How To Update Baseline in Primavera P6

The document describes two options for updating a baseline in Primavera P6 when a project has fallen behind the original baseline schedule. Option 1 involves creating a new baseline based on the current schedule and assigning it to the project. Option 2 is to restore the original baseline so it can be edited, then converting it back to a baseline after making updates. Both options require making configuration changes in the Admin and Project menus to update the project's baseline.

Uploaded by

anoopvvv
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
203 views7 pages

How To Update Baseline in Primavera P6

The document describes two options for updating a baseline in Primavera P6 when a project has fallen behind the original baseline schedule. Option 1 involves creating a new baseline based on the current schedule and assigning it to the project. Option 2 is to restore the original baseline so it can be edited, then converting it back to a baseline after making updates. Both options require making configuration changes in the Admin and Project menus to update the project's baseline.

Uploaded by

anoopvvv
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

How to update Baseline in Primavera P6

Baseline is something we usually do not change. However in some case we need to change it.

I will show you how to do it.

We have a simple project which is assigned a baseline

After a few update period, the project is delayed quite far from the baseline
After discussion with the Owner, they allow us to update our baseline to be identical to current
schedule.

There are some ways to update baseline.

Option 1:

We will create a new baseline based on our current schedule and assign the new baseline to our
project.

First you have to make an important configuration.

Go to menu Admin -> Admin Preferences.

In Earned Value tab, select “At completion values with current dates”
Go to menu Project -> Maintain Baselines. Click Add to create a new baseline
Go to menu Project -> Assign Baselines. Select baseline B2

Now you can see the baseline have been updated


Option 2 : Restore baseline

Go to menu Project -> Assign Baselines. Select Current project

Go to menu Project -> Maintain Baselines. Select the baseline and click on Restore button
Now go to the Project window and we can see the baseline become a normal project which we
can open and update easily.

After finish updating the baseline project, you will convert it to become a baseline again.

Open your “main” project. Go to menu Project -> Maintain Baselines. Click on Add button. Now
we will select option “Convert another project…”
And select the updated baseline project

Now your project will have a new baseline.