How To Update Baseline in Primavera P6
How To Update Baseline in Primavera P6
Baseline is something we usually do not change. However in some case we need to change it.
After a few update period, the project is delayed quite far from the baseline
After discussion with the Owner, they allow us to update our baseline to be identical to current
schedule.
Option 1:
We will create a new baseline based on our current schedule and assign the new baseline to our
project.
In Earned Value tab, select “At completion values with current dates”
Go to menu Project -> Maintain Baselines. Click Add to create a new baseline
Go to menu Project -> Assign Baselines. Select baseline B2
Go to menu Project -> Maintain Baselines. Select the baseline and click on Restore button
Now go to the Project window and we can see the baseline become a normal project which we
can open and update easily.
After finish updating the baseline project, you will convert it to become a baseline again.
Open your “main” project. Go to menu Project -> Maintain Baselines. Click on Add button. Now
we will select option “Convert another project…”
And select the updated baseline project