TG9 - 18 Guide To The Design and Construction of Temporary Roofs and Buildings
TG9 - 18 Guide To The Design and Construction of Temporary Roofs and Buildings
TG9 - 18 Guide To The Design and Construction of Temporary Roofs and Buildings
TG9:18
Guide to the design and construction of
temporary roofs and buildings
NASC
2 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 3
INDEX
1. Introduction
2. Scope
3. Management considerations
4. Types of construction
5. Components
6. Design methods
NASC
3 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 4
1. INTRODUCTION
A temporary roof or building is a sheeted structure designed to provide cover over an area from the effects of
weather, dust, etc. It may stand on the ground or on top of a building or be an extension of a scaffold round
a building. It may have fully sheeted walls and roof or only a roof or a roof with skirts.
This guide is intended to give design and construction information to designers and suppliers of temporary
roofs and buildings constructed with scaffolding materials.
It is not a comprehensive design guide but covers some of the more basic requirements and considerations
that should be made to provide an economical, but safe, completed temporary structure.
The usual types of sheeting employed for temporary buildings are as follows:
a) corrugated steel or corrugated aluminium;
b) flexible plastics;
c) flexible plastics covered panels.
For welding screens and other places where there is a fire hazard, corrugated steel sheeting should be used.
For structures with a very limited life, for example: at sports arenas and exhibitions, fixing cords of known
breaking strength may be used with flexible sheeting to cater for excessive gust wind speeds.
This guide replaces all previous versions of TG9 and takes into consideration BS EN 16508.
NASC
4 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 5
2. SCOPE
Whilst excluded from this guide, these structures will still require specialist design considerations.
NASC
5 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 6
3. MANAGEMENT CONSIDERATIONS
A Full Risk Assessment and Method Statement should be prepared for all installations.
Where a temporary roof is standing on an existing roof or anchored to building, the principle contractor must
ensure that the structure can adequately withstand the additional imposed loads.
Check for hidden services that are likely to cause a problem with loads from standards or kentledge.
Where anchoring to a building is not permitted, ensure that sufficient space is available for buttressing.
The safe method of moving materials to site and to the actual place of installation.
The method of access to the place of the installation for erecting/dismantling and inspection.
The management and protection for members of the public and the workforce of other contractors.
Roof cover
100%
Partial cover – Re-erect or rolling
Sections requiring opening for lowering in of materials etc.
Training of workforce
Ensure that specific training is carried out for the selected roofing system and method of erecting and
dismantling.
NASC
6 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 7
4. TYPES OF CONSTRUCTION
Any of the above types of structure, may be constructed as static structures, mobile or as ‘telescopic’
arrangements (one roof passing over another)
Flexible Sheeting
• Purpose-made sheeting (PVC, Polythene etc) which may be fixed down to beams by various
methods or pulled through and retained by a purpose-made slot in the roof beams (commonly known
as ‘keder’)
NASC
7 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 8
5. COMPONENTS
Figure 5
Prefabricated steel beams are generally warren trusses with 48.3mm diameter chords at approximately
600mm centres. They are available in various standard unit lengths and are connected end to end by 2 or 3
bolts and a spigot at each gusset joint.
The load carrying capacity depends mainly on the frequency of restraint to the compression chord. Guidance
should be sought from the beam supplier for the actual load carrying capacities. Generally, if chords are tied
at the node positions (1.2m approx. intervals) then the maximum bending moment is normally in the range of
12 to 27 kN.m.
It is important that lateral restraint in the form of bracing is provided. Generally this bracing will be required
every 5th bay.
Note: depending on the loading conditions, the compression chord may be either top or bottom chord.
Figure 5 illustrates the use of bracing to achieve stability for groups of prefabricated beams. Generally this
bracing will be required in every 5th bay.
Lacing and bracing may be effected by the use of system components or tube & couplers.
The load carrying capacity largely depends on the frequency and type of restraint to the compression chords.
Guidance should be sought from the supplier/manufacturer for the actual capacities prior to carrying out detail
design.
NASC
8 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 9
It is important that lateral restraint in the form of bracing is provided. Generally this bracing will be required
every 5th bay.
Note depending on the loading conditions, the compression chord may be either top or bottom chord.
Since there is a wide range of this type of beam, with a wide range of properties, it is recommended that the
designer clearly indicates the specific beam used in the design drawing.
Corrugated steel sheets are normally placed and fixed in-situ at roof level with the appropriate safety
measures in place to minimise the risk and consequences of a fall.
For normal use, the recommended sheeting is 22 gauge or 24 gauge thickness. Under no circumstances
should sheeting of thickness less than 26 swg be used.
The design should indicate positions of purlins and overlay tubes and their corresponding couplers. Particular
attention should be paid to those areas subject to increased wind pressures etc.
Figure 8
NASC
9 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 10
NASC
10 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 11
6. DESIGN METHODS
The structure should be designed in accordance with recognized engineering principles and should take into
account the variability of materials, workmanship, site conditions and construction tolerances.
Temporary works systems should be designed with regard to the ease and safety of erection and dismantling.
The designers and suppliers should provide appropriate guidance on the sequence of erection and
dismantling of their design.
The designer will be expected to have considered the buildability of the structure and the design should take
account of the methods of construction. The designer should also provide the relevant information – with
regard to the significant risks involved in its construction.
The layout of the structure should be such that there is a well-defined system for transferring the loads to the
ground. When the form of the design has been chosen, the various structural elements and joints should be
designed and constructed so that the elements themselves and the rigidity of the joints between them are
adequate for their purposes and are used in accordance with the manufacturer's recommendations.
The assembly as a whole should be stable against sliding and sway due to wind forces with a factor of safety
of 1.3 and against overturning with a factor of safety of 1.2. Wind loads should be calculated.
The cross fall of the roof should be such that rain water will be readily shed. The lateral thrusts derived from
arched or ridged roofs should be taken into consideration in the design and construction. In the case of
steeper ridged roofs, ties designed and inserted for this purpose should take the thrust.
The roof drainage arrangements should be agreed between the designer and the user. Gutters should have
a fall of not less than 1 vertical to 100 horizontal. The rain water pipes should be in agreed locations and tied
securely to the structure.
The load resulting from transverse wind forces may be taken account of by the incorporation of suitably stiff
framing and by a means for transferring the local wind loading to it.
The overturning of the structure as a whole may be prevented by ground anchors or kentledge round the
perimeter or by guys and anchors.
If the forces in the knee bracing and in the braces to tube and fittings trusses are too large to be resisted by
one coupler, then supplementary couplers should be added or the fittings pinned with shear pins. When
couplers interfere with the sheeting, a secondary rafter and raised purlins should be added above the truss to
carry the sheeting.
Longitudinal bracing should be inserted in the long walls and transverse bracing in the end walls or end gable.
Plan bracing should be inserted in the roof structure.
When the temporary building is an extension to an access scaffold, the bracing and tying of this access
scaffold should be supplemented as necessary. The effect of the horizontal forces on the walls of the building
should be considered.
When a temporary building or roof is constructed on the top of an existing building, the anchor points should
be suitable to resist the loads imposed upon them.
NASC
11 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 12
The overall roof and the side support scaffolds could be subjected to uplift and joints in the uprights and knee
braces may need to be strengthened by lapping. If the scaffolding structure is of insufficient self weight to
resist the uplifts, as may be the case in a low height, long span roof, then additional resistance must be
provided by anchors, tubes under window heads, kentledge or similar. Overturning and side sway of the total
structure must also be considered to determine the worst combinations of loads.
Any untied, free standing structure may need a buttressed scaffold system with anchors at foundation level
on any buttress lines and should be the subject of detailed design.
Particular attention should be given to the design and detail of the anchors. Refer to NASC Guidance TG4
(Anchorage systems for scaffolding) and TG16 (Anchoring to the ground).
To ensure that servicabilty limits are not exceeded, these loads must be considered in the most onerous
combinations to produce the worst effect on an element or on the structure as a whole.
Note: these loads should be applied in their true directions;
ie. wind loads should be applied perpendicular to the surface,
gravity loads can only act vertically downwards.
Mobile temporary structures may be subject to an overall uplift due to wind pressure. Consideration should
therefore be given to providing kentledge or other means of tying down such structures.
NASC
12 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 13
NASC
13 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 14
LC 1 LC 2 LC 3 LC 4 LC 2a LC 2b LC 3a LC 3b LC 4a
Q1 Dead loads 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
Q2 Working loads – 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
Q3 Other imposed
– 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
loads
Q6 Reduced snow
– – 1.0 – – – 0.5 1.0
load
NASC
14 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 15
Truss
Side
Sheeting
Tie
(b) A gable end where the supporting scaffold is not available or is unnecessary.
Plan girder
Side
Sheeting
NASC
15 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 16
7.1. Design
(A) Has a feasibility study been carried out from a site visit?
(B) Is the designer fully familiar with the product being used in the design?
(C) Is there a full job specific design complete with working drawing and calculations?
(F) Does the design confirm specifications and origin of authorised manufacturer’s loading data for
components used?
(G) Do the proprietary system components used meet with the NASC Code of practice for the hire, sale and
use of system scaffolds?
(H) Can the designed structure be built/dismantled in accordance with manufacturer’s recommended safe
system of work? (User guide)
(J) Has a Design Risk Assessment been carried out and documented to identify significant hazards, in
particular, those associated with overall stability of the structure during the erection/dismantling stages
and minimizing risks of working at height.
7.2. Construction
7.2.1 Method statement
State method for:
(A) For erecting (and dismantling) by trained operatives?
(D) Precautions to be taken when weather conditions may prevent safe working?
NASC
16 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 17
NASC
17 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 18
NASC
18 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 19
With the introduction of the work at height regulations in 2005 (WAHR) have come new duties and
responsibilities affecting many aspects of scaffolding and access. The methods employed to build temporary
roofs are coming under increasing scrutiny in view of the high risk element involved with all of these structures.
AVOID WORK at This is unlikely to be an entire solution but there may be scope for reducing the
HEIGHT amount of working at height.
eg. Assembling sections on the ground and lifting into position.
PREVENT FALL 1. Can the roof be erected entirely from fully guarded platforms?
BY COLLECTIVE 2. Can the roof be built using MEWPs or independent towers?
EQUIPMENT 3. Can the roof design be chosen where most of the work can be carried out
from fully guarded platforms, rather than relying on harnesses? eg. A system
roof where the covering can be pulled across from the scaffold platforms,
rather than a CI roof which has to be worked on in order to install the sheets.
PREVENT FALL If personal fall protection equipment has to be relied on, consider the use of
BY PERSONAL lanyards which would provide work restraint rather than a fall arrest system
WORK (ie it stops the person actually reaching an open edge at all).
EQUIPMENT Location and adequacy of anchor points need careful consideration.
Operatives must be anchored to separate components.
MITIGATE THE eg. Nets below the working areas (if suitable anchor points are available and the
EFFECT OF nets themselves can be fitted safely)
FALL BY USING
COLLECTIVE
MEASURES
MITIGATE THE This is the last resort, and includes fall arrest lanyards. A detailed, job-specific
EFFECT OF method statement should be prepared: the risks are high and demand a
FALL BY USING proportionate level of planning, training and supervision. The location and
PERSONAL adequacy of anchor points need careful consideration. The type of lanyard
MEASURES should be suitable eg. twin lanyards for traversing beams (see SG4). Harness
inspection regimes should be robust (see HSE leaflet INDG367). Rescue
procedure should be in place. Adequate supervision to ensure personal fall
protection equipment is used correctly.
Operatives must be anchored to separate components.
The effect of the Regulations is not to exclude particular methods but they do put pressure on those traditional
methods to justify a compliant safe method of building in-situ compared to more modern proprietary systems.
This can be demanding.
For details of Safe Systems of Work the appropriate Safety Guidance should be followed.
NASC
19 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 20
However, there are other issues that influence the ability to build temporary roofs safely, which include:
• Job specific risk assessment
• A job-specific design aimed at eliminating/reducing the risk of fall and other hazards identified by the
risk assessment.
• Scaffolders should be fully trained in the equipment used, with proof of training.
• The designer should be fully familiar with the equipment selected.
• For proprietary temporary roof systems, erection / user guides on the selected method should be
provided by the supplier.
• If personal fall arrest is utilised, with twin lanyards, job-specific rescue plan must be provided. Anchor
points should be determined for adequacy.
• A materials handling plan should outline the procedure for getting the materials to the workplace, both
to the scaffold working platform and their final fixed position on the roof.
• A job specific method statement developed from the above.
NASC
20 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 21
B.1 Properties
Table B1
When a specification requires a fully watertight roof, it may be necessary to seal the joints with suitable mastic
or sealing strip.
Side laps are usually 1½ to 2 corrugations wide, and as with end laps, may require some form of mastic or
sealant when a watertight roof is specified. It may be necessary to consider having various sheet widths
available (10/3 & 12/3) to overcome overlay tube sheeting couplers clashing with roof beam purlin fixings.
At the edges of the roof where the pressure co-efficient is high, it may be necessary to stitch the side laps
together. This can be carried out using either pop rivets, self tapping screws, blind fixings or as a last resort
nuts and bolts. These fixings would normally be placed at 450mm c/c.
Some contracts may specify the requirement for the provision of natural light whilst also remaining waterproof.
Natural lighting can be achieved using translucent sheeting where the corrugation sizes are compatible with
those of the steel sheets.
When using this form of sheeting, either by itself or in conjunction with steel sheeting, it will be necessary to
check the following points:
Compatibility with the steel sheeting used for the remainder of the roof.
Durability – Effects from sunlight etc.
Strength – This should be looked at in two ways:
G Span between purlin members – It may be necessary to reduce the spacing between
the purlins.
NASC
21 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 22
All of the above points should be checked with the sheet supplier to ensure that the sheeting is suitable for
the specific application.
Where the bolt passes through the sheeting, it should always be located on the crest of a corrugation. This
positioning avoids the possibility of leakage, particularly from a bolt located at the bottom of a corrugation
which forms the normal run off flow line.
The hole through the sheet can be waterproofed using either of the following two methods:
(a) Diamond shaped steel washers curved to take up the sheet profile, sandwiching a diamond shaped
bitumastic washer on to the sheet face.
or
(b) A proprietary plastic washer with either a loose or captivated nut that forms a seal with the sheet face as
the nut is tightened down.
For the safe working load of bolts refer to the manufacturers information as it will vary depending on:
The grade of steel used.
The method of threading.
The method of manufacture.
The thickness of the steel sheet.
It must be borne in mind when designing bolt groups that it is not always the bolts that provide the weak link.
In many instances the sheeting is weaker than the bolt and can collapse or tear under load.
Figure B.1
NASC
22 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 23
When using this type of connector, it would be the failure of the sheet which would be the deciding factor rather
than failure of the bolt.
B.6 Purlins
In temporary roof systems these are usually scaffold tubes which are fixed to the main supporting members
(or rafters.)
Where the main supporting member is some form of I beam or lattice structure then in order to reduce the
effect of lateral buckling, restraint must be provided. Here the purlin takes on the dual role of a sheet support
and lateral restraint member.
The safe bending Moment of Resistance of a new standard scaffold tube 48.3mm dia. x 4mm wall thickness
= 1.12 kN.m.
In axial compression, the allowable loads should be as shown in NASC TG20, “Guide to good practice for
scaffolding with tubes and fittings”.
This particular connector needs to be of the type that will carry the required load but will not interfere with the
sheeting line.
Of the scaffold connectors currently on the market, the following fulfil these objectives:
This coupler will adequately cope with the slip load required to laterally restrain the
rafter.
The major load from uplift created by the wind forces will be adequately coped with
by this fitting, because the load is at right angles to its normally loaded mode.
Figure B.2
At right angles, normal to the roof surface, this fitting can safely be rated at 1.75 kN.
Figure B.3
NASC
23 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 24
General arrangement
Design loading
a) Dead loading
Self-Weight of roof structure (from manufacturer’s data)
= 0.25 kN/m run along beam
b) Service loading
Two concentrated load of 1 kN placed 1m each side of ridge.
c) Imposed loading
c.1) Snow loading (Appendix D)
Ground snow load = 0.4 kN/m2 – from BS EN 1991-1-3 (Slough – Zone 2)
Altitude = 145m
Characteristic snow load = 0.2 + 0.1 Zone + (145-100)/525 = 0.48 kN/m2
Shape coefficient = 0.8
Design snow load = 0.38 kN/m2 = 0.95 kN/m @ 2.5m crs
c.2) Wind loadings (Appendix E)
Map wind speed, Vb = 21 m/s – from BS EN 1991-1-4 (Slough)
Altitude = 145m
Altitude factor, calt = 1 + 145/1000 = 1.145
Basic wind speed, Vb = 21 x 1.145 = 24.05 m/s
Cprob = 1.0, Cdir = 1.0, Cseason = 1.0
Twind (topographical factor) = 1.0
Basic wind pressure, qb = 0.613 x Vb2 / 1000 = 0.35 kN/m2
Combined exposure factor, Cc = 2.08
Peak wind pressure, qp = 0.7 x 0.35 x 2.08 = 0.51 kN/m2
NASC
24 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 25
Figure C.6
Figure C.6
NASC
25 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 26
NASC
26 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 27
Method:
Determine ground snow load or zone
Determine altitude
Determine shape coefficient for roof pitches not greater than 30° = 0.8
Combine for design loadings
Useful tips:
For determination of altitude
google earth – can determine altitude anywhere in world;
– may be downloaded from www.google.com
a)
Angle of pitch (a Shape coefficient
≤ 30° 0.8
0.8 ( 60 – a )
30° < a < 60°
30
10° 0.8
15° 0.8
20° 0.8
25° 0.8
30° 0.8
45° 0.4
Table D.1
NASC
27 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 28
NASC
28 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 29
Northern Scotland
On average, the number of days with snow falling varies from less than 40 per year along the west coast to
over 100 days over the Grampians. The number of days with snow lying has a similar distribution, with less
than 6 over the westernmost islands, about 20 in Shetland and more than 50 days over the higher ground. On
the highest summits, such as Ben Nevis, snow cover typically persists for 6 or 7 months each year.
NASC
29 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 30
Southern England
On average, the number of days with snow falling is about 12-15 per year over the lower lying areas but about
20 days over the higher ground of the Chilterns, North Downs and Weald. The least snow-prone places are
those close to the English Channel, with less than 10 days.
NASC
30 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 31
Wales
The average number of days each year when sleet or snow falls varies from 10 or less in south-western
coastal areas to over 40 in Snowdonia. Snow rarely lies on the ground at sea level before December or after
March, and the average number of days with snow lying in Wales varies from 5 or less around the coasts to
over 30 in Snowdonia.
NASC
31 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 32
Midlands
On average, the number of days with snow falling is about 20 per winter in the lower lying areas, particularly
the lower Severn valley. An average of about 35 days is typical of upland areas in the north and near the Welsh
border. An average increase of about 5 days of snow falling per year per 100 metres increase in altitude has
been found typical.
NASC
32 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 33
Northern England
On average, the number of days with snow falling is about 15-20 per year on the Isle of Man and from 20 to
30 days in lower-lying parts of the mainland but as much as 60 days over the highest ground. An average
increase of about 5 days of snow falling per year per 100 m increase in altitude has been found typical.
NASC
33 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 34
The basic data for the design of structures to resist wind forces are contained in BS EN 1991-1-4 and the UK
National Annex to BS EN 1991-1-4. Additional background information is given in PD 6688-1-4.
Where there are hills or slopes the wind profile changes and the topography, known as “orography” in BS EN
1991-1-4, can become significant. The values for the topography factor Twind for falsework erected up to 50m
in height for other conditions of hills or escarpments are shown in Fig. E.2.
Values for topography factor appropriate for the site should be considered for the wind acting in ALL directions,
and not just the orientation of the falsework structure.
NASC
34 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 35
For a temporary structure erected on the ground the value of z would be taken as the height from the ground
to the top of the structure.
When considering the forces on the temporary structure, the value for z should be taken as the actual height
of the structure. However, if the temporary structure is erected in an elevated position above the surrounding
ground level, for instance at the top of a tall structure, the reference height z, would be measured from the
ground, although the actual structure affected by the wind would only be its own storey height.
An allowance can be made for the effect of surrounding general buildings, such as housing or woodlands, by
using a height displacement (hdis). The displacement height is the lesser of the value in the following two
equations:
hdis = 0.8 have
or hdi = 0.6 h
where hdis is the displacement height (m)
have is the average obstruction height in the area (m)
h is the height of the considered structure for calculating z.
Where the temporary structure is spaced more than six times the average obstruction height away from the
nearest obstruction, the full height of structure is used and hdis = 0.
NASC
35 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 36
31
30
30 29
29
28
28
Inverness
27
Aberdeen
30
Oban Dundee 26
Perth
29
25
28 Glasgow Edinburgh
24
27
Londonderry 26 Newcastle
Carlisle
28 Belfast
23 York Kingston
Preston Leeds upon-Hull
25 Liverpool Manchester
Galway Dublin
Sheffield
Stoke
Nottingham
Limerick
22
Leicester
Norwich
Waterford Birmingham
Aberystwyth
Northampton Ipswich
Cork Bedford
Oxford 23
Swansea 21.5
LONDON
Cardiff
Bristol
28 24
27 26 25 Taunton Brighton
Bournemouth
Kilometres
0 40 80 120 160 Plymouth
22
0 20 40 60
Statute miles
80 100
23
Channel Islands 24 m/s
NASC
36 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 37
Note: Town values are to be considered if more than 2 km inside the edge of the town.
** for hdis see Figure E.3
NASC
37 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 38
Lu Ld Lu
(b) Moderately steep terrain, average slope < 1:5 (c) Moderately steep terrain, average slope < 1:5
Lu Ld Lu
(d) Steep terrain, average slope > 1:3 (e) Steep terrain, average slope > 1:3
Lu horizontal distance of the slope upwind Ld horizontal distance of the slope downwind
6 have
2 have
h dis
h
have
NASC
38 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:17 Page 39
Wind Direction, θ = 0°
Wind Direction, θ = 90°
(& reversed, θ=180°)
Pitch
α°
Angle,
CpeA CpeB CpeC CpeD CpeL CpeR CpeA CpeB CpeC CpeD CpeL CpeR
10 -1.02 -0.60 -0.22 -0.52 0.8 -0.5 -0.65 -0.65 -0.65 -0.65 -0.5 -0.5
0.12 0.00 -0.37 -0.37
12 -0.95 -0.48 -0.39 -0.49 0.8 -0.5 -0.63 -0.63 -0.63 -0.63 -0.5 -0.5
0.16 0.09 -0.28 -0.28
15 -0.80 -0.43 -1.00 -0.40 0.8 -0.5 -0.60 -0.60 -0.60 -0.60 -0.5 -0.5
0.20 0.13 0.00 0.00
18 -0.74 -0.30 -0.90 -0.40 0.8 -0.5 -0.64 -0.64 -0.64 -0.64 -0.5 -0.5
0.30 0.20 0.00 0.00
22.5 -0.65 -0.28 -0.75 -0.40 0.8 -0.5 -0.70 -0.70 -0.70 -0.70 -0.5 -0.5
0.45 0.24 0.00 0.00
30 -0.50 -0.25 -0.50 -0.40 0.8 -0.5 -0.80 -0.80 -0.80 -0.80 -0.5 -0.5
0.70 0.30 0.00 0.00
37.5 -0.25 -0.10 -0.40 -0.30 0.8 -0.5 -0.83 -0.83 -0.83 -0.83 -0.5 -0.5
0.70 0.50 0.00 0.00
45 0.00 -0.20 -0.30 -0.20 0.8 -0.5 -0.90 -0.90 -0.90 -0.90 -0.5 -0.5
0.70 0.40 0.00 0.00
60 0.70 0.00 -0.30 -0.20 0.8 -0.5 -0.80 -0.80 -0.80 -0.80 -0.5 -0.5
G H J I H H H H
NASC
39 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:18 Page 40
Wind Direction, θ = 0°
Wind Direction, θ = 90°
(& reversed, θ=180°)
Pitch
α°
Angle,
CpeA CpeB CpeC CpeD CpeL CpeR CpeA CpeB CpeC CpeD CpeL CpeR
10 -1.36 -0.48 -0.22 -0.52 0.8 -0.5 -1.45 -1.30 -1.45 -1.45 -0.5 -0.5
0.12 0.09 -0.37 -0.37
12 -1.23 -0.43 -0.39 -0.49 0.8 -0.5 -1.39 -1.30 -1.30 -1.39 -0.5 -0.5
0.16 0.13 -0.28 -0.28
15 -0.90 -0.30 -1.00 -0.40 0.8 -0.5 -1.30 -1.30 -1.30 -1.30 -0.5 -0.5
0.20 0.20 0.00 0.00
18 -0.82 -0.28 -0.90 -0.40 0.8 -0.5 -1.26 -1.32 -1.32 -1.26 -0.5 -0.5
0.30 0.24 0.00 0.00
22.5 -0.70 -0.25 -0.75 -0.40 0.8 -0.5 -1.20 -1.35 -1.35 -1.20 -0.5 -0.5
0.45 0.30 0.00 0.00
30 -0.50 -0.20 -0.50 -0.40 0.8 -0.5 -1.10 -1.40 -1.40 -1.10 -0.5 -0.5
0.70 0.40 0.00 0.00
37.5 -0.25 -0.10 -0.40 -0.30 0.8 -0.5 -1.03 -1.25 -1.25 -1.03 -0.5 -0.5
0.70 0.50 0.00 0.00
45 0.00 0.00 -0.30 -0.20 0.8 -0.5 -1.10 -1.40 -1.40 -1.10 -0.5 -0.5
0.70 0.60 0.00 0.00
60 0.70 0.70 -0.30 -0.20 0.8 -0.5 -1.10 -1.20 -1.20 -1.10 -0.5 -0.5
F H J I F G G F
NASC
40 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:18 Page 41
α°
Angle,
CpeA CpeB CpeC CpeL CpeR CpeA CpeB CpeC CpeL CpeR CpeA CpeB CpeC CpeL CpeR
10 -1.26 -1.01 -1.01 0.8 -0.5 -0.85 -0.85 -1.30 -0.5 0.8 -0.70 -0.70 -0.70 -0.5 -0.5
0.10 0.10 0.10 -0.85 -0.85 -1.3
12 -1.07 -0.72 -0.72 0.8 -0.5 -0.87 -0.87 -1.30 -0.5 0.8 -0.74 -0.74 -0.74 -0.5 -0.5
0.14 0.14 0.14 -0.87 -0.87 -1.3
15 -0.80 -0.30 -0.30 0.8 -0.5 -0.90 -0.90 -1.30 -0.5 0.8 -0.80 -0.80 -0.80 -0.5 -0.5
0.20 0.20 0.20 -0.90 -0.90 -1.3
18 -0.74 -0.28 -0.28 0.8 -0.5 -0.88 -0.88 -1.20 -0.5 0.8 -0.84 -0.84 -0.84 -0.5 -0.5
0.30 0.24 0.24 -0.88 -0.88 -1.2
22.5 -0.65 -0.25 -0.25 0.8 -0.5 -0.85 -0.85 -1.05 -0.5 0.8 -0.90 -0.90 -0.90 -0.5 -0.5
0.45 0.30 0.30 -0.85 -0.85 -1.05
30 -0.50 -0.20 -0.20 0.8 -0.5 -0.80 -0.80 -0.80 -0.5 0.8 -1.00 -1.00 -1.00 -0.5 -0.5
0.70 0.40 0.40 -0.80 -0.80 -0.8
37.5 -0.25 -0.10 -0.10 0.8 -0.5 -0.75 -0.75 -0.65 -0.5 0.8 -1.00 -1.00 -1.00 -0.5 -0.5
0.70 0.50 0.50 -0.75 -0.75 -0.65
45 -0.0 -0.0 -0.0 0.8 -0.5 -0.7 -0.7 -0.50 -0.5 0.8 -1.00 -1.00 -1.00 -0.5 -0.5
0.70 0.60 0.60 -0.7 -0.7 -0.5
60 0.70 0.70 0.70 0.8 -0.5 -0.50 -0.50 -0.50 -0.5 0.8 -1.00 -1.00 -1.00 -0.5 -0.5
G H H H H G H H H
NASC
41 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:18 Page 42
α°
Angle,
CpeA CpeB CpeC CpeL CpeR CpeA CpeB CpeC CpeL CpeR CpeA CpeB CpeC CpeL CpeR
10 -1.30 -1.01 -1.01 0.8 -0.5 -0.85 -0.85 -2.40 -0.5 0.8 -1.85 -1.85 -2.25 -0.5 -0.5
0.10 0.10 0.10 -0.85 -0.85 -2.4
12 -1.14 -0.72 -0.72 0.8 -0.5 -0.87 -0.87 -2.44 -0.5 0.8 -1.75 -1.87 -2.31 -0.5 -0.5
0.14 0.14 0.14 -0.87 -0.87 -2.44
15 -0.90 -0.30 -0.30 0.8 -0.5 -0.90 -0.90 -2.50 -0.5 0.8 -1.60 -1.90 -2.40 -0.5 -0.5
0.20 0.20 0.20 -0.90 -0.90 -2.5
18 -0.82 -0.28 -0.28 0.8 -0.5 -0.88 -0.88 -2.22 -0.5 0.8 -1.54 -1.82 -2.34 -0.5 -0.5
0.30 0.24 0.24 -0.88 -0.88 -2.22
22.5 -0.70 -0.25 -0.25 0.8 -0.5 -0.85 -0.85 -1.80 -0.5 0.8 -1.45 -1.70 -2.25 -0.5 -0.5
0.45 0.30 0.30 -0.85 -0.85 -1.80
30 -0.50 -0.20 -0.20 0.8 -0.5 -0.80 -0.80 -1.10 -0.5 0.8 -1.30 -1.50 -2.10 -0.5 -0.5
0.70 0.40 0.40 -0.80 -0.80 -1.1
37.5 -0.25 -0.10 -0.10 0.8 -0.5 -0.75 -0.75 -0.85 -0.5 0.8 -1.30 -1.45 -1.80 -0.5 -0.5
0.70 0.50 0.50 -0.75 -0.75 -0.85
45 -0.0 -0.0 -0.0 0.8 -0.5 -0.7 -0.7 -0.6 -0.5 0.8 -1.30 -1.40 -1.50 -0.5 -0.5
0.70 0.60 0.60 -0.7 -0.7 -0.6
60 0.70 0.70 0.70 0.8 -0.5 -0.50 -0.50 -0.50 -0.5 0.8 -1.20 -1.20 -1.20 -0.5 -0.5
F H H H H F F low G F up
NASC
42 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:18 Page 43
Table E.6a: Cpe for Duo-Pitched Canopies – Central Sections – with Side Wall
(Minimum ϕ = 1)
Wind Direction, θ = 0°
Wind Direction, θ = 90°
Pitch
(& reversed, θ=180°)
α°
Angle,
NASC
43 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:18 Page 44
Table E.6b: Cpe for Duo-Pitched Canopies – Edge Sections – with Side Wall
(Minimum ϕ = 1)
Wind Direction, θ = 0°
Wind Direction, θ = 90°
Pitch
(& reversed, θ=180°)
α°
Angle,
NASC
44 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:18 Page 45
Table E.7a: Cpe for Duo-Pitched Canopies – Central Sections – without Side Wall
(Minimum ϕ = 0)
Wind Direction, θ = 0°
Wind Direction, θ = 90°
Pitch
(& reversed, θ=180°)
α°
Angle,
NASC
45 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:18 Page 46
Table E.7b: Cpe for Duo-Pitched Canopies – Edge Sections – without Side Wall
(Minimum ϕ = 0)
Wind Direction, θ = 0°
Wind Direction, θ = 90°
Pitch
(& reversed, θ=180°)
α°
Angle,
NASC
46 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:18 Page 47
Table E.8a: Cpe for Mono-Pitched Canopies – Central Sections – with Side Wall
(Minimum ϕ = 1)
Wind Direction, θ = 0°
Wind Direction, θ = 90°
Pitch
(& reversed, θ=180°)
α°
Angle,
NASC
47 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:18 Page 48
Table E.8b: Cpe for Mono-Pitched Canopies – Edge Sections – with Side Wall
(Minimum ϕ = 1)
Wind Direction, θ = 0°
Wind Direction, θ = 90°
Pitch
(& reversed, θ=180°)
α°
Angle,
NASC
48 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:18 Page 49
Table E.9a: Cpe for Mono-Pitched Canopies – Central Sections – without Side Wall
(Minimum ϕ = 0)
Wind Direction, θ = 0°
Wind Direction, θ = 90°
Pitch
(& reversed, θ=180°)
α°
Angle,
NASC
49 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:18 Page 50
Table E.9b: Cpe for Mono-Pitched Canopies – Edge Sections – without Side Wall
(Minimum ϕ = 0)
Wind Direction, θ = 0°
Wind Direction, θ = 90°
Pitch
(& reversed, θ=180°)
α°
Angle,
NASC
50 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:18 Page 51
NASC
51 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:18 Page 52
F.1 Prior to the commencement of the construction work, the proposed temporary structure design should
be checked for concept, adequacy, correctness, safe buildability by operatives and compliance with the
design brief.
This check should be carried out by a competent person or persons independent from those
responsible for the design. The ability of the checker and his remoteness or independence from the
designer should be greater where new ideas are incorporated or the temporary works are complex.
F.2 Temporary roof and temporary buildings are complex structures. Therefore, a design check
should be carried out by an individual not involved in the design, and not consulted by the
designer. Typically, this will be a Category 2 check (BS. 5975)
F.3 If a BS. 5975 Category 3 check is required, it should be specified within the design brief.
For a Category 3 check, the check should be carried out by another without reference to the
designer’s calculations, using only the design brief, design statement, drawings and specification and
associated information not produced by the designer.
F.4 On completion of the design and design check, a certificate should be issued, stating the category of
check and confirming that the design complies with the requirements of the design brief, the
standards/technical literature used and the constraints or loading conditions imposed. The certificate
should identify the drawings/sketches, specification and any methodology that are part of the design
and it should be signed by the designer and design checker. The package of information, including this
certificate, should be issued to the person responsible for temporary works who should ensure that
loads imposed by the temporary structure can be safely withstood.
NASC
52 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:18 Page 53
BS EN 74 Steel couplers
BS 5975 Code of practice for temporary works procedures and the permissible stress design
of falsework
NASC TG20 Guide to good practice for scaffolding with tube and fittings.
N ANSA
CS C
53 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:18 Page 54
NASC
54 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:18 Page 55
NASC
55 of 56
24059_NASC_TG9-18 p9:TG9 8/8/18 11:18 Page 56
Whilst every effort has been made to provide reliable and accurate information, we would welcome any corrections to information provided by the Writer which
may not be entirely accurate, therefore and for this reason, the NASC or indeed the Writer, cannot accept responsibility for any misinformation posted.