12RE0517
12RE0517
QUESTION BANK
2. Following is the list of activities associated with the assembly of a space module for an
upcoming mission. Draw the network diagram for the project.
Activity Description Predecessor Act.
A Construct shell of module ---
B Order life support system and scientific experiment. ---
C Order components of control and navigation system ---
D Wire module A
E Assemble control and navigational system C
F Preliminary test of life support system B
G Install life support system in module D, F
H Install scientific experimentation package in module D, F
I Preliminary test of control and navigational system E, F
J Install control and navigational system in module H, I
K Final testing and debugging G, J
3. A new type of water pump is to be designed for an automobile. Major specifications are
given in the table. Draw the network diagram for the project.
Activity Description Predecessor Act.
A Drawing prepared and approved ---
B Cost analysis A
C Tool feasibility A
D Tool manufactured C
E Favorable cost B, C
F Raw materials procured D, E
G Sub – assemblies ordered E
H Sub – assemblies received G
I Parts manufactured D, F
J Final assembly I, H
K Testing and shipment K
9. Adjoining is a list and description of activities for a project XYZ building a boat. Draw the
network:
Activity Description Predecessor Act.
A Design hull None
B Prepare boot shed None
C Design Mmst and mast mount A
D Obtain hull A
E Design sails A
F Obtain mast mount C
G Obtain mast C
H Design rigging C
J Prepare hull B, D
K Fit mast mount to hull F, J
L Step Mast E, H, G, K
M Obtain Sails and Rigging E, H
N Fit sails and rigging L, M
12. An assembly is to be made from two parts X and Y. Both parts must be turned on a lathe
and Y must be polished whereas X need not be polished. The sequence of activities together
with their predecessors is given below.
14. Listed in the table are the activities and sequencing necessary for the completion of a
recruitment procedure for management trainees (MT) in a firm.
Activity Predecessor Act.
A ---
B A
C A
D C
E B
F C
G D,E
H G
I H
J F
K I,J
L K
M L
N J
O M,N
16. The following table gives the activities for buying a new car. Construct the project
network.
Activity Description Predecessor(s)
A Conduct feasibility study -----
B Find potential buyer for present car A
C List possible models A
D Research all possible models C
E Conduct interview with mechanic C
F Collect dealer propaganda C
G Compile pertinent data D,E,F
H Choose top three models G
I Test – drive all three choices H
J Gather warranty and financing data H
K Choose one car I,J
L Choose dealer K
M Search for desired color and options L
N Test-drive chosen model once again L
O Purchase new car B,M,N
2. For a small project of 12 activities, the details are given below. Draw the network
and find earliest occurrence time, latest occurrence time, critical activities and
project completion time:
Activity A B C D E F G H I J K L
Dependence --- --- --- B, A C E E D,F,H E IJ G
Duration(days) 9 4 7 8 7 5 10 8 6 9 10 2
3. A small project consists of seven activities for which the relevant data are given
below:
Activity Preceding activities Activity duration(days)
A ------ 4
B ------ 7
C ------ 6
D A, B 5
E A, C 7
F C, D, E 6
G C, D, E 5
Find the critical path and minimum time duration.
5. Draw network diagram from following activities and find critical path and total slack
of activities:
Job A B C D E F G H I J K
Time(Days) 13 8 10 9 11 10 8 6 7 14 18
Predecessor --- A B C B E D,F E H G, I J
6. The activities involved in Alpha Garment Manufacturing Company are listed with
their time estimates as in the following table.
Activity Description Immediate Duration
Predecessors(s) (days)
8. An architect has been awarded a contract to prepare plans for an urban renewal project. The
job consists of the following activities and their estimated times:
Activity Description Predecessors Time(days)
A Prepare preliminary sketches --- 2
B Outline specifications --- 1
C Prepare drawings A 3
D Write specifications A, B 2
E Run off ‘prints’ C, D 1
F Have specifications B, D 3
G Assemble bid packages E, F 1
(i) Draw an arrow diagram for this project.
(ii) Indicate the critical path, and calculate the total float and free float for each activity.
9. The NRB Company is planning to design, develop and market a new racing cycle. The project is
composed of the following activities:
Activity Description Precedence Duration(weeks)
A Design frame None 4
B Design wheels None 3
C Design gears None 3
D Design handlebars C 2
E Test steering A, B, D 1
F Test gears A, B, D 2
G Performance test E, F 3
H Manufacturing layout A, B, D 3
I Manufacturing demonstrators H 5
J Prepare advertising G 2
K Prepare user’s manuals G 4
L Distribute to dealers I, J, K 2
Construct the network, determine the critical path and the duration of the above project.
Predecessor(s) (months)
A ---- 2
B ---- 6
C ---- 4
D B 3
E A 6
F A 8
G B 3
H C,D 7
I C,D 2
J E 5
K F,G,H 4
L F,G,H 3
M I 13
N J,K 7
(a) Construct the CPM network.
(b) Determine the critical path and project completion time.
(c) Compute total floats and free floats for non-critical activities.
14.
Activity Description(weeks) Immediate
Predecessors
A 14 -------
B 4 A
C 2 B
D 1 C
E 2 A
F 3 E
G 2 E
H 4 E
I 3 H,L
J 12 K
K 4 D,F,G
L 2 J
M 2 H,L
15. XYZ Ltd. Planning a project to introduce a new product, has listed the following
necessary activities:
Activity Preceding activity Expected time(weeks)
A --- 6
B --- 3
C A 5
D A 4
E A 3
F C 3
G D 5
H B,D,E 5
I H 2
J I,G,F 3
Draw the critical path network for the project and determine the critical path and its
duration.
3. A construction company is preparing a PERT network for laying the foundation of a new art
Museum. Given the following set of activities, their predecessor requirements and three time
estimates of completion time:
Activity Predecessors Time estimates (weeks)
Optimistic Pessimistic Most likely
A None 2 4 3
B None 8 8 8
C A 7 11 9
D B 6 6 6
E C 9 11 10
F C 10 18 14
G C, D 11 11 11
H F, G 6 14 10
I E 4 6 5
J I 3 5 4
K H 1 1 1
(i) Draw the PERT network.
(ii) Compute the slack for each activity and determine the critical path.
(iii) The contract specifies a Rs. 5,000 per week penalty for each week the completion of
the project extends beyond 37 weeks. What is the probability that this company will
have to pay a maximum penalty of Rs. 15,000 ?
5. A project consists of activities A, B, C, D, …, H, I. The notation X < Y means that the activity X
must be completed before Y can start and X, Y < W means that W will start only after
completion of the activities X and Y. With this notation:
(i) Construct the network diagram for the following constraints: