Procedure System of Site Qms Training
Procedure System of Site Qms Training
2 Distribution List
Sr. No/ Designation Issue Date Distributed by
Management Management
01 14th August 2018
Representative Representative
Management
02 CEO 14th August 2018
Representative
03 Management
Chairman 14th August 2018
Representative
Management
AJB- SQT - CEO Chairman
1.1 01 01-01-16 14-08-18 Representative
PR-01
Copyright
This document contains confidential information. It may be copied in full or in parts only by Al-Jaber
International Company and only for the purpose of Al-Jaber International Company related activities.
Disclosure of any information contained within this procedure to any person (s) outside the employee of Al-
Jaber International Company without written permission of the Top Management is strictly prohibited.
Page 1 of 9
Al-Jaber International Company
Procedure System of
SITE QMS TRAINING
Original Issue Date: Revision Issue date:
Doc. No: AJB-SQT-PR-01 Issue Number: 01 Revision Number: 01
01st January 2016 14th August 2018
TABLE OF CONTENTS
This document is the property of Al-Jaber International Company. Any copying and distribution of this document
without the approval of the Management is prohibited. Page 2 of 9
Al-Jaber International Company
Procedure System of
SITE QMS TRAINING
Original Issue Date: Revision Issue date:
Doc. No: AJB-SQT-PR-01 Issue Number: 01 Revision Number: 01
01st January 2016 14th August 2018
1. DEFINITIONS AND ACRONYMS
1.1 DEFINITIONS
Project Specific Training
Project specific training is training, developed or accessed by the project to ensure that
project members have the competencies required for project assignments.
Project specific training includes classroom courses, on-the-job training activities,
inductions (and toolboxes).
Training Attendance Record
QA/QC Training Report is a roster template which shall be recorded during training
activities.. Minimum information that shall be included in the form is:
Name of training,
Place of training,
Trainer name,
Date, time and duration of training,
Total man hour
Trainee information (ID, name, surname, company/department and signature)
Training Plan
The Training Plan specifies the project training goals for project members and defines
corporate and project specific training programs to achieve those goals.
Training Register Log
Training log used to determine how many hours’ trainings performed per month and
total score of training hours.
Training Evaluation
Training Evaluation is two paged, scaled questioned evaluation sheet which will be
filled in by Trainees at the end of training sessions in order to make plans for the further
trainings.
1.2 ACRONYMS
Acronym Description
DS Degassing Station
ECP Evaporative Cooler Project
QA/QC Quality Assurance / Quality Control
QMS QA/QC Management System
TSC Technical Services Contract
SGPS Suleimanya Gas Power Station
This document is the property of Al-Jaber International Company. Any copying and distribution of this document
without the approval of the Management is prohibited. Page 3 of 9
Al-Jaber International Company
Procedure System of
SITE QMS TRAINING
Original Issue Date: Revision Issue date:
Doc. No: AJB-SQT-PR-01 Issue Number: 01 Revision Number: 01
01st January 2016 14th August 2018
2. INTRODUCTION
The plant is located in the town of Chamchamal, which is located about 60 Km to the west of
Suleimanya city.
MGH has signed a contract with the Ministry of Electricity in Kurdistan Region to build SGPS with
a Capacity of 1500 MW on basis BOO (Build,Operate and Own). Work Started at site early 2008.
In the first and second phases (simple cycle), eight Frame-9E gas turbines were installed and
operated to produce 1000 MW and the contract for the simple cycle was signed with the
American Company GE and the German Company ABB.
As the Third Phase of the project, MGH started converting SGPS into a Combined Cycle with
additional 500 MWs capacity, by utilizing the gas turbine exhaust heat emissions to produce
steam in Heat Recovery Steam Generators (HRSG), which will used to generate electricity in two
steam turbines. This process increases the production efficiency without using extra fuel. It also
reduces the amount of CO2 emissions and frees the environment from combustion emission.
After the completion of the combined cycle, the plant capacity will be upgraded to 1500 MW.
It is worth mentioning that Sulaymaniyah power station is designed to operate on two types of
fuel, the prime fuel (natural gas) and secondary fuel (diesel).
The substation accompanying the plant is 132 KV for a Simple Cycle and a 400 KV for the
combined cycle, both were supplied by the Swedish company ABB and the power is transferred
from the station site via fourteen high voltage lines connected to the national grid in the
Kurdistan region.
This document is the property of Al-Jaber International Company. Any copying and distribution of this document
without the approval of the Management is prohibited. Page 4 of 9
Al-Jaber International Company
Procedure System of
SITE QMS TRAINING
Original Issue Date: Revision Issue date:
Doc. No: AJB-SQT-PR-01 Issue Number: 01 Revision Number: 01
01st January 2016 14th August 2018
3. PURPOSE
This procedure defines the work process for planning, implementing and documenting the
trainings of MG-DC-JV ECP project members.
4. RESPONSIBILITIES
This document is the property of Al-Jaber International Company. Any copying and distribution of this document
without the approval of the Management is prohibited. Page 5 of 9
Al-Jaber International Company
Procedure System of
SITE QMS TRAINING
Original Issue Date: Revision Issue date:
Doc. No: AJB-SQT-PR-01 Issue Number: 01 Revision Number: 01
01st January 2016 14th August 2018
5. REFERENCE DOCUMENTS
6. PROCEDURE
This document is the property of Al-Jaber International Company. Any copying and distribution of this document
without the approval of the Management is prohibited. Page 6 of 9
Al-Jaber International Company
Procedure System of
SITE QMS TRAINING
Original Issue Date: Revision Issue date:
Doc. No: AJB-SQT-PR-01 Issue Number: 01 Revision Number: 01
01st January 2016 14th August 2018
7. ATTACHMENTS
This document is the property of Al-Jaber International Company. Any copying and distribution of this document
without the approval of the Management is prohibited. Page 7 of 9
Al-Jaber International Company
Procedure System of
SITE QMS TRAINING
Original Issue Date: Revision Issue date:
Doc. No: AJB-SQT-PR-01 Issue Number: 01 Revision Number: 01
01st January 2016 14th August 2018
This document is the property of Al-Jaber International Company. Any copying and distribution of this document
without the approval of the Management is prohibited. Page 8 of 9
Al-Jaber International Company
Procedure System of
SITE QMS TRAINING
Original Issue Date: Revision Issue date:
Doc. No: AJB-SQT-PR-01 Issue Number: 01 Revision Number: 01
01st January 2016 14th August 2018
This document is the property of Al-Jaber International Company. Any copying and distribution of this document