Daily Labour Report 3

1. The daily labour report from Ansal Town site shows a total of 16 workers were present, with tasks including steel cutting, column placing, and cover block fixing. 2. According to the report, the plan for the day was pouring of foundations. The running activity was reported as column placing on the raft area and isolated footings. 3. It was remarked that casting of isolated footings and the basement raft would start the next day at 11 am.

Uploaded by

Kapil Sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3K views2 pages

Daily Labour Report 3

1. The daily labour report from Ansal Town site shows a total of 16 workers were present, with tasks including steel cutting, column placing, and cover block fixing. 2. According to the report, the plan for the day was pouring of foundations. The running activity was reported as column placing on the raft area and isolated footings. 3. It was remarked that casting of isolated footings and the basement raft would start the next day at 11 am.

Uploaded by

Kapil Sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Daily Labour Report

Site : Ansal Town Date :


Sr. No Work Description Maison Labour Blacksmith Shuttering Others
Fitter Helper Carpenter Helper
1 steel cutting for retaining wall vertical 1 1
2 column placing on foundation 2 2
3 Basement raft binding 2 2
4 column plumb 1
5 column vertical & ring shifting 0 3
6 cover block fixing & cleaning 2
7
8

Total 1 2 5 8 0 0 0
Today's Plan as per schedule : Pouring of foundation
Today Running Activity : column placing on Raft area & Isolated footing
Remarks : Casting of Isolated footings & Basement raft will be start tomorrow from 11 am.
6/9/2019
Total
Manpower

2
4
4
1
3
2
0
0
0
0
0
0
0
0
0
0
0
0
16