5.4.1 Create WBS: Inputs 5.4.1.1 Scope Management Plan
5.4.1 Create WBS: Inputs 5.4.1.1 Scope Management Plan
5.4.1 Create WBS: Inputs 5.4.1.1 Scope Management Plan
The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project
team to accomplish the project objectives and create the required deliverables. The WBS organizes
and defines the total scope of the project, and represents the work specified in the current approved
project scope statement.
The planned work is contained within the lowest level of WBS components, which are called work
packages. A work package can be used to group the activities where work is scheduled and
estimated, monitored, and controlled. In the context of the WBS, work refers to work products or
deliverables that are the result of activity and not to the activity itself.
•Verifying that the degree of decomposition of the deliverables is appropriate. A portion of a WBS
with some branches of the WBS decomposed down through the work package level is shown in
Figure 5-11.
Figure 5-11
Figure 5-11. Sample WBS decomposed down through Work Packages
A WBS structure may be created through various approaches. Some of the popular methods include
the topdown approach, the use of organization-specific guidelines, and the use of WBS templates. A
bottom-up approach can be used during the integration of subcomponents. The WBS structure can
be represented in a number of forms, such as:
•Using phases of the project life cycle as the second level of decomposition, with the product and
project deliverables inserted at the third level, as shown in Figure 5-12;
•Using major deliverables as the second level of decomposition, as shown in Figure 5-13; and
•Incorporating subcomponents which may be developed by organizations outside the project team,
such as contracted work. The seller then develops the supporting contract WBS as part of the
contracted work.
Figure 5-12
Figure 5-13
Decomposition of the upper-level WBS components requires subdividing the work for each of the
deliverables or subcomponents into its most fundamental elements, where the WBS components
represent verifiable products, services, or results. The WBS may be structured as an outline, an
organizational chart, or other method that identifies a hierarchical breakdown. Verifying the
correctness of the decomposition requires determining that the lower-level WBS components are
those that are necessary and sufficient for completion of the corresponding higher-level
deliverables. Different deliverables can have different levels of decomposition. To arrive at a work
package, the work for some deliverables needs to be decomposed only to the next level, while
others need additional levels of decomposition. As the work is decomposed to greater levels of
detail, the ability to plan, manage, and control the work is enhanced. However, excessive
decomposition can lead to nonproductive management effort, inefficient use of resources,
decreased efficiency in performing the work, and difficulty aggregating data over different levels of
the WBS.
Decomposition may not be possible for a deliverable or subcomponent that will be accomplished far
into the future. The project management team usually waits until the deliverable or subcomponent
is agreed on, so the details of the WBS can be developed. This technique is sometimes referred to as
rolling wave planning.
The WBS represents all product and project work, including the project management work. The total
of the work at the lowest levels should roll up to the higher levels so that nothing is left out and no
extra work is performed. This is sometimes called the 100 percent rule.
For specific information regarding the WBS, refer to the Practice Standard for Work Breakdown
Structures – Second Edition [7]. This standard contains industry-specific examples of WBS templates
that can be tailored to specific projects in a particular application area.
•Project scope statement. The project scope statement includes the description of the project
scope, major deliverables, assumptions, and constraints.
• WBS. The WBS is a hierarchical decomposition of the total scope of work to be carried out
by the project team to accomplish the project objectives and create the required deliverables. Each
descending level of the WBS represents an increasingly detailed definition of the project work. The
WBS is finalized by assigning each work package to a control account and establishing a unique
identifier for that work package from a code of accounts. These identifiers provide a structure for
hierarchical summation of costs, schedule, and resource information. A control account is a
management control point where scope, budget, actual cost, and schedule are integrated and
compared to the earned value for performance measurement. Control accounts are placed at
selected management points in the WBS. Each control account may include one or more work
packages, but each of the work packages should be associated with only one control account. A
control account may include one or more planning packages. A planning package is a work
breakdown structure component below the control account with known work content but without
detailed schedule activities.
• WBS dictionary. The WBS dictionary is a document that provides detailed deliverable, activity,
and scheduling information about each component in the WBS. The WBS dictionary is a document
that supports the WBS. Information in the WBS dictionary may include, but is not limited to:
○ Description of work,
○ Responsible organization,
○ Schedule milestones,
○ Resources required,
○ Cost estimates,
○ Quality requirements,
○ Acceptance criteria,
○ Agreement information.
Matrix organizations, as shown in Figures 2-2 through 2-4, reflect a blend of functional and
projectized characteristics. Matrix organizations can be classified as weak, balanced, or strong
depending on the relative level of power and influence between functional and project managers.
Weak matrix organizations maintain many of the characteristics of a functional organization, and the
role of the project manager is more of a coordinator or expediter. A project expediter works as staff
assistant and communications coordinator. The expediter cannot personally make or enforce
decisions. Project coordinators have power to make some decisions, have some authority, and
report to a higher-level manager. Strong matrix organizations have many of the characteristics of the
projectized organization, and have full-time project managers with considerable authority and full-
time project administrative staff. While the balanced matrix organization recognizes the need for a
project manager, it does not provide the project manager with the full authority over the project
and project funding. Table 2-1 provides additional details of the various matrix organizational
structures.
At the opposite end of the spectrum to the functional organization is the projectized organization,
shown in Figure 2-5. In a projectized organization, team members are often colocated. Most of the
organization’s resources are involved in project work, and project managers have a great deal of
independence and authority. Virtual collaboration techniques are often used to accomplish the
benefits of colocated teams. Projectized organizations often have organizational units called
departments, but they can either report directly to the project manager or provide support services
to the various projects.
Many organizations involve all these structures at various levels, often referred to as a composite
organization, as shown in Figure 2-6. For example, even a fundamentally functional organization may
create a special project team to handle a critical project. Such a team may have many of the
characteristics of a project team in a projectized organization. The team may include full-time staff
from different functional departments, may develop its own set of operating procedures, and may
even operate outside of the standard, formalized reporting structure during the project. Also, an
organization may manage most of its projects in a strong matrix, but allow small projects to be
managed by functional departments.
Many organizational structures include strategic, middle management, and operational levels. The
project manager may interact with all three levels depending on factors such as: