C172 Inspection Time Intervals
C172 Inspection Time Intervals
5-10-00(Rev 20)
1. General
A. The primary function of this section is to give inspection time intervals. Section 5-10-01 is an index
of the inspections that you can use with 14 CFR, Part 43 inspection scope and detail. It is not
recommended, however, that you use Section 5-10-01 as the primary checklist for inspection of
the airplane.
NOTE: The inspection information in this section is not made to be all-inclusive. No chart can
replace the good judgment of certified Airframe and Powerplant mechanics. The owner
or operator must make sure of the airplane's airworthiness and must use only qualified
personnel to do maintenance on the airplane.
2. Procedure
A. A complete airplane inspection includes all inspection items as required by 14 CFR 43, Appendix D,
Scope and Detail of annual/100 hour inspections. Use the chart in this section as an augmentation
for the inspection.
B. Inspection Operation documents that begin with the letter "M" are those inspections that match
those found in the Chapter 4, Airworthiness Limitations. These are added because there is no grace
period for these inspections.
C. Examine the Component Time Limits section (5-11-00) with this inspection to make sure the correct
overhaul and replacement requirements are completed at the specified times.
D. The intervals shown are recommended intervals at which items are to be examined for normal use
under average environmental conditions. Airplanes operated in extremely humid areas (tropics), or
in unusually cold, damp climates, etc., can need more frequent inspections for wear, corrosion, and
lubrication. Under these adverse conditions, complete periodic inspections related to this chart at
more frequent intervals until operator field experience is used to set individual inspection intervals.
(1) The 14 CFR Part 91 operator's inspection intervals must obey the inspection time limits shown
in this manual except as given below: (Refer to 14 CFR 91.409.)
(a) The airplane can operate only ten hours more than its inspection point, if the airplane is
enroute to a facility to have the inspection completed.
(b) If any operation is scheduled after its inspection point, the next operation in sequence
keeps the required date from the time that the late operation was originally scheduled
(schedule again if late).
(c) If any scheduled operation is completed early, and is 10 hours or less ahead of schedule,
the next scheduled phase can keep its original date.
(d) If any scheduled operation is obeyed early, and it is more than 10 hours ahead
of schedule, the next phase must be rescheduled from the time the operation was
completed.
3. Inspection Terms and Guidelines
A. For inspection terms and guidelines, refer to Time Limits/Maintenance Checks - General.
4. Chart Legend
A. Each page of the inspection given in Inspection Time Limits, Section 5-10-01, contains the five
columns that follow:
(1) REVISION STATUS - This column supplies the date that a given item was added, deleted or
revised. A blank entry in this column is an indication there have been no changes since the
original issue of this manual.
(2) INSPECTION ITEM CODE NUMBER - This column gives a six-digit number permanently
assigned to a scheduled maintenance item. A given inspection item code number will never
change and will not be used again if the scheduled maintenance item is deleted.
(3) REQUIREMENTS - This column supplies a short description of the inspection and/or servicing
procedures. Where more detailed procedure information is required, a reference will be made
to either another section in the maintenance manual or a specific reference to a supplier
publication.
(4) TASK - This column gives a short description of the inspection and/or servicing procedures.
Where a more detailed description of the procedure is necessary, a reference will be made
to another selection found in the maintenance manual or a specific reference to a supplier
publication. If a task does not refer to a specific model and/or system, then the inspection
and/or servicing procedure applies to all equivalent models and/or systems in the airplane.
(5) INTERVAL - This column gives the frequency of the inspection in an alphabetic coded form.
The legend for the alpha code is shown below.
(6) OPERATION - The Progressive Care inspection program lets the work load to be divided into
smaller operations, that can be completed in a shorter time period. This program is supplied
in section 5-12-00, which is the Progressive Care Program.
(7) ZONE - This column gives the locations for the components within a specific zone. For a
breakdown of how the airplane is zoned, refer to Chapter 6, Airplane Zoning - Description
and Operation.
A. 1, 2, 3, 4 Every 50 hours.
E. (Not used. NOTE) First 100 hours and each 500 hours thereafter.
G. (Not used. NOTE) Every 1000 hours or 3 years, whichever occurs first.
J. 11 Every 2 years.
K. 12 Beginning five years from the date of the manufacture, you must make sure of
the serviceability of the components every twelve months. Refer to Airborne Air
and Fuel Products Service Letter Number 39A or latest revision.
M. 14 Every 2 years, or anytime components are added or removed which have the
potential to affect the magnetic accuracy and/or variation of the compass calibra-
tion, or anytime the accuracy of the compass is in question.
Q. 18 Every 6 years.
R. 19 Every 12 years.
S. 20 Every 1 year.
V. 23 Every 100 hours, every annual inspection, every overhaul, and any time fuel lines
or clamps are serviced, removed or replaced.
AI 36 Operation 36 gives the Initial inspection within the first 100 hours of operation,
then repeat every 600 hours of operation or 12 months, whichever occurs first.
NOTE: This interval is not currently used but is given to supply information only.