100% found this document useful (1 vote)
741 views1 page

Standard Building Construction Productivity

This document outlines standard norms and key trades for various construction activities. It lists 5 manpower roles - Mason, Shuttering Carpenter, Steel Fixer, Painter, and Welder. For each role, it specifies the activities performed, unit of measurement (UOM), and estimated man-days required to complete the work. Remarks provide additional details on scope of work or specifications. The norms provide a baseline for estimating labor requirements and productivity for typical construction tasks.

Uploaded by

Sunil B S Rao
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
741 views1 page

Standard Building Construction Productivity

This document outlines standard norms and key trades for various construction activities. It lists 5 manpower roles - Mason, Shuttering Carpenter, Steel Fixer, Painter, and Welder. For each role, it specifies the activities performed, unit of measurement (UOM), and estimated man-days required to complete the work. Remarks provide additional details on scope of work or specifications. The norms provide a baseline for estimating labor requirements and productivity for typical construction tasks.

Uploaded by

Sunil B S Rao
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

STANDARD NORMS - KEY TRADES

Norm /
Sl # Manpower Activities UOM Remarks
M.day

1 Mason Block Masonry - Normal Sqm 10

Block Masonry - Reinforced Sqm 8

Concrete Cum 30

Screed Sqm 20

Plastering-External Sqm 10 Including preparation

Plastering-Internal Sqm 12 Including preparation

Rip-Rap Works Sqm 20 Mortar Rip-Rap

Terrazo Tiling Sqm 12

Ceramic Tiling Sqm 6

Marble tiling Sqm 3

Stone Cladding Sqm 2.5

Interlock Tiling Sqm 15

Plain Cement Tiling Sqm 20

Kerb fixing RM 25

2 Shuttering Carpenter Formwork-Footings, foundations, ground Sqm 8

Formwork-Columns, pedestals Sqm 6

Formwork-Beams and slabs Sqm 8

Formwork-Tie beams, arches, lintels Sqm 5

Formwork-Walls Sqm 8

Formwork-Circular, special shapes Sqm 4

Formwork- Making timber shutters Sqm 8

3 Steel Fixer Reinforcement-Cutting & Bending Kg 400

Reinforcement-Tying < 12mm Kg 250

Reinforcement-Tying > 12mm Kg 300

4 Painter Painting-Emulsion Sqm 15 Primer+2 coats

Epoxy Coating Sqm 10 Primer+2 coats

Painting-Texture/Special Sqm 10 Primer+2 coats

Painting-Enamel/Wood Sqm 10 Primer+2 coats

5 Welder DSS/SS Welding Inch dia 10

CS/LTCS Welding Inch dia 50 Flow line