Tcee 161003100321

Download as pdf or txt
Download as pdf or txt
You are on page 1of 30

TESTING &

MAINTENANCE OF
TRANSFORMER

PRESENTED BY:
SMRITI KESHARWANI
ASST PROF.

DEPARTMENT OF ELECTRICAL ENGINEERING


DR C V RAMAN UNIVERSITY, KOTA C.G.
TESTING OF TRANSFORMER
• TESTING IS CARRIED OUT AS PER IS-2026.
• ROUTINE , TYPE TESTS & SPECIAL TESTS

• ROUTINE TESTS ( TO BE CARRIED OUT ON EACH JOB)


• 1.Measurement of winding resistance
• 2.Measurement of insulation resistance
• 3.Seperate source voltage withstand test (High Voltage tests on HV & LV)
• 4.Induced Over voltage Withstand test (DVDF test)
• 5.Measurement of voltage ratio
• 6.Measurement of NO LOAD LOSS & current.
• 7.Measurement of LOAD LOSS & IMPEDENCE.(EFFICIENCY &
REGULATION)
• 8.Vector Group Verification
• 9.Oil BDV test.
• 10.Tests on OLTC (if Attached)
THESE TESTS ARE CARRIED OUT ONLY ON
ONE TRANSFORMER OF THE LOT.
 All routine tests
 Type tests
1. Lightening Impulse test.
2. Temperature rise test
 Additional Impulse test
 Short circuit test
 Measurement of zero Phase sequence Impedance test.
 Measurement of acoustic noise level.
 Measurement of harmonics of the no load current.
 Magnetic balance test.
1.MEASUREMENT OF WINDING RESISTANCE
This test measures the resistance of the HV & LV
winding. The values of resistance should be balance
for all three phases and should match the designed
values.
Equipment used : Digital resistance meter.
2.MEASUREMENT OF INSULATION RESISTANCE
Measures the insulation resistance of HV & LV
windings with respect to earth (body) and between LV
& HV winding.
INSULATION TESTER OR MEGGER IS USED.
Recommended Values are
2000Mohms for HV & 500 Mohms for LV.
3.SEPERATE SOURCE VOLTAGE WITHSTAND TEST (High
Voltage tests on HV & LV)-

This test checks the insulation property between Primary to earth,


Secondary to earth and between Primary & Secondary.

HV high voltage test : LV winding connected together and earthed.


HV winding connected together and given 28 KV ( for 11KV
transformer) for 1 minute.

LV high Voltage test : HV winding connected together and earthed. LV


winding connected together and given 3 KV for 1 minute.
Equipment used : High Voltage tester ( 100KV & 3KV)
4.INDUCED OVER VOLTAGE WITHSTAND TEST
(DVDF TEST)- This test checks the inter turn
insulation.

For a 11KV/433V transformer,866 Volts are applied


at the 433V winding with the help of a Generator for
1 minute. This induces 22KV on 11KV side. The
frequency of the 866V supply is also increased to
100HZ.
Equipment used : MOTOR GENERATOR SET
5.MEASUREMENT OF VOLTAGE RATIO
This test measures the voltage ratio as per the
customer’s requirement.
V1/V2 = N1/N2
The voltage ratio is equal to the turns ratio in a
transformer. Using this principle, the turns ratio is
measured with the help of a turns ratio meter. If it is
correct , then the voltage ratio is assumed to be
correct.
Equipment used : Turns Ratiometer
6.MEASUREMENT OF NO LOAD LOSS & CURRENT-
The iron losses and no load current are measured in
this test. The 433V winding is charged at 433V
supply & the 11KV winding is left open .The power
consumed by the transformer at no load is the no load
loss in the transformer.
Effect of actual frequency must be taken into account.
Equipment used : Watt meters or power analyzer.
7.MEASUREMENT OF LOAD LOSS &
IMPEDENCE.(EFFICIENCY & REGULATION)

This test measures the power consumed by the


transformer when the 433V winding is short circuited
and The rated current is passed through the 11KV
winding.
Equipment used : Wattmeters or power analyzer.
8.VECTOR GROUP VERIFICATION TEST
This test verifies the Dyn-11 vector group of a
distribution transformer.

Equipment used : voltmeter.


 Oil BDV TEST.
Oil breakdown voltage is checked as per IS-335.
100 mm L X 70 mm B X 80 mm Ht. glass pot.
500ml Oil sample.
Spherical electrodes with gap of 2.5 mm
Recommended value : 60KV
Equipment used : OIL BDV TEST SET.
LIGHTENING IMPULSE TEST
 All the dielectric tests check the insulation level of the job.
 Impulse generator is used to produce the specified voltage
impulse wave of 1.2/50 micro seconds wave
 One impulse of a reduced voltage between 50 to 75% of the
full test voltage and subsequent three impulses at full voltage.
 For a three phase transformer, impulse is carried out on all
three phases in succession.
 The voltage is applied on each of the line terminal in
succession, keeping the other terminals earthed.
 The current and voltage wave shapes are recorded on the
oscilloscope and any distortion in the wave shape is the criteria
for failure.
SHORT CIRCUIT WITHSTAND ABILITY TEST-
 This tests measures the ability of the transformer to withstand
the mechanical and thermal stresses caused by the external
short circuit.
 HV terminals are connected to the supply bus of the testing
plant. The LV is short circuited. The testing plant parameters
are such adjusted to give the rated short circuit current.
 Supply is made on and closed after specified duration of short
circuit. The record of current wave form is noted.
 There should not be any mechanical distortion, fire to the
transformer during this test. Similarly no wave form
distortion. The transformer should also withstand the routine
tests after the short circuit test.
 The reactance of the winding measured before and after the
S.C. test should not vary beyond the limits stated in the
IS2026.
 Transformer is the heart of any power system.
Hence preventive maintenance is always cost
effective and time saving. Any failure to the
transformer can extremely affect the whole
functioning of the organization.
 OIL :
1. Oil level checking. Leakages to be attended.
2. Oil BDV & acidity checking at regular intervals.
If acidity is between 0.5 to 1mg KOH, oil should
be kept under observation.
3. BDV, Color and smell of oil are indicative.
1. Sludge, dust, dirt ,moisture can be removed by
filtration.
2. Oil when topped up shall be of the same make. It
may lead to sludge formation and acidic contents.
 Insulation resistance of the transformer should be
checked once in 6 months.
 Megger values along with oil values indicate the
condition of transformer.
 Periodic Dissolved Gas Analysis can be carried out.
 BUSHINGS
Bushings should be cleaned and inspected for any cracks.
Dust & dirt deposition, Salt or chemical deposition,
cement or acid fumes depositions should be carefully
noted and rectified.
 Periodic checking of any loose connections of the
terminations of HV & LV side.
 Breather examination. Dehydration of Silica gel if
necessary.
 Explosion vent diaphragm examination.
 Conservator to be cleaned from inside after every
three years.
 Regular inspection of OIL & WINDING
TEMPERATURE METER readings.
 Cleanliness in the Substation yard with all nets, vines,
shrubs removed.
 The best way of protecting a transformer is to have
good preventive maintenance schedule.
 Oil Temperature Indicators.
 Winding Temperature indicators.
 Buchholz Relay.
 Magnetic Oil level Gauge.
 Explosion Vent.
 HT fuse & D.O. fuse.
 LT circuit breaker.
 HT Circuit breaker with Over load, Earth Fault relay
tripping.
 Oil Surge Relay for OLTC.
 PRV for OLTC.
 HORN GAPS & Lightening Arrestor.
 Breather.
 InsufficientOil level.
 Seepage of water in oil.
 Prolonged Over loading.
 Single Phase loading.
 Unbalanced loading.
 Faulty Termination (Improper sized lugs etc)
 Power Theft.
 Prolonged Short Circuit.
 Faulty operation of tap changer switch.
 Lack of installation checks.
 Faulty design

 Bad Quality of raw material.


 Transit damaged transformers.
 After failure , transformer is removed and replaced
with new/repaired one without removing the cause of
failure which results in immediate or short time failure.

You might also like