API IP 1594 - Nov 2002
API IP 1594 - Nov 2002
API IP 1594 - Nov 2002
IP 1594
November 2002
INITIAL PRESSURE STRENGTH TESTING OF
AIRPORT FUEL HYDRANT SYSTEMS WITH WATER
IP 1594
November 2002
Published by
The Institute of Petroleum, London
A charitable company limited by guarantee
The Institute of Petroleum gratefully acknowledges the financial contributions towards the scientific and
technical programme from the following companies:
No part of this book may be reproduced by any means, or transmitted or translated into
a machine language without the written permission of the publisher.
Further copies can be obtained from Portland Customer Services, Commerce Way,
Whitehall Industrial Estate, Colchester CO2 8HP, UK. Tel: +44 (0) 1206 796 351
email: [email protected]
CONTENTS
Page
Foreword . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . vii
Acknowledgements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . viii
1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.2 Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.3 Referenced publications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.4 Other sources of information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.5 Terms and definitions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.6 Abbreviations used . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.7 Units used . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2 Design considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
2.1 Understanding the design of the system . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
2.2 Water draining . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
2.3 Design for pigging . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
2.4 Low points . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
v
Contents Cont.... Page
6 Start-up procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
7 Records . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Annex A - Tables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
vi
FOREWORD
This Institute of Petroleum Aviation Committee publication provides guidance for the initial pressure strength
testing, using water as the test liquid, of new fuel hydrant systems. It may also be applied to testing extensions to
existing systems where positive isolation can be achieved between the extension and the existing part of the system.
It is not intended to document precise testing procedures, as these will follow the established practices of the
companies involved in the test as well as statutory procedures applicable locally. The main aim of the publication
is to recommend methods of dewatering and drying after testing the system with water.
The Institute of Petroleum is not undertaking to meet the duties of employers to warn and equip their employees,
and others exposed, concerning health and safety risks and precautions, nor undertaking their obligations under local
and regional laws and regulations.
Although it is hoped and anticipated that this publication will assist those responsible for designing, constructing,
commissioning operating and maintaining aviation fuel handling systems, the IP cannot accept any responsibility,
of whatever kind, for damage or loss, or alleged damage or loss, arising or otherwise occurring as a result of the
application of the guidance contained herein.
Suggested revisions are invited and should be submitted to the Technical Department, The Institute of Petroleum,
61 New Cavendish Street, London, W1G 7AR.
vii
ACKNOWLEDGEMENTS
This publication was prepared by Mr R. A. Simpson under the direction of a Working Group of IP Aviation
Committee members:
The Working Group recognises the input provided by Richard Christopher1 on the drying of tested systems.
A draft version of this publication was reviewed by technical representatives of the following companies:
AgipPetroli
Air BP Limited
Air TOTAL
Aviation Fuel Services & Management GmbH
ChevronTexaco
Conoco Limited
ExxonMobil Aviation International Ltd.
Kuwait Petroleum International Aviation Company Ltd.
Shell Aviation Ltd.
1
Hydrostatic Testing Consultants Ltd., Unit 427, Ash Road, Wrexham Industrial Estate, Wrexham, Clyd, LL13 9UG, U.K.
Tel: +44 (0)1978 661 182, Fax: +44 (0) 1978 661 184, email: [email protected]
viii
1
GENERAL
1.1.1 Traditionally, most airport fuel hydrant 1.2.1 The guidance in this publication relates only to
systems have been pressure strength tested using the underground part of the hydrant system from the
kerosene. Now that environmental considerations are final depot flange before the pipework goes
becoming more stringent, some countries and/or underground. This often is the cathodic protection
authorities do not allow the use of kerosene as the test insulating flange. For details of design considerations
liquid when carrying out the initial pressure strength for the above ground section of the system, see IP
testing of the system. Further, research commissioned Model Code of Safe Practice Part 7 Airports safety
by the IP2 has shown that there can be a wide variation code 3.
in results when testing with kerosene. Therefore, it is
likely that the use of water for testing will become more 1.2.2 Off-airport feeders, even though they may be
widespread. run underground for the whole or part of the way from
the supply point to airport storage, are considered to be
1.1.2 This publication is intended to give guidance the responsibility of the relative supply and distribution
to designers, engineers and operators of airport fuel entity. They are not, therefore, included in the scope of
hydrant systems in the use of water for testing and, in this publication.
particular, the subsequent dewatering procedures
required in bringing the system into commission. Whilst 1.2.3 The guidance included in this publication
such operations/procedures are commonplace in other applies only to the initial pressure strength testing of a
sectors of the pipeline industry, they have not been new system or of extensions to existing systems. As
generally adopted in the testing of airport fuel hydrant water is to be the test liquid, when testing extensions to
systems. an existing system it is essential that there is positive
isolation between the extension and the existing system,
1.1.3 Thorough drying of the hydrant system using physical separation or a line blind. (In-line valves,
following testing with water is essential to ensure that including double block and bleed are not considered
the system, when in service, will not affect the quality adequate for this purpose.) Routine tightness control
of the fuel within it.
2
Report on a study into pressure effects on liquid kerosene.
3
A 4th edition of the IP Airports safety code is in preparation. It is intended to be published as a joint API/IP document with
a new title.
1
INITIAL PRESSURE STRENGTH TESTING OF AIRPORT FUEL HYDRANT SYSTEMS WITH WATER
system testing will continue to be carried out with fuel BS 8010 Part 2 Pipelines on land: design, construction
as the test liquid as the test pressure used is the same as, and installation, Section 2.8 Steel for oil and gas
or close to, (up to 110 %) the normal maximum
permissible operating pressure. Such testing is not ISO 13623 Petroleum and natural gas industries –
included within the scope of this publication. Pipeline transportation systems
4
Available from API Publications, Global Engineering Documents, 15 Inverness Way East, M/S C303B, Englewood,
CO80112-5776, USA. Tel: 303 397 7956, Fax: 303 397 2740, www.api.org
5
Available from Portland Customer Services, Commerce Way, Whitehall Industrial Estate, Colchester, CO2 8HP. Tel:
+44(0)1206 796 351, email: [email protected]; or API Publications, Global Engineering Documents, 15
Inverness Way East, M/S C303B, Englewood, CO80112-5776, USA. Tel: 303 397 7956, www.api.org
6
Available from the IP library.
7
Available from Portland Customer Services, Commerce Way, Whitehall Industrial Estate, Colchester, CO2 8HP. Tel:
+44(0)1206 796 351, email: [email protected]
8
Available from Publications Sales, Institution of Gas Engineers and Managers, 12 York Gate, London NW1 4QG, Tel: +44
(0)20 7636 6603, Fax: +44 (0)20 7636 6602, www.igaseng.com
2
GENERAL
ft/sec feet per second Within this publication SI Units are used with US
g gram Customary Units following in parentheses.
in. inch Internationally agreed conversions have been applied to
kPa kiloPascal these values with rounding where applicable, e.g. 1 bar
l litre is taken as 100 kPa (rather than 101,3 kPa) and equated
m/sec metres per second to 15 psi.
mg/l milligrams per litre
EC degree Celsius
EF degree Fahrenheit
psi pounds per square inch
USG U.S. Gallon
3
INITIAL PRESSURE STRENGTH TESTING OF AIRPORT FUEL HYDRANT SYSTEMS WITH WATER
4
2
DESIGN CONSIDERATIONS
2.1 UNDERSTANDING THE DESIGN 2.2.3 To avoid unintended low points, there must be
OF THE SYSTEM adequate support for the lines: backfill may well cause
the line to sag if it is not adequately supported.
Having a thorough understanding of the geometry of
the hydrant system being tested is critical to the
subsequent accurate assessment of the cleanliness and 2.3 DESIGN FOR PIGGING
dryness of the system. Constructional drawings of the
system should be available to the persons involved in 2.3.1 Pigs can be used to remove the bulk of the
setting up and managing the testing of the system. initial pressure strength test water and to assist in drying
the pipe. The system to be tested should be designed to
aid the use of such pigs. This is discussed in 6.2 of
2.2 WATER DRAINING API/IP 1585 Guidance in the cleaning of airport
hydrant systems.
2.2.1 The system should be designed to allow
removal by draining of the bulk of the water used for 2.3.2 Bends and any changes in pipe diameter
the initial pressure strength test. The use of adequate should be reviewed to ensure they will allow free
slopes to assist the moving of water to low points is movement of the pigs.
discussed in 6.1.4 of API/IP 1585 Guidance in the
cleaning of airport hydrant systems. Further 2.3.3 Low point drain/sampling lines should be
information on the migration of particulate matter and removable if they will impede the passage of a pig, (see
water to low points may be found in An investigation 2.3.1).
into the effectiveness of hydrant pipeline gradient in
assisting the migration of particulate and free water 2.3.4 Bars should be fitted across the side branches
contaminants at typical product flow rates. of 'T' connections and low point sumps if there is the
possibility of a pig becoming trapped.
2.2.2 Spurs should be designed so that water will
drain back to the main line. If this is not possible, e.g. 2.3.5 Suitable pig launching and receiving traps will
due to other underground services, other means of need to be provided, even if only on a temporary basis.
water removal should be provided. Initial drying of the
spur should be carried out by venting dry air through it.
The risers can be checked as in 5.1.8.
5
INITIAL PRESSURE STRENGTH TESTING OF AIRPORT FUEL HYDRANT SYSTEMS WITH WATER
6
3
7
INITIAL PRESSURE STRENGTH TESTING OF AIRPORT FUEL HYDRANT SYSTEMS WITH WATER
material if the water is not sufficiently clean. Water of transferred under that high pressure to the next section
potable quality is required to ensure that this does not to be tested. The system should first be depressurised to
happen. Whilst it is thought that the level of chlorine prevent damage to a line valve being opened under the
found in potable water will not present a problem in test pressure.
testing of a system with water, potable water containing
higher than normal levels of chlorine could have a 3.2.8 The guidance in this publication is based on
damaging effect on pipeline weld joints, as these are not the assumption that sufficient suitable water is
coated. available. However, at locations where suitable water is
not available the advice of an appropriately qualified
3.2.4 A research study into the disposal of and experienced body or entity should be sought.
hydrostatic test water within the USA is detailed in API
Publication 1157, Hydrostatic test water treatment and 3.2.9 In some locations, disposal of test water may
disposal options for liquid pipeline systems. It should be problematical and must be considered when planning
be noted that this document 'is a research study to to test with water. This should not normally present a
provide the (USA) liquid pipeline industry with problem, as the pipework under consideration in this
credible data and information relative to hydrostatic test publication will not have contained hydrocarbons but
water…' and it is not a regulatory document. The study contact with potential contaminants should be
included both new and existing pipelines. considered prior to disposal. In cold climates ethylene
glycol may have to be added to the water to prevent
3.2.5 Frequently, the only locally available source of freezing. In some countries legislation requires test
water in sufficient quantities to test a system is the water to be colour-dyed. Both of these instances will
airport’s fire main water. Normally the quality of this affect the manner of disposal.
water is not acceptable for testing the fuel hydrant
system due to the high level of contaminants that may 3.2.10 The use of a biocide in less than clean water
cause microbiological problems. requires very careful consideration and should not be
undertaken without seeking expert advice. The
3.2.6 Filtration of the water before use as the test effectiveness of the biocide needs critical study and its
medium may be an option worthy of consideration, complete removal with the bulk water and in
although this is unlikely fully to remove subsequent drying is vital. For instance, consideration
microbiological contaminants. Ideally, the solids needs to be given to any impact by a biocide on internal
contamination level should be less than 1 mg/l lining or seal materials. Again, the use of biocide
(3,8 mg/USG). treated water will require special disposal procedures.
3.2.7 If there is good quality water available, but not 3.2.11 All gaskets and other like materials used
in sufficient quantity to test the whole of a system, should be compatible with both water and jet fuel. It has
consideration should be given to testing the system been known for some types of gasket material to absorb
section by section thus conserving the water. However, water in the testing so presenting a problem in the
testing against a closed valve should not be considered drying process.
and water used in testing one section should not be
8
4
9
INITIAL PRESSURE STRENGTH TESTING OF AIRPORT FUEL HYDRANT SYSTEMS WITH WATER
clean as in 4.2.2, a soft foam pig or pigs should be run This will offer the facility to minimise the quantity of
through the line, propelled by dry and oil-free air to water/fuel egress should a failure occur. Drain and vent
remove dust and dirt. Inspection of the pig(s) after valves may remain in a semi-closed state, under the
passing through the line will give an indication of the same proviso, but should have blind flanges fitted to the
internal condition of the line. outlets.
4.3.2 In order to minimise the effects of temperature 4.3.6 The section to be tested should be filled slowly
change during the test, the line trench should be with the test water (as part of the cleaning process).
backfilled with at least the material used surrounding During the filling, venting of air should be carried out
the pipe but not necessarily with the final concrete. progressively as the line fills.
4.3.3 Ideally, valves, instruments and instrument 4.3.7 The pressure test should then be carried out in
signal lines should not be installed at this stage. Low accordance with the agreed procedures.
point sampling/flushing lines should be removed if their
presence would interfere with the passage of a pig. 4.3.8 After satisfactory completion of the test, the
test pressure should be reduced to zero gauge through
4.3.4 Testing against a closed valve should not be a pressure letdown valve at a controlled rate.
allowed unless the valve is rated to withstand the test
pressure. A line blind should be used if the valve is not 4.3.9 The test water should be removed from the
so rated. Drain and vent valves may remain in place system within 14 days as longer contact with water may
provided that they are able to withstand the test pressure affect the pipe lining. The system should be completely
to be used. dewatered and then dried. Where a permit to dispose of
the test water is required, local regulations should be
4.3.5 Where multiple sections are to be tested, it observed. API Publication 1157 Hydrostatic test water
may be advisable to permit the in-line valves to remain treatment and disposal options for liquid pipeline
in situ and in a semi-open state, providing the pressure systems may provide useful information.
rating of the seals is above the intended test pressure.
10
5
11
INITIAL PRESSURE STRENGTH TESTING OF AIRPORT FUEL HYDRANT SYSTEMS WITH WATER
5.1.7 The line can be considered to be free of bulk commence. Open a drain or vent closest to the air-
water when the pig is seen to be clean after transiting drying unit and measure the dew point. Continue
the system and there is negligible dirt in the receiving purging until a measurement of 200 ppm is obtained.
pig trap if used. An open cage used to receive the pigs This is equivalent to the dew point at -35 EC (-31 EF) at
will not, of course, be of such use in determining the atmospheric pressure (0 psig).
cleanliness.
5.2.8 Move to the next vent or drain point and
5.1.8 Vertical risers may be cleaned and dried by measure the dew point. Purge until a measurement of
using swabs and pull-throughs after removing the base 200 ppm is obtained.
flange blind. Visual inspection should be carried out to
determine the cleanliness and dryness of the riser. 5.2.9 Continue measuring in the flow direction until
a measurement of 200 ppm is obtained at the end of the
system.
5.2 DRYING USING DRIED AIR
5.2.10 Close down the air compressor and carefully
5.2.1 For the drying, an adequate supply of pigs and release the pressure in the system to atmospheric.
appropriate air compressors capable of supplying dry
and oil-free air will be required. A record of pigs 5.2.11 When ready to commission the system, fit the
entered into and removed from the system should pit valves, low point tubes etc. and then LP air test for
always be maintained to ensure that none are left in the a final leak check of all newly made joints. It is
system. Equipment for measuring the dew point of the essential that dry, oil-free air be used. On completion,
air will be needed. the system should be filled with product and the soak
test and other commissioning procedures carried out.
5.2.2 At this stage it may be preferable to re-install
all line valves removed before the hydrostatic test. All
valves should be identified (numbered etc.) to facilitate 5.3 DRYING BY VACUUM METHOD
checking against records. Pit valves should not be
installed at this point. 5.3.1 The principle of this method is to reduce the
pressure in the line to a level where water will boil at
5.2.3 If there is to be a delay between testing and the temperature of the pipeline surroundings. The
filling of the system with fuel, it may be preferable not remaining water vapour may then be removed and the
to install the valves, but to carry out the drying process system pressure reduced to a level where the pipeline is
and then inhibit the system with nitrogen. (See 5.4 at or below the saturated vapour pressure.
warning.) Each case needs to be considered and a
decision made as to when to fit the valves. 5.3.2 Drying by the vacuum method may take longer
than drying with air but, when fuel costs are taken into
5.2.4 Suitable driers (e.g. silica gel) should be account, it may prove to be cost effective.
connected between the air compressor and the line and
again the pressure should be limited to 50 kPa (7 psi). 5.3.3 A typical sequence for vacuum drying is
outlined in 5.3.3.1 – 5.3.3.10.
5.2.5 Check that all drain and vent valves are closed.
If valves and fittings are installed that were not in place 5.3.3.1 After the removal of water by draining and
during the hydraulic test, the system should be pigging, the vacuum pump and associated equipment
pressurised, with dry, oil-free air, to 50 kPa (7 psi) and should be set up. The pump will be connected to the
a Low-Pressure (LP) test carried out. The reason for pipework through a manifold. This is normally fitted
this test is to ensure there is no major leak at any of the with an in-line valve to isolate the pump when required
valves and fittings installed after the hydraulic test. and at least three off tappings and fittings for
instrumentation. It is preferable to house the
5.2.6 Close the air compressor drying unit outlet instruments in a suitable shelter and it should include a
valve and maintain the 50 kPa (7 psi) air test pressure digital thermometer, a digital pressure
for at least one hour. reading instrument and a dew point meter. A vacuum
gauge should be installed at the opposite end of the
5.2.7 Purging the system with air should now system to ensure equal vacuum is pulled throughout.
12
DEWATERING AND DRYING
5.3.3.2 The pump should then be started and 5.3.3.8 The pump should now be isolated from the
evacuation of air commence. At a pressure of system and a soak of a minimum of 12 hours should
approximately 50 kPa (7 psi) the pump should be take place. The pressure should remain fairly constant
stopped and isolated. This pressure should be held for if the system is dry. If any freezing did take place this
at least two hours whilst a leak check is carried out. A soak period will allow for de-icing.
rise in pressure may indicate a leak. This pressure is
suggested as it is well above the SVP where water 5.3.3.9 If during the soak period, significant or
evaporation would lead to a misleading pressure constant pressure rises are noted, it is likely that
increase. evaporation is still taking place. Further drying will
have to be carried out.
5.3.3.3 After a successful leak check the SVP is
determined by taking a temperature reading and 5.3.3.10 Once the drying has been completed dry air or
consulting the SVP table, see Annex A, Table 1. nitrogen should be introduced until a positive pressure
of 50 kPa (7 psi) is achieved. Dew point readings
5.3.3.4 Pre-drying can now take place. Once SVP has should be taken at both ends and, where possible, at
been reached, evaporation of free water will commence. intermediate points. A further period of 12 hours at this
Vapour may be seen exiting the vacuum pump. During pressure is recommended after which dew point
this stage of the drying the speed of the pump should be readings are again taken. If the required dew point is
carefully controlled via the pump inlet valves to attained, the system pressure should now be raised to at
maintain the pressure at a constant level. This will assist least 100 kPa (15 psi) using dry air or nitrogen to
in avoiding freezing of the water in the line, which will prevent ingress of moisture. A leak check should then
lead to erroneous dew point readings. be carried out. If this is satisfactory, the drying
operations will be completed.
5.3.3.5 Throughout the operation, readings of
pressure, temperature and dew point should be taken
and recorded at regular intervals. The amount of free 5.4 NITROGEN INHIBITING
water, the capacity of the vacuum pump and ambient
temperature will determine the duration of this stage. WARNING: If nitrogen is used there is a possibility
of the gas accumulating in valve chambers. Before
5.3.3.6 The evaporation can be speeded up by entry the atmosphere within the chamber must be
introducing a dry air 'leak' into the system at the end tested to ensure it is safe.
opposite the vacuum pump. The dry air introduced into
the system at !40 EC (!40 EF) will expand and in so 5.4.1 Whilst nitrogen is an inert gas, it cannot
doing will absorb moisture before exiting the vacuum support life and all due precautions need to be taken
pump. However, care must be taken to regulate the air when filling, monitoring and evacuating the gas from
supply to the speed of the pump in order to maintain the system before filling with product. The pressure
SVP. should not exceed 70 kPa (10 psi) and prominently
displayed notices to warn that the system is under
5.3.3.7 A lack of vapour exiting the vacuum pump and nitrogen should be displayed. System pressure should
a noticeable decrease in pressure will signal the end of be monitored weekly.
the evaporation stage. Main drying can now take place.
The water being converted to a gas at SVP enables the 5.4.2 All nitrogen should be purged from the
maintaining of a set pressure within the system as, system, under controlled conditions and using clean dry
whilst the vacuum pump is attempting to evacuate the air, before commencing to fill the system with fuel.
system, the gas is taking the place of the evacuated air.
When no more water is left to convert to vapour, the
vacuum pump will continue to evacuate the system
causing a noticeable pressure drop.
13
INITIAL PRESSURE STRENGTH TESTING OF AIRPORT FUEL HYDRANT SYSTEMS WITH WATER
14
6
START-UP PROCEDURES
6.1 The pressure in the system should be checked. If it installed and a LP air test should be carried out. On
has been held under positive pressure in dry air or satisfactory completion of this test the pressure should
nitrogen, as in 5.3.3.10, a loss of pressure may indicate be reduced to atmospheric and the system readied for
a leak. Action to resolve this situation should be taken filling.
before proceeding further with the filling process.
6.4 Filling should be carried out in a controlled
6.2 If the pressure is satisfactory, it should, where manner, mainly by gravity where possible, and air
necessary, be reduced to atmospheric before venting carried out at all possible points.
commencing to fill the system with fuel. If nitrogen has
been used, it must be purged with clean dry air and the 6.5 Reference to Section 10 of API/IP 1585 Guidance
nitrogen disposed of safely. Note the warning in 5.4. in the cleaning of airport hydrant systems may be found
to be useful in carrying out the commissioning process.
6.3 All valves and low points, as required, may now be
15
INITIAL PRESSURE STRENGTH TESTING OF AIRPORT FUEL HYDRANT SYSTEMS WITH WATER
16
7
RECORDS
Maintaining accurate records is an intrinsic part of the — Acceptance criteria for test results.
procedure. The following list is not exhaustive, as — Pressure testing certificates as required.
variations depending on the method used, location etc. — Record of pigs entered and recovered.
will be necessary. As a minimum it is recommended — Weight of pigs before and after running through
that the following records should be included: the system.
— Condition of pigs examined after running.
— Information necessary to define/describe the — Dew point readings at the various points and times
system to be tested and the process to be used. at which they were taken.
— Key personnel involved (contractors, site — Pressure readings taken during the vacuum drying
supervisors etc.) soak test as in 5.3.3.8 and 5.3.3.9.
— Work Permits issued. — If nitrogen is used, amount put into the system,
— Calibration Certificates for testing equipment source of the nitrogen (if necessary).
where applicable. — Safe disposal of nitrogen where applicable.
— Location and identity of low point sampling lines — Certificate of testing the atmosphere within valve
removed and replaced. chambers before entry.
— Amount of water entered to fill the system.
— Amount of water added to raise the system to test Where disposal of the test water is subject to regulatory
pressure. requirements, records such as Certificate of Water
— Amount of water removed to reduce the system Quality and Test Results should be maintained in
pressure to atmospheric. agreement with the responsible authority.
— Records of test pressures observed.
17
INITIAL PRESSURE STRENGTH TESTING OF AIRPORT FUEL HYDRANT SYSTEMS WITH WATER
18
ANNEX A
TABLES
Table 1 – Water vapour table (for saturated vapour pressure and saturated vapour density)
19
INITIAL PRESSURE STRENGTH TESTING OF AIRPORT FUEL HYDRANT SYSTEMS WITH WATER
(This table shows the amount of water per 100 m of pipe based on a film thickness of 0,1 mm and the internal
area of standard weight pipe.)
The above pipe diameters may vary slightly according to the pipe standard used. The inch dimensions are the
Nominal Bore (NB) sizes widely used in the industry and are not the actual outside diameter for pipe sizes below
14 inches. Therefore the quantity of water per 100 feet of pipe quoted in the table is approximate.
20