P&ID Report2
P&ID Report2
Submitted to:
Engr. Ramiro Emerson Amon
Instructor
Submitted by:
Mary Regine M. Calamba
BS ChE-IV
July 2018
Unit Operations Control
Unit operations deal generally with the transfer and change of energy and of materials
primarily by physical means but also by physical-chemical means. Examples of these are
distillation, absorption, evaporation, and more (Geankoplis, 1993). Moreover, unit operations
control is an engineering process control discipline that deals with architectures, mechanisms
of unit operations involve in a chemical processing plant that maintains the output of the
process within a desired range.
Types of P&IDs
According to McKetta (1992), these are the types of P&IDs:
I. Systems P&IDs show the production, utility, and pollution-control processes; this
category includes:
Process P&IDs – these drawings are for the actual manufacturing process: reaction,
purification, materials handling, separations and other unit operations from the
process flow diagram. They show all the process equipment, piping, controls; the
main process flow is left to right.
Utility-generation P&IDs – these drawings show utility systems such as boilers,
cooling towers, heat-transfer fluid heaters, refrigeration/brine coolers, and air
compressors, but they do not typically show how these utilities are distributed through
the plant.
Environmental P&IDs – these are for pollution-control processes such as scrubbing,
incineration, and wastewater treatment follow the same format as process P&IDs.
Vest and discharge-collection systems should follow the format of distribution
P&IDs.
II. Distribution P&IDs show how utilities, chemicals, and other non-process streams
are distributed through the plant. These drawings include all headers and sub-
headers, laid out to approximate their actual arrangement. Vents and relied
systems are also in this category:
Utility-distribution P&IDs – these show how stream, cooling water, and other
utilities are distributed. Root valves at braches should be included, but controls and
check valves on equipment lines will be shown on the process P&IDs.
Safety-system P&IDs – these define the depressing and safety-relief systems, and
include the piping networks that run from relieving devices through blow-down
drums or gas holders to vents, stacks, and other destinations.
Chemicals-distribution P&IDs – distribution is shown for utilities.
III. Auxiliary-system P&IDs show compressor lubrication and cooling systems,
hydraulic systems, pump seals, and other auxiliaries related to major equipment.
All these types are developed through several stages, or issues, during the conception,
design, and construction processes. These issues were:
1. Approval Issue – These are the ones the client checks, and revises if necessary,
before giving approval to proceed with engineering. It is often designated as Revision
0.
2. Engineering Issue – This incorporates the client’s changes and so is often called
Revision 1. It is a formal document used to start design engineering and procurement.
It normally includes everything shown on the approval issue plus instrument numbers;
line numbers; full descriptions of equipment, including motor horsepowers; piping-
specialty numbers; tie-ins; sizes of control valves and nonline-size valves; and sizes of
safety-system lines and valves.
3. Construction Issue – The first construction issue is used for final checking of designs
and drawings. Frequently, the client staff will review this issue line by line. These
completed P&IDs include all the information on the engineering issue plus details of
all packaged equipment, details for vendor drawings, and up-to-date input from
detailed design. The first construction issue is typically accompanied by several
documents including updated line-designation tables; updated (if required) specialty
items summary, instrument data sheets, and tie-in index; and preliminary steam-trap
summary. There may also be a list of revisions made since the previous issue;
alternatively, the revisions may be indicated on the drawings.
A P&ID should be clear, and for that reason, the following should not be included in the
diagram:
Instrument root valves
Control relays
Primary instrument tubing and valves
Pressure temperature and flow data
Elbow, trees and similar standard fitting
Extensive explanatory notes
Location of Devices
A single horizontal bar across any of the four graphical elements means the function
resides in the primary location category. A double line indicates an auxiliary location, and no
line places the device or function in the field. Devices located behind a panel-board in some
other inaccessible location are shown with a dashed horizontal line.
Tag Identification
Letter and number combinations appear inside each graphical element and letter
combinations are defined by the ISA standard. Numbers are user assigned and schemes vary
with some companies’ use of sequential numbering. Some tie the instrument number to the
process line number. Others may choose to adopt unique and sometimes unusual numbering
systems.
The first letter defines the measured or initiating variables. Examples include Analysis
(A), Flow (F), Temperature (T), etc. with succeeding letters defining readout, passive, or
output functions such as Indicator (I), Record (R), Transmit (T), and so forth.
Miscellaneous
Equipment is comprised of miscellaneous P&ID units that don't fit into the other
categories. This group includes hardware like compressors, conveyors, motors, turbines,
vacuums, and other mechanical devices.
A pipe is a tube that transports fluid substances. Piping can be made of various
materials, including metal and plastic. The piping group is made up of one-to-many pipes,
multi-line pipes, separators, and other types of piping devices.
P&ID Limitations
Since P&IDs are graphic representations of processes, they have some inherent
1. Not to Scale - P&IDs can't be relied on as a scale guide for where pipes, equipment or
2. Not Geometrically Accurate - P&IDs don't illustrate geometry. The level of detail
that goes into symbols for equipment will vary, but is almost never geometrically
correct.
3. Color Blind - P&IDs are not good at using color to convey meaning.
4. Not Definitive - P&IDs do not include complete specs for all the equipment in the
5. Not Drawn Consistently - Sadly, P&IDs seldom look consistent between companies.
That's because there is a lot of flexibility in how one can go about drawing a P&ID.
References
Cook, R. (2010). Interpreting Piping and Instrumentation Diagrams. Retrieved July 2018,
from https://www.aiche.org/chenected/2010/09/interpreting-piping-and-
instrumentation-diagrams-symbology
Lucid Software, Inc. (2017). What are Piping & Instrumentation Diagrams. Retrieved July
2018, from Lucidchart: https://www.lucidchart.com/pages/p-and-id