipes
• impact from slewing excavators and cranes
• injury from improper manual lifting or failure to use appropriate lifting equipment
• injury from cutting tools
• being electrocuted by live electrical equipment
• fire (from various sources)

The type of hazards which is more general are:

• having an heart attach as a result of work overload


• loose of consciousness as a result of low blood pressure
• getting a social disease
• being effected from infection disease due to living together with others
• getting sick due to lack of hygiene
• leak or disposal of environmentally harmful liquids over accepted standards
• emission of environmentally harmful exhaust gases over accepted standards

3.3. Assessment of Probability and Effects of Potential Hazards

The hazard assessment is performed in four steps:

• First step: Description of the activity


• Second step: Assessment of potential hazards
• Third step: Assessment of probability of happening

6/15
• Fourth step: Assessment of impact of consequences of happening

The activities in the project and relevant potential hazards are described in section 3.1 and 3.2
respectively. The preventive measures is determined on the basis of the possibility and effect of
harm to human beings, material damage and environmental pollution and taken into consideration
the following:

• Nature of work

1. Labor requirement (health, physiology, psychology, skills, training, experience etc.)


2. Materials involved (flammable, toxic, pressurized etc.)
3. Equipment operation (moving, rotating, energy supply etc.)
4. Working environment (crowd, accessible, escape routes etc.)
5. Working location (underground, elevated, confined space etc.)
6. Interfacing activities (any other operation nearby the work area or related with system)
7. Indirect products (heat, chips, dust, gas, liquid etc. and their effects on human and
environment)

• Lack of information / awareness


• Lack of control on others
• Changes in conditions by time
• Presence of error enforcing conditions

The line supervisors will make an hazard assessment for the specific activity at the work planning
stage. He will use the standard HSE procedures and prepare a new procedure specific to the job.
He will clearly state the safety measures and take project managers / site chief approval and then
would discuss these in toolbox meetings with the work force or subcontractors before start of the
job.

3.4. Determining Preventive & Protective Measures for Potential Hazards

The preventive & protective measures can be classified as follows:

• planning of the work (including changes in conditions by time)


• staff training
• assigning responsibilities to individuals
• motivation of staff for active participation
• labeling, warning signs and barriers for potential hazards
• use of protective equipment
• use of proper and well maintained equipment
• use of work permit system for HSE critical activities
• certificates of HSE control for specific activities before start of work
• execution of the work according to HSE procedures based on codes and standards
• carrying out inspections & audits

Based on the above listing, the procedures & instructions required for this project are produced
for each specific work. These procedures & instructions are listed in section 7 and the paper
copies are given as attachment to this plan. Any other specific procedure required for a work
should be initiated and produced by a member of project management team with the support from
head office HSE section. This activity will be shown in HSE activity plan & schedule.

7/15
3.5. Contingency Planning & Emergency Response Procedures

In execution of a work, there are lots of parameters which are independent of each other.
Therefore, the first level of the preventive and protective measures taken sometimes fails and the
workforce is subject to hazards directly. Depending on the impact of consequence of an accident,
it is necessary to take second level of preventive or protective measure. This is defined as
contingency planning.

Emergency procedures are parts of contingency planning after accidents happen. There is always
potential for an accident whatever you do, due to lack of integrity in HSE management system or
other reasons which is out of control. In order to minimize to impact of the accident and to
prevent time losses for remedial action, the following cases are classified as emergency in this
project and emergency procedures are prepared:

• sickness like heart attacks, loss of conscious


• injury with severe bleeding, broken bone, risk of loss of a body organ, loss of conscious etc.
• fire
• vehicle accident
• earthquakes, water drowning, land slide or soil collapse

The procedures defines who is doing what, in which sequence and includes the response
capabilities available, communication ways, escape / evacuation roots and plans, rescue and
intervention responsibilities and methods. The external connections and the communication
procedures for emergency situations are also provided.

3.6. Drills & Exercises

The procedures and systems developed will be tested with drills and exercises for confirmation of
understanding by the staff to check the performance and to detect any inconvenience and review
for improvement. These drills will alert all the persons involved likely to be affected by
emergency conditions and to alert the people and equipment comprising the response capability.
The frequency of these drills are once in two months.

The type of drills are:

• fire / explosion evacuation


• fire intervention
• road traffic accident
• Beside the drills, the understanding and capability of staff, performance of equipment will be
checked with exercises as a part of system testing. The exercises are considered for use of
alarm equipment, use of communication means, use of evacuation equipment, use of
intervention equipment.

8/15
Section 4

HSE REFERENCES

4.1. Laws & Regulations

The main objective in making HSE plans is the full implementation of the policy with the
minimum standard of legislative requirements and client specifications.

The HSE management system, organization and procedures are based on Turkish laws &
regulations as a minimum requirement and international standards where applicable.

Turkish regulations related with HSE, which all staff is almost familiar with, is based on the
Clause 7/8602 approved by Ministerial Council issued on official gazette dated September 12,
1974.

This document is available in all work sites and available for reference to everyone. Additionally,
read and signed by each worker for confirmation of understanding.

4.3. Reference HSE Standards

The HSE standards will be kept in head office and provided for site team when required.

4.4. HSE Administrative Documentation and Registration

The project HSE administrative documentation and registration on site will be:

• contract HSE specifications


• Site Specific HSE Plan
• HSE technical procedures
• HSE emergency procedures
• training file
• incident and accident report file
• accident investigation report file
• clinic visit register
• first aid treatment register
• property loss and damage register
• material waste and disposal record file
• HSE meetings file
• inspection & audit file
• HSE equipment inspection log book
• heavy equipment license file
• safety officer log book

9/15
Section 5

HSE ORGANIZATION

5.1. SOCAR CONSTRUCTION Headoffice and Site Organization

HSE is a line responsibility and HSE performance can be maintained at required levels by active
participation of all staff to the Site Specific HSE Plan. In order to carry out activities in a
disciplined manner, the following key personnel in this project will be responsible for HSE
aspects:

Job Title Location Responsibility


HSE Coordinator Head Office Site Specific HSE plan preparation, site
audits
Project Manager Site Overall responsibility of HSE performance
Site HSE Manager Site Overall implementation of HSE plan
HSE Engineers Site HSE plan in their work site, follow up of
action items in audits, drills, records, unsafe
act/condition auditing
Doctor Mobile Training, site audit
Nurses Site First-aid
HSE crews Site Safety equipment maintenance, follow-up of
audit action items, daily inspections
Super Intendents Site HSE plan support, hazard assessment,
preventive measures for hazard management
Discipline engineers Site Tool box meetings, unsafe act/condition
Auditing

5.2. Responsibilities

The specific responsibilities of staff at site are as follows:

Project Manager:

a) Ensures that the COMPANY’s safety policy is understood and appreciate the responsibility
allocated to each grade.
b) Ensures that contract is adequate to cover sound methods of working and reasonable wellfare
facilities.
c) Determines at the planning stage:
i) the most appropriate order and method of working.
ii) allocation of responsibilities with the COMPANY and subcontractors.
d) Ensures that safe working practices and methods are adopted and are carried out as planned.
e) Maintains working methods in accordance with the safety regulations.

Site Safety Manager and Engineers:

a) Supervise the implementation of Site Specific HSE Plan on:


i) Prevention of injury to personnel and damage to material and equipment,
ii) Further improvements in existing working methods,
iii) Application of SOCAR CONSTRUCTION Safety Procedures and those of the
Project,

10/15
iv) Insuring availability of valid and appropriate test certificates for hired materials and
equipment,
v) Potential hazards on new sections before work starts,
vi) The site/work area safety organization and fire precautions required.
b) Carry out survey and inspections on regular basis in association with supervision to ensure
that safe working practices are followed.
c) Supervise the recording and analysis of information on injuries, damage and production loss,
assess accident trends and review overall safety performances.
d) Assist in the training of all levels of employees to promote awareness of injury prevention
and damage control.
e) Arrange for safety lectures and film presentation as much as possible for all grades.
f) Arrange for safety posters, signs, bulletin boards and change material at regular intervals.

Superintendents:

a) Ensure that all plant and equipment on site or place of work is safe, guarded and equipped
with appropriate safety devices.
b) Ensure that all personnel employed are suitable for the jobs for which they have been
recruited.
c) Check that periodic test, inspections and maintenance work are being carried out.
d) Attend promptly to all equipment defects notified, and call to the attention of the site
management for the need of dangerous equipment to be taken out of service, until properly
repaired.
e) Appraise the effectiveness of all Engineers and Supervision under his control, regarding
safety practices.

Engineers:

a) Organize sites / places of work, so that work is carried out to the required standard with
minimum risk to men, equipment and materials.
b) Know the broad requirements of relevant safety regulations and Project specific provisions.
c) Give precise instructions for his personnel on their responsibilities for correct working
methods.
d) Plan and maintain a tidy site/work area, and arrange for the removal of debris daily.
e) Implement arrangements with Sub-Contractors and others to avoid any confusion about areas
of responsibility.
f) Check that all machinery and equipment are maintained in good condition.
g) Make sure adequate equipment is issued to each person accordingly (including personnel
protective equipment).
h) Ensure that all persons under his control know what to do in the event of fire or other
emergency.
i) Liaison with his superiors on matters of safety and where necessary consult the Resident
Safety Engineer / cooperate with the Safety Engineering and Fire Department and act on their
recommendation.

Foremen:

a) Incorporate safety instruction in routine orders and see that they are obeyed.
b) Prevent men from taking any risks.
c) Ensure that all new employees understand the Project Safety Regulations and Standards of
Work required.
d) Report defects on site and equipment promptly to their superior.

11/15
All Employees:

a) Should use the correct materials, tools, equipment and Safety Equipment for the work they
are carrying out.
b) Report all defects on material and equipment immediately to the supervisor.
c) Develop a personal concern for themselves and others around them.
d) Avoid taking any risk.
e) Refrain from horseplay and the abuse of safety devices, equipment and welfare facilities.
5.3. Training of Workforce

It is deemed to be necessary to conduct a detailed HSE training program in this project. In this
respect, the following HSE training courses are considered for supervisory staff and also
dedicated HSE team members with the request to pass the information to their subordinates and
labor in tool-box meetings, audits and in every opportunity to do this:

Basic Safety 1 day


Defensive Driving 1 day
First Aid 2 day
Fire Fighting 0.5 day
Unsafe Act / Condition Auditing 0.5 day
Construction Safety 1 day

According to the level of responsibility and working area the staff will attend these courses till the
end of first month after mobilization and each new employee afterwards will attend a 2 day basic
orientation program which will be given by safety engineer & crew on site. Additionally, a basic
safety training will be provided to labor for half day after completion of mobilization and in the
third quarter of the project.

The staff will be motivated with promotions for good HSE performance and goodwill to increase
awareness. It will be the objective to introduce HSE as a part of their work and also for their own
benefit.

The site safety manager will arrange the training courses with the support of HSE coordinator.

It is the responsibility of all project management team to transfer the basic information received
during the training courses to work force in every opportunity. This would be done by means of
induction to employees, toolbox meetings every week before start of a new work, HSE meetings
and site HSE audits.

5.4. Information Transfer & Communication

The information will be transferred for the following activities and cases:

• HSE instructions, from project management team to workforce


• HSE feedback, from workforce to project management team
• HSE activities in general, from project management team to workforce
• Inspections & Audits, from project management team to workforce
• Drills & Exercises, from project management team to workforce
• Emergency conditions, from anyone to supervisor / HSE engineer / Project Manager
• Accidents / Incidents, from anyone to supervisor / HSE engineer / Project Manager
• Accident investigation results, from project management team to workforce

12/15
• Statistical Data, from HSE engineer to project management team & workforce

According to the legal requirements and contract specifications, the above information shall be
transferred to authorities and the COMPANY representatives.

The communication means which shall be used are instruction notes, reports, memorandums,
meetings, training courses, drills, exercises. Radio communication shall be used only for
emergency cases where available.

5.5. HSE Meetings

The structure of meetings would be as follows:

• HSE related talks with labor in toolbox meetings every week


• HSE discussions during weekly progress meetings
• Monthly HSE meetings with workforce
• HSE meetings with the COMPANY every 2 months

In these meetings, the objectives are to discuss and review contract objectives, the progress
against plan, to give statistical feedback of performance, to discuss the cause and preventive
measures for any accident happened, to discuss hazards related with future works in detail and to
discuss any problem areas related with HSE. Of course, the content and duration’s would be
different meetings.

5.6. Inspection and Audits

The inspections and audits will be performed with the understanding of:

- Direct elimination of potential causes of accidents partially by checking unsafe acts and
conditions
- Indirect elimination of potential causes of accidents completely by increasing HSE awareness
of staff

The inspection and audit plan will be as follows:

• Construction equipment checks & inspections (periodically)


• HSE equipment checks & inspections (periodically)
• HSE audit just after completion of mobilization
• Daily unsafe act / condition audits
• HSE audits every 3 months

Equipment Checks & Inspections

All of the HSE equipment will be checked, inspected or certified according to individual
requirements.

Additional to HSE equipment, construction equipment, facilities and vehicles will be inspected
frequently, certified periodically (where relevant) in order to maintain good and safe conditioning
of them and to prevent any potential incidents or accidents. These are:

• Transportation means like cars, trucks


• Construction equipment (excavators, loaders etc.)
13/15
• Loading & Unloading equipment like cranes, hoist, forklifts etc. and accessories
• Welding machines, equipment and gas bottles
• Generators, engines
• Pumps and compressors
• Electric tools and extension cables, connections
• Catering facilities
• Housekeeping

The details about how these equipment are required to be inspected are described in relevant
procedures.

5.7. Subcontractor HSE Management

In order to maintain the same standards of working practices, the following principles would be
applied for subcontractors:

• HSE awareness, commitment to contract HSE clauses and past HSE performance will be a
criteria for prequalification.
• The Site Specific HSE plan will be discussed with them, signed for confirmation of
understanding.
• They will attend the HSE training courses and monthly HSE meetings at supervisory level.
• Their workshops, bases will be visited with the purpose of auditing.
• The contracts will be terminated with the subcontractors who are not able to reach the
required HSE performance.
• The safety requirements of the subcontract will be same as the contract and any modification
or waiver of any of the requirements will be approved by SOCAR CONSTRUCTION.
• The subcontractor will designate a Safety Representative who will act on behalf of the
subcontractor on HSE matters, and reporting to SOCAR CONSTRUCTION Safety Manager.

14/15
Section 6

HSE & EQUIPMENT

6.1. Personnel Protective Equipment (PPE)

Personnel protective equipment is required to be used for protection of people from potential
hazards where there may be a threat for head, eye, hand, foot, body, breathing, hearing.

In the construction sites, all individuals have to wear a safety hat, coverall and a safety boot. The
exceptions for specific cases can be acceptable with a written permission by safety engineer.

The use of the equipment will be shown in “basic HSE course” and the requirements will be
explained in “hazard assessment and management” course.

The personnel protective equipment will be delivered to all staff with a receipt form signed by the
employee. When it needs to replace the equipment, the old one will be returned back and the new
one will be given in the same method.

6.2. General Protective Equipment

As a part of preventive and protective measures, there are protective equipment required in the
project other than the ones used for personnel protection. These are:

• Instruction & Warning Signs, Barriers in general


• Medical equipment & facilities for health problems and injuries
• Fire Detection, Alarm and Fire Fighting Equipment for fire
• Life Saving Equipment for emergency cases
• Electrical Safety Equipment for facilities
• Disposal Facilities Equipment for waste management

According to the scope and nature of the works in the project, the “execution plan” shall involve
the requirements and

These equipment shall be under responsibility and control of site HSE engineer & HSE crew
unless otherwise specified.

6.3. Protective Measures on Equipment

The protective measures on some of the equipment is also important to prevent incidents and
accidents. These equipment are:

• Medical treatment equipment, for hygiene


• Moving equipment, like vehicles, plant equipment etc.
• Rotating equipment, like pumps, compressors, generators, grinding machines etc.
• Lifting equipment, like cranes, hoists, ropes etc.
• Equipment with radioactive sources, like inspection equipment
• Pressurized equipment, like test pumps or compressors
• Electrically powered equipment, for earthing
• Electrical equipment, like switchboards, distribution boxes, cables etc.

15/15
7. Winterization Plan

www.socarcons.com | [email protected]
Winterization Plan
Contents
1 Purpose
2 Necessity of a plan
3 Winterization Plan
4 Details of the Plan
5 Conclusion
6 Summary
Purpose of this Document 
The purpose was to explain the precautions taken during the wintertime to ensure that 
required productivity levels can be attained. 
The aim was to ensure that the machinery remains in working condition and working areas 
have temperatures comfortable for the workers in the harsh wintertime of the region.  
We aimed to have temperatures over 0°C, but believed that temperatures as low as ‐10°C 
might be acceptable during the harshest conditions, which were not expected to be frequent 
and abundant.
Winterization 
Necessity Of a Plan
In Russia,  Equipment designed for use in 
the winter  particularly extreme cold conditions also undergoes a 
temperature can  "winterization" process. Many complex devices 
drop to ‐60C, making  (automobiles, electronics and radios) as well as 
it one of the coldest  common materials (metals, rubbers, petroleum 
places to live in the  lubricants) are not designed to operate at extremely 
low temperatures and must be winterized to operate 
world.
without severe damage from the elements in such 
conditions. 
Winterization Plan

The Plan
1 Winterization of Equipments
2 Winterization of Work Areas
3 Winterization for specific 
work items
4 Other Provisions
Winterization of Construction Equipment
Before the winter, all construction 
equipment was prepared for the winter.  In this regard, 
the maintenance suggested by the manufacturer was
carried out.  The oils and hydraulic was replaced with 
those suitable for wintertime in the region and anti‐
freezing agents was added to all fluids.
Winterization for Vehicles
The most important step in preparing Vehicles for winter is the replacement 
of fluids with those suitable for winter conditions in the region (including but not limited to 
application of Anti‐Freezing Agents).  As an additional precaution, the vehicles were  kept in 
a proper place  where they were kept ready for utilization.
Winterization for Crawlers & Large Equipment

Since moving such equipment to and from the proper places  
was not possible, they were  kept at working conditions at or near 
their working areas. A dedicated team, heated the engines before 
start up in order to run the engines in ideal conditions.
Winterization of Offices & WorkShops
SOCAR Construction had a Central Heating System for its TSF
Area; & completed the construction of the Boiler Room for the same.
Workshops had own Central Heating Systems, which was supported with electrical and diesel 
heaters as necessary. 
Containers at Site, which primarily served as offices for Site Supervision, was insulated and 
heated with Electrical Heaters.
Winterization 
Winterization of Piperacks
Pipe Racks was covered on both sides with un‐
insulated Tarpaulin at two sides from top to bottom to the level of 
scaffolding (in order to break the wind), and  provide additional  
tents and heating at  working locations.  The tents, which are made 
of fireproof material, was heated. Electrical Heaters on higher levels
were used.
Tarpaulin cover and tents were segmented and each segment was arranged in such a way that they could
be opened easily and quickly both from the inside and the outside in order to allow quick evacuation in case of an 
emergency.
Winterization of Piperacks
Since the power requirement for 
such setup was high, SOCAR Construction 
believed that extra generators were 
needed to compensate for the additional 
power requirement.  SOCAR 
Construction’s calculations showed that 
two 450‐kVA Generators would be 
sufficient for such requirement.

SOCAR Construction 
also planned to have 
Junction Boxes to provide 
power along the Pipe Racks.
Provided Winterization was 
used for both Steel Structure 
Erection and Piping Works.
Winterization of Piperacks
Winterization of Columns (for internals)

This applies  to the Internals Installation for Columns C‐11330, C‐11350, C‐11360 and 
C‐11370, however, may be extended to cover the Installation of other Internals.  The heating was
provided by means of Electrical Heaters.  The level just above the active manhole (i.e. the manhole 
being used to deliver the materials required for the installation of Internals at the current level) was 
covered by Tarpaulin to reduce the volume to be heated.  Similarly, the level below the current level 
was also closed by Tarpaulin.  
In order to improve heat preservation, an insulating jacket was installed around the working level.
Tarpaulin covering was arranged in a way to allow the workers inside to evacuate easily and quickly in 
case of an emergency.
Winterization of Heaters
SOCAR Construction  
provides jacketing around the 
working levels and used
Electrical Heaters inside.  

SOCAR Construction closes
the Convection Modules with 
Tarpaulin and provide heating 
with Electrical Heaters.

The arrangements is made in 
such a fashion to allow quick 
evacuation in case of an 
emergency. 
Winterization of Rotary Equipment
SOCAR Construction covers the Compressors completely with Tarpaulin and 
provided heating by means of Electrical and Diesel Heaters.  The covering  allowed quick 
evacuation in case of an emergency.  Other provisions as stated in the Vendor Manuals was
taken.  If temporary heating systems were present within the equipment, they were plugged 
in to keep the core temperature of the rotating parts within acceptable limits as per Vendor 
instructions.In general, oils and fluids of Pumps and other Rotary Equipment was substituted 
with ones suitable for wintertime if required.
Winterization for Around Equipment Piping

Winterization for Around‐
Equipment Piping is made in a way similar to that of 
the Pipe Racks; however, instead of covering the 
entire area with Tarpaulin, the covering is limited to 
working areas. The tents, which are made of 
fireproof material, are heated by Diesel Heaters on 
Ground Level and Electrical Heaters on higher 
levels.
Winterization
Winterization for Welding & NDT tests
Welder Helpers had a Propane 
Cylinder and Torch handy to preheat the Pipe 
when necessary.
Electrodes and other Welding Consumables were
stored in ambient‐controlled environments.

SOCAR Construction’s NDT 
devices are capable of working at low
temperatures so having an environment 
comfortable for workers would be sufficient for 
NDT Activities at site.
For Penetrant test, temperatures around +10°C 
was required; which was obtained by providing 
additional Heaters inside the Tents.  Since this 
activity was only  required for very few joints, 
SOCAR Construction believed this would not 
present a major problem.
Other Provisions – Electrical Setup 
SOCAR Construction studies the 
current Lighting Setup at Site and provides covered areas (Pipe 
Racks, Internals, Tents, etc.) needed to  be illuminated 
separately. SOCAR Construction provided permanent lighting at 
suitable locations around the Site; but the Illumination for Tents 
and other covered areas was designed to be portable.

As explained above, SOCAR Construction studied the Power 
requirement at the peak; and extra two Generators, with 450 
kVA capacity each, became sufficient to compensate for the 
additional requirement with some reserve.

The Setup inside the Rest Shelters  included time‐controlled 
switches to ensure that the temperature inside the Shelter was
maintained at night.
Other Provisions – Mobilization Team 

SOCAR Construction  had a dedicated Mobilization Team, 


which prepares the tents and areas for future works (this includes heating and illumination 
of the Tent prior to work start).
SOCAR Construction has a dedicated Electrical Team who would roam the Site continuously 
and provide maintenance and repair for the Heaters, Lights and Electrical Setup.  SOCAR 
Construction dedicates  two teams that shifted during day time and night in order to 
maintain all electrical apparatus. 
Summary 
1 Winterization of Equipment
1,1 Equipment Oils & Hydraulics replaced √
1,2 Anti freezing agents √
1,3 To keep in proper place at night √
1,4 Night shift for heating machines √
2 Winterization of Offices & Workshops
2,1 Central Heating for offices, office containers, dining halls √
2,2 Electrical Heating for workshops √
3 Piperacks
3,1 Both sides covered with Tarpaulin from slab level to bottom of scaffolding √

3,2 Additional tents & heating at working locations (40*15KW) √


3,3 450 Kva *2 Generator √
4 Equipment piping
4,1 Covering working areas with tarpaulin‐ diesel heaters √
5 Welding
5,1 Propane bottles & Torch for preheat the pipe √
6 Electrical Setup
6,1 30* 250 W lamps √
6,2 time controlled switches to ensure temp. İnside is maintained. √
7 Warm clothing
7,1 Insulated boots & jacket √
7,2 helmets & high visibility vests & protective glasses √
8 Mobilization team
8,1 Prepare tents & areas for future works(Incl. Heating + illumination) √
8,2 Electrical Team provide maintenance & repair for heaters + lights & electrical set up √

2 teams of 3, 1 for day shift & 1 team for night 
8,3 shift √
9 Additional Resources
9,1 Additional workforce due to maintain productivity √
9,2 New workshop for NDT & night shift at site. √
Conclusion 
SOCAR Construction has extensive experience with and necessary 
knowhow for working in the harsh winter conditions expected in the region; and is confident 
that the target productivity rates can be attained with the provisions discussed in this 
document.  
Moscow, Prechistenskaya Nab. No:17 | Tel :  +7 (499) 502 88 88 
54 Elif Hajıyev Street, Baku, AZ1060, Azerbaijan | Tel: (+99412) 521 07 80/81 | Fax: (+99412) 422 30 50
www.socarcons.com | [email protected]

You might also like