Bridge
Bridge
Bridge
Sika at Work
Project Description The structural engineers and the ready-mix supplier wanted at least
The project time: 2007.08.21. – 2009.05.30. two different possible solutions for this problem.
The Liberty Bridge is in Budapest, over the Danube River. This bridge The quality requirements of concrete bridge-deck:
was the 3rd which have made contact between Buda and Pest, at the C30/37-24/KK f50 vz5 (KK means: F2. During the project it was chan-
end of 19th century. ged to F3, because of the steel reinforcement was dense.)
On the bridge are railways and roadways and two sidewalks. In the
middle of bridge lay the tram rails, and outsides are the roadways.
Total length: 333,6 m Sika Solution
Width: 20,1 m The Concrete Division of Sika Hungary Ltd. recommended two diffe-
Distance between pylons and beach: 79,3 + 175 + 79,3 m rent solutions.
Rebuilds after the II World War: 1945; 1946; First:
low w/c ratio, max.: 0,42
According to the original plan – end of 19th century – it’s a steel latti- sand poor mix design,
ce-bridge. During the renovation project some elements were changed, Sika® ViscoCrete® 1035 HRWR and
some were strengthened. The concrete bridge-deck was changed. The 3 V% entrained air content with SikaAer®.
new bridge-deck during the lifetime will transmit the stresses to steel Second:
elements, because according to the new plan this deck and steel ele- low w/c ratio, max.: 0,42
ments working as a composite structure. sand poor mix design,
Sika® ViscoCrete® 1035 HRWR and
Shrinkage reduced concrete mix, with Sika® Control-40.
Requirements
The composite structure requires keeping low the level of shrinkage of Preliminary examinations
the concrete deck. The shrinkage of the concrete deck is the one of the To select the best solution the structural engineers have made some
loads which transmit to the steel elements. The special requirement of preliminary examination by Department of Construction Materials
the concrete material was the decreased level of shrinkage. and Engineering Geology of Budapest University of Technology and
Nevertheless an important point of view was the low costs level. Economics (BME).
The main contractor requested two ready-mix companies – Holcim
Hungary Co. and TBG Hungary Beton Ltd. (Heidelberg group). Both
companies presented two mix designs. After short lab tests the con-
crete mixes were mixed in plants and delivered after to the site.
On site the main contractor and lab of the Department of Construction
Materials and Engineering Geology have taken concrete cubes and
beams.
150 x 150 x 150 mm cubes for compressive strength and
freezing tests.
70 x 70 x 250 mm beams for flexural test and freezing tests and
shrinkage measurements.
200 x 200 x 120 mm for waterproofing tests.
Project Participants
The owner: Hungarian State
The original architect in 1894: János Feketeházy.
Gerber-construction steel lattice-bridge.
Designer of renovation: FÖMTERV Co.
Main contractors:
– Hídépítő Co.
– Hídtechnika Ltd.
– Közgép Co.
– Vegyépszer Co.
Executor of concrete works: Monotop Ltd.
Ready-mix producer: TBG Hungária Beton Ltd.
Admixture supplier: Sika Hungária Ltd
Sika Services AG Our most current General Sales Conditions shall apply.
Corporate Business Unit Contractors Please consult the Product Data Sheet prior to any use and processing.
Speckstrasse 22
CH-8330 Pfäffikon
Switzerland
Phone +41 58 436 23 64
Fax +41 58 436 23 77
www.sika.com