Method Statement For Pipe Line Re-Routing
Method Statement For Pipe Line Re-Routing
Method Statement For Pipe Line Re-Routing
TABLE OF CONTENTS
1.0 PURPOSE: ..........................................................................................................................................3
2.0 SCOPE: ...............................................................................................................................................3
3.0 LOCATION: .........................................................................................................................................3
4.0 REFERENCES: ...................................................................................................................................3
5.0 RESPONSIBILITY ...............................................................................................................................2
6.0 MATERIALS/EQUIPMENT: ................................................................................................................4
7.0 WORK PERMITS ................................................................................................................................4
8.0 PROCEDURE ......................................................................................................................................3
9.0 HEALTH, SAFETY AND ENVIRONMENTAL ASSESSMENTS ........................................................5
10.0 QUALITY ASSURANCE AND CONTROL .........................................................................................6
11.0 JOB HAZARD ANALYSIS ..................................................................................................................6
Document Title
METHOD STATEMENT FOR RE-ROUTING Doc
4088-DESS-9-19-0002
OF DN 200 MM HDPE FIRE WATER No.
PIPELINE
Rev.: 00
Date: 29-05-2019
Page: 2 of 7
1.0 PURPOSE:
The purpose of this method statement is to define the methods adopted in re-routing of the DN 200
mm diameter HDPE Fire water Pipeline from the proposed new Secondary School in Dukhan
Township.
2.0 SCOPE:
This method statement presents the methodology to be implemented for the Site Survey works for
re-routing of the DN 200 mm HDPE fire water pipeline in Dukhan Township.
The scope of work to be carried out under this method statement is as follows:
Site survey shall be conducted for the existing fire pipeline areas
Scanning within the site boundary to identify location of exiting underground services shall be
done; same shall be informed to QP.
Interference for proposed area shall be checked.
Installation of new fire water pipeline.
All tie-in works, shutdown and cutting of the existing pipeline.
Removal of all scraps and waste material from the site.
Excavation, backfilling and compaction.
3.0 LOCATION:
Dukhan Township
4.0 REFERENCES:
IFC drawings
Qatar Construction Specification (QCS 2014)
5.0 RESPONSIBILITY
The primary responsibility of carrying out all the activities mentioned in this method statement rests
with the site in charge unless mentioned otherwise.
5.4 SURVEYOR
Will be responsible for survey of the whole project.
6.0 MATERIALS/EQUIPMENT:
Total station
Tripods.
Auto leveling machine
Leveling staff.
Underground Scanning machine.
Excavator.
Fork Lift
200 mm diameter HDPE pipes.
Tie-in accessories/fittings.
8.0 PROCEDURE
2. Perform a survey of existing and proposed 200 mm diameter PE 100, PN16 HDPE Fire Water
pipeline route to identify the existing Fire Water pipelines, Tie-in points, Blind off locations and
other nearby facilities at the site.
Before commencing any work it shall be ensured that all permits are valid until the completion of
activity.
Prior to the commencement of any activities, the workforce will receive an induction talk on the
Project site safety requirements. This induction talk will include both activity safety issues, as well
as general safety requirements.
Where possible hazards may arise from Laying of the Pipeline related activities, the necessary
safety measures will be taken to prevent accident or injury at all times. This may include barriers,
warning tape/ Net, signage, watchman, and proper lighting.
The Construction team will enforce that Personal Protective Equipment be worn by site personnel
at all times during construction activities.
Heat Stress Training will be provided.
Provisions of adequate cool drinking water, shade, and salt water tablets will be in place.
All equipment shall be provided with reverse horns.
Routine pipeline inspection will be done
Personal Protective Equipment (PPE) Requirement
Hard hat
Safety Shoes
Safety Eye glasses
Hand gloves
High visibility vest
Red, green flags
Document Title
METHOD STATEMENT FOR RE-ROUTING Doc
4088-DESS-9-19-0002
OF DN 200 MM HDPE FIRE WATER No.
PIPELINE
Rev.: 00
Date: 29-05-2019
Page: 2 of 7
The quality management plan is a controlled document and will be reviewed on a regular basis
and updated as required.
The Quality control plan will be developed by The QA QC in charge in collaboration with the
Project Manager. The plan is a controlled document and will be reviewed as required.