Ep Wells Daily Operations Report: Event Summary

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

RESTRICTED

EP WELLS DAILY OPERATIONS REPORT Report 38 08/09/2017


Company PERMIAN
Well Type Development
Well UNIVERSITY 19 UNIT 2 2506
Wellbore UNIVERSITY 19 UNIT 2 2506
WBS No/API No 30261557 / 4230133054.00

Event Summary
Event Type Completion only Event Start Date 05/10/2017 Days on Location 38.00
Objective Install Completion Original Spud Date 11/21/2016
Est. Days 20.00 Contractor PERMIAN WELL SVC
Work Unit PERMIAN COMPLETIONS Days To Release
Rig Phone/FAX No.

Well Status
Supervisor Bruce Smiley Measured Depth(ft)

Engineer Jordan Sawyer TVD(ft)


Other Supervisor Mike Reber 24 Hr Progress(ft)
Depth Ref/Grd Elev/Water Depth(ft) DFE: 2,882.30 / 2,856.30 Hole size(in)
THF Datum
Daily NPT(hr/%) 24.00/100.00 Last Casing MD
Days Ahd(-) Bhnd(+)(50/50) Next Casing MD
Actual cost to date/AFE 3,688,629/4,860,392.00 Current MW / BH EMW(ppg) /

Actual divided by AFE 0.76 LOT/FIT EMW(ppg)


Daily Cost 54,017 Lithology
Formation/MD Top

HSE Summary
Last Incident Date Days Last Incident Date Days KPI's

LWC PSI TRCF


RWC NII LWCF
MTC HPI Safety Cards - Safe
FAC GOAL ZERO DAYS Safety Card - Unsafe
Last casing pressure test PS BARRIER EVENT SSE%
PS barrier bowtie review Last casing pressure(psi)

Safety Comments:
344 working hours
44 driving hours

HSE Drills
Drills/Tests Date Days Since Last

Last Derrick Inspection JSA's/Toolbox Talks


Last BOP function test Days Since Last Drill 37
Last BOP Test
Next BOP Test

Operations Summary
24 Hour Summary
MIRU CT package, MU new motor and 3.75" bit, test, repair WH pressure in CT cabin
Update Since Report Time
Finish repairing WH pressure in CT cabin, replace high pressure grease port, open well, RIH
24 Hour Forecast
RIH and finish drilling plugs 30-37, POOH, move over to 2505, change BHA, test, RIH drilling plugs

08/10/2017 05:08:25 Report Version: 4.1.16R9 Generated from data in EDM/OpenWells/PROFILE 1


RESTRICTED
EP WELLS DAILY OPERATIONS REPORT Report 38 08/09/2017
Well UNIVERSITY 19 UNIT 2 2506
Wellbore UNIVERSITY 19 UNIT 2 2506

Time Summary

Start Hours PH OPN Detail Drilled NPT Rig Description


Depth (ft) level Rate
0:00 10.25 COIL RGO 1 *** NPT CONTINUES CUDD COIL TUBING GOOSENECK
SUPPORT BENT***

No Activity, CT reel spooling new 2-3/8" CT, CT pump being re-built,


CT gooseneck being replaced
10:15 0.75 COIL SAF 1 HELD SAFETY MEETING / DAYS OPS / JAS /12 LSR/ HIGH PSI
/RU
11:00 6.00 COIL SAF 1 START SPOTTING AND RIGGING UP CTU AND HIGH PSI PUMP

17:00 1.50 COIL SAF 1 PUT ON CT CONN. PULL TEST TO 44K PSI TEST TO 3000 PSI

18:30 0.50 COIL SAF 1 START PUTTING ON BHA

19:00 5.00 COIL SAF 2 Prep to pressure test 2.875" CT BHA to 3,000 psi, SD

***NPT STARTS CUDD CT DOGHOUSE CAN'T READ WH


PRESSURE***

While checking equipment during UnCAPP, WH pressure from the


Martin Decker and the digital package are not reading WH
pressure, appears to be obstruction in the hose, crew starts
troubleshooting, crew breaks hydraulic connection at back of reel
trailer and trys to pump and establish flow with Enerpac pump, flow
weak, break connection at hose package spool on back of
powerpack trailer, flow weak, crew calls for new Martin Decker
gauge and will continue troubleshooting WH hoses in CT cab after
function test motor and pressure test
NOTE WH pressure, CP pressure, and weight are all required by
Cerberus to properly fatigue new 2.375" CT string.

21:00 Proceed with test tools to bottom of XRV to 3,000 psi for 10
min / good test / swing to cellar, drain and BD test sub, MU 2.875"
Titan motor to spec 2,500 ft-lbs, confirm OD on Varel roller bit at
3.75", function test motor as follows
-1 bbl / 1,500 psi
-2 bbl / 2,000 psi
-3 bbl / 3,500 psi

21:30 BHA #2 MU complete, final RIH as follows


-3" OD 0.81' long dimple connecter
-2.88" OD 1.41' long Dual Back Pressure Valve
-2.88" OD 3.82' long Hailey Jar
-2.88" OD 2.24' long Hydraulic Disconnect
-2.88" OD 1.58' long Dual circulating sub
-2.88" OD 2.24' long XRV Extended reach Tool
-2.88" OD 13.52' long Titan Supermax HT Motor
-3.13" OD 0.42' long Rotary Sub
-3.75" OD 0.52' long Roller Cone Bit
Total length = 26.56'

21:45 PAUSE, walk lines with CUDD and Extreme valve team,
break circulation to gas buster, shut in at choke manifold, pressure
test 500 psi / low / 5 min, pressure test 8,000 psi high / 10 min,
good test, attach guywire package, bleed pressure to 0 psi

22:15 Revise JSA for working under CT console, BD and flush WH


hydraulic line at Martin Decker, flush at hose bulkhead underneath
and in console, continue troubleshoot at report time.

***NPT CONTINUES CUDD CT DOGHOUSE CAN'T READ WH


PRESSURE***

Total 24.00

08/10/2017 05:08:25 Report Version: 4.1.16R9 Generated from data in EDM/OpenWells/PROFILE 2


RESTRICTED
EP WELLS DAILY OPERATIONS REPORT Report 38 08/09/2017
Well UNIVERSITY 19 UNIT 2 2506
Wellbore UNIVERSITY 19 UNIT 2 2506

06.00 Update
Start Hours PH OPN Detail Drilled NPT Description
Depth (ft) level
0:00 1.00 COIL SAF 2 ***NPT CONTINUES CUDD CT DOGHOUSE CAN'T READ WH
PRESSURE***
BD hose at bulkhead outside of doghouse (all established strong flow
with Enerpac), re-break and establish strong flow at hose manifold at
back of reel trailer, hose manifold at hose spool, supervisor goes to 4:1
de-booster on Quad BOP's and breaks connection and has good flow
from enerpac, CT operator can read digital WH pressure now and
properly update Cerberus string fatigue database.

***NPT ENDS CUDD CT DOGHOUSE CAN'T READ WH


PRESSURE***
1:00 0.25 COIL SAF 1 Walk the lines, re-confirm valve orientation, break circulation to gas
buster, SD, shut in at choke manifold, bring pressure to 3,800 psi (well
pressure 3,700 psi), SD, leak on high pressure grease fitting on
roadside hydraulic valve on flow cross, bleed off, break out grease
fitting.
1:15 3.75 COIL SAF 2 ***NPT STARTS CUDD CT REPLACE 15K HP GREASE FITTING***

CUDD does not have a 15K auto-clave HP grease fitting for this
hydraulic valve, crew member heads to meet CUDD shop hand and PU
same, will also PU Martin Decker WH gauge, parts on location, head up
and install 15K HP grease fitting, install Martin Decker WH gauge.

***NPT ENDS CUDD CT REPLACE 15K HP GREASE FITTING***

NPT Summary

Start Date/Time Responsible NPT Failure MD Ops Type* Equipment Net Gross Severity Status
Company Code (ft) Code Type time time
(hr) (hr)

08/09/2017 19:00 CUDD PUMPING Rig/Work SAF EN Coil Tubing 6.00 6.00 OPEN
SERVICES INC Unit Misc Surface
Equipment

Description: CT DOGHOUSE CAN'T READ WH Title: CT DOGHOUSE CAN'T READ WH PRESSURE


PRESSURE***
While checking equipment during UnCAPP, wellhead hose not
reading and not able to pump up, crews troubleshoot hose and are
able to get flow through hose after breaking and working on at hose
manifold at back of trailer and hose manifold on power pack trailer,
crew pumps up gauge and gauge appears to be out of service,
supervisor calls shop
Total 6.00 6.00