Br. No.-312 A
Br. No.-312 A
Br. No.-312 A
(CONSTRUCTION ORGANIZATTION)
CLIENT:
Dy. Chief Engineer/Con/MLG/III
N.F. RAILWAY,
Maligaon, Guwahati CONSULTANT
1 Design Basis 1 to 6
Page 1 of 97
Design Basis Report
SN LOADS & FORCES BRIDGE RULES SUB-STR & FOUNDATION CODE CODAL PROVISION
Density of material(Ref-IS-875) Part-I Rcc-
1 Dead Load(DL) 2.2 5.2 2.5 T/m2,steel -7.85 T/m2,Ballast-2.6
T/m2,soil-1.8 T/m2
Page 2 of 97
CDA=0.15+8/(6+L) equation-(1) subjected
to maximum of 1.0. L is Loaded
length of span (m) CDA to multiplied
by factor for calculation of
pressure/reaction at different level of
gravity type substructure(cl.5.4).
(i) Top surface of bed block=1 (ii)
Bottom surface of bed block=0.5 (iii) Top
5 Dynamic Augument (I) 2.4 5.4
3m of substructure=0.50 decreasing
uniformly to zero (iv) Beyond a
depth 3 m below bed block=-no impact
need to be allowed. For ballast wall-upto
depth of 1.5 m=0.5. For design of non
gravity type of substructure full dynamic
augument effect as per equation
(1) should be considered upto scoure level
Page 3 of 97
Where any portion of structure is not free
to expand or contract under variation of
6 Temperature effect 2.6 5.5
temperature,allowence shall be made for
the stresses resulting from this condition
Page 4 of 97
Shall be calculated for abutment/wing /
Return wall as applicable LL surcharge
10 Earth pressure due to surcharge 5.8.2 to 5.8.4
=13.7 t/m for 25 T loading on width of
uniform distribution at FL of 3m
Page 5 of 97
in clause 5.14 and 5.15 of bridge substructure and foundation code
Note: In case design by Limit State ,Limit states of clause 10.2 & 10.3 of IRS concrete bridge code shall be considered .
Consideration Consideration of others factors such as deflection ,fatiuge,& durablity will need to be made as refered to in clause 10.4 of the code .
combination of load s to be taken as per clause 1]with appropriate partial safety factor for load s given in table 12 of IRS CBC
2 GEOTECHNICAL DESIGNE (FOUNDATION)
2.1 Foundation must be designed in acccordance with clause 6.0 of Bridge substructure and foundation code adequately against any expected failures.
2.2 The foundation has been checked for minimum & maximum pressure effect up to HFL & LWL due to buoyancy.
2.3 For determination of Allowable bearing capacity clause 6.3,6.4,6.5&6.6 of substructure code shall be reffered.
3 Material Properties
3.1 Cement As percl-4.1 of IRS CBC
3.2 Concrete
(a) Density Density of Concrete -RCC = 25 Kn/m3 PCC=24 Kn/m3
(b) Minimum grade of concrete As per Cl No- 5.4.4 of IRS CBC
3.3 Reinforcement-As per clause 4.5 IRS CBC
Page 6 of 97
DESIGN OF ABUTMENT AND
FOUNDATION(A2)
Page 7 of 97
DESIGN OF ABUTMENT AND FOUNDATION
BRIDGE NO. 312A
ABUTMENT NO. A2
SPAN ARRANGEMENT:- 5 x 6.1 m
1.0 INTRODUCTION
The system consists of a solid rectangular abutment with monolithic dirt wall, square return wall and solid
abutment cap. The top dimensions of the abutment cap are fixed so as to fit in the details of PSC Slab
superstucture.
2.0 REFERENCE
For the design of the abutment and its different components generally the provisions of IRS(Indian Railway
Standards) Codes have been followed. Followings are the main references.
Seismic Zone = V
Z = 0.36 Z/2R = 0.06
Importance Factor (I) = 1.5 Sa/g = 2.5
R = 3
4.1 Span 1
Page 8 of 97
5.0 SKETCHES
1.065 m
T.O.Pc 52.843 m
GL 51.897 m
51.343 m 1.5 m
2.0175 m
5.1 m
ELEVATION
18.56 m 18.58 m
2.0175 m
1.065 m
PLAN
+ -
Page 9 of 97
6.0 DEAD LOAD CALCULATION
Anticlockwise Moments are taken as positive
+ -
6.1 Dead Load from Railway Superstructure PSC Slab (Refer Drawing No. RDSO/B-10274)
Load for DL = 50.57 T
Weight of superstructure (Span) = 50.57 T
Reaction on Abutment = 25.285 T
No of Superstructures = 3 nos
Longitudinal Eccentricity of Reaction w.r.t. C/L of Abutment, eL1 = 0.271 m
Longitudinal Eccentricity of Reaction w.r.t. C/L of Pile cap, eL2 = 0.271 m
Longitudinal Moment due to DL about C/L of Abutment = 3 x 25.285 x 0.271 = 20.557 T-m
Longitudinal Moment due to DL about C/L of Pile cap = 3 x 25.285 x 0.271 = 20.557 T-m
The Superstructure is symmetric about Centre Line of Soffit; therefore there is no Transverse Eccentricty
Transverse Eccentricity of Reaction, eT = 0m
Transverse Moment due to DL = 25.285 x 0 = 0 T-m
Longitudinal Moment due to SIDL about C/L of Abutment = 3 x 23.286 x 0.271 = 18.932 T-m
Longitudinal Moment due to SIDL about C/L of Pile cap = 3 x 23.286 x 0.271 = 18.932 T-m
The Superstructure is symmetric about Centre Line of Soffit; therefore there is no Transverse Eccentricty
Transverse Eccentricity of Reaction, eT = 0m
Transverse Moment due to SIDL = 23.286 x 0 = 0 T-m
1.065 m 0.4 m
C/L of bearing
C/L of abutment
0.271
1.065 m
Page 10 of 97
[c] Dead Load of Raised Portion of Seismic Restrainer Block
s/w of seismic restrainer block = 6 x 0.910 x 0.690 x 0.523 x 2.5 = = 4.926 T
Total = 4.926 T
Eccentricity w.r.t. Abutment CG 0.271 m
Eccentricity w.r.t. Pile Cap CG 0.271 m
Total Dead Load from Abutment Cap, dirt wall and seismic restrainer blocks
= 15.427 + 19.766 + 4.926 = 40.119 T
Total Longitudinal Moment about CL of Abutment due to above Dead Load
= 15.427 x -0.271 + 19.766 x 0+4.926x0.271 = -2.850 T-m
Total Longitudinal Moment about CL of Pile Cap due to above Dead Load
= 15.427 x -0.271 + 19.766 x 0+4.926x0.271 = -2.850 T-m
1.065 m
TRAFFIC DIRECTION
18.56 m
18.58 m
Traffic Direction
Page 11 of 97
Here total 3 Nos. tracks are placed on single sub-structure
Total EUDL Load (Shear) for 7.145 m span ( when 1 track loaded, concentrically ) = 315.000 T
Page 12 of 97
Therefore, Net Longitudinal Force Transferred to Abutment = 49.98 T
Tractive force for Type A Live Load = 49.98 T
Lever Arm w.r.t. Base of Abutment = 55.653 - 52.843 = 2.810 m
Lever Arm w.r.t. Base of Pile Cap = 55.653 - 51.343 = 4.310 m
Moment Calculation
[a] When single track at edge loaded (Type A)
Moment about Base of Abutment = 49.98 x 2.81 = 140.444 T-m
Moment about Bottom of Pile Cap = 49.98 x 4.31 = 215.414 T-m
φ = 30 ° = 0.524 radians
i = 0 ° = 0.000 radians
δ = 10.00 ° = 0.175 radians
α = 0 ° = 0.000 radians
γ = 1.8 T per cum
Ka = Cos2(φ-α)/[Cos2αCos(α+δ)[1+√((Sin(φ+δ)Sin(φ-i))/(Cos(α+δ)Cos(α-i)))]2]xCosδ
Ka = 0.304
3.445 m
4.945
Page 13 of 97
Lever Arm w.r.t. Pile Cap Base = ( 1.5 / 3 ) x [ ( 2 x 1.885 + 2.706) / ( 1.885 + 2.706 ) ]
= 0.705 m
Total Force at bottom of Pile Cap = 60.263 + 63.976 = 124.239 T
Total Moment at bottom of Pile Cap = 60.263 x ( 1.148 + 1.5 ) + 63.976 x 0.705
= 204.68 T-m
P2
4.945 3.445 P1
Page 14 of 97
Final Result:
at pile cap
P1 = 3.822 T/m
acting at = 2.4725 m
P2 = 3.150 T/m
acting at = 3.297 m
Transverse direction
(Note : Seismic Force will act at Top of Bed Block )
Lever Arm w.r.t. Base of Abutment = 55.653 + 0 - 52.843 = 2.810 m
Lever Arm w.r.t. Bottom of Pile Cap = 55.653 + 0 - 51.343 = 4.310 m
Moment about Base of Abutment = 17.067 x 2.81 = 47.958 T-m
Moment about Bottom of Pile Cap = 17.067 x 4.31 = 73.559 T-m
Transverse direction
(Note : Seismic Force will act at Top of Bed Block )
Lever Arm w.r.t. Base of Abutment = 55.653 + 0 - 52.843 = 2.810 m
Lever Arm w.r.t. Bottom of Pile Cap = 55.653 + 0 - 51.343 = 4.310 m
Moment about Base of Abutment = 15.718 x 2.81 = 44.168 T-m
Page 15 of 97
Moment about Bottom of Pile Cap = 15.718 x 4.31 = 67.745 T-m
Page 16 of 97
10.8 ON 50% LIVE LOAD IN TRANSVERSE DIRECTION
(Note : Refer clause 2.12.6, IRS:Bridge Rules)
Point of application of the force at Top of Bed Block = 55.653 m RL
Lever Arm w.r.t. Base of Abutment = 55.653 - 52.843 = 2.810 m
Lever Arm w.r.t. Bottom of Pile Cap = 55.653 - 51.343 = 4.310 m
[a] When single track at edge loaded (Type A)
Horizontal Seismic Force = [ 277.0425 / ( 1 + 0.759 ) ] x 0.50 x 0.225 = 17.719 T
Moment about Base of Abutment = 17.719 x 2.81 = 49.790 T-m
Moment about Bottom of Pile Cap = 17.719 x 4.31 = 76.369 T-m
10.9 SEISMIC FORCES IN VERTICAL DIRECTION DUE TO DEAD LOADS
Seismic Force on Abutment due to Dead Loads in Vertical Direction
= 67.499 x 0.15 / 0.225 = 44.999 T
Seismic Force on Pile Cap due to Dead Loads in Vertical Direction
= 147.451 x 0.15 / 0.225 = 98.310 T
Page 17 of 97
Lever Arm w.r.t. Pile Cap Bottom = 0.66 x 4.945 = 3.264 m
Increment in Moment about Pile Cap Bottom = 91.091 x 3.264 = 297.321 T-m
Page 18 of 97
= 1.1 x ( 24.2855 ) + 1.0 x ( 60.263 + 95.918 ) = 180.467 T
Horizontal Load in Transverse Direction (HT) = = 0T
Page 19 of 97
Longitudinal Moment (ML) =
= 1.25 x ( 20.557 -2.85 0 ) + 1.5 x ( 18.932 ) + 0.5 x(75.079+140.4438 ) + 1.7 x (69.182 + 185.318 ) = 1039.13 T-m
+ 1.2 x ( 146.875 +73.072 +153.543 )
Transverse Moment (MT) =
0.5 x ( 27.70425 ) = 13.852 T-m
Horizontal Load in Longitudinal Direction (HL) =
0.5x 49.98+ 1.7 x (60.263+95.918) + 1.2 x ( 67.499 +42.422 + 67.521 ) = 503.428 T
Horizontal Load in Transverse Direction (HT) = = 0T
Page 20 of 97
Transverse Moment (MT) =
= 1.0 x ( 27.704 ) = 27.7 T-m
Horizontal Load in Longitudinal Direction (HL) =
1.0 x 49.98+ 1 x 0+ 1.0 x (124.239+129.40032) = 303.619 T
Horizontal Load in Transverse Direction (HT) = = 0T
Page 21 of 97
Case - IV (Normal Load + Transverse Seismic + Vertical Seismic DN)
Vertical Load (V) =
= 1.0 x ( 75.855 + 40.119 + 119.093+0+355.3425 ) + 1.2 x ( 69.858)
+ 1.0 x 277.0425+ 1.0 x ( 232.195) + 1.0 x (98.31) = 1155.078 T
Longitudinal Moment (ML) =
= 1.0 x ( 20.557 -2.85 0 ) + 1.2 x ( 18.932 )
+ 1.0 x ( 204.68 + 368.146 ) + 1.0 x (-357.812 ) + 0.5 x (75.079 + 215.4138 ) = 400.686 T-m
Page 22 of 97
Longitudinal Moment (ML) =
= 1.25 x ( 20.557 -2.85 0 ) + 1.5 x ( 18.932 )
+ 1.7 x ( 204.68 + 368.146 ) + 1.25 x (-357.812 )
= 577.071 T-m
Transverse Moment (MT) =
= 0.5 x ( 27.704 ) + 1.2 x (308.088 +76.369) = 475.200 T-m
Horizontal Load in Longitudinal Direction (HL) =
0.5 x 49.98+ 1.7 x (124.239+129.40032) = 456.177 T
Horizontal Load in Transverse Direction (HT) = = 198.204 T
= 1.2 x ( 147.451+17.719 )
14 Summary of Forces
14.1 at Base of Abutment
Serviceability Limit State (SLS) Ultimate Limit State (ULS)
all Loads are in ton all Loads are in ton
Case - I Case - II Case - III Case - IV Case - I Case - II Case - III Case - IV
V 595.94 595.939 412.42 412.42 V 821.41 918.374 468.97 468.97
ML 510.45 363.1654 776.18 402.69 ML 794.38 595.008 1039.13 590.94
MT 27.70 0.000 63.64 210.52 MT 38.79 0.000 13.85 249.85
HL 206.16 363.165 358.61 181.17 HL 335.48 308.007 503.43 290.50
HT 0.00 0 0.00 85.22 HT 0.00 0 0.00 102.26
Page 23 of 97
SAMPLE PILE CAPACITY CALCULATION
[Around (BH-03) Abutment Locations]
Pile Shaft Length = 14.00 m from Bottom of Pile Cap (51.343 M).
Maximum Scour Level = (54.641-50.977) = 3.664 m below Existing Ground Level.
Diameter of Pile = 1200 mm Critical depth 17.00 D
FOS of Shaft Resistance = 2.50 Maximum OVP = 11.69 t/sqm
FOS for End Bearing = 2.50
So, maximum Depth upto which pressure will increase = 13.63 m
Layer Top Depth Bottom Depth Eff. Depth Cohesion Φ Adhesion Factor K0 Eff. Density Mean Pressure
No. (M) (M) (M) (kg/sqcm) (Degree) (α) (gm/cc) (t/sqm)
IA 3.66 4.50 0.84 -- -- 1.000 1.00 0.80 0.33
I 4.50 8.50 4.00 -- -- 1.000 1.00 0.80 2.27
II 8.50 10.50 2.00 -- -- 1.000 1.00 0.85 4.72
III 10.50 17.30 6.80 -- -- 1.000 1.20 0.90 8.63
Layer Eff. Depth Effective σz fs1 = α C fs2 = K0σztanΦ fs =fs1 +fs2 Ultimate Shaft Safe Shaft
No. (M) (t/sqm) (t/sqm) Resistance (T) Resistance (T)
IA 0.84 0.33 -- -- -- -- --
I 4.00 2.27 -- -- -- -- --
II 2.00 4.72 -- -- -- -- --
III 6.80 8.63 -- -- -- -- --
13.63 0.00 0.00
For End Bearing
Cohesion C= 0 kg/sqcm
Friction Angle = 34 °
Nq = 42.69
Nγ = 42.90 [ Refer to Table No. 1 of IS 6403 : 1981]
Eff. Ovp. Pressure=p(tip) 11.69 t/sqm
q(tip) =p(tip).Nq+0.5.γ.D.Nγ = 520.84 t/sqm
Ultimate End Bearing = 589.06 T
Safe End Bearing = 235.62 T
Safe Shaft Resistance= 0.00 T Note: Skin friction of the sand layers have been neglected for siesmic zone-V.
So, Total Pile Capacity = 235.62 T
So, Recommended Pile Capacity = 230 T
Page 24 of 97
SAMPLE PILE CAPACITY CALCULATION
[Around (BH-03) Abutment Locations]
Pile Shaft Length = 16.00 m from Bottom of Pile Cap (51.343 M).
Maximum Scour Level = (54.641-50.977) = 3.664 m below Existing Ground Level.
Diameter of Pile = 1200 mm Critical depth 17.00 D
FOS of Shaft Resistance = 2.50 Maximum OVP = 13.49 t/sqm
FOS for End Bearing = 2.50
So, maximum Depth upto which pressure will increase = 15.63 m
Layer Top Depth Bottom Depth Eff. Depth Cohesion Φ Adhesion Factor K0 Eff. Density Mean Pressure
No. (M) (M) (M) (kg/sqcm) (Degree) (α) (gm/cc) (t/sqm)
IA 3.66 4.50 0.84 -- -- 1.000 1.00 0.80 0.33
I 4.50 8.50 4.00 -- -- 1.000 1.00 0.80 2.27
II 8.50 10.50 2.00 -- -- 1.000 1.00 0.85 4.72
III 10.50 19.30 8.80 -- -- 1.000 1.20 0.90 9.53
Layer Eff. Depth Effective σz fs1 = α C fs2 = K0σztanΦ fs =fs1 +fs2 Ultimate Shaft Safe Shaft
No. (M) (t/sqm) (t/sqm) Resistance (T) Resistance (T)
IA 0.84 0.33 -- -- -- -- --
I 4.00 2.27 -- -- -- -- --
II 2.00 4.72 -- -- -- -- --
III 8.80 9.53 -- -- -- -- --
15.63 0.00 0.00
For End Bearing
Cohesion C= 0 kg/sqcm
Friction Angle = 34 °
Nq = 42.69
Nγ = 42.90 [ Refer to Table No. 1 of IS 6403 : 1981]
Eff. Ovp. Pressure=p(tip) 13.49 t/sqm
q(tip) =p(tip).Nq+0.5.γ.D.Nγ = 597.69 t/sqm
Ultimate End Bearing = 675.97 T
Safe End Bearing = 270.39 T
Safe Shaft Resistance= 0.00 T Note: Skin friction of the sand layers have been neglected for siesmic zone-V.
So, Total Pile Capacity = 270.39 T
So, Recommended Pile Capacity = 260 T
Page 25 of 97
PILE DESIGN
CALCULATION OF LENGTH OF FIXITY, HORIZONTAL PILE CAPACITY
& MOMENT AT CUT-OFF LEVEL
Around Abutment Locations:
Design "N" = 19
Cantilever length(L1) = 40 cm
Dia of pile = 1200 mm
fck of concrete = 35 MPa
Allowable Limiting Deflection = 12 mm (1% pile dia as per IRC-78:2014)
Modulus of Subgrade reaction ηh = 0.302 kg/cucm from Table 3 of IS 2911 (Part 1/Sec 2):2010
4
Moment of inertia (I) = 1.018E+07 cm
E of concrete = 29580.39892 N/sqmm = 295803.989 kg/sqcm
Hence, H = 65.28 T
Corrected actual moment = 3.70 t-m per T of Thrust
Hence, H = 23.79 T
Corrected actual moment = 3.16 t-m per T of Thrust
Page 26 of 97
Design of Pile Foundation
PILE REACTION FOR A RECTANGULAR PILE CAP AND CHECK FOR PILE CAPACITY
Page 27 of 97
[D] Co-ordinate of Piles
Longitudinal Transverse
2 2
Pile No Co-Ordinate Co-Ordinate n xi yi
xi (m) yi (m)
P1 1.800 7.500 1 3.2400 56.25
P2 1.800 3.750 1 3.2400 14.06
P3 1.800 0.000 1 3.2400 0.00
P4 1.800 -3.750 1 3.2400 14.06
P5 1.800 -7.500 1 3.2400 56.25
P6 -1.800 7.500 1 3.2400 56.25
P7 -1.800 3.750 1 3.2400 14.06
P8 -1.800 0.000 1 3.2400 0.00
P9 -1.800 -3.750 1 3.2400 14.06
P10 -1.800 -7.500 1 3.2400 56.25
Total ∑ 10 32.40 281.25
Traffic Direction
6 1
7 2
3.750
8 3
X X
1
0
5
Y
3.6
5.10
Page 28 of 97
[E] Summary of Loads and Moments at Center Line of Pile Cap Base
WORKING LOAD CONDITION
Case - I (Vertical Load-Considering Live Load)
Page 29 of 97
WORKING LOAD CONDITION
Load/Case Case I Case II Case III Case IV
V (T) 1169.51 892.46 1279.63 1279.63
ML (T - m) 542.15 356.32 1256.09 434.44
MT (T - m) 27.70 0.00 27.70 412.16
HL (T) 303.62 277.92 604.63 278.63
HT (T) 0.00 0.00 0.00 165.17
ZL = 18.00 m3
ZT1 = 37.5 m3 ZT2 = 75 m3
Page 30 of 97
WORKING LOAD CONDITION
Pile Load Case
Reaction Case I Case II Case III Case IV
P1 147.81 109.04 198.48 163.09
P2 147.44 109.04 198.12 157.59
P3 147.07 109.04 197.75 152.10
P4 146.70 109.04 197.38 146.60
P5 146.33 109.04 197.01 141.11
P6 87.57 69.45 58.92 114.82
P7 87.20 69.45 58.55 109.32
P8 86.83 69.45 58.18 103.83
P9 86.46 69.45 57.81 98.33
P10 86.09 69.45 57.44 92.84
Max Value 147.81 109.04 158.79 130.47
Min Value 87.57 69.45 45.95 91.85
Adding Self Weight of Pile
Max Value 174.951 136.185 185.9302 157.6142
Min Value 114.713 96.593 73.0958 118.9974
HR (T) 30.36 27.79 60.46 32.39
Page 31 of 97
ULTIMATE LOAD CONDITION
Pile Reaction Load Cases
(T)
Case I Case II Case III Case IV
Pmax = 255.81 T
Corresponding Horizontal load = = 82.239 T
Pmin = 83.89 T
Corresponding Horizontal load = = 82.239 T
(B)Section Property
Diameter of Pile Section (D) = 1200 mm
Clear cover = 75 mm
Diameter of Outer Links = 12 mm
Diameter of main vertical R/F outer layer = 25 mm
After multiplication of reduction factor with fixed head pile and free head pile , semi fix head
pile capacity moment is calculated
Moment per tonne Horizontal load = 3.430 t-m/t
Effective Cover (d') = (75 + 12 + 25 / 2) = 99.5 mm
d'/D = 99.5 / 1200 = 0.083 mm
Page 32 of 97
(D) Critical Load Case 2 (Maximum load case)
Axial Load Pu = 255.81 T
Moment Mu = 82.239 x 3.43 = 282.08 T-m
Pu /fck D2 = 0.05
Mu / fck D3 = 0.05
Let us provide
In Layer - I 28 nos. 32 mm diameter bars as main R/F in outer layer
Page 33 of 97
DESIGN OF ABUTMENT AND FOUNDATION
BRIDGE NO. 312A
ABUTMENT NO. Platform -A2
SPAN ARRANGEMENT:- 1 x 21.145 m
1.0 INTRODUCTION
The system consists of a solid rectangular abutment with monolithic dirt wall, square return wall and solid
abutment cap. The top dimensions of the abutment cap are fixed so as to fit in the details of PSC Slab
superstucture.
2.0 REFERENCE
For the design of the abutment and its different components generally the provisions of IRS(Indian Railway
Standards) Codes have been followed. Followings are the main references.
Seismic Zone = V
Z = 0.36 Z/2R = 0.06
Importance Factor (I) = 1.5 Sa/g = 2.5
R = 3
4.1 Span 1
Page 34 of 97
5.0 SKETCHES
1.065 m
T.O.Pc 52.843 m
GL 51.897 m
51.343 m 1.5 m
2.0175 m
5.1 m
ELEVATION
8.56 m 8.56 m
2.0175 m
0.5 m
1.065 m
PLAN
+ -
Page 35 of 97
6.0 DEAD LOAD CALCULATION
Anticlockwise Moments are taken as positive
+ -
The Superstructure is symmetric about Centre Line of Soffit; therefore there is no Transverse Eccentricty
Transverse Eccentricity of Reaction, eT = 0.27 m
Transverse Moment due to DL = 134.845 x 0.27 = 36.408 T-m
Longitudinal Moment due to SIDL about C/L of Abutment = 1 x 21.767 x 0 = 0.000 T-m
Longitudinal Moment due to SIDL about C/L of Pile cap = 1 x 21.767 x 0 = 0.000 T-m
The Superstructure is symmetric about Centre Line of Soffit; therefore there is no Transverse Eccentricty
Transverse Eccentricity of Reaction, eT = 0.27 m
Transverse Moment due to SIDL = 21.767 x 0.27 = 5.877 T-m
1.25 m 0.6 m
C/L of bearing/abutment
1.065 m
Page 36 of 97
[b] Dead Load of Abutment Cap
Dead Load = 1.25 x 0.6 x 8.56 x 2.5 = 16.050 T
Eccentricity w.r.t. Abutment CG = 0.093 m
Eccentricity w.r.t. Pile Cap CG = 0.093 m
Total Dead Load from Abutment Cap, dirt wall and seismic restrainer blocks
= 13.261 + 16.05 + 4.926 = 34.237 T
Total Longitudinal Moment about CL of Abutment due to above Dead Load
= 13.261 x -0.485 + 16.05 x 0.093+4.926x0.271 = -3.600 T-m
Total Longitudinal Moment about CL of Pile Cap due to above Dead Load
= 13.261 x -0.485 + 16.05 x 0.093+4.926x0.271 = -3.600 T-m
1.065 m
TRAFFIC DIRECTION
8.56 m
Page 37 of 97
5.1 m
8.56 m
Traffic Direction
Longitudinal Moment due to Pedestrian Live load about C/L of Abutment = 81.769 x 0 = 0 T-m
Longitudinal Moment due to Pedestrian Live Load about C/L of Pile cap = 81.769 x 0 = 0 T-m
There is an eccentricity between the c/l of Platform and the c/l of Abutment
Transverse Eccentricity of Reaction, eT = 0.27 m
Transverse Moment due to Pedestrian live load = 22.078 T-m
φ = 30 ° = 0.524 radians
i = 0 ° = 0.000 radians
δ = 10.00 ° = 0.175 radians
α = 0 ° = 0.000 radians
γ = 1.8 T per cum
Ka = Cos2(φ-α)/[Cos2αCos(α+δ)[1+√((Sin(φ+δ)Sin(φ-i))/(Cos(α+δ)Cos(α-i)))]2]xCosδ
Page 38 of 97
Ka = 0.304
5.06 m
6.56
Page 39 of 97
Case - 2
a 2.050 c
b
P1
Height of abutment = 5.060 m
5.560
d
6.56 m g P2
-0.500 Bottom of Abutment
P2'
1.5 m
f e
0.717
Final Result:
at pile cap
P1 = 7.692 T/m
acting at = 4.226 m
P2 = 0.717 T/m
acting at = 0.500 m
Page 40 of 97
9.0 VERTICAL LOAD DUE TO EARTH
9.1 VERTICAL LOAD DUE TO BACKFILL ON PILE CAP
Height of back fill behind abutment wall = 5.060 m
Avg. height of back fill beyond Return Wall in Trans. Direction = 5.060 m
Eff. width of outer cantilever Pile Cap loaded with Earthfill = 0 m
W = ( 8.56 - 2 x 0.5 ) x 2.0175 x 5.06 x 1.8 = 138.918 T
Eccentricity w.r.t. CG of Pile Group = - [ ( 2.0175 + 1.065 ) / 2.0 ] = -1.541 m
Longitudinal Moment about CG of Pile Group = 138.918 x ( -1.541 ) = -214.073 T-m
Transverse direction
(Note : Seismic Force will act at Top of Bed Block )
Lever Arm w.r.t. Base of Abutment = 55.69 + 0.3 - 52.843 = 3.147 m
Lever Arm w.r.t. Bottom of Pile Cap = 55.69 + 0.3 - 51.343 = 4.647 m
Moment about Base of Abutment = 30.34 x 3.147 = 95.480 T-m
Moment about Bottom of Pile Cap = 30.34 x 4.647 = 140.990 T-m
Transverse direction
(Note : Seismic Force will act at Top of Bed Block )
Lever Arm w.r.t. Base of Abutment = 55.69 + 0.3 - 52.843 = 3.147 m
Lever Arm w.r.t. Bottom of Pile Cap = 55.69 + 0.3 - 51.343 = 4.647 m
Moment about Base of Abutment = 4.898 x 3.147 = 15.414 T-m
Moment about Bottom of Pile Cap = 4.898 x 4.647 = 22.761 T-m
Page 41 of 97
Moment about Base of Abutment = 2.984 x 3.954 + 3.611 x 2.547
= 20.996 T-m
Moment about Bottom of Pile Cap = 2.984 x 5.454 + 3.611 x 4.047
= 30.888 T-m
Page 42 of 97
For - ve αv
λ = tan-1[αh / (1 - αv)]
= 0.2588 radians = 14.826 °
Page 43 of 97
IRS CBC TABLE-12 Cl-6.7 RDSO Seismic Guideline
Normal condition Seismic Condition
Case-1 ULS SLS Case-2 ULS SLS Description ULS SLS
DL 1.25 1 DL 1.25 1 DL 1.25 1
SIDL 2 1.2 SIDL 2 1.2 SIDL 1.5 1.2
TEMP 1.5 1 Frictional 1.5 1 LL 0.5 0.5
EP 1.7 1 EP 1.7 1 EQ 1.2 1
LL 1.4 1 EP 1.7 1
Page 44 of 97
12.0 Combination of Loads and Moments at Base of Abutment
12.2 Ultimate Limit State (ULS)
(Note : Partial Safety Factors are as per Table 12, IRS Concrete Bridge Code)
Case - I ( Vertical Load Case-Considering LL & Temperature Load)
Vertical Load (V) =
= 1.25 x ( 134.845 + 34.237 + 51.211 +12.761 ) + 2.0 x ( 21.767) + 1.4 x ( 81.769 )
= 449.328 T
Longitudinal Moment (ML) =
= 1.25 x ( 0 -3.6 -19.66 ) + 2.0 x ( 0 ) + 1.4 x ( 0+0 ) + 1.7 x (89.347 + 180.258 ) =
= 429.254 T-m
Transverse Moment (MT) =
= 1.4x ( 22.078 ) + 1.25 x 36.408 + 1.5 x 5.877 = 85.235 T-m
Horizontal Load in Longitudinal Direction (HL) =
= 1.4 x ( 0) + 1.7 x ( 52.962 + 62.77 ) = 196.744 T
Horizontal Load in Transverse Direction (HT) = = 0T
Page 45 of 97
At the bottom of pile cap
SL No. LOAD DESCRIPTION V ML MT HL HT
a Dead Load
6.1 From Railway Super-structure 134.845 0.000 36.408 0 0
6.3 SIDL 21.767 0.000 5.877 0 0
6.4 From Abt. Cap, railing, pedestal, OHE 34.237 -3.600 0 0 0
6.5 From Abt. Shaft 51.211 0.000 0 0 0
6.6 From pile cap 163.710 0.000 0 0 0
6.7 From square return 12.761 -19.660 0 0 0
6.9 Weight of backfill 138.918 -214.073 0 0 0
6.10 Due to Dead Load and LL Surcharge 0.000 0.000 0 0 0
b Live Load
7.0 Pedestrian Live Load 81.769 0.000 22.078 0 0
c Frictional Resistance for bearing
8.1 Due to DL & SIDL 0 20.424 0 4.698 0
e Earth Pressure
8.2.1 Due to backfill 0 198.102 0 93.787 0
8.2.2 Due to surcharge effect 0 290.638 0 75.474 0
f Temperature load
8.3 Thermal Expansion of Slab and Retainer 0 0.000 0 0.000 0
g Seismic force
9.1 Dead Load seismic 62.050 264.069 264.069 93.061 93.061
9.2 When single track loaded 0.000 0.000 0.000 0 0.000
9.3 Dynamic incr. of earth pressure 0 216.549 0 66.021 0
9.4 Dynamic incr. of surcharge earth pressure 0 230.049 0 53.129 0
Page 46 of 97
+ 1.0 x (-214.073 ) + 1.0 x (264.069 + 216.549+230.049 ) = 962.074 T-m
Page 47 of 97
Horizontal Load in Longitudinal Direction (HL) =
1.4 x 0+ 1.7 x (93.787+75.474) + 1.5 x 0 = 294.321 T
Horizontal Load in Transverse Direction (HT) = = 0T
Page 48 of 97
14.2 at Base of Pile cap
Servicibility Limit State (SLS)
all Loads are in ton
Case - I Case - II Case - III Case - IV
V (T) 643.57 643.571 540.64 540.64
ML (T-m) 251.41 271.831 962.07 251.41
MT (T-m) 65.54 65.5 65.54 318.57
HL (T) 169.26 173.959 381.47 288.41
HT (T) 0.00 0 0.00 93.06
Page 49 of 97
Design of Pile Foundation
PILE REACTION FOR A RECTANGULAR PILE CAP AND CHECK FOR PILE CAPACITY
Longitudinal Transverse
2 2
Pile No Co-Ordinate Co-Ordinate n xi yi
xi (m) yi (m)
P1 1.800 3.000 1 3.2400 9.00
P2 1.800 0.000 1 3.2400 0.00
P3 1.800 -3.000 1 3.2400 9.00
P4 -1.800 3.000 1 3.2400 9.00
P5 -1.800 0.000 1 3.2400 0.00
P6 -1.800 -3.000 1 3.2400 9.00
Total ∑ 6 19.44 36.00
Page 50 of 97
Traffic Direction
1.280
4 1
3.000
X 5 2 X
8.560
3.000
6 3.600 3
1.280
Y
3.6
5.10
TRAFFIC DIRECTION (LONGITUDINAL)
PLAN OF PILE CAP
[E] Summary of Loads and Moments at Center Line of Pile Cap Base
WORKING LOAD CONDITION
Case - I (Vertical Load-Considering Live Load)
Page 51 of 97
Horizontal Load in Transverse Direction (HT) = 0.00 T
ZL = 10.80 m3
ZT1 = 12 m3
Page 52 of 97
For P1 = P/N+ML/ZL+MT/ZT1
P2 = P/N+ML/ZL
P3 = P/N+ML/ZL-MT/ZT1
P4 = P/N-ML/ZL+MT/ZT1
P5 = P/N-ML/ZL
P6 = P/N-ML/ZL-MT/ZT1
Page 53 of 97
ULTIMATE LOAD CONDITION
Pile Reaction Load Cases
(T)
Case I Case II Case III Case IV
Pmax = 282.60 T
Corresponding Horizontal load = = 90.399 T
Pmin = 32.69 T
Corresponding Horizontal load = = 90.399 T
(B)Section Property
Diameter of Pile Section (D) = 1200 mm
Clear cover = 75 mm
Diameter of Outer Links = 12 mm
Diameter of main vertical R/F outer layer = 25 mm
After multiplication of reduction factor with fixed head pile and free head pile , semi fix head
pile capacity moment is calculated
Moment per tonne Horizontal load = 3.430 t-m/m
Effective Cover (d') = (75 + 12 + 25 / 2) = 99.5 mm
d'/D = 99.5 / 1200 = 0.083 mm
Page 54 of 97
Mu / fck D3 = 0.05
Let us provide
In Layer - I 26 nos. 32 mm diameter bars as main R/F in outer layer
Page 55 of 97
DESIGN OF PIER AND
FOUNDATION
Page 56 of 97
DESIGN OF PIER AND FOUNDATION
BRIDGE NO. 312A
PIER NO. P3
SPAN ARRANGEMENT:- 5 x 6.1 m
1.0 INTRODUCTION
The system consists of a solid rectangular Pier The top dimensions of the Pier cap are fixed so as to fit in the details of PSC Slab
superstucture.
2.0 REFERENCE
For the design of the pier and its different components generally the provisions of IRS(Indian Railway
Standards) Codes have been followed. Followings are the main references.
Seismic Zone V R= 3
Z = 0.36 Z/2R = 0.06
Importance Factor = 1.5 Sa/g = 2.5
4.1 Span 1
Effective span between c/c of bearing 6.697 m
Overall span 7.145 m
Span between c/c of Expansion Joints 7.165 m
Page 57 of 97
5.0 SKETCHES
Rail Formation Level=
56.288 m
6.1 m PSC Slab (Refer Drawing No. RDSO/B-10274) 6.1 m PSC Slab (Refer Drawing No. RDSO/B-10274)
Bed Block level =
55.653 m
0.600m 1.065m
55.053 m
1.065m
GL 50.715m
Top of pile cap
51.543 m
1.500m
50.043m
2.018m 5.100m
ELEVATION
0.0
C/L of Pier /Pile Cap
17.980m
18.000m 16.935m
1.065m
PLAN
Page 58 of 97
6.0 DEAD LOAD CALCULATION
Anticlockwise Moments are taken as positive
+ -
The Superstructure is symmetric about Centre Line of Soffit; therefore there is no Transverse Eccentricty
Transverse Eccentricity of Reaction, eT = 0.000 m
Transverse Moment due to DL = 151.71 x 0 = 0.000 T-m
Longitudinal Moment due to SIDL about C/L of Pier = 139.718 x 0 = 0.000 T-m
Longitudinal Moment due to SIDL about C/L of Pile cap = 139.718 x 0 = 0.000 T-m
The Superstructure is symmetric about Centre Line of Soffit; therefore there is no Transverse Eccentricty
Transverse Eccentricity of Reaction, eT = 0m
Transverse Moment due to SIDL = 139.718 x 0 = 0 T-m
Uniform portion
Length of bed block = 18.580 m
Width of bed block = 1.065 m
Depth of bed block = 0.600 m 1.065 0.600m
Tappered portion
Length of bed block at top = 18.58 m
Length of bed block at bottom = 18.000 m
Width of bed block at top = 1.065 m
Width of bed block at bottom = 1.065 m
Page 59 of 97
[c] Dead Load of Seismic Restrainer:
Dead Load of Seismic Retainer Blocks = 0.690 x 0.910 x 1.065 x 2.5 x 2 = 5.929 T
= 5.929 T
1.065m
TRAFFIC DIRECTION
18.000m
5.100m
17.980m
Traffic Direction
PLAN OF PILE CAP
The tolerancess for finished concrete bridge structures is due to mainly deviation from plumb or specified, batter for face
of exposed piers as per IRS concrete bridge code Cl. No-6.5
The deviation is 1 in 250, subjected to a maximum value of 0.05 times the least lateral dimension of pier.
Page 60 of 97
Load calculation for P1
Height of Pier : = 3.510 m
Thickness of Pier = 1.065 m
Length of Pier Cap = 18.580 m
Width of Pier Cap = 1.065 m
Thickness of Pier Cap = 0.600 m
Unit weight of Concrete = 2.5 T/m3
Longitudinal Eccentricity w.r.t C/L of Pier, single span loaded eL1 = 0.271 m
Longitudinal Eccentricity w.r.t C/L of Pier, both span loaded eL3 = 0.000 m
Page 61 of 97
Computation of Co-efficient of Dynamic Augment (CDA)
(Note : Please refer clause 2.4.1.1 (a) of IRS:Bridge Rule)
CDA = 0.15 + [ 8 / (6 + L)] Subject to Maximum of 1.0
Therefore, CDA (case-a) = 0.15 + [ 8 / ( 6 + 7.145 ) ] = 0.759
For( case b) = 0.550
Augmented load calculation
[a] When single track at edge loaded
Total Live Load (Shear) = 105 x (1 + 0.759 ) = 184.695 T
Live Load Reaction on Pier = = 92.348 T
Longitudinal Moment due to LL on Pier, ML = 92.3475 x 0.271 = 25.026 T-m
Transverse Moment due to LL on Pier, MT = 92.3475 x 0.1 = 9.235 T-m
Page 62 of 97
Moment Calculation
[a] When single track, single span loaded (Type A)
Moment about Base of Pier = 16.66 x 4.11 = 68.473 T-m
Moment about Bottom of Pile Cap = 16.66 x 5.61 = 93.463 T-m
[b] When single track both span loaded (Type B)
Moment about Base of Pier = 31.5 x 4.11 = 129.5 T-m
Moment about Bottom of Pile Cap = 31.5 x 5.61 = 176.715 T-m
Transverse direction
(Note : Seismic Force will act at Top of Bed Block)
Lever Arm w.r.t. Base of Pier = 55.9405 - 51.543 = 4.110 m
Lever Arm w.r.t. Bottom of Pile Cap = 55.9405 - 50.043 = 5.610 m
Moment about Base of pier = 34.135 x 4.11 = 140.295 T-m
Moment about Bottom of Pile Cap = 34.135 x 5.61 = 191.497 T-m
Page 63 of 97
Transverse direction
(Note : Seismic Force will act at Top of Bed Block)
Lever Arm w.r.t. Base of Pier = = 4.110 m
Lever Arm w.r.t. Bottom of Pile Cap = = 5.610 m
Moment about Base of Pier = 31.437 x 4.11 = 129.206 T-m
Moment about Bottom of Pile Cap = 31.437 x 5.61 = 176.362 T-m
Page 64 of 97
Moment about Base of Pier = 5.906 x 4.11 = 24.274 T-m
Moment about Bottom of Pile Cap = 5.906 x 5.61 = 33.133 T-m
[b] When single track both span loaded (Type B)
Horizontal Seismic Force = [ 139.291 / ( 1 + 0.55 ) ] x 0.50 x 0.225 = 10.11 T
Moment about Base of Abutment = 10.11 x 4.11 = 41.552 T-m
Moment about Bottom of Pile Cap = 10.11 x 5.61 = 56.717 T-m
Page 65 of 97
SUMMARY OF LOADS IN TABULAR FORM
At the bottom of pier
SL No. LOAD DESCRIPTION V ML MT HL HT
a Dead Load
1 From Super-structure 151.710 0 0 0 0
2 SIDL 139.718 0 0 0 0
3 From Pier Cap, railing, pedestal, OHE 35.611 0 0 0 0
4 From Pier. Shaft 166.090 0 0 0 0
b Live Load
5 Type A Loading 92.348 25.026 9.235 0 0
7 Type B Loading 139.291 0 13.929 0 0
c Effect of Construction tolerance
8 construction tolerance 1.578
d Tractive force/Braking force
9 Type A Loading 0 68.473 0 16.66 0
10 Type B Loading 0 129.465 0 31.5 0
e Frictional Resistance
11 Type A Loading 0 598.880 0 145.714 0
12 Type B Loading 0 598.885 0 145.714 0
f Temperature load
13 Thermal Expansion of Slab and Retainer 0 0.000 0 0.000 0
g Seismic force
14 Dead Load seismic 73.568 360.534 360.534 109.620 109.620
15 For Type A Loading 3.964 0 24.274 0 5.906
16 For Type B Loading 6.785 0 41.552 0 10.110
h Water current force
Water current force 0 0.03 0.17 0.02 0.106
Page 66 of 97
+ 1.0 x ( 360.53418+0.034 )+1 x1.578
Transverse Moment (MT) =
0.5 x ( 9.23475) + 1 x (0.17 ) = 7.135 T-m
Horizontal Load in Longitudinal Direction (HL) =
0.5 x 31.5 + 1.0 x ( 109.62+0.0212 ) = 125.391 T
Horizontal Load in Transverse Direction (HT) = = 10.110 T
Page 67 of 97
Case - IV (Normal Load + Transverse Seismic + Vertical Seismic UP)
Vertical Load (V) =
= 1.25 x ( 151.71 + 35.611 + 166.09 ) + 1.5 x ( 139.718) + 0.5 x ( 139.291 ) - 1.2 x (73.568 +6.785 ) = 624.56 T
Longitudinal Moment (ML) =
= 1.25 x ( 0 + 0+0 ) + 1.5 x ( 0 ) + 0.5 x ( 25.0261725+129.465 )+1.51.578 = 79.61 T-m
Transverse Moment (MT) =
= 0.5 x ( 13.9291 ) + 1.4 x (0.17 ) + 1.2 x (360.534 +41.5521) = 489.71 T-m
Horizontal Load in Longitudinal Direction (HL) =
0.5 x 31.5 = 15.750 T
Horizontal Load in Transverse Direction (HT) =
1.2 x (109.62+10.11)= = 143.676 T
Page 68 of 97
Longitudinal Moment (ML) =
= 1.0 x ( 0 + 0 + 0+0 ) + 1.2 x ( 0 ) + 1.1x ( 25.026308)+1.1x(176.715) + 1.1 x (0.572)+ 1.1 x 1.578 = 224.28 T-m
Transverse Moment (MT) =
= 1.1 x ( 9.2348)+1.1 x(2.86 ) = 18.468 T-m
Horizontal Load in Longitudinal Direction (HL) =
1.1 x 31.5 = 34.650 T
Horizontal Load in Transverse Direction (HT) = = 0T
Page 69 of 97
Case - III (Normal Load +Longitudinal Seismic+Vertical Seismic UP)
Vertical Load (V) =
= 1.25 x ( 0 + 0 + 0+0 ) + 1.5 x ( 0)
+ 0.5 x 139.291) - 1.2 x 6.785 - 1.2 x 125.492 = 992.09 T
Longitudinal Moment (ML) =
= 1.25 x ( 0 + 0 + 0 + 0+0.572 ) + 1.5 x ( 0 ) + 0.5 x ( 25.026308+176.715)
+ 1.25 x (582.987 )+1.51.578 = 791.02 T-m
Transverse Moment (MT) =
= 0.5 x ( 13.9291 )+1.4 x (2.86 ) = 10.969 T-m
Horizontal Load in Longitudinal Direction (HL) =
0.5 x 31.5+ 1.2 x (186.991) + 1.4 x (0.3366) = 240.610 T
Horizontal Load in Transverse Direction (HT) = = 0T
Page 70 of 97
SAMPLE PILE CAPACITY CALCULATION
[Around (BH-02) Pier Locations]
Pile Shaft Length = 14.00 m from Bottom of Pile Cap (50.043 M).
Maximum Scour Level = (51.381-48.736) = 2.645 m below Existing Ground Level.
Diameter of Pile = 1200 mm Critical depth 17.00 D
FOS of Shaft Resistance = 2.50 Maximum OVP = 10.91 t/sqm
FOS for End Bearing = 2.50
So, maximum Depth upto which pressure will increase = 12.69 m
Layer Top Depth Bottom Depth Eff. Depth Cohesion Φ Adhesion Factor K0 Eff. Density Mean Pressure
No. (M) (M) (M) (kg/sqcm) (Degree) (α) (gm/cc) (t/sqm)
I 2.65 5.50 2.855 -- -- 1.000 1.00 0.80 1.14
II 5.50 10.00 4.50 -- -- 1.000 1.00 0.85 4.20
III 10.00 15.34 5.34 -- -- 1.000 1.20 0.90 8.51
Layer Eff. Depth Effective σz fs1 = α C fs2 = K0σztanΦ fs =fs1 +fs2 Ultimate Shaft Safe Shaft
No. (M) (t/sqm) (t/sqm) Resistance (T) Resistance (T)
I 2.86 1.14 -- -- -- -- --
II 4.50 4.20 -- -- -- -- --
III 5.34 8.51 -- -- -- -- --
12.69 0.00 0.00
For End Bearing
Cohesion C= 0 kg/sqcm
Friction Angle = 34 °
Nq = 42.69
Nγ = 42.90 [ Refer to Table No. 1 of IS 6403 : 1981]
Eff. Ovp. Pressure=p(tip) 10.91 t/sqm
q(tip) =p(tip).Nq+0.5.γ.D.Nγ = 489.09 t/sqm
Ultimate End Bearing = 553.15 T
Safe End Bearing = 221.26 T
Safe Shaft Resistance= 0.00 T Note: Skin friction of the sand layers have been neglected for siesmic zone-V.
So, Total Pile Capacity = 221.26 T
So, Recommended Pile Capacity = 220 T
Page 71 of 97
SAMPLE PILE CAPACITY CALCULATION
[Around (BH-02) Pier Locations]
Pile Shaft Length = 16.00 m from Bottom of Pile Cap (50.043 M).
Maximum Scour Level = (51.381-48.736) = 2.645 m below Existing Ground Level.
Diameter of Pile = 1200 mm Critical depth 17.00 D
FOS of Shaft Resistance = 2.50 Maximum OVP = 12.71 t/sqm
FOS for End Bearing = 2.50
So, maximum Depth upto which pressure will increase = 14.69 m
Layer Top Depth Bottom Depth Eff. Depth Cohesion Φ Adhesion Factor K0 Eff. Density Mean Pressure
No. (M) (M) (M) (kg/sqcm) (Degree) (α) (gm/cc) (t/sqm)
I 2.65 5.50 2.855 -- -- 1.000 1.00 0.80 1.14
II 5.50 10.00 4.50 -- -- 1.000 1.00 0.85 4.20
III 10.00 17.34 7.34 -- -- 1.000 1.20 0.90 8.51
Layer Eff. Depth Effective σz fs1 = α C fs2 = K0σztanΦ fs =fs1 +fs2 Ultimate Shaft Safe Shaft
No. (M) (t/sqm) (t/sqm) Resistance (T) Resistance (T)
I 2.86 1.14 -- -- -- -- --
II 4.50 4.20 -- -- -- -- --
III 5.34 8.51 -- -- -- -- --
14.69 0.00 0.00
For End Bearing
Cohesion C= 0 kg/sqcm
Friction Angle = 34 °
Nq = 42.69
Nγ = 42.90 [ Refer to Table No. 1 of IS 6403 : 1981]
Eff. Ovp. Pressure=p(tip) 12.71 t/sqm
q(tip) =p(tip).Nq+0.5. γ.D.Nγ = 565.94 t/sqm
Ultimate End Bearing = 640.06 T
Safe End Bearing = 256.03 T
Safe Shaft Resistance= 0.00 T Note: Skin friction of the sand layers have been neglected for siesmic zone-V.
So, Total Pile Capacity = 256.03 T
So, Recommended Pile Capacity = 250 T
Page 72 of 97
PILE DESIGN
CALCULATION OF LENGTH OF FIXITY, HORIZONTAL PILE CAPACITY
& MOMENT AT CUT-OFF LEVEL
Around Pier Locations:
Design "N" = 17
Cantilever length(L1) = 130 cm
Dia of pile = 1200 mm
fck of concrete = 35 MPa
Allowable Limiting Deflection = 12 mm (1% pile dia as per IRC-78:2014)
Modulus of Subgrade reaction ηh = 0.281 kg/cucm from Table 3 of IS 2911 (Part 1/Sec 2):2010
4
Moment of inertia (I) = 1.018E+07 cm
E of concrete = 29580.39892 N/sqmm = 295803.989 kg/sqcm
Hence, H = 58.87 T
Corrected actual moment = 4.21 t-m per T of Thrust
Hence, H = 20.11 T
Corrected actual moment = 3.42 t-m per T of Thrust
Page 73 of 97
Design of Pile
PILE REACTION FOR A RECTANGULAR PILE CAP AND CHECK FOR PILE CAPACITY
Page 74 of 97
[D] Co-ordinate of Piles
Longitudinal Transverse C
Pile No Co-Ordinate o-Ordinate n xi2 yi2
xi (m) yi (m)
P1 1.800 7.200 1 3.24 51.84
P2 1.800 3.600 1 3.24 12.96
P3 1.800 0.000 1 3.24 0.00
P4 1.800 -3.600 1 3.24 12.96
P5 1.800 -7.200 1 3.24 51.84
P6 -1.800 7.200 1 3.24 51.84
P7 -1.800 3.600 1 3.24 12.96
P8 -1.800 0.000 1 3.24 0.00
P9 -1.800 -3.600 1 3.24 12.96
P10 -1.800 -7.200 1 3.24 51.84
Total ∑ 10 32.4 259.20
Y
3.6
P P
6 1
`
P P
7 2
3.6
X P P X
8 3
P P
9 4
P
P 10
5
TRAFFIC DIRECTION
PLAN OF PILE CAP
[E] Summary of Loads and Moments at Center Line of Pile Cap Base
Page 75 of 97
UNFACTORED LOAD CONDITION (for determining Pile Capacity)
Case - I (Normal Load Case, Considering Frictional Load Case)
Page 76 of 97
Load/Case Case I Case II Case III Case IV
V (T) 836.999 976.29 1108.57 1108.57
ML (T - m) 819.61 178.87 673.49 90.51
MT (T - m) 2.86 16.79 16.79 656.49
HL (T) 146.05 31.84 203.08 16.09
HT (T) 1.683 1.68 1.68 198.78
ZL = 18.000 m3
ZT1 = 36.000 m3 ZT2 = 72 m3
Page 77 of 97
Length of Pile above Scour Level, L1 1.307 m
Depth of Fixity 7.980 m
RL at Depth of Fixity 42.063 m
Hence we take the pile length 16.000 m
Keep Founding Level at 34.043 m
Pmax = 210.722 T
Pmin = 46.628 T
Ultimate Horizontal Load Per Pile = 29.883 T
(B)Section Property
Diameter of Pile Section (D) = 1200 mm
Clear cover = 75 mm
Diameter of Outer Links = 12 mm
Diameter of main vertical R/F outer layer = 25 mm
Moment per tonne Horizontal load = 3.81 t-m/t (from soil report)
Effective Cover (d') = (75 + 12 + 25 / 2) = 99.5 mm
d'/D = 99.5 / 1200 = 0.083 mm
Page 78 of 97
From Chart- 60 of SP: 16 - 1980, which corresponds to Fe - 500 grade of Reinforcement
p/fck = 0.02
p = 0.7 %
Therefore; Asc = ( π / 4 x 1200^2x0.7%) = 7916.813487 mm2
Let us provide
In Layer-I 24 nos. 25 mm diameter bars as main R/F in outer layer
Page 79 of 97
DESIGN OF PIER AND FOUNDATION
BRIDGE NO. 312A
PIER NO. Platform-P3
SPAN ARRANGEMENT:- 2 x 20.43 m
1.0 INTRODUCTION
The system consists of a solid rectangular Pier The top dimensions of the Pier cap are fixed so as to fit in the details of PSC Slab
superstucture.
2.0 REFERENCE
For the design of the pier and its different components generally the provisions of IRS(Indian Railway
Standards) Codes have been followed. Followings are the main references.
Seismic Zone V R= 3
Z = 0.36 Z/2R = 0.06
Importance Factor = 1.5 Sa/g = 2.5
4.1 Span 1
Effective span between c/c of bearing 21.145 m
Overall span 21.705 m
Span between c/c of Expansion Joints 21.845 m
Page 80 of 97
5.0 SKETCHES
Rail Formation Level=
57.903 m
0.500 1.650m
0.500 55.190 m
1.065m
2.018m 5.100m
ELEVATION
0.0
C/L of Pier /Pile Cap
8.000m
6.000m 4.935m
1.065m
PLAN
Page 81 of 97
6.0 DEAD LOAD CALCULATION
Anticlockwise Moments are taken as positive
+ -
Effective Longitudinal Moment due to DL about C/L of pier = 134.845 x 0.35 - 91.384 x 0.35 = 15.211 T-m
Effective Longitudinal Moment due to DL about C/L of Pile cap = 134.845 x 0.35 - 91.384 x 0.35 = 15.211 T-m
The Superstructure is symmetric about Centre Line of Soffit; therefore there is no Transverse Eccentricty
Transverse Eccentricity of Reaction, eT = 0.010 m
Transverse Moment due to DL = 226.229 x 0.01 = 2.262 T-m
Longitudinal Moment due to SIDL about C/L of Pier = 21.37 x 0.35 - 14.35 x 0.35 = 2.457 T-m
Longitudinal Moment due to SIDL about C/L of Pile cap = 21.37 x 0.35 - 14.35 x 0.35 = 2.457 T-m
The Superstructure is symmetric about Centre Line of Soffit; therefore there is no Transverse Eccentricty
Transverse Eccentricity of Reaction, eT = 0.010 m
Transverse Moment due to SIDL = 35.712 x 0.01 = 0.357 T-m
Page 82 of 97
6.3 Dead Load from pier Cap
Uniform portion
Length of bed block = 8.000 m
Width of bed block = 1.650 m
Depth of bed block = 0.500 m 1.650 0.500m
0.500
Tappered portion
Length of bed block at top = 8.00 m
Length of bed block at bottom = 6.000 m
Depth of bed block = 0.500 m 1.065m
Width of bed block at top = 1.650 m
Width of bed block at bottom = 1.065 m
Dead Load of Seismic Retainer Blocks = 0.690 x 0.910 x 1.065 x 2.5 x 2 = 5.929 T
= 5.929 T
6.000m
Page 83 of 97
Total cross sectional area of pier section = 6.147 m2
Volume of Pier Shaft = 3.647 x 6.147 = 22.417 m3
Dead Load of Pier Shaft = 22.417 x 2.5 = 56.050 T
Longitudinal Eccentricity w.r.t. C/L of Pile Cap, eL = 0.000 m
Longitudinal Moment about C/L of Pile Cap = 56.05 x 0 = 0.000 T-m
5.100m
8.000m
Traffic Direction
PLAN OF PILE CAP
Effective Longitudinal Moment due to Pedestrian load about C/L of Pier = 54.513 x 0.35 - 36.6 x 0.35 = 6.27 T-m
Effective Longitudinal Moment due to Pedestrian Load about C/L of Pile cap = 54.513 x 0.35 - 36.6 x 0.35 = 6.27 T-m
There is an eccentricity between the c/l of Platform and the c/l of Pier
Transverse Eccentricity of Reaction, eT = 0.02 m
Transverse Moment due to Pedestrian live load = 1.822 T-m
The tolerancess for finished concrete bridge structures is due to mainly deviation from plumb or specified, batter for face
of exposed piers as per IRS concrete bridge code Cl. No-6.5
The deviation is 1 in 250, subjected to a maximum value of 0.05 times the least lateral dimension of pier.
Load calculation for P1
Height of Pier : = 3.647 m
Thickness of Pier = 1.065 m
Length of Pier Cap = 8.000 m
Width of Pier Cap = 1.065 m
Thickness of Pier Cap = 0.600 m
Unit weight of Concrete = 2.5 T/m3
Page 84 of 97
Shift in top level of Pile due to construction tolerance = 3.647/250 = 0.01459 m
At Pier frictional resistance arised from both span will act in opposite direction with equal magnitude and nullify each other.
Transverse direction
(Note : Seismic Force will act at Top of Bed Block)
Lever Arm w.r.t. Base of Pier = 56.9465 - 51.543 = 4.447 m
Lever Arm w.r.t. Bottom of Pile Cap = 56.9465 - 50.043 = 5.947 m
Moment about Base of pier = 50.902 x 4.447 = 226.361 T-m
Moment about Bottom of Pile Cap = 50.902 x 5.947 = 302.714 T-m
Page 85 of 97
Transverse direction
(Note : Seismic Force will act at Top of Bed Block)
Lever Arm w.r.t. Base of Pier = = 4.447 m
Lever Arm w.r.t. Bottom of Pile Cap = = 5.947 m
Moment about Base of Pier = 8.035 x 4.447 = 35.732 T-m
Moment about Bottom of Pile Cap = 8.035 x 5.947 = 47.784 T-m
12 ON PIER CAP
[b] Pedestals
Horizontal Seismic Force = 0.225 x 1.412 = 0.318 T
Distance of C.G. from top of Pier Cap = 0.171 / 2.0 = 0.086 m
Lever Arm w.r.t. Base of Pier = 55.69 + 0.5 - 51.543 = 4.233 m
Lever Arm w.r.t. Bottom of Pile Cap = 55.69 + 0.086 - 50.043 = 5.733 m
13 ON PIER WALL
Horizontal Seismic Force = 0.225 x 56.05 = 12.611 T
Level of C. G. of Pier (RL) = ( 55.19 + 51.543 ) / 2.0 = 53.3665 m
Lever Arm w.r.t. Pier Base = 53.3665 - 51.543 = 1.8235 m
Lever Arm w.r.t to Bottom of Pile Cap = 53.3665 - 50.043 = 3.324 m
Moment about Base of Pier = 12.611 x 1.824 = 23.00 T-m
Moment about Bottom of Pile Cap = 12.611 x 3.324 = 41.919 T-m
14 ON PILE CAP
Horizontal Seismic Force = 0.225 x 153 34.425 T
Level of C. G. of Pile Cap (RL) = ( 50.043 + 51.543 ) / 2 = 50.793 m
Lever Arm w.r.t to Bottom of Pile Cap = 50.793 - 50.043 = 0.750 m
Moment about Bottom of Pile Cap = 34.425 x 0.75 = 25.819 T-m
Page 86 of 97
16.0 SEISMIC FORCES IN VERTICAL DIRECTION DUE TO DEAD LOADS
Seismic Force on pier due to Dead Loads in Vertical Direction
= 78.251 x 0.151 / 0.225 = 52.516 T
Seismic Force on Pile Cap due to Dead Loads in Vertical Direction
= 112.676 x 0.151 / 0.225 = 75.618 T
Page 87 of 97
Transverse Moment (MT) =
= 1.0 x ( 0.17 + 2.262) + 1.2 x (0.357 ) = 2.860 T-m
Horizontal Load in Longitudinal Direction (HL) =
= 1.0 x 3.029 + 1 x 0.0212 = 3.050 T
Horizontal Load in Transverse Direction (HT) = = 0.106 T
Page 88 of 97
Longitudinal Moment (ML) =
= 1.25 x ( 15.211 + 0+0 ) + 2.0 x ( 2.457 ) + 1.4 x ( 6.27)+2x0.823 = 34.35 T-m
Transverse Moment (MT) =
= 1.4 x ( 1.822+0.17 ) + 1.25 x (2.262) + 1.5 x (0.357 ) = 6.2 T-m
Horizontal Load in Longitudinal Direction (HL) =
= 1.4 x ( 0 ) = 0.000 T
Horizontal Load in Transverse Direction (HT) = = 0T
Page 89 of 97
Longitudinal Moment (ML) =
= 1.0 x ( 0 + 0 + 0+0 ) + 1.0 x ( 17.105)+ 1.0 x ( 0.572)+1x0.823 = 18.50 T-m
Transverse Moment (MT) =
1x(2.86 ) + 1 x (2.262) + 1.2 x (0.357 ) = 5.550 T-m
Horizontal Load in Longitudinal Direction (HL) =
1.0 x (3.029 + 0.3366) = 3.366 T
Horizontal Load in Transverse Direction (HT) = = 1.683 T
Page 90 of 97
Longitudinal Moment (ML) =
= 1.25 x ( 0 + 0 + 0+0 )+2x(0)+ 1.75 x ( 6.27+0 ) + 2 x ( 0.572)+2x 0.823 = 13.76 T-m
Transverse Moment (MT) =
= 1.75 x (1.822+2.86 )+ 1.25 x 2.262 + 1.5 x 0.357 = 11.6 T-m
Horizontal Load in Longitudinal Direction (HL) =
1.75 x 0.3366 = 0.589 T
Horizontal Load in Transverse Direction (HT) = = 0T
Page 91 of 97
Design of Pile
PILE REACTION FOR A RECTANGULAR PILE CAP AND CHECK FOR PILE CAPACITY
Page 92 of 97
[D] Co-ordinate of Piles
Longitudinal Transverse C
Pile No Co-Ordinate o-Ordinate n xi2 yi2
xi (m) yi (m)
P1 1.800 3.000 1 3.24 9.00
P2 1.800 0.000 1 3.24 0.00
P3 1.800 -3.000 1 3.24 9.00
P4 -1.800 3.000 1 3.24 9.00
P5 -1.800 0.000 1 3.24 0.00
P6 -1.800 -3.000 1 3.24 9.00
Total ∑ 6 19.44 36.00
Y
3.6
1.00 P P
4 1 `
3.00
8.00
X P P X
5 2
3.00
P P
6 3
1.00
TRAFFIC DIRECTION
PLAN OF PILE CAP
[E] Summary of Loads and Moments at Center Line of Pile Cap Base
Page 93 of 97
Horizontal Load in Longitudinal Direction (HL) = 3.37 T
Page 94 of 97
ULTIMATE LOAD CONDITION
ZL = 10.800 m3
ZT1 = 12.000 m3
Page 95 of 97
ULTIMATE LOAD CONDITION
Pile Reaction Load Cases
(T) Case I Case II Case III Case IV
P1 113.32 138.841 151.362 182.097
P2 112.623 137.878 150.672 124.637
P3 112.623 137.878 150.672 124.637
P4 108.132 136.292 49.06 181.626
P5 107.434 135.329 48.371 124.166
P6 108.132 136.292 49.06 181.626
Max Value 140.463 165.984 178.505 209.24 Adding self weight of Pile
Min Value 107.434 135.329 48.371 124.166
HR (T) 0.841 0.098 22.619 28.59
Pmax = 209.24 T
Pmin = 48.371 T
Ultimate Horizontal Load Per Pile = 28.59 T
(B)Section Property
Diameter of Pile Section (D) = 1200 mm
Clear cover = 75 mm
Diameter of Outer Links = 12 mm
Diameter of main vertical R/F outer layer = 25 mm
Moment per tonne Horizontal load = 3.81 t-m/t (from soil report)
Effective Cover (d') = (75 + 12 + 25 / 2) = 99.5 mm
d'/D = 99.5 / 1200 = 0.083 mm
Page 96 of 97
Let us provide
In Layer-I 24 nos. 25 mm diameter bars as main R/F in outer layer
Page 97 of 97