2018 SGN 01 Ground Bearing Slabs Good Practice Guide-1
2018 SGN 01 Ground Bearing Slabs Good Practice Guide-1
2018 SGN 01 Ground Bearing Slabs Good Practice Guide-1
2018 SGN 01
Ground bearing slabs: good practice
guide
SSN Insight
Filename
Description
Signature
Filename
Description
Signature
Filename
Description
Signature
Contents
Page
Introduction 1
1.1 Scope 2
1.2 Judgement 2
Nature of slabs 2
Client expectations 3
Other issues 35
7.1 Perimeter cladding support 35
7.2 Under-slab insulation 36
7.3 Underfloor heating 36
7.4 Ground gases and radon 36
7.5 Mesh detailing: flying ends 37
References 38
Appendices
Appendix A
Supporting guidance
Introduction
As a forward-thinking firm, Arup strives to design buildings that perform well,
use best practice and deliver on our client’s expectations.
This Note considers the technical literature and collective Arup experience on
ground bearing slabs, which has developed significantly since the previous SGN
on this subject was written in November 1983.
The guidance should be used in conjunction with and not as a substitute for the
design guides and codes that are referred to within the text. Section 8 contains a
complete list.
This Note generally focusses on the standards, construction methods and design
guidance used in the UK, although much of the guidance in terms of design
principles is equally applicable worldwide.
The majority of published guidance in the UK regarding the design and
construction of ground bearing floor slabs is very specific to industrial type uses.
In practice this guidance is not always applicable to non-industrial, lightly-loaded
ground bearing slabs for use in offices, schools & other institutional type
buildings or even car parks.
These ‘normal’ building types generally do not require slabs to support large
concentrated point loads, or to be built to the tight surface tolerances required for
high bay storage facilities. Furthermore, the surface of the slab is in many cases
concealed beneath floor coverings such as carpet, vinyl or raised access systems
which will be more forgiving to imperfections and narrow cracking than the
exposed surfaces found in industrial facilities.
When faced with such a ‘normal’ slab to design, it is common for engineers to
take one of two approaches, depending on the individual’s inclination;
1. adapt a similar methodology to one used previously and apply it, often
conservatively, or
2. ask a colleague with previous experience what they have done in the past.
While there will be numerous examples of slabs designed and built using both of
these methods, without any problems, a more ordered approach would be
beneficial.
This Note sets out the design principles applicable to all ground bearing slabs and
provides such an ordered approach to both industrial and ‘normal’ more lightly
loaded slabs. For residential slabs, a more standardised simplified approach to
BS 8204 [1] [2] and NHBC [3] guidance is outlined.
For industrial warehouses, the floor is often the most valuable asset and yet
insufficient attention is often applied to its design and detailing.
1.1 Scope
This Note applies to internal slabs in buildings, and different approaches (often
using unreinforced pavements) are used for design of external slabs, which are
beyond the scope of this guide. Section 6 of IGN 01 [4] provides useful
complementary guidance on concrete hardstandings around buildings.
Water-resisting, damp proofing and insulation requirements are not considered
here. Neither does this Note cover raft slabs, suspended slabs or post-tensioned
ground bearing slabs.
1.2 Judgement
Readers should also be aware that a degree of engineering judgement will be
required in applying any recommendations made in this Note, since it is not
possible to consider every variable.
Nature of slabs
A ground bearing slab, sometimes called a ‘solid floor’ or a ‘slab on grade’, is one
of the simplest forms of construction. It is widely used throughout the world and
there are many sources of information on design and construction. Yet, despite
this wealth of experience and availability of information, ground bearing slabs are
a regular source of confusion, queries and differences between expectations and
actual performance.
It may seem that little can go wrong with a slab cast on the ground, but in
problems such as settlement, cracking, surface irregularities and dampness can
arise due to inadequate design, unsuitable detailing, insufficient site preparation,
poorly controlled construction etc. The situation is exacerbated by the growing
tendency to build on sites with natural or made ground of poor loadbearing
qualities, the need in industrial developments to have close tolerance on the
finished level and to accommodate substantial (and ever increasing) storage, plant
or vehicle loads.
Sound guidance on the design, specification and construction of ground bearing
slabs is thus worth reading. This note, which builds on Structural Guidance Note
(SGN) 4.5 from 1983 [5] (now withdrawn but available on request from AT+R),
draws attention to some recommended sources, and current thinking regarding
best practice.
Client expectations
Every floor should be designed to suit the individual requirements of the end user.
This sounds straightforward, however there is a lot more to consider than just
establishing the floor loadings and then designing the floor to support them
structurally.
It is important to establish what the client’s expectations are at an early stage,
before decisions are made about the form of construction of the floor. Beyond
simply establishing the design loadings, key questions could include:
Is there any requirement for future flexibility (e.g. a mezzanine or additional
plant or storage in the future)?
What is the nature of the loading, e.g. significant point, patch, pattern, uniform
loads; is the load static or not?
Is the floor trafficked (i.e. materials handling equipment, MHE)?
What is the precise nature of the trafficking / MHE?
What finishes are proposed? Will there be any brittle or bonded finishes?
Will any screeds or levelling compounds be used? Are there any raised floor
areas?
What are the surface finish requirements, e.g. flatness and regularity
(particularly for exposed slabs)?
Are there joint and crack requirements, and does the client understand the
implications of the different approaches to managing joints and cracks?
Is underfloor heating proposed? Is insulation required?
Are any recessed areas required (i.e. for showers, revolving doors etc. A
75mm finish zone is unlikely to be sufficient)?
What are the expectations with respect to maintenance?
Other considerations e.g. ground gas, radon, damp or water proofing.
Warehouse slabs will often have storage racking, MHE etc. requiring very
tight tolerances. Manufacturing and other industrial facilities will usually not
have the same strict tolerance needs, however in either case the requirements
should be discussed at an early stage with the Client.
Residential slabs. These have the least published design guidance. They will
generally have an applied finish, are poured in smaller areas and are lightly
loaded.
Slabs for other ‘normal’ non-residential uses, e.g. institutional buildings,
offices, schools etc. This Note sets out the approaches when using standard
fabric (mesh) reinforcement for these slab types.
Two distinct approaches are in use in the firm for such ‘normal’ situations: a
jointed solution with planned construction joints and saw cut joints, and a
largely unjointed solution developed by Arup in Bristol. Both approaches
have been successful, and a decision on which to adopt will depend on
knowledge of issues such as finishes, contractor preference, client
expectations and workmanship considerations.
If adopting an unjointed (or predominantly unjointed) approach, attention to
details (i.e. particularly re-entrant corners, restraint, slip membranes etc.)
becomes even more critical, and these aspects must be carefully considered
improved subgrade. A set of plate bearing tests on the top of the improved
subgrade is the most appropriate way to determine an appropriate stiffness (k
value) for slab design, but this needs to be considered alongside other
geotechnical parameters and testing to assess the overall settlement potential.
Top of foundations set below slab Top of foundations flush with underside of
slab
Allows flexibility for below-slab drainage. In Below-slab drainage, picking up down pipes
normal circumstances 600 to 650mm from top adjacent to columns, will need to be cast in to
of slab (TOS) is required. the foundations.
A degree of vertical isolation of the slab from No vertical isolation between foundations and
the column can be achieved: ground floor slab. Foundations will form ‘hard
> 200mm of stone sub-base between spots’, which the slab should be checked for.
foundation and slab will act to reduce The slab may require local thickening and/or
‘hard spots’ forming additional reinforcement to increase its
bending moment capacity.
< 200mm of stone between foundation
and slab will be difficult to compact. Less excavation (particularly significant for a
hard or near surface rock site).
Possible details for both situations listed in Table 1 are shown in section 6.3.6 of
this Note.
5.4 Sub-base
A sub-base (usually a compacted layer of Type 11 graded granular material) is
normally provided over the subgrade2, and contributes to the platform stiffness.
Some points:
If the finish slab surface requires a tight flatness and regularity tolerance, then
the level of the underlying subgrade will also need closer tolerance. This
should be specified and highlighted to the, often different, subcontractor.
1
‘Type 1’ is a classification defined in the Specification for Highway Works [9] which has been
revised in accordance with BS EN 13285 [10] and BS EN 13242 [11].
2
‘Subgrade’ and ‘sub-base’ should not be confused: the subgrade is the ground material below the
sub-base.
Type 1 is more expensive, but provides a more even grading which will provide a
better finish surface than 6F1/6F2 which is much lumpier, but cheaper. 6F1/6F2 is
easier to lay in wet conditions. It is recommended that the contractor is involved
in the decision making process, especially if the sub-base is required to act as a
construction works platform or piling mat. When the sub-base is trafficked it will
become worn and uneven. It is common practice to specify that the top 50 to
75mm is scraped off and disposed of before a light sand dusting/blinding is
applied and rolled to closure.
The stone layer is finished (rolled to closure) with a layer of fines to close the
surface. Sand is most commonly used, although a lean concrete mix is an
alternative which may be advisable for heavily reinforced slabs.
The blinding helps ensure that the slab is free to move horizontally due to thermal
and early age effects, minimising restraint that can lead to cracking. Sand blinding
also reduces the risk of puncturing the slip membrane.
Sand blinding should be specified as “sand blinded and rolled to closure”, rather
than “min X mm of sand blinding”, since any thickness of sand above the stone
will be easily displaced and reinforcement spacers will sink into it under foot
traffic. Having a surface that is not closed can lead to surface rutting, creasing of
the membrane and increased restraint, which is especially critical where a very
high tolerance for subbase flatness has been specified.
Reference [9] contains guidance on the layering, compaction and minimum
thicknesses to be used, and should be referenced in our documentation.
5.5 Slip-membranes
A slip membrane (typically 1200 gauge
Waterproofing and gas
polythene) is usually placed over the sub-base. As
protection are not
the name implies, the slip membrane reduces
friction between the underside of the slab and the considered in this Note
sub-base below. It also helps prevent loss of
cement fines from fresh concrete, protects the slab from ground borne sulphates
(alongside appropriate concrete mix specification) and can be designed and
detailed to act as a damp proof membrane (DPM).
Note that a polythene membrane may not provide adequate resistance to water
vapour, so this final point shouldn’t be taken for granted. Its adequacy in this
regard will depend on the use of the building.
Slip membranes will need suitable detailing at joints to provide adequate slip and
damp proofing. Typically, this would be by lapping the membrane sheets,
commonly using a 300mm minimum lap (although taped joints may be a
requirement depending on conditions, and whether the membrane also has a
vapour/gas resistance requirement, in which case specialist manufacturers
recommendations should be followed).
If gas protection is a requirement, membrane systems (membranes and joint tapes
etc.) are available with various grades. These membranes are generally of a
different colour to distinguish them from polythene membranes that only provide
a slip membrane and DPM function.
Specification of membranes as DPM’s or for gas protection is beyond the
scope of this SGN.
Introduction
Much has changed since the issue of SGN 4.5 – the main change being that the
Concrete Society (formerly published by the Cement & Concrete Association -
C&CA) Technical Report 34 (commonly referred to as TR34) has been released
and has gone through several updates (at the time of writing the current edition is
the 4th, published in August 2013, revised October 2013 [7]). The design guidance
in TR34 on assessing structural performance is also available as a Tekla Tedds
calculation. TR34 is only applicable to design of internal slabs.
Though the ‘computerisation’ of the calculation is to be welcomed, there is
concern that it is sometimes used without adequate understanding. Figure 1 shows
the iterations for an industrial slab design:
Check joint
widths, fillers, Finishes
ariss details
Determine loadings
General loadings are taken from Eurocodes, British Talk to the client
Standards, and the like. There are also loads from and user about
specialist suppliers to take into account such as shelving loading in the
& racking, plant loads, forklift trucks (FLT’s) and other facility
MHE, mezzanines etc.
Global area floor loads are seldom the governing design case for the slab in
industrial buildings but may be critical for settlement calculations, so pass these to
the geotechnical engineer. Point loads (from racking leg loads, mezzanines and
materials handling equipment MHE) generally dominate the slab design, and may
need to be considered in combination.
distributed
Leg load (tonnes) Loading
Fork lift capacity
(kN/m2)
(tonnes) Width of racks (m)
150 2.4 2.3 2.2 2.1 1.5 1.6 1.6 1.6 1.7 1.7 1.7 41 88
175 3.5 3.3 3.2 3.0 2.0 2.0 2.1 2.1 2.1 2.2 2.2 44 94
200 4.8 4.6 4.4 4.2 2.5 2.6 2.6 2.7 2.7 2.8 2.8 47 101
225 6.2 5.9 5.6 5.3 3.0 3.2 3.2 3.3 3.3 3.5 3.5 50 108
250 8.4 7.9 7.5 7.0 3.6 3.8 3.9 4.0 4.0 4.2 4.2 53 115
275 11.0 10.4 9.9 9.3 4.2 4.6 4.7 4.8 4.8 4.9 5.0 56 122
300 13.4 12.6 12.0 11.4 4.9 5.4 5.5 5.6 5.7 5.8 5.9 59 130
Table 2 predates the 3rd Edition of TR34 and so has somewhat more conservative
values than the current best practice, but is useful for obtaining an initial estimate
of required thickness.
The loading repetitions in the table are based on pneumatic tyres, and so may not
necessarily be entirely representative of modern MHE which predominantly use
small plastic wheels.
An alternative ‘rule of thumb’ approach to initial sizing of ground supported mesh
fabric reinforced slabs is to take the maximum rack leg load in kN and add
100mm to give an initial thickness estimate (i.e. 75kN on 175mm floor, 100kN on
200mm floor).
The most commonly used slab thickness in
medium to heavy duty industrial applications is The most common slab
175mm. Generally, it takes quite onerous non- thickness in typical
standard loading to be applied (or other medium to heavy duty
influencing factors such as a required industrial applications is
minimum thickness for embedded items) 175mm.
before a typical slab needs to exceed 200mm in
thickness.
Note that 150mm thick slabs in industrial applications can be problematic as any
loss of thickness due to workmanship or construction issues brings them into the
range (100mm – 125mm) where curling and other effects are problematic. For this
reason it is recommended that 150mm slabs are only used for very lightly loaded
situations with no dynamic loading, and that slabs of less than 150mm thickness
should be avoided in industrial applications. TR34 includes a requirement for a
minimum thickness of 150mm
Isolation joints – these formed joints have no restraint. They are used around
columns and walls or adjacent to plinths supporting vibrating machinery and
allow both vertical and horizontal movement.
Free-movement joints – aim to cause minimum restraint to horizontal
movement, but restrict vertical movement. They can be either sawn or formed.
Restrained-movement joints – allow limited (1-2mm) horizontal movement
and can be either sawn or formed.
Tied joints – are formed joints used to provide a break in construction and
have enough reinforcement to prevent opening.
Reinforcement
Reinforcement is required in order to use the design methods presented in TR34,
as TR34 does not cover unreinforced slabs. (The TR34 calculations are based on
plastic analysis and reinforcement is required to ensure that the concrete remains
ductile.) Reinforcement can be either loose bar, fabric or fibres.
The most common types of fibre reinforcement are steel and plastics. Plastic
fibres come in two distinct forms often referred to as macro and micro synthetic
fibres.
Fibres should conform to BS EN 14889. Micro synthetic fibres may affect the
properties of the plastic concrete but will have a negligible effect in hardened
concrete. They are sometimes used in combination with other steel or plastic
macro synthetic fibres. Steel fibres and macro synthetic fibres may impart
residual or post cracking strength to the concrete matrix.
Fibre reinforcement
Fibres are distributed through the whole section as they are mixed in with the
concrete. Fibres are generally a proprietary item, supplied by a specialist provider
who has carried out their own testing – for example Dramix by Bekaert.
It should be noted that generally synthetic (plastic) fibres do not provide reliable
post crack ductility and so are not considered in strength design calculations.
If using fibres, it is usual to get the proprietary supplier to carry out a design. The
suppliers will provide mix requirements for input into the concrete specification.
Proprietary designs, the properties of fibre reinforced concrete and the testing
work used to substantiate the design values should be reviewed by someone
familiar with the relevant test standards and design methods.
Mix design is crucial with fibre reinforced concretes to ensure that the mix
remains adequately workable.
It is unlikely in the UK that fibres would be added at the batching plant, and there
is therefore frequently a manual handling operation of adding fibres to the
concrete at the site.
Quality control and monitoring is particularly important to ensure that the fibres
are consistently mixed, distributed evenly through the concrete and are not
‘balling’ within the mix.
Fibres have a health and safety advantage over fabric or loose bar. They:
doesn’t need to be placed, reducing manual installation work
do not present a trip hazard.
However, fibres may be seen at the surface, even when the surface is power
floated. The fibres can be removed after curing with a heat tool, but care should be
taken not to ‘burn’ the concrete surface.
Induced joints
These are relatively narrow – normally formed or a saw cut (normally 5mm wide
and the greater of 0.3 × slab thickness or 50mm deep). The joints will open as the
concrete moves, and could close if there is expansion in the slab. Saw cut joints
are introduced soon after the concrete is poured to accommodate the contraction
associated with the early thermal effects of cement hydration.
Crack inducers placed at the base of the slab during construction should not be
used as these can promote uncontrolled cracks forming prior to saw cutting.
3
http://www.permaban.com/products/dowel-systems/diamond-dowel-1
Formed joints
Joints can comprise a sealant
and a filler board. The filler
should be compressible to
accommodate some movement
while also being sufficiently
rigid to support the joint filler
during construction and in
service. The sealant prevents
water / dirt / ice getting into a
joint and damaging it, and should Figure 3. Formed joint (Detail G026 from [13]).
support the arris. It can affect the [Compressible Filler should not usually be used!]
appearance of the floor.
It is relatively unusual to include formed expansion joints (i.e. with a
compressible filler) into a warehouse floor slab. The early thermal contraction and
contraction at formed joints is generally of far greater magnitude than any
subsequent expansion, so that such joints are generally unnecessary.
Using a compressible material opens the joint leaving arrises more vulnerable to
trafficking
If an expansion joint closes up, the filler board is unlikely to fully expand again
and this can lead to contraction manifesting itself at other joints, making them
more susceptible to damage.
Where a design requirement for such a joint is identified, it is recommended that a
proprietary armoured joint solution is adopted, with steel plates reinforcing the
arrises etc.
Proprietary armoured joints are also preferred for formed contraction joints,
particularly where there is heavy MHE use.
Finish
As with all concrete, curing is critical to achieving a satisfactory finish. A suitable
curing agent and curing regime (often using spray on acrylic resin type products)
should be used.
resistance just where it is needed. Increasing the concrete strength can also
give a higher resistance, however dry shakes are more effective than
increasing concrete strength. Dry shakes are commonly used with fibres to
reduce incidence of fibres becoming exposed on the surface. Refer to TR34
and suppliers information for more guidance. A well cured and well finished
slab should have sufficient abrasion resistance to pass the usual tests.
Some sprinkle finishes are applied using spreaders which can create
cementitious dust and so can present a health and safety concern.
Delamination problems can also arise. Care is therefore needed in selecting an
appropriate product, not specifying such products unless there is a specific
requirement, and in following manufacturer’s recommendations for safe
application.
Direct finish, e.g. power floating etc. Floors are typically floated to rough
level and then power trowelled and/or power floated to give the smooth
polished finish associated with industrial/warehouse floors. Power
trowelling/floating will give a denser finish and also a smooth finish. Brush
finishes can give grip in wet conditions (a requirement for such finishes is
unusual in internal slabs with generally dry conditions). A Skip finish may be
suitable under applied finishes.
Painting. Painting can be used to define bays or access routes, alter appearance
and give resistance or grip.
Chemical resistance. This will depend on the application of the floor slab and
is normally provided by applying an appropriately resistant finish. Concrete is
generally resistant to many liquids used in industry, but chemical resistance is
a consideration for some aggressive substances (acids for instance).
Use for cold storage. Refer to specialist supplier details & TR34 for further
information
Rapid loss of water from the surface can also cause plastic shrinkage cracks.
Synthetic fibre reinforcement can help to resist this, as can dampening the
subgrade as well as reducing or avoiding the factors above. Evaporation retarders
are available but they are not curing agents, per se, and normal curing will still be
required. If plastic shrinkage cracks do appear, the finisher may be able to close
them during refinishing.
Fatigue effects can occur through frequent trafficking with heavy MHE and this
needs special consideration in heavy warehouses, paper stores etc.
Cracking can have an adverse effect on the performance of MHE, creating
‘bumps’ which the operator must slow down to cross and reducing operational
efficiency. This is a relatively common operational concern where excessive
cracking occurs in a new facility.
Foundations
Standard details at the edge of the building are included in the SSN Typical
Details [13].
To minimise restraint to movement the slab should be independent of any
foundations, columns or walls which penetrate the slab.
Columns
Generally, foundations are piled or pads, with the superstructure fixed directly to
the foundations. The slab is commonly laid at a later date, preferably when the
building envelope has been constructed to aid curing, It will run directly up to the
edge of each column, so will need an isolation joint around the columns.
Walls
Generally there are walls at the edge
of the building. The SSN Typical
Details show a thickening below the
wall line. As there is a change in
depth, it is normal to locate a joint
(typically an expansion joint) where
the slab ‘necks’ and without which
significant restraint is introduced.
A free movement joint to avoid
restraint between the slab and any
thickenings is therefore strongly
Figure 5. Perimeter wall (Detail G004 from [13]).
recommended.
Rather than building a chamfer, some contractors prefer to build a vertical face as
they find it easy to form (see standard detail G006 [13]). Discuss the detail with
the contractor where possible.
The depth below ground level needs to meet the requirements of the Building
Regulations in the UK. Refer to Part A: Minimum depth of strip foundations,
section 2E4 [15].
Where walls are located within the building, choose from the following
approaches:
provide a thickening with joints where the slab necks (see detail G011 [13])
build the wall on a separate foundation and cast the slab up to the wall (similar
detail to G008 [13]). This would be the preferred detail to avoid increased
restraint.
build the wall on the slab. Check the slab for a line load and inform the
geotechnical engineer so that long term settlement can be reviewed.
Construction
There are two main construction techniques for industrial slabs: large area pours
and long strip construction. The construction method and pour layout adopted will
determine the final joint layout.
Formed free-movement joints that open up to 20mm (it is unlikely that this much
movement will occur when intermediate joints are used) are provided at
perimeters (40m to 50m is the normal maximum dimension) with sawn restrained-
movement joints cut on a 6m grid in both directions.
It is now more common to omit the intermediate joints, where measures such as
fibres are used, and where knowledge of how the slab will be trafficked permits
this to be considered. In general, where fewer joints are used with wider joint
spacing, a higher level of workmanship, construction control and appropriate
detailing and mix design is needed to achieve satisfactory results.
A variation on large area pour is wide bay construction, which gives an improved
control on tolerance.
6.2 Residential
Introduction
The design basis for residential slabs is much less codified than for industrial
slabs. Residential floors in general have small panels, light loads and in most
cases have finishes applied. Cracking, surface regularity, abrasion resistance and
strength are normally not significant issues. Unreinforced slabs are often used.
BS 8204 [1] [2] and the NHBC [3] are the principal design guides.
Slab Thickness
The BS 8204 and NHBC (chapter 5.1, ‘Substructure and ground bearing floors’)
guidance for slab thickness is that, “Ground bearing concrete floor slabs should
be not less than 100mm thick, including monolithic screed where appropriate”.
A 100mm slab is therefore the minimum code recommendation, and to avoid
curling risk etc. a greater slab thickness would generally be recommended.
100mm may be adequate in a private dwelling on good ground conditions with
careful detailing, however it would not be recommended for a multi-occupancy
residential building like a hotel, student accommodation, multi-storey flats, care
homes etc. (i.e. the type of residential projects which Arup are most likely to be
involved in).
In most cases, on reasonable ground conditions, a 150mm slab with one layer of
A142 fabric reinforcement mesh is likely to provide an adequate design. Often in
lightly loaded slabs experience has shown that the reinforcement can be placed
centrally or in the top, to assist in distributing shrinkage cracking.
Sub-base
BS 8204 states that “the tolerance on a sub-base should be +0mm/-25mm”,
consistent with TR34 (see also section 5.4 of this Note).
Importantly, the NHBC adds that “ground bearing slabs are not acceptable where
fill exceeds 600mm in depth”. In this case, a suspended slab should be used.
Joints
A joint is generally detailed between the slab and the wall construction.
Generally, no internal joints are required. If they are, refer to BS 8204 for more
details.
Introduction
Ground bearing slabs are often used in schools, universities, public facilities,
offices, canteens etc. Although loads are generally much lighter than in industrial
uses, a mesh design sizing based on TR34 [7], rather than BS 8204 [1], [2] is
recommended as it gives a rigorous check and calculation.
Generally, in these buildings, the slab:
will have an applied finish in most areas (possibly not in plant rooms)
will be insulated to meet building regulation requirements
may have internal line loads from internal walls
could have a requirement for heating elements built into the floor build up.
Table 3 presents a comparison of the characteristics of these ‘normal’ use slabs
with those of industrial slabs.
Table 3. Comparison with more heavily loaded industrial slabs.
Characteristic Heavily loaded industrial slabs Lightly loaded “normal” slabs
Slab strength critical Yes – high point loads and UDLs No (only to bridge soft or hard
spots)
Placement of mesh Bottom (for bending strength) Top (for crack control where
unjointed) or middle (in 150mm
slabs to allow saw cut joints
above)
Use of induced joints Yes, regular, crack control Possibly not (if all aspects careful
detailed and top mesh used)
Typical surface Impact & abrasion resistance, use To receive a floorcovering
requirements of sealants/toppings, surface
regularity and level,
reinforcement of joints
It goes without saying that, where the technical requirements of a slab are closer
aligned to those of an industrial slab, then the design should follow that approach
– refer Section 6.1 of this Note.
In contrast, where the characteristics of the slab align closer with those of a
‘normal’ use slab, it is appropriate to design accordingly.
A reduced quantity of movement joints (both induced and formed) can simplify
the slab detailing and construction considerably and can equate to reduced
construction costs.
However, it requires a good level of construction control (workmanship), and
recognition by the client and architect that the approach does present a higher risk
of some uncontrolled cracking, whilst having the advantage of avoiding some of
the detailing considerations associated with providing joints.
The flow chart shown in Figure 6 maps out the design process for adopting an
unjointed design approach.
It should be noted that to provide the minimum reinforcement to restrain initial
cracks against further opening (in accordance with Ciria C660 and EC3 Part 2) a
higher level of reinforcement would be needed than the usual single layer of
mesh.
The expression for the reinforcement area that would be required for this is:
As,min = kck Act fctm(t) / fky
Figure 5. Typical detail for a 150mm slab with central mesh, using a jointed
approach.
If an unjointed approach is not welcomed, the alternative is to place the mesh
centrally in the slab (typically an A193 mesh central in a 150mm thick slab depth)
and to use formed and saw cut joints at 6m to 7.5m centres. This jointed approach
has a lower risk of uncontrolled cracks occurring, may be more ‘safe’ and is
suitable where brittle or bonded floor finishes are proposed. The disadvantages are
that there is a cost associated with forming the joints, positioning of the joints
needs consideration, and detailing the finishes and internal walls to coordinate
with the joints becomes important.
Figure 6. Flow chart for designing lightly loaded internal floor slabs.
Applied finishes
The type of surface finish the slab is to receive will normally be determined by the
architect or client to suit the intended use of the building. It is important that we
understand what the applied finishes will be when we are designing the slab and
making decisions about whether to include movement control joints, isolation
joints around columns and specifying the surface finish.
Some finishes are inherently more sensitive to movement and cracking of the slab
than others. Table 5 lists the sensitivities of common finishes. Unjointed slabs are
only advocated when used in conjunction with the ‘sensitive’ and ‘less sensitive’
finishes although, in all instance, the expectations should be communicated to the
client.
Table 5. Floor finishes.
Key:
Bonded screed
(e.g. ceramic)
Raised access
Insulation &
= very sensitive
Exposed
Timber
Carpet
screed
Vinyl
Tiles
floor
= sensitive
(no tick) = less sensitive
Contraction joints
Where required, the layout of contraction joints is important, since joints or cracks
in the slab will generally be repeated in the finishes.
Agreeing the location of any contraction joints (which may be planned
construction pour joints or saw cut joints) with the architect is therefore necessary.
The exclusion, or reduction of joints will be likely to be well received by the
architect, since their detailing and coordination will be simplified by not having to
coordinate joint locations with internal subdividing partitions (which are much
more prevalent in institutional buildings than they are in industrial buildings, but
rarely on a 6m x 6m grid).
However, even where an unjointed slab can be justified, it may also be prudent to
include isolation joints around structural columns – see section 6.3.6.
Joints along block work wall lines are also recommended. Where provided, these
should be aligned to one side of block work wall lines (where they will be under
the skirting), not bridged by the block walls.
Under heavier walls, where these sit on the slab, slab thickenings or a separate
strip foundation may be required.
Where joints are used (typically at 6m to 7m centres), panels should not exceed
1.5:1 ratio of sides. If they do, a crack across the middle of the panel is very
likely.
2. Steel/concrete column & foundation set up. Inclusion of a soft joint between slab
Any type of floor finish. and column is of little or no benefit
(no vertical movement possible, and
horizontal movement can only take
place if the slab and base are
structurally separate with a slip
membrane such as two layers of
polythene between them.
Crack control bars are not usually
required unless the foundation size is
small.
3. Steel column, with raised access floor Concrete surround to steel column
below slab level.
Inclusion of a soft joint between
concrete surround to column and slab
is unlikely to have any adverse
structural effects, so is recommended.
Such a soft joint should also be easy
to construct.
Detail Comments
4. Steel column with thin finishes The benefits of including a joint need
to be considered on a project by
project basis, and discussed openly
with the rest of the project team,
weighing up against practical aspects
(e.g. the position of the DPM,
buildability, etc).
o Benefit of a soft joint will be
limited to allowing horizontal
movement. Differential vertical
movement will be prevented by
the column encasement.
o The detailing of the DPM may
make the inclusion of a soft joint
impractical.
o Whilst it is fiddly to apply the
compressible board around the
profile of the column, the
alternative is to have it
unsupported of infill in between
the column flanges prior to
casting the slab.
Slab thickness
For lightly loaded applications the thickness of the slab is rarely governed by
strength, unless the ground conditions are particularly poor or the slab is
particularly thin.
As previously discussed, almost all available methods for designing ground
bearing slabs are intended for industrial type slabs subject to point loads and
heavy UDLs. The choice of slab thickness for most lightly loaded applications
tends to be made based on engineering judgement and past experience.
150mm thick slabs are typical, as for slabs any thinner than this, there is a risk due
to subgrade tolerances of thin sections (125mm or less) that would potentially be
subject to excess cracking or curling due to shrinkage.
Amongst the available published guidance, Curtins et al [8] has attempted to apply
some science to sizing the thickness by dividing ground conditions into four
categories of decreasing stiffness and increasing variability. These categories are
used to size a notional ‘soft spot’ over which the slab needs to be capable of
spanning, as shown in Figure 7.
Whilst the selection of category for soil classification will be open to a degree of
interpretation, and the sizes of soft spots suggested could be seen as being
somewhat arbitrary, a comparison of this method against the designs for past
projects does show a good degree of correlation.
The Curtins method has not been widely tested in Arup, however it does appear to
offer a good alternative to relying solely on past experience and engineering
judgement.
Other issues
C) Separate strip or trench footing Reasons that this detail might be adopted:
Reasonable ground at relatively shallow
depth
Suited to load bearing perimeter walls
rather than framed construction
If slab is going to be constructed after
the envelope
This detail is more common for domestic scale
buildings
Figure 8. Lapped mesh, with (left) and without (right) flying ends.
References
[1] BRITISH STANDARDS INSTITUTE. BS 8204-1:2003 +A1:2009.
Screeds, bases and in situ floorings —Part 1: Concrete bases
and cementitious levelling screeds to receive floorings —
Code of practice. 2009.
[2] BRITISH STANDARDS INSTITUTE. BS 8204-2:2003 +A2:2011.
Screeds, bases and in situ floorings —Part 2: Concrete
wearing surfaces — Code of practice. 2011.
[3] NATIONAL HOUSE BUILDING COUNCIL. NHBC Standards 2014.
Part 5 – Substructure, ground floors, drainage and basements.
2014.
[4] ARUP. IGN01. Pavement Design for Lightly Trafficked Roads and
Parking Areas, Civil Engineering and Utilities Network,
Jonathan Millard, August 2016.
[5] ARUP. SGN 4.5. Ground-Bearing Floor Slabs, (later renamed 1997
SGN 10), November 1983.
[6] GARBER, G. Design and Construction of Concrete Floors.
2nd Edition. June 2006.
[7] CONCRETE SOCIETY. Technical Report 34. Concrete industrial
ground floors — A guide to design and construction.
4th Edition, October 2013.
[8] CURTIN, W. G. et al, Structural Foundation Designers’ Manual,
2nd Edition. 2006. Available from Arup library as an e-book:
http://site.ebrary.com/lib/arupuk/detail.action?docID=102366
55
[9] HIGHWAYS AGENCY. Manual of Contract Documents for
Highways Works. Volume 1, Specification for Highway
Works, Series 800, Road pavements – Unbound materials.
2009.
[10] BRITISH STANDARDS INSTITUTE. BS EN 13285:2010. Unbound
mixtures – Specifications. 2010.
[11] BRITISH STANDARDS INSTITUTE. BS EN 13242:2013.
Aggregates for unbound and hydraulically bound materials
for use in civil engineering work and road construction, 2013.
[12] CHANDLER, J.W.E. Design of Floors on Ground. Technical
Report 550, MPA Cement, 1982.
[13] ARUP, SSN UK Structural Typical Details, April 2016.
http://networks.intranet.arup.com/structural/tools/typical_deta
ils_drawings/uk/structural_typical_details/structural_typical_
details_home.cfm
General
[Some typical notes – these will not cover all situations, and the notes will need
review in each instance to suit the specific project requirements]
Refer to the earthworks specification / drawing(s) for requirements for
excavation, fill and for slab subbase materials and compaction.
[For smaller projects, earthworks specification and subbase requirements may
be given on the drawings]
The compacted subbase is to be blinded with fine material to fill surface voids
and the finished surface is to be rolled to closure. A surface layer of fines or
sand is not to be used as this may not provide a suitably stable platform to
support the membrane and reinforcement chairs etc. during construction.
The slab is to be laid on one layer of minimum 1200 gauge BBA polythene
with 150mm lapped, taped and sealed joints (polythene membrane providing
the function of acting as a slip membrane). Waterproofing (DPM)
requirements to be confirmed by the architect (the minimum slip membrane
polythene may be satisfactory to provide the requirement, subject to the
architect specifying that this is the case).
For details of the required extent and specification of below slab insulation
refer to Architects details.
[Project Specific. Note only required where there is below-slab insulation.
The assumed design stiffness of subgrade needs to take account of insulation]
Provide pairs of diagonal bars in ground slab at all re-entrant corners / box
outs in slab, as shown on Arup substructure/reinforcement drawings.
The contractor is to consider his pour sequence, bay size and construction joint
locations to minimise slab shrinkage, and submit proposals to Arup prior to
construction.
The positions and details of all construction joints not shown on the drawings
are to be agreed with XXX [Project specific] before work commences.
The spacing and arrangement of sawn and formed joints should follow the
indicative arrangement on the drawings. There is a risk of cracking in all
concrete floors. The risk increases with the size of bays and distance between
stress relief joints, Joints should generally be at less than 6m centres. Panel
aspect ratios should not be greater than 1:1.5 following saw cutting.
Sawn joints shall be 3-4mm wide and cut as soon as practicable after placing
the concrete (nominally 24 hours or less after placing). Appropriate experience
on the part of the ground works contractor is required as saw cutting too early
damages the surface, and if cutting too late, cracks may already have formed
and therefore would be likely to continue to propagate in uncontrolled manner.
Underfloor heating pipes must not be cast into ground bearing slabs.
The ground bearing slab is mesh reinforced without contraction joints. The
Contractor is to consider his pour sequence, bay size and construction joint
locations to minimise slab shrinkage, and submit proposals to Arup prior to
construction.
Construction joint locations are also to be agreed with the Architect to avoid
sensitive areas. The architect’s attention is drawn to the likelihood of random
hairline cracks (typically less than 0.5mm in width) forming in the slab and
the need to ensure that any applied finishes are compatible with this.
A2 NSCS
The following is an extract from NSCS [16]: