Semi Automatic Donning and Doffing Mechanism
Semi Automatic Donning and Doffing Mechanism
Semi Automatic Donning and Doffing Mechanism
Mechanism
BY
Supervised by
Prof. Dr. Wasim Ahmad Khan
May 2017
Semi-Automatic Doffing/Donning
Mechanism
BY
Supervised by
Prof. Dr. Wasim Ahmad Khan
May 2017
FACULTY OF MECHANICAL ENGINEERING
Ghulam Ishaq Khan Institute of Engineering Sciences and Technology
Name and
signature of Advisor(s):
Date:_____________
I
Abstract
The Doffing and donning process in the spinning in textile industry is largely manual. The
manual operations are cost, labor and time intensive. The cost of automation is huge
furthermore the automation requires radical changes in infrastructure. The best approach to the
solution of the problems arising from manual doffing is to devise a semi-automatic mechanism
that decreases the human interaction during the process. The project developed novel
mechanisms mounted on a mobile platform powered by an operator to perform the doffing and
donning operation. The mechanism consists of a
(i) Trolley
(ii) Locating/Timing Mechanism
(iii) Doffing Mechanism
(iv) Donning Mechanism
The design carefully takes into consideration that in order to be applicable in Pakistani textile
industry the final product must be
Table of Contents
Page
Abstract I
Table of Content II
Chapter 1 Introduction 1
1.1 Background and Motivation 1
1.2 Problem Statement 1
1.3 Scope and Expected Outcomes 2
1.4 Report Outline 2
1.5 Project Schedule and Deadlines 2
1.6 Individual and Team Contribution 2
Chapter 7 Conclusion 65
7.1 Summary 65
7.2 Future Considerations 66
V
References 67
Appendices 68
1
Chapter 1
INTRODUCTION
The Yarn is the crudest form of thread made as the result of basic processing of the cotton bale.
The most important processes in the yarn making are the processes of Doffing of Cops (The
filled bobbins) and the Donning of empty bobbins. The processes of Doffing and Donning are
largely manual in Pakistan. There exist some automatic machines but they are expensive and
require extensive up gradation of the infrastructure of the factory floor. Also the extent of the
use of manual machines is of such a magnitude that the automation of all the prevailing
machines would be almost impossible for the already struggling industry.
Therefore there is a need for development of such a mechanism that replaces the human from
the process while requiring minimum changes to the existing machines and achieving the
desired outcome at the minimum cost.
Chapter 2
LITERATURE REVIEW
1. Crane Type
2. Frame Type
3. Wagon Type
1. Intermittent type
2. Continuous type
The intermittent require the trolley to stop at certain intervals and perform the doffing and
donning and then move to the next stations to be doffed. This type has a problem of rapid
acceleration and deceleration that causes forces to be exerted on the structure making it
unstable thus making it’s designing difficult. Also the timing of the mechanism presents a
different kind of challenge that further increases the complications associated with the auto
doffer.
The continuous auto doffers doff the Cops and don the bobbins while keeping their motion.
This kind of auto doffers could be further classified into double disk and spatial cam types.
The continuous auto doffer is relatively easy to design and operate. However the double disk
type may damage the spindles of the spinning machine. Also the gripper may grip the Cop
while coming in contact with the yarn that may damage the yarn and render it useless.
7
There has been considerable research in the domain of continuous type and Toyoda had
developed a successful model on this concept(Watanabe, 1965). A paper (“A Novel
Continuous Single-Spindle Doffing Robot with a Spatial Cam and Multiple Grippers” by
Sicheng Yand and others) deals with the designing of a Novel Continuous auto doffer and
discusses the results of a successful experiment carried out on the model.
The paper by Sicheng was made the bases of all the further work on the project and a design
was developed based on ideas presented in the paper.
8
Chapter 3
DESIGN AND ANALYSIS
You can see a spinning machine in action, the goal is to remove and install bobbins from
this machine. The problem at hand was using workforce to accomplish this task. Several
new machines can do this installation/removal process automatically. Though, to replace
machines with new ones is not a cost effective option.
The motive was to create a machine which may be cost effective as well as time saving to
install and remove bobbins at the same time. Factory was considered in this problem
definition which was “Saif Textile Mill” with several visits and literature review the
following items play an important role to define the design methodology.
3. A doffing mechanism consisting of gripper which may follow a spatial cam path to
grip the bobbin and move upward in order to remove it from the machine, as we are
talking about wrapped bobbin.
4. A donning mechanism where the bobbins may be present and may fall on the empty
pins. Empty bobbins in this case.
5. Time the whole mechanism of doffing and donning with the tracking mechanism
discussed at point one.
6. Timing might be done with belts and chains. The scenario of timing is like “Bobbins
may be removed” – “the trolley moves forward” – “The empty bobbins may be
filled from the removed bobbins area” – “The trolley keeps moving forward
removing and adding bobbins”
These points from 1 – 6 actually show the whole mechanism decided as an outcome of
literature review. Thus, it is a “Semi-Automatic Trolley cum Doffing/Donning
Mechanism”. This idea is easy to assemble while also easy to move around. This also saves
time and is easy to repair at the same time too, while involving the least number of stresses.
Ring Frame Auto Doffing/Machine Installed Gadget Doffing – It’s like an addition of
a whole comb which may be responsible for adding and removing bobbins, which also
requires heavy machine changes. Thus, this method is not suitable
Reiter Automatic Doffer – This is a complete machine solution, which has an automatic
electric control, this reduces the labor but in this case the whole machine needs to be
replaced, or needs some technical changes in machine.
The other methods being used either require machine modifications, space limitations or
are costly enough to not give a cost limited perfect solution. Thus, an external gadget
addition is the best at hand possible solution. Following issues are solved:
3. The tracking wheel solution fits perfectly on the pins base (location where bobbins
are installed)
4. The doffing and donning mechanism sits perfectly on the top of the trolley, allowing
simultaneous removal and addition.
5. The trolley can be connected with motor or can also be strolled with a person.
6. The strength issues can be handled by increasing the strength of material used in
trolley construction.
Problem Defined
Designing Spatial
Designing Doffing Design Donning
Cam/Pulleys/Grippe
Mechanism Mechanism
r to pull out bobbins
The locating mechanism is mounted on the trolley. This arrangement is called as rack and
pinion. Similar to being used in cars. The rack in this case is the spinning machines bobbin
pins base, and pinion is the trolleys gear.
Similarly, we can find motor torque required, as well as the fatigue factor of human.
The chain and sprockets calculations are necessary. The chain selected in this mechanism
is ANSI 40 and the sprockets selected are also ANSI 40 since the chain should be able to
mesh well with the sprockets. The size of chain sprocket is subjected to change upon further
research during manufacturing.
The shaft of the sprockets is attached to the locating mechanism driving power with the
help of the pulleys and belts. The locating mechanism is rotated with the rack and pinion
mechanism through the spinning machine, which as a result gives turn to the sprockets.
The chain is a mounting type, which is attached to the rod of the gripper, thus in turn gripper
rotates with the chain. The gripper then follows a special path of the spatial cam. This
enables one gripper to grip the wrapper bobbin (as shown in figure 3-1) and then pull it out
of the spinning machine.
We’ve used the Geneva mechanism inside the donning mechanism to give a delay or gap
time for bobbins to fall perfectly on the pins present on the spinning machine, as was shown
in the Figure 3-2. Now, below you can see the bottom view of the Figure 3-8 to get an
understanding.
machine present in the factory, and doffing/donning trolley is going to perform its operation
on spinning machine.
The alone gadget can be seen below without the spinning machine.
3.4 Analysis
3.4.1 Model Information
There are two basic operations i.e. doffing the cops and donning the bobbins. There are
some requirements to be fulfilled during the process of doffing the cops.
19
(a) The relative motion trend in the horizontal direction between the cop and the spindle is
not allowed for protecting spindles before the cop leaves the spindle totally.
(b) Grippers cannot touch the yarn, so as not to damage the yarn.
Doffing Mechanism
The grippers capture the cops from the top to avoid the damaging of the yarn as there is no
yarn in the top region of the cop.
The grippers are attached to the sliding blocks. Furthermore, the sliding blocks are attached
to the vertical guide rail and move up and down along the rail. The sliding blocks are also
sleeved on the space curve guide rail and follow the path of the space curve guide rail. The
vertical guide rails are fixed to the mechanical chain through fixed hinges. The distance
between the two consecutive vertical rails is constant and moves along the mechanical
chain. The sliding block will follow the horizontal motion of vertical guide rails and also
move up and down following the path of space curve guide rail. In this way, the gripper
attains the three dimensional motion.
The horizontal component of the grippers’ velocity is equal to the velocity v1 of the
mechanical chain in the linear direction. When the velocity v1 of the mechanical chain is
equal to the velocity v0 of the frame, the gripper and spindle would be relatively static and
will do the doffing of cops.
20
Locating Mechanism
The locating mechanism is a gear type toothed disc, meshed up with the base of spindles,
providing the proper linear motion of the trolley so that doffing of cops and donning of
bobbins can be done in an excellent way. The toothed disc is mounted on the solid
shaft/input shaft which is fixed in between the upper and lower sheets of the trolley. The
input shaft is also connected to another shaft/output shaft through the belt and pulley
mechanism. The output shaft is further connected to the doffing system. As the output shaft
rotates, the doffing system starts its work.
Donning Mechanism
There is a spring attached from the back side of the box. The spring pushes the bobbins
towards the disc in which there are round holes. Thee bobbins get trapped into these holes.
As the disc rotates, the bobbins also rotate and reach their position where they have to fall.
Then, the installed Geneva mechanism gives dwell so that the empty bobbins can fall on
the spindles properly. In this way, the donning mechanism is achieved.
The method used in our case is the adaptive method to get the results of stresses being
applied on the sheet.
On the top of the sheet, there lies doffing and donning mechanisms so, the forces applied
on the sheet by these two mechanisms are as follows:
Table 3 - 3: Loading
3.4.8 Conclusion
From the analysis, it is concluded that the circumference of the hole made for the shaft on
which the locating mechanism is mounted and the upper surface of the sheet closer to the
hole and to the weldment of one side are the critical regions. As the shaft, mounted with
locating mechanism, has to rotate continuously so the wear will occur at this position
first. The maximum value of the stress (von-Mises) is 6.096e+04 N/(m^2) and the yield
strength of the material is 6.204e+08 N/(m^2) so, the sheet is still in the safe zone. We
have done our analysis on the upper sheet of the trolley because the number of forces is
acting on it and hence, the stress applied on it. The other parts are not comprises of such
number of forces so we have not performed the analysis on those parts.
3.4 Summary
The overall calculations required to complete the concept design are shown which include
governing mechanisms to take bobbins out and add new empty bobbins on the spinning
26
machine. Later, after the perfecting timing of these mechanisms with spinning machine, a
better idea is given through CAD models which are embedded in this section.
The trolley moves over the spinning machine making sure the wrapper bobbins are
removed from spinning machine and empty bobbins are installed. The whole trolley is
pushed by a human and as proposed can be automated too with motors.
27
Chapter 4
PHYSICAL MODEL DEVELOPMENT AND TESTING
1. Trolley
a. Main Frame
b. Wheels
c. Locating Mechanism
i. Locating wheel
ii. Transmission Pulley
iii. Shaft
iv. Bearing and housing
2. Doffing Mechanism
a. Main Structure
i. Top Plate
ii. Bottom Plate
iii. Support Rods
28
b. Transmission Shafts
c. Spatial Cam
d. Chain and Sprocket
e. Gripper Assembly
i. Attachments
ii. Gripper Shaft
iii. Gripper
3. Donning Mechanism
a. Main Structure
b. Bobbin magazine
c. Geneva Mechanism
d. Transmission Shaft
e. Transmission Pulley
The group researched about bearing housings for mounting the locating assembly on the
trolley. In the end it was decided to use UC205 universal flanged bearings. The CAD model
for UC205 was generated and the complete CAD model was tested by meshing it with the
CAD model of spinning machine to ensure the dimensional accuracy.
Calculations were performed to calculate the nearest center to center distance to the
design center to center distance that could be achieved using the selected chain and
sprockets. The center to center is distance of 9 in was chosen as the final value. The
special cam was remodeled to achieve to desired center to center distance.
After the fabrication of the trolley the dimensions of the trolley were matched with the
dimensions of the spinning machine. The height of the trolley was as per the intended
requirements.
The donning mechanism and the doffing mechanism were tested in the Workshop by giving
manual input. The donning mechanism exhibited the intended intermittent motion and the
bobbins were donned as intended. The doffing mechanism however showed some problems
as discussed in detail in Chapter 5.
4.3 Summary
To sum it all up the whole machine was broken down into modules based upon the intended
function of each module. The modules were then broken down into parts. The order of
precedence between modules was developed i.e. trolley was manufactured first then based
on its dimensions doffing and donning were manufactured. The drawings for each part of
the each module were generated and later using the drawings the parts were manufactured
in the Workshop and CNC lab at FME. The part models were iterated and remodeled at
each phase to make up for the limitations in terms of facilities and of the shelf solutions
available.
53
Chapter 5
5.1 Results
Once the modules were completed each module was tested for its specific desired
performance indicators. The critical performance indicators for the each module were as
follows:
Table 5 - 1: Result
The donning mechanism met all of its desired performance indicators. The intermittent
motion was perfectly executed. The transition of bobbins from bobbin holding
compartment to magazine was initially not smooth. After filling of edges and slight
modifications in design the transition was made smooth.
The trolley also met all its performance indicators the height was matched with the
spinning machine using a yard stick to model the height of the spinning machine.
The Doffing mechanism had some issues mainly due to unavailability of sufficient
machining facilities and desired attachment chain. However the prototype was insightful
54
in revealing certain aspects of design that could not be otherwise realized in the computer
environment. The doffing met the requirements of smooth vertical motion of the gripper
in the gripper support rods and the smooth transmission of chain and sprocket with the
exception of slight flex due to small pitch of the chain and non-specialized attachments.
5.3 Summary
Overall the first iteration of the design was somewhat successful in achieving the desired
requirements. Certain design concepts were proven and groundwork was laid for any
further work on the project. The problems that could not be understood in the computer
environment were revealed and solutions for them were developed. Design is an iterative
process so every lesson learnt is a success.
55
Chapter 6
IMPACT AND ECONOMIC ANALYSIS
The analysis of these stake holder for the social impact goes from cradle to grave, when it
comes to the product.
56
Workers
Consumers
Home Made
Done
Utility
Job Satisfaction: The doffing machine helps to remove the wrapper/filled bobbins from
the machine, and the involvement of machines ensures quick and to the mark Job. This
quick and perfect delivery of work with various options to tweak actually gives the Job
satisfaction to the workers. The same goes for the consumers, which in this case is the
factory.
Time Saving: The time can be largely allowed not to be wasted with the addition of a smart
machine, just like the advent of the technological gadgets the time is saved a lot, this semi-
automatic doffing/donning mechanism allows the workers to doff the spinning machine
with quite an ease and in no time. This ensures that least amount of their time is utilized
57
and they are able to invest this time on something better inside the factory which keeps the
employer happy.
Accurate Results: The other aspect is the accuracy satisfaction, with the machine one can
tweak enough to make the whole process automated. This helps the workers and the
consumers get the accurate results.
Less Labor Intensive: Any work which gets more labor intensive, the good spirits of the
workers are doomed. Human nature works well if the job is in accordance with the mind.
If the mind is not relaxed and the workers are doing work just because they have to do it,
despite being labor intensive or not labor intensive. However, with this product, the labor
intensity is reduced a lot, which is a positive social impact.
Home Made Utility: The thing made in home from top to the bottom, as compared to a
hidden foreign formula thing, the one made at home is preferred more. The people value
domestic things more, and same is the social impact of this product.
Goals of the Product: The definite goal which product serves, which in our case is the
automation of the spinning machines bobbins.
Analysis of the Market: The consumer analysis and the needs of the market related to the
product. Includes regional as well as the technological aspect.
Sustainability Points: The criterions over which the sustainability of the product is
analyzed, decided only after the analysis of the market.
Sustainability Assessment: The final assessment of the sustainability of the product is
done to ensure that everything goes in the right direction towards the proper survival of the
product.
6.2.2.1 Goals
The goals of the machine developed and the designed made are to automate a manual
process which is labor intensive in nature and time consuming. The goal also includes that
something to be made which is easily assembled inside the factory environment. The goal
of doffing/donning automation with the ease of making the automatic machine on the
factory floor.
59
6.2.2.2.1 Easy Availability of Parts: is one sustainability criteria which must be fulfilled
if the product serviceability character has to be kept in mind. Without the parts availability
the production of the factory floor might get delayed which can have some negative impact.
The materials mostly used in the Doffing/Donning robot are of standard qualifications and
are readily available in even low market demand areas like Gadoon. Below is the
breakdown of the parts used:
6.2.2.2.4 Required Technicians: is the workface which understands the working of the
automation. If the technicians at the factory floor don’t understand the whole process than
the life of the product is heavily impacted. The P/PC is the formula to increase the life, if
we keep on taking production (the numerator) and don’t add to the production capacity (the
denominator) then the product is going to retire too soon. Thus, the technicians with proper
training must be a part of the cycle.
The easy assembly makes sure that every component is taken apart and a new is installed
with ease.
materials like soothe in case of diesel powered and other gases. But, instead the machine
was kept fully human powered, which helps workers remain mentally fit and active and
also supports the closed environment of the factory.
The whole lifecycle of machine till the grounding time has environmental friendly base.
6.4.1 Hazards
1. Sprockets are a hazard as the rotating teeth can cause harm.
2. Geneva mechanism can pose threat, because of the gear.
3. The trolley due to unbalanced weight.
4. The metallic wheels.
5. Gripper for gripping the bobbins.
6. The chain over the sprocket teeth.
7. The lubricating oil
6.5 Summary
The Social Impact ensures that the criterion to be applied actually gives us sound outputs
to the consumer as well as workers group. The workers get satisfaction and time safety in
terms of perfection. The workers are able to do more and this gives them job surely and
security which is a huge social impact and on the whole the product is increased giving
boost to overall lives of people involved.
The sustainability analysis ensures that the parts and the manufacturing process is well
recognized at the factory and local market level so that the replacement of the parts and
things like sustainability and serviceability are well pursued. The sustainability of the
product ensures a long lasting life cycle. The automatic doffing/donning in this case has
been made and designed on common principle of availability and easy assembly.
Due to non-usage of any hazardous emissions and making sure the material used is
biologically recycled, makes this product earth friendly.
The safety measures and the identification of hazards like oil, sprockets and moving gears
and suggestions to avoid any injury with impact are actually outlines in detail to ensure the
smooth working of the machine.
65
Chapter 7
CONCLUSION
7.1 Summary
The problem at hand was that the existing machines available at the factory floor of the
textile spinning mills in Pakistan were largely manual. So the aim of the project was to
develop a solution for automating the process of doffing and donning of bobbins from the
spindles of the spinning machines. After some primary research it was found that the
solution must have the following features:
The group underwent a mechanical design exercise to develop a novel solution to the
problem. Some concepts were developed and after careful examination of each concept
the Spatial Cam based concept was finalized. A model of spinning machine was
generated in Solid Works. Initial CAD models were generated for the concept and tested
in Solid Works motion study. The dimensions were iterated and modifications were made
to improve model performance. Once the CAD models were finalized the drawings of
parts were generated and the parts were manufactured in FME Workshop and CNC Lab.
The parts were then assembled to form the individual modules. The modules were tested
for their intended aim by manual input and meshing with the actual spinning machine at
the factory floor. The modules were then assembled into a single machine.
66
The Donning mechanism worked perfectly fine and the dropping of bobbins was
successfully demonstrated. However, the doffing mechanism developed minor problems
mainly due to the limitations faced in terms of machining facility for spatial cam and
unavailability of attachment chain. The spatial cam angle turned out to be too steep and
the forces in real life were much greater than those in the simulations.
Reference
1. Hathiringe, G. (2012). Keeping pace: How Pakistan can benefit from textile automation. Express
Tribune.
2. Shimotsuma, Y., & Sakaguehi, K. (1965). Auto-doffer* as a Means of Automation. Journal of the
Textile Machinery Society of Japan, 11(5-6), 170-172.
3. Watanabe, E. (1965). Toyoda Continuous Auto-doffer. Journal of the Textile Machinery Society
of Japan, 11(5-6), 213-216.
68
Appendix
69
70