Deep Foundations: Limit State Design, Tensile Load and Load Tests
Deep Foundations: Limit State Design, Tensile Load and Load Tests
Deep Foundations: Limit State Design, Tensile Load and Load Tests
Q bu Qsu
R (9.12a)
g RC
or
Q bu Qsu
R (9.12b)
g Rb g Rs
Design Approach 3
Combination : (A1 or A2) “+” M1 “+” R3
A1 :on structural actions
A2 :on geotechnical actions
Lp - 15
200 kPa 200 kPa
Q bu , des
A p sc N cc u 2, des gL p
gRb
For d/B 0, sc N c 6.2 from Figure 8.10
0.752
6.2 200 18 15
Q bu , des 4 334 kN
2.0
c
For non - displacement piles, 1.16 - u for 30 c u 150
185
D0 L pc u1, des 0.75 15 0.62 100
Qsu, des 1370 kN
g Rs 1.6
To satisfy ULS :
g A Q A self - weight of pile R
g A Q g concA p L p R
0.752
1.0 Q 24 15 1704
4
Q 1545 kN
0.75 15 0.62 100 L p 15 0.35 200
1.6
1370 103 L p 15
103L p 205
3000 10.6L p 391 4.42L p 103L p 205
3000 10.6L p 186 107.42L p
96.8L p 2814
L p 29 m
Check : d/B (29 - 15)/0.75 18.7, s c N c 9.0 is O.K.
where q c average cone resistance over 1.5D 0 above and below the base of the pile.
Compression
Tension
Uplift
Fig. 9.15 Shaft friction in tension: (a) a for non-displacement piles in fine-grained soil,
(b) shaft resistance for non-displacement piles in coarse-grained soil.
Trial piles are piles which are constructed solely for the
purposes of load testing, usually before the main piling
work commence. If sufficient load can be applied, these
piles can be tested to the ULS to verify the pile capacity.
Fig. 9.16 Static load testing of piles: (a) using kentledge, (b) using reaction piles.
1.Load to 100% of the design (working) load, also called the design
verification load in 25% increments;
2.Unload fully in 25% increments;
3.Reload directly to 100% design verification load, then load to 150% of
the working load (also called proof load) in 25% increments;
4.Unload fully in 25% increments
1/Pult =0.000375
0.008
0.006
0.004
0.002
0
0 5 10 15 20 25
Settlement (mm)
Chin' s method :
1
Pult 2665 kN
0.000375
R avg R min
R k min ,
1 2
(Coduto 2001)