Activity 1. Formworks Columns at Grabe Beam 1 and 2

1. The document provides a schedule for concrete pouring and formwork delivery for Project I-Tower 3 located at 1129 Dos Castillas St. Sampaloc Manila. 2. The schedule includes dates for delivery and installation of formworks for columns, grade beams, STP tanks and fire tanks from May 26 to June 10. 3. Concrete pours are scheduled between May 29 to June 30 for columns, grade beams, STP tanks, fire tanks, tower crane foundation and ground floor slab requiring between 16 to 97 cubic meters of concrete per pour.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
76 views2 pages

Activity 1. Formworks Columns at Grabe Beam 1 and 2

1. The document provides a schedule for concrete pouring and formwork delivery for Project I-Tower 3 located at 1129 Dos Castillas St. Sampaloc Manila. 2. The schedule includes dates for delivery and installation of formworks for columns, grade beams, STP tanks and fire tanks from May 26 to June 10. 3. Concrete pours are scheduled between May 29 to June 30 for columns, grade beams, STP tanks, fire tanks, tower crane foundation and ground floor slab requiring between 16 to 97 cubic meters of concrete per pour.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

PROJECT : I - TOWER 3

LOCATION : 1129 DOS CASTILLAS ST. SAMPALOC MANILA


OWNER : COMMUNITY SUITES REALTY DEVELOPMENT CORP.
DATE : MAY 20, 2019
SUBJECT : SCHEDULE OF CONCRETE POURING AND FORMWORKS DELIVERY
(BASED ON ACTUAL SITE CONDITION)

ITEMS/QTY
ACTIVITY TO DELIVER
START DATE FINISH DATE DELIVERY DATE
1. FORMWORKS
COLUMNS AT GRABE BEAM 1 AND 2
3/4" PHENOLIC BOARD- 20 PCS
ALUMA BEAM(2.4m)- 50
ALUMA BEAM(1.2m)- 24
TIE ROD(3m)- 8 PCS
WING NUT(16 mm DIA)- 180
GI PIPE (6)-30
SWIVEL CLAMP-100 PCS
26-May 29-May 25-May BASE JACK - 20
PE PIPE - 1 ROLL
DUCT TAPE 2" - 1
WELDING ROD (6011) - 3KLS
STRUCTURAL STYRO - 5 PCS
STAIR LADDER- 15 PCS
FLAT FORM - 15 PCS
ACROPOST (4m) -15

3/4" PHENOLIC BOARD- 20 PCS


JOINT PIN- 120
ALUMA BEAM(2.4)- 40
ALUMA BEAM (1.2)- 20
TIE ROD (16 mmDIA x 3m) - 14
WING NUT (16 mmDIA) -240
26-May SWIVEL CLAMP -120
ACROPOST (4m) -20
STRUCTURAL STYRO - 8 PCS
BASE JACK - 20
GI PIPE- 50

3/4" PHENOLIC BOARD- 20 PCS


ALUMA BEAM(2.4m)- 50
27-May ALUMA BEAM(1.2m)- 30
ACROPOST (4m) -20

28-May
GRADE BEAMS

3/4" PHENOLIC BOARD - 10


STRUCTURAL STYRO- 7
ACROPOST- 25
U-HEAD - 30
BASE JACK-41
STRAIR LADDER- 12
1-Jun 7-Jun 6-Jun FLATFORM - 12
JOINT PIN - 100
TIE ROD (3m)-4
WING NUT - 40
SWIVEL CLAMP - 100
GI PIPE (6) - 50

3/4" PHENOLIC BOARD - 10


STRUCTURAL STYRO- 7
ACROPOST- 25
U-HEAD - 30
BASE JACK-41
STRAIR LADDER- 12
FLATFORM - 12
JOINT PIN - 100
TIE ROD (3m)-4
WING NUT - 40
SWIVEL CLAMP - 100
GI PIPE (6) - 50

STP AND FIRETANKS ( FIRST LIFT) 4-Jun 10-Jun


STP AND FIRETANKS ( SECOND LIFT) 9-Jun 10-Jun
GROUND FLOOR SLAB 22-Jun 28-Jun
2. CONCRETE POURING DELIVERY DATE VOLUME cu.m. REQUIRED STRENGTH
COLUMNS AT GRABE BEAM 1 AND 2 29-May 29-May 29-May 16 cu.m. 7000 psi
GRADE BEAMS 7-Jun 7-Jun 7-Jun 23 cu.m. 7000 psi
STP AND FIRETANKS ( FIRST LIFT) 7-Jun 7-Jun 7-Jun 97 cu.m. 5000 psi
STP AND FIRETANKS ( SECOND LIFT) 10-Jun 10-Jun 10-Jun 64 cu. m. 5000 psi
TOWER CRANE FOUNDATION 14-Jun 14-Jun 14-Jun 81 cu.m. 5000 psi
GROUND FLOOR SLAB 30-Jun 30-Jun 30-Jun 21 cu.m 5000 psi