Transmission Line Design Standard
Transmission Line Design Standard
Summary
This standard defines the performance design parameters for overhead transmission lines constructed to
connect to and form part of the TransGrid network.
TransGrid publishes this information under clause 5.2A.5 of the National Electricity Rules.
Document Control
1. Purpose ..................................................................................................................................................... 3
2. Scope ......................................................................................................................................................... 3
3. Objectives.................................................................................................................................................. 3
4. Definitions ................................................................................................................................................. 3
6. General ...................................................................................................................................................... 4
6.1 Design parameters ........................................................................................................................... 4
6.2 Safety in design ................................................................................................................................ 5
6.3 Design drawings ............................................................................................................................... 5
8. Electrical Design....................................................................................................................................... 7
8.1 Insulation........................................................................................................................................... 7
8.2 Electrical clearances ......................................................................................................................... 7
8.2.1 Clearance to ground and roads ......................................................................................... 7
8.2.2 Clearance to structures ...................................................................................................... 8
8.2.3 Maintenance clearances .................................................................................................... 8
8.3 Transpositions .................................................................................................................................. 8
8.4 Earthing............................................................................................................................................. 8
8.4.1 Earthing metalwork ............................................................................................................ 8
8.4.2 Footing resistance.............................................................................................................. 8
8.4.3 Earthing safety ................................................................................................................... 8
8.5 Electric and magnetic fields .............................................................................................................. 8
8.6 Induction ........................................................................................................................................... 8
8.7 Vibration ............................................................................................................................................ 8
9. Structural Design...................................................................................................................................... 9
9.1 General requirement ......................................................................................................................... 9
9.2 Loadings ........................................................................................................................................... 9
9.3 Structure and design ........................................................................................................................ 9
9.4 Footing design .................................................................................................................................. 9
9.5 Prototype and testing ........................................................................................................................ 9
9.6 Fauna consideration ....................................................................................................................... 10
This standard for Transmission Line Design specifies the minimum structural, electrical and geotechnical
design required for overhead transmission lines used in TransGrid’s network. This standard complies with
AS/NZS 7000 and any exceptions are explicitly noted.
2. Scope
This standard specifies the requirements that shall be met for the design of new towers, poles or similar
structures that support the conductor of TransGrid overhead transmission lines.
This standard is not intended as a substitute for AS/NZS 7000 or other Regulatory Standards, Codes or Acts.
Every effort has been made to ensure that this standard complies with AS/NZS 7000 except where explicitly
stated, however it remains the users’ responsibility to ensure that all relevant regulatory requirements are
satisfied, particularly where recent amendments have been made.
3. Objectives
TransGrid requires works to be carried out in accordance with this standard to ensure:
That relevant Australian legal requirements are met
That the requirements of the National Electricity Rules are met
Personnel and public safety
Safety of TransGrid’s assets
Ease in operation and maintenance
Reliability and continuity of power supply from the power transmission network
Minimum disruption to the power supply system following a fault
Alignment with TransGrid’s network management strategies and TransGrid’s established maintenance
practices
That the exposure of TransGrid’s business to risk is minimised.
4. Definitions
The meanings and interpretations of terms and phrases used in this document are as listed below.
Term Definition
Conductor This is generally a reference to the phase conductors on a transmission line but is also a
generic term for the uninsulated cables that are used for either phase conductor or
overhead earthwire.
Suspension A structure that primarily supports the transverse and vertical load of the conductors and is
Structure subject to minimal longitudinal load. The conductor is supported by insulation that is usually
perpendicular to the conductor. Insulator types include I string, D string, V string, horizontal
V, line post, braced line post.
Tension Structure A structure where the conductors are terminated with insulators in-line with the conductor
and supports longitudinal conductor loads in addition to the transverse and vertical loads.
The structure is incapable of resisting termination loads on one face of the structure alone.
Termination (Dead- A tension structure that is capable of resisting terminated conductor loads on one face of
Term Definition
6. General
The following issues shall be addressed in the transmission line design to ensure that the line meets the
operation requirements of the TransGrid network:
Structure security is required to limit the consequential damage in the event of a structural failure and
particularly to reduce the risk of cascade failures
Network Reliability should be maximised for all transmission line designs through all aspects of
construction, operation and maintenance
Thermal Rating – phase conductors and maximum operating temperature shall be selected to
minimise annealing and maximise conductor life. All lines shall maintain statutory ground clearances
at the maximum design operating temperature
Fault Currents – current, future and ultimate fault levels should be considered in the selection of
conductors and earthwires to ensure they are adequately rated
Lightning Performance - The lightning performance of a transmission line shall be managed through
control of earthwire shielding angle, structure earth resistance and insulation level to achieve the
lightning outage rates shown in the table below:
Required Clearances Around Structures - The following are the minimum requirements to provide for
a safe work area around each type of structure:
o 15m from any crossing power line structure or conductors
o 15m to any road carriageway, or barricade outside the edge of the carriageway
o 15m to the property boundary of any rail corridor
o Consideration of conductor blowout towards structures to maintain safe electrical clearances
o All parts of structures and conductors of any parallel electricity line to be outside the
easement, overlapping easements are acceptable
8. Electrical Design
8.1 Insulation
Insulation co-ordination shall be in accordance with AS 1824.
8.3 Transpositions
Phase conductors are transposed on long transmission lines to balance the mutual impedances and reduce
the load current unbalance.
Transpositions are usually not required in 500kV lines or 330kV lines less than 100km in length. Where
required, they will be specified by TransGrid.
For lines less than 50km transposition is not usually required. For lines greater than 50km, consultation with
TransGrid is required regarding the possible need for a transposition.
8.4 Earthing
8.4.1 Earthing metalwork
In general all metallic pole fittings such as cross-arms, insulator bases and pole bands shall be bonded to the
structure earthing system.
Step bolts are not required to be earthed.
8.6 Induction
Magnetic fields due to load or fault current can couple with nearby conductive infrastructure to produce
hazardous voltages, particularly where the structure is long, parallel and close to the transmission line.
Metallic pipelines, power lines, metallic fences, conveyor belts and copper telecommunication lines are typical
examples.
The risk and mitigation measures shall be assessed in accordance with AS 4853 or HB 102.
Fences on the easement should generally be dealt with during construction according to the TransGrid
Fencing Guideline.
8.7 Vibration
Where a conductor, earthwire or OPGW is strung at a tension in excess of the limits of AS/NZS 7000 vibration
dampers shall be installed to limit fatigue.
9.2 Loadings
Structures shall be designed to meet the loading requirements specified in AS/NZS7000 as the minimum
including, but not limited to, the following load cases:
Wind loads shall be calculated in accordance with AS 1170.2 and AS/NZS 7000 in conjunction with
other relevant Australian codes and standards to achieve system security levels required
Where lines of significant length crossover wind regions, the appropriate region can be applied to
each respective section, however any change in wind pressure along the line should be done at a
termination structure, with the higher wind pressure applied to the structure itself