Manual de Ingenieria
Manual de Ingenieria
Conservation Department of
Service Agriculture
National
Engineering
Manual
Title 210
Foreword
NORM A. BERG,
Chief
NATIONAL ENGINEERING MANUAL
PRIMARY TABLE OF CONTENTS
GENERAL
500 INTRODUCTION
501 AUTHORIZATIONS
502 RESPONSIBILITIES
503 SAFETY
504 INVESTIGATIONS, STUDIES AND REPORTS
505 NON-NRCS ENGINEERING
506 TECHNICAL MATERIALS
MANAGEMENT
510 PLANNING
511 DESIGN
512 CONSTRUCTION
513 OPERATION AND MAINTENANCE
APPLICATIONS
TECHNOLOGY
530 HYDROLOGY
531 GEOLOGY
532 BIOLOGICAL ENGINEERING
533 SOILS ENGINEERING
534 HYDRAULIC ENGINEERING
535 LANDSCAPE ARCHITECTURE
536 STRUCTURAL ENGINEERING
537 ENVIRONMENTAL ENGINEERING
i
(210-V-NEM, Amend. 23, March 1997)
NATIONAL ENGINEERING MANUAL
PRIMARY TABLE OF CONTENTS
SUPPORT
ii
(210-V-NEM, Amend. 23, March 1997)
SUBCHAPTER A - GENERAL
500.00 General.
500.01 Scope.
500.02 Abbreviations.
501.00 General.
501.01 Scope.
501.02 Technical quality.
501.03 Compliance of engineering work with laws and
regulations.
501.04 Engineering job approval authority.
501.05 Engineering job review.
501.06 Engineering work reviewed for other agencies.
501.07 Classification of engineering jobs.
501.08 Exhibit 1 Engineering job classifications that utilize
controlling factors.
501.09 Exhibit 2 Engineering job approval authority.
501.20 General.
501.21 Scope.
501.22 Applicable standards.
501.23 Dams installed without NRCS assistance.
501.24 Special conditions.
501.30 General.
501.31 National Handbook of Conservation Practices (NHCP).
501.32 Channel stability criteria.
iii
(210-V-NEM, Amend. 23, September 1997)
SUBPART D – ENGINEERING WORK ON NATIONAL FORESTS
501.40 General.
501.41 Scope.
501.42 Water storage or transmission structures built on
national forests.
501.50 General.
501.51 Scope
501.52 Coordination with Corps of Engineers.
501.53 Requirements for assistance.
501.60 General.
501.61 NRCS Responsibilities.
SUBPART G - EXHIBITS
(Reserved)
503.00 General.
503.01 Scope.
503.02 General considerations.
503.03 Investigations.
503.04 Buried utilities.
503.05 Checklist.
503.06 State laws.
iv
(210-V-NEM, Amend. 23, September 1997)
SUBPART B - PUBLIC SAFETY AT STRUCTURE SITES
503.10 General.
503.11 Scope.
503.12 Recommended safety measures.
503.13 Maintenance of steep slopes.
503.20 General.
503.21 Scope.
503.22 Hazard potential.
504.00 General.
504.01 Scope.
504.02 Reporting problems, deficiencies, and failures.
504.03 Committee assignments.
504-04 Procedures.
504.05 Engineering report.
504.06 Report review and acceptance.
504.07 Release and distribution of reports.
504.10 General.
v
(210-V-NEM, Amend. 23, September 1997)
504.11 Scope.
504.12 Reporting major flows.
504.13 Assignments.
504.14 Procedures.
504.15 Report.
504.16 Review and approval.
504.20 General.
504.21 Survey plans.
504.22 Procedures.
504.23 Reports.
504.30 General.
504.31 Scope.
504.32 Approval procedures.
504.33 Study plan.
504.34 Reports.
504.40 General.
504.41 Scope.
504.42 Policy.
SUBPART A - INTRODUCTION
505.00 General.
505.01 State criteria.
505.02 Exchange of technical services between government
agencies.
505.03 Review of work performed by consultants and suppliers.
vi
(210-V-NEM, Amend. 23, September 1997)
SUBPART C - CRITERIA
SUBPART D - PROCEDURES
SUBPART E - EXHIBITS
506.00 General.
506.01 Definition of Terms.
506.02 Organization of permanent materials.
506.03 Metrication.
506.04 Developing NEH materials.
506.05 Distribution of materials within NRCS.
506.06 Distribution of materials outside NRCS.
vii
(210-V-NEM, Amend. 23, September 1997)
PART 500 - INTRODUCTION
SUBCHAPTER A - GENERAL
500.00 General
500.01 Scope.
500.02 Abbreviations.
500-1
(210-V-NEM, Amend. 23, September 1997)
PART 500 - INTRODUCTION
RO - Regional Office
500-2
(210-V-NEM, Amend. 23, September 1997)
PART 501 - AUTHORIZATIONS
501.00 General.
501.01 Scope.
501.08 Exhibit 1 – Engineering job classifications that utilize controlling factors (continued).
Practice Practice Name Controlling Factor Units Class Class Class Maximum
Code V VI VII Review
Capability
454 Subsidence Fill height feet 20 All All
Treatment
455 Toxic Discharge Flow cfs 100 1000 All
Control
582 Open Channel Design capacity cfs 1000 2000 All
Design velocity fps 10 12 All
516 Pipeline Pressure psi 300 All All
533 Pumping Plant Axial flow pump capacity gpm 50,000 100,000 All
for Water Control Centrifugal & turbine
pump capacity gpm 3500 5000 All
Centrifical pump static head ft 350 500 All
Turbine pump statichead ft 500 1000 All
Recreation Water supply or daily
facilities sewage treatment design
Onsite capacity 200 400 All
Offsite public (people) 400 800 All
584 Stream Channel Design capacity cfs 1000 2000 All
Stabilization Design velocity fps 10 12 All
580 Streambank and Bankfull capacity cfs 5000 20,000 All
Shoreline Bankfull velocity fps 10 12 All
Protection Water height above shoreline feet 3 5 All
608 Surface Drain, Design capacity cfs 1000 2000 All
Main or Lateral Design velocity fps 10 12 All
313 Waste Storage Storage capacity cu. ft. 2000 5000 All
Facility (thous.)
359 Waste Treatment Aerobic surface area acres 25 50 All
Lagoon Anaerobic volume cu. ft. 2000 5000 All
(thous.)
Name_________________________Title_________________Grade________Location_____________________
Delegated by__________________________Title______________________________________Date_________
(Responsible Engineer)
Concurred _____________________________Title_________________________________Date_____________
(Supervisor)
Practice Practice Name Controlling Factor Units Class Class Class Class Class Class Maximum
Code
I II III IV V VI Approval
Authority
Any practice Hazard potential as class Low Low Low Low Low Signif-
defined in §503 icant
Any practice Alter the visual resources of None None None None None All
beaches and shoreline on oceans
and the Great Lakes
560 Access Road Surface Treatment Kind Soil Gravel Asphalt Concrete All All
Length feet 2000 5000 10,000 20,000 All All
Maximum Grade percent 8 10 15 20 All All
Culvert Pipe inches 18 24 48 50 72 84
323 Agri-Chemical Tank Storage gallons 250 500 1000 2500 5000 All
Handling Facility Volume
310 Bedding Area acres 40 100 320 640 All All
317 Composting Capacity dead animals cu. ft. none 1250 2500 5000 All All
Facility Litter/Manure cu. ft. none 10,000 20,000 50,000 All All
326 Clearing & Length of Reach feet 1000 2500 5000 15,000 All All
Snagging
397 Commercial Hazard class class A A A A A B
Fishponds Effective height feet 15 20 25 30 35 50
Conduit inches 12 24 36 42 48 60
Storage X height ac. ft. 500 1000 2000 3000 All All
335 Controlled Area Controlled acres 5 10 50 160 All All
Drainage
348 Dam, Diversion Streamflow (25-yr) cfs 100 500 1000 1500 2000 3000
Flow diverted cfs 25 50 100 150 200 500
Height of drop feet 3 3 5 7 8 15
Dams and Structures
402 Dam, Floodwater Drainage area acres 20 99 320 640 12,800 25,600
Retarding Effective height feet 15 20 25 30 35 50
349 Dam, Multiple- Conduit inches 12 24 36 42 48 60
Purpose Storage X height ac. ft. 500 1000 2000 3000 All All
410 Grade Stabilization Embankment over None None None None None All
Structure active fault
501.21 Scope.
501.41 Scope.
50l.5l Scope.
501.60 General.
The National Resources Inventory And Snow Survey and Water Supply
Forecasting Manual (RISS) presents SCS policies for carrying out
snow survey and water supply forecast responsibilities.
1. PURPOSE
2. SCOPE
3. RESPONSIBILITIES
C. Joint Responsibilities.
In all programs of both Services which involve mutual
interests, it is imperative that each agency inform the other at
the first inception of a potential structure construction or
rehabilitation so that on-going cooperation can be maintained.
SUPPLEMENTATION
As needed to cover local conditions, this agreement may be
supplemented at the State level, by agreement between State
Conservationists and Regional Foresters.
DURATION
The working agreement shall become effective upon the date of the
last affixed signature and shall continue in effect until
terminated in writing: by either party upon giving 60 days'
notice to the other.
_________/S/______________ _____/S/_______________
R. M. DAVIS, Administrator JOHN R. McGUIRE, Chief
Soil Conservation Service Forest Service, USDA
4/6/77 1/24/77
Date Date
Attachment:
Exhibit A
Exhibit B
501.71. Flow chart for engineering activities between SCS and FS.
RECOMMENDED FLOW CHART EXHIBIT A
for
ENGINEERING ACTIVITIES
between
SOIL CONSERVATION SERVICE & FOREST SERVICE
PL-46
(Reserved.)
503.00 General.
503.01 Scope.
503.03 Investigations.
(5) Fill out lost card Form SCS-ENG-5, sign, and return to
SCS after the required action has been completed. Failure to
return completed postcard will result in termination of SCS
assistance.
(b) The responsible SCS employee must make sure that the
preceding steps have been carried out by the land owner or
operator or the sponsoring organizations before beginning work in
the vicinity of the buried utility.
503.05 Checklist.
503.10 General.
503.11 Scope.
(a) Post warning signs where they are clearly visible but not
visually degrading.
(e) Use low-level inlets to keep normal water level below main
inlet.
(h) Use catwalks only where absolutely necessary and use guard
rails or protective fences with a locked gate where they are
necessary.
(k) Install guard rails on the top of highwalls and steep cuts
that cannot be protected with fences.
503.20 General.
503.21 Scope.
(c) The Federal Guidelines for Dam Safety were prepared by the
Ad Hoc Interagency Committee on Dam Safety of the Federal
Coordinating Council for Science, Engineering and Technology.
The guidelines were prepared in response to a Presidential
memorandum of April 23, 1977, and were published on June 25,
1979. the guidelines were transmitted to the Federal agencies
for implementation by the President's memorandum of October 4,
1979, which stated, "... I ask that the head of each Federal
Agency responsible for or involved with planning, site selection,
design, construction, certification or regulation, inspection,
maintenance and operation, repair, financial or technical
assistance, or ultimate disposition of dams adopt and implement
the Federal guidelines, as applicable."
(3) Seeing that all levels of NRCS are aware of the need for
actions to ensure that dams installed with NRCS assistance are
safe;
(b) Consistency with the model state law prepared by the United
States Committee on Large Dams (USCOLD);
well as new ones that are built. Until a State implements its
dam-safety program, the state conservationist may wish to assist
by making inspection assistance available. NRCS assistance may
also be desirable for the initial formal inspections of new class
(b) and (c) dams. However, as a general rule, the state
conservationist should encourage the State to eventually take on
full responsibility and phase out the NRCS assistance.
1 PURPOSE
This regulation establishes a USDA Dam Safety Committee. Establishment is in
the public's interest in that it will strengthen darn safety efforts in the
Department and support the Executive Branch in the implementation of the
"Federal Guidelines for Dam Safety."
2 SPECIAL INSTRUCTIONS
Secretary's Memorandum No. 2007, February 25, 1980, is canceled and is
replaced by this regulation.
3 FUNCTIONS
This committee will coordinate and provide leadership to dam safety activities
in the Department. It will assist in defining needs and in implementing
procedures to enhance the safety of the dams under the agencies' jurisdiction.
The committee will be concerned with the agencies' administrative and
technical practices related to dam safety including design, construction,
operation, maintenance, periodic inspections, and rehabilitation of dams.
The committee will be advisory to the Secretary and to the agency heads.
4 MEMBERSHIP
The committee is to consist of the dam safety officers appointed by the agency
heads of Farmers Home Administration (FmHA), Forest Service (FS), Rural
Electrification Administration (REA), Agricultural Research Service (ARS), and
the Soil Conservation Service (SCS).
The Assistant Secretary for Natural Resources and Environment is to be the
Chairman. The Dam Safety Officer for SCS is to be Executive Secretary.
5 DAM SAFETY OFFICERS
Each of the member agencies is to name a dam safety officer. The
responsibility of this position is to see that the agency, as a matter of
policy and in actual practice, makes every reasonable and prudent effort to
enhance the safety of the dams under the agency's jurisdiction. Duties should
include surveillance and evaluation of the agency's administrative and
technical practices related to dam safety concerning the design and
construction of new damns and the operation, maintenance, periodic
inspections, or rehabilitation of existing dams. Also, the officer is to make
recommendations for strengthening safety practices and procedures and is to
maintain an inventory of agency dams.
The dam safety officer is to report directly to the agency head on matters of
dam safety. The officer is to function as an advisor to the head of the agency
and through the head of the agency to the administrative and technical units.
504.00 General.
504.01 Scope.
(f) For Class VII or VIII jobs, the state conservationist and
the head of the NTC engineering Staff are to determine the
committee membership. The head of the NTC engineering Staff is
to consult with the state conservation engineer and the Director
of Engineering about the disciplines to be included and the
membership of the committee. The state conservationist is to
arrange for the participation of the members and issue the letter
of appointment.
504.04 Procedures.
(5) Determine the time the deficiency was discovered and the
time of the last inspection of the structure.
504.10 General.
504.11 Scope.
504.13 Assignments.
504.14 Procedures.
(9) Geologic map and profiles of the control section and the
exit channel.
504.15 Report.
504.20 General
504.22 Procedures.
504.23 Reports.
504.30 General.
504.31 Scope.
(b) The study plan needs to describe fully the need, the
benefits, the approach to be taken, the anticipated schedule, and
the resources required. These must be ion sufficient detail to
permit a valid assessment of the potential for obtaining the
needed data and of the potential demands for resources--
personnel, equipment, and costs.
504.34 Reports.
504.41 Scope.
504.42 Policy.
SUBPART A - INTRODUCTION
505.00 General.
505-1
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
505-2
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
505-3
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
505-4
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
505-5
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
505-6
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
505-7
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
505-8
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
505-9
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
505-10
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
505-11
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
(b) Among the services NRCS engineers do not provide are the
following:
505-12
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
SUBPART C - CRITERIA
505-13
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
SUBPART D - PROCEDURES
505-14
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
505-15
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
505-16
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
505-17
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
SUBPART E - EXHIBITS
1. PURPOSE
The purpose of this agreement is to establish procedures for an
exchange of technical services between the Natural Resources
Conservation Service (NRCS) and the Forest Service (FS). Either
agency may provide technical assistance depending on the
location, scope, and complexity of the work and the availability
of necessary skills. This interdepartmental agreement will not
alter and/or change the delegations of authority or agency policy
of practice in the planning, design, installation, or maintenance
of works of improvement. The intent of this exchange is to
expedite and improve technical work of the agencies by utilizing
the expertise of the personnel skills of both agencies and by
enhancing on-the-job training.
2. SCOPE
3. PROCEDURE
FS regional foresters and/or area directors and NRCS state
conservationists are normally responsible for initiating and
505-18
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
4. SUPPLEMENTS
505-19
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
5. DURATION
505-20
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
SUBPART E – EXHIBITS
MEMORANDUM OF UNDERSTANDING
between
UNITED STATES DEPARTMENT OF AGRICULTURE
NATURAL RESOURCES CONSERVATION SERVICE (NRCS)
and
LAND IMPROVEMENT CONTRACTORS OF AMERICA (LICA)
I. PURPOSE
II. GENERAL
505-21
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
III. RESPONSIBILITIES
505-22
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
505-23
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
505-24
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
SUBPART E - EXHIBITS
USDA
NATURAL RESOURCES CONSERVATION SERVICE
400 Water Street
Anytown, Anystate 00000
Current Date
Name
Address
Dear:
Thank you for your support in protecting our soil and water
resources.
Sincerely,
District Conservationist
505-25
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
SUBPART E - EXHIBITS
USDA
NATURAL RESOURCES CONSERVATION SERVICE
400 Water Street
Anytown, Anystate 00000
Current Date
Name
Address
Dear
You have requested cost sharing from the Farm Service Agency
(FSA) for practice 313, Waste storage Facility. You have
indicated that your system will be designed by a private
consultant. The Natural Resources Conservation Service (NRCS)
welcomes the involvement of your consultant. However, you need
to be aware that the NRCS will require that the consultant be
responsible for meeting NRCS standards and specifications and for
certifying the work.
Prior to construction
505-26
(210-V-NEM, Amend. 23, September 1997)
PART 505 - NON-NRCS ENGINEERING SERVICES
During Construction
After Construction
2. NRCS will make a field visit to the site and will certify
completion to FSA based on the consultants certification
statement.
Sincerely,
District Conservationist
cc:
505-27
(210-V-NEM, Amend. 23, September 1997)
PART 506 – TECHNICAL MATERIALS
506.00 General.
where,
(1) The primary table of contents for the NEH shall parallel
the table of contents for this NEM in part names and Part
numbers, except Part numbers will be 6xx. The primary table of
contents for the NEH will also contain additional part names and
part numbers for field handbooks which contain engineering
material, but are intended primarily for use by non-engineers.
506.03 Metrication
510.00 General
510.01 Planning scope.
510.02 Documentation.
510.03 Engineering data to support plans.
510.04 Criteria.
510.05 Cost estimates.
510.06 Post design life considerations.
SUBPART A - PROCEDURES
511.00 General.
511.01 Design objectives.
511.02 Design stages.
511.03 Operating procedures.
511.04 Design analysis.
511.05 Design checking and review.
511.06 Independent reviews.
511.07 Design criteria.
511.08 Construction plans.
SUBPART B - DOCUMENTATION
511.10 Scope.
511.11 Design folders.
SUBPART C - INSTRUMENTATION
511.20 General.
511.21 Scope.
511.22 Need for reliable instruments.
511.23 Use of instrumentation.
511.24 Instrumentation plans.
511.25 Instrumentation monitoring and reporting.
SUBPART A - INTRODUCTION
512.00 General.
512.20 General.
512.21 Evaluation procedures.
512.22 Waivers of material certification.
512.23 Prequalification of materials.
512.50 General.
512.51 Applicability.
512.52 Documentation.
512.53 Disposition.
(Reserved)
510.00 General
510-1
(210-V-NEM, Amend. 23, September 1997)
PART 510 - PLANNING
510.02 Documentation
510-2
(210-V-NEM, Amend. 23, September 1997)
PART 510 - PLANNING
510.04 Criteria
510-3
(210-V-NEM, Amend. 23, September 1997)
PART 510 - PLANNING
510-4
(210-V-NEM, Amend. 23, September 1997)
PART 510 - PLANNING
510-5
(210-V-NEM, Amend. 23, September 1997)
PART 511 - DESIGN
SUBPART A – PROCEDURES
511.00 General.
(c) The principles defined in this part apply to all sizes and
complexities of designs. The detail to which the procedures are
to be followed varies according to the need. The simplest
conservation practice may require only a few notes, computations,
and drawings. Larger and more complex works may require numerous
notes, computations, and drawings to complete all stages of the
design. Likewise, the complexity of site conditions and
engineering along with the number of alternatives and
organizational units affects the intensity and duration of work
at each design stage.
(c) Stage one includes data collection and evaluation for all
information on:
(1) Physical data. Topographic, hydrologic, visual,
biologic, geologic, and archeologic data.
(a) The design analysis defines the scope of the design and
evaluates the relationships of the principles that determine the
design. It consists of a step-by-step description of the
procedures used. Each step is to be described concisely and
completely.
(1) That the basic data and assumptions were used in the
computations.
(2) That mathematic computations are accurate.
(3) That details are consistent from sheet to sheet.
(4) That drawings comply with the design.
(5) That drawings comply with the specifications.
(6) That computed critical elevations, costs, and quantities
are accurate.
(7) That construction drawings are complete.
511.10 Scope.
511.20 General.
511.21 Scope.
SUBPART A - INTRODUCTION
512.00 General.
512.01 Scope.
512.02 Definitions.
512.14 Partnering.
512.20 General.
(c) New products that have not been used previously for
conservation practice application must be evaluated and approved
for use before being specified. Trial use of new products must
be under the approval of the state conservation engineer and
shall be supported by industry or applicable standards,
specifications, evaluation data and/or reports.
512.30 General.
512.31 Definitions.
512.41 Records.
512.50 General.
512.51 Applicability.
512.52 Documentation.
(b) Geology.
512.53 Disposition.
(Reserved.)
520.00 General.
520.01 Minimizing erosion and pollution during construction.
520.10 General.
520.11 Scope.
520.12 Description.
520.13 Types of measures.
520.14 Risk to life and property.
SUBPART C - DAMS
520.20 General.
520.21 Definition and classes.
520.22 Design criteria.
520.23 Classification.
520.24 Special considerations.
520.25 Clearing reservoirs.
520.26 Independent reviews for dam safety.
520.27 Emergency action plans--class (c) dams.
520.28 Potential impact area--class (a) dams of inventory size
and all class (b) dams.
521.00 General.
521.01 Pollution abatement in conservation operations.
521.02 Pollution abatement in project activities.
521.03 Effect of NRCS activities on water quality.
521.04 Effect of water quality on NRCS activities.
522.00 General.
522.01 Authority and request for assistance.
522.02 Responsibility.
522.03 NRCS technical review.
522.04 Reservoir operation guide review.
522.05 Reservoir operation guide contents.
SUBPART B - (RESERVED)
523.00 General.
523.01 Technical assistance.
523.02 Irrigation guides.
523.03 Assistance on irrigation projects.
523.04 Water management for salinity control
523.05 Irrigation training.
(Reserved)
(Reserved)
(Reserved)
(Reserved)
520.00 General.
520.10 General.
520.11 Scope.
520.12 Description.
(e) Combinations of depth (in feet) and velocity (in fps) can
be used as indicators of risk. Products of 5 or 7 have been used
as a limit for "people safety" and values of l5 or 20 for
"structural safety."
520.20 General.
(2) Class (a) dams more than 6 feet in overall height and
with a storage capacity of 50 acre-feet or more; and
(a) Class (a) earth dams with a product of storage times the
effective height of the dam of less than 3,000 and with an
effective height of the dam of 35 feet or less are to meet or
exceed the requirements of Practice Standard 378, Pond (NHCP).
(b) Class (a) earth dams whose product of storage times the
effective height of the dam is 3,000 or more; those more than 35
feet in effective height; and all Class (b) and (c) dams are to
meet or exceed the requirements of Technical Release No. 60.
(c) Dams of materials other than earth are to comply with the
applicable portions of Practice Standard 378 and Technical
Release No.60. Other features are to meet or exceed the
requirements as stated in other applicable SCS standards.
520.23 Classification.
(3) Class (c) dams and those with permanent storage are not
to be constructed over an active fault without the concurrence of
the Director of Engineering.
(l) The state conservation engineer and the head of the NTC
Engineering Staff are to make a joint recommendation to the state
conservationist on whether an independent review is needed. The
recommendation is to be supported by a justification statement
and include a brief description of the site, the proposed
structure layout, composition of technical specialists making up
the view team, and other essential data. This is to become a
part of the design folder. An independent review may be
initiated at any state of design or construction.
(ii) For dams not in series but which would affect a common
downstream area, it is usually adequate to consider the failure
of each dam individually unless special circumstances would
warrant multiple failures.
520.30 General.
520.3l Definition.
522.00 General.
522.02 Responsibility.
522-1
(210-V-NEM, Amend 19, November 1991)
PART 522 – SNOW SURVEY AND WATER SUPPLY FORECASTING
522-2
(210-V-NEM, Amend 19, November 1991)
SUBPART A – RESERVOIR OPERATIONS GUIDE FOR SNOWMELT
(a) Introduction
(1) Background for guide request
(iv) Recreation
(v) Other
522-3
(210-V-NEM, Amend 19, November 1991)
PART 522 – SNOW SURVEY AND WATER SUPPLY FORECASTING
(iii) Pump
(iv) Gated outlet
(v) Other
(iv) Seepage
522-4
(210-V-NEM, Amend 19, November 1991)
SUBPART A – RESERVOIR OPERATIONS GUIDE FOR SNOWMELT
(vi) Other
(2) Topography
(i) Geology
522-5
(210-V-NEM, Amend 19, November 1991)
PART 522 – SNOW SURVEY AND WATER SUPPLY FORECASTING
(i) Diversions
522-6
(210-V-NEM, Amend 19, November 1991)
SUBPART A – RESERVOIR OPERATIONS GUIDE FOR SNOWMELT
(i) Average
(i) April-July
(ii) May-July
(iii) June-July
522-7
(210-V-NEM, Amend 19, November 1991)
PART 522 – SNOW SURVEY AND WATER SUPPLY FORECASTING
(9) Summary
(i) Guide is an operational tool for risk
assessment and project regulation
522-8
(210-V-NEM, Amend 19, November 1991)
SUBPART A – RESERVOIR OPERATIONS GUIDE FOR SNOWMELT
(1) Recommendations
(h) APPENDICES
522-9
(210-V-NEM, Amend 19, November 1991)
PART 522 – SNOW SURVEY AND WATER SUPPLY FORECASTING
(i) Averages
(j) Approval
522-10
(210-V-NEM, Amend 19, November 1991)
SUBPART A - RESERVOIR OPERATION GUIDE FOR SNOWMELT
__________________________ ______________________________
Operator Soil and Water Conservation
District
__________________ ___________________
Date Date
__________________________ ______________________________
State Conservationist State Conservation Engineer
__________________ ___________________
Date Date
522-11
(210-V-NEM, Amend 19, November 1991)
PART 523 - IRRIGATION
523.00 General.
(Reserved.)
530.00 General.
530.01 Available hydrologic information.
503.02 Hydrometeorological instrumentation.
503.03 Hydrologic reports.
530.10 General.
530.11 Hydrologic procedures.
530.12 Hydrologic criteria.
531.20 General.
531.21 Ground water management.
531.22 Site investigations.
531.23 Resource Investigations.
531.24 Procedures.
531.40 General.
531.41 Scope.
531.42 Layered mineral deposits.
531.43 Liquid or gaseous deposits.
531.50 General.
531.51 Guidelines.
531.60 General.
531.61 Scope.
531.62 Receiving facilities.
531.63 Packaging.
531.64 Shipment.
531.65 Overseas samples.
531.66 Equipment used to collect or move soil.
531.67 Regulated counties and APHIS district offices.
531.70 General
531.71 Damages caused by erosion and sediment.
531.72 Sediment storage allocation for reservoirs.
531.73 Sedimentation and erosion studies for channel
modification.
531.74 Effects of land treatment and structural measures on
sedimentation.
531.75 Reservoir sedimentation surveys.
531.76 Investigations related to water quality.
531.77 Structural deficiencies caused by sedimentation.
531.78 Special erosion and sediment studies.
531.80 General
531.81 Reports
532.00 General.
532.01 NRCS Biological and Agricultural engineering assistance.
532.02 Non-NRCS Biological and Agricultural engineering
assistance.
533.10 General.
533.11 Data collection.
533.12 Testing.
533.13 Soil engineering analyses.
533.14 National benefit activities.
533.20 General.
533.21 Scope.
533.22 Engineering responsibilities.
(Reserved)
535.00 General.
535.01 Definitions.
535.02 Services.
535.03 Technical quality.
536.00 General.
536.01 Standard detail drawings.
536.02 Use of standard detail drawings.
536.03 Adaptation of standard detail drawings.
536.04 Revision of standard detail drawings.
536.05 Availability of standard detail drawings to the public.
536.06 National standard detail drawings.
536.07 NTC standard detail drawings.
536.08 4100 Series standard drop-spillway drawings.
536.09 State standard detail drawings.
536.10 Standard detail drawings prepared by non-NRCS engineers.
536.11 Reserved.
536.12 Reserved.
536.13 Reserved.
536.14 Reserved.
536.15 Reserved.
536.16 Reserved.
536.17 Reserved.
536.18 Reserved.
536.19 Reserved.
536.20 Design Criteria for reinforced Concrete.
530.00 General.
530-1
(210-V-NEM, Amend. 23, September 1997)
PART 530 - HYDROLOGY
530-2
(210-V-NEM, Amend. 23, September 1997)
PART 530 - HYDROLOGY
530-3
(210-V-NEM, Amend. 23, September 1997)
PART 530 - HYDROLOGY
may be used for instruments and for analysis of data needed for
planning and designing a reservoir. These funds should be
included as part of the engineering services cost of the
structure. Snow survey or other appropriate federal funds may be
used.
530-4
(210-V-NEM, Amend. 23, September 1997)
PART 530 - HYDROLOGY
(b) Reports may include, but are not limited to, the
following:
530-5
(210-V-NEM, Amend. 23, September 1997)
PART 530 - HYDROLOGY
530.10 General.
530-6
(210-V-NEM, Amend. 23, September 1997)
PART 530 - HYDROLOGY
530-7
(210-V-NEM, Amend. 23, September 1997)
PART 531 - GEOLOGY
531.00 General
The scope and intensity of geologic investigation shall be consistent with the
geologic and geomorphic complexity and stability of the site; pertinent social,
economic and safety considerations; size and purpose of the structure, practice or
project; kinds of construction materials to be used; and the potential for damage or
loss of life if the structure or practice fails.
A geologic reconnaissance described in 531.02 is required for all dam sites, and
conservation practices, components of practices, or structures that involve
significant ground construction activity, such as ponds, pond sealing, waste storage
facilities, streambank and shoreline protection, stream channel stabilization, wetland
development or restoration, and mine reclamation.
Geologic reconnaissance includes the collection and review of existing data; a site
visit to assess engineering and geomorphic feasibility of the site; and consideration
of how operation of the proposed project, structure, or practice might adversely
impact local resources, particularly soil, surface waters (including the sediment-
water balance), and ground water.
Before going to the field, all available pertinent technical materials, such as
regional and state geologic maps, topographic maps, well logs, aerial photographs,
satellite imagery, soil surveys, water quality reports, mineral resource surveys, and
published and unpublished reports of the site or similar sites are reviewed.
A site visit shall be conducted to assess the engineering significance of the geologic
setting, topography, site drainage, soil and rock materials, and other conditions in
the area that can affect the suitability of the site for its intended use. The local
physical resources in the area, including sediment, soils, surface waters, and ground
water are identified, as well as offsite resources that may be impacted by project
implementation. The resources are assessed in terms of the potential adverse impacts
that operation of the proposed project, structure, or practice may have on them.
The results of the geologic reconnaissance are used to assess the need for more
detailed investigation and whether additional technical expertise is needed. These
needs are based on site complexity and experience of personnel in the project area.
The findings, conclusions, and recommendations for additional investigation are
documented as prescribed in 531.15.
Documentation includes a geologic map prepared according to 531.14. The map is filed
with the geologic report.
All outcrops, cut banks, and other surface exposures are thoroughly inspected.
Erosion conditions, landslides, seeps, springs, and other pertinent conditions in and
adjacent to the watershed are examined. The information is gathered in the context of
site feasibility for project implementation and engineering performance.
The investigation shall be sufficiently detailed to furnish the planning team with
information for making sound preliminary designs and cost estimates.
All geologic conditions that may influence design, layout, construction, and safe
functioning of the structure shall be investigated, characterized, and documented.
Documentation shall include a geologic map prepared according to 531.14 and a geologic
report that conforms to 531.15.
The tools used in subsurface investigation vary from site to site depending on local
conditions, and may include geophysical surveys, such as electromagnetic, ground
penetrating radar, and seismic refraction or reflection; power equipment, such as core
drills, backhoes, bulldozers, and augers; cone penetrometers; and hand tools. The
results of all geophysical surveys shall be verified by penetrative exploration or
correlation with nearby outcrops and other physical features.
Seepage potential of the permanent pool area and dam site of water holding reservoir
sites shall be evaluated.
(210 - V-NEM, November, 1999)
531-2
PART 531 - GEOLOGY
Exploratory bore holes shall be not be left uncovered overnight. At completion of the
investigation, all test pits, exploratory bore holes, and trenches are back filled in such a
manner as to protect ground water quality and to remove the physical hazard to people, animals,
and machinery.
531.05 Requirements for geologic investigation during construction and project implementation
Geologic investigation shall be conducted during construction and the project implementation
phase on all Group I dams as defined in 531.20 to verify all assumptions and interpretations made
in previous investigations and to identify differing conditions that may impact the long term
performance of the structure. Differing geologic conditions that require design modification
shall be documented in the as-built records.
Engineering structures and practices requiring repair or rehabilitation may need additional
geologic information to support design changes that may result from a change to a higher
structure class, changes in criteria or standards, or a lack of specific information in the area
of interest.
The determination of the adequacy of available geologic information is conducted as part of the
design review process, explained in 501.05. The design engineer and geologist shall jointly
determine the need for a geologic plan of investigation based on the results of the review.
Policies provided in Subpart B - Dam Site Investigations, and Subpart D - Erosion and
Sedimentation Investigations, apply for geologic investigations for repair or rehabilitation of
engineering structures and practices. Geologic information is gathered to address
• the needs for sound engineering design and
• the potential impacts on applicable local physical resources, including soil quality,
sediment quality, ground water and surface water quality, and stream channel stability.
Investigations of impoundment structures and practices shall address the sediment pool in terms
of:
• The location, type, and quality of sediment that will be affected by rehabilitation
measures.
• The location, type, and quality of sediment that will be exposed to erosion and
• downstream transport.
• The location, type, and quality of sediment that will be dredged or excavated to reclaim
designed water or sediment storage.
• The effects of changes in the sediment-water balance on the geomorphic stability of the
stream channel downstream of the site.
The geologic report is filed with the engineering records for the repaired or rehabilitated
structure or practice.
Engineering structures and practices selected for decommissioning may involve the complete or
partial removal of a structure, or a change in its original design function.
The determination of the adequacy of available geologic information is conducted as part of the
design review process, explained in 501.05. The design engineer and geologist shall jointly
determine the need for a geologic plan of investigation based on the results of the review.
Policies provided in Subpart B - Dam Site Investigations, and Subpart D - Erosion and
Sedimentation Investigations, apply for geologic investigations for decommissioning of
engineering structures and practices. Geologic information is gathered to address:
• the needs for sound engineering design and
• the potential impacts on applicable local physical resources, including soil quality,
sediment quality, ground water and surface water quality, and stream channel stability.
The geologic report is filed with the engineering records for the decommissioned
structure or practice.
Criteria for erosion, sediment, and pollution control contained in 520.01 apply during
geologic site investigations.
(a) Soil
Soil material shall be classified in the field according to the Unified Soil
Classification System, ASTM D 2488, Standard Practice for Description and
Identification of Soils (Visual-Manual Procedure). Samples for laboratory testing and
analysis are classified according to ASTM D 2487, Standard Test Method for
Classification of Soils for Engineering Purposes, as explained in 533.01.
(b) Rock
Rock material is classified by common rock type names according to a simplified
geologic scheme, such as NEH Part 628, Chapter 52, table 52-1. Rock used for specific
engineering purposes in NRCS work is classified by TR-71, Rock Material Field
Classification System.
All rock cores are labeled and photographed according to ASTM D 5079 and ENG Geology
Note 5. Photographs are annotated and filed with the project design folder. Policy
provided in 533.11, Soil Mechanics Data Collection, applies during geologic
investigation.
The storage and maintenance of soil and rock samples cannot be continued indefinitely. However,
their engineering significance and replacement costs need to be carefully considered prior to
disposal.
Soil samples stored at project locations for purposes of site showings and material
classification may be disposed of after completion of the construction contract.
Rock core stored at project locations for purposes of site showings and material classification
may be disposed of after photographic documentation and logging of the core are completed or
after completion of the construction contract.
Soil and rock samples tested at NRCS facilities may be disposed of at the discretion of the
facility.
For sites with special construction or material problems, the submitting NRCS office may request
the testing facility to hold the samples for a specified period. Such samples are disposed of by
the facility with the concurrence of the submitting office. All soil and rock samples are stored
and discarded in compliance with all applicable pest control regulations, as explained in 531.13.
Before soil samples and rock cores are discarded, they may be offered to a state geological
survey or geological repository; school, college, or university geology, engineering,
archaeology, or anthropology department; or any interested civil or cultural organization.
531.13 Quarantines on movement of soil samples, and soil sampling and moving equipment.
Soil movement regulations are designed to stop the human-assisted spread of agricultural pests,
such as imported fire ant, corn cyst nematode, golden nematode, witchweed, and Mexican Fruit Fly.
The shipping or transport of all soil samples and soil moving equipment under any NRCS activity
or program shall conform to regulations of the Animal and Plant Health Inspection Service
(APHIS), USDA.
Soil samples from regulated areas, shall be shipped only to USDA approved facilities for
processing, testing, or analysis. The current list of regulated areas is available from APHIS:
US Department of Agriculture
Animal and Plant Health Inspection Service
Plant Protection and Quarantine Programs, Permit Unit
4700 River Road
Riverdale, MD 20737
Telephone 301-734-8896
Internet Location: Http://www.aphis.usda.gov
Soil samples from regulated areas are not sent or transported to any facility without first
determining whether the receiving facility is approved by APHIS. The following NRCS facilities
are approved by APHIS to receive soil samples:
National Soil Mechanics Center (NSMC) - Lincoln, NE
NSMC - Ft. Worth, TX
National Soil Survey Center - Lincoln, NE
The NSMC, Lincoln, NE is the only NRCS facility that accepts Pacific Basin and foreign soil
materials.
Private facilities shall apply to the appropriate APHIS headquarters for approval in order to
receive NRCS soil samples.
Land owners and operators who receive NRCS technical assistance but ship their own soil samples
to private facilities must be informed of these regulations.
(a) Packaging
All soil samples from regulated areas must be shipped so that no spillage or breakage occurs in
transit. Undisturbed samples in moisture-proof containers may be shipped in the usual manner.
Other samples must be shipped in containers that resist tearing and puncturing. Canvas bags
inside wooden or metal boxes are most desirable. Small samples may be shipped inside heavy
plastic bags inside strong canvas bags, each tied separately and securely.
Soil samples taken from below a depth of 3 ft in regulated areas may be shipped as UNREGULATED
samples if care is taken not to contaminate them while collecting and preparing them for
shipment. If there is any question of contamination, ship as REGULATED.
(b) Labeling of samples. All samples shall be labeled with the following information: date
of sample, project location (project name, county, state) depth interval of sample, sampling
location number, name of securing sample.
(c) Shipment. The exterior of each shipping carton containing regulated soil samples must
be clearly marked CONTENTS: SOIL SAMPLES.
(1) Domestic samples. Each sample is identified by stamping or printing the word
REGULATED in red on both the inside and outside tags. Samples sent to the National Soil
Mechanics Center Labs shall be identified as REGULATED on Form NRCS-ENG-534, Soil Sample List,
and Form NRCS-ENG-356, Request for Soil Mechanics Laboratory Test.
(2) Overseas samples. All soil samples from any foreign source, offshore possession,
or Hawaii shall be shipped under permit. Form PPQ-525 is required and is obtained from APHIS
(address given in 321.14 above)
Equipment and hand tools used to collect soil samples in regulated areas shall be thoroughly
cleaned of all soil residues at the collection site before removal to unregulated areas.
Soil-moving equipment being moved from regulated areas to unregulated areas shall be cleaned of
all soil residues at the work site from which it is being moved. These regulations shall apply to
NRCS-owned and operated equipment, as well as to the tools and equipment of drilling and earth-
moving contractors.
Contractors shall be advised of quarantine requirements through the applicable clause in bid
notifications and contracts as covered under GENERAL or SPECIAL PROVISIONS.
Contact APHIS (address above) for the current list of counties under Federal domestic plant
quarantine, including address and phone number of APHIS headquarters in each state.
An engineering geologic map is drawn to identify and spatially represent zones of geologic
material that meet similar engineering performance criteria. In some cases, a geomorphic map,
showing landforms, slope stability, and topography is appropriate. The map shows the locations
of all measurements, samples, or observations, as well as the data collected. Supplements may
include structural contour maps showing elevations on geologic contacts, tops of key beds, or
other surfaces of interest; and isopach maps showing contoured thickness of a mapped unit.
Cross-sections, profiles, fence diagrams, columnar sections, perspective drawings, and other
illustrations may be used to represent geologic features.
A geologic evaluation map is a plan view diagram or drawing, representing a given area, depicting
the orientation and location of key geologic and related features that could significantly affect
the performance of a proposed or existing structure or practice. It may include profiles, cross-
sections, or other supplemental figures to help illustrate the information. A geologic
evaluation map is used to support planning documents, such as an environmental assessment or
environmental impact statement.
Maps are prepared on the best available topographic base map or aerial photograph using standard
signs and symbols, at a chosen scale and projection. Plane table, air photo, GPS, and
conventional surveying techniques may be applied to develop a detailed geologic map.
For small structures at low hazard sites, a site sketch is considered adequate. A site sketch is
drawn free-hand from observation or uncontrolled surveys showing only approximate space, scale,
and orientation relationships of the main features of an area.
The accuracy and scale of a map shall be commensurate with the scope of the project and
complexity of the site.
Maps drawn to scale include a graphic scale and a verbal statement using different units such as
1 inch equals 1 mile or a representative fraction such as 1:200. Maps with exaggerated vertical
scales are explained with a verbal statement such as, vertical scale 10x horizontal scale.
All maps and sketches shall include a key to symbols used and a north arrow.
All geologic reports of investigation are prepared, signed, and dated by the
investigating geologist or person holding the appropriate engineering job-approval
authority for the class of structure, as outlined in 501.04.
The general outline and contents of the report should conform to guidance presented in
ASTM D 420. As a minimum, the report shall include the following headings.
Location of the area investigated. The location is given in terms pertinent to the
project, and may include maps, sketches, and photographs on which test pits, bore
holes, and sample areas are plotted.
Geologic terms and symbols not specifically defined in NRCS literature shall conform
to ASTM D 653, Standard Terminology Relating to Soil, Rock, and Contained Fluids; the
American Geological Institute (AGI) Glossary of Geology; or current AGI Data Sheets.
To establish criteria for geologic investigation and sampling, dam sites are categorized into two
groups according to the fill height of the structure, construction materials, purpose of
structure, and structure class.
Group II dam sites include all other types of dams that do not classify as Group I, such as
embankment structures of Conservation Practice Standards 378, Pond; Waste Storage Facility, 313;
and Grade Stabilization Structure, 410.
All preliminary, detailed, and construction (as-built) site investigations shall be conducted
under the supervision of a qualified geologist.
A qualified geologist is defined as an individual who meets the minimum requirements for the
practice of geology as defined by the State Board of Registration of the state in which the
individual resides. In the absence of state registration requirements or a state definition of
geologist for the practice of geology, a qualified geologist shall meet the requirements for the
title of Certified Professional Geologist, as defined by the American Institute of Professional
Geologists.
Subsurface exploration shall be of sufficient intensity to determine all conditions that can
influence the design, layout, construction, and functioning of the proposed structure.
Before the investigation is completed, the geologist, the engineer designated for soil mechanics
leadership, and the design engineer shall jointly review the findings of the investigation to
determine the adequacy of the sampling program for testing. The data are reviewed for adequacy
for use in all stages of design and construction.
All soil and rock units shall be characterized beneath the entire base of the structure and
abutments. For all earth fill dams in Group I, borings at all stations within the footprint of
the structure shall be extended to depths equal to or greater than the equivalent proposed height
of fill associated with the points of boring, or to hard, massive, unaltered rock or similar
limiting layer. Borings shall be extended deep enough into rock to establish whether it is in
situ.
For all concrete dams, borings shall extend to depths equivalent to at least 1.5 times the
proposed effective height of the dam as measured from the maximum proposed depth of excavation.
All geologic materials and features with engineering significance at or near the site are
characterized, documented, and assessed according to current industry standards.
Characterization includes classification and determination of material properties and mass
properties, especially stratigraphic and structural discontinuities, such as faults, joints, and
fractures with engineering significance.
Sufficient borings are made along the proposed centerlines of drop inlets or other conduits to
provide correlation of geologic materials from the riser to the outlet and to a depth equal to
the zone of influence of the structure.
Sufficient borings are made along the proposed centerline of dams to provide
correlation of geologic materials and to define the rock surface profile.
At least one bore hole is placed at the riser, at the intersection of the centerlines
of the dam and conduit, and at the outlet.
Delineate the incompressible rock surface where it occurs within the depth of
influence of the structure.
Locate earth material proposed for use as fill and determine its quantity and
engineering suitability using appropriate soil mechanics tests, as needed.
Determine the depth to ground water, seasonal variation of water table, and extent and
character of aquifers within the zone of influence of the structure.
Evaluate the need for controlling ground water during construction and determine the
need for controlling moisture content in borrow material.
Evaluate whether economic mineral deposits, including sand and gravel, occur within
the area of influence, or would be preempted or otherwise impacted by the project.
Assess the influence of rock mass properties on the slope stability of rock materials
in the spillway cut slopes.
Evaluate the need for hydraulic pressure testing in rock foundations and abutments of
proposed dams for water storage reservoirs.
531.22 Requirements for geologic investigation during construction of all Group I dam
sites.
The geologist shall prepare an as-built geologic report. All findings and
interpretations that differ from those reported in previous geologic investigations
shall be identified and explained. Differing conditions with engineering and
geomorphic significance are, to the extent possible, measured and assessed in the
field, and documented in the report. The report shall include logs, cross-sections,
engineering geologic maps, and photographs, as needed, to support the documentation.
Maps and report shall conform to 531.14 and 531.15, respectively. The report is filed
as a supplement to the engineering design folder of the project (explained in 512.52
b).
531.24 Requirements for logging soil and rock at Group I dam sites
(a) All Group I dam sites for sampling soil and rock at all Group I dam sites:
• Representative samples are obtained for classification purposes of all geologic
materials identified in the foundation, borrow, relief well, principal spillway,
and auxiliary spillway areas.
• Undisturbed samples for shear tests are obtained from all strata of fine grained
soils of questionable stability in the foundation within a depth equivalent to
one-half the maximum fill height of the dam, as measured from low point on
centerline.
(b) All Group I dam sites that have permanent storage. For all Group I dam sites
in which storage other than sediment pool storage is to be incorporated into the
design and in which significant leakage is suspected:
• Samples are obtained of materials underlying the permanent pool area to determine
reservoir sealing requirements.
(c) Structure class a, b, and c dam sites. For all structure class a dam site
that have a maximum fill height equal to or greater than 35 ft, and for all structure
class b and c dam sites:
• Samples for compaction and shear tests are obtained from the borrow areas and
auxiliary spillway areas.
• Undisturbed samples for consolidation tests are obtained of all compressible fine
grained materials from the foundation within a depth equivalent to the maximum
height of the dam (as measured from low point on centerline). If compressible
materials are suspected to occur at greater depths, drilling and sampling of the
compressible materials are conducted to depths within the zone of influence.
(d) Group I dam sites that have a maximum fill height greater than 20 ft
Undisturbed samples for compaction tests are obtained for all materials of
questionable shear strength, such as soft clays and soft silts, in the foundation of
the dam.
(e) Other Group I dam sites for any other type of Group I dam site not listed in
521 (a-d):
• Samples for compaction tests are obtained from borrow and auxiliary spillway areas
if information and experience in the area are inadequate to conclusively predict
the engineering behavior of the materials.
531.25 Requirements for logging soil and rock at Group II dam sites
For all Group II dam sites, samples are not required if adequate information and
experience in the area are available. If such information and experience are
unavailable or if questionable conditions occur, sampling is conducted the same as for
Group I dam sites.
(a) Seismic Assessment. All dams in seismic zones 3 and 4, Alaska, Puerto Rico,
Virgin Islands, and Hawaii, and all structure class c dams in seismic zone 2 require
special investigations to determine liquefaction potential of cohesionless strata,
including very thin layers, and the presence at the site of any faults determined to
be active in Holocene time. The potential for earthquake induced seiches of the
reservoir pool shall be evaluated. A map shall be prepared indicating the location of
all intensity V or magnitude 4 or greater earthquakes of record, and any historically
active faults within a 100 km (65 mi) radius of the site. The geologic report also
shall summarize any other possible earthquake hazards, such as ground compaction,
landslides, and excessive shaking of unconsolidated materials. For slope stability
analysis, earthquake information, including acceleration, duration, and recurrence
interval, is collected from the US Geological Survey
(b) Subsidence. Assess the potential for ground surface subsidence caused by past
or future extraction of solid minerals or fluids, including ground water and natural
gas.
(c) Collapsible Soils. Evaluate the potential for collapse upon saturation or
wetting of certain unconsolidated materials associated with deposits such as, alluvial
fans, terraces, and eolian materials in arid and semiarid regions. If the potential
exists, investigate and conduct appropriate sampling for laboratory analysis to
provide quantitative information for design and construction.
(d) Earth Spillways. For all Group I dams as defined in 531.20, the geologist
provides specific geologic information to the design engineer for the stability
analysis and integrity analysis of auxiliary spillways, as explained in NEH Part 628,
Chapters 50 (Earth Spillway Design) and 51 (Earth Spillway Erosion Model, SITES
program). All earth materials occurring beneath the spillway down to the elevation of
the flood plain are mapped by the headcut erodibility index according to NEH Part 628,
Chapter 52, Field Procedures Guide for the Headcut Erodibility Index. The
investigation shall be sufficiently detailed to provide all input parameters for the
index, and shall include a plan view map and longitudinal sections. The investigating
geologist and responsible engineer jointly determine the engineering significance of
all material that has a headcut erodibility index less than or equal to 10.
(e) Mass Movements. Assess landslides and landslide potential at dam and
reservoir sites and summarize the history of mass movements in the project area.
(f) Karst Areas. Evaluate limestone, dolomite, gypsum, and other soluble rocks at
dam and reservoir sites for subsidence potential and leakage potential.
(g) Multipurpose Dams. Evaluate the ground water regime and hydraulic
characteristics of the entire reservoir area of water storage dams to determine
leakage potential and the need for reservoir sealing.
(h) Other. Evaluate other geologic conditions or materials that have engineering
significance. These include, but are not limited to, dispersive soil; soil containing
highly soluble sodium salts; expansive soil; gypsiferous soil; soil that has vertic
properties; gap-graded soil, sensitive clay; highly compressible soil; pyritic shale;
fissile shale; stress relief and rebound joints; and shallow artesian ground water.
Evaluate anticipated changes in the ground water regime with respect to the intended
function of the structure.
Special investigations are required for the planning and design of dams and spillways
subject to deep foundation subsidence that can result from collapse of underground
mines, or extraction of fluids, such as water, oil, and natural gas from beneath the
Earth's surface. The required foundation supports established in this subpart are
essential to the design of safe embankments.
This policy applies where foundation subsidence is or could be a threat to the safety
of all structure class b and c dams and all class a dams for which the product of
storage (ac-ft) times effective height (ft) of dam is greater than 3,000.
At the ground surface, surface and subsurface landrights shall encompass an area that
extends outward beyond the base of the dam a horizontal distance equivalent to the
depth of the deepest mineral deposit below ground surface. This requirement may be
modified as a result of a detailed site specific study by, and at the consequent
recommendation of, a qualified consulting mining engineer.
Fee simple title or subordination agreements may or may not be required for the area
of the reservoir upstream of the dam that is beyond the area required for the
stability of the dam. The need for the legal right to control the mining of the
reservoir area depends on the following types of evaluation:
• An evaluation by the sponsors or owners of their possible liability for damage to:
- the mine or mining operation caused by flooding, increased pumping costs, a
reduction in amount of the mineral that can be removed, or other possible
damage; or
- surface areas and improvements on the periphery of the reservoir that may
subside and thereby suffer increased damage, such as, from inundation or
increased flood flow in inlet channels.
If any of the problems listed above occur, NRCS will advise the sponsors or owners in
writing to:
• Seek legal counsel and a qualified mining engineer to help determine the extent of
the risk the sponsors or owners should assume;
• Consider purchasing necessary landrights to protect against possible damage suits;
• Consider the feasibility of taking easements to an elevation higher than normal by
an amount equal to or greater than the anticipated subsidence. NRCS shall make
available to the sponsors or owners all of its data pertinent to the subsidence
problem and the proposed dam.
If studies indicate that the predicted subsidence cannot be remedied, the site shall
be abandoned.
531.30 General
Technical guidance for ground water development is contained in NEH 18, Ground Water;
NEH 631.33, Investigations for Ground Water Resources Development; EFH, Chapter 12,
Springs and Wells, Ground Water Manual (Bureau of Reclamation, 2nd ed., 1995). Other
methods not described in these references may be considered at the discretion of the
investigating geologist.
The NRCS geologist has responsibility for the following types of investigations and
evaluations:
• Evaluating ground water development potential of aquifers.
• Conducting ground water budget analyses in watersheds and evaluating ground water
overdraft potential.
• Evaluating ground water quantity, quality, and geologic factors that influence
design and construction of production wells, and well head protection measures.
• Estimating ground water consumption or demand in watersheds.
• Evaluating potential for underground disposal of surface waters.
• Evaluating potential for conjunctive use of ground water with surface water
supplies.
• Determining aquifer boundary conditions and potential for well interference.
• Determining aquifer recharge potential.
The NRCS geologist has responsibility for the following types of investigations and
evaluations to provide sufficient information for planning or design:
• Aquifer restoration or enhancement.
• Location, construction, rehabilitation, decommissioning, and problem
investigations of water wells.
• Ground water pollution potential relative to agricultural point and nonpoint
sources.
• Potential for ground water pollution by components of agricultural waste
management systems.
• Influence of karst terrace on construction and performance of conservation
practices and structures.
• Well head protection zones.
• Areas having ground water recharge potential.
• Location of ground water divides and delimiting recharge areas in karst terrane
and other highly pervious geologic materials.
• Saline seeps.
• Saltwater intrusion.
The NRCS person holding the appropriate engineering job-approval authority for the
class of structure, as outlined in 501.04, is responsible for conducting the following
types of investigations and evaluations to provide sufficient information in the
planning or design phases of a project:
• Investigations for controlling the water table with respect to:
- agricultural drainage and irrigation water management activities;
- engineering drainage for excavation de-watering of foundations, borrow areas,
quarries, buildings, and mines;
- seepage evaluations for blankets, drains, filters, and grouting;
- engineering subdrainage for slope stability.
Technical guidance for investigation of the water table are in EFM Chapter 14,
Drainage; NEH 16, Drainage.
531.40 General
A qualified geologist is responsible for the survey, and analysis and interpretation
of data related to geomorphic processes. These processes include detachment,
transport, deposition, consolidation, cementation, and lithification of soil and rock
particles.
The NRCS geologist shall, in collaboration with related technical specialists, develop
supplemental guidelines and geomorphology field procedures consistent with the state’s
needs, as determined by the state conservation engineer.
Design criteria for the allocation of sediment storage in all reservoirs impounded by
Group I dams as defined in 531.20, shall be determined by a geologist. For Group II
sites, the determinations may be made by others who have been trained by a qualified
geologist in recognizing and evaluating the effects of sedimentation on pond
performance. A specialist with expertise in sedimentation is consulted for Group II
dams with complex sedimentation problems or for Group II sites where data are to be
applied to another area or site.
Methods to be used are provided in NEH-3, Ch. 8, Sediment --Storage Design and
Criteria. These methods include the gross erosion/sediment delivery ratio,
measurement of sediment in similar ponds and reservoirs, suspended load records of
gauged streams, and direct predictive equations. Other methods not described in NEH-3
may be considered at the discretion of the investigating geologist.
Watershed sediment yield and sediment budget studies are conducted to evaluate the
effectiveness of land treatment and structural measures in reducing erosion and
sediment yield in the treated area. They also are conducted to provide basic data for
planning and design of soil and water conservation measures.
Methods for determining watershed sediment yield are provided in NEH-3, Ch. 8. Other
methods not described in NEH-3 may be considered at the discretion of the
investigating geologist.
Sedimentation surveys for Conservation Practice Standard 378, Pond, are conducted by
personnel trained in sedimentation surveys. Sedimentation surveys for Conservation
Practice Standard 402, Dams, are conducted by a geologist.
Reports for each reservoir sedimentation survey are prepared according to requirements
in NEH-3, Chapter 7, and are filed at the state office with a copy sent to the
Director, CED.
The report includes data on watershed conditions that affect sediment yield, for
examples, soils, surface geology, topography and land forms, land use and treatment,
and all types of significant erosion. The report includes information about land use
management changes through time in the contributing watershed.
The state conservation engineer is responsible for the technical adequacy of the
report.
A qualified geologist is responsible for the development of sediment budgets that identify
sources and sinks and allocate sediment by sources. Sediment budgets identify sediment particle
size ranges by source. Problem identification is specific as to the sediment particle sizes
causing problems.
Water quality standards as they pertain to turbidity have been established by the states for
interstate and coastal waters under provisions of the Water Quality Act of 1965.
Guidelines and standards for investigating, analyzing, and evaluating sediment as related to
quality of surface waters are provided in consensus industry sources, including:
• ASTM, Section 11--Water and Environmental Technology, Volumes 11.01 and 11.02 on Water.
Other pollutants associated with sediment-related water quality are investigated, analyzed, and
evaluated by a specialist that has appropriate expertise.
The state conservation engineer collaborates with other technical disciplines and is responsible
for developing supplemental guidelines and field procedures consistent with program needs of the
state.
Policy contained in 504, Subpart A provides requirements for investigation of structural problems
caused by sedimentation and erosion, and provides for committee assignments; procedures; and
engineering reports.
531.47 Geologic investigation of sedimentation and erosion processes in the stream channel and
stream corridor
Geologic investigations may include analyzing sediment transport capacity of the channel,
determining change in transport capacity caused by the planned modification, and determining
bedload sediment sources. Stream channel investigations may consider the dimension, pattern,
profile and other pertinent geomorphic factors of the stream, as well as activities in the
watershed that can affect sediment supply and subsequent stream channel behavior and stability.
Technical guidance is contained in NEH Part 653, Stream Corridor Restoration Handbook; EFH,
Chapter 16, Streambank and Shoreline Protection; and NEH-3, Sedimentation.
The intensity of evaluation of rock material to be used for erosion control depends
on the size and design requirements of the individual project, the quantity and
quality of rock required, and the potential risk for property damage or loss of human
life.
Special erosion and sedimentation studies are conducted according to policy contained
in Subpart A - Geologic Investigations.
532.00 General.
533.00 General
533.01 Scope
SUBPART B - OPERATIONS
533.10 General
§533.12 Testing
533.20 General
533.21 Scope
(Reserved.)
535.00 General.
535.01 Definitions.
535.02 Services.
536.00 General.
(b) After the 4100 Series was issued, research revealed that
the tendency for scour to occur downstream from the apron
increases as the ratio of the depth of the weir to the height of
the headwall increases. Therefore, the 4100 Series is to be used
only if the ratio of weir depth to headwall height is lower than
0.5. (See NEH-11, Chapter 5, page 5.1.)
536.11 (Reserved.)
536.12 (Reserved.)
536.13 (Reserved.)
536.14 (Reserved.)
536.15 (Reserved.)
536.16 (Reserved.)
536.17 (Reserved.)
536.18 (Reserved.)
536.19 (Reserved.)
537.00 General.
540.00 General.
540.01 Format.
540.02 Precision and accuracy.
540.03 Staking.
540.04 Contractor surveys.
540.05 Checking.
540.06 Responsibility.
541.0 General.
541.1 Media.
541.2 Sheet Size.
541.3 Title Blocks.
541.4 Cover Sheet.
541.5 Orientation.
541.6 Style and Content.
541.7 Standard Title Block for ANSI A (8.5x11) Sheet.
541.8 Standard Title Block for ANSI B (11x17) and ANSI D
(22x34) Sheets.
541.9 Standard ANSI A (8.5x11) Sheet.
541.10 Standard ANSI D (22x34) and ANSI B (11x17) Sheets.
542.10 General.
542.11 Technical Services.
SUBPART C - EXHIBIT
543.00 General.
543.01 Scope.
543.02 Preparation of material specifications.
543.03 Use of new materials.
544.00 General.
544.01 Transporting equipment.
544.02 Adjustment and calibration.
544.03 Maintenance.
544.04 Storage.
544.05 State procedures.
(Reserved)
540.00 General.
540.01 Format.
(a) For Class V - VIII jobs and other major projects in which
work is usually performed by formal contract; or, if the notes
may be needed as supporting data in potential legal actions:
540-1
PART 540 – FIELD SURVEYS
§40.03 Staking.
540-2
PART 540 – FIELD SURVEYS
540.05 Checking.
540.06 Responsibility.
540-3
210 - National Engineering Manual
541.0 General
C. Drawings reflect the professional quality of NRCS engineering services to the owner,
contractor, and general public. Drawings should be legible, accurate, complete, and should
have a consistent appearance throughout the agency.
541.1 Media
A. Drawings can be developed by manual drafting techniques and/or computer aided design
(CAD) methods.
B. Paper is appropriate for most NRCS conservation work. More durable medium such as
vellum or mylar should be considered for standard drawings that will be reused repeatedly, or
for drawings that need to be retained for many years.
C. CAD files should be saved on media appropriate for retention period shown in NRCS
Records Management Guide. Permanent record files should be upgraded to newer, more
durable media as technology evolves.
C. Normally, full size sheets should be used for projects involving large land areas or
complex structures. Half size sheets should be used for smaller, simpler work. Page size
sheets should be limited to simple details.
D. Other size paper may be used for NRCS work as needed to facilitate local paper supply
availability and special plotting, copying, or reproduction equipment limitations.
A. Each sheet in a set of construction drawings shall have a title block to identify the
drawing and provide other information about the drawing. Location data including State,
County, Township, Section or similar information shall be included in each title block.
B. Full and half size drawing sheets shall have a vertical title block on the right side of the
sheet. Page size sheets shall have horizontal title blocks across the bottom of the sheet.
C. The standard title blocks for NRCS work shown in 541.07 through 541.10 shall be used
for all new drawings or drawing forms prepared by NRCS.
D. Alternative title blocks can be used or added for work prepared by other agencies, local
organizations, or private firms. Such alternate title blocks shall contain at least the same
drawing identity and other information as contained on the NRCS standard title block.
A. Each set of construction drawings consisting of more than five sheets shall have a cover
sheet showing the name and location of the project, the names of the sponsoring agencies or
owners, an index of the drawings, space for approval signatures, and professional seals as
appropriate.
B. The cover sheet for major, long lasting NRCS work such as dams and channels may also
include a location map, general notes, and project data.
541.5 Orientation
A. Maps should be drawn with north toward the top of the sheet. If this orientation is not
feasible, the map should be drawn with north toward the left. A north arrow shall be shown
on all maps.
B. Layout drawings (plan view) should be drawn so that the direction of flow is from left to
right or bottom to top of the sheet. A north arrow and flow arrow indicating direction of flow
shall be shown.
C. Cross section and elevation views of structures representing surfaces essentially parallel
to the direction of the stream flow should be drawn so that flow is from left to right.
D. Cross section and elevation views representing surfaces essentially normal to flow should
be drawn so that they are viewed looking downstream. If such orientation makes the drawing
unclear, it may be changed and the orientation labeled on the drawing. For example,
orientation could be labeled as “Looking Upstream”.
A. Drawings should present as much related information as reasonable on the same sheet for
efficiency and clarity. If possible, details should be drawn on the same sheet as the work to
which they apply. If details are shown on a separate sheet, appropriate sheet references
should be noted. Dimensions and sizes of components should be shown on the drawings
rather than referenced to the specifications.
B. Drawings shall follow agency and industry standards for content, appearance, details, and
symbols to best communicate requirements to reviewers, contractors, and the building trades.
Standards include:
National Digital Geospatial Map Symbols Handbook, Title 170, Part 601
C. Scales for drawings should be selected carefully to assure clarity of details and
accommodate reduced size reproductions. Bar scales are preferred for maps and plan views
and are necessary for any drawings that will be reduced for contracting.
D. The minimum scale for structural drawings should be: ¼ inch equals 1 foot for layout
sheets, 3/8 inch equals 1 foot for reinforcing steel sheets, and ½ inch equals 1 foot for any
sheets that will be reduced. Drawings that will be reduced shall include bar or graphic scales,
or each reduced sheet shall bear a prominent warning note stating that the drawing is a
reduced size and the indicated scales are not accurate.
E. Notes on the drawings should be limited to those required for complete and accurate
description of the drawings and those required to supplement the contract specifications.
F. All lines and letters must be clear, sharp, and dense to ensure clear reproductions and one-
half scale reductions. Manually drafted letters shall be single stroke type.
G. Drawings should include geographic location information. Routine work should show at
least a simple location map containing readily identifiable landmarks. Major work should
include structure reference lines and right-of-way limits referenced to fixed and readily
identifiable geographical points.
H. Drawings should include geologic and soils information where available. Boring
numbers, station and offset of borings, waterline depth and date of waterline, and soil
classification at various depths can be displayed on cross section and profile views.
I. Drawings should include survey information, i.e. benchmark location, data and datum
used, where available.
541.8 Standard Title Block for ANSI B (11x17) and ANSI D (22x34) Sheets
542.00 General.
542.01 Scope.
542-1
PART 542 - SPECIFICATIONS
542-2
PART 542 - SPECIFICATIONS
542-3
PART 542 - SPECIFICATIONS
542-4
PART 542 - SPECIFICATIONS
542.10 General
542-5
PART 542 - SPECIFICATIONS
SUBPART C - EXHIBIT
542-6
PART 543 – MATERIALS
543.00 General.
543.01 Scope
544.00 General.
544.03 Maintenance.
544.04 Storage