Identifying Poor HX
Identifying Poor HX
exchanger performance
Identifying root causes of poor crude unit debutaniser reboiler performance and low-cost
solutions that help meet exchanger original design conditions. Of primary importance is
the impact factors such as fouling have on the service heat-transfer coefficient
H
eat exchangers are designed
with engineering tools that
allow the designer to evaluate
the influence of various parameters Unstabilised
on projected performance and select naphtha
the optimum combination. However,
computer model results are just
calculations and only reflect actual
performance if the model assumptions
correctly predict what actually happens
inside the exchanger. Consequently,
when an exchanger does not perform Gas oil 42 kg/cm2
product steam
per design, the model assumptions
are not correct. Heat exchanger
performance, just like that of any other
refinery process equipment, depends on Stabilised
naphtha
specific equipment design and not on
the ideals of the computer model.
Figure 1 Crude debutaniser reboiler system
Reboiler system
In 2000, National Petroleum Refiners of was operating satisfactorily. The new case, theories included inherently poor
South Africa (PTY) Ltd (Natref, a joint steam reboiler was designed to supply heat transfer when using U-tubes instead
venture of Sasol and Total South Africa) the balance of the debutaniser heat of straight tubes, insufficient shell-side
commissioned a major crude/vacuum requirements during normal operation fluid circulation resulting in excessive
unit expansion. As part of the revamp, a and the total column heat requirements, vapourisation and two-phase flow
new reboiler was installed on the crude so the gas oil reboiler could be taken irregularities in the reboiler return
debutaniser to provide increased duty to offline for maintenance. This larger piping. Another was that the exchanger
stabilise the increased production from reboiler was designed for 42 kg/cm2 simply was not big enough and a new
the preflash and atmospheric crude pressure steam (Figure 1) to replace one larger exchanger was needed. Many tests
columns. Total reboiler heat input using 16 kg/cm2 pressure steam. After were conducted to investigate these and
needed to increase to remove enough of commissioning, the exchanger had a various other hypotheses that could
the C4s to meet the light straight-run calculated service overall heat-transfer explain the poor performance.
(LSR) Rvp specification for gasoline pool coefficient (U) as low as 25% of design. Determination of root causes must
blending. However, the debutaniser Various field tests were done to evaluate begin with a review of the specific
reboiler heat input was not sufficient to potential root causes. The exchanger system and equipment design, and the
meet the light naphtha Rvp specifications was eventually taken out of service and application of fundamental engineering
after startup, particularly when processing inspected to ensure the actual design principles. As engineering tools become
light crude blends. The debutaniser’s conformed to the drawings and assess increasingly complex, sophisticated and
maximum throughput was limited to whether the shell or tube sides were easier to use, such as computational
90% of design when the reboilers were badly fouled. However, only a marginal fluid dynamics (CFD) models, engineers
clean. While in operation, fouling performance improvement was noted have a tendency to rely on these models
resulted in a 3.5% reduction in reboiler when the exchanger was put back into and search for complex causes and
duty per month (equivalent to a reduced service. Even when the reboiler was solutions. This should not be a surprise
maximum throughput of about 750 bpd clean, its U value was less than 25% of given the increasing focus on
every month). At times, this began to design clean performance. Although the engineering tools rather than on
limit the overall crude unit throughput. reboiler was never significantly fouled, understanding fundamental equipment
The revamped debutaniser column its performance was sensitive even to operating principles. Yet, understanding
was designed to operate with two small amounts of fouling compared to these principles remains the single most
reboilers. One used gas oil product. Its the other reboiler. important factor in the design of process
heat input was therefore set by product It is common to speculate on equipment and troubleshooting when
yield. This reboiler, which had not been potential causes when equipment does the equipment does not perform as
mechanically altered during the revamp, not meet expected performance. In this expected.
Steam
hl
Condensate
out
Inlet
Condensate
Figure 2 H-Shell exchanger
Solution
Many solutions were considered
including a new larger exchanger shell Figure 6 Original bundle
and bundle, and new reboiler return
piping, both of which were expensive
options. Furthermore, these options did Double Full-diameter
not address the root cause and may not segmental baffle
baffle
have worked. Instead, a new exchanger
bundle was designed and installed in
the same shell.
A new bundle was designed with the
intent to improve the flow distribution
to fully utilise the tube surface area
(Figures 7 and 8) and maximise the tube
outside coefficient ho. Vertical double Double
segmental baffles were installed to Full-diameter segmental
baffle baffle
improve the flow distribution. The baffle
Plan view
design was optimised to ensure shell- (top)
side fluid was forced through the entire
bundle. Thermosiphon hydraulics were
checked to ensure the higher pressure Figure 7 Bundle modification
drop would not reduce circulation and
cause problems with high percentage
vapourisation. The skid bars were
redesigned and impingement plates
eliminated. In addition, full-diameter
vertical baffles were installed between
the inlet nozzles to help with flow
distribution. After the new bundle was
installed, the service heat-transfer
coefficient improved from 250 kcal/h m2
°C or less to 950 kcal/h m2 °C (Figure 9).
The debutaniser was now able to process
light crudes while meeting LSR product
RVP specification.
30
Abe du Pont is the manager for process Installation GJ/hr C11068 duty 1400
Heat transfer coefficent U,