ID Task Mode Task Name Duration Start Finish: Project: & (PROPOSED RESIDEN For Leonard Mugaga Muk Date: Tue 12/12/17
ID Task Mode Task Name Duration Start Finish: Project: & (PROPOSED RESIDEN For Leonard Mugaga Muk Date: Tue 12/12/17
Mode Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
1 PROPOSED RESIDENTIAL HOUSE ON PLOT NO. 811, 308 days Mon 1/8/18 Tue 1/1/19
BLOCK NO. 395
2 PHASE 1 63 days Mon 1/8/18 Wed 3/21/18
3 Preliminaries 5 days Mon 1/8/18 Fri 1/12/18
4 Site Preparation 14 days Sat 1/13/18 Mon 1/29/18
5 Substructure 30 days Tue 1/30/18 Mon 3/5/18
6 Super structure (Ground to first) 30 days Thu 2/15/18 Wed 3/21/18
7 M&E first fix 2 days Mon 3/5/18 Tue 3/6/18
8 PHASE 2 55 days Thu 3/22/18 Thu 5/24/18
9 Super structure (First to roof) 30 days Thu 3/22/18 Wed 4/25/18
10 Walling 25 days Thu 4/26/18 Thu 5/24/18
11 Roofing and Ceiling 15 days Thu 4/26/18 Sat 5/12/18
12 PHASE 3 52 days Thu 4/26/18 Mon 6/25/18
13 Doors and Windows 14 days Thu 4/26/18 Fri 5/11/18
14 External wall finnishes 20 days Fri 5/25/18 Sat 6/16/18
15 Internal Wall finnishes 20 days Sat 6/2/18 Mon 6/25/18
16 PHASE 4 45 days Tue 6/26/18 Thu 8/16/18
17 Internal and External Floor Finnishes 21 days Tue 6/26/18 Thu 7/19/18
18 Doors and Windows 14 days Fri 7/20/18 Sat 8/4/18
19 Internal Plumbing (Main House) 14 days Wed 8/1/18 Thu 8/16/18
20 PHASE 5 68 days Fri 8/17/18 Sat 11/3/18
21 Internal Electricals (Main House) 21 days Fri 8/17/18 Mon 9/10/18
22 All works for Guest House 60 days Mon 8/27/18 Sat 11/3/18
23 PHASE 6 45 days Mon 11/5/18 Wed 12/26/18
24 Boundary Walling (1st Stage) 30 days Mon 11/5/18 Sat 12/8/18
25 Boundary Walling (2st Stage) 15 days Mon 12/10/18 Wed 12/26/18
26 PHASE 7 35 days Thu 11/22/18 Tue 1/1/19
27 Land Scaping 14 days Thu 11/22/18 Fri 12/7/18
28 External Plumbing 7 days Sat 12/8/18 Sat 12/15/18
29 External Electricals + CCTV 14 days Mon 12/17/18 Tue 1/1/19