Ep Wells Daily Operations Report: Event Summary
Ep Wells Daily Operations Report: Event Summary
Ep Wells Daily Operations Report: Event Summary
Event Summary
Event Type Completion only Event Start Date 05/10/2017 Days on Location 38.00
Objective Install Completion Original Spud Date 11/21/2016
Est. Days 20.00 Contractor PERMIAN WELL SVC
Work Unit PERMIAN COMPLETIONS Days To Release
Rig Phone/FAX No.
Well Status
Supervisor Bruce Smiley Measured Depth(ft)
HSE Summary
Last Incident Date Days Last Incident Date Days KPI's
Safety Comments:
344 working hours
44 driving hours
HSE Drills
Drills/Tests Date Days Since Last
Operations Summary
24 Hour Summary
MIRU CT package, MU new motor and 3.75" bit, test, repair WH pressure in CT cabin
Update Since Report Time
Finish repairing WH pressure in CT cabin, replace high pressure grease port, open well, RIH
24 Hour Forecast
RIH and finish drilling plugs 30-37, POOH, move over to 2505, change BHA, test, RIH drilling plugs
Time Summary
17:00 1.50 COIL SAF 1 PUT ON CT CONN. PULL TEST TO 44K PSI TEST TO 3000 PSI
19:00 5.00 COIL SAF 2 Prep to pressure test 2.875" CT BHA to 3,000 psi, SD
21:00 Proceed with test tools to bottom of XRV to 3,000 psi for 10
min / good test / swing to cellar, drain and BD test sub, MU 2.875"
Titan motor to spec 2,500 ft-lbs, confirm OD on Varel roller bit at
3.75", function test motor as follows
-1 bbl / 1,500 psi
-2 bbl / 2,000 psi
-3 bbl / 3,500 psi
21:45 PAUSE, walk lines with CUDD and Extreme valve team,
break circulation to gas buster, shut in at choke manifold, pressure
test 500 psi / low / 5 min, pressure test 8,000 psi high / 10 min,
good test, attach guywire package, bleed pressure to 0 psi
Total 24.00
06.00 Update
Start Hours PH OPN Detail Drilled NPT Description
Depth (ft) level
0:00 1.00 COIL SAF 2 ***NPT CONTINUES CUDD CT DOGHOUSE CAN'T READ WH
PRESSURE***
BD hose at bulkhead outside of doghouse (all established strong flow
with Enerpac), re-break and establish strong flow at hose manifold at
back of reel trailer, hose manifold at hose spool, supervisor goes to 4:1
de-booster on Quad BOP's and breaks connection and has good flow
from enerpac, CT operator can read digital WH pressure now and
properly update Cerberus string fatigue database.
CUDD does not have a 15K auto-clave HP grease fitting for this
hydraulic valve, crew member heads to meet CUDD shop hand and PU
same, will also PU Martin Decker WH gauge, parts on location, head up
and install 15K HP grease fitting, install Martin Decker WH gauge.
NPT Summary
Start Date/Time Responsible NPT Failure MD Ops Type* Equipment Net Gross Severity Status
Company Code (ft) Code Type time time
(hr) (hr)
08/09/2017 19:00 CUDD PUMPING Rig/Work SAF EN Coil Tubing 6.00 6.00 OPEN
SERVICES INC Unit Misc Surface
Equipment