Common Facilities STR
Common Facilities STR
Common Facilities STR
SUB HEAD :-
STRUCTURAL DRAWINGS
CONSULTANT:
GENERAL NOTES
1. BUILDING DESCRIPTION & DESIGN 8 CONC. PROTECTION & LAPS TO STEEL
a. MIN. COVER TO BARS SHALL BE AS UNLESS GIVEN ON DRAWINGS
16. HOOKED BAR EMBEDMENT
a. BUILDING IS 1 STOREY. DESIGNED AS FRAME STRUCTURE.
b. LAPS IN COLUMNS BE PREFFERED AT MID ( COMP. ZONE). LAP BE THE FOLLOWING EMBEDMENT LENGTHS SHALL BE
FOR ZONE -2B
AS TENSION SPLICE UBC 1997, ACI 2005 & B. CODE OF PAK. CONSIDERED FOR ALL HOOKED BARS WITH STANDARD HOOKS,
LAP 55 DIA
b- DESIGN OF STRUCTURE IS BASED ON PAKISTAN BUILDING CODE SP 2007. = fy' / 65 fc' UNLESS OTHERWISE SPECIFIED.
MID
(S.P- 2007) , ACI 318-2005 AND UBC 97. fy' = YIELD STRENGHT OF STEEL , fc' = CONC STRENGTH
Bar No. #3 #4 #5 #6 #7 #8
c- BEARING CAPACITY OF SOIL IS 0.30 T/SFT FOR RAFT FOUNDATION
Bar Dia (inches) 3/8 1/2 5/8 3/4 7/8 1
STRUCTURAL MEMBER COVER LAP TO BARS
Lap Length (inch) 9 9 10 12 13 15
2. BUILDING LAYOUT FOUNDATIONS 3" TO PCC GRADE -60 STEEL
H
a. BUILDING LAYOUT BE DONE WRT TO STRUCTURAL DRAWINGS SLABS , RCC WALLS 3/4" 55 DIA 17. ACCESSORIES
AND ARCH DRAWINGS COLUMNS & BEAMS 1.5"
a. BAR SUPPORTS , SPACERS & AND OTHER ACCESSORIES ARE
b. ANY DIFFERENCE BE DISCUSSED WITH STR. DESIGNER. NOT SHOWN IN DRAWINGS.
b. THE BAR SUPPORTS BE PROVIDES AS APPROVED
9. FORMWORK & REMOVEL BY ENGINEER
3. EXCAVATION AND TERMITE TREATMENT a. FORMWORK TO CONCRETE SHALL BE OF METAL SHEETS c. SUPPORTS TO BARS BE SUFFICIENT & STRONG
a. FOUNDATIONS TO BE PLACED ON COMPACTED SOIL OR PLY WOOD. SUCH THAT THE STEEL REMAIN IN POSITION
b. THE FORMWORK BE DONE AS PER STRUCTURAL FORMS DURING CONCRETING.
b. IN CASE OF FILL / OVERBURDEN REMOVE IT. c. FORMWORK BE WATER TIGHT.
c. IN CASE OF RAISED PLINTH, FILL WITH SAND / GRAVEL & d. FORMWORK BE REMOVED AS PER FOLLOWING SCHEDULE
COMPCAT BEFORE FLOORING. COLUMNS & SIDE OF BEAMS & WALLS 24 HOURS 18. BAR BENDING & HOOKS
SLAB, BOTTOM OF BEAMS 14 DAYS.
d. PROVIDE TERMITE TREATMENT IN FOUNDATIONS AND IN FLOOR
BEFORE LAYING PCC.
db
10. JOINTS
db
4db
4. W:C:S: AGGREGATES AND SIZES a. EXPANSION JOINTS BE FINALIZED AND GOT APPROVED 8db
BY THE RESIDENT ENGINEER.
12db
FRESH WATER: IN ACCORDANCE OF UBC 97 SECTION 1903.4 4db 4db
CEMENT: FRESH PORTLAND CEMENT TO BE USED FOR ALL WORKS. b. EXPANSION JOINT IN THE BUILDING BE PROVIDED AS SHOWN 2.5 in (mm)
ON THE DRAWIGS. 4db
SAND : LAWRANCEPUR / GHAZI.
AGGREGATES:IN ACCORDANCE OF UBC 97 SECTION 1903.3
11. STEEL BINDING (PRIMARY REINF.) (PRIMARY REINF.)
MARGALLA STONE CRUSHED AGGREGATES SHALL BE AS: a. STEEL BARS BE PLACED IN THE FORM AS PER DRAWINGS.
STRUCTURAL ELEMENTS MAXIMUM AGGREGATE SIZE b. ALL JUNCTION OF THE BARS / CROSS BE TIED WITH BINDING
H
WIRE. 2-#6
FOUNDATIONS 1.25 " DOWN GRADED
LAP 55 DIA
MID
COLUMNS & BEAMS 3/4 DOWN GRADED 12. DRAIN PIPES & SLEEVES
10
SLABS 3/4" DOWN GRADED
db
TYP. DETAIL OF RCC
a. TOILET WASHING & DRAIN PIPES BE PLACED IN SLAB AT PROPER 2-#6 2-#6 RETAINING WALL
3/4" DOWN GRADED MEANS 1/2" AND 3/8" MIX DESIGNED POSITION BEFORE CONCRETE.
1D=4db
b. WHERE PLUMBING AND OTHER PIPES ARE PLACES IN SLAB
ADDITIONAL STEEL BARS BE PROVIDED ABOVE AND BELOW db
DUCT OPEN
a. DESIGN OF STRUCTURE IS BASED ON STEEL DEFORMED 13. WALL TIES (STIRRUPS & TIE REINF.) TYP DUCT OPENING DETAIL
MAIN STEEL FOR ASTM A 706 a. WALL TIES OF #3 (10MM) BARS BE PLACED IN COLUMNS AS
FOUNDATION, COLUMNS, BEAMS, SLABS GRADE - 40 WALL TIES AT 2' CC TO ANCHOR THE WALLS
BEAMS > 30'-0" SPAN ARE DESIGNED AS GRADE - 60
14. BRICK , CONC BLOCK MASONRY
b. SAMPLES OF STEEL BE GOT TESTED BEFORE USE.
a. FIRST CLASS BRICKS BE USED FOR MASONRY WORK.
b. BRICKS BE SOACKED IN WATER A DAY BEFORE USE.
c. CONCRETE BLOCKS BE MOISED JUST BEFORE USE. RAFT
6 CONC. MIXING & PLACING d. JOINTS BE 3/8" FILLED WITH CEMENT SAND MORTAR.
e. ALL MORTAR BE MACHINE MIXED. TYP COL. ELE.
a. CONCRETE BE WELL MIXED, VIBRATED, COMPACTED , CURED,
TESTED AND RECORD TO BE MAINTAINED AS PER f. MORTAR FOR WALLS 8" , 9" SHALL BE 1:5
ACI 318 AND UBC 1997 CHAPTER 19 FOR 4" & 4.5" SHALL BE 1:4
g. ALL INTERNAL PARTITIONS 4.5" BRICKS / 6" HOLLOW BLOCKS /
b. MIXED CONCRETE BE PLACED IN POSITION WITHIN 15 MINUTES WOODEN PARTITION OUTER 8" HOLLOW / 9" BRICKS OR 12" CAVITY WALLS.
c. MIN WATER IN CONC. GIVES MORE STRENGHT. h. ALL ABOVE ITEM TO BE EXECUTED ,TESTED AND MAITAINED IN ACCORDANCE
OF UBC 1997 CODE STANDARD CHAPTER 21.
d. TRY 5 TO 6 GALLONS OF WATER / BAG OF CEMENT
e. MIXING TIME OF CONCRETE PER BATCH 1.5 MINUTES AFTER 15. STEEL BAR SPACING
ADDING WATER.
a. FIRST & LAST BAR IN WALLS & SLAB BE PLACED AT 1/2 OF
THE SPACING OF BARS.OR JUST GIVE COVER AND PLACE THE BAR
7 CONC. STRENGTHS b. FIRST AND THE LAST HOOP/TIE IN BEAMS & COLUMNS BE
a. CONCRETE BE TESTED AT IMPORTANT PLACES & STRENGTH BE AS BE PLACED AT 2" FROM THE SUPPORT.
FOUND. WALLS, BEAMS, SLAB 3000 PSI 28 DAYS CYLINDER STRENGTH c. COLUMN TIES TO BE PROVIDED THROUNGHOUT FROM
COLUMNS MIN 1:1.5:3 4000 PSI 28 DAYS CYLINDER STRENGTH FOUNDATION TO TOP.
COL. HOOPS
Y Y
#3@12"c/c LB
#4 dowel bars @ 18"c/c
BRICK/BLOCK MASONRY Column ties are
necessary in
this region INTERIOR BEAM HOOPS
2#4
DETAIL OF COLUMN WALL TIE DETAIL OF WINDOW
PROJECTION
PLAN SECTION
BEAM TOP BARS TYPICAL SEISMIC-RESISTANT JOINT DETAILS
SECTION AT X-X
PRIMARY BEAM
BEAM HOOPS
1 1/2" CL.
TO END OF HOOKS BEAM BARS
COLUMN HOOPS
ON BEAM BARS
1 1/2" CL.
TO END OF HOOKS
M ON BEAM BARS
BEAM HOOPS
1. SHRINKAGE STRIPS MUST BE PROVIDED AT A SPACING OF 2#4
WATER
STOPPER
PARTITION WALL
OPEN OPEN
1 #3@36"C/C
3
(ANCHOR BAR) COLUMN
116'-1034"
6" 6"
18' 15'-1134" 15'-1134" 15'-1134" 15'-1134" 15'-1134" 18'
2'
2'
1'
BOTTOM #4@10"C/C
16'-6"
B
51'-712"
BOTTOM #4@10"C/C
16'-712"
TOP #4@10"C/C
2'-9"
A 2'-9" A
2'-9"
C
2'-9" 2'-9"
17'-6"
BOTTOM #4@10"C/C
TOP #4@10"C/C
1'
D
2'
2'
FOUNDATION LAYOUT PLAN
116'-1034"
6" 6"
18' 15'-1134" 15'-1134" 15'-1134" 15'-1134" 15'-1134" 18'
1'
C1 C1 C1 C1 C1 C1 C1 C1
A
17'-6"
B C1 C1 C1 C1 C1 C1 C1 C1
10'
10'
51'-712"
16'-712"
C1 C1 C1 C1
6'-712"
6'-712"
C C1 C1 C1 C1
17'-6"
18'-112"
17'-9"
C1 C1
C1 C1 C1 C1
9"
1'
1'
6" 8'-10" 9'-214" 9'-412" 1' 1' 9'-412" 9'-214" 8'-10" 6"
28'-1012" 28'-1012"
116'-1034"
6" 6"
18' 15'-1134" 15'-1134" 15'-1134" 15'-1134" 15'-1134" 18'
1'
PB-1 PB-1
10'
51'-712"
16'-712"
6'-712"
C
17'-6"
17'-6"
17'-6"
1'
1'
6" 8'-10" 9'-214" 9'-412" 1' 1' 9'-412" 9'-214" 8'-10" 6"
1 1
28'-10 " 2 28'-10 " 2
G.L
F.R.L F.R.L
SECTION AT A-A
3-#6 3-#6
#3@4"c/c #3@8"c/c
2'
9"
9"
16-#6
#3@6"CC
1'-3"
2'
12-#6
2'
1'-3"
3-#6 3-#6 1.5" COVER
EDGE MID
SECTION SECTION
P-B 1 9"
116'-1034"
6" 6"
18' 15'-1134" 15'-1134" 15'-1134" 15'-1134" 15'-1134" 18'
1'
B-1 B-1
B-1 B-1
B B-1 B-1 B-1 B-1 B-1 B-1
10'
10'
51'-712"
16'-712"
6'-712"
B-1 B-1
C
17'-6"
17'-6"
17'-6"
GROUND FLOOR
SLAB BEAMS KEY PLAN
1'
1'
6" 8'-10" 9'-214" 9'-412" 1' 1' 9'-412" 9'-214" 8'-10" 6"
1 1
28'-10 " 2 28'-10 " 2
L/3 L/3
5-#6 3-#6 5-#6
5-#6 3-#6
6"
#3@6"CC
#3@6"c/c #3@6"c/c
1'
5-#6 3-#6
0'-9"
B-1 X
1'-6" #3@7"c/c #3@7"c/c
4-#6 6-#6
116'-1034"
6" 6"
18' 15'-1134" 15'-1134" 15'-1134" 15'-1134" 15'-1134" 18'
1'
#4@6"c/c
#4@6"c/c
#4@6"c/c
#4@6"c/c
#4@6"c/c #4@6"c/c
17'-6"
#4@6"c/c
#4@6"c/c
#4@6"c/c
B
#4@6"c/c
#4@6"c/c #4@6"c/c
51'-712"
16'-712"
#4@6"c/c
#4@6"c/c
9"c/c
9"c/c
#4@
#4@
C
6"c/c
6"c/c
#4@
#4@
#4@6"c/c #4@6"c/c
17'-6"
#4@ #4@
#4@6"c/c
#4@6"c/c
9"c/c 9"c/c
1'
1'
6" 8'-10" 9'-214" 9'-412" 1' 1' 9'-412" 9'-214" 8'-10" 6"
1 1
28'-10 " 2 28'-10 "
2
116'-1034"
6" 6"
18' 15'-1134" 15'-1134" 15'-1134" 15'-1134" 15'-1134" 18'
1'
A
#4@6"c/c #4@6"c/c
4'
4'
4'
4'
17'-6"
#4@6"c/c #4@6"c/c
4'
4'
4'
4'
B
2'
2'
4'
4'
#4@6"c/c
#4@6"c/c
#4@6"c/c
#4@6"c/c
51'-712"
16'-712"
#4@6"c/c
2'
2'
4'
4'
C
4'
4'
#4@6"c/c #4@6"c/c
#4@6"c/c
#4@6"c/c
4' 4'
17'-6"
#4@6"c/c #4@6"c/c
4'
4'
1'
1'
6" 8'-10" 9'-214" 9'-412" 1' 1' 9'-412" 9'-214" 8'-10" 6"
1 1
28'-10 " 2 28'-10 " 2