Economical Analysis For Rising Main: J. M. S. P. L. Dharwad
Economical Analysis For Rising Main: J. M. S. P. L. Dharwad
PURE WATER RISING MAIN FROM WTP CLEAR WATER SUMP TO MBT 1 @ REVANSIDDESHWAR TEMPLE VILLAGE
DESCRIPTION
Sl DI Pipe
Pipe Material
No.
Dia of Pipe- in mm 150 200 250 300 350 400
2 PUMPING HOURS 16 16 16 16 16 16
3 LENGTH OF RISING MAIN (m) 3000 3000 3000 3000 3000 3000
DESIGNED LENGTH OF RISING MAIN
4 3300 3300 3300 3300 3300 3300
(m)
VO normal velocity in pipe before
5 2.76 1.55 0.99 0.69 0.51 0.39
closure
6 Frictional Slope in m (s) 0.0577 0.0142 0.0048 0.0020 0.0009 0.0005
7 TOTAL FRICTIONAL LOSS (m) 190.37 46.89 15.82 6.51 3.07 1.60
LOWEST WATER LEVEL AT PUMPING
8 443.00 443.00 443.00 443.00 443.00 443.00
POINT OR JN-GL RL(m)
19 RATE OF PIPE / m (in Rs) 1847 2464 3275 4149 4952 5939
20 COST OF PIPE (in Rs) 5541000 7392000 9825000 12447000 14856000 17817000
J. M. S. P. L. Dharwad
WATER HAMMER DESIGN
PURE WATER RISING MAIN FROM WTP CLEAR WATER SUMP TO MBT 1 @ REVANSIDDESHWAR TEMPLE VILLAGE
8 WATER VELOCITY IN PIPE (m /s) 2.76 1.55 0.99 0.69 0.51 0.39
9 WATER HAMMER PRESSURE (m) 350.87 191.440 119.90 81.60 59.05 44.53
11 (2) Design Pressure = 2 * Static Head 161.00 161.00 161.00 161.00 161.00 161.00
Economical Size Of Rising Main is 250 mm Dia Pipe, Working Total Water Pressure of 200.41 m, Hence 250 mm dia of DI K-
9 Pipe is recommended.