Contractors Guide Seweracc16
Contractors Guide Seweracc16
Contractors Guide Seweracc16
construction
guide
2 United Utilities Site Sewer Construction Guide United Utilities Site Sewer Construction Guide 3
Safety in sewers and excavations Safety in sewers and excavations
4 United Utilities Site Sewer Construction Guide United Utilities Site Sewer Construction Guide 5
Manhole chambers Manhole chambers
6 United Utilities Site Sewer Construction Guide United Utilities Site Sewer Construction Guide 7
Manhole chambers Manhole chambers
8 United Utilities Site Sewer Construction Guide United Utilities Site Sewer Construction Guide 9
Manhole chambers Manhole chambers
Manhole rings and step irons Cover slabs and access openings
Manhole rings must be The distance from ground level For 600 x 600mm square openings on 750mm
seated on a mortar bed and to the 1st step or ladder rung 1050mm diameter chamber rings and above,
adequately pointed to prevent must be no more than 675mm. United Utilities Standard Detail Specification
the ingress of ground water. Remember the top step must is that a 600 x 750 mm cover slab is fitted,
Alternatively, proprietary be a minimum of 150mm from reduced to a 600 x 600mm square opening
bitumen or mastic bedding the underside of the cover by the use of an eccentric raising piece to suit
600mm
materials can be used. slab. A site engineer should set the manhole cover and frame used.
Manhole ring lifting eyes must out the cover slab levels prior
Generally, where manhole chambers are
be pointed flush with the to construction so that this
between 1.5 – 3.0m deep from finished
chamber walls. specification is achieved.
ground level to benching landing area, a
In areas of traffic loading, high 600 x 600mm clear unobstructed opening is
ground water table levels or normally suitable.
Positioning of cover slab
contaminated ground, 150mm Where chambers are less than 1.5m deep
GEN 3 concrete surrounds to from finished ground level to benching
manhole chambers must be landing area, consideration should be given
provided. Alternatively, wide to accessing and carrying out maintenance
wall rings can be considered. activities within the chamber.
600mm
The step rungs must be plumb,
For 1050mm and 1200mm diameter rings less
in vertical alignment and
than 1.5m deep to benching, 750 x 750mm
equally spaced, leading to a
covers shall be fitted.
landing area of a minimum area
675mm
of 600 x 600mm square from (max)
For 1500mm diameter rings less than 1.5m
the edge of the main channel to deep to benching, 1200 x 675mm covers shall 600mm
the chamber wall. be fitted.
Please note, cover slabs must not be cut With opening reduction
Ladders to increase opening dimensions as this will
significantly weaken the cover slab.
Stainless
steel ladder
To maintain a
Ring chamber walls 600 x 600mm square
clear opening, the
step rungs or ladders
must be plumb and
in alignment with the
cover slab opening.
10 United Utilities Site Sewer Construction Guide United Utilities Site Sewer Construction Guide 11
Manhole chambers Manhole chambers
12 United Utilities Site Sewer Construction Guide United Utilities Site Sewer Construction Guide 13
Manhole chambers
Pipes and bedding
Manhole cover and frames Before final surfacing, it is recommended Sewer pipes Protection of sewers
that all frames are checked for alignment
Sewers for Adoption specifies that all and sound bedding. Resetting frames and and bedding Sewers located within highway or areas of
manhole frames located in adopted highways associated reinstatement can be costly, time specification traffic should have 1.2m of cover. In other
must be a minimum of 150mm deep and only consuming and spoil the appearance of a areas, 0.9m of cover is required. Where this
100mm frames are permitted in residential newly surfaced area. Pipes used on main adoptable is not possible, a full protective concrete bed
cul-de-sacs. Covers must be Kitemarked sewer lengths must comply and surround must be provided, inclusive of
and comply with BS EN124 with Class with Sewers for Adoption specification. flexible joints.
D400 covers used in all areas used by road Should there be any queries as to the
vehicles. It is however recommended that all suitability of materials, these should be Pipe bedding
cover and frames subject to traffic loading clarified before construction. Vitrified clay
pipes should comply with requirements BS Pipes must be evenly bedded along
have 150mm deep cover and frames fitted.
EN 295 for foul pipes and BS 65 for surface the length of the pipe. Under normal
Should you have any queries with regards to
water pipes. circumstances, United Utilities’ specification
the suitability of manhole covers and frames,
for the bedding of pipes is Class S, full bed
please clarify the requirements with United Thermoplastic structural walled pipes must and surround for rigid, semi rigid and flexible
Utilities. comply with Water Industry Standard 4-35-01 pipe materials. Please consult with the pipe
Inappropriate bedding of manhole frames and achieve Class 8k/Nm2 nominal short term manufacturer’s recommendations and agreed
often leads to movement of both the ring stiffness. Please note, not all structural drawings.
manhole cover within the frame and the walled pipes meet this specification and
disintegration of the surrounding ground, pipes which do not meet these requirements
especially in trafficked areas. are unacceptable. Pipes must be Kitemarked
Generally covers must be bolted together or have a similar E.U. certification mark.
with manhole key holes free from debris and
ready for inspection. Handling and storage of
Block paved or masonry inset covers must
pipes
not be installed on United Utilities public Pipes are expensive and should be handled
sewerage apparatus. with care and stored safely in flat areas,
away from excavations, stacked no greater
than manufactures recommendations. In
particular, PVC pipes should be stored on
surfaces that prevent distortion of both the
pipe circumference and linear profile.
Recycled pipe bedding
materials
Manhole covers must be correctly selected in
accordance with the given location and must Recycled materials must comply with
be correctly seated in alignment with the BS 8500-2.
adjusting brick work or raising pieces below.
14 United Utilities Site Sewer Construction Guide United Utilities Site Sewer Construction Guide 15
Pipes
Testing of sewers
Laying and jointing of pipes Backfilling Sewers up to 750mm diameter must be
available for testing either by air or water.
CCTV surveys
Pipes should be laid in 3m maximum lengths Pipes should be backfilled and compacted All sewers proposed for adoption must
with the joints ‘pushed home’ into sockets. in 150mm layers to 300mm above the Air testing be inspected by CCTV survey. For sewers
Furthermore, care must be taken to ensure pipe crown. Care should be taken during subject to a S104 Agreement, United
For air testing, the sewer must hold a head
the pipe jointing seals are free from grit, silt compaction so that the sewer remains in Utilities will survey the sewers. In advance
from 100mm to a minimum of 75mm for
etc. which will likely cause the pipe length to good line and level, in particular adjacent to of the CCTV survey, it is the developer’s
5 minutes once the pressure is initially
fail later air testing. It is recommended that manhole chambers to prevent rocker pipes responsibility to ensure that sewers are
stabilised.
sewers are air tested at regular intervals as being pushed down from stub pipes. suitably cleansed otherwise the survey work
pipes are laid.
Water testing will be abandoned.
Pipes should be cleanly cut, be free from Thermoplastic pipes are also subject to
The sewer should be filled with water to
defects and laid without back fall and dips. profile laser light-line surveying which
provide 1.2 – 6.0m head of water above the
It is recommended that sewers are laid using measures any deformation within the
soffit of the pipes at the highest point. To
pipe lasers to achieve a single consistent pipeline. Pipes with deformation in excess of
allow for absorption, after 2 hours water
gradient. Where there is little fall such as 5% must be replaced.
should be added at 5 minute intervals and
gradients up to 1:150 extra care should be
the volume of water required to keep the For sewers subject to S185 Sewer
taken to prevent dips.
water at the initial level recorded. The rate of Diversion Agreements, it is the developer’s
Back laying of pipes should be avoided where water loss must not exceed 0.5 litres / per 30 responsibility to provide CCTV footage of
possible as level errors and the positioning minutes / metre diameter / linear metre. cleansed sewers before flows are diverted.
of unforeseen existing services may require However, CCTV surveys recorded during the
corrective measures which can be either jetting works or surveys of dry pipelines are
expensive or impossible to rectify. not suitable as an indication of the level of the
pipe can not be achieved.
Please note, pipe defects, dips, back fall and
poor jointing highlighted by these surveys will
need to be repaired.
16 United Utilities Site Sewer Construction Guide United Utilities Site Sewer Construction Guide 17
Connections Connections
Soffit of new
connection level
with soffit of
main channel
18 United Utilities Site Sewer Construction Guide United Utilities Site Sewer Construction Guide 19
Connections Access
Pre-formed junction Back drop connections Bespoke or manhole
connections Generally, internal backdrop connections are chambers for storage
Oblique preformed junctions only must be not permitted. Should an external backdrop systems
installed using proprietary couplings. have a high risk of blockages, a rodding
point extending to ground level should be Chamber ring diameters should be selected
‘T junctions must not be used. on size of manhole inlets and outlets and
provided.
Openings in the existing sewer must be should also be able to accommodate the
squarely and accurately cut, free from rough Remember, once connections have been number of connections, associated channels
edges. The installed fitting should be in good made, please leave the area exposed for and provide a minimum 600mm x 600mm
alignment with the existing sewer. inspection by United Utilities. landing area.
For 600mm diameter pipes and above,
where benching and a landing area is
constructed 50% diameter above invert,
a 500mm x 150mm recess must be cast
within the manhole base, for step irons to be
installed to lead down to the main channel
invert.
Handrails must also be installed to United
Utilities Standard Detail Specification.
Core-drilled saddle
connections
All saddle connections must be core-drilled.
Please note, forming openings using circular
cutting wheels weakens the pipe and causes
structural defects.
20 United Utilities Site Sewer Construction Guide United Utilities Site Sewer Construction Guide 21
Access Typical surface water flow control
manhole
Alternative access arrangements for larger diameter
surface water sewer manholes Minimum 600 x 600mm
square landing area must High level overflow Integral bypass wire and handle
remain dry during normal not always required - fitted in position accessible from
For 600mm diameter surface water sewers see agreed drawings ground level, below cover.
dry weather conditions.
and above with headroom limited to 2m or
less, suitable access into the channel can
be achieved by a forming a recess within
the manhole base, with step rungs installed
leading down to a landing area formed and
finishing at a point 150mm above channel
invert. Step rungs must be plumb and vertical
alignment as shown below.
Sump
WIDTH 600MM
Channel formed.
Sump (adhere
to flow control
manufacturer’s
recommendations).
Bypass sewer
constructed for the
event of flow control
blockages, in addition
to unit integral
Step rungs in plumb and vertical alignment bypass.
equally distanced apart.
Fully operational penstock
fitted to rising type spindle.
22 United Utilities Site Sewer Construction Guide United Utilities Site Sewer Construction Guide 23
Fixings and rails Other information
Metal fixings and Typical 1:20 manhole details
chains Typical
TYPICAL foul
FOUL water
WATER manhole
MANHOLE Typical SW
TYPICAL SW storage
STORAGE manhole
MANHOLE (≥3m
(≥3m deep deep to soffit)
to soffit)
Safety chains
Safety chains are required
on sewer outlets greater
than 525mm internal
diameter. The chain must
be 8mm diameter and made
from stainless steel.
24 United Utilities Site Sewer Construction Guide United Utilities Site Sewer Construction Guide 25
Other information
26 United Utilities Site Sewer Construction Guide United Utilities Site Sewer Construction Guide 27
United Utilities Wastewater Developer Services and Planning
Warrington North Wastewater Treatment Works
Barnard Street off Liverpool Old Road
01/16/SD/6805