July 2017 Eco
July 2017 Eco
July 2017 Eco
QUESTION 2
a) i) Differentiate Tender Price Index and Building Cost Index
TPI
- Indicates tender price of building works.
- Compiled by comparing tender rates from acceptable tenders with Base Schedule
Rates
- An output index that measures the changes in tender price
- It measures he difference in the sum paid by the client
- The index is calculated in consideration of building and/or construction cost,
changes in market conditions, types of contract, inflation, profit and overhead
- The best index which should be used by QS because the client is more interested in
how much he has to pay to the contractor
- Currently prepared and published by JKR – twice a year
- Source of TPI is from the tender document itself, priced tenders by contractors
BCI
- Index for resources like plant, material and labour.
- The average index can only be prepared if cost of each resource of typical building is
monitored over time
- Cost index is an input index that measures changes over time in resource cost such
as labour, plant and material.
- Cost index is usually used by contracts to measure the changes in cost which is spent
by the contractor
- Cost index can be prepared for the total cost of building or type of building to reflect
general increase in cost.
- Difficult to apply cost index to reflect total cost of building due to numerous
methods of construction, variety of materials used and types building
- Sources of cost index – department of statistics, Malaysia produced monthly (Special
release 1 and Special release 2)
b) 3 major documents for preparation of ECA. Describe information extracted from the
documents.
Contract documents
- BQ
- List of prime cost sums
-
-
Working drawings and the specifications
- Calculate the quantity factor and others
-
-
Tender report
- the market,
- number of tenderers etc
-
QUESTION 4
a) Approximate estimating
i) 4 nos panel door size 900mm x 2100mm
Information
Door leaf 900mm x 2100mm – rm 320/no
Door frame – rm10/m
Painting to door leaf – rm15/m2
Painting to frame – rm7/m
Door frame
0.90
2/2.10
5.10 @ 10.00 51.00
Painting
Door leaf
0.90 x 2.10
1.89 @ 15.00 28.35
Door frame
5.10 @ 7.00 35.70
4/435.05
1740.20
To collection 1740.20
ii) 4.50mm x 6.00mm internal clg finishes – asbestos free cement sheet
Information (idk how to do this one)
Clg panel size 1200mm x 2100mm – rm320/no
Clg joist 100mm x 50mm @ 600mm span – rm 7/m
Spacer 50mm x 50mm @ 1200mm across clg joist and 6—mm along clg joist
– rm/5
Painting -rm 12/m2
Beading (all around the clg area) 15mm x 25mm – rm 2/m
b) Unit method is used by QS at preliminary stage. Explain the situation when this
method is suitable, how it is applied and give reasons why QS seldom use this
method
- This method is used to estimate the cost of building whose sizes depend upon the
units of accommodation e.g. number of pupils in schools, number of beds in
hospital, number of seats in cinemas, number of car spaces in carpark
- Unit method is also referred as cost to building function
Application
- The number of units of accommodation may be given by the building owner or
otherwise determined.
- This number of units is then multiplied by the unit rate per unit accommodation to
arrive at the approximate cost of the building
- For example, if from historical data, i.e. cost information of past projects, the cost
per pupil of schools is rm1000 and proposed school to accommodate 500 pupils is to
be erected, then the approximate cost of the proposed school will be rm1000 x 500
= rm500000, if the proposed buildings is identical to the building whose unit rate has
been used
Why QS uses this method
- It is a simple method of comparison
- It is a suitable form of long term estimating for large programmes of similar buildings
where variations in individual buildings will cancel each other out
- Provides a convenient form of stating a cost limit or budget.
QUESTION 5
a) Factors affecting price level
1. Difference in general market price
2. Variation between the contractor’s price level and general market price level at
tender date
3. Difference in site conditions and locations
4. Difference in contract condition, weather conditions and the like
b) Explain the rules of controlling variation works during post-contract stage adopted by
public sectors
- Variation must be kept to a minimum. Efforts must be made to resist variation.
Request for variation must be in writing
- Variation works must be scrutinized to see if it is really required. If variation cannot
be avoided, possibility of having it executed by other means must be considered
- Only works if executed by other means which will cause disturbance to the regular
progress and completion of work by contractor to be executed on variation
- The scope and extent of extra work ordered must be within the contract. Work
omitted must be really not required. Work included cannot be omitted to be
executed by others.
- No variation work ordered after date of completion or after extended date
- No variation shall be ordered until the effects on contract sum and the regular
progress of work by contractor has been evaluated, necessary prior approval by
treasury, necessary funds have been approved.