Term of Reference
Term of Reference
Term of Reference
INTRODUCTION
This TOR Template provides the guidelines for procuring any or all of the following ICT
resource requirements of the procuring entity for the implementation of its
Information Systems Strategic Plan (ISSP) as indicated in its Annual Procurment
Plan , namely:
Goods
Supply, delivery, installation, testing and acceptance of ICT and ICT-related goods
(e.g. equipment, devices, special solutions and the like), and
Infrastructure
Consulting Services
The following terms are presented as defined in the Revised Implementing Rules and
Regulations of the Republic Act 9184 (RA 9184), otherwise known as Government
Procurement Reform Act (GPRA):
Procurement
Refers to the acquisition of Goods, Consulting Services, and the contracting for
Infrastructure Projects by the Procuring Entity. In case of projects involving mixed
procurements, the nature of the procurement, i.e., goods, infrastructure projects, or
consulting services, shall be determined based on the primary purpose of the
contract. Procurement shall also include the lease of goods and real estate. With
respect to real property, its procurement shall be governed by the provisions of
Republic Act 8974 and other applicable laws, rules and regulations.
Procring Entity
Consulting Services
Refer to services for Infrastructure Projects and other types of projects or activities
of the GOP (NGA), requiring adequate external technical and professional expertise
that are beyond the capability and/or capacity of the GOP (NGA), to undertake such
as, but not limited to:
General principles on consulting services are provided for in Annex “B” of the
Revised IRR.
Goods
Refer to all items, supplies, materials and general support services, except consulting
services and infrastructure projects, which may be needed in the transaction of
public businesses or in the pursuit of any government undertaking, project or
activity, whether in the nature of equipment, furniture, stationery, materials for
construction, or personal property of any kind, including non-personal or
contractual services such as the repair and maintenance of equipment and furniture,
as well as trucking, hauling, janitorial, security, and related or analogous services, as
well as procurement of materials and supplies provided by the procuring entity for
such services. The term “related” or “analogous services” shall include, but not be
limited to, lease or purchase of office space, media advertisements, health
maintenance services, and other services essential to the operation of the procuring
entity.
Infrastructure Projects
Bidding Documents
Refer to the documents issued by the procuring entity as the bases for bids,
furnishing all information necessary for a prospective bidder to prepare a bid for the
infrastructure projects, goods and/or consulting services required by the procuring
entity
Pursuant to the Phillippine Bidding Document for Consulting Services, the Terms of
Reference normally contain the following sections to be provided by the Procuring
Entity:
(a) Background;
(b) Objectives;
This TOR Template also provide relevant information about the project involving
procurement of ICT and ICT-related resource requirements. These are:
TABLE OF CONTENTS
APPROVAL PAGE
A. BACKGROUND
B. PROJECT ESTIMATES
F. PAYMENT SCHEDULE/MILESTONES
G. OTHER CONSIDERATIONS
DEFINITION OF TERMS
DOCUMENT REFERENCES
STANDARD FORMS
APPENDICES
PREPARED BY:
DOCUMENT HISTORY
Primary
Version Description/Changes Issue Date
Author (s)
DISTRIBUTION LIST
APPROVAL PAGE
<Project Title>
Terms of Reference
Version <9.99>
A. BACKGROUND
In reference to the procuring entity’s approved Information Systems Strategic Plan (ISSP)
and the Annual Procurement Plan (APP), this portion shall describe the background and
circumstances that led to the project initiation. This enables anyone to get a quick
preview of why the project has been undertaken. Usual questions that must be
answered are –
Describe the project scope. The project scope is the definition of what the project is
supposed to accomplish and the budget of both time and money that has been created
to achieve these objectives. It may consists of two main components.
Usually, scope changes occur in the form of "scope creep". Scope creep is the piling up
of small changes that by themselves are manageable, but in aggregate are significant.
Hence, it is important to specifly the tasks to be performed or results to be delivered.
Project scope may include, but is not limited to some of the following considerations:
o a specific geographic location; a particular group as the target beneficiary;
o level of effort.
Tabulate the project development schedule. This shall describe how the project shall
be completed at a high level. The main function of the Project Development Schedule
is to establish the strategy and the order by which a project specifies, implements, tests,
and performs its activities.
The appropriate Project Development Schedule can streamline the project and help
ensure that each step moves closer toward attainment of project goals.
o base-leveling,
o prototyping,
o single-system, and
State briefly the strategy on how the project shall be undertaken, whether by phase or
one time. State also the project duration and life span.
B. PROJECT ESTIMATES
List and indicate the cost estimate/ceiling per project component (if necessary).
The ABC authorized for the <project name>. shall be sourced from the
<funding source name> pursuant to <governing law/issuance/policy>.
List and indicate the source of funds for the project component (if necessary).
List the ICT and ICT-related consulting services and support services to be provided:
List the physical set up and commissioning of any of the ICT and ICT-related
infrastructure
o Platform
o Features
o Functionalities
o Design Considerations
o Development/Management Methodologies
o Development/Staging Facilities
o Warranty
o Maintenance
Define also the non-functional requirements that act to constrain the solution. Use the
PIECES framework to identify these non-functional requirements:
List and describe the related database/s to be built up/ converted/migrated to support
the operationalization of the information system application system in terms of the
following:
o Platform
o Features
o Functionalities/Design Considerations
o Development/Management Methodologies
o Development/Staging Facilities
List and describe the other consulting and support services to be provided. Describe
the scope of the services (e.g. training, system integration, project management,
change management, etc.) required to support the operation of of the information
systems/application systems to be developed/enhanced.
Training/Technology Transfer
List and describe in detail the trainings to be conducted in terms of - Course Title and
Description, Learning Objectives, Class Size and Composition, Course Duration and
Venue, Training Sequence. The type of training shall depend on the function of the
participant:
Warranty
Describe the hardware and software warranty requirement. Warranty must follow the
industry standard on warranty for parts and labor.
Describe the maintenance and support plan requirement, to9 include among others,
the following information:
Describe the risk management plan requirement. Risk is defined as the probability of
an unforeseen incident and its consequent penalty. Exposure to risk could lead to
disaster or loss in the form of diminished quality of the product, increased costs, delays
or failures and etc. To prevent the occurrence of loss, the project contractor must
provide a risk management plan detailing the strategies and appropriate measures to
be undertaken.
Describe the Disaster Recovery Plan requirement. As disaster strikes when least
expected, precautions must be undertaken so that the effects of a disaster shall be
minimized or almost negligible or occur unnoticed. The Disaster Recovery Plan must
be detailed enough for all possible disasters, such as, but not limited to power outage,
computer failure/malfunctiomn, natural calamities or human error. It must contain
the comprehensive procedures necessary to resume business to its normal operation in
the least possible time.
Describe the Change Management Plan requirement. The change management plan
must deal with specific actions required to reduce and/or eliminate resistance from
the users in sharing of their resources and participation in the
development/enhancement of the information systems/ application systems, among
others.
Documentation
List the hardware, software and network resources to be provided and describe its
relevant characteristics and/or performance requirements. Describe the hardware,
software, and network products/solutions to be required in terms of.
o Functional requirement
o Features
o Number of units
o Expandability
Hardware
Define clearly the Indicative and functional specifications of all the server (if any)
requirement
Processor board
Main memory
Operating Systems
Expansion slots
Physical dimensions
(Standalone frame)
Net weight
Power requirements
Power supply
Warranty
Define clearly the Indicative and functional specifications of all the workstation (if
any) requirement
Processor
Form factor
Memory, maximum
Memory slots
Internal drive
Storage controller
Graphics
Optical drive
Ports
Slots
Network interface
Audio
Power supply
Weight
Dimensions (W x D x H)
Warranty
Define clearly the Indicative and functional specifications of all the impact printers
(if any) requirement
Functional Requirement Feature No. of Units/
Expanadability
Branded/Brand New
Impact Printer
Print Speed (cps @10 cpi)
Input Buffer
Sound Level
Standard Interface
Printer Language
Define clearly the Indicative and functional specifications of all the non-impact
printers (if any) requirement
Functional Requirement Feature No. of Units/
Expanadability
Branded/Brand New
Non-impact printers
Resolution
Input Buffer
Printer Fonts
Define clearly the Indicative and functional specifications of all the uninteruptive
power supply (if any) requirement
Functional Requirement Feature No. of Units/
Expanadability
Branded/Brand New
Voltage Capacity
Input Volatge
Output Volatge
Battery Redundancy
Maintainability
Define clearly the Indicative and functional specifications of all the firewall
appliance (if any) requirement
Nodes Supported
Throughput
Gateway Anti0virus
Throughput
Connections
DoS Protection
Software
Define clearly the Indicative and functional specifications of all the software (if any)
requirement
Network Operating
System (NOS)
Office Automation
Software
Browser/Navigation
Utility
System Development Tools
Database Management
System
Others
Network
Define clearly the Indicative and functional specifications of all the networking (if
any) requirement. It is of paramount importance that the hardware and software to
be proposed be able to provide a coherent, compatible and interoperable processing
environment and enable the effective networking of the system's computing facilities.
Netwrok Security
Define clearly the Indicative and functional specifications of all the network security
(if any) requirement. The security required must be capable of real time detection
and prevention of attackers from exploiting operating system and application
vulnerabilities. In addition, the security devices and software must also filter and
monitor traffic and with antispam capabilities.
Define clearly the Indicative and functional specifications of all the Civil Works (if
any) requirement
Define clearly the Indicative and functional specifications of all the Mechanical
Works (if any) requirement
Define clearly the Indicative and functional specifications of all the Air Conditioning
System (if any) requirement
Define clearly the Indicative and functional specifications of all the LAN cabling (if
any) requirement
Define clearly the Indicative and functional specifications of all the A/C Mechanical
Works (if any) requirement
Define clearly the indicative and functional specifications of all the Close Circuit
Television (CCTV) and Security Access System Works (if any) requirement
Define clearly the Indicative and functional specifications of all the Raised Flooring
Works (if any) requirement
Define clearly the Indicative and functional specifications of all the Emergency
Generator with Automatic Transfer Switch (ATS) (if any) requirement
Structured Cabling
Define clearly the Indicative and functional specifications of all the Structured
Cabling (if any) requirement:
Internet Connectivity
Define clearly the Indicative and functional specifications of all the Iinternet
Conectivity (if any) requirement:
This shall describe how to document the process and timing of project reviews and
approvals, This shall include, but not limited to, the following:
This shall also describe the monitoring and control process, frequency of status
reporting and other tracking activities.
Moreover, this shall specify the coordination and communication with subcontractors
and other groups who may be involved, their relationships to one another, and the
authority and responsibility of each organization for carrying out required activities.
This shall indicate the meetings and reporting schedules set for the Project.
In addition, this shall describe the organizational structure to be used on the project.
It shall describe the roles, responsibility and allocated effort for each team member.
This shall describe the acceptance criteria and procedure for every deliverable from
requirements definition to maintenance. This shall be the basis for determining the
amount or percentage of total project cost for the progressive payments to be paid.
o Project Charter
o Project Organization (Project Management Office, if needed)
o Project Implementation Plan (Activities, Schedules, Milestones, Responsibility)
List and describe the scope of usage of the resources that are made available which can
be provided by the procuring entity to the project contractors, to include but not limited
to the following:
o Data,
o Local Services,
o Personnel, and
o Facilities
o Site preparation
o Development area/location
o Development environment (server, workstations, etc.)
F. PAYMENT SCHEDULE/MILESTONES
The project shall be paid on the schedule indicated below (if necessary) which
shall not exceed the ceiling specified:
o An advance payment
o The final payment shall be made only after the final report and a final
statement, identified as such, shall have been submitted and approved as
satisfactory by the Procuring Entity.
G. OTHER CONSIDERATIONS
(Note: Contents of this section is derived from the Revised Implementing Rules
and Regulations of the Governmnet Procurement Reform Act or RA 9184.)
Legal Documents
Technical Documents
Financial Documents
Legal Documents
Technical Documents
Financial Document
The BAC shall specify in the Request for Expression of Interest the
set of criteria and rating system for short listing of consultants to
be used for the particular contract to be bid, which shall consider
the following, among others:
The BAC shall open the first bid envelopes of prospective bidders in public to
determine each bidder’s compliance with the documents required to be
submitted for eligibility and for the technical requirements, as prescribed in
this IRR. For this purpose, the BAC shall check the submitted documents of
each bidder against a checklist of required documents to ascertain if they are
all present, using a non-discretionary “pass/fail” criterion, as stated in the
Instructions to Bidders. If a bidder submits the required document, it shall be
rated “passed” for that particular requirement. In this regard, bids that fail to
include any requirement or are incomplete or patently insufficient shall be
considered as “failed”. Otherwise, the BAC shall rate the said first bid
envelope as “passed”.(a)
For the procurement of goods where, due to the nature of the requirements
of the project, the required technical specifications/requirements of the
contract cannot be precisely defined in advance of bidding, or where the
problem of technically unequal bids is likely to occur, a two (2)-stage bidding
procedure may be employed. In these cases, the procuring entity concerned
shall prepare the Bidding Documents, including the technical specification in
the form of performance criteria only. Under this procedure, prospective
bidders shall be requested at the first stage to submit their respective
eligibility requirements if needed, and initial technical proposals only (no
price tenders). The concerned BAC shall then evaluate the technical merits of
the proposals received from eligible bidders vis-à-vis the required
performance standards. A meeting/discussion shall then be held by the BAC
with those eligible bidders whose technical tenders meet the minimum
required standards stipulated in the Bidding Documents for purposes of
drawing up the final revised technical specifications/requirements of the
contract. Once the final revised technical specifications are completed and
duly approved by the concerned BAC, copies of the same shall be issued to
all the bidders identified in the first stage who shall then be required to
submit their revised technical tenders, including their price proposals in two
(2) separate sealed envelopes in accordance with this IRR, at a specified
deadline, after which time no more bids shall be received. The concerned
BAC shall then proceed in accordance with the procedure prescribed in this
IRR.
The BAC shall conduct a detailed evaluation of bids using either of the
following evaluation procedures as specified in the Bidding
Documents: