Engr. Romano E. Torrano
Engr. Romano E. Torrano
College of Engineering
Submitted to
Instructor
Submitted by
Claveria, Cristobal
April 2019
CONTENTS
A. Overview
B. Design Population
C. Water Consumptions
Part 1 Overview
B. Reservoirs
Elevated Reservoir
Fill-and-Draw Reservoirs
Capacity
Tank Description
Chapter 4 Pumps
A. Design of Pumps
References
Chapter 1
Water Demand
In this Chapter, the procedure of finding the water magnitude needed by a new water
utility project to supply the population in Barangay 10, Balayan, Batangas will be described.
A. Overview
Water demands are influenced by the following factors:
6. Climatological conditions;
Water service levels are classified in the Philippines under three types (3), depending
on the method by which the water is made available to the consumers. For this particular
design,
taps. It is generally suited for densely populated urban areas where the population can
The Design Population is the targeted number of people that the project will serve.
Population Households
3,184 496
C. Water Consumptions
Water consumptions served by small water utilities are commonly classified into
Domestic Use, Commercial Use, Institutional Use, or Industrial Use. In rural areas, water
consumption is generally limited to domestic uses, i.e., drinking, cooking, cleaning, washing
Unit consumption for domestic water demand is expressed in per capita consumption
per day. The commonly used unit is liters per capita per day (lpcd). For Level III type, 80 -
100 lpcd (6 member per Household).
140
120
100
Liters*1000
80
60 Liter*1000
40
20
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Hours
Therefore;
Water demand varies within the day and also within the year. This demand variation
is dependent on the consumption pattern of the locality and is measured by four demand
Minimum day demand: The minimum amount of water required in a single day over
year.
Average day demand: The average of the daily water requirement spread in a year.
Maximum day demand: The maximum amount of water required in a single day over
a year.
Peak hour demand: The highest hourly demand in a day.
Each of the above demand conditions is designated a demand factor to define its value
based on the average day demand. For a Level II/III system, the following demand factors
are
recommended:
Design of Reservoir
This Chapter discusses the factors that must be taken into account in the design of
PART 1 (Overview)
• To balance the supply and demand in the system. In small distribution systems,
variations in demand may be three or more times the average hourly consumption.
• To avoid the total interruption of water service when repairing pipes between the
source of supply and the reservoir.
• To allow pumps to be operated uniformly throughout the day. Such pumps may be
much smaller than would otherwise be required.
B. Reservoirs
Reservoirs may be classified according to their function, their relative position with
respect to the earth’s surface, manner of operation, and the type of material of construction.
The design follows the following considerations:
Elevated Reservoirs
Reservoirs are constructed in elevated or hilly areas. In case of flat areas, a supporting
frame or tower is installed to support the storage tank. This is known as an elevated
reservoir. Standpipes are reservoirs with height greater than their diameter.
Fill-And-Draw Reservoir
Water flows or is pumped directly into the reservoir and from the reservoir, water supply
is distributed to the consumers through gravity flow. The tank is usually installed near the
water source to minimize head losses due to friction losses. In the fill-and-draw system,
however, water is conveyed to the storage tank at high pumping capacity at shorter time
Capacity
As a rule of thumb, the storage tank volume should be at least equal to one-fourth (25%)
Tank Description
Capacity: 67 m3
Tank Diameter: 4 m
Elevation Profile
Part 2 (Structural Analysis)
𝑃 = 𝛾ℎ
FIGURE
𝑁𝑃𝐷𝑜 2.5(58.86)(4)
𝑡= = = 1.25𝑚𝑚
2𝜕𝑆𝑌 ή 2(276 × 106 )
4𝜋𝑟 2 4𝜋23
𝑉ℎ = = = 16.755𝑚3
3(2) 6
𝑘𝑔⁄ (67.02𝑚3 )
𝑚 = 1000 𝑚3 = 67,020 𝑘𝑔
𝐷0 = 4𝑚
𝐷𝑖 = 3.996𝑚
4 2
𝑉ℎ′ = 𝜋(𝑟𝑜 3 − 𝑟𝑖 3 ) = 𝜋(23 − 1.9983 ) = 0.05022 𝑚3
3(2) 3
𝜋 𝜋
𝑉𝑐 ′ = (𝐷𝑜 2 − 𝐷𝑖 2 )ℎ = (42 − 3.9962 )(4) = 0.10048 𝑚3
4 4
1 1 1
𝑉𝑐𝑜′ = 𝜋𝑟 2 ℎ = (2)2 (0.5) − 𝜋(1.998)2 (0.498) = 0.012548 𝑚3
3 3 3
𝑉𝑇 = 𝑉𝑐′ + 𝑉ℎ′ + 𝑉𝑐𝑜′ = 0.05022 𝑚3 + 0.10048 𝑚3 + 0.012548 𝑚3 = 0.16324𝑚3
𝑘𝑔⁄
𝜌 = 7942.7730 𝑚3
𝑘𝑔⁄
𝑚 = 𝑉𝑡 𝜌 = 0.16324𝑚3 (7942.7730 𝑚3 ) = 1296.5981 𝑘𝑔
WEIGHT OF TANK
ROUND BAR
𝑘𝑔⁄
𝑊𝐸𝐼𝐺𝐻𝑇 𝑂𝐹 𝑅𝑂𝑈𝑁𝐷 𝐵𝐴𝑅 = 2.47 𝑚
𝑘𝑔⁄
𝑀𝐴𝑆𝑆 𝑂𝐹 𝑅𝑂𝑈𝑁𝐷 𝐵𝐴𝑅𝑆 = 48.631𝑚 (2.47 𝑚) = 120.1186𝑘𝑔
SQUARE BARS
𝑘𝑔⁄
𝑊𝐸𝐼𝐺𝐻𝑇 𝑂𝐹 𝑆𝑄𝑈𝐴𝑅𝐸 𝐵𝐴𝑅𝑆 = 1.31 𝑚
𝑘𝑔⁄
𝑀𝐴𝑆𝑆 = 17.4𝑚 (1.131 𝑚 = 19.6794𝑘𝑔)
ROUND BARS
𝐷𝑅 = 0.02 𝑚
16 Rings
𝐶𝑅𝑇 = 243.728𝑚
𝑘𝑔⁄
𝑊𝐸𝐼𝐺𝐻𝑇 = 2.47 𝑚
𝑘𝑔⁄ (243.728𝑚)
𝑀𝐴𝑆𝑆 = 2.47 𝑚 = 602.00816𝑘𝑔
VARYING LOADS
490.5𝑁
50𝑘𝑔 = = 163.5𝑁
3
882.9𝑁
90𝑘𝑔 = = 294.3𝑁
3
@50 kg @90 kg
𝑅1 = 𝑅2 = 81.75𝑁 𝑅1 = 𝑅2 = 147.15 𝑁
𝑙𝑏 6.8948𝑘𝑃𝑎
𝑆𝑢 = 35 𝑘𝑝𝑠𝑖 𝑆𝑛 = 16𝑘𝑝𝑠𝑖 = 16000 × 𝑙𝑏 = 110.317𝑀𝑃𝑎
𝑖𝑛2 1 2
𝑖𝑛
1
Use N=8, 8
= 𝑆𝑦 = 170 𝑀𝑃𝑎
990.9114 𝑁. 𝑚 283.0921𝑁. 𝑚
1 𝑑 3 𝑑3
= +
8 𝑁 𝑁
170 × 106 2 110.317 × 106 2
𝑚 𝑚
Since the factor of safety is too big, we consider limiting the factor to 2.5, because the
application was only for the catwalk of the storage tank, we get
990.9114 𝑁. 𝑚 283.0921𝑁. 𝑚
1 𝑑 3 𝑑3
= +
2.5 𝑁 𝑁
170 × 106 2 110.317 × 106 2
𝑚 𝑚
𝑑 = 0.0276𝑚 ≈ 27.5838 𝑚𝑚
The diameter of the round bar that can be used is 27.5838mm. so we decided to use 20 mm.
DIAGONALS
𝐷𝐼𝐴𝐺𝑂𝑁𝐴𝐿 = 0.71𝑚
𝜋(5.7)
𝑁𝑈𝑀𝐵𝐸𝑅 𝑂𝐹 𝐷𝐼𝐴𝐺𝑂𝑁𝐴𝐿𝑆 = = 35.8 ≈ 36 × 2 = 72
0.5
𝑘𝑔⁄
𝑇𝑂𝑇𝐴𝐿 𝑀𝐴𝑆𝑆 = (51.12𝑚) (0.591 𝑚) = 32.21192𝑘𝑔
677.758
𝐿𝑂𝐴𝐷 𝑃𝐸𝑅 𝐶𝑂𝐿𝑈𝑀𝑁 = = 169.4395𝐾𝑁
4
𝐹𝑊 = 67.361 𝐾𝑁
1 2
𝐹 = 𝑃𝑑𝐴 = 𝜌𝑣
2
𝑘𝑔⁄
𝜌 = 1.2 𝑚3
RECTANGULAR AREA
𝐴1 = 4𝑚 × 4𝑚 = 16𝑚2
SEMI CIRCLE
𝜋𝑟 2 𝜋(2)2
𝐴2 = = = 6.283𝑚2
2 2
TRIANGLE
1 1
𝐴3 = 𝑏ℎ = (4)(0.8) = 1.6𝑚2
2 2
𝐴𝑇 = 𝐴1 + 𝐴2 + 𝐴3 = 16𝑚2 + 6.283𝑚2 + 1.6𝑚2 = 23.283𝑚2
1
𝐹𝑊 = (1.2)(23.883)(69.44)2 = 67.361𝐾𝑁
2
Section Dimension:
G = 3.86 in
H = 7 in
t = 0.392in
𝐼𝑥 = 26.3𝑖𝑛4
𝐼𝑦 = 2.31𝑖𝑛4
𝑆𝑥 = 8.77𝑖𝑛4
𝑆𝑦 = 1.3𝑖𝑛4
677.758
𝐿𝑂𝐴𝐷 𝑃𝐸𝑅 𝐶𝑂𝐿𝑈𝑀𝑁 = = 169.4395𝐾𝑁
4
𝐹𝑤 = 67.361 𝐾𝑁
𝐺 = 3.565"
𝐻 = 6"
ℎ = 6 − 2(0.465) = 5.07
𝑔 = 3 − 0.465 = 2.535
𝑡 = 0.465
COMPTATION FOR k
1 𝐺𝐻 3 − 𝑔ℎ3
𝑘=√ ( )
2 𝐺𝐻 − 𝑔ℎ
1 (3.565)(6)3 − (2.535)(5.07)3
=√ ( ) = 5.0749𝑖𝑛
2 (3.565)(6) − (3.565)(5.07)
𝑘𝑒
3.0 < < 120
𝑘
12.146
𝐿𝑒 = = 6.078𝑚 𝑜𝑟 239.2913𝑖𝑛
2
𝐿𝑒 239.2913
= = 47.1566
𝑘 5.0744
BY JB JOJNSON FORMULA
𝑆𝑦 = 24656.41646𝑝𝑠𝑖
𝐸 = 29 × 106 𝑝𝑠𝑖
𝐴 = (2𝐺𝑇 + 𝑡ℎ)
𝐿𝑒
1 − 𝑆𝑦 ( )2
𝐹𝐶 = 𝑆𝑦 𝐴[ 𝑘 ]
4𝜋 2 𝐸
(24656.41646)(47.1566)2
𝐹𝑐 = (24656.41646)(5.673)(1 − )
4𝜋 2 (29 × 106 )
𝑭𝑪 > 𝑅 𝑜𝑘
1 1
𝐼𝑋 = (𝐺𝐻 3 − 𝑔ℎ3 ) = (3.565)(6)3 − (2.535)(5.07)3 = 36.630𝑖𝑛4 𝑜𝑟 1.525 × 10−5 𝑚4
12 12
𝐻 6
𝐶𝐸𝑁𝑇𝑅𝑂𝐼𝐷 = = = 3𝑖𝑛 𝑜𝑟 0.0762𝑚
2 2
∈ 𝑀𝑜 = 𝑀𝐴𝑋 𝑀𝑂𝑀𝐸𝑁𝑇
𝑀𝐶 22.7099(0.0762)
𝜎= = = 113.473𝑀𝑃𝑎
𝐼 1.525 × 10−5
Chapter 3
Design Calculation
Source: http://www.pipeflow.com/sitemap/pipe-roughness
Table 3.3 Values of K for Various Fitting Types
PIPE LINE LAYOUT DESIGN
𝑳 𝟏 𝒅𝒂𝒚 𝟏 𝒉𝒓
𝑻𝒐𝒕𝒂𝒍 𝑸𝑫 = 𝟖𝟎 ∗ 𝟔 ∗ 𝟒𝟗𝟔 ∗ ∗ = 𝟐. 𝟕𝟔 𝒍𝒑𝒔
𝒑−𝒅 𝟐𝟒 𝒉𝒓𝒔 ∗ 𝟑𝟔𝟎𝟎 𝒔
𝟏
𝑸(𝑸𝟏−𝑲𝟏) = 𝑵𝒐. 𝑯𝒐𝒖𝒔𝒆𝒉𝒐𝒍𝒅𝑸𝟏−𝑷𝟏 ∗ 𝟖𝟎 ∗ 𝟔 ∗ = 𝟎. 𝟓𝟓𝟑 𝒍𝒑𝒔
𝟐𝟒 ∗ 𝟑𝟔𝟎𝟎
𝑸(𝑸𝟏−𝑲𝟏) 𝟎. 𝟓𝟓𝟑/𝟏𝟎𝟎𝟎 𝒎
𝑽(𝑸𝟏−𝑲𝟏) = 𝟐
= 𝟐
= 𝟎. 𝟎𝟒𝟑𝟔
𝝅(𝑫) 𝝅(𝟎. 𝟏𝟐𝟕) 𝒔
𝟒 𝟒
Calculating for Reynold’s number
𝑽𝑫 𝟎. 𝟎𝟒𝟑𝟔 ∗ 𝟎. 𝟏𝟐𝟕
𝑹𝒆 = = = 𝟔𝟗𝟓𝟖𝟕𝟓𝟎. 𝟗𝟔𝟖
𝝂 𝟏. 𝟎𝟏𝑬 − 𝟔
𝟏 𝟔. 𝟗 ∈/𝑫 𝟐
= −𝟏. 𝟖𝒍𝒐𝒈 [ +( ) ]
√𝒇 𝑹𝑬 𝟑. 𝟕
𝟏
𝒇=
𝟏. 𝟓𝟐𝑬 − 𝟔 𝟏.𝟏𝟏
𝟔. 𝟗
−𝟏. 𝟖𝒍𝒐𝒈 [ + ( 𝟎.𝟑.𝟏𝟐𝟕 ) ]
𝟔𝟗𝟓𝟖𝟕𝟖𝟎. 𝟗 𝟕
{ }
𝒇 = 𝟎. 𝟎𝟎𝟗𝟑𝟒𝟗𝟕𝟐
With the aid of Excel Spreadsheet repeat the same procedure all throughout
the design, we obtain the following results:
Loop 1
Pipe L(m) D(m) Q(d) Q (lps) V(m/s) RE f H
TankAL1 25 5 2.76 2.76 0.217876677 5392987.058 0.00956337 0.004554806
AL1Q1 23 5 2.6378 2.6378 0.208230108 4741873.754 0.00968279 0.003875364
Q1B 51.6 5 2.0845 2.0845 0.16455215 8406822.704 0.00921013 0.005164399
BC 30 5 2.0345 2.0345 0.160605109 4770448.77 0.00967703 0.003005242
CD 29 5 2.0123 2.0123 0.158852622 4561114.897 0.00972042 0.002854758
DE 16 5 1.9683 1.9683 0.155379226 2461453.085 0.01041908 0.001615224
EF 39 5 1.9294 1.9294 0.152308428 5881216.522 0.00948737 0.003444732
FG 39 5 1.8514 1.8514 0.146151044 5643456.136 0.00952312 0.003183794
GH 19.3 5 1.7194 1.7194 0.135730855 2593668.806 0.01035222 0.00147722
HI 19 5 1.7234 1.7234 0.136046618 2559292.812 0.01036914 0.00146342
IN1 60.62 5 1.6814 1.6814 0.132731103 7966494.534 0.00924827 0.003963869
N1Q 26.41 5 1.0931 1.0931 0.086290216 2256360.991 0.01053347 0.000831305
QR 25.26 5 1.0542 1.0542 0.083219418 2081309.399 0.01064326 0.000747231
RS 31 5 0.9672 0.9672 0.076351566 2343463.907 0.01048317 0.000760305
ST 19.65 5 0.9322 0.9322 0.073588637 1431699.722 0.01119831 0.000478227
TO1 19.16 5 0.8882 0.8882 0.070115241 1330106.945 0.01131669 0.000427796
O1M1 46.36 5 0.7493 0.7493 0.05915036 2715060.099 0.01029495 0.000670162
M1U 9 5 0.6443 0.6443 0.050861574 453221.9428 0.01342343 0.000125425
UV 29 5 0.5715 0.5715 0.045114682 1295372.044 0.01136001 0.000269097
VX 27 5 0.4665 0.4665 0.036825895 984454.6159 0.01183324 0.000173889
XY 36 5 0.3775 0.3775 0.029800161 1062183.973 0.01169778 0.000150086
YA1 49 5 0.2995 0.2995 0.023642777 1147025.82 0.01156427 0.000127118
A1C1 50 5 0.1335 0.1335 0.0105386 521712.8785 0.01310538 2.92067E-05
C1P1 30.85 5 0.0002 0.0002 1.57882E-05 482.2424659 0.09072951 2.80004E-10
P1D1 173 5 0.0012 0.0012 9.4729E-05 16225.85671 0.02716795 1.69265E-08
F1D1 28 5 -0.05 0.05 0.003947041 109422.9258 0.01754055 3.07073E-06
G1F1 30.5 5 -0.0833 0.0833 0.006575771 198575.2546 0.01559213 8.2527E-06
H1G1 46.1 5 -0.1997 0.1997 0.015764483 719547.1836 0.0124291 5.71475E-05
I1H1 40 5 -0.2664 0.2664 0.021029836 832864.784 0.01214355 8.62134E-05
J1I1 23.2 5 -0.3442 0.3442 0.027171432 624135.8634 0.01271992 8.74369E-05
K1J1 134.39 5 -0.3775 0.3775 0.029800161 3965191.781 0.00986215 0.00047236
Q1K1 161 5 -0.553 0.553 0.043654276 6958750.968 0.00934973 0.001151266
DeltaH 0.037526945
Loop 2
Pipe L(m) D(m) Q(d) Q (L/s) V Re f H H/Q
N1J 19 5 0.5583 0.5583 0.044072663 829089.693 0.01215222 0.000179989 0.322386833
JK 31.28 5 0.4696 0.4696 0.037070611 1148087.848 0.01156269 0.000199472 0.424770367
KL 43 5 0.4304 0.4304 0.033976131 1446508.552 0.011182 0.000222758 0.517560349
LM 53 5 0.3474 0.3474 0.027424043 1439083.425 0.01119015 0.000179008 0.51527881
MN 12.38 5 0.2752 0.2752 0.021724515 266286.6301 0.0147575 3.46044E-05 0.125742597
NO 53 5 0.1312 0.1312 0.010357036 543488.0407 0.01301554 2.96966E-05 0.226345911
OP 91 5 0.0532 0.0532 0.004199652 378384.4775 0.013852 8.92232E-06 0.167712742
PP1 67 5 0.00092 0.00092 7.26256E-05 4817.735105 0.03816561 5.41282E-09 0.005883496
C1P1 30.85 5 -0.0002 0.0002 1.57882E-05 482.2424659 0.09072951 2.80004E-10 0.00140002
A1C1 50 5 -0.1335 0.1335 0.0105386 521712.8785 0.01310538 2.92067E-05 0.21877695
YZ 49 5 -0.22995 0.22995 0.018152443 880663.0628 0.01203809 7.80048E-05 0.339224998
XY 36 5 -0.3775 0.3775 0.029800161 1062183.973 0.01169778 0.000150086 0.397578954
VX 27 5 -0.4661 0.4661 0.036794319 983610.4961 0.01183478 0.000173613 0.372480737
UV 29 5 -0.57 0.57 0.04499627 1291972.117 0.01136433 0.000267789 0.469804578
M1U 9 5 -0.6443 0.6443 0.050861574 453221.9428 0.01342343 0.000125425 0.194668106
O1M1 46.36 5 -0.7993 0.7993 0.063097401 2896233.2 0.01021592 0.00075673 0.946741494
T1O1 19.16 5 -0.8882 0.8882 0.070115241 1330106.945 0.01131669 0.000427796 0.481644218
ST 19.65 5 -0.9322 0.9322 0.073588637 1431699.722 0.01119831 0.000478227 0.51300876
RS 31 5 -0.9762 0.9762 0.077062033 2365270.333 0.01047099 0.00077362 0.792481125
QR 26.26 5 -1.0542 1.0542 0.083219418 2163704.862 0.01059004 0.000772928 0.73318895
N1Q 26.41 5 -1.0931 1.0931 0.086290216 2256360.991 0.01053347 0.000831305 0.760501884
DeltaH -0.004010275 8.52718188
The analysis satisfies the zero head loss in closed network main line
connection. Therefore, the data are correct
Chapter 4
Pumps
A. Design of Pump
A cost analysis of pumping should consider both the initial cost (capital investment),
and operating cost. The type and size of pumping equipment, pipeline size, and system
design
affect not only the initial cost but also the operating cost. For example, using large pipes may
cost more but could allow the use of the less expensive, smaller horsepower pumps which
entail
lower energy costs; whereas a piping system with a smaller diameter pipe would require
pumps
If the water distribution system has a reservoir, the pump capacity must be equal to
the
𝑙 1 𝑑𝑎𝑦
𝑃𝑢𝑚𝑝 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 = 331,136 × = 4.1810 𝑙𝑝𝑠
𝑑𝑎𝑦 22 ℎ𝑟𝑠 × 60 𝑚𝑖𝑛𝑠 × 60 𝑠𝑒𝑐
Therefore:
Q 5 lps
Reservoir Water level 16 meter
Pumping Level 20 meter
Suction Length 36 meter
Get head loss per 100 m using Table 11.2; with Q = 5 lps and 75 mm dia.
9
𝐻𝑓 =
100
𝟗
𝑯𝑳 = 𝑯𝒇 ∗ 𝑻𝒐𝒕𝒂𝒍 𝒑𝒊𝒑𝒆 𝒍𝒆𝒏𝒈𝒕𝒉 = ∗ 𝟕𝟑. 𝟏𝟒 𝒎 = 𝟔. 𝟓𝟖𝟐𝟔 𝐦
𝟏𝟎𝟎
Pump TDH
𝑊𝐻𝑃 2.845
𝐵𝐻𝑃 = = = 4.741 𝐻𝑃
0.6 0.6
𝐵𝐻𝑃 = 4.741 ℎ𝑝 ≈ 5 ℎ𝑝
from the manufacturers pump curve, using the TDH and BHP the pump design will be:
Item No. 3 Submersible Pump/Motor, Riser and Transmission Line Pipes and Fittings
Description and Computation Unit Quantity Unit Cost Amount
A. Material Cost
Pump and Motor, submersible, 230 gpm
(15 hp motor) set 1 290,000.00 290,000.00
Pipe, G.I., 50 mm dia. X 6m, sched. 40
threaded ends with HD couplings pcs 12 1,680.00 20,160.00
Gate Valve pcs 2 1,750.00 3500
Check Valve pcs 2 4,500.00 9000
Pressure Gauge pc 1 750.00 750
Miscellaneous lot 1 1,500.00 1500
Cable,submersible meters 120 850.00 102000
Splicing kit set 1 2,500.00 2500
Panelboard set 1 38,000.00 38000
Electrical Wire meters 500 17.00 8500
Electrical Supply, misc. fittings, etc. lot 1 3,000.00 3000
Subtotal P 478,910.00
the Philippines, at least 60 percent of the capital of which is owned by citizens of the
Philippines;
controlled corporations.
Environmental etc.)
1. Proof of land ownership of, legal title to, or right to use, the property on which the
water
source is situated;
4. Brief Description of the project stating among others, how water will be used,
amount
applicable;
Other Requirements – In addition to the requirements under the above Section, the
A. For Well Drilling – All applications involving extraction of groundwater shall include
the name of a duly registered well driller who will undertake the drilling.
B. For Transfer of a Water Permit – A verified petition for the transfer of a water
permit
shall state the reasons for the transfer and shall attach the contract or agreement for the
transfer.
C. For Lease of a Water Right – A verified petition for the lease of a water permit shall
shall be for a continuous period exceeding five (5) years, otherwise the contract shall