Ms Project Test Pile

This document provides a schedule for the CFA pile installation project from May 2019 through September 2019. It outlines 21 tasks including the mobilization of equipment and personnel, test pile installations, production pile installations at various levels, and pile integrity testing and reporting. The schedule shows the planned start and finish dates for each task over the months included to complete the project on time by September 4, 2019.

Uploaded by

Gad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
83 views1 page

Ms Project Test Pile

This document provides a schedule for the CFA pile installation project from May 2019 through September 2019. It outlines 21 tasks including the mobilization of equipment and personnel, test pile installations, production pile installations at various levels, and pile integrity testing and reporting. The schedule shows the planned start and finish dates for each task over the months included to complete the project on time by September 4, 2019.

Uploaded by

Gad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Overall Time Schedule CFA Piles Print Date: Jun 12 '19

ID Task Task Name Start Finish Baseline Start Baseline Finish May 2019 June 2019 July 2019 August 2019 September 2019Octobe
Mode 2328 3 8 13182328 2 7 12172227 2 7 12172227 1 6 1116212631 5 1015202530 5
0 CFA PILES - May 6 '19 Sep 4 '19 NA NA

1 Turbine Building May 6 '19 Sep 4 '19 NA NA

2 Contract Signage May 6 '19 May 6 '19 NA NA 5/6

3 Advance Payment May 6 '19 May 6 '19 NA NA 5/6

4 Mobilization to site (Office Containers) May 23 '19 May 23 '19 NA NA

5 Mobilization Test Equipment May 6 '19 May 24 '19 NA NA

6 Mobilization FRANKI Rig May 6 '19 May 28 '19 NA NA

7 Bore Test 1 and test 2 piles (6 piles ) for test rig (T/G Building) May 24 '19 May 28 '19 NA NA

8 Setup pile test rig & test pile 1 (11 day cure) (T/G Building) Jun 10 '19 Jun 14 '19 NA NA

9 Setup pile test rig & test pile 2 (11day cure) (T/G Building) Jun 19 '19 Jun 25 '19 NA NA

10 Results Test Pile 1 Jun 17 '19 Jun 19 '19 NA NA

11 Results Test Pile 2 Jun 26 '19 Jun 28 '19 NA NA

12 Piles Installatio at Level -5.5m (45 piles) (around turbine ext) Jul 1 '19 Jul 8 '19 NA NA

13 Execution Pile Integrity Tests (PET) +report (45 piles) Jul 19 '19 Jul 25 '19 NA NA

14 Piles Installation at Level -5.5m (55 piles) Jul 9 '19 Jul 17 '19 NA NA

15 Execution Pile Integrity Tests (PET) +report (55 piles) Jul 30 '19 Aug 6 '19 NA NA

16 Piles Installation at Level -3.0m (41 piles) Jul 18 '19 Jul 25 '19 NA NA

17 Execution Pile Integrity Tests (PET) +report (41 piles) Aug 7 '19 Aug 13 '19 NA NA

18 Piles Intallation at level -12m (hotwell) (10 piles) Jul 26 '19 Jul 30 '19 NA NA

19 Execution Pile Integrity Tests (PET) +report (10 piles) Aug 12 '19 Aug 15 '19 NA NA

20 Piles Installtion level -8.5m (turbine base) (80 piles) Jul 31 '19 Aug 13 '19 NA NA

21 Execution Pile Integrity Tests (PET) +report (80 piles) Aug 26 '19 Sep 4 '19 NA NA

Project: Project Summary Task Milestone


Created:
Summary Actual Progress Penalized Milestone or Deadline
Status Date: Jun 12 '19

Page 1 of 1 Approved by:yyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy