Sr. No. Requirements: Ppap Check List
Sr. No. Requirements: Ppap Check List
PSW
1) Part No.
2 2) Revision No.
3) Run @ rate
4) Part Wt.
5) Signed Copy
PFD
4 1)Process including sub process & Supplier name
2)CC parameter must be mentioned
3)List of CC & SC parameter Siged out with weber.
PFMEA
1) As per PFD
5 2) fit from function parameter failure modes
3) correct rating & RPN
4) Top ten RPN must be need to list out.
5) Top RPN improvement Action plan from supplier.
6) SC &CC characteristics need to be highlighted.
Control Plan
1) As per PFMEA.
2) Production control plan need to submit.
3) All parameters must be included.
6 4) Correct selection of All instruments for all parameters.
5) Inspection frequency must be defined.
6) First piece inspection parameters must be same as per control plan.
7) Operation wise quality plan.
8)SC & CC parameter must be measured during first piece.If any third party inspection required so
define the frequency.
ISIR
1) all parameters including notes.
2) All dimensions must be within spec. by the correct instruments.
7 3) ISIR Summary shuold include list of nc parameters in ISIR.
4) ISIR must be signed off.
5) Material Test reports ,third party & Raw material Suppliers.
6) Salt spray report if applicable.
7) Outside lab report applicable for CC & SC parameter.
Prepared By Approved
Mr. k kamlakar Mr. Ajay m fasge
Document Checklist
S. NO Requirements S
WEBER Specific Documents (Part of CSR)
1 Process-cum-Inspection Planning Sheet (PIPS)
2 Packaging Data Sheet - Handling
3 Operation Wise Quality Plan
4 Special Process Validation
a. Qty despatched
b.Qty Rejected
5
c.CA -8D (to be submitted if Sample/Trial lot are rejected)
d. Deviation if any
PPAP Checklist
S. NO Requirements S
1 Customer Drawing (Design Record)
2 Engineering Change Document
3 Customer Engineering Approval
4 Design FMEA
5 Process Flow Diagram
6 Process FMEA
7 Control Plan
8 Measurement System Analysis Studies (MSA)
9 Dimensional Results
10 Material / Performance Test Results
11 Initial Process Study (SPC)
12 Quality Laboratory Documentation
13 Appearance Approval Report
14 Sample Product
15 Master Sample
16 Checking Aids
17 Customer Specific Requirements
Part Submission Warrant (PSW)
18
Bulk Material Requirement Checklist
Prepared By Approved By
Mr. S.A. Mane Mr. Atul Daptardar
R NA