FCR-N Design of Requirements
FCR-N Design of Requirements
FCR-N Design of Requirements
AUTHORS
ROBERT ERIKSSON SVENSKA KRAFTNÄT
NIKLAS MODIG SVENSKA KRAFTNÄT
ANDREAS WESTBERG SVENSKA KRAFTNÄT
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
Contents
1. INTRODUCTION ...................................................................................................................4
1.1 BACKGROUND OF THE PROJECT ............................................................................................................................ 4
1.2 SCOPE OF THE PROJECT – FCR-N ........................................................................................................................... 6
1.3 GOALS............................................................................................................................................................ 7
1.4 CONSTRAINTS .................................................................................................................................................. 7
1.5 OUTLINE ......................................................................................................................................................... 7
6. CONCLUSIONS .................................................................................................................. 43
7. REFERENCES .................................................................................................................... 43
Page 2 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
CONSTRAINTS
TABLE 2. SPECIFIED CONSTRAINTS
Parameter Value
𝐸k−min 120 GWs
Page 3 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
1. INTRODUCTION
Frequency quality is a measure of the power balancing in a synchronous system. The balancing is
driven by variations in production and consumption, together with the control response of the
reserves and inertia. The frequency quality in the Nordic system has reduced over the last years
indicated by increased minutes outside normal band. The normal frequency band is 50±0.1 Hz
which should not be exceeded more than 10 000 minutes per year. The frequency containment
reserve for normal operation (FCR-N) is to handle the short term stochastic net power variation in
production and consumption. Recently, secondary control, automatic frequency restoration
reserve (aFRR) has been introduced in order to improve the quality but is not seen as the sole
solution of the problem. Revision of the FCR-N in order move towards better quality is a
complementary solution. One aim of the frequency containment process project (FCP project) is to
develop thorough requirements on the FCR-N ancillary service to ensure good frequency quality.
This document describes steps that have been taken to create the new FCR-N requirements.
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
sine-in-sine-out tests were performed in open loop by injection of an artificial frequency signal in
the governor, i.e. a super imposed sinusoidal frequency signal fed into the governor. From this,
transfer functions were estimated and stability in closed loop system was analysed. During these
tests much new knowledge was gained in how the FCR requirements were implemented in
practice, some were good and some were not. An example of the difference in implementation is
shown in Figure 1 where in total 39 different sine-sweep tests using the twelve different hydro
power stations are presented in a discrete Nyquist-like graphi. Each dashed curve is a test, at a
hydro power plant, excited by a set of sinusoidal signals with different time periods injected into
the governor. The response of the Nyquist curve at discrete frequencies is marked with ‘x’ and
linear interpolation has been applied in between. Ideally, a curve should not enter the black circle
and shall not appear on the left hand side of the point -1 (red dot) by encircle this point. Such
response acts de-stabilising, clearly, units that act destabilising could be identified. Figure 2 shows
two selected responses illustrating one response that stabilises the system (blue curve) and
another that de-stabilises (red curve).
i
The graph is created by assuming that all FCR-N providers have the same dynamic response as the tested unit.
Page 5 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
FIGURE 1. RESULT FROM SINE-SWEEP TESTS PERFORMED DURING THE 60S PHASE 1 AND 2 PROJECTS
The results from previous projects show that there is a clear need to physically test and verify the
dynamic performance. The existing requirements state that a unit shall have full activation after
150-180 seconds from a stepwise change in the frequency within the normal operating band of
the FCR-N. In Sweden there is an additional requirement that 63 % of the steady state power
response shall be activated after 60 seconds. The sine-sweep tests clearly showed that there is
some unwanted dynamic performance that can be seen with sine-sweep tests but not with step
response tests that have previously been used in the Nordic synchronous area.
FIGURE 2. SELECTED RESPONSES FROM REAL TESTING, BLUE RESPONSE ACTS STABILISING AND RED ACTS DE-STABILISING.
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
project will only set the technical requirements for FCR-N and FCR-D products with constraints
given. Impact from voltage dependency in loads, distributed inertia and activated network
protections schemes are not considered. The analysis of the design is performed only on a linear
single-input-single-output system with no voltage dependency but is verified in non-linear
simulations.
1.3 GOALS
The goals are to come up with requirements on the FCR-N. The requirements shall
3. improve the frequency quality in relation to specified key performance indicators (KPIs) in
relation to the system of today. The KPIs are to be specified in the project,
4. specify the dynamic response from net power variation to frequency deviation to meet the
KPIs.
1.4 CONSTRAINTS
Constraints are given in Table 2.
1.5 OUTLINE
This document is organised as follows. In Section 2 a theoretical background is given for general
control systems on the basis of transfer function with the concepts stability and performance.
Next section provides the model description of an FCR-unit and different per unit scaling. The
reference hydro power unit is also introduced which is used throughout the document. In Section
4 the requirements are described and motived, also results from simulations are provided. Section
5 gives an overview of real test procedure on site and how to achieve the response in order to
verify qualification.
2. THEORETICAL BACKGROUND
In most physical systems non-linearities are to be considered in the control design. However,
linear control design is often used and then verified by non-linear simulations and testing. This
Page 7 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
section describes linear control design for a single-input-single-output (SISO) system and how the
non-linearity introduced by backlash can be included.
2.1 STABILITY
First some terminology on stability is used in terms of asymptotic stability which means that there
exists no initial condition or no bounded input signal that drives the output to infinity.
Figure 3 shows a SISO system where F(s) is the transfer function of the control process, G(s) the
plant, d is a disturbance signal entering the system, y is the output of the closed loop system and s
is the Laplace operator.
disturbance
d output
∑ F(s) ∑ G(s)
- y
Control system
unit
FIGURE 3. OVERVIEW OF A FEEDBACK SYSTEM
The aim is to determine whether or not the closed loop system is stable. The mathematical
framework of transfer functions provides an elegant method, which is called loop analysis. The
basic idea of loop analysis is to trace how a sinusoidal signal propagates in the feedback loop, this
by investigating if the propagated signal grows or decays. One way to analyse stability is by using
the Nyquist criterion which in turn uses the loop gain. The loop gain is defined as
𝐺𝑂 (𝑠) = 𝐹(𝑠)𝐺(𝑠). (2.1)
The loop transfer function, also named sensitivity, is defined as
1
𝑆(𝑠) = 1+𝐺 (2.2)
O (𝑠)
and describes the propagation of a signal through the loop i.e. how the output amplifies through
the loop.
The amplification of a signal is determined by the denominator. Whether the signal grows as it is
phase shifted by 180o (the signal has opposite sign) in the loop determines if the system is stable
or not. The point where a signal has this phase shift and its amplitude remains (gain equals to one)
corresponds to where to denominator is equal to zero i.e.
𝐺O (𝑠)|𝑠=𝑗𝜔0 = −1.
(2.3)
At such conditions the signal grows to infinity, thus, the point -1 is of interest together with the
loop gain.
The Nyquist curve is the loop gain, that can be plotted in the complex plane, with the Laplace
operator s replaced by the complex value jω and ω varying as shown in Figure 4. The system is
asymptotically stable if the Nyquist curve does not encircle the point -1. Basically, at the point
where the Nyquist curve has a phase shift of 180 o the loop transfer function should be smaller
Page 8 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
than one. This holds true for simple enough systems (loop gains) as one could in reality cross the
negative real axis twice to the left of the point -1 and still not encircle this point. Note that this is
only valid if the loop gain is at least marginally stable i.e. no poles in the right half plane. For a
more detailed description readers are referred to [1] and textbooks in the field of linear control
theory. In practice it is not enough that a system is stable. There should also be some margins of
stability that would describe how stable the system is and its robustness to perturbations. A
stability margin is introduced by a distance between the Nyquist curve and the point -1. It can be
specified in terms of amplitude marginii (also known as gain margin), (Am), phase marginiii, (ϕm),
and the smallest Euclidian distance, r, between the curve and the point -1 (referred to as the
stability margin).
G0(jω)=
F(jω)G(jω)
FIGURE 4. NYQUIST DIAGRAM. NOTE THAT THE INDICATED PHASE AND GAIN MARGIN ARE HERE IMPOSED BY THE CIRCLE. THE BLUE CURVE
HAS LARGER MARGIN THAN GUARANTEED BY THE EUCLIDIAN DISTANCE.
However, specifying the Euclidian norm guarantees that the amplitude and phase become as
follows
1
𝐴m ≥ (2.4)
1−𝑟
𝒓
𝝋𝐦 ≥ 𝟐 𝒔𝒊𝒏−𝟏 ( 𝟐). (2.5)
A drawback with gain and phase margins is the necessity to state both of them in order to
guarantee the Nyquist curve not to become close to the critical point. Moreover, phase and
amplitude margin, stand-alone or combined, do not guarantee a certain distance to the point -1.
Note that none of the mentioned margins guarantee closed loop stability themselves – the point
-1 may be encircled without entering the r-circle, and both the unit circle and the negative real
axis may be crossed multiple time. However, it can be assumed that the loop gain is simple enough
so that such margins ensure stability.
ii
the factor by which the loop gain can be increased until the Nyquist curve intersects with the point -1+ 0∙j
iii
angle between the negative real axis and the point where the curve crosses a circle centred in origin with unity
radius.
Page 9 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
The stability margin expressed by the Euclidian norm limits the sensitivity function below a certain
value as follows
1
|𝑆(𝑠)| ≤ = 𝑀s (2.6)
𝑟
e disturbance
D(s)
d output
∑ F(s) ∑ G(s)
- ∆f
FCR unit system
Page 10 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
Now consider a disturbance, e(t)=sin(ωt) and |e(jω)|=1, that enters the system through a filter
D(s), shown in Figure 5. Then, assume the control object to be |∆f(jω)|<1 for all ω. From (2.7) the
following can be derived
1
|𝑆(𝑗𝜔)| < [𝐷(𝑗𝜔)𝐺(𝑗𝜔)] (2.8)
Note that this describes how a signal that enters the system does not propagate in the system so
its amplitude is larger than the initial value of the disturbance for any frequency. However, the
system is linear and the output is obtained by superposition of the signals that have propagated
through the system. If the disturbance signal contains several frequencies, e.g. stochastic signals,
they interrelate and may therefore result in input amplitude larger than one even though the
power is very low at particular frequencies. Therefore, since the system is linear the output is
obtained by superposition. The bottom-line is, the output may therefore also be larger than one.
Figure 6 shows a random signal generated by a Gaussian white noise process. White noise has a
power spectrum of one and the probability of a random sample to occur outside ±1 is about 32%.
3. MODEL DESCRIPTION
This section provides a description of the power system (G(s)) and the control unit (F(s)) models
used. The system consists of generation and consumption distributed in the grid. Thus inertia and
Page 11 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
frequency control is distributed and connected through the grid. In this project, the modelling of
the power system and the FCR providing units is performed with the one machine equivalent,
assumptions for this are given below.
𝑯𝒙 𝒅𝟐 𝜽𝒙
= 𝑷𝒎𝒙 − 𝑷𝒆𝒙 (3. 1)
𝝅𝒇𝟎 𝒅𝒕𝟐
where 𝜃𝑥 is the angle in rad of generator x, 𝐻𝑥 is the inertia constant, Pmx and Pex are the
mechanical and electrical powers, respectively, expressed on a power base. 𝑓0 is the nominal
frequency. Consider the synchronous machines on a common system base (𝑆n ). Assume the
machine rotors swing coherently, i.e. all 𝑑𝜃𝑥 /𝑑𝑡 are equal, the powers and the dynamics can then
be added as
𝐻𝑥 𝑑 2 𝜃𝑥 (3.2)
∑ = ∑(𝑃𝑚𝑥 − 𝑃𝑒𝑥 )
𝜋𝑓0 𝑑𝑡 2
𝑥 𝑥
This results in
𝐻 𝑑2𝜃 (3.3)
= 𝑃𝑚 − 𝑃𝑒
𝜋𝑓0 𝑑𝑡 2
where the equivalent inertia constant H for the complete system is given by
𝐻 = ∑ 𝐻𝑥 ∀𝑥 (3.1)
Page 12 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
However, here it is assumed that the summed response acts on the coherently swinging system,
𝐹(𝑗𝜔)
𝐹𝑥 (𝑗𝜔)
explained above. The control response is therefore here assumed to be delivered by a single unit
which control response is scaled to correspond to the total regulating strength in the system.
Figure 8 shows several units in parallel providing control response to the system.
Page 13 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
The rating and droop value play a role in the provision of FCR, the scaling of individual units’
response are explained in Subsection 3.3. Note that the droop value in combination of the power
base of the unit defines the regulating strength.
Further details of the hydro power plant modelling can be found in the description of the Nordic
frequency Model [2].
Backlash has been added in the model shown in Figure 10 which is added after the servo.
Page 14 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
The internal feedback can also be by feedback of the power, thus, the backlash is compensated
and its impact reduces. The impact from backlash is illustrated in Figure 12 which shows an input
signals that passes through a backlash which affects both the phase and amplitude of the output.
Note that we here define backlash as ±b. An input with amplitude A then the output reduces to A-
b (if b<A and the backlash centred).
Figure 11 shows the phase shift as function of backlash and is the ratio between the fundamental
components of the input and output. Figure 12 provides the phase shift in the time domain and is
provided by calculating the fundamental component (through Fast Fourier transform – FFT) of the
output signal. Note that only the backlash is considered here, if the input signal passes through an
LTI block before it enters the backlash additional phase shift adds up.
FIGURE 11. PHASE SHIFT AS FUNCTION OF THE RATIO BETWEEN THE BACKLASH AND SIGNAL AMPLITUDE.
Page 15 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
Applying the Fast Fourier transform (FFT) of a sinusoidal signal with amplitude A results in an
amplitude of A at the particular frequency of the sinusoidal. However, the FFT of the output signal
with backlash results in an amplitude larger than A-b. Thus, the impact of backlash is indirectly
reflected in linear analysis as it is included in the output response. The fundamental component
scaling takes into account the fact that the amplitude of the fundamental component is larger
than the actual signal, as shown in Figure 13.
Page 16 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
The calculation of the fundamental scaling factor, α, is done based on the size of the backlash in
relation to the signal strength. In a block diagram in Figure 14 the calculation is shown. In the sine-
in-sine-out tests the unit is trying to provide a signal 𝑎(𝑡) but due to the backlash the signal will
not be purely sinusoidal. The signal 𝑦(𝑡) represents the output signal due to backlash. Signals a(t)
and y(t) are the blue and red curves in Figure 13, respectively. 𝑎(𝑡) is given as
𝑎(𝑡) = sin(𝜔0 𝑡) (3.4)
where 𝜔0 is an arbitrary frequency > 0.
𝑎(𝑡) 𝑦(𝑡)
𝑇𝑜𝑡𝑎𝑙 𝐵𝑎𝑐𝑘𝑙𝑎𝑠ℎ𝑝𝑢
Now the output signal 𝑦(𝑡) can be simulated with a(t) entering the backlash block, shown in
Figure 14. The discrete FFT is calculated of the input and output signals as
𝑁−1
−𝑗2𝜋𝑛𝑘 (3.5)
𝐴(𝑘) = ∑ 𝑎(𝑛) 𝑒 𝑁
0
𝑵−𝟏
−𝒋𝟐𝝅𝒏𝒌
𝒀(𝒌) = ∑ 𝒚(𝒏) 𝒆 𝑵
(3.6)
𝟎
Page 17 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
The fundamental scaling factor can be calculated after performing the Fourier transforms.
𝑌(𝜔0 ) (3.7)
𝛼=
𝐴(𝜔0 )
Table 3 shows different backlash values and the corresponding scaling factor, α.
TABLE 3. BACKLASH SCALING FACTOR (𝜶) AS A FUNCTION OF TOTAL BACKLASH IN PERCENT OF TOTAL SIGNAL STRENGTH (±𝒃)
2𝑏 0% 1% 2% 3% 4% 5% 6%
α 1 0.999 0.998 0.997 0.996 0.994 0.992
2𝑏 7% 8% 9% 10 % 11 % 12 % 13 %
α 0.99 0.988 0.986 0.984 0.981 0.979 0.976
2𝑏 14 % 15 % 16 % 17 % 18 % 19 % 20 %
α 0.974 0.971 0.968 0.965 0.962 0.959 0.956
2𝑏 21 % 22 % 23 % 24 % 25 % 26 % 27 %
α 0.953 0.95 0.946 0.943 0.94 0.936 0.932
2𝑏 28 % 29 % 30 %
α 0.929 0.925 0.921
The internal feedback, ep, in an FCR-unit is most often expressed in percentage and is called droop.
This percentage value is expressed on its own power base, most often rated power, and is defined
as
𝑑𝑓 (3.8)
⁄𝑓
0
𝑒𝑝 = ∆𝑃⁄ .
𝑆n−𝐹𝐶𝑅
This equation states, a unit changes its power by 100 % at frequency change of ep [%]. Example, a
unit with droop of 6 % requires the frequency to drop 0.06 ∙ 50 𝐻𝑧 = 3 𝐻𝑧 to change its power by
100 %. Droops are commonly in the range 2-12% which implies the power change for FCR-N (±0.1
Hz) is in the range of ±10 % to ±1.67 % of the machines’ power base.
Backlash reduces the output and a typical backlash value of hydro power plants in the Nordic
system is around ±0.005 puiv [3]. Note that this value is given on the power base of the machine
and is independent of the droop. However, the ratio backlash divided by FCR-N capacity is strongly
depended on the droop. In order to achieve the required total steady-state capacity backlash is
compensated according to
𝑑𝑓 1
Δ𝑃FCR = 𝑆n−FCR [ ∙ − 𝑏] (3.9)
𝑓0 𝑒p
iv
Based on the machine’s power base
Page 18 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
Hence, it is important to know on which base the per unit values refers to as they may seem to be
similar. The beauty with per unit is that individual units’ responses are scaled to one whereas the
system also scales to one which then makes them compatible without further scaling. More
detailed description is given below.
Alternatively, each unit on the base Sn-FCR, using droop of 6 %, delivers a capacity of
Page 19 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
𝑑𝑓 1
Δ𝑃 = 𝑆N−FCR ∙ ∙𝑒 (3.12)
𝑓0 P
Simulation runs performed in the Nordic frequency model are based on this per unit scaling. Since
the model, backlash excluded, is linear one single machine can be used to provide the whole
capacity.
FIGURE 15. A (SISO) FREQUENCY CONTROL MODEL. SEE TABLE 1 FOR VARIABLE DEFINITION.
The input and output static gain for the FCR-provider becomes one per unit. This step of the
scaling can be achieved since the droop 𝑒𝑝 is defined as
d𝑓
⁄𝑓
0
𝑒p = (3.17)
𝑑𝑃⁄
𝑆n−FCR
Page 20 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
where d𝑓 and 𝑓0 are the frequency deviation limit and nominal frequency, respectively. 𝑑𝑃 is the
static capacity of the unit and 𝑆N−FCR the rated power of the unit.
The response from an FCR-unit is one per unit with droop of 0.002 (0.2 %) and rated power 600
MVA. This simplification of the modelling is shown in Figure 17.
Page 21 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
4. DESIGN OF REQUIREMENTS
The goals of the design are to improve the frequency quality and to ensure stability. The main
measure of frequency quality is minutes outside normal band (MoNB) – mathematically defined as
∫ 𝑑𝑡 , |∆𝑓(𝑡)| > 0.1 𝐻𝑧
{
0, |∆𝑓(𝑡)| < 0.1 𝐻𝑧 (4. 1)
𝑘𝑝𝑖𝑀𝑜𝑁𝐵 = .
∫ 𝑑𝑡
This KPI is mentioned in the constraints and specifies that MoNB should be less than 10 000
minutes per year corresponding to 1.9 % of the time.
The methodology developed within this project, for creating the future requirements imposed on
the FCR-N, is based on linear design considering fundamental limitations [4]. Stability and
performance are expressed with and without uncertainty as
Robust stability: The system is stable for all perturbed plants/controller about the nominal
model up to the worst-case model uncertainty.
Robust performance: The system satisfies the performance specifications for all perturbed
plants/controllers about the nominal model up to the worst-case model uncertainty.
The project applies robust stability for the low inertia system in addition to low frequency
dependency of loads. This implies an uncertainty for the low inertia system, given by the Euclidian
distance, is allowed before instability. Thus, there is an uncertainty margin which can either be in
the plant or in the FCR-unit response. This can be realised from the Nyquist curve as the loop gain
is defined by the system response times the controller response.
Moreover, the project has chosen to use nominal performance which means performance meets
the requirements in the average inertia system without uncertainty and provides acceptable
frequency quality on average. However, it is likely that the power disturbance varies over the year
but not necessarily correlated with the variation in the inertia of the system.
Hence, stability is expressed on the low inertia system and performance is expressed on the
average inertia system. The project believes that by using nominal performance and robust
stability a significant policy step forward is made compared to the current situation in the Nordic
synchronous area. In the future, an enhancement of this policy would be to move from nominal
performance towards robust performance.
Page 22 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
Thus, a circle with radius 1/Ms is plotted in the Nyquist diagram centred at the point -1. For
accepted control response, i.e. robust stability, the Nyquist curve shall not enter the circle or
encircle the point -1. However, so far the response is on the complete FCR response and not on
unit level. This can also be expressed as a requirement on the sensitivity function as
|𝑆min (𝑠)|∀𝜔 < 𝑀s = 2.31
(4.3)
where 𝑆𝑚𝑖𝑛 (𝑠) expresses the low inertia system. Scaling to individual units is explained in Section
5.
Example:
To exemplify the robustness, study the margin for the increased regulating strength. Stability
requires the point -1 to not be encircled. Therefore, consider the loop point that has 180o phase
shift (F(jω1)∙G(jω1)=-1) pointing in the negative direction along the real axis. Assume the point to
lie just at the circle, i.e. the coordinate is 0j+(r-1). Then, the loop gain is written as a function of the
regulating strength as follows
(𝑅0 + ∆𝑅)
𝐺0 |𝜔1 = 𝐹(𝑗𝜔1 )𝐺(𝑗𝜔1 ) = (1 − 𝑟)𝑒 𝑗𝜋 (4.4)
6000
where R0=6000 MW/Hz is the regulating strength used in the design and ∆R is the additional
regulating strength.
This corresponds to scale the regulating strength as follows
(6000 + ∆𝑅)
(1 − 𝑟)𝑒 𝑗𝜋 > −1 (4.5)
6000
Then, ∆𝑅 < 4582 MW/Hz
Note that the frequency will oscillate and the quality may be poor but stability is ensured.
Additional regulating strength coming from backlash is not included. Since the capacity is reduced
from backlash the regulating strength in terms of MW per Hz will increase as backlash comes in to
play. This is explained by the fact that the procured capacity is the steady state capacity.
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
bidding areas within Sweden. The tie-lines used to measure the net imbalances of a larger area
were the AC tie-lines interconnecting Areas SE3 and SE4, see Figure 18. This area was measured
because there is a very small amount of FCR-N active within this area, giving the measured values
a high degree of relevancy for the underlying stochastic generation-load imbalances. Also, the load
within the southern Swedish area constitutes on average a third of the total load in the Nordic
system. The data processing and detailed results are provided by the Imbalance study, see [5].
FIGURE 18. SCHEMATIC DESCRIPTION OF WHICH TIE-LINES MEASURED TO ESTIMATE GENERATION-LOAD IMBALANCES. MEASURED CUTS ARE
THOSE SHOWN WITH A RED LINE IN THE MAP ON RIGHT HAND SIDE.
The study aimed to emulate the statistical properties of the measured net-variation by modelling
it as the output of a linear filter with white noise as input. The study estimated the variations to
have low-pass characteristics and the process is given by
√3 ∙ 12 (4.6)
𝑑 = 𝐷est (𝑠)𝑤 = 𝑤
𝑠
where d is the net-power variation and w is the white noise input to the filter Dest(s). The aFRR also
contributes to balance the system and with its integration balancing from 2-3 minutes in addition
to the tertiary frequency control, manual frequency restoration reserve. In steady-state the
capacity is specified to 600 MW and therefore the imbalance profile is mapped to a first order
filter as
Page 24 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
600 (4.7)
𝐷(𝑠) =
𝑇dist 𝑠 + 1
where Tdist is the time constant of the imbalance profile.
Measurement data were not available over longer periods to estimate net-power variations in
order to verify the spread.
Eq. (2.7) states how a disturbance propagates through the system and is now written as
𝑆avg (𝑠)𝐷(𝑠)𝐺avg (𝑠)𝑤 = 𝑓
(4.8)
where Gavg(s) is the transfer function of the average inertia system. Rewriting this as
1
𝑆avg (𝑠)𝑤 = 𝐷(𝑠)𝐺 𝑓. (4.9)
avg (𝑠)
The power spectral density (PSD) state the relation between the input signal and the output given
as
2 1
|𝑆avg (𝑗𝜔)| ∅𝑤 (𝑗𝜔) = |𝐷(𝑗𝜔)𝐺 ∅f (𝑗𝜔) (4.10)
2
avg (𝑗𝜔)|
where ∅w (𝑗𝜔) is white noise with PSD equal to one and ∅f (𝑗𝜔) is the PSD of the frequency
deviation.
An output with equal limitation at each frequency and the PSD is constant ∅f (𝑗𝜔) = 𝜎f2 is
required.
This choice specifies a boundary of the amplification of all frequencies and a variance of the
frequency deviation. The performance requirement then becomes
𝜎 |𝑇 𝑠+1|
|𝑆𝑎𝑣𝑔 (𝑠)| < |𝐷(𝑠)𝐺 f dist
= 𝜎𝑓 𝐷(𝑗0)|𝐺 . (4.11)
avg (𝑠)| avg (𝑠)|
From this, the steady-state value is 6000 MW/Hz which is the ratio between 𝜎𝑓 and D(j0). As
mentioned before, deterministic disturbance signals require that (4.11) is fulfilled (with 𝜎f = 0.1)
in order to let an input signal of amplitude 600∙sin(ωt) MW (=1 pu) not result in a frequency
deviation larger than 0.1∙sin(ωt) Hz (=1 pu).
Enforcing the frequency target to 0.1 Hz/Hz at all frequencies and select the time constant to align
the transfer function in (4.11) does not necessarily ensure the frequency within ±0.1 Hz. As
argued above, stochastic signals are better described by the statistical property. If the output
frequency has the characteristics of white noise the frequency target have to be significantly
reduced. Fortunately this is not the case as the bandwidth of the output is bounded since the
inertia of the system reduces the effect on the output at high frequencies - what matter is the
variance of the output frequency.. The power spectrum does not necessary have to be smaller
than 0.1 Hz/Hz for all frequencies as it appears smaller at other frequencies.
In order to match the disturbance spectrum, and to still be able to obtain acceptable frequency
quality, an appropriate time constant must be found. The filter constant is found through analysis
Page 25 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
of a huge amount of simulation runs with various parameters sweeps that were performed in the
Nordic frequency model.
In order to reduce the quadratic sum of the frequency deviation, which relates to variance of the
output frequency, the approach above is not most appropriate. However, the approach specified
above has advantage when it comes to real testing and implementation as it is straightforward to
put requirement at particular time periods. Also, linear optimisation, see Appendix B, was
performed to find parameters (Kp and Ki) for the linear reference unit that fulfilled the
requirements. It was shown that there is a correlation between the resonance peak of the
sensitivity function and frequency quality. This peak is directly related to the stability margin.
The imbalance study indicated that the disturbance could be mapped to a low pass filter. There is
a trade-off between the filter constant and frequency quality while harder requirements result in
less capacity on the market. The simulations are performed with the Nordic frequency model-
profile by parameter sweeps over, Kp, Ti, backlash and droop. Then the minutes outside normal
band, described in next subsection, are quantified.
4.3 REQUIREMENTS
There are several aspects to consider when deciding the filter constant of the disturbance filter. As
described earlier, backlash has a great impact on the stability and performance. Thus, the signal
strength plays an important role and there is a trade-off between this and the filter time constant.
Figure 19 illustrates an example of the sensitivity functions for specific parameters of the linear
hydro power model.
𝑺𝒎𝒊𝒏 (𝒔)
𝑺𝒂𝒗𝒈 (𝒔)
Stability req.
Performance req.
Note that, inspection of Figure 19 clearly shows typical margins between the sensitivity function of
the low inertia system and the performance requirement. The low inertia system, instead, is
limited by the stability requirement. Note that, the performance requirement is here plotted
based on the average inertia system. The slope in the performance curve is moved to the right
with decreased inertia.
To create a picture of the trade-off, a huge amount of simulations were performed. Figure 19
indicates that the performance requirement is close to be violated around ω=10 -2 rad/s and the
Page 26 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
stability requirement around ω=6∙10-1 rad/s. Thus, performance is the limiting factor at longer
time periods (≈600-200 s) and stability at shorter time periods (≈60-10 s).
In the beginning of the project 30 mHz was proposed for testing, with time it turned out backlash
had too much impact compared to the units’ response.
Since the signal strength has great impact it has to be coordinated in order to find reasonable
over-all requirements. It turned out that impact on the performance from backlash occurred at
longer time periods where the phase lag of the FCR-response still was low. The backlash is more or
less fixed as it comes from mechanical parts and is here specified in per unit, as described earlier.
From the tests performed with 50 mHz amplitude it was seen that it is only possible to fulfil the
requirements for backlash up to ±0.004 pu, shown in Table 4. As set of parameters is a
combination of Kp and Ki, the range of the parameters simulated in Table 4 is
Ki=[0.1, 0.15, 0.2, 0.25, 0.3, 0.4]
and
Kp=[1, 1.5, 2, 2.5, 3, 3.5, 4, 4.5, 5, 5.5, 6, 6.5, 7, 7.5, 8, 8.5, 9, 9.5, 10]
which leads to 72 combinations. In addition to this, a sweep is run over backlash and droop. In
total 4752 number of qualification runs were performed.
Page 27 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
TABLE 4. NUMBER OF QUALIFIED PARAMETER SETS (MAXIMUM 72) AS TIME CONSTANT OF THE DISTURBANCE FILTER VARIES BETWEEN 70 S –
100 S.
70 s
80 s
90 s
100 s
One can argue, if the backlash is ±10 % for an input amplitude of ±100 mHz, i.e. the maximum
output is 90 %. Then if reducing the input amplitude to ±50 mHz, the maximum output becomes
80 %. Clearly, the loss in amplitude has increased by a factor of two. Supported by this argument,
and the fact that only a low value of the backlash was allowed, an amplitude of ±100 mHz was
chosen for performancev requirements to reduce the impact from the backlash.
The impact from backlash on the stability requirement is more complex as both the amplitude and
phase lag are reduced at the time periods of interest. A first attempt was to use amplitude of 50
mHz. This in order to capture instability in the range of small variation of the input which is the
normal variation of today in the Nordic power system.
In order to decide a proper time constant for performance another round of simulations were
performed on the Nordic frequency model. The results when varying backlash and droop are
v
Also for stability – motivated by the fact that it will make the actual testing simpler without affecting the results too
much.
Page 28 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
shown in Table 7 and Table 8 for variation of the droop. These were then compared to each other
together with the MoNB. The parameter sweeps are shown in Table 5 where the number of
combinations are 19∙10∙12∙6=13680. The parameters that are sweeped are Kp, Ti, droop and
backlash. These are sweeped for each choice of performance time constant i.e. 50-90 s. Table 6
shows the percentage of qualified units’ parameters and Figure 20 shows the duration curve with
600 MW FCR-N for different time constants. The x-axis indicates the percentage of all qualified
units producing MoNB that is lower than or equal to a certain value (y-axis). Based on all
simulations and studying the MoNB the time constant was selected to 70 s.
The control structure used in the models has Ki implemented, see Figure 9. In the simulations Ki is
scaled with ep so Ti becomes the same for any droop. The base case used is with a droop of 6 %.
Page 29 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
TABLE 7. NUMBER OF COMBINATIONS (MAXIMUM 100) QUALIFIED FOR PERFORMANCE AND STABILITY.
50 s
Droop\BL 0 0,001 0,002 0,003 0,004 0,005 0,006 0,007 0,008 0,009 0,01 0,011 0,012
2% 20 16 11 9 7 4 2 1 0 0 0 0 0
4% 30 24 20 17 14 9 6 4 1 0 0 0 0
6% 32 23 12 8 6 2 0 0 0 0 0 0 0
8% 37 22 8 6 1 0 0 0 0 0 0 0 0
10% 41 21 4 3 1 0 0 0 0 0 0 0 0
12% 45 22 4 0 0 0 0 0 0 0 0 0 0
60 s
Droop\BL 0 0,001 0,002 0,003 0,004 0,005 0,006 0,007 0,008 0,009 0,01 0,011 0,012
2% 29 25 21 15 12 9 6 4 2 1 0 0 0
4% 41 36 28 24 20 14 10 6 3 0 0 0 0
6% 44 35 18 12 11 5 2 0 0 0 0 0 0
8% 51 35 12 9 2 1 0 0 0 0 0 0 0
10% 59 36 6 4 2 0 0 0 0 0 0 0 0
12% 69 39 6 1 0 0 0 0 0 0 0 0 0
70 s
Droop\BL 0 0,001 0,002 0,003 0,004 0,005 0,006 0,007 0,008 0,009 0,01 0,011 0,012
2% 38 34 29 24 20 13 10 7 4 2 0 0 0
4% 50 45 39 32 26 20 16 9 6 2 1 0 0
6% 56 50 25 16 16 7 5 2 0 0 0 0 0
8% 68 51 16 13 5 3 0 0 0 0 0 0 0
10% 76 52 8 6 4 0 0 0 0 0 0 0 0
12% 80 51 9 3 0 0 0 0 0 0 0 0 0
80 s
Droop\BL 0 0,001 0,002 0,003 0,004 0,005 0,006 0,007 0,008 0,009 0,01 0,011 0,012
2% 48 42 37 31 28 19 15 11 7 4 1 0 0
4% 61 55 52 41 33 26 20 14 10 4 2 0 0
6% 72 63 33 23 21 14 8 3 1 0 0 0 0
8% 81 66 21 17 9 5 2 0 0 0 0 0 0
10% 86 64 11 10 6 0 0 0 0 0 0 0 0
12% 88 57 12 5 1 0 0 0 0 0 0 0 0
90 s
Droop\BL 0 0,001 0,002 0,003 0,004 0,005 0,006 0,007 0,008 0,009 0,01 0,011 0,012
2% 56 50 45 39 34 25 19 15 11 8 4 0 0
4% 73 67 61 49 42 33 25 18 12 6 3 1 0
6% 81 72 41 31 26 18 11 5 1 0 0 0 0
8% 87 72 29 21 11 6 3 0 0 0 0 0 0
10% 91 69 15 13 7 0 0 0 0 0 0 0 0
12% 92 61 16 7 1 0 0 0 0 0 0 0 0
Page 30 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
TABLE 8. QUALIFIED COMBINATIONS (MAXIMUM 72) OF TI AND KP FOR VARYING BACKLASH AND DROOP.
50s Ti \ Kp 1 2 3 4 5 6 7 8 9 10
10 0 0 0 0 0 1 2 2 3 4
20 0 4 8 10 12 10 12 14 15 17
30 2 7 12 16 18 17 19 21 22 24
40 2 7 13 17 18 18 22 21 22 24
50 0 3 4 5 4 5 7 7 8 10
60 0 0 0 0 0 0 0 0 1 2
70 0 0 0 0 0 0 0 0 0 1
80 0 0 0 0 0 0 0 0 0 0
90 0 0 0 0 0 0 0 0 0 0
100 0 0 0 0 0 0 0 0 0 0
60s Ti \ Kp 1 2 3 4 5 6 7 8 9 10
10 0 0 0 0 0 1 2 2 3 4
20 0 4 8 10 12 10 12 14 15 17
30 2 7 12 16 18 17 19 21 22 24
40 3 9 15 21 23 23 26 26 26 27
50 3 8 14 17 20 19 22 22 23 24
60 1 4 5 7 6 9 11 13 13 14
70 0 0 0 0 0 1 1 3 5 6
80 0 0 0 0 0 0 1 2 3 4
90 0 0 0 0 0 0 0 1 2 4
100 0 0 0 0 0 0 0 1 2 3
70s Ti \ Kp 1 2 3 4 5 6 7 8 9 10
10 0 0 0 0 0 1 2 2 3 4
20 0 4 8 10 12 10 12 14 15 17
30 2 7 12 16 18 17 19 21 22 24
40 3 10 18 24 25 25 28 27 27 28
50 4 10 16 22 24 26 26 27 27 28
60 3 9 14 20 19 23 22 24 22 23
70 2 4 6 8 11 12 13 15 16 16
80 0 0 0 0 1 3 5 6 7 8
90 0 0 0 0 0 1 3 5 6 6
100 0 0 0 0 0 1 3 4 5 6
80s Ti \ Kp 1 2 3 4 5 6 7 8 9 10
10 0 0 0 0 0 1 2 2 3 4
20 0 4 8 10 12 10 12 14 15 17
30 2 7 12 16 18 17 19 21 22 24
40 3 10 18 24 25 25 28 27 27 28
50 4 12 20 26 27 29 30 29 29 30
60 4 10 17 24 26 27 28 29 27 28
70 4 9 16 20 20 24 23 25 24 24
80 3 6 10 12 12 16 16 18 17 17
90 0 0 0 2 4 6 7 8 8 9
100 0 0 0 1 2 5 6 7 8 8
90s Ti \ Kp 1 2 3 4 5 6 7 8 9 10
10 0 0 0 0 0 1 2 2 3 4
20 0 4 8 10 12 10 12 14 15 17
30 2 7 12 16 18 17 19 21 22 24
40 3 10 18 24 25 25 28 27 27 28
50 4 12 20 26 27 29 30 29 29 31
60 4 13 20 27 28 30 30 32 30 30
70 4 13 19 26 25 28 28 30 28 29
80 4 9 16 19 21 24 23 25 24 24
90 3 6 10 12 15 16 17 19 17 18
100 0 0 2 5 6 9 9 11 10 11
Page 31 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
FIGURE 20. DURATION CURVE OF MONB USING DIFFERENT DISTURBANCE FILTER TIME CONSTANT AND A VOLUME OF 600 MW FCR-N.
As described in Appendix there is a clear relation between the resonance peak of the sensitivity
function and the minutes outside normal band. Moreover, the performance requirement was
designed not to let a disturbance result in too high output even though the minutes outside on
average are acceptable. Figure 21 shows two sets of Kp and Ki parameters where the non-qualified
unit fails at a particular time period but performs better in terms of minutes outside normal band
than a qualified unit.
Page 32 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
Figure 22 shows qualified and non-qualified sets of parameters for a unit with 2 % droop and
varying backlash. Clearly, on average the qualified units perform much better in terms of minutes
outside normal band than non-qualified units. As expected, including non-linearities show that
there is no clean cut between qualified and non-qualified units and sets of parameters. Also there
is a difference coming from the quantification of MoNB, which is rather rough, and the fact that
quantifying measures in the time and frequency domain have different objectives. One aim has
been to reduce the overlap which is also a reason for choosing the 70 second time constant of the
disturbance filter.
Page 33 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
FIGURE 22. GREEN MARK INDICATES A QUALIFIED SET OF KP AND KI PARAMETERS, WHEREAS RED IS NOT QUALIFIED FOR A UNIT WITH 2%
DROOP.
Page 34 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
Stability Performance
A. Sensitivity S–A. P–A.
|𝑆min (𝑠)| < 𝑀𝑠 vi 𝜎𝑓
|𝑆𝑎𝑣𝑔 (𝑠)| <
|𝐷(𝑠)𝐺avg (𝑠)|
B. Nyquist S–B. P–B.
1
|−𝐹(𝑠)vii 𝐺(𝑠) + 1| > 𝑀 |𝐷(𝑠)𝐺avg (𝑠)|
s |−𝐹(𝑠)vii 𝐺avg (𝑠) + 1| >
|𝜎f |
C. FCR-plane S–C. P–C.
1 1 |𝐷|
𝐹(𝑠)vii − 𝐹(𝑠)vii − 𝐺 > |𝜎f |
𝐺min (𝑠) avg (𝑠)
vi
1
>
Ms |𝐺min (𝑠)|
The requirements are translated into a requirement of power plant performance and stability in
order to be tested and verified locally at each FCR provider “𝐹(𝑠 = 𝑗𝜔)”. The FCR-N response is
defined by internally apply the negative feedback, shown in Figure 23. This implies the loop gain to
be re-defined as
𝐺0 (𝑠) = −𝐺(𝑠) ∙ (−𝐹(𝑠)) (4.13)
which is equivalent of a phase shift of 180o. For sensitivity or Nyquist the positive feedback is
handled by simple phase shift the FCR response by 180o. The method mapped to the FCR-plane
considered the sign in the derivation.
vi
This holds if nominal stability is ensured
vii
Note, the FCR response is here defined with positive feedback and the negative sign included in the internal
response.
Page 35 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
A. SENSITIVITY
Sensitivity has been described and it is used as the starting point to develop performance in the
Nyquist and FCR-plane. This is a common way to describe combined requirements of Euclidian
norm for stability and rejection of disturbances.
Stability in the Nyquist plane was explained in Section 2.1. The performance requirement can also
be expressed in the Nyquist plane. The requirement in (4.11) is re-written as
𝐷(𝑠)𝐺avg (𝑠)
|𝐹(𝑠)𝐺(𝑠) + 1| > | | = |𝑟p (𝑠)|. (4.14)
𝜎f
Thus, to fulfil the performance requirement the Nyquist curve shall stay outside the Nyquist
performance circles rp(s) for all frequencies. Thus, circles centred at the point -1 with various
radiuses – each point (frequency) of the Nyquist must lie outside the corresponding circle. An
example is plotted in Figure 24 with two different performance circles in addition to the firm
stability circle.
Page 36 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
FIGURE 24. NYQUIST DIAGRAM FOR TWO DIFFERENT UNITS. BLACK CIRCLE IS THE STABILITY REQUIREMENT AND BLUE AND DARK RED ARE
PERFORMANCE REQUIREMENTS AT DIFFERENT TIME PERIODS.
C. THE FCR-PLANE
The FCR-planeviii is a mapping of the requirement expressed in sensitivity to an FCR response (FCR-
vector). The absolute value of the sensitivity function 𝑆(𝑗𝜔) can be expressed as the inverse of the
distance between a Nyquist curve and the point -1. The FCR function is given with positive
feedback, thus the sensitivity function is rearranged to
1 1
|𝑆(𝑠)| = = . (4.15)
|𝐺O (𝑠)−(−1)| |−𝐹(𝑠)∙𝐺(𝑠)−(−1)|
This can be interpreted as the joint response of all FCR providers and the controlled system that
they together should have a stronger response than the disturbance vs. frequency quality target
viii
For more information on M-circles please see [7]
Page 37 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
that is required, with phase shift considered. The controlled system’s load frequency dependency
continuously helps to dampen the effects of the active power disturbances whereas the system
inertia reduces the additional work required by the FCR providers only at short period times. The
same holds for stability margins but here the total system response should be larger than a
different value.
The technical implications of (4.16)-(4.17) is that the FCR response, 𝐹(𝑗𝜔), is a complex valued
function of 𝜔. With the FCR response being complex valued this entails that it can be depicted as a
vector in the complex plane. Then this implies that the distance between the vectors 𝐹(𝑗𝜔) and
1 |𝐷(𝑗𝜔)|
, which is also complex valued, must be greater than a certain value, |𝜎f |
for performance
𝐺(𝑗𝜔)
1
and for stability margins. In graphical terms this implies that the FCR vector must
𝑀s |𝐺min (𝑗𝜔)|
|𝐷(𝑗𝜔)| 1 1
point outside a circle with the radius of or with their centre at and
|𝜎f | Ms |𝐺min (𝑗𝜔)| 𝐺avg (𝑗𝜔)
1
, as shown in Figure 25 . This implies the radius and the centre of the circle are a function of
𝐺min (𝑗𝜔)
frequency (jω). Hence, the circles move around in the FCR-plane and can only be visualised at
discrete frequencies, exemplified in Figure 26.
FIGURE 25. GRAPHIC INTERPRETATION OF THE REQUIREMENT STATED IN (4.17) WITH PERFORMANCE REQ. SHOWN TO THE LEFT AND
STABILITY MARGINS REQ. SHOWN TO THE RIGHT. THE FCR PROVIDER “𝑭(𝒋𝝎)” FULFILS THE REQUIREMENT IN (4.16) IF THE
𝑭(𝒋𝝎)-VECTOR POINTS “OUTSIDE” THE GREEN CIRCLES.
Page 38 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
FIGURE 26. VISUALISATION OF THE THREE FCR-VECTORS FOR DIFFERENT TIME PERIODS.
5. TEST PROCEDURE
In a simulation model one can perform the testing in a continuous manner. However, real testing
requires testing at discrete and finite number of test periods of the injected sinusoidal. Stability
and performance requirements specify limits on the sensitivity functions specified on the total
system (for Gmin and Gavg). The aim of the requirements on an FCR-N provider is that an individual
unit shall be able to be tested locally on site. The performance and stability requirements
described above are not expressed on such form. Per unit scaling simplifies the performance
70𝑠+1
requirement to |𝑆avg (𝑠)| < .
pu 𝐺avg (𝑠)
This can be done since the regulating strength is 6000 MW/Hz and this is then one per unit.
The beauty of using per unit comes at the point of testing different units as no rescaling from per
unit on individual power bases is necessary. Recall definition of the loop gain as G(s) times F(s).
The static gain of an FCR provider x is 𝐹x (𝑗0) and the number 𝑛x time the static unit response shall
result in the total gain of dP, i.e.
Page 39 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
𝐹𝑥 (𝑗0)𝑛𝑥 = 𝑑𝑃 (5.1)
Then the loop gain can be written as
𝐹𝑥 (𝑗0) ∙ 𝑛𝑥 𝑑𝑃
𝐺(𝑠)𝐹(𝑠) = 𝐺(𝑠) ∙ 𝐹𝑥 (𝑠) ∙ 𝑛𝑥 = 𝐺(𝑠) ∙ 𝐹𝑥 (𝑠) ∙ 𝑛𝑥 = 𝐺(𝑠) ∙ 𝐹𝑥 (𝑠) ∙ 𝑛𝑥 =
𝐹𝑥 (𝑗0) ∙ 𝑛𝑥 𝐹𝑥 (𝑗0) ∙ 𝑛𝑥
𝐹𝑥 (𝑠) 𝐹𝑥 (𝑠)
= 𝐺(𝑠) ∙ 𝑑𝑃 ∙ = 𝐺𝑝𝑢 (𝑠) ∙ (5.2)
𝐹𝑥 (𝑗0) 𝐹𝑥 (𝑗0)
Note that the system expressed in physical units is scaled to per unit by dP. The last term is the per
unit scaling of an individual unit and it is clear that the requirements can be mapped to the per
unit response of a unit with any capacity contribution.
Page 40 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
The normalisation consists of two steps, first backlash is to be found and secondly the
fundamental component scaling has to be included.
Hence, the normalized gain of the transfer function for any angular frequency 𝜔 can be calculated
as
|𝐹𝐶𝑅𝑥 (𝑗𝜔)|
|𝐹𝑥−pu (𝑗𝜔)| = (5.6)
𝑒𝑥
360°
φ = Arg(-F(jω)) = ∆𝑡 (5.9)
𝑇
where T is the time period (s) and ∆𝑡 is the time difference (s) of the input (frequency) signal and
output (power) signal, as shown in Figure 28.
To allow some uncertainty during real tests the true requirement is set to 95 % at each time
period. This would allow for 5 % error for stability or performance. The radius of the stability circle
in the Nyquist plane in reduced by 5 % and so is each performance circle.
Page 41 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
FIGURE 28. SINE TESTS, TRANSFER FUNCTION VALUES AND BODE PLOTS.
Page 42 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
6. CONCLUSIONS
This work describes the new requirements that have been developed for the frequency
containment reserve for normal operation, FCR-N. The main aim was to develop new
requirements that improve the frequency quality in the Nordic synchronous area. Moreover, the
requirements shall be expressed such that they can be implemented in a unified manner. New
requirements have been developed which are testable locally on site by performing step and sine-
in-sine-out tests. The requirements are expressed in stability and performance requirement which
are combined. These can be expressed in terms of limit on the sensitivity function, Nyquist plane
or FCR-plane. Stability is expressed with a margin in order to maintain stability with uncertainties
included. Performance is expressed in terms of amplification from a disturbance, at any frequency,
to the impact on the output frequency quality.
7. REFERENCES
[1] H. Nyquist, ”Regeneration theory,” The Bell System Technical Journal, pp. 126-147, 1932.
[2] ”Description of Nordic frequency model,” Control design working group, 2017.
[3] T. Ellefsrød, ”Nordic Grid - FNR Frequency Containment, Generating equipment performance -
review report,” Norconsult, 2016.
[4] S. Skogestad och I. Postlethwaite, Multivariable Feedback Control, 2nd red., Wiley, 2005.
[5] ”Imbalance study SE3-4,” Control design working group, Sundbyberg, 2016.
[6] ” DESCRIPTION OF NORDIC FREQUENCY MODEL", Control design working group, 2017.
[7] T. Hägglund och K. J. Åström, Advanced PID Control, ISA-The Instrumentation, Systems, and
Automation Society, 2006.
Page 43 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
The technical Requirements for Frequency Containment Reserve Provision in the Nordic
Synchronous Area specify formal technical requirements for Frequency Containment Reserve
(FCR) providers as well as requirements for compliance verification and information exchange. The
requirements are based on SOGL 1, with proper adjustments to be suitable for the Nordic
conditions.
In this document the time domain model for simulating the frequency behavior of the Nordic
Synchronous system is described. The model is based on the initial model developed for the
Nordic project called “RAR” which was conducted in 20.
8.4 “ POWER PLANT QUALIFICATION STUDY, FINAL DESIGN WITH 70S PROFILE“,
CONTROL DESIGN WORKING GROUP, FREDERICIA, 2017
This document reports on the results from simulations of a pre-qualification study of a hydro
power plant according to the performance specification of the FCR-N as described in section 8.1.
The simulations were performed with the Nordic Frequency model described in section 8.2.
8.5 “SYSTEM PERFORMANCE STUDY, FINAL DESIGN WITH 70S PROFILE“, CONTROL
DESIGN WORKING GROUP, FREDERICIA, 2017
In this document the system frequency performance obtained with the new FCR-N requirements
as defined by section 8.1 is compared with the system frequency performance of the existing
Nordic FCR-N reserves anno 2017.
Page 44 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
This appendix describes an optimizing routine developed on a simplified linear model. The routine
uses different hard and soft tuning targets to develop an optimized parameter settings on the
turbine governor.
THE OPTIMIZATION ROUTINE STATES THAT FOR THE HARD TUNING TARGET THE REQUIREMENT SHALL BE MET WHEREAS FOR THE SOFT TARGET
THEY SHALL BE MINIMIZED.
The soft targets are developed to i) minimize the open-loop bandwidth of an FCR-N provider from grid
frequency input to active power output and ii) minimize the resonance peak of the closed-loop system from
power disturbances to grid frequency deviations. Varying the factor K in the soft target for bandwidth
limitation allows the routine to develop different system configurations / parameterizations that can be
evaluated against each other.
Two different simulations have been attempted
i. Four different hard performance requirements have been tested combined with varying the K-
factor. The intention with varying the K-factor is that it will realize the system from one extreme
point (slow FCR response) to another extreme point (minimized resonance peak).
ii. Ten different hard performance requirements have been tested combined with a fixed K-factor
(minimize FCR-N bandwidth). The hard performance requirement is here tested with 600 MW and
a time constant that ranges from 10 s to 100 s, in steps of 10 s.
Page 45 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
FIGURE 30.SUMMARY PLOT OF DIFFERENT TRANSFER FUNCTIONS DESCRIBING THE OPTIMIZED SYSTEM. FOR THIS PARTICULAR SYSTEM THE
PERFORMANCE REQUIREMENT IS MODELLED WITH 900 MW STEADY STATE CAPACITY AND 90S TIME CONSTANT OF THE
𝟏.𝟐𝟏𝟎
DISTURBANCE PROFILE. THE K-FACTOR FOR LIMITING FCR-N BANDWIDTH IS SET TO RAD/S.
𝟏𝟎
FIGURE 31. PI PARAMETERS FOR AN FCR-N UNIT WITH 6% DROOP PLOTTED AGAINST THE PEAK GAIN OF THE NORMALIZED TRANSFER
FUNCTION OF 𝑮 ∗ 𝑺.
Page 46 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
FIGURE 32. BODE MAGNITUDE FOR THE NORMALIZED TRANSFER FUNCTION G*S OF THE NOMINAL SYSTEM. [COLOR = STEADY STATE
DISTURBANCE CAPACITY / DISTURBANCE TIME CONSTANT]: BLUE = 900 MW / 60 S, YELLOW = 900 MW, RED = 600 MW /
90 S, BLACK = 600 MW, 60 S.
FIGURE 33. BODE MAGNITUDE FOR THE SENSITIVITY TRANSFER FUNCTION, S, OF THE NOMINAL SYSTEM. [COLOR = STEADY STATE
DISTURBANCE CAPACITY / DISTURBANCE TIME CONSTANT]: BLUE = 900 MW / 60 S, YELLOW = 900 MW, RED = 600 MW /
90 S, BLACK = 600 MW, 60 S.
Figure 32 shows that the peak gain is higher for a system with a higher static capacity of the disturbance
transfer function, D. This means that efficiency per MW of FCR-N resource is lower for larger amounts of
FCR-N. An example explaining the resonance peak follows below.
D: 900 MW, 90s time constant: ‖𝐺(𝑗𝜔)𝑎𝑣𝑔 𝑆(𝑗𝜔)𝑎𝑣𝑔. ‖ = 8.60 [𝑝. 𝑢. ] = 9.60 ∗ 10−4 [𝐻𝑧/𝑀𝑊]
∞
D: 600 MW, 90s time constant: ‖𝐺(𝑗𝜔)𝑎𝑣𝑔 𝑆(𝑗𝜔)𝑎𝑣𝑔 ‖ = 7.62 [𝑝. 𝑢. ] = 12.4 ∗ 10−4 [𝐻𝑧/𝑀𝑊]
∞
Ratio of peak gains between MW steady state gains and resonance peaks
Page 47 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
900
𝑀𝑊𝑟𝑎𝑡𝑖𝑜 : = 1.5 [𝑝. 𝑢. ]
600
9.60 ∗ 10−4
𝑃𝑒𝑎𝑘 𝑔𝑎𝑖𝑛𝑟𝑎𝑡𝑖𝑜 : = 0.77 [𝑝. 𝑢. ]
12.4 ∗ 10−4
The ratio between the MW-ratio and the peak gain-ratio shows which system that has the highest MW-
efficiency for reducing the total system resonance peak.
𝑀𝑊𝑟𝑎𝑡𝑖𝑜 1.5
𝜂𝑀𝑊 = = = 1.95 [𝑝. 𝑢. ]
𝑃𝑒𝑎𝑘 𝑔𝑎𝑖𝑛𝑟𝑎𝑡𝑖𝑜 0.77
The example shows that the 600 MW-system has approximately double the efficiency of suppressing the
resonance peak compared to the 900 MW-system per MW of FCR-N capacity. However, the 900 MW-
system still suppresses the resonance peak to only 75% of the 600 MW-resonance peak in [Hz/MW].
Optimization for 10 different scenarios and fixed K-factor
FIGURE 34. PI PARAMETERS FOR AN FCR-N UNIT WITH 6% DROOP PLOTTED AGAINST THE PEAK GAIN OF THE NORMALIZED TRANSFER
FUNCTION OF ∗ 𝑺 .
Page 48 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
FIGURE 35. BODE MAGNITUDE FOR THE NORMALIZED TRANSFER FUNCTION OF G*S OF THE NOMINAL SYSTEM.
FIGURE 36. BODE MAGNITUDE FOR THE SENSITIVITY TRANSFER FUNCTION, S, OF THE NOMINAL SYSTEM.
Figure 30 to Figure 38 indicate that if the time constant for the disturbance function, D, is
decreased then the peak gain of the normalized transfer function of 𝑮 ∗ 𝑺 is also decreased and
̂ ∗ 𝑺 is also reduced.
the variance of the physical transfer function of 𝑮
Comparisons – Frequency domain vs. time domain
The frequency domain doesn’t tell the complete story. Therefore, the system has also been simulated with
disturbance time series that were developed in the RAR-project. From these simulations, the response in
relation to the kpis’ is evaluated.
Optimization for four different scenarios and varying the K-factor
Page 49 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
FIGURE 37. SUMMARY OF THE DEVELOPED KPIS’ PLOTTED AGAINST EITHER THE PEAK GAIN OF THE NORMALIZED TRANSFER FUNCTION OF ∗ 𝑺
̂ ∗ 𝑺 OR THE VARIANCE OF THE NORMALIZED TRANSFER FUNCTION
, THE CALCULATED VARIANCE OF THE PHYSICAL SYSTEM OF 𝑮
𝒔 ∗ 𝑪 ∗ 𝑮 ∗ 𝑺.
Figure 37 shows some different and interesting things.
KPI: MoNB
i. There is a relationship between the MoNB and the variance of the physical transfer function of
̂ ∗ 𝑺 where a reduction of the variance reduces the kpi.
𝑮
ii. It is also visible that the total FCR-N steady state capacity here has a positive influence in that it
supresses the kpi further.
iii. Further suppression of the kpi is attained if the disturbance time constant is reduced from 90 s to
60 s. The efficiency of the time constant is lower though than an increase in the static capacity (ii).
KPI: Balance
i. There is a relationship between the MoNB and the variance of the physical transfer function of
̂ ∗ 𝑺 where a reduction of the variance reduces the kpi.
𝑮
ii. It is also visible that the total FCR-N steady state gain here has a positive influence in that it
supresses the kpi further.
iii. Further suppression of the kpi is attained if the disturbance time constant is reduced from 90 s to
60 s. The efficiency of the time constant is lower though than an increase in the static capacity (ii).
KPI: Δf(t)-path
i. There is a clear relation between the relative arc length of the grid frequency deviation vs the peak
gain of the normalized transfer function for 𝑮 ∗ 𝑺.
Page 50 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
ii. It is also visible that the total FCR-N steady state capacity here has a positive influence in that it
supresses the kpi further.
KPI: Δu(t)-path
i. If the total FCR-N steady state capacity is increased then the kpi is increased.
ii. The smaller the resonance peak is for the normalized transfer function 𝑮 ∗ 𝑺, the larger the kpi
becomes
iii. There seems to be a minimum value for the peak gain where the kpi is at its smallest value
iv. At larger peak gain values the kpi takes on larger values again.
i. There seems to be some type of exponential relationship between the variance of the normalized
transfer function G*S and s*C*G*S.
i. There is a general linear relationship between the normalized transfer of s*C*G*S and the relative
arc length of the FCR-N controller output.
ii. The linear relationship seems to only hold down to a certain point and then the relative arc length
increases.
i. The more effort that is put in to suppressing the resonance peak the more work an FCR-N provider
has to do.
ii. If the FCR-N provider reduces its bandwidth too much giving a large resonance peak then the work
performed starts to increase.
iii. The steady state gain of the FCR-N is more important for the MoNB and balance kpis’ than the
bandwidth of the FCR-N provider.
Page 51 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
FIGURE 38. SUMMARY OF THE DEVELOPED KPIS’ PLOTTED AGAINST EITHER THE PEAK GAIN OF THE NORMALIZED TRANSFER FUNCTION OF
̂ ∗ 𝑺 OR THE VARIANCE OF THE NORMALIZED TRANSFER FUNCTION
𝑮 ∗ 𝑺 , THE CALCULATED VARIANCE OF PHYSICAL SYSTEM OF 𝑮
OF 𝒔 ∗ 𝑪 ∗ 𝑮 ∗ 𝑺.
i. There is a relationship between the MoNB and the variance of the physical transfer function of
̂ ∗ 𝑺 where a reduction of the variance reduces the kpi. It is not linear, however, but seems to be
𝑮
exponential.
KPI: Balance
i. There is a relationship between the Balance and the variance of the physical transfer function of
̂ ∗ 𝑺 where a reduction of the variance reduces the kpi. It is not linear however but exponential.
𝑮
KPI: Δf(t)-path
i. There is a clear relation between the relative arc length of the grid frequency deviation vs the peak
gain of the normalized transfer function for 𝑮 ∗ 𝑺.
KPI: Δu(t)-path
i. There is a clear relation between the relative arc length of the FCR-N controller output vs the peak
gain of the normalized transfer function for 𝑮 ∗ 𝑺.
ii. The more effort that is put in to suppressing the resonance peak the more work and FCR-N provider
has to do.
Page 52 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu
European Network of
Transmission System Operators
for Electricity
i. There seems to be some type of exponential relationship between the variance of the normalized
transfer function of G*S and s*C*G*S.
i. There is a general linear relationship between the normalized transfer of s*C*G*S and the relative
arc length of the FCR-N controller output.
ii. The linear relationship seems to only hold down to a certain point and then the relative arc length
i. The more effort that is put in to suppressing the resonance peak the more work an FCR-N provider
has to do.
ii. If the FCR-N provider reduces its bandwidth too much giving a large resonance peak then the work
performed again starts to increase.
iii. The steady state gain of the FCR-N is more important for the MoNB and balance kpis’ than the
bandwidth of the FCR-N provider.
Page 53 of 53
ENTSO-E AISBL • Avenue Cortenbergh 100 • 1000 Brussels • Belgium • Tel +32 2 741 09 50 • Fax +32 2 741 09 51 • [email protected] • www.entsoe.eu