1.3.1 Level 1 (Single Line) Barchart

This document outlines the procedures for planning, scheduling, progress measurement, and monitoring the engineering, procurement, construction, and commissioning of the topside for a drilling platform project. It defines key terms, assigns responsibilities, and describes the scheduling process from developing the initial schedule to regularly updating it to track progress. Attachments include organization charts, fabrication sequences, calendars, critical path networks, resource loading charts, and formats for progress measurement reporting. The overall aim is to provide an auditable method for meeting the mechanical completion deadline of February 28, 2014 for the topside scope of work.

Uploaded by

duy thanh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
456 views126 pages

1.3.1 Level 1 (Single Line) Barchart

This document outlines the procedures for planning, scheduling, progress measurement, and monitoring the engineering, procurement, construction, and commissioning of the topside for a drilling platform project. It defines key terms, assigns responsibilities, and describes the scheduling process from developing the initial schedule to regularly updating it to track progress. Attachments include organization charts, fabrication sequences, calendars, critical path networks, resource loading charts, and formats for progress measurement reporting. The overall aim is to provide an auditable method for meeting the mechanical completion deadline of February 28, 2014 for the topside scope of work.

Uploaded by

duy thanh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 126

1.3.

1 Level 1 (Single Line) Barchart


PLANNING PACKAGE PROCEDURE NO.:
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE

REVISION LIST

SECTION REV. DATE DESCRIPTION OF AMENDMENT


All sections 0 12 July 13 Issuance for Approval
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 1 OF 21

TABLE OF CONTENTS

SECTION DESCRIPTION PAGE

1. PURPOSE 2

2. SCOPE 2

3. REFERENCES 2

4. DEFINITIONS 2

5. PROCEDURE 4

5.1 Project Overview 4

5.2 General 5

5.3 Responsibility 5

5.4 Scheduling Procedure 6

5.5 Procedure for overall coordination of scheduling activities 10

5.6 Progress Measurement Procedure 12

5.7 Planning Implementation & Execution 19

6. SPECIAL REQUIREMENTS 21

7. RECORDS 21

ATTACHMENT

Attachment 1: Organization Chart


Attachment 2: Yard Layout and Fabrication Sequence
Attachment 3: Project’s Calendar and Report
Attachment 4: Critical Path Network (Topside)
Attachment 5: Overall Schedule (Topside)
Attachment 6: S-Curves (Topside)
Attachment 7: Manhour Histogram, Manpower resource loading &
Equipment resource loading (Topside)
Attachment 8: Progress Measurement Format
Attachment 9: Sub-contracting Plan
Attachment 10: Payment Schedule
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 2 OF 21

1. PURPOSE

This procedure is developed to provide an auditable and reliable method for planning,
measuring project progress and monitoring and updating project schedule of the WORK as
required by EPCC Contract of Diamond project.

2. SCOPE

Regarding to the planning and scheduling of EPCC scope of Diamond Drilling Platform,
EPCC Contractor will develop the planning package of Jacket and Topside. The planning
package for Jacket was issued in April 2013. The planning package for Topside is developed
in this procedure. The scope of this procedure covers all activities from the initial Contract
Award up to Start up of Diamond Topside. This procedure will be used as reference to all
parties involved in executing the project meeting the project MCD and Start-up date which is
stated in Exhibit II of the Contract. The scope of work shall cover “Engineering, Procurement,
Construction and Commissioning” of Diamond Topside for Diamond Drilling Platform
Development Project.

3. REFERENCES

CSP-02 Rev.1 ‘Progress Measurement Format’


CSP-04 Rev.4 ‘Project Specific Procedure Guidelines’
Contract Document as per contract No: PCV/DMDP-A/2012/616; EPCC FOR DMDP-
A-DRILLING PLATFORM.

4. DEFINITIONS

EPCC Engineering, Procurement, Construction and Commissioning


PCVL PC Vietnam Limited
PVC-MS Petroleum Equipment Assembly & Metal Structure JSC
MCD Mechanical Completion Date
MTO Material Take-Off
WQT Welder Qualification Test
WPS Welding Procedure Specification
CSB Contract Schedule Baseline: a series of schedule levels
developed from the Contract Schedule. These schedules will
range from Level 1 through Level 5. The progress and schedule
baseline is derived from the CSB. This baseline will remain in
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 3 OF 21

effect for the entire duration of the contract.


WBS A coding structure used to identify all levels of work elements.
This structure allows for roll up summarization from the lowest
levels to each and every higher level.

CPN (Critical Path A time related milestone and activity logic network that is
Network): developed with the Primavera.

Level 1 (Project A time scaled bar-chart indicating the major time blocks allocated
Master Schedule): to the major project contract packages. This schedule is
developed and controlled by PCVL Planner / Scheduler and will
not be revised without the approval of the PCVL Project Manager

Level 2 (Contract The Level 2 Contract Schedule is the link between PCVL’s and
Schedule) Contractor’s planning and scheduling. This level contains all key
activities and milestones.

Level 3 (Contract The Level 3 Contract Control Schedule is a breakdown of the


Control Schedule): Contract Schedule. A detailed level schedule which defines critical
path activities day-to-day basis. This schedule contains more
detail than the level 3 WBS.
Level 4 (Contract A detailed schedule used by the contractor to coordinate and
Detailed Schedule): manage its work. This schedule includes and identifies all
deliverable elements (e.g., CTRs, drawings / documents, each
piece of equipment, each spool, etc.)
Activity A single time consuming work step or task that has a recognizable
beginning and end.

Duration: The Time taken for an activity to complete its work or task in terms
of days.

Logic: The order or sequence in which activities are to be accomplished.

Network Analysis: Mathematical analysis of the network’s logic.

ES (Early Start): The earliest time an activity can possibly start.

EF (Early Finish): The earliest time an activity can finish starting from its ES and
completed within the specified duration.
LS (Late Start): The latest time an activity can start without delaying the scheduled
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 4 OF 21

completion.
TF (Total Float): The amount of time (in days) an activity can be delayed or
deferred without affecting the project scheduled completion date.
Critical Path: Activities that must be started and completed on their ES and EF
for the project to complete within the scheduled duration. These
are activities with total float of Zero day and they are on the
longest duration in the network.
Milestone: An event selected for its importance in the project; achievement of
the planned milestone dates is a key management indicator of
progress on the project.
5. PROCEDURE

5.1 Project Overview


The EPCC of Diamond Development Project (Jacket and Topside) was awarded to
PVC-MS on 4th February 2013 by PCVL.
Contract Information:

EPCC FOR TOPSIDE OF DMDP-A-DRILLING PLATFORM


Contract Award 4th February 2013
Contractual Fabrication duration 9 months
MCD of Topside 28th February 2014
Location PVC-MS Oil & Gas Fabrication Yard (VUNGTAU)
Load out Method Load out by Trailer and Load out beam
Total Direct Manhours 734,864 Mhrs
TOPSIDE MAJOR WORKS
Structure 1,686 T
Mechanical 458 T
Piping 39,000 diameter inch (estimated)
E&I 43,992 meter length (24,062m of Instrument and
19,930m of Electrical)
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 5 OF 21

5.2 General
The overall plan is generated based on agreed dates from various relevant department
i.e Engineering, Procurement, Contract, Construction, QA/QC and Pre-commissioning
Team.

The target plan for all activities are presented in the form of bar chart, S-curve and
critical network and support by histogram.

Once approved, this procedure will be issued to all relevant departments to follow. The
approved procedure will be a basis for developing progress measurement format,
milestone progress claims and all project progress reports.

5.3 Responsibility
The Project Planning Department is the custodian of this document and is responsible
for its review and reissue and for ensuring compliance with its contents.

It is responsibility of all distributed persons to ensure the most current revision of this
document is available at the work place and that the documents referenced in it are
applied to all aspects of the project.

This document will be subject to regular review and will be updated to reflect any
necessary changes.

The recipient of this document is responsible for distributing the procedure to other
parties working under his / her supervision to ensure the procedure is implemented by
all parties involved.

The Project Planning Engineer will report to the Planning Manager who is in turn
reports to the Project Manager. The Planning Manager is responsible for checking all
planning information prior to submitting to PCVL.

The Project Planning Engineer will be responsible for:

 Review and integration of all schedules submitted at the proposal or post


award stage of the project by the major groups operating within of for the
project.

 Issue of the Contract Schedule to all groups responsible for developing the
detailed schedule.
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 6 OF 21

 Producing Level 1 through Level 4 schedules, which give due consideration


to the Contractual Milestones dates, as part of the Contract Schedule
Baseline package.

 Reviewing the interfaces and dependencies between major project


components, ensuring that all planning aspects of the project from
engineering to commissioning, as defined by the contract requirement, are
satisfied.

 Ensuring that all approved milestone or network changes are incorporated


into the project plan.

 Co-ordination of any major schedule revision as may be required to suit


management or PMT directives.

 Update the actual progress of project against plan progress to support PMT
controlling and monitoring the project schedule.

5.4 Scheduling Procedure


Critical Path Network (CPN) technique is used for planning the project. A project
scheduling software, “PRIMAVERA”, is used for analyzing the network. Initially the
entire scope of work is divided into a number of activities and their inter-relationship is
determined. Activities are then broken down further or combined together to get the
optimum number which best shows the sequence of activities either serial or parallel
which need to be performed to complete the project. Based on similar past project, the
quantum of work involved and estimated man-hours are worked out for each activity.

CPN network is then drawn indicating the preceding activity (PA), the succeeding
activity (SA), the activity description (AD), the duration (DU) and the manpower
(resource).The network uses the precedence method of activity linking to establish the
project interdependencies across the major contributors.

The interdependencies will be based on the required hand over dates of such items as
drawings, materials or of physical access, collectively known as deliverables, which
allows the subsequent activities to continue within the project objectives. When it has
been proved that the defined interdependencies have been met within the individual
network sections of the project, the sections will be merged by activity constraint links
to form an integrated project network.

Through analysis of the integrated network, the critical path of the project will be
identified together with the total float on non-critical items. At the time of analysis all
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 7 OF 21

required project milestones will be imposed to ensure that the project targets are being
maintained.

The schedule is structured in accordance with the project WBS and all activities in the
CBS will be assigned a WBS code that will allow for roll up to each and every WBS
level. The planning system contains the following WBS levels:

 Level 1 Overall

 Level 2 Work Packs

 Level 3 Phases

 Level 4 Area / Section

 Level 5 Disciplines, Activities / Sub-activities

Level 2 Work Packs divides the scope of work into the following elements:

 WP01 – Item Common to the Entire Work

 WP02 – Topside DMDP-A

Each Work Pack is detailed by activity using the following activity codes:

 A – Project Key Milestone.

 B– Front-end Activity/ Mobilization.

 C – Engineering.

 D – Procurement.

 E – Onshore Fabrication.

 F – Testing& Pre-commissioning.

 I – Load out and Sea fastening.

 H- Hook up and Commissioning

Activities Codes assigned for all activities are in line with the requirements of PCVL
Specification for Work Breakdown Structure. Each activity will be assigned at least four
(4) activity codes such as WP (Work pack code), PHAS (Phase code), AREA (Area
code) and DISC (Discipline code). Base on these activity codes, Planning Engineer
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 8 OF 21

can easily identify and export all activities of the work scope and after that, the
progress will be updated for these activities base on the progress measurement
system. Finally, these activities will be imported back into the CSB. The CSB will be
resource loaded to allow the progress S-curves and progress information to be
generated by Primavera in line with the requirements of the Contract and Client
Planning and Progress Measurement Specification.

The Work activities shall be developed to the level 4 details, such that the activities
required to execute the work can be monitored on daily basis. The Level 4 schedule
shall clearly identify all the detailed activities along with all of the milestones in the
Contract. The detailed activities shall all be weighted. The Level 4 detailed network
shall also clearly identify and / or allow time for PCVL review activities. The activities in
respect of project management, supervision, planning administration and quality
assurance shall be shown as separate “hammock” activities without a specified
duration. Each activity in the network shall show as a minimum, the following:

 Activity number;
 Activity description;
 Planned activity duration taking into account holiday, facility shutdowns and
the like;
 Early / Late Start & Finish dates;
 Total float;
 Actual start, actual finish dates;
 Percent Complete.
The project calendar adopted shall be based on a normal working hours of eight (8)
hours per day and six (6) days per week, except that for Load out and Sea-fastening
24 hours per day and seven (7) calendar working days per week is adopted. All
approved public holidays and Sundays are observed as holidays in the project
calendar except for Load out and Sea-fastening. See attachment 3.
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 9 OF 21

Project planning to utilize industrial standard


Software

Develop planning network

Establish the project interdependencies across


the major contributes

Define interdependencies are within the


Individual network

The section to be merged by activity constraint,


link to form an integrated project network

Analysis of the integrated network

Identify the critical path of the project

Imposed all project milestones to ensure that


project targets are being maintained

Standard reports output from the system

Figure 1: Scheduling Procedure


PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 10 OF 21

5.5 Procedure for overall coordination of scheduling activities


At the proposal stage, planning team gets all information regarding to the Contractor’s
current utilization of resources, PCVL’s requirement in the issued ITB and other
technical clarifications to develop level 2 contract schedule. This schedule is as
baseline for developing working schedule in implementation stage.
After contract is awarded the level 3 working schedule will be developed for all parties
to follow. The first target CSB Level 3 plan shall be circulated to all departments
including Construction, Contract, Engineering, Procurement and Quality Control. An
interdepartmental review meeting shall be held and comments from these departments
shall be incorporated. Once agreed internally, the plan (i.e. Revision A) shall be
submitted to PCVL for their review, comments and approval.
The comments from PCVL shall be incorporated into the target CSB Level 3 plan and
issued as part of the CSB Package Revision 0. After approval from PCVL, that target
plan shall be distributed to all internal departments to follow.
The approved CSB Level 3 plan form the basis for the progress reporting for the
project. From this target plan, all derivative outputs like bar chart, S-curve, Manpower
histogram and activity listing with dates shall be generated. Contractor shall evaluate,
update and forecast the progress of the Work no less frequently than weekly.
The Planning Manager is responsible to the Project Manager for overall coordination
of scheduling activities

See attachment 1, 2, 4 and 5.


PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 11 OF 21

Project Director/
Proposal Group Project Planning
Manager
Proposal group to Project planning to
Contributing groups
distribute all proposal issue the contract
will (each) generate a
document to all level 2 schedule to
schedule to maintain
contributing each operating
the project requirement
groups group
Ability and commitment
Level 2 schedule
schedule

Project planning to Operating groups


amalgamate the to produce the level
individual schedule 3 schedule

Level 3 working
Individual schedule
schedule
Update the schedule if Operating groups
required to issue an
information list

Information list
Operating groups to revise
following project requirements Operating groups
to submit their
schedule to project
planning for
integration
No Yes Project manager
to authorize a
compromise or
corrective action
Level 2:
- Application
- Usability
- Timing
Submit Level 3:
integrated - Application
schedule to - Usability
PCVL - Timing

Figure 2: Procedure for Coordination of Scheduling Activities


PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 12 OF 21

5.6 Progress Measurement Procedure


The percent weightage distribution has been determined with a fixed weighted value
for Level 1 through Level 3 planning activities based on previous experience of PCVL
and the CONTRACTOR.

It is understood that the weightage distribution will be used for the Diamond project
only. It has been discussed and agreed before applying. The CONTRACTOR shall use
the weightage given to develop Progress Measurement Format which is a basis for
identifying, planning and monitoring the actual work progress. See attachment 8 –
Progress Measurement Format.

The activities description and weightage assigned for identifying, planning and
monitoring the work progress is divided into three (3) parts:

 Weightage for Level 1 Activities


 Weightage for Level 2 Activities
 Weightage for Level 3 Activities
The overall detailed breakdown for the weightage assigned for each task or
activity to complete the Project shall be developed by the Planning Department
based on this format and submitted as part of the Project's Planning Package for
PCVL's approval.

5.6.1 Weightage for overall EPCC of Diamond Drilling Platform


The weightage assigned for the Jacket EPCC and Topside EPCC are in accordance
with their Contract’s value as follow:
Topside
1 Jacket EPCC 21.00%
2 Topside EPCC 79.00%
100.00%
5.6.2 Weightage for Level 1 Activities
The weightage assigned for EPCC of Topside are further broken down to one
common set of Level 1 activities according to the major categories or discipline as
shown below:
Topside
1 Engineering 6.00%
2 Procurement 40.00%
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 13 OF 21

3 Construction 43.00%
4 Hook up and
11.00%
Commissioning
100.00%
Note: The weightage of Engineering, Procurement, Fabrication and Hock up &
Commissioning (HUC) are in accordance with their Contract’s value.

5.6.3 Weightage for Level 2 Activities


Level 2 activities give a detailed breakdown of Level 1 components. Weightages are
assigned in accordance with the quantity of work required for that activity:
5.6.3.1 Weightage Assignment for Engineering.
Engineering activities are sub-grouped as Detailed Engineering, and Construction
Engineering with the weightage assigned as follows:
Topside
1 Detailed Engineering 50.00%
2 Construction Engineering 50.00%
100.00%
5.6.3.2 Weightage Assignment for Procurement
For material procurement, the weightage adopted at Level 2 will essentially be
based on the estimated man-hours for the various tasks/activities such as bidding,
evaluation, meetings, expediting, inspection receipt and acceptance to complete
the identified procurement process, i.e. Issued RFQ, Issued P.O. Material Receipt
and Acceptance, etc.. The weightage assigned are sub-grouped into two (2)
categories:
Topside
1 PCVL Supplied Materials 19.00%
2 PVCMS Supplied Materials 81.00%
100.00%

5.6.3.3 Weightage Assignment for Construction.


The fabrication Weightage adopted are broken down into the following sub-groups:

Topside
1 Front end activities and 20.00%
mobilization
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 14 OF 21

2 Onshore Fabrication 64.00%

3 Testing an Pre- 7.00%


commissioning
4 Load out and Sea- 9.00%
fastening
100.00%

5.6.3.4 Weightage Assignment for Hook up & Commissioning.


The fabrication Weightage adopted are broken down into the following sub-groups:

Topside
1 Onshore Preparation 15.00%
2 Offshore Hook up and 80.00%
Commissioning
3 Final documentation 5.00%

100.00%
5.6.4 Weightage for Level 3 Activities
Level 3 activities give a detailed breakdown of Level 2 components. Weightages are
assigned in accordance with the quantity of work required for that activity:
5.6.4.1 Weightage Assignment for Engineering.
Engineering level 3 activities are sub-grouped as AFC, Post-AFC, shop drawings,
material take-off (MTO) and procedures with the weightage assigned as follows:
Topside
1. Detail Engineering 50.00%
1.1 AFC 70.00%
1.2 Post - AFC 30.00%
2. Construction Engineering 50.00%
2.1 Shop Drawings 83.00%
i) Structural 32.00%
ii) Piping/Plumbing
28.00%
Mechanical
iii) Electrical 9.00%
iv) Instrument 10.00%
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 15 OF 21

v) HVAC/Ducting 2.00%
vi) Architectural 2.00%
2.2 Material Take-Off (MTO) 13.00%
i) Structural 2.00%
ii) Piping/Plumbing 2.00%
iii) Mechanical 2.00%
iv) Electrical 2.00%
v) Instrument 2.00%
vi) HVAC/Ducting 1.00%
vii) Architectural 1.00%
viii) Others (Paint, etc.) 1.00%
2.3 Procedures 4.00%
i) Procedures 4.00%

100.00%
5.6.4.2 Weightage Assignment for Procurement
For material procurement, the weightage adopted at Level 3 will essentially be
based on the estimated man-hours for the various tasks/activities such as bidding,
evaluation, meetings, expediting, inspection receipt and acceptance to complete
the identified procurement process, i.e. Issued RFQ, Issued P.O. Material Receipt
and Acceptance, etc.. The weightage assigned are sub-grouped into two (2)
categories:
Topside
CONTRACTOR Supplied Materials 81.00%
i) Structural Steel 15.00%
ii) Piping, Fitting & Valves 20.00%
iii) Mechanical Items/ 16.00%
Equipment
iv) Electrical 10.00%
v) Instrument Items 11.00%
vi) HVAC/Ducting 3.00%
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 16 OF 21

vii) Architectural 2.00%


viii) Other Material 4.00%
PCVL Supplied Materials 19.00%
i) Long Lead Items 19.00%
100.00%

5.6.4.3 Weightage Assignment for Front-End Activities/ Mobilisation.


The weightage for Front-End activities / Mobilization shall be assigned as follows:

Topside
Mobilization of Project
i) 9.00%
Management Team
ii) Project planning and monitoring
5.00%
format
iii) Yard Preparation 15.00%

iv) Fabrication Framing/ Support


52.00%
Foundation
v) Mobilization of NDT Source
3.00%
Inspection
vi) Mobilization of Heat Treatment
3.00%
Sub-contractor
vii) Mobilization of Insulation 3.00%

viii) Mobilization of Leak Test & Bolt


3.00%
Tensioning Sub-contractor
ix) Mobilization of Weighing & load out
3.00%
Sub-contractor
x) WQT & WPS 3.00%

xi) Test Panel/ Coating System


1.00%
Qualification Test
100.00%
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 17 OF 21

5.6.4.4 Weightage Assignment for Fabrication.


The fabrication Weightage adopted are broken down into the following sub-groups:

Topside
i) Structural 50.00%
ii) Piping/ Plumbing 19.00%

iii) Mechanical 3.00%

iv) Electrical 8.00%

v) Instrument 8.00%

vi) HVAC/Ducting 2.00%

vii) Blasting/ Painting 8.00%

viii) Architectural/ Finishing 2.00%

100.00%

5.6.4.5 Weightage Assignment for Load-out and Seafastening


The weightage for load-out and seafastening will be assigned in accordance with
the following:

Topside
i) Drawings 7.00%

ii) Materials 4.00%

iii) Seafastening Fabrication 17.00%

iv) Load-out and Positioning 42.00%

v) Tie-down Arrangements 30.00%

100.00%
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 18 OF 21

5.6.4.6 Weightage Assignment for Onshore Preparation


The weightage for Onshore Preparation will be assigned in accordance with the
following:
Topside
i) Preparation HUC 40.00%
Procedures
ii) Mobilization Manpower, 25.00%
Material
iii) Mobilization Tool & 25.00%
Equipment
iv) Mobilization HUC Barge 10.00%

100.00%

5.6.4.7 Weightage Assignment for Hook-up and Commissioning


The weightage for Offshore Hook-up and Commissining will be assigned in
accordance with the following:
Topside
i) Hook Up 60.00%

ii) Commissioning 40.00%

100.00%

5.6.4.8 Weightage Assignment for Final Documentation


For the Final Documentation, the weightage adopted at Level 3 will essentially be
based on the following categories:

Topside
i) Equipment Dossier 22.00%

ii) QA/QC Documentation 17.00%

iii) Material Documentation 8.00%

iv) Testing & Precommisioning 10.00%


Documentation
v) Design Data 3.00%
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 19 OF 21

vi) As-Built Drawings 31.00%

vii) Close-Out Report 2.00%

viii) Shiploose List 6.00%

ix) NDT Radiographic Film 1.00%

100.00%

5.6.5 Weightage for Level 4 Activities


Level 4 activities are a detailed breakdown of the various tasks of Level 3
components.
The activities identified in the CPN shall be of the form such that the actual physical
progress can be easily measured (physically quantifiable as far as possible).
The detailed breakdown of weightage assigned for Level 4 activities are further
developed as shown in CSP-02 Rev.1 - ‘Progress Measurement Format’.

5.7 Planning Implementation & Execution


60 days Schedule

At the commencement of the project and prior to the development of the Level 3
schedule, a “60 days schedule” is prepared and issued to plan in detail all works
performed within that period by discipline. This schedule is updated weekly and used
for control until the level 3 schedule and the engineering and procurement progress
measurements are implemented.

Resource Loading

The detail schedule shall be fully resource loaded. Then, the project S-curves and
Manpower histogram will be generated. These S-curves and Manpower histogram will
be updated and monitoring weekly.

See attachment 6 and 7.

General Maintenance / Development

The CSB will be maintained on a day to day basis with details being incorporated as
and when they become available along with the re-allocating of resource loadings /
weightings from the higher level activities to the lower level activities.
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 20 OF 21

External interfaces and dependencies between major project components will be


incorporated into the schedule as they are defined, ensuring that all external planning
aspects of the project and all internal planning aspects from engineering to hook-up&
commissioning, as defined by the contract requirements, are satisfied.

Updating

The Document Controller will record the status of engineering deliverables in the
Document Register Database on a continuous basis and provide the Planning
Engineer with the status summary for deliverable based engineering activities on a
weekly basis.

Engineering Coordinator will provide the Planning Engineer with the status update for
non-deliverable bases engineering activities on a weekly basis.

The Procurement Manager will provide an updated Procurement Status Report on a


weekly basis to the Planning Engineer after the weekly cut-off. The Procurement
Status Report will contain an updated forecast for the remaining procurement
activities.

The Construction Manager will provide the required progress information regarding to
Onshore Fabrication activities to the Planning Engineer on a daily basis.

For updating the CSB, the Planning Engineer will extract the dates from these Level 3
schedule, or base on the progress measurement system to update progress for each
activity and then all activities will imported to the Overall CSB level 3 – schedule base
on the activity ID that was assigned for each activity. This schedule shall be updated
and reissued every two (2) weeks using a “time now” line to emphasize progress
achieved, then Planning Engineer will analysis and issue a “two weeks look ahead”
control schedule for every updating period.

Reporting and Monitoring

The Planning Engineer shall be responsible for this task. He shall liaise with all
concerned departments for information required for the preparation of weekly / monthly
progress report.

All concerned departments shall furnish their respective works status to the Planning
Engineer on the weekly/ monthly cut-off date for compilation. The weekly cutoff date is
every Friday. The monthly cut-off date is on 25th every month. PVC-MS shall issue the
Weekly Report within Tuesday every week and issue Monthly Reports on first Tuesday
of the following month to PCVL Representative.
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02

REVISION: 0
TOPSIDE PAGE 21 OF 21

The Planning Engineer shall update the Level 4 progress in the spread sheet. The
calculated Level 4 progress percentage shall then be entered onto the CPN together
with actual start date and actual finish date of the activities. The percentage
completion of each activity will be calculated in accordance with particular
measurement factor stipulated in “Progress Measurement Format” as per
attachment 8.

Upon completion of the weekly updating, the Planning Engineer shall re-analyze the
CPN and prepare the weekly progress report. The analyzing schedule include the
following:

- Planned progress percentage vs. actual progress percentage for each of the major
work break-up as given in the progress report.

- Planned manpower vs. actual manpower.

- Progress milestone status vs. planned milestone period.

- Overall priority of the ongoing jobs and its criticality.

The Project Manager shall then be advised on any delay or potential delays. The root
cause of delays or potential delays shall be identified and the recommended remedial
actions proposed shall be included in the progress report. Consequently, appropriate
instructions will be transferred from Project Manager to specific relevant disciplines for
immediately resolving the problems. Planning Engineer then is responsible for
recording and reporting the performance of each discipline as assigned.

The Project Manager shall review the compiled progress reports prior to the
submission to PCVL for review and approval.

PVC-MS Planner will once a month meet with PCVL Planner to discuss the update
such as progress schedule, progress monitoring, etc.

Schedule Revisions

If during the course of the project both Client and Contractor agree that the CSB no
longer contains the proper relationship to the current status of the project, a schedule
re-baseline will take place and the re-baseline will become the revised CSB. However,
changes to Milestones will only be by Changer Oder Authorizations.

6. SPECIAL REQUIREMENTS

7. RECORDS
ATTACHMENT
ATTACHMENT 1
Project Organization Chart
ATTACHMENT 2
Fabrication Sequence & Yard Layout
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
ATTACHMENT 3
Project’s Calendar and Report
1. REPORT

Monthly
Contractor Weekly Cut- Weekly Report Contractor Monthly Monthly Report
Week Report
off Delivered to Company Cut-off Delivered to Company
No
Weekly
Project
Report Day Date Day Date Day Date Day Date
week
No
1 1 Friday 22-Feb-13 Tuesday 26-Feb-13
2 2 Friday 1-Mar-13 Tuesday 5-Mar-13
3 3 Friday 8-Mar-13 Tuesday 12-Mar-13
4 4 Friday 15-Mar-13 Tuesday 19-Mar-13
5 5 Friday 22-Mar-13 Tuesday 26-Mar-13
6 6 Friday 29-Mar-13 Tuesday 2-Apr-13 1 Friday 29-Mar-13 Tuesday 2-Apr-13
7 7 Friday 5-Apr-13 Tuesday 9-Apr-13
8 8 Friday 12-Apr-13 Tuesday 16-Apr-13
9 9 Friday 19-Apr-13 Tuesday 23-Apr-13
10 10 Friday 26-Apr-13 Tuesday 30-Apr-13 2 Friday 26-Apr-13 Thusday 2-May-13
11 11 Friday 3-May-13 Tuesday 7-May-13
12 12 Friday 10-May-13 Tuesday 14-May-13
13 13 Friday 17-May-13 Tuesday 21-May-13
14 14 Friday 24-May-13 Tuesday 28-May-13
15 15 Friday 31-May-13 Tuesday 4-Jun-13 3 Friday 31-May-13 Tuesday 4-Jun-13
16 16 Friday 7-Jun-13 Tuesday 11-Jun-13
17 17 Friday 14-Jun-13 Tuesday 18-Jun-13
18 18 Friday 21-Jun-13 Tuesday 25-Jun-13
19 19 Friday 28-Jun-13 Tuesday 2-Jul-13 4 Friday 28-Jun-13 Tuesday 2-Jul-13
20 20 Friday 5-Jul-13 Tuesday 9-Jul-13
21 21 Friday 12-Jul-13 Tuesday 16-Jul-13
22 22 Friday 19-Jul-13 Tuesday 23-Jul-13
23 23 Friday 26-Jul-13 Tuesday 30-Jul-13 5 Friday 26-Jul-13 Tuesday 30-Jul-13
24 24 Friday 2-Aug-13 Tuesday 6-Aug-13
25 25 Friday 9-Aug-13 Tuesday 13-Aug-13
26 26 Friday 16-Aug-13 Tuesday 20-Aug-13
27 27 Friday 23-Aug-13 Tuesday 27-Aug-13
28 28 Friday 30-Aug-13 Tuesday 3-Sep-13 6 Friday 30-Aug-13 Tuesday 3-Sep-13
29 29 Friday 6-Sep-13 Tuesday 10-Sep-13
30 30 Friday 13-Sep-13 Tuesday 17-Sep-13
31 31 Friday 20-Sep-13 Tuesday 24-Sep-13
32 32 Friday 27-Sep-13 Tuesday 1-Oct-13 7 Friday 27-Sep-13 Tuesday 1-Oct-13
33 33 Friday 4-Oct-13 Tuesday 8-Oct-13
34 34 Friday 11-Oct-13 Tuesday 15-Oct-13
35 35 Friday 18-Oct-13 Tuesday 22-Oct-13
36 36 Friday 25-Oct-13 Tuesday 29-Oct-13 8 Friday 25-Oct-13 Tuesday 5-Nov-13
37 37 Friday 1-Nov-13 Tuesday 5-Nov-13
38 38 Friday 8-Nov-13 Tuesday 12-Nov-13
39 39 Friday 15-Nov-13 Tuesday 19-Nov-13
40 40 Friday 22-Nov-13 Tuesday 26-Nov-13
41 41 Friday 29-Nov-13 Tuesday 3-Dec-13 9 Friday 29-Nov-13 Tuesday 3-Dec-13
42 42 Friday 6-Dec-13 Tuesday 10-Dec-13
43 43 Friday 13-Dec-13 Tuesday 17-Dec-13
44 44 Friday 20-Dec-13 Tuesday 24-Dec-13
45 45 Friday 27-Dec-13 Tuesday 31-Dec-13 10 Friday 27-Dec-13 Tuesday 31-Dec-13
46 46 Friday 3-Jan-14 Tuesday 7-Jan-14
47 47 Friday 10-Jan-14 Tuesday 14-Jan-14
48 48 Friday 17-Jan-14 Tuesday 21-Jan-14
49 49 Friday 24-Jan-14 Tuesday 28-Jan-14
50 50 Wednesday 29-Jan-14 Wednesday 5-Feb-14 11 Wednesday 29-Jan-14 Wednesday 5-Feb-14
51 51 Friday 7-Feb-14 Tuesday 11-Feb-14
52 52 Friday 14-Feb-14 Tuesday 18-Feb-14
53 53 Friday 21-Feb-14 Tuesday 25-Feb-14
54 54 Friday 28-Feb-14 Tuesday 4-Mar-14 12 Friday 28-Feb-14 Tuesday 4-Mar-14
55 55 Friday 7-Mar-14 Tuesday 11-Mar-14
56 56 Friday 14-Mar-14 Tuesday 18-Mar-14
57 57 Friday 21-Mar-14 Tuesday 25-Mar-14
58 58 Friday 28-Mar-14 Tuesday 1-Apr-14 13 Friday 28-Mar-14 Tuesday 1-Apr-14

PROJECT HOLIDAY/NON WORKING DAYS

1. Hung Vuong King Ceremony: 4/19/2013

2. Nation Independence Day: 4/30/2013

3. Labor Day: 5/1/2013

4. National Day: 9/2/2013

5. New Year Holiday: 1/1/2014

6. Lunar New Year Holiday 2013: From 30-Jan to 4-Feb-2014


2. CALENDAR
+ Calendar for Procurement, Engineering
+ Calendar for Procurement, Engineering (Cont.)
+ Calendar for Procurement, Engineering (Cont.)
+ Calendar for Onshore Fabrication
+ Calendar for Onshore Fabrication (Cont.)
+ Calendar for Onshore Fabrication (Cont.)

Normal working hours Overtime


working
hours
+ Calendar for Load out and Sea-fastening
+ Calendar for Hook-up and Commissioning
ATTACHMENT 4
Critical Path Network (Topside)
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

CRITICAL PATH NETWORK
Activity ID Activity Name Original Start Finish 2013 2014
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
359 01-Feb-13 24-Apr-14 01-Feb-13 24-Apr-14
DMDP-A OVERALL EPCC SCHEDULE TOPSIDE
333 04-Feb-13 24-Mar-14 04-Feb-13 24-Mar-14
PROJECT MILESTONE
GENERAL 0 04-Feb-13 04-Feb-13 04-Feb-13 04-Feb-13
A1000 LETTER OF AWARD ISSUED BY PCVL 0 04-Feb-13*
LETTER OF AWARD ISSUED BY PCVL
FABRICATION 223 01-Jun-13 28-Feb-14 01-Jun-13 28-Feb-14
A1005 START DATE FOR FABRICATION 0 01-Jun-13*
START DATE FOR FABRICATION
A1010 FINISH DATE FOR FABRICATION (MCD) 0 28-Feb-14*
FINISH DATE FOR FABRICATION (MCD)
LOAD OUT AND SEAFASTENING 0 10-Mar-14 10-Mar-14 10-Mar-14 10-Mar-14
A1020 FINISH DATE FOR LOAD OUT AND SEAFASTENING 0 10-Mar-14*
FINISH DATE FOR LOAD OUT AND SEAFASTENING
HOOK-UP AND COMMISSIONIN G (HUC ) 0 24-Mar-14 24-Mar-14 24-Mar-14 24-Mar-14
H4105 START OFFSHORE HUC 0 24-Mar-14*
START OFFSHORE HUC
ENGINEERING 0

DETAILED ENGINEERING 0
AFC STAGE 0
POST-AFC STAGE 0
SHOP DRAWINGS 0
STRUCTURAL 0
PIPING/PLUMBING MECHANICAL 0
ELECTRICAL 0
INSTRUMENT 0
HVAC/DUCTING 0
ARCHITECTURAL 0
MATERIAL TAKE-OFF (MTO) 0
STRUCTURAL 0
PIPING/PLUMBING 0
MECHANICAL 0
ELECTRICAL 0
INSTRUMENT 0
ARCHITECTURAL 0
HVAC/DUCTING 0
OTHER MATERIAL 0
PROCEDURES 0
291 01-Feb-13 29-Jan-14 01-Feb-13 29-Jan-14
PROCURMENT
PCVL-SUPPLIED MATERIALS 291 01-Feb-13 29-Jan-14 01-Feb-13 29-Jan-14
STRUCTURAL STEEL (ETA) 0
MECHANICAL ITEMS/EQUIMENT (ETA) 291 01-Feb-13 29-Jan-14 01-Feb-13 29-Jan-14
MATERIAL HANDLING - PEDESTAL CRANE 244 01-Feb-13 23-Jan-14 01-Feb-13 23-Jan-14
D1010 DELIVERY ON SITE MATERIAL HANDLING - PEDESTAL CRANE BD-7301 (MAIN DECK) 244 01-Feb-13* 23-Jan-14
CRUDE HEATER UNIT 191 01-Feb-13 07-Nov-13 01-Feb-13 07-Nov-13
D1020 DELIVERY ON SITE CRUDE HEATER UNIT A-1510 (CELLAR DECK) 191 01-Feb-13* 07-Nov-13
CRUDE OIL TRANSFER PUMP 244 01-Feb-13 23-Jan-14 01-Feb-13 23-Jan-14
D1030 DELIVERY ON SITE CRUDE OIL TRANSFER PUMP (COTP) P-1310A/B (CELLAR DECK) 244 01-Feb-13* 23-Jan-14
BOOSTER COMPRESSOR 248 01-Feb-13 29-Jan-14 01-Feb-13 29-Jan-14
D1040 DELIVERY ON SITE BOOSTER COMPRESSOR A-2410 (MAIN DECK) 248 01-Feb-13* 29-Jan-14
GAS LIFT COMPRESSOR 248 01-Feb-13 29-Jan-14 01-Feb-13 29-Jan-14
D1050 DELIVERY ON SITE GAS LIFT COMPRESSOR A-0610 (MAIN DECK) 248 01-Feb-13* 29-Jan-14
FUEL GAS SKID 0
CHEMICAL INJECTION SKID 0
LAUNCHER 0
CLOSE DRAIN VESSEL 0
ELECTRICAL ITEMS/EQUIMENT (ETA) 228 05-Feb-13 03-Jan-14 05-Feb-13 03-Jan-14
DIESEL ENGINE GENERATOR (DEG) 189 05-Feb-13 08-Nov-13 05-Feb-13 08-Nov-13
D1110 DELIVERY ON SITE DIESEL ENGINE GENERATOR (DEG) A-7740 (CELLAR DECK) 189 05-Feb-13* 08-Nov-13

Actual Work Critical Remaining Work Summary Page 1 of 6 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

CRITICAL PATH NETWORK
Activity ID Activity Name Original Start Finish 2013 2014
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
GAS ENGINE GENERATOR A-7700 228 05-Feb-13 03-Jan-14 05-Feb-13 03-Jan-14
D1120 DELIVERY ON SITE GAS ENGINE GENERATOR A-7700 (CELLAR DECK) 228 05-Feb-13* 03-Jan-14
INSTRUMENT/ TELECOMMUNICATION ITEMS/EQUIMENT (ETA ) 241 01-Feb-13 29-Nov-13 01-Feb-13 29-Nov-13
MULTIPHASE FLOW METER 0
PMCS/SIS/FIELD TRANSMITTER/ FGS 0
WELL HEAD CONTROL PANEL 0
ACTUATED BALL VALVES 206 01-Feb-13 29-Nov-13 01-Feb-13 29-Nov-13
D1160 DELIVERY ON SITE ACTUATED BALL VALVES 206 01-Feb-13* 29-Nov-13
CHOKE VAVLES 167 01-Feb-13 04-Oct-13 01-Feb-13 04-Oct-13
D1170 DELIVERY ON SITE CHOKE VAVLES 167 01-Feb-13* 04-Oct-13
TELECOMUNICATION EQUIPMENT 0
PVCMS-SUPPLIED MATERIALS 0
STRUCTURAL STEEL (ETA) 0
ALUMINIUM HELIDECK 0
STRUCTURE STEEL 0
MISCELANCENEOUS 0
GRATING 0
M CLIP (INCL. MATERIAL) 0
FIRE BLAST WALL 0
ARCHITECTURAL (ETA) 0
FIRE RATED DOORS 0
TEMPORARY SHELTER AND BATHROOM 0
PIPING (ETA) 0
PIPING BULKS 0
MANUAL VALVES 0
ACCESS FITTINGS (SAMPLING CONNECTION, CHEMICAL INJECTION, CORROSION COUPON) 0
ADDITIONAL ITEMS FOR SAMPLING CONNECTION 0
HOSES AND COUPLINGS 0
BUG SCREEN 0
STRAINER 0
CONTINUOUS DRAINERS 0
SIGHT GLASS 0
FLAME ARESTOR 0
PIPING SUPPORT 0
MECHANICAL (ETA) 0
GAS OPERATED PUMP 0
RECIPROCATING PUMPS 0
CENTRIFUGAL PUMP (MISC) 0
TOTE TANKS 0
RECTANGULAR TANKS 0
CLOSED DRAIN TRANSFER PUMP 0
SEPATATOR SKID 0
NITROGEN BOTTLES 0
CO2 VENT SNUFFING 0
HANDLING & LIFTING EQUIPMENT 0
SAFETY & FIRE FIGHTING, LIFE SAVING EQUIPMENT 0
AIR CONDITIONING & VENTILATION SYSTEM 0
ELECTRICAL (ETA) 0
JUCTION BOX AND RCU 0
CABLE GLAND 0
CABLE E&I 0
CABLE TRAY AND LADDER 0
TUBING AND FITTING 0
EARTHING BOSS 0

Actual Work Critical Remaining Work Summary Page 2 of 6 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

CRITICAL PATH NETWORK
Activity ID Activity Name Original Start Finish 2013 2014
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
SOCKET AND OUTLET 0
HEAT TRACING 0
LIGHTING & FIXTURES 0
MULTI CABLE TRANSIT 0
MISCELLANEOUS 0
CONTROL VALVES (PCV, LCV, FCV, ADV) 0
NAVIGATION AIDS 0
PUSH BUTTON 0
400V AC LV SWICH BOARD 0
UPS 0
DISTRIBUTION BOARD 0
HELIDECK LIGHTING 0
INSTRUMENT (ETA) 0
FLOW METTER 0
FUSIBLE PLUG LOOP PANEL 0
PIG SIGNALLER 0
SAFETY RELIEF VALVE 0
RESTRICTION ORIFICES, ORIFICES PLATE AND FLANGES 0
SAND MONITORING 0
PRESSURE GAUGES 0
PRESSURE REGULATOR VALVES 0
LEVEL GAUGES 0
146 03-Sep-13 28-Feb-14 03-Sep-13 28-Feb-14
CONSTRUCTION
FRONT-END ACTIVITIES/ MOBILIZATION 0
MOBILIZATION OF PROJECT MANAGEMENT TEAM 0
PROJECT PLANNING AND MONITO RING F ORMAT 0
YARD PREPARATIONS 0
CONCRETE FOUNDATION / TEMPORARY SUPPORT FABRICATION 0
CONCRETE FOUNDATION/ TEMPORARY SUPPORTS AT FINAL POSITION FABRICATION 0
TEMPORARY SUPPORTS AT FINAL POSITION FABRICATION 0
CONCRETE FOUNDATION SUPPORTS AT FINAL POSITION FABRICATION 0
CONCRETE FOUNDATION/ TEMPORARY SUPPORTS CELLAR DECK FABRICATION 0
TEMPORARY SUPPORTS CELLAR DECK FABRICATION 0
CONCRETE FOUNDATION SUPPORTS CELLAR DECK FABRICATION 0
CONCRETE FOUNDATION/ TEMPORARY SUPPORTS MAIN DECK FABRICATION 0
TEMPORARY SUPPORTS MAIN DECK FABRICATION 0
CONCRETE FOUNDATION SUPPORTS MAIN DECK FABRICATION 0
TEMPORARY SUPPORTS VENT BOOM FABRICATION 0
MOBILISATION OF SUB-CONTRACTOR 0
MOBILISATION OF DETAIL ENGINEEING SUB-CONTRACTOR 0
MOBILISATION OF NDT SUB-CONTRACTOR 0
MOBILISATION OF HEAT TREATMENT SUB-CONTRACTOR 0
MOBILISATION OF LEAK TEST & BOLT TENSIO NING SUB-CO NTRACTOR 0
MOBILISATION OF INSULATION SUB-CONTRACTOR 0
MOBILISATION OF WEIGHING & LOAD OUT SUB-CONTRACTOR 0
WQT & WPS 0
PANEL COATING SYSTEM QUALIFICATION TEST 0
ONSHORE FABRICATION 7 03-Sep-13 10-Sep-13 03-Sep-13 10-Sep-13
STRUCTURAL 7 03-Sep-13 10-Sep-13 03-Sep-13 10-Sep-13
FABRICATION OF TUBULARS 0
FABRICATION OF PIPE LEGS 0
FABRICATION OF BRACING 0
FABRICATION OF STRUCTURAL MEMBERS 0

Actual Work Critical Remaining Work Summary Page 3 of 6 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

CRITICAL PATH NETWORK
Activity ID Activity Name Original Start Finish 2013 2014
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
FABRICATION OF CELLAR DECK FRAME 0
FABRICATION WF BEAMS OF CELLAR DECK 0
FABRICATION OF CELLAR DECK PART II 0
FABRICATION OF PRIMARY FRAME PART II 0
FABRICATION OF SECONDARY FRAME PART II 0
FABRICATION OF JOINT DETAIL PART II 0
FABRICATION OF DECK PLATING PART II 0
FABRICATION OF CELLAR DECK PART III 0
FABRICATION OF PRIMARY FRAME PART III 0
FABRICATION OF SECONDARY FRAME PART III 0
FABRICATION OF JOINT DETAIL PART III 0
FABRICATION OF DECK PLATING PART III 0
FABRICATION OF CELLAR DECK PART I 0
FABRICATION OF PRIMARY FRAME PART I 0
FABRICATION OF SECONDARY FRAME PART I 0
FABRICATION OF JOINT DETAIL PART I 0
FABRICATION OF DECK PLATING PART I 0
FABRICATION OF MAIN DECK FRAME 0
FABRICATION WF BEAMS OF MAIN DECK 0
FABRICATION OF MAIN DECK PART II 0
FABRICATION OF PRIMARY FRAME PART II 0
FABRICATION OF SECONDARY FRAME PART II 0
FABRICATION OF JOINT DETAIL PART II 0
FABRICATION OF DECK PLATING PART II 0
FABRICATION OF MAIN DECK PART III 0
FABRICATION OF PRIMARY FRAME PART III 0
FABRICATION OF SECONDARY FRAME PART III 0
FABRICATION OF JOINT DETAIL PART III 0
FABRICATION OF DECK PLATING PART III 0
FABRICATION OF MAIN DECK PART I 0
FABRICATION OF PRIMARY FRAME PART I 0
FABRICATION OF SECONDARY FRAME PART I 0
FABRICATION OF JOINT DETAIL PART I 0
FABRICATION OF HELI DECK 0
FABRICATIN OF VENT BOOM 0
FABRICATION OF OTHER ITEMS 0
ERECTION 7 03-Sep-13 10-Sep-13 03-Sep-13 10-Sep-13
E1750 CELLAR DECK PART II STACK UP 7 03-Sep-13* 10-Sep-13
TRIAL FIT AND WEIGH ING 0
PIPING/ PLUMBING 0
FABRICATION OF PIPE/PLUMBING SUPPORTS 0
INSTALLATIO N O F PIPE/PLUMBIN G SUPPORTS 0
INSTALLATIO N O F VALVES (NUMBER OF VALVES) 0
LEAK TEST OF VALVES (NUMB ER OF VALVES) 0
FLUSHING, HYDROTESTING AND ACID CLEANING 0
INSULATION 0
MECHANICAL 0
SETTING UP EQUIPMENT ON DECK 0
SETTING UP EQUIPMENT ON CELLAR DECK 0
SETTING UP EQUIPMENT ON MAIN DECK 0
MECHANICAL COMPLETION (TIE-IN) 0
TIE-IN EQUIPMENT ON CELLAR DECK 0
TIE-IN EQUIPMENT ON MAIN DECK 0
INSTRUMENT 0

Actual Work Critical Remaining Work Summary Page 4 of 6 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

CRITICAL PATH NETWORK
Activity ID Activity Name Original Start Finish 2013 2014
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
FABRICATE INSTRUMENT SUPPORTS 0
INSTALLATIO N O F INSTRUMENT SUPPO RTS 0
TUBING TRAY I CABLE TRAY I LADDER INSTALLATION 0
CALIBRATE INSTRUMENT 0
INSTRUMENT EQUIPMENT INSTALLATION 0
CABLE PULLING 0
DRESSING, GLANDING, TAGGING AND TERMINATION 0
PULL AND HOOK-UP TUBING 0
ELECTRICAL 0
FABRICATION OF ELECTRICAL SUPPO RT 0
INSTALLATIO N O F ELECTRICA L SUPPORT 0
CABLE TRAY I CABLE LADDER INSTALLATION 0
CALIBRATE ELECTRICAL EQUIPMENT 0
ELECTRICAL EQUIPMENT INSTALLATION 0
CABLE PULLING 0
DRESSING, GLANCING, TAGGING AND TERMINATION 0
MCT INSTALLATION 0
EARTHING BOSS INSTALLATION 0
BLASTING / PAINTING 0
STRUCTURE STEEL 0
PIPING SUPPORTS/SPOOLS 0
PIPING VALVES 0
INSTRUMENT SUPPORTS 0
ELECTRICAL SUPPORTS 0
ARCHITECTURAL 0
TESTTING & PRE-COMMISSIONING 9 19-Feb-14 28-Feb-14 19-Feb-14 28-Feb-14
PROCESS SYSTEM 7 19-Feb-14 26-Feb-14 19-Feb-14 26-Feb-14
F1010 110-PROCESS GAS 7 19-Feb-14 26-Feb-14
POWER SYSTEM 0
PROCESS UTILITIES SYSTEM 0
GENERAL UTILITIES SYSTEM 0
CONTROL SYSTEM 0
TELECOMMUNICATIONS SYSTEM 0
TOPSIDE ONSHORE MCD 0 28-Feb-14 28-Feb-14 28-Feb-14 28-Feb-14
F1020 TOPSIDE ONSHORE MCD 0 28-Feb-14*
TOPSIDE ONSHORE MCD
LOAD-OUT AND SEAFASTENING 0
DRAWINGS 0
LOAD-OUT BEAM FABRICATION 0
MATERIALS (TONNAGE) 0
LOAD-OUT AND POSITIONING 0
SEAFASTENING FABRICATION 0
TIE-DOWN ARRANGEMENTS 0
0 24-Apr-14 24-Apr-14 24-Apr-14 24-Apr-14
HOOK UP & COMMISSIONING
ONSHORE PREPARATION ACTIVITIES 0
PREPARATION HUC PROCEDURES 0
MOBILIZATION MANPOWER, MATERIAL 0
MOBILIZATION TOOL & EQUIPMENT 0
MOBILIZATION HUC BARGE 0
OFFSHORE HOOK UP AND COMMISSIONIN G 0 24-Apr-14 24-Apr-14 24-Apr-14 24-Apr-14
HOOK UP 0
HOOK UP STRUCTURE 0
INSTALL MECHANICAL ITEMS 0
HOOK UP PIPING 0

Actual Work Critical Remaining Work Summary Page 5 of 6 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

CRITICAL PATH NETWORK
Activity ID Activity Name Original Start Finish 2013 2014
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
HOOK UP RISER 0
HOOK UP FOR FLOWLINE 0
HOOK UP FOR SLOT 4P 0
HOOK UP FOR SLOT 1P 0
HOOK UP FOR SLOT 2P 0
HOOK UP FOR SLOT 3P 0
HOOK UP FOR OTHER PIPING SYSTEMS 0
LEAK TEST PIPING 0
HOOK UP ELECTRICAL 0
HOOK UP INSTRUMENT 0
TOUCH UP PAINTING/ MARKING 0
COMMISSIONING 0
PROCESS SYSTEM 0
PROCESS UTILITIES SYSTEM 0
GENERAL UTILITIES SYSTEM 0
POWER SYSTEM 0
CONTROL SYSTEM 0
TELECOMMUNICATIONS SYSTEM 0
TOPSIDE START UP 0 24-Apr-14 24-Apr-14 24-Apr-14 24-Apr-14
H6000 TOPSIDE START UP 0 24-Apr-14*
TOPSIDE START UP
FINAL DOCUMENTATION 0
EQUIMENT DOSSIER 0
QA/QC DOCUMENTATION 0
MATERIAL DOCUMENTATION 0
TESTTING & PRECOMMISSIONING DOCUMENTATION 0
DESIGN DATA 0
AS-BUILT DRAWINGS 0
CLOSE-OUT REPORT 0
SHIPLOOSE LIST 0
NDT RADIOGRAPHIC FILMS 0

Actual Work Critical Remaining Work Summary Page 6 of 6 Date Revision Checked Approved

Remaining Work Milestone
ATTACHMENT 5
Overall Schedule (Topside)
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
534 05-Sep-12 18-Jun-14 05-Sep-12 18-Jun-14
DMDP-A OVERALL EPCC SCHEDULE TOPSIDE
333 04-Feb-13 24-Mar-14 04-Feb-13 24-Mar-14
PROJECT MILESTONE
GENERAL 0 04-Feb-13 04-Feb-13 04-Feb-13 04-Feb-13
A1000 LETTER OF AWARD ISSUED BY PCVL 0 04-Feb-13*
LETTER OF AWARD ISSUED BY PCVL
FABRICATION 223 01-Jun-13 28-Feb-14 01-Jun-13 28-Feb-14
A1005 START DATE FOR FABRICATION 0 01-Jun-13*
START DATE FOR FABRICATION
A1010 FINISH DATE FOR FABRICATION (MCD) 0 28-Feb-14*
FINISH DATE FOR FABRICATION (MCD)
LOAD OUT AND SEAFASTENING 0 10-Mar-14 10-Mar-14 10-Mar-14 10-Mar-14
A1020 FINISH DATE FOR LOAD OUT AND SEAFASTENING 0 10-Mar-14*
FINISH DATE FOR LOAD OUT AND SEAFASTENING
HOOK-UP AND COMMISSIONIN G (HUC ) 0 24-Mar-14 24-Mar-14 24-Mar-14 24-Mar-14
H4105 START OFFSHORE HUC 0 24-Mar-14*
START OFFSHORE HUC
283 18-Feb-13 18-Jan-14 18-Feb-13 18-Jan-14
ENGINEERING
DETAILED ENGINEERING 189 18-Feb-13 30-Sep-13 18-Feb-13 30-Sep-13
AFC STAGE 41 18-Feb-13 05-Apr-13 18-Feb-13 05-Apr-13
C11650 PROJECT MANAGEMENT 41 18-Feb-13 05-Apr-13
C11660 PROCESS 32 18-Feb-13 26-Mar-13
C11680 MECHANICAL 25 22-Feb-13 22-Mar-13
C11690 PIPING 33 20-Feb-13 29-Mar-13
C11700 INSTRUMENT 35 18-Feb-13 29-Mar-13
C11710 ELECTRICAL 31 18-Feb-13 25-Mar-13
C11720 STRUCTURAL 35 18-Feb-13 29-Mar-13
POST-AFC STAGE 159 25-Mar-13 30-Sep-13 25-Mar-13 30-Sep-13
C11570 PROJECT MANAGEMENT 159 25-Mar-13 30-Sep-13
C11580 PROCESS 149 05-Apr-13 30-Sep-13
C11590 SAFETY 125 08-Apr-13 04-Sep-13
C11600 MECHANICAL 130 08-Apr-13 10-Sep-13
C11610 PIPING 130 02-Apr-13 04-Sep-13
C11620 INSTRUMENT 106 08-Apr-13 12-Aug-13
C11630 ELECTRICAL 132 25-Apr-13 28-Sep-13
C11640 STRUCTURAL 118 08-Apr-13 26-Aug-13
SHOP DRAWINGS 230 28-Mar-13 25-Dec-13 28-Mar-13 25-Dec-13
STRUCTURAL 144 28-Mar-13 16-Sep-13 28-Mar-13 16-Sep-13
C1000 PREPARATIO N/ SU BMISSION/ APPROVAL SHOP DRAWINGS FOR STRUCTURAL 144 28-Mar-13 16-Sep-13
PIPING/PLUMBING MECHANICAL 120 03-Jun-13 21-Oct-13 03-Jun-13 21-Oct-13
C1010 PREPARATIO N/ SU BMISSION/ APPROVAL SHOP DRAWINGS FOR PIPING/ PLUMBING MECHANICAL
120 03-Jun-13 21-Oct-13
ELECTRICAL 110 21-Jun-13 28-Oct-13 21-Jun-13 28-Oct-13
C1020 PREPARATIO N/ SU BMISSION/ APPROVAL SHOP DRAWINGS FOR ELECTRICAL 110 21-Jun-13 28-Oct-13
INSTRUMENT 110 27-Jun-13 02-Nov-13 27-Jun-13 02-Nov-13
C1030 PREPARATIO N/ SU BMISSION/ APPROVAL SHOP DRAWINGS FOR INSTRUMENT 110 27-Jun-13 02-Nov-13
HVAC/DUCTING 80 18-Sep-13 19-Dec-13 18-Sep-13 19-Dec-13
C1040 PREPARATIO N/ SU BMISSION/ APPROVAL SHOP DRAWINGS FOR HVAC/ DUCT ING 80 18-Sep-13 19-Dec-13
ARCHITECTURAL 85 18-Sep-13 25-Dec-13 18-Sep-13 25-Dec-13
C1050 PREPARATIO N/ SU BMISSION/ APPROVAL SHOP DRAWINGS FOR ARCHITECTUAL 85 18-Sep-13 25-Dec-13
MATERIAL TAKE-OFF (MTO) 137 28-Mar-13 07-Sep-13 28-Mar-13 07-Sep-13
STRUCTURAL 12 28-Mar-13 10-Apr-13 28-Mar-13 10-Apr-13
C1060 PREPARATIO N/ SU BMISSION/ APPROVAL MTO FOR STRUTURAL 12 28-Mar-13 10-Apr-13
PIPING/PLUMBING 12 28-Mar-13 10-Apr-13 28-Mar-13 10-Apr-13
C1070 PREPARATIO N/ SU BMISSION/ APPROVAL MTO FOR PIPING/ PLUMBING 12 28-Mar-13 10-Apr-13
MECHANICAL 12 20-Apr-13 06-May-13 20-Apr-13 06-May-13
C1080 PREPARATIO N/ SU BMISSION/ APPROVAL MTO FOR MECHANICAL 12 20-Apr-13 06-May-13
ELECTRICAL 12 22-Apr-13 07-May-13 22-Apr-13 07-May-13
C1090 PREPARATIO N/ SU BMISSION/ APPROVAL MTO FOR ELECTRICAL 12 22-Apr-13 07-May-13
INSTRUMENT 12 06-May-13 18-May-13 06-May-13 18-May-13
C1100 PREPARATIO N/ SU BMISSION/ APPROVAL MTO FOR INSTRUMENT 12 06-May-13 18-May-13

Actual Work Critical Remaining Work Summary Page 1 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
ARCHITECTURAL 12 23-May-13 05-Jun-13 23-May-13 05-Jun-13
C1110 PREPARATIO N/ SU BMISSION/ APPROVAL MTO FOR ARCHITECTUAL 12 23-May-13 05-Jun-13
HVAC/DUCTING 12 23-May-13 05-Jun-13 23-May-13 05-Jun-13
C1120 PREPARATIO N/ SU BMISSION/ APPROVAL MTO FOR HVAC/ DUCTING 12 23-May-13 05-Jun-13
OTHER MATERIAL 45 17-Jul-13 07-Sep-13 17-Jul-13 07-Sep-13
C1135 PREPARATIO N/ SU BMISSION/ APPROVAL MTO FOR TOP UP MATERIAL 45 17-Jul-13 07-Sep-13
PROCEDURES 235 15-Apr-13 18-Jan-14 15-Apr-13 18-Jan-14
C1140 PREPARATIO N/ SU BMISSION/ APPROVAL PROCEDURES 235 15-Apr-13 18-Jan-14
425 05-Sep-12 29-Jan-14 05-Sep-12 29-Jan-14
PROCURMENT
PCVL-SUPPLIED MATERIALS 346 17-Sep-12 29-Jan-14 17-Sep-12 29-Jan-14
STRUCTURAL STEEL (ETA) 100 17-Sep-12 04-Feb-13 17-Sep-12 04-Feb-13
D1000 DELIVERY ON SITE FIRST SHIPMENT(7-Jan-13) 66 17-Sep-12* 17-Dec-12
D1005 DELIVERY ON SITE 2ND SHIPMENT(4-Feb-13) 100 17-Sep-12* 04-Feb-13
MECHANICAL ITEMS/EQUIMENT (ETA) 248 01-Feb-13 29-Jan-14 01-Feb-13 29-Jan-14
MATERIAL HANDLING - PEDESTAL CRANE 244 01-Feb-13 23-Jan-14 01-Feb-13 23-Jan-14
D1010 DELIVERY ON SITE MATERIAL HANDLING - PEDESTAL CRANE BD-7301 (MAIN DECK) 244 01-Feb-13* 23-Jan-14
CRUDE HEATER UNIT 191 01-Feb-13 07-Nov-13 01-Feb-13 07-Nov-13
D1020 DELIVERY ON SITE CRUDE HEATER UNIT A-1510 (CELLAR DECK) 191 01-Feb-13* 07-Nov-13
CRUDE OIL TRANSFER PUMP 244 01-Feb-13 23-Jan-14 01-Feb-13 23-Jan-14
D1030 DELIVERY ON SITE CRUDE OIL TRANSFER PUMP (COTP) P-1310A/B (CELLAR DECK) 244 01-Feb-13* 23-Jan-14
BOOSTER COMPRESSOR 248 01-Feb-13 29-Jan-14 01-Feb-13 29-Jan-14
D1040 DELIVERY ON SITE BOOSTER COMPRESSOR A-2410 (MAIN DECK) 248 01-Feb-13* 29-Jan-14
GAS LIFT COMPRESSOR 248 01-Feb-13 29-Jan-14 01-Feb-13 29-Jan-14
D1050 DELIVERY ON SITE GAS LIFT COMPRESSOR A-0610 (MAIN DECK) 248 01-Feb-13* 29-Jan-14
FUEL GAS SKID 157 07-Feb-13 26-Sep-13 07-Feb-13 26-Sep-13
D1060 DELIVERY ON SITE FUEL GAS SKID  A-5800 (CELLAR DECK) 157 07-Feb-13* 26-Sep-13
CHEMICAL INJECTION SKID 157 07-Feb-13 26-Sep-13 07-Feb-13 26-Sep-13
D1070 DELIVERY ON SITE CHEMICAL INJECTION PUMP SKID A-6800 ( CELLAR DECK) 157 07-Feb-13* 26-Sep-13
LAUNCHER 128 07-Feb-13 15-Aug-13 07-Feb-13 15-Aug-13
D1090 DELIVERY ON SITE LAUNCHER L-1330 (CELLAR DECK) 128 07-Feb-13* 15-Aug-13
CLOSE DRAIN VESSEL 171 18-Feb-13 18-Oct-13 18-Feb-13 18-Oct-13
D1100 DELIVERY ON SITE CLOSE DRAIN VESSEL V-6400 171 18-Feb-13* 18-Oct-13
ELECTRICAL ITEMS/EQUIMENT (ETA) 228 05-Feb-13 03-Jan-14 05-Feb-13 03-Jan-14
DIESEL ENGINE GENERATOR (DEG) 189 05-Feb-13 08-Nov-13 05-Feb-13 08-Nov-13
D1110 DELIVERY ON SITE DIESEL ENGINE GENERATOR (DEG) A-7740 (CELLAR DECK) 189 05-Feb-13* 08-Nov-13
GAS ENGINE GENERATOR A-7700 228 05-Feb-13 03-Jan-14 05-Feb-13 03-Jan-14
D1120 DELIVERY ON SITE GAS ENGINE GENERATOR A-7700 (CELLAR DECK) 228 05-Feb-13* 03-Jan-14
INSTRUMENT/ TELECOMMUNICATION ITEMS/EQUIMENT (ETA ) 206 01-Feb-13 29-Nov-13 01-Feb-13 29-Nov-13
MULTIPHASE FLOW METER 157 01-Feb-13 20-Sep-13 01-Feb-13 20-Sep-13
D1130 DELIVERY ON SITE MULTIPHASE FLOW METER A-1210 (CELLAR DECK) 157 01-Feb-13* 20-Sep-13
PMCS/SIS/FIELD TRANSMITTER/ FGS 147 01-Feb-13 06-Sep-13 01-Feb-13 06-Sep-13
D1140 DELIVERY ON SITE PMCS/SIS/FIELD TRANSMIT TER/ F GS 147 01-Feb-13* 06-Sep-13
WELL HEAD CONTROL PANEL 122 01-Feb-13 02-Aug-13 01-Feb-13 02-Aug-13
D1150 DELIVERY ON SITE WELL HEAD CONTROL PANEL WHCP-0100 (CELLAR DECK) 122 01-Feb-13* 02-Aug-13
ACTUATED BALL VALVES 206 01-Feb-13 29-Nov-13 01-Feb-13 29-Nov-13
D1160 DELIVERY ON SITE ACTUATED BALL VALVES 206 01-Feb-13* 29-Nov-13
CHOKE VAVLES 167 01-Feb-13 04-Oct-13 01-Feb-13 04-Oct-13
D1170 DELIVERY ON SITE CHOKE VAVLES 167 01-Feb-13* 04-Oct-13
TELECOMUNICATION EQUIPMENT 148 15-Mar-13 14-Oct-13 15-Mar-13 14-Oct-13
D1180 DELIVERY ON SITE TELECOMU NICATION EQUIPMENT 148 15-Mar-13* 14-Oct-13
PVCMS-SUPPLIED MATERIALS 407 05-Sep-12 07-Jan-14 05-Sep-12 07-Jan-14
STRUCTURAL STEEL (ETA) 316 05-Sep-12 04-Dec-13 05-Sep-12 04-Dec-13
ALUMINIUM HELIDECK 316 05-Sep-12 04-Dec-13 05-Sep-12 04-Dec-13

Actual Work Critical Remaining Work Summary Page 2 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
D1185 RFP TO VEND OR 1 05-Sep-12* 05-Sep-12
D1188 PO ISSUE DATE 1 23-May-13 23-May-13
D1190 DELIVERY ON SITE (ALUMINIUM HELIDECK) 2 29-Nov-13* 02-Dec-13
D1193 MATERIAL ACCEPTANCE (ALUMINIUM HELIDECK) 2 03-Dec-13 04-Dec-13
STRUCTURE STEEL 207 05-Sep-12 03-Jul-13 05-Sep-12 03-Jul-13
D1195 RFP TO VEND OR 1 05-Sep-12* 05-Sep-12
D1197 PO ISSUE DATE 1 19-Mar-13 19-Mar-13
D1200 DELIVERY ON SITE (STRUCTURE STEEL) 4 17-Jun-13* 20-Jun-13
D1205 MATERIAL ACCEPTANCE (STRUCTURE STEEL) 4 28-Jun-13 03-Jul-13
MISCELANCENEOUS 185 10-Sep-12 06-Jun-13 10-Sep-12 06-Jun-13
D1207 RFP TO VEND OR 1 10-Sep-12* 10-Sep-12
D1209 PO ISSUE DATE 1 13-Mar-13 13-Mar-13
D1210 DELIVERY ON SITE (MISCELANCENEOUS) 2 03-Jun-13* 04-Jun-13
D1215 MATERIAL ACCEPTANCE (MISCELANCENEOUS) 2 05-Jun-13 06-Jun-13
GRATING 256 07-Sep-12 13-Sep-13 07-Sep-12 13-Sep-13
D1217 RFP TO VEND OR 1 07-Sep-12* 07-Sep-12
D1219 PO ISSUE DATE 1 19-Mar-13 19-Mar-13
D1220 DELIVERY ON SITE (GRATING) 2 10-Sep-13 11-Sep-13
D1225 MATERIAL ACCEPTANCE (GRATING) 2 12-Sep-13 13-Sep-13
M CLIP (INCL. MATERIAL) 240 27-Sep-12 11-Sep-13 27-Sep-12 11-Sep-13
D5810 RFP TO VEND OR 1 27-Sep-12* 27-Sep-12
D5890 PO ISSUE DATE 1 12-Apr-13 12-Apr-13
D5915 DELIVERY ON SITE (M CLIP) 2 06-Sep-13* 09-Sep-13
D5917 MATERIAL ACCEPTANCE (M CLIP) 2 10-Sep-13 11-Sep-13
FIRE BLAST WALL 98 11-Apr-13 29-Aug-13 11-Apr-13 29-Aug-13
D1227 RFP TO VEND OR 1 11-Apr-13 11-Apr-13*
D1229 PO ISSUE DATE 1 03-Jul-13 03-Jul-13
D1230 DELIVERY ON SITE (FIRE BLAST WALL) 2 26-Aug-13* 27-Aug-13
D1235 MATERIAL ACCEPTANCE (FIRE BLAST WALL) 2 28-Aug-13 29-Aug-13
ARCHITECTURAL (ETA) 287 05-Sep-12 25-Oct-13 05-Sep-12 25-Oct-13
FIRE RATED DOORS 286 06-Sep-12 25-Oct-13 06-Sep-12 25-Oct-13
D1797 RFP TO VEND OR 1 06-Sep-12* 06-Sep-12
D1799 PO ISSUE DATE 1 23-May-13 23-May-13
D1800 DELIVERY ON SITE (FIRE RATED DOORS) 2 21-Oct-13* 23-Oct-13
D1805 MANUFAC TU RE (FIR E RATED DOORS) 2 23-Oct-13 25-Oct-13
TEMPORARY SHELTER AND BATHROOM 253 05-Sep-12 06-Sep-13 05-Sep-12 06-Sep-13
D1815 RFP TO VEND OR 1 05-Sep-12* 05-Sep-12
D1817 PO ISSUE DATE 1 31-May-13 31-May-13
D1820 DELIVERY ON SITE (TEMPORARY SHELTER) 2 03-Sep-13 04-Sep-13*
D1825 MATERIAL ACCEPTANCE (TEMPORARY SHELT ER) 2 05-Sep-13 06-Sep-13
PIPING (ETA) 366 13-Sep-12 27-Nov-13 13-Sep-12 27-Nov-13
PIPING BULKS 298 14-Sep-12 11-Sep-13 14-Sep-12 11-Sep-13
D1246 RFP TO VEND OR 1 14-Sep-12* 14-Sep-12
D1248 PO ISSUE DATE 1 18-Mar-13 18-Mar-13
D1250 DELIVERY ON SITE 1st SHIPMENT ( PIPING BULKS) 2 17-Jun-13* 18-Jun-13
D1252 DELIVERY ON SITE REMAINING SHIPMENTS (PIPING BULKS) 2 05-Sep-13* 07-Sep-13
D1255 MATERIAL ACCEPTANCE 1st SHIPMENT (PIPING BULKS) 2 19-Jun-13 20-Jun-13
D1257 MATERIAL ACCEPTANCE REMAINING SHIPMENTS (PIPING BULKS) 2 09-Sep-13 11-Sep-13
MANUAL VALVES 304 14-Sep-12 27-Nov-13 14-Sep-12 27-Nov-13
D1256 RFP TO VEND OR 1 14-Sep-12* 14-Sep-12
D1258 PO ISSUE DATE 1 12-Mar-13 12-Mar-13
D1260 DELIVERY ON SITE (MANUAL VALVES) 2 22-Nov-13* 25-Nov-13
D1265 MATERIAL ACCEPTANCE (MANUAL VALVES) 2 26-Nov-13 27-Nov-13
ACCESS FITTINGS (SAMPLING CONNECTION, CHEMICAL INJECTION, CORROSION COUPON) 242 13-Sep-12 29-Aug-13 13-Sep-12 29-Aug-13

Actual Work Critical Remaining Work Summary Page 3 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
D1266 RFP TO VEND OR 1 13-Sep-12* 13-Sep-12
D1268 PO ISSUE DATE 1 14-Mar-13 14-Mar-13
D1270 DELIVERY ON SITE (ACCESS FITTINGS (SAMPLING CONNECTION, CHEMICAL INJECTION, CORROSION COUPON)
2 26-Aug-13* 27-Aug-13
D1275 MATERIAL ACCEPTANCE (ACCESS FITTINGS (SAMPLING CONNECTION, CHEMICAL INJECTION, CORROSION COUPON)
2 28-Aug-13 29-Aug-13
ADDITIONAL ITEMS FOR SAMPLING CONNECTION 164 04-Jan-13 03-Sep-13 04-Jan-13 03-Sep-13
D11170 RFP TO VEND OR 1 04-Jan-13* 04-Jan-13
D11180 PO ISSUE DATE 1 07-May-13 07-May-13
D11185 DELIVERY ON SITE (ADDITIONAL ITEMS FOR SAMPLING CONNECTION) 2 28-Aug-13* 29-Aug-13
D11190 MATERIAL ACCEPTANCE (ADDITIONAL ITEMS FOR SAMPLING CONNECTION) 2 30-Aug-13 03-Sep-13
HOSES AND COUPLINGS 288 14-Sep-12 05-Nov-13 14-Sep-12 05-Nov-13
D1276 RFP TO VEND OR 1 14-Sep-12* 14-Sep-12
D1278 PO ISSUE DATE 1 19-Jul-13 19-Jul-13
D1280 DELIVERY ON SITE (HOSES AND COUPLINGS) 2 31-Oct-13* 01-Nov-13
D1285 MATERIAL ACCEPTANCE (HOSES AND COUPLINGS) 2 04-Nov-13 05-Nov-13
BUG SCREEN 219 19-Sep-12 02-Aug-13 19-Sep-12 02-Aug-13
D1286 RFP TO VEND OR 1 19-Sep-12* 19-Sep-12
D1288 PO ISSUE DATE 1 12-Mar-13 12-Mar-13
D1290 DELIVERY ON SITE (BUG SCREEN) 2 30-Jul-13* 31-Jul-13
D1295 MATERIAL ACCEPTANCE (BUG SCREEN) 2 01-Aug-13 02-Aug-13
STRAINER 243 19-Sep-12 06-Sep-13 19-Sep-12 06-Sep-13
D1296 RFP TO VEND OR 1 19-Sep-12* 19-Sep-12
D1298 PO ISSUE DATE 1 03-May-13 03-May-13
D1300 DELIVERY ON SITE (STRAINER) 2 03-Sep-13* 04-Sep-13
D1305 MATERIAL ACCEPTANCE (STRAINER) 2 05-Sep-13 06-Sep-13
CONTINUOUS DRAINERS 241 14-Sep-12 29-Aug-13 14-Sep-12 29-Aug-13
D1306 RFP TO VEND OR 1 14-Sep-12* 14-Sep-12
D1308 PO ISSUE DATE 1 24-May-13 24-May-13
D1310 DELIVERY ON SITE (CONTINUOUS DRAINERS) 2 26-Aug-13* 27-Aug-13
D1315 MATERIAL ACCEPTANCE (CONTINUOUS DRAINERS) 2 28-Aug-13 29-Aug-13
SIGHT GLASS 255 17-Sep-12 20-Sep-13 17-Sep-12 20-Sep-13
D1336 RFP TO VEND OR 1 17-Sep-12* 17-Sep-12
D1338 PO ISSUE DATE 1 02-Apr-13 02-Apr-13
D1340 DELIVERY ON SITE (SIGN GLASS) 2 17-Sep-13* 18-Sep-13
D1345 MATERIAL ACCEPTANCE  (SIGN GLASS) 2 19-Sep-13 20-Sep-13
FLAME ARESTOR 238 19-Sep-12 29-Aug-13 19-Sep-12 29-Aug-13
D1346 RFP TO VEND OR 1 19-Sep-12* 19-Sep-12
D1348 PO ISSUE DATE 1 10-May-13 10-May-13
D1350 DELIVERY ON SITE (FLAME ARESTOR) 2 26-Aug-13* 27-Aug-13
D1355 MATERIAL ACCEPTANCE  (FLAME ARESTOR) 2 28-Aug-13 29-Aug-13
PIPING SUPPORT 177 18-Sep-12 04-Jun-13 18-Sep-12 04-Jun-13
D9000 RFP TO VEND OR 1 18-Sep-12* 18-Sep-12
D9010 PO ISSUE DATE 1 22-Feb-13 22-Feb-13
D9020 DELIVERY ON SITE (PIPING SUPPORT) 2 30-May-13* 31-May-13
D9030 MATERIAL ACCEPTANCE  (PIPING SUPPORT) 2 03-Jun-13 04-Jun-13
MECHANICAL (ETA) 339 05-Sep-12 07-Jan-14 05-Sep-12 07-Jan-14
GAS OPERATED PUMP 267 05-Sep-12 26-Sep-13 05-Sep-12 26-Sep-13
D9040 RFP TO VEND OR 1 05-Sep-12* 05-Sep-12
D9050 PO ISSUE DATE 1 15-Apr-13 15-Apr-13
D9080 DELIVERY ON SITE (PORTABLE CHEMICAL TRANSFER PUMP P-6835) 2 23-Sep-13* 24-Sep-13
D9090 DELIVERY ON SITE (OPEN DRAIN PUMP P-6510) 2 23-Sep-13* 24-Sep-13
D9100 MATERIAL ACCEPTANCE (GAS OPERATED PUMP) 2 25-Sep-13 26-Sep-13
RECIPROCATING PUMPS 337 05-Sep-12 03-Jan-14 05-Sep-12 03-Jan-14
D9060 RFP TO VEND OR 1 05-Sep-12* 05-Sep-12
D9070 PO ISSUE DATE 1 15-May-13 15-May-13

Actual Work Critical Remaining Work Summary Page 4 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
D9110 DELIVERY ON SITE (SCSSV EQUALIZATION INJECTION PUMP P-6720) 2 30-Dec-13* 31-Dec-13
D9120 DELIVERY ON SITE (PORTABLE PIPELINE DIESEL INJECTION PUMP P-6730) 2 30-Dec-13* 31-Dec-13
D9130 MATERIAL ACCEPTANCE ( RECIPROCATING PUMPS P-6720/ PUMP P-6730) 2 02-Jan-14 03-Jan-14
CENTRIFUGAL PUMP (MISC) 337 05-Sep-12 03-Jan-14 05-Sep-12 03-Jan-14
D9140 RFP TO VEND OR 1 05-Sep-12* 05-Sep-12
D9150 PO ISSUE DATE 1 15-May-13 15-May-13
D9340 DELIVERY ON SITE (DIESEL TRANSFER PUMP P-6710) 2 30-Dec-13* 31-Dec-13
D9350 DELIVERY ON SITE (WASH WATER PUMP P-5110) 2 30-Dec-13* 31-Dec-13
D9360 MATERIAL ACCEPTANCE (CENTRIFUGAL PUMPS P-6710/ PUMP P-5110) 2 02-Jan-14 03-Jan-14
TOTE TANKS 301 05-Sep-12 13-Nov-13 05-Sep-12 13-Nov-13
D9160 RFP TO VEND OR 1 05-Sep-12* 05-Sep-12
D9170 PO ISSUE DATE 1 04-Jul-13 04-Jul-13
D9370 DELIVERY ON SITE (PORTABLE CHEMICAL TOTE TANK) 2 08-Nov-13* 11-Nov-13
D9380 DELIVERY ON SITE (WAX DISSOLVER STANDARD TOTE TANK T-6850) 2 08-Nov-13* 11-Nov-13
D9390 DELIVERY ON SITE (GENERAL PURPOSE TOTE TANK T-5300) 2 08-Nov-13* 11-Nov-13
D9400 MATERIAL ACCEPTANCE (TOTE TANKS) 2 12-Nov-13 13-Nov-13
RECTANGULAR TANKS 290 05-Sep-12 29-Oct-13 05-Sep-12 29-Oct-13
D9180 RFP TO VEND OR 1 05-Sep-12* 05-Sep-12
D9190 PO ISSUE DATE 1 14-May-13 14-May-13
D9410 DELIVERY ON SITE (WASH WATER STORAGE TANK T-5100A/B) 2 24-Oct-13* 25-Oct-13
D9420 DELIVERY ON SITE (PORTABLE WATER TANK T-5200) 2 21-Oct-13* 22-Oct-13
D9430 DELIVERY ON SITE (OPEN DRAIN TANK T-6500) 2 21-Oct-13* 22-Oct-13
D9440 DELIVERY ON SITE (OPEN DRAIN HEATER E-6520) 2 21-Oct-13* 22-Oct-13
D9450 MATERIAL ACCEPTANCE (RECTANGULAR TANKS) 2 28-Oct-13 29-Oct-13
CLOSED DRAIN TRANSFER PUMP 317 05-Sep-12 05-Dec-13 05-Sep-12 05-Dec-13
D9200 RFP TO VEND OR 1 05-Sep-12* 05-Sep-12
D9210 PO ISSUE DATE 1 08-Apr-13 08-Apr-13
D9460 DELIVERY ON SITE (CLOSED DRAIN TRANSFER PUMP P-6410A/B) 2 02-Dec-13* 03-Dec-13
D9470 MATERIAL ACCEPTANCE (CLOSED DRAIN TRANSFER PUMP P-6410A/B) 2 04-Dec-13 05-Dec-13
SEPATATOR SKID 317 05-Sep-12 05-Dec-13 05-Sep-12 05-Dec-13
D9220 RFP TO VEND OR 1 05-Sep-12* 05-Sep-12
D9230 PO ISSUE DATE 1 08-Apr-13 08-Apr-13
D9480 DELIVERY ON SITE (HP SEPARATOR SKID A-1020) 2 02-Dec-13* 03-Dec-13
D9490 DELIVERY ON SITE (LP SEPARATOR SKID A-1010) 2 28-Nov-13 29-Nov-13*
D9500 MATERIAL ACCEPTANCE (HP SEPARATOR SKID A-1020/ A-1010) 2 04-Dec-13 05-Dec-13
NITROGEN BOTTLES 268 06-Sep-12 30-Sep-13 06-Sep-12 30-Sep-13
D9240 RFP TO VEND OR 1 06-Sep-12* 06-Sep-12
D9250 PO ISSUE DATE 1 15-Apr-13 15-Apr-13
D9510 DELIVERY ON SITE (NITROGEN BOTTLES A-5900) 2 25-Sep-13* 26-Sep-13
D9520 MATERIAL ACCEPTANCE (NITROGEN BOTTLES A-5900) 2 27-Sep-13 30-Sep-13
CO2 VENT SNUFFING 269 06-Sep-12 01-Oct-13 06-Sep-12 01-Oct-13
D9260 RFP TO VEND OR 1 06-Sep-12* 06-Sep-12
D9270 PO ISSUE DATE 1 08-Apr-13 09-Apr-13
D9530 DELIVERY ON SITE (CO2 VENT SNUFF ING  A-8600) 2 26-Sep-13* 27-Sep-13
D9540 MATERIAL ACCEPTANCE (CO2 VENT SNUFFING A-8600) 2 30-Sep-13 01-Oct-13
HANDLING & LIFTING EQUIPMENT 338 06-Sep-12 07-Jan-14 06-Sep-12 07-Jan-14
D9280 RFP TO VEND OR 1 06-Sep-12* 06-Sep-12
D9290 PO ISSUE DATE 1 29-Apr-13 29-Apr-13
D9550 DELIVERY ON SITE (HANDLING & LIFTING EQUIPMENT) 2 02-Jan-14* 03-Jan-14
D9560 MATERIAL ACCEPTANCE (HANDLING & LIFTING EQUIPMENT) 2 06-Jan-14 07-Jan-14
SAFETY & FIRE FIGHTING, LIFE SAVING EQUIPMENT 178 11-Mar-13 19-Nov-13 11-Mar-13 19-Nov-13
D9300 RFP TO VEND OR 1 11-Mar-13* 11-Mar-13
D9310 PO ISSUE DATE 1 09-Jul-13 09-Jul-13
D9570 DELIVERY ON SITE (SAFETY & F IRE F IGHTING, LIFE SAVING EQUIPMENT) 2 14-Nov-13* 15-Nov-13

Actual Work Critical Remaining Work Summary Page 5 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
D9580 MATERIAL ACCEPTANCE (SAFETY & FIRE FIGHTING, LIFE SAVING EQUIPMENT) 2 18-Nov-13 19-Nov-13
AIR CONDITIONING & VENTILATION SYSTEM 294 07-Sep-12 06-Nov-13 07-Sep-12 06-Nov-13
D9320 RFP TO VEND OR 1 07-Sep-12* 07-Sep-12
D9330 PO ISSUE DATE 1 26-Apr-13 26-Apr-13
D9590 DELIVERY ON SITE (AIR CONDITIONING & VENTILATION SYSTEM) 2 01-Nov-13* 04-Nov-13
D9600 MATERIAL ACCEPTANCE (AIR CONDITIONING & VENTILATION SYSTEM) 2 05-Nov-13 06-Nov-13
ELECTRICAL (ETA) 317 05-Sep-12 05-Dec-13 05-Sep-12 05-Dec-13
JUCTION BOX AND RCU 259 10-Sep-12 19-Sep-13 10-Sep-12 19-Sep-13
D10120 RFP TO VEND OR 1 10-Sep-12* 10-Sep-12
D10130 PO ISSUE DATE 1 08-Apr-13 08-Apr-13
D10160 DELIVERY ON SITE (JUCTION BOX AND RCU) 2 16-Sep-13* 17-Sep-13
D10170 MATERIAL ACCEPTANCE (JUCTION BOX AND RCU) 2 18-Sep-13 19-Sep-13
CABLE GLAND 259 10-Sep-12 19-Sep-13 10-Sep-12 19-Sep-13
D10140 RFP TO VEND OR 1 10-Sep-12* 10-Sep-12
D10150 PO ISSUE DATE 1 30-May-13 30-May-13
D10180 DELIVERY ON SITE (CABLE GLAND) 2 16-Sep-13* 17-Sep-13
D10190 MATERIAL ACCEPTANCE (CABLE GLAND) 2 18-Sep-13 19-Sep-13
CABLE E&I 266 05-Sep-12 25-Sep-13 05-Sep-12 25-Sep-13
D10200 DELIVERY ON SITE (CABLE E&I) 2 20-Sep-13* 23-Sep-13
D10210 MATERIAL ACCEPTANCE (CABLE E&I) 2 24-Sep-13 25-Sep-13
D9650 RFP TO VEND OR 1 05-Sep-12* 05-Sep-12
D9660 PO ISSUE DATE 1 08-May-13 08-May-13
CABLE TRAY AND LADDER 224 10-Sep-12 31-Jul-13 10-Sep-12 31-Jul-13
D10220 MATERIAL ACCEPTANCE (CABLE TRAY AND LADDER) 2 30-Jul-13 31-Jul-13
D9670 RFP TO VEND OR 1 10-Sep-12* 10-Sep-12
D9680 PO ISSUE DATE 1 11-Mar-13 11-Mar-13
D9690 DELIVERY ON SITE (CABLE TRAY AND LADDER) 2 26-Jul-13* 29-Jul-13
TUBING AND FITTING 249 11-Sep-12 06-Sep-13 11-Sep-12 06-Sep-13
D10230 MATERIAL ACCEPTANCE (TUBING AND FITTING) 2 05-Sep-13 06-Sep-13
D9700 RFP TO VEND OR 1 11-Sep-12* 11-Sep-12
D9710 PO ISSUE DATE 1 24-Apr-13 24-Apr-13
D9720 DELIVERY ON SITE (TUBING AND FITTING) 2 03-Sep-13* 04-Sep-13
EARTHING BOSS 199 11-Sep-12 27-Jun-13 11-Sep-12 27-Jun-13
D10240 MATERIAL ACCEPTANCE (EARTHING BOSS) 2 26-Jun-13 27-Jun-13
D9730 RFP TO VEND OR 1 11-Sep-12* 11-Sep-12
D9740 PO ISSUE DATE 1 27-Feb-13 27-Feb-13
D9750 DELIVERY ON SITE (EARTH ING  BOSS) 2 24-Jun-13* 25-Jun-13
SOCKET AND OUTLET 249 11-Sep-12 06-Sep-13 11-Sep-12 06-Sep-13
D10250 MATERIAL ACCEPTANCE (SOCKET AND OUTLET) 2 05-Sep-13 06-Sep-13
D9760 RFP TO VEND OR 1 11-Sep-12* 11-Sep-12
D9770 PO ISSUE DATE 1 14-Jun-13 14-Jun-13
D9780 DELIVERY ON SITE (SOCKET AND OUTLET) 2 03-Sep-13* 04-Sep-13
HEAT TRACING 286 10-Sep-12 28-Oct-13 10-Sep-12 28-Oct-13
D10260 MATERIAL ACCEPTANCE (HEAT T RACING ) 2 25-Oct-13* 28-Oct-13
D9790 RFP TO VEND OR 1 10-Sep-12* 10-Sep-12
D9800 PO ISSUE DATE 1 17-Jun-13 17-Jun-13
D9810 DELIVERY ON SITE (HEAT TR AC ING) 2 23-Oct-13* 24-Oct-13
LIGHTING & FIXTURES 294 10-Sep-12 07-Nov-13 10-Sep-12 07-Nov-13
D10270 MATERIAL ACCEPTANCE (LIGHTING FITTING) 2 06-Nov-13 07-Nov-13
D9820 RFP TO VEND OR 1 10-Sep-12* 10-Sep-12
D9830 PO ISSUE DATE 1 23-May-13 23-May-13
D9840 DELIVERY ON SITE (LIGHTING FITTING) 2 04-Nov-13* 05-Nov-13
MULTI CABLE TRANSIT 246 12-Sep-12 04-Sep-13 12-Sep-12 04-Sep-13
D10280 MATERIAL ACCEPTANCE (MULTI CABLE TRANSIT) 2 03-Sep-13 04-Sep-13

Actual Work Critical Remaining Work Summary Page 6 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
D9850 RFP TO VEND OR 1 12-Sep-12* 12-Sep-12
D9860 PO ISSUE DATE 1 22-May-13 22-May-13
D9870 DELIVERY ON SITE (MULTI CABLE TRANSIT) 2 29-Aug-13* 30-Aug-13
MISCELLANEOUS 242 14-Sep-12 30-Aug-13 14-Sep-12 30-Aug-13
D10290 MATERIAL ACCEPTANCE (MISCELLANOUES) 2 29-Aug-13 30-Aug-13
D9880 RFP TO VEND OR 1 14-Sep-12* 14-Sep-12
D9890 PO ISSUE DATE 1 09-Apr-13 09-Apr-13
D9900 DELIVERY ON SITE (MISCELLANOUES) 2 27-Aug-13* 28-Aug-13
CONTROL VALVES (PCV, LCV, FCV, ADV) 316 06-Sep-12 05-Dec-13 06-Sep-12 05-Dec-13
D10300 MATERIAL ACCEPTANCE (CONTROL VALVES (PCV, LCV, FCV, ADV)) 2 04-Dec-13 05-Dec-13
D9910 RFP TO VEND OR 1 06-Sep-12* 06-Sep-12
D9920 PO ISSUE DATE 1 25-Mar-13 25-Mar-13
D9930 DELIVERY ON SITE (CONTROL VALVES (PCV, LCV, FCV, ADV) ) 2 02-Dec-13* 03-Dec-13
NAVIGATION AIDS 282 10-Sep-12 22-Oct-13 10-Sep-12 22-Oct-13
D10310 MATERIAL ACCEPTANCE (NAVIGATION AID S) 2 21-Oct-13 22-Oct-13
D9940 RFP TO VEND OR 1 10-Sep-12* 10-Sep-12
D9950 PO ISSUE DATE 1 04-Apr-13 04-Apr-13
D9960 DELIVERY ON SITE (NAVIGATION AIDS) 2 17-Oct-13* 18-Oct-13
PUSH BUTTON 247 14-Sep-12 09-Sep-13 14-Sep-12 09-Sep-13
D10320 MATERIAL ACCEPTANCE (PUSH BUTTON) 2 06-Sep-13 09-Sep-13
D9970 RFP TO VEND OR 1 14-Sep-12* 14-Sep-12
D9980 PO ISSUE DATE 1 17-Jun-13 17-Jun-13
D9990 DELIVERY ON SITE (PUSH BUTTON) 2 04-Sep-13* 05-Sep-13
400V AC LV SWICH BOARD 272 17-Sep-12 15-Oct-13 17-Sep-12 15-Oct-13
D10000 RFP TO VEND OR 1 17-Sep-12* 17-Sep-12
D10010 PO ISSUE DATE 1 23-Apr-13 23-Apr-13
D10020 DELIVERY ON SITE (400V AC LV SWICH BOARD) 2 10-Oct-13* 11-Oct-13
D10030 MATERIAL ACCEPTANCE (400V AC LV SWICH BOARD) 2 14-Oct-13 15-Oct-13
UPS 301 27-Sep-12 05-Dec-13 27-Sep-12 05-Dec-13
D10040 RFP TO VEND OR 1 27-Sep-12* 27-Sep-12
D10050 PO ISSUE DATE 1 13-May-13 13-May-13
D10060 DELIVERY ON SITE (UPS) 2 02-Dec-13 03-Dec-13*
D10070 MATERIAL ACCEPTACE (UPS) 2 04-Dec-13 05-Dec-13
DISTRIBUTION BOARD 271 28-Sep-12 25-Oct-13 28-Sep-12 25-Oct-13
D10080 RFP TO VEND OR 1 28-Sep-12* 28-Sep-12
D10090 PO ISSUE DATE 1 24-Apr-13 24-Apr-13
D10100 DELIVERY ON SITE (DISTRIBUTION BOARD) 2 22-Oct-13* 23-Oct-13
D10110 MATERIAL ACCEPTANCE (DISTRIBUTION BOARD) 2 24-Oct-13 25-Oct-13
HELIDECK LIGHTING 164 21-Mar-13 11-Nov-13 21-Mar-13 11-Nov-13
D9610 RFP TO VEND OR 1 21-Mar-13* 21-Mar-13
D9620 PO ISSUE DATE 1 03-Jun-13 03-Jun-13
D9630 DELIVERY ON SITE (HELIDECK LIGHTING) 2 06-Nov-13* 07-Nov-13
D9640 MATERIAL ACCEPTANCE (HELIDECK LIGHTING) 2 08-Nov-13 11-Nov-13
INSTRUMENT (ETA) 334 10-Sep-12 03-Jan-14 10-Sep-12 03-Jan-14
FLOW METTER 289 12-Sep-12 04-Nov-13 12-Sep-12 04-Nov-13
D12000 RFP TO VEND OR 1 12-Sep-12* 12-Sep-12
D12010 PO ISSUE DATE 1 23-May-13 23-May-13
D12020 DELIVERY ON SITE (FLOW METTER) 2 30-Oct-13* 31-Oct-13
D12280 MATERIAL ACCEPTANCE (FLOW METTER) 2 01-Nov-13 04-Nov-13
FUSIBLE PLUG LOOP PANEL 246 11-Sep-12 03-Sep-13 11-Sep-12 03-Sep-13
D12030 RFP TO VEND OR 1 11-Sep-12* 11-Sep-12
D12040 PO ISSUE DATE 1 08-Mar-13 08-Mar-13
D12050 DELIVERY ON SITE (FUSIBLE PLUG LOOP PANEL) 2 28-Aug-13* 29-Aug-13
D12290 MATERIAL ACCEPTANCE (FUSIBLE PLUG LOOP PANEL) 2 30-Aug-13 03-Sep-13

Actual Work Critical Remaining Work Summary Page 7 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
PIG SIGNALLER 334 10-Sep-12 03-Jan-14 10-Sep-12 03-Jan-14
D12060 RFP TO VEND OR 1 10-Sep-12* 10-Sep-12
D12070 PO ISSUE DATE 1 22-Apr-13 22-Apr-13
D12080 DELIVERY ON SITE (PIG SIGNALLER) 2 30-Dec-13* 31-Dec-13
D12300 MATERIAL ACCEPTANCE (PIG SIGNALLER) 2 02-Jan-14 03-Jan-14
SAFETY RELIEF VALVE 293 11-Sep-12 07-Nov-13 11-Sep-12 07-Nov-13
D12090 RFP TO VEND OR 1 11-Sep-12* 11-Sep-12
D12100 PO ISSUE DATE 1 18-Mar-13 18-Mar-13
D12110 DELIVERY ON SITE (SAFETY RELIEF VALVE) 2 04-Nov-13* 05-Nov-13
D12310 MATERIAL ACCEPTANCE (SAFETY RELIEF VALVE) 2 06-Nov-13 07-Nov-13
RESTRICTION ORIFICES, ORIFICES PLATE AND FLANGES 271 14-Sep-12 11-Oct-13 14-Sep-12 11-Oct-13
D12120 RFP TO VEND OR 1 14-Sep-12* 14-Sep-12
D12130 PO ISSUE DATE 1 24-May-13 24-May-13
D12140 DELIVERY ON SITE (RESTRICTION ORIFICES, ORIFICES PLATE AND FLANGES) 2 08-Oct-13* 09-Oct-13
D12320 MATERIAL ACCEPTANCE (RESTRICTION ORIFICES, ORIFICES PLATE AND FLANGES) 2 10-Oct-13 11-Oct-13
SAND MONITORING 274 12-Sep-12 14-Oct-13 12-Sep-12 14-Oct-13
D12150 RFP TO VEND OR 1 12-Sep-12* 12-Sep-12
D12160 PO ISSUE DATE 1 04-Jul-13 04-Jul-13
D12170 DELIVERY ON SITE (SAND MONITORING) 2 09-Oct-13* 10-Oct-13
D12330 MATERIAL ACCEPTANCE (SAND MONITORING) 2 11-Oct-13 14-Oct-13
PRESSURE GAUGES 283 11-Sep-12 24-Oct-13 11-Sep-12 24-Oct-13
D12180 RFP TO VEND OR 1 11-Sep-12* 11-Sep-12
D12190 PO ISSUE DATE 1 03-Jun-13 03-Jun-13
D12200 DELIVERY ON SITE (PRESSURE GAUGES (PG, PDG, T G)) 2 21-Oct-13* 22-Oct-13
D12340 MATERIAL ACCEPTANCE (PRESSURE GAUGES (PG, PDG, TG)) 2 23-Oct-13 24-Oct-13
PRESSURE REGULATOR VALVES 279 11-Sep-12 18-Oct-13 11-Sep-12 18-Oct-13
D12210 RFP TO VEND OR 1 11-Sep-12* 11-Sep-12
D12220 PO ISSUE DATE 1 09-May-13 09-May-13
D12230 DELIVERY ON SITE (PRESSURE REGULATOR VALVES) 2 15-Oct-13* 16-Oct-13
D12240 MATERIAL ACCEPTANCE (PRESSURE REGULATOR VALVES) 2 17-Oct-13 18-Oct-13
LEVEL GAUGES 304 14-Sep-12 27-Nov-13 14-Sep-12 27-Nov-13
D12250 RFP TO VEND OR 1 14-Sep-12* 14-Sep-12
D12260 PO ISSUE DATE 1 15-Mar-13 15-Mar-13
D12270 DELIVERY ON SITE (LEVEL GAUGES) 2 22-Nov-13* 25-Nov-13
D12350 MATERIAL ACCEPTANCE (LEVEL GAUGES) 2 26-Nov-13 27-Nov-13
348 04-Jan-13 10-Mar-14 04-Jan-13 10-Mar-14
CONSTRUCTION
FRONT-END ACTIVITIES/ MOBILIZATION 289 04-Jan-13 19-Dec-13 04-Jan-13 19-Dec-13
MOBILIZATION OF PROJECT MANAGEMENT TEAM 7 19-Feb-13 26-Feb-13 19-Feb-13 26-Feb-13
B1000 MOBILISATION OF PROJECT MANAGEMENT TEAM 7 19-Feb-13 26-Feb-13
PROJECT PLANNING AND MONITO RING F ORMAT 42 30-Mar-13 21-May-13 30-Mar-13 21-May-13
B1010 60 DAYS SCHEDULE 9 30-Mar-13 09-Apr-13
B1015 PLANING PACKAGE 33 10-Apr-13 21-May-13
YARD PREPARATIONS 32 30-Jan-13 15-Mar-13 30-Jan-13 15-Mar-13
B1020 FABR ICATION YARD PREPARATION 21 20-Feb-13 15-Mar-13
B1030 SITE OFFICE PREPARATION 26 06-Feb-13 15-Mar-13
B1040 BUILD UP MATERIAL AND EQUIPMENT STORAGE AND FENCE PREPARATION 20 30-Jan-13 01-Mar-13
B1050 WORKSHOP AND FACILITIES PREPARATION 21 08-Feb-13 12-Mar-13
CONCRETE FOUNDATION / TEMPORARY SUPPORT FABRICATION 133 09-May-13 11-Oct-13 09-May-13 11-Oct-13
CONCRETE FOUNDATION/ TEMPORARY SUPPORTS AT FINAL POSITION FABRICATION 40 06-Jul-13 21-Aug-13 06-Jul-13 21-Aug-13
TEMPORARY SUPPORTS AT FINAL POSITION FABRICATION 25 24-Jul-13 21-Aug-13 24-Jul-13 21-Aug-13
B8940 MARK/ CUT TEMPORARY SUPPORTS AT FINAL POSITION 10 24-Jul-13 03-Aug-13
B8950 FIT UP TEMPORARY SUPPORTS AT FINAL POSITION 15 26-Jul-13 12-Aug-13
B8960 WELDING TEMPORARY SUPPORTS AT FINAL POSITION 18 29-Jul-13 17-Aug-13

Actual Work Critical Remaining Work Summary Page 8 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
B8970 NDT TEMPORARY SUPPORTS AT FINAL POSITION 16 03-Aug-13 21-Aug-13
CONCRETE FOUNDATION SUPPORTS AT FINAL POSITION FABRICATION 30 06-Jul-13 09-Aug-13 06-Jul-13 09-Aug-13
B8980 CONCRETE FOUNDATION SUPPORTS AT FINAL POSITION 30 06-Jul-13 09-Aug-13
CONCRETE FOUNDATION/ TEMPORARY SUPPORTS CELLAR DECK FABRICATION 15 09-May-13 25-May-13 09-May-13 25-May-13
TEMPORARY SUPPORTS CELLAR DECK FABRICATION 15 09-May-13 25-May-13 09-May-13 25-May-13
B8840 MARK/ CUT TEMPORARY SUPPORTS CELLAR DECK 9 09-May-13 18-May-13
B8850 FIT UP TEMPORARY SUPPORTS CELLAR DECK 9 11-May-13 21-May-13
B8860 WELDING TEMPORARY SUPPORTS CELLAR DECK 9 14-May-13 23-May-13
B8870 NDT TEMPORARY SUPPORTS CELLAR DECK 9 16-May-13 25-May-13
CONCRETE FOUNDATION SUPPORTS CELLAR DECK FABRICATION 9 09-May-13 18-May-13 09-May-13 18-May-13
B8880 CONCRETE FOUNDATION SUPPORTS CELLAR DECK FABR ICATION 9 09-May-13 18-May-13
CONCRETE FOUNDATION/ TEMPORARY SUPPORTS MAIN DECK FABRICATION 26 10-Jun-13 09-Jul-13 10-Jun-13 09-Jul-13
TEMPORARY SUPPORTS MAIN DECK FABRICATION 23 13-Jun-13 09-Jul-13 13-Jun-13 09-Jul-13
B8990 MARK/ CUT TEMPORARY SUPPORTS MAIN DECK 10 13-Jun-13 24-Jun-13
B9000 FIT UP TEMPORARY SUPPORTS MAIN DECK 15 15-Jun-13 02-Jul-13
B9010 WELDING TEMPORARY SUPPORTS MAIN DECK 18 18-Jun-13 08-Jul-13
B9020 NDT TEMPORARY SUPPORTS MAIN DECK 14 24-Jun-13 09-Jul-13
CONCRETE FOUNDATION SUPPORTS MAIN DECK FABRICATION 15 10-Jun-13 26-Jun-13 10-Jun-13 26-Jun-13
B9030 CONCRETE FOUNDATION SUPPORTS MAIN DECK 15 10-Jun-13 26-Jun-13
TEMPORARY SUPPORTS VENT BOOM FABRICATION 23 16-Sep-13 11-Oct-13 16-Sep-13 11-Oct-13
B9040 MARK/ CUT TEMPORARY SUPPORTS VENT BOOM 10 16-Sep-13 26-Sep-13
B9050 FIT UP TEMPORARY SUPPORTS MAIN DECK 15 18-Sep-13 04-Oct-13
B9060 WELDING TEMPORARY SUPPORTS MAIN DECK 18 20-Sep-13 10-Oct-13
B9070 NDT TEMPORARY SUPPORTS MAIN DECK 14 26-Sep-13 11-Oct-13
MOBILISATION OF SUB-CONTRACTOR 289 04-Jan-13 19-Dec-13 04-Jan-13 19-Dec-13
MOBILISATION OF DETAIL ENGINEEING SUB-CONTRACTOR 32 04-Jan-13 18-Feb-13 04-Jan-13 18-Feb-13
B11360 TENDER D.E SUB-CONTRACTOR 21 04-Jan-13 28-Jan-13
B11370 AWARD D.E SUB-CONTRACTOR 1 06-Feb-13 06-Feb-13
B11380 MOBILISE D.E SUB-CONTRACTOR (READY TO COMMENCE WORK) 2 08-Feb-13 18-Feb-13
MOBILISATION OF NDT SUB-CONTRACTOR 47 09-Mar-13 06-May-13 09-Mar-13 06-May-13
B1160 TENDER NDT SUB-CONTRACTOR 30 09-Mar-13 12-Apr-13
B1170 AWARD NDT SUB-CONTRACTOR 3 13-Apr-13 16-Apr-13
B1180 MOBILISE NDT SUB-CONTRACTOR (READY TO COMMENCE WORK) 4 02-May-13 06-May-13
MOBILISATION OF HEAT TREATMENT SUB-CONTRACTOR 47 09-Mar-13 06-May-13 09-Mar-13 06-May-13
B11390 TENDER HEAT TREATMENT SUB-CONTRACTOR 30 09-Mar-13 12-Apr-13
B11400 AWARD HEAT TREATMENT SUB-CONTRACTOR 3 13-Apr-13 16-Apr-13
B11410 MOBILISE HEAT TREATMENT SUB-CONTRACTOR (READY TO COMMENCE WORK) 4 02-May-13 06-May-13
MOBILISATION OF LEAK TEST & BOLT TENSIO NING SUB-CO NTRACTOR 55 16-Sep-13 18-Nov-13 16-Sep-13 18-Nov-13
B1130 TENDERING 30 16-Sep-13 19-Oct-13
B1140 AWARD SUB-CONTRACTOR 3 29-Oct-13 31-Oct-13
B1150 MOBILISE SUB-CONTRACTOR (READY TO COMMENCE WORK) 4 14-Nov-13 18-Nov-13
MOBILISATION OF INSULATION SUB-CONTRACTOR 84 24-Jul-13 30-Oct-13 24-Jul-13 30-Oct-13
B11420 TENDERING INSULATION SUB-CONTRACTOR 30 24-Jul-13 27-Aug-13
B11430 AWARD INSULAT IO N SUB-CON TR ACTOR 3 06-Sep-13 09-Sep-13
B11440 MOBILISE INSULATION SUB-CONTRACTOR (READY TO C OMMENC E WORK) 4 26-Oct-13 30-Oct-13
MOBILISATION OF WEIGHING & LOAD OUT SUB-CONTRACTOR 49 24-Oct-13 19-Dec-13 24-Oct-13 19-Dec-13
B1190 TENDER SUB-CONTRACTOR 24 24-Oct-13 20-Nov-13
B1200 AWARD SUB-CONTRACTOR 12 21-Nov-13 04-Dec-13
B1210 MOBILISE SUB-CONTRACTOR (READY TO COMMENCE WORK) 2 18-Dec-13 19-Dec-13
WQT & WPS 104 28-Mar-13 30-Jul-13 28-Mar-13 30-Jul-13
B1220 PREPARATIO N PQ R/ W PS FO R ST RUCTUR AL 30 28-Mar-13 04-May-13
B1230 PRE-QUALITIFICATION STRUCTURE WELDER 16 06-May-13 23-May-13
B1240 PREPARATIO N PQ R/ W PS FO R PIPING 45 17-May-13 08-Jul-13
B1250 PREPARATIO N W QT FOR PIPING 25 02-Jul-13 30-Jul-13

Actual Work Critical Remaining Work Summary Page 9 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
PANEL COATING SYSTEM QUALIFICATION TEST 24 15-May-13 11-Jun-13 15-May-13 11-Jun-13
B1260 PANEL TEST/ COATING SYSTEM QUALIFICATION TEST 24 15-May-13 11-Jun-13
ONSHORE FABRICATION 250 20-Apr-13 21-Feb-14 20-Apr-13 21-Feb-14
STRUCTURAL 215 21-May-13 28-Jan-14 21-May-13 28-Jan-14
FABRICATION OF TUBULARS 63 01-Jun-13 13-Aug-13 01-Jun-13 13-Aug-13
FABRICATION OF PIPE LEGS 37 01-Jun-13 13-Jul-13 01-Jun-13 13-Jul-13
E1550 MARK/ CUT PIPE LEGS 18 01-Jun-13 21-Jun-13
E1560 FIT UP PIPE LEGS 20 13-Jun-13 05-Jul-13
E1570 WELDING PIPE LEGS 22 15-Jun-13 10-Jul-13
E1580 NDT PIPE LEGS 20 21-Jun-13 13-Jul-13
FABRICATION OF BRACING 33 06-Jul-13 13-Aug-13 06-Jul-13 13-Aug-13
E1670 MARK/ CUT BRACING PIPE 12 06-Jul-13 19-Jul-13
E1680 FIT UP BRACING PIPE 15 12-Jul-13 29-Jul-13
E1690 WELDING BRACING PIPE 18 18-Jul-13 07-Aug-13
E1700 NDT BRACING PIPE 18 24-Jul-13 13-Aug-13
FABRICATION OF STRUCTURAL MEMBERS 191 21-May-13 30-Dec-13 21-May-13 30-Dec-13
FABRICATION OF CELLAR DECK FRAME 88 21-May-13 30-Aug-13 21-May-13 30-Aug-13
FABRICATION WF BEAMS OF CELLAR DECK 13 01-Jun-13 15-Jun-13 01-Jun-13 15-Jun-13
E20000 MARK/ CUT PLATE STEEL FOR WF CELLAR DECK 3 01-Jun-13 04-Jun-13
E20010 FIT UP PLATE STEEL FOR WF CELLAR  DECK 6 03-Jun-13 08-Jun-13
E20020 WELDING WF FOR CELLAR DECK 7 06-Jun-13 13-Jun-13
E20030 NDT WF FOR CELLAR DECK 5 11-Jun-13 15-Jun-13
FABRICATION OF CELLAR DECK PART II 72 21-May-13 12-Aug-13 21-May-13 12-Aug-13
FABRICATION OF PRIMARY FRAME PART II 44 21-May-13 10-Jul-13 21-May-13 10-Jul-13
E20040 LAYOUT TEMPORARY SU PPO RTS FOR CELLAR DECK PART II 6 21-May-13 27-May-13
E20050 INSTALL PIPE LEGS FOR CELLAR DECK PART II 4 05-Jun-13 08-Jun-13
E20060 MARK/ CUT PRIMARY FRAME FOR CELLAR DECK PART II 12 01-Jun-13 14-Jun-13
E20070 FIT UP PRIMARY FRAME FOR CELLAR DECK PART II 15 10-Jun-13 26-Jun-13
E20080 WELDING PRIMARY FRAME FOR CELLAR DECK PART II 10 25-Jun-13 05-Jul-13
E20090 NDT PRIMARY FRAME FOR CELLAR DECK PART II 10 29-Jun-13 10-Jul-13
FABRICATION OF SECONDARY FRAME PART II 33 13-Jun-13 20-Jul-13 13-Jun-13 20-Jul-13
E20100 MARK/ CUT SECONDARY FRAME FO R CELLAR DECK PART II 12 13-Jun-13 26-Jun-13
E20110 FIT UP SECONDARY FRAME FOR CELLAR DECK PART II 15 26-Jun-13 12-Jul-13
E20120 WELDING SECONDARY FRAME FOR CELLAR DECK PART II 15 01-Jul-13 17-Jul-13
E20130 NDT SECONDARY FRAME FOR CELLAR DECK PART II 15 04-Jul-13 20-Jul-13
FABRICATION OF JOINT DETAIL PART II 43 05-Jun-13 24-Jul-13 05-Jun-13 24-Jul-13
E20140 MARK/ CUT JOINT DETAIL FOR  CELLAR DECK PART II 15 05-Jun-13 21-Jun-13
E20150 FIT UP JOINT DETAIL FOR CELLAR DECK PART II 25 15-Jun-13 13-Jul-13
E20160 WELDING JOINT DETAIL FOR CELLAR DECK PART II 20 24-Jun-13 16-Jul-13
E20170 NDT JOINT DETAIL F OR CELLAR DECK PART II 20 02-Jul-13 24-Jul-13
FABRICATION OF DECK PLATING PART II 40 27-Jun-13 12-Aug-13 27-Jun-13 12-Aug-13
E20180 MARK/ CUT DECK PLATING FOR CELLAR DECK PART II 15 27-Jun-13 13-Jul-13
E20190 FIT UP DECK PLATING FOR CELLAR DECK PART II 20 09-Jul-13 31-Jul-13
E20200 WELDING DECK PLATING FOR CELLAR DECK PART II 20 15-Jul-13 06-Aug-13
E20210 NDT DECK PLATING FOR CELLAR DECK PART II 20 20-Jul-13 12-Aug-13
FABRICATION OF CELLAR DECK PART III 75 27-May-13 21-Aug-13 27-May-13 21-Aug-13
FABRICATION OF PRIMARY FRAME PART III 41 27-May-13 12-Jul-13 27-May-13 12-Jul-13
E20390 LAYOUT TEMPORARY SU PPO RTS FOR CELLAR DECK PART III 6 27-May-13 01-Jun-13
E20400 MARK/ CUT PRIMARY FRAME FOR CELLAR DECK PART III 12 05-Jun-13 18-Jun-13
E20410 FIT UP PRIMARY FRAME FOR CELLAR DECK PART III 15 12-Jun-13 28-Jun-13
E20420 WELDING PRIMARY FRAME FOR CELLAR DECK PART III 10 27-Jun-13 08-Jul-13
E20430 NDT PRIMARY FRAME FOR CELLAR DECK PART III 10 02-Jul-13 12-Jul-13
FABRICATION OF SECONDARY FRAME PART III 40 14-Jun-13 30-Jul-13 14-Jun-13 30-Jul-13
E20440 MARK/ CUT SECONDARY FRAME FO R CELLAR DECK PART III 12 14-Jun-13 27-Jun-13

Actual Work Critical Remaining Work Summary Page 10 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
E20450 FIT UP SECONDARY FRAME FOR CELLAR DECK PART III 18 28-Jun-13 18-Jul-13
E20460 WELDING SECONDARY FRAME FOR CELLAR DECK PART III 18 04-Jul-13 24-Jul-13
E20470 NDT SECONDARY FRAME FOR CELLAR DECK PART III 18 10-Jul-13 30-Jul-13
FABRICATION OF JOINT DETAIL PART III 35 14-Jun-13 24-Jul-13 14-Jun-13 24-Jul-13
E20480 MARK/ CUT JOINT DETAIL FOR  CELLAR DECK PART III 15 14-Jun-13 01-Jul-13
E20490 FIT UP JOINT DETAIL FOR CELLAR DECK PART III 20 20-Jun-13 12-Jul-13
E20500 WELDING JOINT DETAIL FOR CELLAR DECK PART III 20 26-Jun-13 18-Jul-13
E20510 NDT JOINT DETAIL F OR CELLAR DECK PART III 20 02-Jul-13 24-Jul-13
FABRICATION OF DECK PLATING PART III 44 02-Jul-13 21-Aug-13 02-Jul-13 21-Aug-13
E20520 MARK/ CUT DECK PLATING FOR CELLAR DECK PART III 15 02-Jul-13 18-Jul-13
E20530 FIT UP DECK PLATING FOR CELLAR DECK PART III 20 16-Jul-13 07-Aug-13
E20540 WELDING DECK PLATING FOR CELLAR DECK PART III 22 22-Jul-13 15-Aug-13
E20550 NDT DECK PLATING FOR CELLAR DECK PART III 22 27-Jul-13 21-Aug-13
FABRICATION OF CELLAR DECK PART I 83 27-May-13 30-Aug-13 27-May-13 30-Aug-13
FABRICATION OF PRIMARY FRAME PART I 46 27-May-13 18-Jul-13 27-May-13 18-Jul-13
E20220 LAYOUT TEMPORARY SU PPO RTS FOR CELLAR DECK PART I 6 27-May-13 01-Jun-13
E20230 MARK/ CUT PRIMARY FRAME FOR CELLAR DECK PART I 12 07-Jun-13 20-Jun-13
E20240 FIT UP PRIMARY FRAME FOR CELLAR DECK PART I 15 14-Jun-13 01-Jul-13
E20250 WELDING PRIMARY FRAME FOR CELLAR DECK PART I 10 02-Jul-13 12-Jul-13
E20260 NDT PRIMARY FRAME FOR CELLAR DECK PART I 10 08-Jul-13 18-Jul-13
FABRICATION OF SECONDARY FRAME PART I 44 19-Jun-13 08-Aug-13 19-Jun-13 08-Aug-13
E20270 MARK/ CUT SECONDARY FRAME FO R CELLAR DECK PART I 12 19-Jun-13 02-Jul-13
E20280 FIT UP SECONDARY FRAME FOR CELLAR DECK PART I 12 08-Jul-13 20-Jul-13
E20290 WELDING SECONDARY FRAME FOR CELLAR DECK PART I 18 13-Jul-13 02-Aug-13
E20300 NDT SECONDARY FRAME FOR CELLAR DECK PART I 18 19-Jul-13 08-Aug-13
FABRICATION OF JOINT DETAIL PART I 35 17-Jun-13 26-Jul-13 17-Jun-13 26-Jul-13
E20310 MARK/ CUT JOINT DETAIL FOR  CELLAR DECK PART I 15 17-Jun-13 03-Jul-13
E20320 FIT UP JOINT DETAIL FOR CELLAR DECK PART I 20 22-Jun-13 15-Jul-13
E20330 WELDING JOINT DETAIL FOR CELLAR DECK PART I 20 28-Jun-13 20-Jul-13
E20340 NDT JOINT DETAIL F OR CELLAR DECK PART I 20 04-Jul-13 26-Jul-13
FABRICATION OF DECK PLATING PART I 48 06-Jul-13 30-Aug-13 06-Jul-13 30-Aug-13
E20350 MARK/ CUT DECK PLATING FOR CELLAR DECK PART I 15 06-Jul-13 23-Jul-13
E20360 FIT UP DECK PLATING FOR CELLAR DECK PART I 20 25-Jul-13 16-Aug-13
E20370 WELDING DECK PLATING FOR CELLAR DECK PART I 22 31-Jul-13 24-Aug-13
E20380 NDT DECK PLATING FOR CELLAR DECK PART I 22 06-Aug-13 30-Aug-13
FABRICATION OF MAIN DECK FRAME 115 17-Jun-13 29-Oct-13 17-Jun-13 29-Oct-13
FABRICATION WF BEAMS OF MAIN DECK 29 17-Jun-13 19-Jul-13 17-Jun-13 19-Jul-13
E22540 MARK/ CUT PLATE STEEL FOR WF MAIN DECK 7 17-Jun-13 24-Jun-13
E22550 FIT UP PLATE STEEL FOR WF MAIN DECK 12 20-Jun-13 03-Jul-13
E22560 WELDING WF FOR MAIN DECK 12 28-Jun-13 11-Jul-13
E22570 NDT WF FOR MAIN DECK 12 06-Jul-13 19-Jul-13
FABRICATION OF MAIN DECK PART II 83 09-Jul-13 14-Oct-13 09-Jul-13 14-Oct-13
FABRICATION OF PRIMARY FRAME PART II 46 09-Jul-13 30-Aug-13 09-Jul-13 30-Aug-13
E22640 LAYOUT TEMPORARY SU PPO RTS FOR MAIN DECK PART II 6 10-Jul-13 16-Jul-13
E22650 INSTALL PIPE LEGS FOR MAIN DECK PART II 5 17-Jul-13 22-Jul-13
E22660 MARK/ CUT PRIMARY FRAME FOR MAIN DECK PART II 10 09-Jul-13 19-Jul-13
E22670 FIT UP PRIMARY FRAME FOR MAIN DECK PART II 15 23-Jul-13 08-Aug-13
E22680 WELDING PRIMARY FRAME FOR MAIN DECK PART II 15 08-Aug-13 24-Aug-13
E22690 NDT PRIMARY FRAME FOR MAIN DECK PART II 15 14-Aug-13 30-Aug-13
FABRICATION OF SECONDARY FRAME PART II 46 20-Jul-13 12-Sep-13 20-Jul-13 12-Sep-13
E22700 MARK/ CUT SECONDARY FRAME FO R MAIN DECK PART II 12 20-Jul-13 02-Aug-13
E22710 FIT UP SECONDARY FRAME FOR MAIN DECK PART II 15 10-Aug-13 27-Aug-13
E22720 WELDING SECONDARY FRAME FOR MAIN DECK PART II 18 16-Aug-13 06-Sep-13
E22730 NDT SECONDARY FRAME FOR MAIN DECK PART II 18 22-Aug-13 12-Sep-13

Actual Work Critical Remaining Work Summary Page 11 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
FABRICATION OF JOINT DETAIL PART II 54 17-Jul-13 18-Sep-13 17-Jul-13 18-Sep-13
E22740 MARK/ CUT JOINT DETAIL FOR  MAIN DECK PART II 20 17-Jul-13 08-Aug-13
E22750 FIT UP JOINT DETAIL FOR MAIN DECK PART II 25 10-Aug-13 09-Sep-13
E22760 WELDING JOINT DETAIL FOR MAIN DECK PART II 25 14-Aug-13 12-Sep-13
E22770 NDT JOINT DETAIL F OR MAIN DECK PART II 25 20-Aug-13 18-Sep-13
FABRICATION OF DECK PLATING PART II 58 07-Aug-13 14-Oct-13 07-Aug-13 14-Oct-13
E22780 MARK/ CUT DECK PLATING FOR MAIN DECK PART II 20 07-Aug-13 29-Aug-13
E22790 FIT UP DECK PLATING FOR MAIN DECK PART II 20 28-Aug-13 20-Sep-13
E22800 WELDING DECK PLATING FOR MAIN DECK PART II 25 10-Sep-13 08-Oct-13
E22810 NDT DECK PLATING FOR MAIN DECK PART II 25 16-Sep-13 14-Oct-13
FABRICATION OF MAIN DECK PART III 74 26-Jul-13 21-Oct-13 26-Jul-13 21-Oct-13
FABRICATION OF PRIMARY FRAME PART III 36 26-Jul-13 06-Sep-13 26-Jul-13 06-Sep-13
E22820 LAYOUT TEMPORARY SU PPO RTS FOR MAIN DECK PART III 4 29-Jul-13 01-Aug-13
E22830 MARK/ CUT PRIMARY FRAME FOR MAIN DECK PART III 8 26-Jul-13 03-Aug-13
E22840 FIT UP PRIMARY FRAME FOR MAIN DECK PART III 12 02-Aug-13 15-Aug-13
E22850 WELDING PRIMARY FRAME FOR MAIN DECK PART III 15 14-Aug-13 30-Aug-13
E22860 NDT PRIMARY FRAME FOR MAIN DECK PART III 15 20-Aug-13 06-Sep-13
FABRICATION OF SECONDARY FRAME PART III 34 07-Aug-13 16-Sep-13 07-Aug-13 16-Sep-13
E22870 MARK/ CUT SECONDARY FRAME FO R MAIN DECK PART III 10 07-Aug-13 17-Aug-13
E22880 FIT UP SECONDARY FRAME FOR MAIN DECK PART III 12 14-Aug-13 27-Aug-13
E22890 WELDING SECONDARY FRAME FOR MAIN DECK PART III 18 20-Aug-13 10-Sep-13
E22900 NDT SECONDARY FRAME FOR MAIN DECK PART III 18 26-Aug-13 16-Sep-13
FABRICATION OF JOINT DETAIL PART III 39 13-Aug-13 27-Sep-13 13-Aug-13 27-Sep-13
E22910 MARK/ CUT JOINT DETAIL FOR  MAIN DECK PART III 15 13-Aug-13 29-Aug-13
E22920 FIT UP JOINT DETAIL FOR MAIN DECK PART III 20 20-Aug-13 12-Sep-13
E22930 WELDING JOINT DETAIL FOR MAIN DECK PART III 25 23-Aug-13 21-Sep-13
E22940 NDT JOINT DETAIL F OR MAIN DECK PART III 25 29-Aug-13 27-Sep-13
FABRICATION OF DECK PLATING PART III 49 24-Aug-13 21-Oct-13 24-Aug-13 21-Oct-13
E22950 MARK/ CUT DECK PLATING FOR MAIN DECK PART III 18 24-Aug-13 14-Sep-13
E22960 FIT UP DECK PLATING FOR MAIN DECK PART III 22 05-Sep-13 30-Sep-13
E22970 WELDING DECK PLATING FOR MAIN DECK PART III 25 17-Sep-13 15-Oct-13
E22980 NDT DECK PLATING FOR MAIN DECK PART III 25 23-Sep-13 21-Oct-13
FABRICATION OF MAIN DECK PART I 71 07-Aug-13 29-Oct-13 07-Aug-13 29-Oct-13
FABRICATION OF PRIMARY FRAME PART I 48 07-Aug-13 02-Oct-13 07-Aug-13 02-Oct-13
E22990 LAYOUT TEMPORARY SU PPO RTS FOR MAIN DECK PART I 4 29-Aug-13 03-Sep-13
E23000 MARK/ CUT PRIMARY FRAME FOR MAIN DECK PART I 8 07-Aug-13 15-Aug-13
E23010 FIT UP PRIMARY FRAME FOR MAIN DECK PART I 12 04-Sep-13 17-Sep-13
E23020 WELDING PRIMARY FRAME FOR MAIN DECK PART I 10 16-Sep-13 26-Sep-13
E23030 NDT PRIMARY FRAME FOR MAIN DECK PART I 10 21-Sep-13 02-Oct-13
FABRICATION OF SECONDARY FRAME PART I 48 19-Aug-13 14-Oct-13 19-Aug-13 14-Oct-13
E23040 MARK/ CUT SECONDARY FRAME FO R MAIN DECK PART I 10 19-Aug-13 29-Aug-13
E23050 FIT UP SECONDARY FRAME FOR MAIN DECK PART I 12 16-Sep-13 28-Sep-13
E23060 WELDING SECONDARY FRAME FOR MAIN DECK PART I 15 21-Sep-13 08-Oct-13
E23070 NDT SECONDARY FRAME FOR MAIN DECK PART I 15 27-Sep-13 14-Oct-13
FABRICATION OF JOINT DETAIL PART I 56 24-Aug-13 29-Oct-13 24-Aug-13 29-Oct-13
E23080 MARK/ CUT JOINT DETAIL FOR  MAIN DECK PART I 15 24-Aug-13 11-Sep-13
E23090 FIT UP JOINT DETAIL FOR MAIN DECK PART I 20 21-Sep-13 14-Oct-13
E23100 WELDING JOINT DETAIL FOR MAIN DECK PART I 25 25-Sep-13 23-Oct-13
E23110 NDT JOINT DETAIL F OR MAIN DECK PART I 25 01-Oct-13 29-Oct-13
FABRICATION OF HELI DECK 20 05-Dec-13 27-Dec-13 05-Dec-13 27-Dec-13
E1300 INSTALL HELI DECK FRAME 20 05-Dec-13 27-Dec-13
FABRICATIN OF VENT BOOM 68 12-Oct-13 30-Dec-13 12-Oct-13 30-Dec-13
E1310 LAYOUT SUPPORTS FOR VENT BOOM 3 12-Oct-13 15-Oct-13
E1320 MARK/ CUTTING FRAME FOR VENT BOOM 12 16-Oct-13 29-Oct-13

Actual Work Critical Remaining Work Summary Page 12 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
E1330 FIT UP FRAME FOR VENT BO OM 30 24-Oct-13 27-Nov-13
E1340 WELDING FRAME FOR VENT BOOM 36 09-Nov-13 20-Dec-13
E1350 NDT FRAME FOR VENT BOOM 30 26-Nov-13 30-Dec-13
FABRICATION OF OTHER ITEMS 87 11-Sep-13 20-Dec-13 11-Sep-13 20-Dec-13
E1360 FABR ICATION HANDRAIL 48 14-Oct-13 09-Dec-13
E1370 FABR ICATION LADDER 48 14-Oct-13 07-Dec-13
E1380 FABR ICATION STAIRWAY 48 26-Oct-13 20-Dec-13
E1390 FABR ICATION DECK DRAIN 48 14-Oct-13 07-Dec-13
E1400 FABR ICATION EQUIPMENT MOUN TING 48 14-Oct-13 07-Dec-13
E1410 FABR ICATION LIFE RAFT SUPPORT 48 14-Oct-13 07-Dec-13
E1430 FABR ICATION LIFTING PADEYE 48 14-Oct-13 07-Dec-13
E1440 FABR ICATION VENT BO OM SUPPORT 48 01-Oct-13 25-Nov-13
E1450 FABR ICATION MONORAIL 48 14-Oct-13 07-Dec-13
E1480 FABR ICATION SECURITY GATE AND WALL 48 14-Oct-13 07-Dec-13
E1500 FABR ICATION CONDUCTO R G UIDE 24 14-Oct-13 09-Nov-13
E1510 FABR ICATION HATCH COVER 24 14-Oct-13 09-Nov-13
E1520 FABR ICATION CRANE ACCESS PLATFORM 24 19-Oct-13 15-Nov-13
E1530 FABR ICATION FIRE & BLASTWALL 24 11-Sep-13 08-Oct-13
E1540 FABR ICATION PLATFORM NAME PLATE 12 06-Nov-13 19-Nov-13
E1545 FABR ICATION CONES (4 PCS) 12 16-Sep-13 28-Sep-13
ERECTION 127 22-Aug-13 18-Jan-14 22-Aug-13 18-Jan-14
E1730 LAYOUT/ERECTION SUPPORTS & LOAD OUT BEAMS TO FIN AL POSITION 7 22-Aug-13 29-Aug-13
E1750 CELLAR DECK PART II STACK UP 7 03-Sep-13* 10-Sep-13
E1760 CELLAR DECK PART III STACK UP 7 12-Sep-13 19-Sep-13
E1765 CELLAR DECK PART I STACK UP 7 21-Sep-13 28-Sep-13
E1770 PIPE LEGS ERECTION 15 30-Sep-13 16-Oct-13
E1775 BRACING PIPE ERECTION (PART 1) 20 30-Sep-13 22-Oct-13
E1780 BLAST WALL ERECTION (PART 1) 10 09-Oct-13 19-Oct-13
E1790 MAIN DECK PART II (AXIS 1/2) STACK UP 10 05-Nov-13 15-Nov-13
E1810 MAIN DECK PART III (AXIS 2/2a) STACK UP 8 20-Nov-13 28-Nov-13
E1820 MAIN DECK PART I (AXIS 1a/1) STACK UP 7 25-Nov-13 02-Dec-13
E1825 HELI DECK ERECTION 6 28-Dec-13 04-Jan-14
E1830 BRACING ERECTION (REMAINING PART) 15 09-Dec-13 25-Dec-13
E1833 BLAST WALL ERECTION (REMAINING PART) 12 09-Dec-13 21-Dec-13
E1835 ERECTION OTHER ITEMS 21 25-Dec-13 18-Jan-14
TRIAL FIT AND WEIGH ING 21 04-Jan-14 28-Jan-14 04-Jan-14 28-Jan-14
E1840 VENT BOOM TRIAL FIT 6 16-Jan-14 22-Jan-14
E1850 FABR ICATE/ ERECTION PADEYES 14 04-Jan-14 20-Jan-14
E1855 TRIAL FIT/ LAYOUT T&I SLING S 7 21-Jan-14 28-Jan-14
E1860 TOPSIDE WEIGHING 2 09-Jan-14* 10-Jan-14
PIPING/ PLUMBING 199 15-Jun-13 14-Feb-14 15-Jun-13 14-Feb-14
FABRICATION OF PIPE/PLUMBING SUPPORTS 149 15-Jun-13 06-Dec-13 15-Jun-13 06-Dec-13
E1870 FABR ICATE PIPE SUPPORT 60 15-Jun-13 23-Aug-13
E2280 FABR ICATE PIPE SPOOL 105 06-Aug-13 06-Dec-13
INSTALLATIO N O F PIPE/PLUMBIN G SUPPORTS 105 10-Sep-13 10-Jan-14 10-Sep-13 10-Jan-14
E2690 INSTALL PIPE SUPPORT 100 10-Sep-13 04-Jan-14
E3100 INSTALL PIPE SPOOL 100 16-Sep-13 10-Jan-14
INSTALLATIO N O F VALVES (NUMBER OF VALVES) 40 10-Dec-13 25-Jan-14 10-Dec-13 25-Jan-14
E3520 INSTALL VALVES 40 10-Dec-13 25-Jan-14
LEAK TEST OF VALVES (NUMB ER OF VALVES) 35 24-Dec-13 13-Feb-14 24-Dec-13 13-Feb-14
E3510 LEAK TEST VALVES 35 24-Dec-13 13-Feb-14
FLUSHING, HYDROTESTING AND ACID CLEANING 63 22-Nov-13 14-Feb-14 22-Nov-13 14-Feb-14
E3530 FLUSHING 45 23-Nov-13 15-Jan-14
E3540 HYDROTEST 50 22-Nov-13 20-Jan-14

Actual Work Critical Remaining Work Summary Page 13 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
E3550 ACID CLEANING 35 25-Dec-13 14-Feb-14
INSULATION 60 22-Nov-13 11-Feb-14 22-Nov-13 11-Feb-14
E3560 INSULATION OF PIPING 60 22-Nov-13 11-Feb-14
MECHANICAL 114 30-Sep-13 21-Feb-14 30-Sep-13 21-Feb-14
SETTING UP EQUIPMENT ON DECK 107 30-Sep-13 13-Feb-14 30-Sep-13 13-Feb-14
SETTING UP EQUIPMENT ON CELLAR DECK 105 30-Sep-13 11-Feb-14 30-Sep-13 11-Feb-14
E3570 SETTING UP CLOSE DRAIN VESSEL V-6400 SKID 4 19-Oct-13 23-Oct-13
E3600 SETTING UP CRUDE HEATER UNIT A-1510 (CELLAR DECK PART III) 4 14-Nov-13 18-Nov-13
E3610 SETTING UP PMCS/SIS/FIELD TRANSMITTER/ FGS (CELLAR DECK PART I) 8 11-Nov-13 19-Nov-13
E3620 SETTING UP CRUDE OIL TRANSFER PUMP P-1310A/B (CELLAR DECK PART II) 4 27-Jan-14 11-Feb-14
E3630 SETTING UP FUEL G AS SKID  A-5800 (CELLAR DECK PART III) 4 30-Sep-13 03-Oct-13
E3640 SETTING UP CHEMICAL IN JECTIO N PUMP SKID A-6800 (CELLAR DECK PART III) 4 04-Oct-13 08-Oct-13
E3650 SETTING UP LAUNCHER L-1330 (CELLAR DECK PART III) 4 09-Oct-13 12-Oct-13
E3660 SETTING UP DIESEL ENG INE G EN ERATOR (DEG)  A-7740 (CELLAR DECK PART I) 4 14-Nov-13 19-Nov-13
E3670 SETTING UP GAS ENGINE GENERATOR A-7700 (CELLAR DECK PART I) 4 07-Jan-14 11-Jan-14
E3680 SETTING UP MULTIPHASE FLOW METER A-1210 ( CELLAR  DECK PART II) 4 05-Oct-13 09-Oct-13
E3690 SETTING UP WELL HEAD CONTRO L PANEL WHCP-0100 (CELLAR DECK PART II) 4 10-Oct-13 14-Oct-13
E3700 SETTING UP TEST/ PRODUCTION/ GASLIFT HEADER (CELLAR DECK PART II) 4 15-Oct-13 18-Oct-13
E3710 SETTING UP WASH WATER PUMP P-5110 (CELLAR DECK PART III) 4 04-Jan-14 08-Jan-14
E3720 SETTING UP CO2 VENT SNUFFING A-8600 (VENT BOOM) 4 03-Jan-14 07-Jan-14
E3730 SETTING UP DIESEL TRANSFER PUMP P-6710 (CELLAR DECK PART II) 4 04-Jan-14 08-Jan-14
E3740 SETTING UP NITROGEN BOTTLES A-5900 (CELLAR DECK PART III) 4 01-Oct-13 04-Oct-13
E3750 SETTING UP SCSSV EQUALIZATION PUMP P-6720 (CELLAR DECK PART II) 4 04-Jan-14 08-Jan-14
E3760 SETTING UP PIPELINE DIESEL INJECTIO N PUMP P-6730 (CELLAR DECK PART II) 4 07-Jan-14 10-Jan-14
SETTING UP EQUIPMENT ON MAIN DECK 55 29-Nov-13 13-Feb-14 29-Nov-13 13-Feb-14
E3800 SETTING UP MATERIAL HANDLING - PEDESTAL CRANE BD-7301 (MAIN DECK) 5 27-Jan-14 12-Feb-14
E3810 SETTING UP BOOSTER COMPRESSOR A-2410 (MAIN DECK) 2 11-Feb-14 13-Feb-14
E3820 SETTING UP GAS LIFT COMPRESSOR A-0610 (MAIN DECK) 2 11-Feb-14 13-Feb-14
E3830 SETTING UP DIESEL STORAGE TANK T-6700 2 29-Nov-13 30-Nov-13
E3840 SETTING UP WASH WATER STORAGE STANK T-5100A/B 2 02-Dec-13 03-Dec-13
E3850 SETTING UP POTABLE WATER TANK T-5200 2 04-Dec-13 05-Dec-13
E3860 SETTING UP GENERAL PU RPOSE TOTE TANK T-5300 2 06-Dec-13 07-Dec-13
E3890 SETTING UP PORTABLE CHEMICAL TRANSFER PUMP P-6835 2 09-Dec-13 10-Dec-13
E3900 SETTING UP HP SEPARATOR SKID A-1020 2 11-Dec-13 12-Dec-13
E3910 SETTING UP LP SEPARATOR SKID A-1010 2 13-Dec-13 14-Dec-13
MECHANICAL COMPLETION (TIE-IN) 100 16-Oct-13 21-Feb-14 16-Oct-13 21-Feb-14
TIE-IN EQUIPMENT ON CELLAR DECK 98 16-Oct-13 19-Feb-14 16-Oct-13 19-Feb-14
E3940 TIE-IN CLOSE DRAIN VESSEL V-6400 40 01-Nov-13 17-Dec-13
E3950 TIE-IN CRUDE HEATER UNIT A-1510 30 29-Nov-13 03-Jan-14
E3960 TIE-IN PMCS/SIS/FIELD TRANSMITTER/ FGS 30 30-Nov-13 04-Jan-14
E3970 TIE-IN CRUDE OIL TRANSFER PUMP P-1310A/B 7 11-Feb-14 19-Feb-14
E3980 TIE-IN FUEL GAS SKID  A-5800 30 25-Nov-13 28-Dec-13
E3990 TIE-IN CHEMICAL INJECTION PUMP SKID A-6800 21 16-Nov-13 10-Dec-13
E4000 TIE-IN LAUNCHER L-1330 45 24-Oct-13 14-Dec-13
E4010 TIE-IN DIESEL ENGINE GENERATOR (DEG) A-7740 10 03-Dec-13 13-Dec-13
E4020 TIE-IN GAS ENGINE GENERATOR A- 7700 7 17-Jan-14 25-Jan-14
E4030 TIE-IN MULTIPHASE FLOW METER A-1210 30 21-Oct-13 23-Nov-13
E4040 TIE-IN WELL HEAD CONTROL PANEL WHCP-0100 30 25-Oct-13 28-Nov-13
E4050 TIE-IN TEST/ PRODUCTION/ GASLIFT HEADTER 30 30-Oct-13 03-Dec-13
E4060 TIE-IN WASH WATER PU MP P-5110 7 09-Jan-14 16-Jan-14
E4070 TIE-IN CO2 VENT SNUFFING A-8600 7 08-Jan-14 15-Jan-14
E4080 TIE-IN DIESEL TRANSFER PUMP P-6710 7 09-Jan-14 16-Jan-14
E4090 TIE-IN NITROGEN BOTTLES A-5900 30 16-Oct-13 19-Nov-13

Actual Work Critical Remaining Work Summary Page 14 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
E4100 TIE-IN SCSSV EQUALIZATION PUMP P-6720 7 09-Jan-14 16-Jan-14
E4110 TIE-IN PIPELINE DIESEL INJECTION PUMP P-6730 7 11-Jan-14 18-Jan-14
TIE-IN EQUIPMENT ON MAIN DECK 60 02-Dec-13 21-Feb-14 02-Dec-13 21-Feb-14
E4160 TIE-IN PORTABLE CHEMICAL TRANSFER PU MP P-6835 10 11-Dec-13 21-Dec-13
E4170 TIE-IN HP SEPARATOR SKID A-1020 10 13-Dec-13 24-Dec-13
E4180 TIE-IN LP SEPARATOR SKID A-1010 10 16-Dec-13 26-Dec-13
E4190 TIE-IN MATERIAL HANDLING - PEDESTAL CRANE BD-7301 7 12-Feb-14 20-Feb-14
E4200 TIE-IN BOOSTER COMPRESSOR A-2410 7 13-Feb-14 21-Feb-14
E4210 TIE-IN GAS LIFT COMPRESSOR A-0610 7 13-Feb-14 21-Feb-14
E4220 TIE-IN DIESEL STO RAGE TANK T-6700 12 02-Dec-13 14-Dec-13
E4230 TIE-IN WASH WATER STORAGE STANK T-5100A/B 12 04-Dec-13 17-Dec-13
E4240 TIE-IN POTABLE WATER TANK T- 5200 12 06-Dec-13 19-Dec-13
E4250 TIE-IN GENERAL PURPOSE TOTE TANK T-5300 12 09-Dec-13 21-Dec-13
INSTRUMENT 173 11-Jul-13 10-Feb-14 11-Jul-13 10-Feb-14
FABRICATE INSTRUMENT SUPPORTS 40 11-Jul-13 26-Aug-13 11-Jul-13 26-Aug-13
E4270 FABR ICATE  SUPPORT FOR FIRE AND GAS SYSTEM 35 11-Jul-13 20-Aug-13
E4280 FABR ICATE SUPPORT FOR INSTRUMENT EQUIPMENT 35 11-Jul-13 20-Aug-13
E4290 FABR ICATE SUPPORT FOR TELECOM EQUIPMENT 35 11-Jul-13 20-Aug-13
E4300 FABR ICATE SUPPORT FOR  INSTRUMENT JBs 35 11-Jul-13 20-Aug-13
E4310 FABR ICATE SUPPORT FOR CABLE TRAY AND T UBING  TRAY 35 11-Jul-13 20-Aug-13
E4320 FABR ICATE SUPPORT FOR  BULKEAD 35 17-Jul-13 26-Aug-13
INSTALLATIO N O F INSTRUMENT SUPPO RTS 55 11-Oct-13 13-Dec-13 11-Oct-13 13-Dec-13
E4330 INSTALL  SUPPORT FO R F IRE AND GAS SYSTEM 55 11-Oct-13 13-Dec-13
E4340 INSTALL SUPPORT F OR INST RUMENT EQUIPMENT 55 11-Oct-13 13-Dec-13
E4350 INSTALL SUPPORT F OR TELECOM EQUIPMENT 55 11-Oct-13 13-Dec-13
E4360 INSTALL SUPPORT F OR  IN STRU MENT JBs 55 11-Oct-13 13-Dec-13
E4370 INSTALL SUPPORT F OR CABLE TRAY AND TUBING TRAY 55 11-Oct-13 13-Dec-13
E4380 INSTALL SUPPORT F OR  BULKEAD 55 11-Oct-13 13-Dec-13
TUBING TRAY I CABLE TRAY I LADDER INSTALLATION 55 19-Oct-13 21-Dec-13 19-Oct-13 21-Dec-13
E4390 INSTALL CABLE LADDER/ TRAY FOR INSTRUMENT 55 19-Oct-13 21-Dec-13
CALIBRATE INSTRUMENT 55 11-Oct-13 13-Dec-13 11-Oct-13 13-Dec-13
E4400 CALIBRATE INSTRUMENT EQUIPMENTS 55 11-Oct-13 13-Dec-13
INSTRUMENT EQUIPMENT INSTALLATION 78 23-Oct-13 22-Jan-14 23-Oct-13 22-Jan-14
E4410 INSTALL INSTRUMENT JBs AND BULKEAD 55 29-Oct-13 31-Dec-13
E4420 INSTALL GAUGE EQUIPMENTS 40 06-Dec-13 22-Jan-14
E4430 INSTALL TELECOM EQUIPMENTS 55 23-Oct-13 25-Dec-13
E4440 INSTALL TRANSMITER EQUIPMENTS 55 23-Oct-13 25-Dec-13
E4450 INSTALL FIRE & GAS EQUIPMENTS 55 23-Oct-13 25-Dec-13
CABLE PULLING 47 12-Nov-13 06-Jan-14 12-Nov-13 06-Jan-14
E4460 CABLE PULLING  FIRE & GAS CABLE (FROM EQUIPMENT TO  JB) 35 20-Nov-13 30-Dec-13
E4470 CABLE PULLING  MULTICORE CABLE FROM PACKAG ES TO E-HOUSE 35 26-Nov-13 06-Jan-14
E4480 CABLE PULLING  FOR TELECOM 20 04-Dec-13 26-Dec-13
E4490 CABLE PULLING FOR FIELD INSTRUMENT DEVICES (FROM EQUIPMENT TO JB) 40 12-Nov-13 27-Dec-13
DRESSING, GLANDING, TAGGING AND TERMINATION 44 10-Dec-13 10-Feb-14 10-Dec-13 10-Feb-14
E4500 DRESSING, GLANDING FOR MULTICORE CABLE FROM PACKAG ES TO E-HOUSE 35 19-Dec-13 29-Jan-14
E4510 DRESSING, GLANDING FOR CABLE FOR TELECOM 35 10-Dec-13 20-Jan-14
E4520 DRESSING, GLANDING FOR FIELD DEVICES (FROM EQUIPMENT TO JB) 25 17-Dec-13 15-Jan-14
E4530 DRESSING, GLANDING FOR FIRE & GAS CABLE (FROM EQUIPMENT TO  JB) 35 20-Dec-13 10-Feb-14
PULL AND HOOK-UP TUBING 30 26-Dec-13 10-Feb-14 26-Dec-13 10-Feb-14
E4540 PULL AN D HOOK-UP TUBING FROM WHCP  TO BULKEAD PLATE 30 26-Dec-13 10-Feb-14
E4550 PULL AN D HOOK-UP TUBING FROM PIPING  TO INSTRUMENT DEVICES 30 26-Dec-13 10-Feb-14
E4560 PULL AN D HOOK-UP TUBING FROM CHEMICAL INJECTION TO PIPING 20 03-Jan-14 25-Jan-14
ELECTRICAL 182 11-Jul-13 21-Feb-14 11-Jul-13 21-Feb-14
FABRICATION OF ELECTRICAL SUPPO RT 50 11-Jul-13 07-Sep-13 11-Jul-13 07-Sep-13

Actual Work Critical Remaining Work Summary Page 15 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
E4570 FABR ICATE SUPPORT FOR LIGHTING SYSTEM 50 11-Jul-13 07-Sep-13
E4580 FABR ICATE SUPPORT FOR ELECTRICAL JBs 30 23-Jul-13 26-Aug-13
E4590 FABR ICATE SUPPORT FOR CABLE TRAY/LADDER 50 11-Jul-13 07-Sep-13
INSTALLATIO N O F ELECTRICA L SUPPORT 55 10-Oct-13 12-Dec-13 10-Oct-13 12-Dec-13
E4600 INSTALL SUPPORT F OR CABLE TRAY/LADDER 55 10-Oct-13 12-Dec-13
E4610 INSTALL SUPPORT F OR LIGHTIN G SYSTEM 55 10-Oct-13 12-Dec-13
E4620 INSTALL SUPPORT F OR ELECT RIC AL JBs 55 10-Oct-13 12-Dec-13
CABLE TRAY I CABLE LADDER INSTALLATION 55 16-Oct-13 18-Dec-13 16-Oct-13 18-Dec-13
E4630 INSTALL CABLE LADDER/ TRAY FOR ELECTRICAL 55 16-Oct-13 18-Dec-13
CALIBRATE ELECTRICAL EQUIPMENT 50 08-Nov-13 06-Jan-14 08-Nov-13 06-Jan-14
E4640 CALIBRATE  ELECTRICAL EQUIPMENTS 50 08-Nov-13 06-Jan-14
ELECTRICAL EQUIPMENT INSTALLATION 76 26-Oct-13 23-Jan-14 26-Oct-13 23-Jan-14
E4650 INSTALL  ELECTRICAL JBs 55 26-Oct-13 28-Dec-13
E4660 INSTALL  NAVIGATION AID EQUIPMENTS 6 07-Jan-14 13-Jan-14
E4670 INSTALL  HEATRACING EQUIPMENTS 33 16-Dec-13 23-Jan-14
E4680 INSTALL  SMALL POWER EQUIPMENT S 30 25-Nov-13 28-Dec-13
E4690 INSTALL LIGHTING EQUIPMENTS 50 20-Nov-13 17-Jan-14
CABLE PULLING 65 21-Nov-13 17-Feb-14 21-Nov-13 17-Feb-14
E4700 CABE PULLING  FOR MAIN EARTHING 14 18-Jan-14 14-Feb-14
E4710 CABE PULLING  FOR SKID 35 26-Dec-13 17-Feb-14
E4720 CABE PULLING  FOR HELI DECK 12 11-Jan-14 24-Jan-14
E4730 CABE PULLING  FOR GENERATOR 30 14-Dec-13 20-Jan-14
E4740 CABE PULLING  FOR HEATRACING 21 30-Dec-13 23-Jan-14
E4750 CABE PULLING  FOR SMALL POWER 50 21-Nov-13 18-Jan-14
E4760 CABE PULLING  FOR LIGHTING 20 06-Dec-13 28-Dec-13
E4770 CABE PULLING  FOR BATTERY (FROM E-HOUSE TO) 10 17-Dec-13 27-Dec-13
DRESSING, GLANCING, TAGGING AND TERMINATION 51 12-Dec-13 21-Feb-14 12-Dec-13 21-Feb-14
E4780 DRESSING, GLANDING FOR SMALL POWER CABLE 12 15-Jan-14 28-Jan-14
E4790 DRESSING, GLANDING FOR MAIN EARTHING CABLE 12 24-Jan-14 18-Feb-14
E4800 DRESSING, GLANDING FOR SKID CABLE 30 07-Jan-14 21-Feb-14
E4810 DRESSING, GLANDING FOR HELI DECK CABLE 12 17-Jan-14 10-Feb-14
E4820 DRESSING, GLANDING FOR GENERATOR CABLE 10 20-Jan-14 11-Feb-14
E4830 DRESSING, GLANDING FOR HEATRACING CABLE 18 09-Jan-14 29-Jan-14
E4840 DRESSING, GLANDING FOR LIGHTING CABLE 25 12-Dec-13 10-Jan-14
E4850 DRESSING, GLANDING FOR BATTERY (FROM E-HOUSE TO ) 14 24-Dec-13 09-Jan-14
MCT INSTALLATION 21 03-Dec-13 26-Dec-13 03-Dec-13 26-Dec-13
E24640 MCT INSTALLATION 21 03-Dec-13 26-Dec-13
EARTHING BOSS INSTALLATION 21 11-Jan-14 15-Feb-14 11-Jan-14 15-Feb-14
E24650 EARTHING BOSS INSTALLATION 21 11-Jan-14 15-Feb-14
BLASTING / PAINTING 221 20-Apr-13 07-Jan-14 20-Apr-13 07-Jan-14
E4861 DELIVERY ON SITE PAINTING MATERIAL 1 20-Apr-13* 20-Apr-13
STRUCTURE STEEL 220 22-Apr-13 07-Jan-14 22-Apr-13 07-Jan-14
E4865 BLASTING/ PRIMER PAINTING PRIMARY STRUCTURE OF CELLAR DECK 9 22-Apr-13 03-May-13
E4870 FINAL BLASTING/ PAINTING CELLAR DECK PART II 15 13-Aug-13 29-Aug-13
E4873 FINAL BLASTING/ PAINTING CELLAR DECK PART III 15 24-Aug-13 11-Sep-13
E4876 FINAL BLASTING/ PAINTING CELLAR DECK PART I 15 04-Sep-13 20-Sep-13
E4885 BLASTING/ PAINTING PRIMARY STRUCTURE OF MAIN DECK 14 04-May-13 20-May-13
E4890 FINAL BLASTING/ PAINTING MAIN DECK PART II 15 15-Oct-13 31-Oct-13
E4893 FINAL BLASTING/ PAINTING MAIN DECK PART III 15 22-Oct-13 07-Nov-13
E4896 FINAL BLASTING/ PAINTING MAIN DECK PART I 15 30-Oct-13 15-Nov-13
E4920 BLASTING/ PAINTING BRACING PIPES 14 14-Aug-13 29-Aug-13
E4930 BLASTING/ PAINTING VENT BOOM 6 31-Dec-13 07-Jan-14
PIPING SUPPORTS/SPOOLS 153 22-Jun-13 18-Dec-13 22-Jun-13 18-Dec-13
E4940 BLASTING/ PAINTING PIPE SUPPORTS 60 22-Jun-13 30-Aug-13

Actual Work Critical Remaining Work Summary Page 16 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
E5350 BLASTING/ PAINTING PIPE SPOOL 100 23-Aug-13 18-Dec-13
PIPING VALVES 25 28-Nov-13 26-Dec-13 28-Nov-13 26-Dec-13
E5760 BLASTING/ PAINTING PIPING VALVES 25 28-Nov-13 26-Dec-13
INSTRUMENT SUPPORTS 12 21-Aug-13 04-Sep-13 21-Aug-13 04-Sep-13
E5770 BLASTING/ PAINTING SUPPORT FOR FIRE AND GAS SYSTEM 7 21-Aug-13 28-Aug-13
E5780 BLASTING/ PAINTING SUPPORT FOR INSTRUMENT EQUIPMENT 7 21-Aug-13 28-Aug-13
E5790 BLASTING/ PAINTING SUPPORT FOR TELECOM EQUIPMENT 7 21-Aug-13 28-Aug-13
E5800 BLASTING/ PAINTING SUPPORT FOR  INSTRUMENT JBs 7 21-Aug-13 28-Aug-13
E5810 BLASTING/ PAINTING SUPPORT FOR CABLE TRAY AND TUBING TRAY 10 21-Aug-13 31-Aug-13
E5820 BLASTING/ PAINTING SUPPORT FOR  BULKEAD 7 27-Aug-13 04-Sep-13
ELECTRICAL SUPPORTS 50 18-Jul-13 14-Sep-13 18-Jul-13 14-Sep-13
E5830 BLASTING/ PAINTING SUPPORT FOR LIGHTING SYSTEM 50 18-Jul-13 14-Sep-13
E5840 BLASTING/ PAINTING SUPPORT FOR ELECTRICAL JBs 30 30-Jul-13 03-Sep-13
E5850 BLASTING/ PAINTING SUPPORT FOR CABLE TRAY/LADDER 50 18-Jul-13 14-Sep-13
ARCHITECTURAL 48 22-Oct-13 16-Dec-13 22-Oct-13 16-Dec-13
E5860 INSTALL UP FIRE RATED DOORS 9 30-Nov-13 10-Dec-13
E5880 INSTALL TEMPORARY SHELTER/ WORKSHOP/STORAGE AREA 48 22-Oct-13 16-Dec-13
TESTTING & PRE-COMMISSIONING 42 31-Dec-13 28-Feb-14 31-Dec-13 28-Feb-14
PROCESS SYSTEM 40 31-Dec-13 26-Feb-14 31-Dec-13 26-Feb-14
F1000 100-PROCESS LIQUID 5 31-Dec-13 06-Jan-14
F1010 110-PROCESS GAS 14 11-Feb-14 26-Feb-14
POWER SYSTEM 30 07-Jan-14 20-Feb-14 07-Jan-14 20-Feb-14
F1090 510-POWER GENERATION 10 07-Jan-14 17-Jan-14
F1100 520-MAIN POWER DISTRIBUTION 10 18-Jan-14 29-Jan-14
F1110 530-DIRECT CURRENT 10 24-Jan-14 14-Feb-14
F1120 540-MINOR POWER DISTRIBUTION 10 10-Feb-14 20-Feb-14
PROCESS UTILITIES SYSTEM 26 18-Jan-14 27-Feb-14 18-Jan-14 27-Feb-14
F1030 230-BLOWDOWN AN D RELIEF VENT 4 18-Jan-14 22-Jan-14
F1040 250-PROCESS HEATING 7 19-Feb-14 26-Feb-14
F1050 260-CHEMICAL INJECTION 8 19-Feb-14 27-Feb-14
GENERAL UTILITIES SYSTEM 14 23-Jan-14 18-Feb-14 23-Jan-14 18-Feb-14
F1060 310-FUEL & LUBRICATION 5 23-Jan-14 28-Jan-14
F1070 340-HVAC 7 23-Jan-14 10-Feb-14
F1080 350-UTILITY/INSTRUMENT/FUEL GAS 7 11-Feb-14 18-Feb-14
CONTROL SYSTEM 20 23-Jan-14 25-Feb-14 23-Jan-14 25-Feb-14
F1130 610-PROCESS CONTROL 10 14-Feb-14 25-Feb-14
F1140 620-ALARM AND SHUTDOWN 10 23-Jan-14 14-Feb-14
F1150 630-FIRE AND GAS DET EC TION 10 29-Jan-14 19-Feb-14
TELECOMMUNICATIONS SYSTEM 5 20-Feb-14 25-Feb-14 20-Feb-14 25-Feb-14
F1160 710-COMMUNICATION EQUIPMENT 5 20-Feb-14 25-Feb-14
TOPSIDE ONSHORE MCD 0 28-Feb-14 28-Feb-14 28-Feb-14 28-Feb-14
F1020 TOPSIDE ONSHORE MCD 0 28-Feb-14*
TOPSIDE ONSHORE MCD
LOAD-OUT AND SEAFASTENING 283 01-Jun-13 10-Mar-14 01-Jun-13 10-Mar-14
DRAWINGS 244 01-Jun-13 30-Jan-14 01-Jun-13 30-Jan-14
I1040 PREPARATIO N/ SU BMISSION/ APPROVAL DRAWINGS F OR  LO AD O UT BEAMS 25 01-Jun-13 25-Jun-13
I1050 PREPARATIO N/ SU BMISSION/ APPROVAL DRAWINGS F OR  SEAFASTENING 28 03-Jan-14 30-Jan-14
LOAD-OUT BEAM FABRICATION 52 26-Jun-13 16-Aug-13 26-Jun-13 16-Aug-13
I1000 MARK & CUT LOAD-OUT BEAM 25 26-Jun-13 20-Jul-13
I1010 FIT UP  LOAD-OUT BEAM 30 28-Jun-13 27-Jul-13
I1020 WELDING  LOAD-OUT BEAM 40 03-Jul-13 11-Aug-13
I1030 NDT  LOAD-OUT BEAM 40 08-Jul-13 16-Aug-13
MATERIALS (TONNAGE) 1 06-Feb-14 06-Feb-14 06-Feb-14 06-Feb-14
I1060 RECEIPT MATERIAL 1 06-Feb-14 06-Feb-14
LOAD-OUT AND POSITIONING 1 05-Mar-14 05-Mar-14 05-Mar-14 05-Mar-14

Actual Work Critical Remaining Work Summary Page 17 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
I1070 LOAD-OUT AND POSITIONING 1 05-Mar-14 05-Mar-14
SEAFASTENING FABRICATION 32 07-Feb-14 10-Mar-14 07-Feb-14 10-Mar-14
I1080 MARK & CUT FRAME SEAFASTENING 14 07-Feb-14 20-Feb-14
I1090 FIT UP FRAME SEAFASTENING 3 06-Mar-14 08-Mar-14
I1100 WELDING FRAME SEAFASTENING 3 07-Mar-14 09-Mar-14
I1110 NDT FRAME SEAFASTENING 3 07-Mar-14 10-Mar-14
TIE-DOWN ARRANGEMENTS 14 24-Feb-14 10-Mar-14 24-Feb-14 10-Mar-14
I1120 TIE- DOWN MATERIALS ON TRANSPORTATION BOAT 14 24-Feb-14 10-Mar-14
245 21-Aug-13 18-Jun-14 21-Aug-13 18-Jun-14
HOOK UP & COMMISSIONING
ONSHORE PREPARATION ACTIVITIES 162 03-Sep-13 19-Mar-14 03-Sep-13 19-Mar-14
PREPARATION HUC PROCEDURES 120 03-Sep-13 20-Jan-14 03-Sep-13 20-Jan-14
H1010 PREPARE HSE PROCEDURE 60 03-Sep-13* 11-Nov-13
H1020 PREPARE QA/QC PROCEDURE 60 03-Sep-13 11-Nov-13
H1030 PREPARE JOB CARDS 80 03-Sep-13 04-Dec-13
H1040 PREPARE PLANNING PROCEDURE 40 05-Dec-13 20-Jan-14
MOBILIZATION MANPOWER, MATERIAL 26 14-Feb-14 17-Mar-14 14-Feb-14 17-Mar-14
H1050 MOBILIZATION MANPOWER 26 14-Feb-14 17-Mar-14
H1060 INSPECTION/PACKING SHIP-LOOSE MATERIAL ON WORK BARGE 14 28-Feb-14 17-Mar-14
MOBILIZATION TOOL & EQUIPMENT 9 06-Mar-14 17-Mar-14 06-Mar-14 17-Mar-14
H1070 MOBILIZATION HUC TOOL&EQUIPMENT 9 06-Mar-14 17-Mar-14
MOBILIZATION HUC BARGE 5 14-Mar-14 19-Mar-14 14-Mar-14 19-Mar-14
H1080 MOBILIZATION WORK BARGE TO PVCMS'S JETTY 5 14-Mar-14 19-Mar-14
OFFSHORE HOOK UP AND COMMISSIONIN G 32 24-Mar-14 24-Apr-14 24-Mar-14 24-Apr-14
HOOK UP 29 24-Mar-14 22-Apr-14 24-Mar-14 22-Apr-14
HOOK UP STRUCTURE 19 24-Mar-14 12-Apr-14 24-Mar-14 12-Apr-14
H1110 INSTALL GANWAY 1 24-Mar-14 25-Mar-14
H1120 ERECT TEMPORARY STAIR  WAY TO CELLAR DECK & SERVICE PLATFORM 1 25-Mar-14 26-Mar-14
H1130 INSTALL STAIR WAY FROM OPEN& CLOSED DRAIN DECK TO C ELLAR DEC K 6 26-Mar-14 01-Apr-14
H1135 INSTALL STAIR WAY TO SERVICE PLAT FORM 2 03-Apr-14 05-Apr-14
H1145 REMOVE 04 LIFTING PADEYES/ PROTECTION FRAME 4 28-Mar-14 01-Apr-14
H1150 INSTALL DECK PLATES, HANDRAILS 3 01-Apr-14 04-Apr-14
H1160 ERECT SCAFFOLDING FOR CORRECTING FLARE BOOM POSITION 2 04-Apr-14 06-Apr-14
H1170 INSTALL STRUSS ROWS 2 06-Apr-14 08-Apr-14
H1175 INSTALL RISER GUARD 2 08-Apr-14 10-Apr-14
H1180 CUT OFF TEMPORARY SUPPORT OF CRANE 2 01-Apr-14 03-Apr-14
H1190 TOUCH UP PAITING FOR STRUCTURE 6 06-Apr-14 12-Apr-14
H1200 TOUCH UP PAINTING FOR JOINTS OF TOPSIDE'S LEGS TO JACKET 6 27-Mar-14 02-Apr-14
INSTALL MECHANICAL ITEMS 4 27-Mar-14 31-Mar-14 27-Mar-14 31-Mar-14
A11550 SETTING UP/ INSTALL CLOSED DRAIN PUMPS 2 27-Mar-14 29-Mar-14
A11560 SETTING UP/ INSTALL OPEN DRAIN PUMPS 2 29-Mar-14 31-Mar-14
HOOK UP PIPING 26 25-Mar-14 20-Apr-14 25-Mar-14 20-Apr-14
HOOK UP RISER 8 25-Mar-14 02-Apr-14 25-Mar-14 02-Apr-14
H3875 HOOK UP RISER SPOOLS 8 25-Mar-14 02-Apr-14
HOOK UP FOR FLOWLINE 15 29-Mar-14 13-Apr-14 29-Mar-14 13-Apr-14
HOOK UP FOR SLOT 4P 9 29-Mar-14 07-Apr-14 29-Mar-14 07-Apr-14
H1290 INSTALL PL PIPE SPOO LS 9 29-Mar-14 07-Apr-14
H1310 INSTALL PG PIPE SPOOLS 7 31-Mar-14 07-Apr-14
HOOK UP FOR SLOT 1P 9 31-Mar-14 09-Apr-14 31-Mar-14 09-Apr-14
H3885 INSTALL PL PIPE SPOO LS 9 31-Mar-14 09-Apr-14
H3895 INSTALL PG PIPE SPOOLS 7 02-Apr-14 09-Apr-14
HOOK UP FOR SLOT 2P 9 02-Apr-14 11-Apr-14 02-Apr-14 11-Apr-14
H3905 INSTALL PL PIPE SPOO LS 9 02-Apr-14 11-Apr-14
H3915 INSTALL PG PIPE SPOOLS 7 04-Apr-14 11-Apr-14

Actual Work Critical Remaining Work Summary Page 18 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
HOOK UP FOR SLOT 3P 9 04-Apr-14 13-Apr-14 04-Apr-14 13-Apr-14
H3925 INSTALL PL PIPE SPOO LS 9 04-Apr-14 13-Apr-14
H3935 INSTALL PG PIPE SPOOLS 7 06-Apr-14 13-Apr-14
HOOK UP FOR OTHER PIPING SYSTEMS 15 31-Mar-14 15-Apr-14 31-Mar-14 15-Apr-14
H3945 HOOK UP WP SYSTEM 5 31-Mar-14 05-Apr-14
H3965 HOOK UP DH SYSTEM 4 31-Mar-14 04-Apr-14
H3975 HOOK UP DN SYSTEM 4 05-Apr-14 09-Apr-14
H3985 HOOK UP DC SYSTEM 4 04-Apr-14 08-Apr-14
H3995 HOOK UP WI SYSTEM 2 09-Apr-14 11-Apr-14
H4005 HOOK UP VL SYSTEM 4 08-Apr-14 12-Apr-14
H4015 HOOK UP FD SYSTEM 4 11-Apr-14 15-Apr-14
H4025 HOOK UP UG SYSTEM 2 06-Apr-14 08-Apr-14
H4035 HOOK UP VT SYSTEM 4 11-Apr-14 15-Apr-14
H4045 HOOK UP FD SYSTEM 4 11-Apr-14 15-Apr-14
H4115 HOOK UP FW SYSTEM 4 11-Apr-14 15-Apr-14
H4125 HOOK UP VA SYSTEM 4 08-Apr-14 12-Apr-14
LEAK TEST PIPING 7 13-Apr-14 20-Apr-14 13-Apr-14 20-Apr-14
H4065 LEAK TEST FOR FLOWLINE 5 13-Apr-14 18-Apr-14
H4075 LEAK TEST FOR OTHER PIPING SYSTEM 5 15-Apr-14 20-Apr-14
HOOK UP ELECTRICAL 25 28-Mar-14 22-Apr-14 28-Mar-14 22-Apr-14
H1730 INSTALL ELECTRICAL SUPPO RT 4 28-Mar-14 01-Apr-14
H1740 INSTALL CABLE TRAY 4 29-Mar-14 02-Apr-14
H1750 INSTALL LIGHTING EQUIPMENT 4 31-Mar-14 04-Apr-14
H1760 UNROLL, GLAND, TERMINATE CABLE FOR LIGHTING 4 04-Apr-14 08-Apr-14
H1770 UNROLL, GLAND, TERMINATE CABLE FOR MAIN EARTHING 2 06-Apr-14 08-Apr-14
H1780 INSTALL HEATRACING 11 09-Apr-14 20-Apr-14
H1790 TESTING 2 20-Apr-14 22-Apr-14
HOOK UP INSTRUMENT 16 04-Apr-14 20-Apr-14 04-Apr-14 20-Apr-14
H1810 HOOK UP INSTRUMENT FOR SLOT 4P 7 04-Apr-14 11-Apr-14
H1820 HOOK UP INSTRUMENT FOR SLOT 1P 7 06-Apr-14 13-Apr-14
H3855 HOOK UP INSTRUMENT FOR SLOT 2P 7 08-Apr-14 15-Apr-14
H3865 HOOK UP INSTRUMENT FOR SLOT 3P 7 10-Apr-14 17-Apr-14
H3868 HOOK UP INSTRUMENT FOR OTHER INSTRUMENT ITEMS 9 11-Apr-14 20-Apr-14
TOUCH UP PAINTING/ MARKING 5 17-Apr-14 22-Apr-14 17-Apr-14 22-Apr-14
H1880 TOUCH UP PAINTING & MARKING 5 17-Apr-14 22-Apr-14
COMMISSIONING 20 03-Apr-14 23-Apr-14 03-Apr-14 23-Apr-14
PROCESS SYSTEM 15 08-Apr-14 23-Apr-14 08-Apr-14 23-Apr-14
H6010 100-PROCESS LIQUID 5 08-Apr-14 13-Apr-14
H6020 110-PROCESS GAS 6 17-Apr-14 23-Apr-14
PROCESS UTILITIES SYSTEM 5 12-Apr-14 17-Apr-14 12-Apr-14 17-Apr-14
H6030 250-PROCESS HEATING 5 12-Apr-14 17-Apr-14
H6040 260-CHEMICAL INJECTION 3 13-Apr-14 16-Apr-14
H6160 230-BLOWDOWN AN D RELIEF VENT 3 12-Apr-14 14-Apr-14
GENERAL UTILITIES SYSTEM 5 08-Apr-14 13-Apr-14 08-Apr-14 13-Apr-14
H6050 310-FUEL & LUBRICATION 4 08-Apr-14 12-Apr-14
H6060 340-HVAC 4 08-Apr-14 12-Apr-14
H6070 350-UTILITY/INSTRUMENT/FUEL GAS 5 08-Apr-14 13-Apr-14
POWER SYSTEM 5 03-Apr-14 08-Apr-14 03-Apr-14 08-Apr-14
H6080 510-POWER GENERATION 5 03-Apr-14 08-Apr-14
H6090 520-MAIN POWER DISTRIBUTION 5 03-Apr-14 08-Apr-14
H6100 530-DIRECT CURRENT 5 03-Apr-14 08-Apr-14
H6110 540-MINOR POWER DISTRIBUTION 5 03-Apr-14 08-Apr-14
CONTROL SYSTEM 7 05-Apr-14 12-Apr-14 05-Apr-14 12-Apr-14
H6120 610-PROCESS CONTROL 4 08-Apr-14 12-Apr-14

Actual Work Critical Remaining Work Summary Page 19 of 20 Date Revision Checked Approved

Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM

EPCC OVERALL SCHEDULE (TOPSIDE)

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
H6130 620-ALARM AND SHUTDOWN 3 05-Apr-14 08-Apr-14
H6140 630-FIRE AND GAS DET EC TION 5 05-Apr-14 10-Apr-14
TELECOMMUNICATIONS SYSTEM 5 10-Apr-14 15-Apr-14 10-Apr-14 15-Apr-14
H6150 710-COMMUNICATION EQUIPMENT 5 10-Apr-14 15-Apr-14
TOPSIDE START UP 0 24-Apr-14 24-Apr-14 24-Apr-14 24-Apr-14
H6000 TOPSIDE START UP 0 24-Apr-14*
TOPSIDE START UP
FINAL DOCUMENTATION 204 21-Aug-13 18-Jun-14 21-Aug-13 18-Jun-14
EQUIMENT DOSSIER 159 21-Aug-13 14-Apr-14 21-Aug-13 14-Apr-14
I1130 SUBMISSION EQUIMENT DOSSIER 120 21-Aug-13 18-Feb-14
I1140 APPROVAL EQUIMENT DOSSIER 80 30-Oct-13 28-Feb-14
I1150 FINAL SET EQ UIMEN T DOSSIER 30 03-Mar-14 14-Apr-14
QA/QC DOCUMENTATION 145 13-Nov-13 18-Jun-14 13-Nov-13 18-Jun-14
I1160 SUBMISSION QA/QC DOCUMENTATIO N 120 13-Nov-13 15-May-14
I1170 APPROVAL QA/QC DOCUMENTATION 80 10-Feb-14 04-Jun-14
I1180 FINAL SET QA/QC  DO CUMEN TATION 30 08-May-14 18-Jun-14
MATERIAL DOCUMENTATION 145 13-Nov-13 18-Jun-14 13-Nov-13 18-Jun-14
I1190 SUBMISSION MATERIAL DOCUMENTATION 120 13-Nov-13 15-May-14
I1200 APPROVAL MATERIAL DOCUMENTATION 80 10-Feb-14 04-Jun-14
I1210 FINAL SET MATERIAL DOCUMENTATION 30 08-May-14 18-Jun-14
TESTTING & PRECOMMISSIONING DOCUMENTATION 79 28-Nov-13 28-Mar-14 28-Nov-13 28-Mar-14
I1220 SUBMISSION TESTTING & PRECOMMISSIONING DOCUMENTATION 50 28-Nov-13 18-Feb-14
I1230 APPROVAL TESTTING & PRECOMMISSIONING DOCUMENTATION 40 25-Dec-13 28-Feb-14
I1240 FINAL SET TESTTING & PRECOMMISSIONING DOCUMENTATION 20 03-Mar-14 28-Mar-14
DESIGN DATA 145 13-Nov-13 18-Jun-14 13-Nov-13 18-Jun-14
I1250 SUBMISSION DESIGN DATA 120 13-Nov-13 15-May-14
I1260 APPROVAL DESIGN DATA 80 10-Feb-14 04-Jun-14
I1270 FINAL SET DESIGN DATA 30 08-May-14 18-Jun-14
AS-BUILT DRAWINGS 159 21-Aug-13 14-Apr-14 21-Aug-13 14-Apr-14
I1280 SUBMISSION AS- BU ILT DR AWINGS 120 21-Aug-13 18-Feb-14
I1290 APPROVAL AS-BUILT DRAWINGS 80 30-Oct-13 28-Feb-14
I1300 FINAL SET AS-BUILT DRAWINGS 30 03-Mar-14 14-Apr-14
CLOSE-OUT REPORT 65 17-Mar-14 18-Jun-14 17-Mar-14 18-Jun-14
I1310 SUBMISSION CLOSE-OUT REPORT 40 17-Mar-14 15-May-14
I1320 APPROVAL CLOSE-OUT REPORT 20 08-May-14 04-Jun-14
I1330 FINAL SET CLOSE- OUT REPORT 10 05-Jun-14 18-Jun-14
SHIPLOOSE LIST 52 05-Dec-13 27-Feb-14 05-Dec-13 27-Feb-14
I1340 SUBMISSION SHIPLOOSE LIST 45 05-Dec-13 18-Feb-14
I1350 APPROVAL SHIPLOOSE LIST 20 16-Jan-14 24-Feb-14
I1360 FINAL SET SHIPLOOSE LIST 10 13-Feb-14 27-Feb-14
NDT RADIOGRAPHIC FILMS 125 11-Dec-13 18-Jun-14 11-Dec-13 18-Jun-14
I1370 SUBMISSION NDT RADIOGRAPHIC FILMS 100 11-Dec-13 15-May-14
I1380 APPROVAL NDT RADIOGRAPHIC FILMS 70 24-Feb-14 04-Jun-14
I1390 FINAL SET ND T RADIOGRAPHIC FILMS 30 08-May-14 18-Jun-14

Actual Work Critical Remaining Work Summary Page 20 of 20 Date Revision Checked Approved

Remaining Work Milestone
ATTACHMENT 6
S-Curves (Topside)
72

20-Jun-14 100.00% 100.00% 100.00% 0.01%


71

20-Jun-14 13-Jun-14 100.00% 99.98% 99.99% 0.01%


70

13-Jun-14
6-Jun-14 100.00% 99.49% 99.99% 0.00%
69

6-Jun-14
30-May-14 100.00% 99.49% 99.99% 0.01%
30-May-14
68

23-May-14 100.00% 99.48% 99.98% 0.01%


23-May-14
67

16-May-14 100.00% 99.48% 99.98% 0.01%


16-May-14
66

9-May-14 99.99% 99.47% 99.97% 0.01%


9-May-14
65

2-May-14 99.99% 99.46% 99.96% 0.01%


2-May-14
64

25-Apr-14 99.99% 99.45% 99.95% 0.45%


25-Apr-14
63

18-Apr-14 99.80% 99.00% 99.50% 2.37%


18-Apr-14
62

11-Apr-14 97.63% 96.63% 97.13% 3.94%


11-Apr-14
61

4-Apr-14 94.20% 92.20% 93.20% 1.61%


4-Apr-14
60

28-Mar-14 92.59% 90.59% 91.59% 0.49%


28-Mar-14
59

21-Mar-14 21-Mar-14 92.10% 90.10% 91.10% 0.26%


58

14-Mar-14 14-Mar-14 91.84% 89.84% 90.84% 0.77%


57

7-Mar-14 7-Mar-14 91.07% 89.07% 90.07% 2.82%


56

28-Feb-14 28-Feb-14 88.25% 86.25% 87.25% 1.22%


55

21-Feb-14 21-Feb-14 87.04% 85.04% 86.04% 0.86%


54

14-Feb-14
14-Feb-14 86.18% 84.18% 85.18% 0.62%
53

7-Feb-14
7-Feb-14 85.56% 83.56% 84.56% 0.73%
31-Jan-14
52

31-Jan-14 84.83% 82.83% 83.83% 1.42%


24-Jan-14
51

24-Jan-14 84.41% 80.41% 82.41% 1.63%


17-Jan-14
50

17-Jan-14 82.78% 78.78% 80.78% 0.86%


10-Jan-14
49

10-Jan-14 81.92% 77.92% 79.92% 1.40%


3-Jan-14
48

3-Jan-14 80.52% 76.52% 78.52% 3.00%


27-Dec-13
47

27-Dec-13 77.52% 73.52% 75.52% 0.88%


20-Dec-13
46

20-Dec-13 76.64% 72.64% 74.64% 1.26%


13-Dec-13
45

13-Dec-13 75.38% 71.38% 73.38% 1.15%


6-Dec-13
44

6-Dec-13 74.22% 70.22% 72.22% 3.30%


29-Nov-13
43

29-Nov-13 70.93% 66.93% 68.93% 3.04%


22-Nov-13
42

22-Nov-13 67.89% 63.89% 65.89% 1.50%


EPCC FOR TOPSIDES OF DMDP-A DRILLING PLATFORM

15-Nov-13
41
Actual Cum

15-Nov-13 66.39% 62.39% 64.39% 1.56%


8-Nov-13
40

8-Nov-13 64.83% 60.83% 62.83% 3.53%


1-Nov-13
39

1-Nov-13 61.29% 57.29% 59.29% 2.38%


25-Oct-13
DMDP-A DRILLING PLATFORM

38

25-Oct-13 58.92% 54.92% 56.92% 2.16%


18-Oct-13
Mean Plan Cum
Overall EPCC S-Curve for Topside (Rev 0)

37

18-Oct-13 56.76% 52.76% 54.76% 1.78%


11-Oct-13
36

11-Oct-13 54.98% 50.98% 52.98% 1.34%


4-Oct-13
35

4-Oct-13 53.64% 49.64% 51.64% 1.35%


27-Sep-13
34

27-Sep-13 52.29% 48.29% 50.29% 2.32%


20-Sep-13
33
Late Plan Cum

20-Sep-13 49.97% 45.97% 47.97% 1.85%


13-Sep-13
32

13-Sep-13 48.12% 44.12% 46.12% 1.44%


6-Sep-13
31

6-Sep-13 46.68% 42.68% 44.68% 2.43%


30-Aug-13
30

23-Aug-13 30-Aug-13 44.25% 40.25% 42.25% 2.45%


29

23-Aug-13 41.80% 37.80% 39.80% 1.06%


Series1

16-Aug-13
28

9-Aug-13 16-Aug-13 40.74% 36.74% 38.74% 1.07%


27

2-Aug-13 9-Aug-13 39.67% 35.67% 37.67% 1.03%


26

26-Jul-13 2-Aug-13 38.65% 34.65% 36.65% 1.62%


25

19-Jul-13 26-Jul-13 37.03% 33.03% 35.03% 0.78%


24

12-Jul-13 19-Jul-13 36.25% 32.25% 34.25% 0.88%


23

5-Jul-13 12-Jul-13 35.36% 31.36% 33.36% 1.03%


28-Jun-13 22
21 5-Jul-13 34.33% 30.33% 32.33% 1.69%
21-Jun-13 28-Jun-13 32.64% 28.64% 30.64% 1.39%

20
14-Jun-13 21-Jun-13 31.25% 27.25% 29.25% 2.28%

19
7-Jun-13 14-Jun-13 28.97% 24.97% 26.97% 0.67%

18
31-May-13 7-Jun-13 28.30% 24.30% 26.30% 1.10%

17
24-May-13 31-May-13 27.20% 23.20% 25.20% 0.53%

16
17-May-13 24-May-13 26.68% 22.68% 24.68% 2.37%

15
10-May-13 17-May-13 23.30% 21.30% 22.30% 1.55%

14
3-May-13 10-May-13 21.76% 19.76% 20.76% 0.90%

13
26-Apr-13 3-May-13 20.86% 18.86% 19.86% 0.56%

12
19-Apr-13 26-Apr-13 20.30% 18.30% 19.30% 0.94%

11
12-Apr-13 19-Apr-13 19.35% 17.35% 18.35% 0.95%

10
5-Apr-13 12-Apr-13 18.40% 16.40% 17.40% 1.29%
29-Mar-13 5-Apr-13 17.12% 15.12% 16.12% 0.62%

9
22-Mar-13
29-Mar-13 16.50% 14.50% 15.50% 0.42%

8
15-Mar-13
22-Mar-13 16.08% 14.08% 15.08% 1.88%

7
8-Mar-13
15-Mar-13 14.20% 12.20% 13.20% 1.72%

6
1-Mar-13
8-Mar-13 12.48% 10.48% 11.48% 1.12%

5
22-Feb-13
1-Mar-13 11.36% 9.86% 10.36% 0.92%

4
15-Feb-13
22-Feb-13 10.44% 8.94% 9.44% 0.98%

3
8-Feb-13
15-Feb-13 9.47% 7.97% 8.47% 0.23%

2
Progress Cummulative

100.00%

0.00%
90.00%

80.00%

70.00%

60.00%

50.00%

40.00%

30.00%

20.00%

10.00%
8-Feb-13 9.24% 7.74% 8.24% 8.24%

1
Week No.

% Actual Per Week


Period

% Mean Plan Cum


% Early Plan Cum

% Plan Per Week


% Late Plan Cum

% Actual Cum

% Variance
56

28-Feb-14
28-Feb-14 100.00% 100.00% 100.00% 0.00%
55

21-Feb-14
21-Feb-14 100.00% 100.00% 100.00% 0.00%
54

14-Feb-14
14-Feb-14 100.00% 100.00% 100.00% 0.00%
53

7-Feb-14
7-Feb-14 100.00% 100.00% 100.00% 0.00%
31-Jan-14
52

31-Jan-14 100.00% 100.00% 100.00% 0.00%


24-Jan-14
51

24-Jan-14 100.00% 100.00% 100.00% 0.00%


17-Jan-14
50

17-Jan-14 100.00% 99.00% 100.00% 0.05%


10-Jan-14
49

10-Jan-14 100.00% 98.95% 99.95% 0.05%


3-Jan-14
48

3-Jan-14 100.00% 98.90% 99.90% 0.05%


27-Dec-13
47

27-Dec-13 100.00% 98.85% 99.85% 0.14%


20-Dec-13
46

20-Dec-13 100.00% 98.71% 99.71% 0.31%


13-Dec-13
45

13-Dec-13 101.40% 97.40% 99.40% 0.36%


6-Dec-13
44

6-Dec-13 101.05% 97.05% 99.05% 0.36%


43

29-Nov-13
29-Nov-13 100.69% 96.69% 98.69% 0.36%
42

22-Nov-13
22-Nov-13 100.33% 96.33% 98.33% 0.36%
41

15-Nov-13
15-Nov-13 99.98% 95.98% 97.98% 0.36%
40

8-Nov-13
8-Nov-13 99.62% 95.62% 97.62% 0.36%
39

1-Nov-13
1-Nov-13 99.26% 95.26% 97.26% 0.71%
38

25-Oct-13
25-Oct-13 99.55% 93.55% 96.55% 1.21%
37

18-Oct-13
18-Oct-13 98.34% 92.34% 95.34% 1.66%
36

11-Oct-13
11-Oct-13 96.68% 90.68% 93.68% 1.66%
35

4-Oct-13
4-Oct-13 95.03% 89.03% 92.03% 1.82%
34

27-Sep-13 27-Sep-13 93.20% 87.20% 90.20% 1.99%


33

20-Sep-13 20-Sep-13 91.22% 85.22% 88.22% 1.91%


Actual Cum

32

13-Sep-13 13-Sep-13 89.31% 83.31% 86.31% 2.43%


31

6-Sep-13 6-Sep-13 88.88% 78.88% 83.88% 2.54%


Engineering S-Curve for Topside (Rev 0)

30

30-Aug-13 86.34% 76.34% 81.34% 2.88%


EPCC FOR DMDP-A DRILLING PLATFORM

30-Aug-13
Mean Plan Cum

29

23-Aug-13 23-Aug-13 83.46% 73.46% 78.46% 2.96%


DMDP-A DRILLING PLATFORM

28

16-Aug-13 16-Aug-13 80.51% 70.51% 75.51% 2.85%


27

9-Aug-13 9-Aug-13 77.66% 67.66% 72.66% 2.69%


26

2-Aug-13 2-Aug-13 74.97% 64.97% 69.97% 3.01%


Late Plan Cum

25

26-Jul-13 26-Jul-13 71.96% 61.96% 66.96% 2.87%


24

19-Jul-13 19-Jul-13 69.08% 59.08% 64.08% 3.11%


23

12-Jul-13 12-Jul-13 65.97% 55.97% 60.97% 3.11%


22

5-Jul-13 5-Jul-13 62.86% 52.86% 57.86% 2.17%


Series1

21

28-Jun-13 28-Jun-13 60.69% 50.69% 55.69% 1.99%


20

21-Jun-13 21-Jun-13 58.70% 48.70% 53.70% 1.62%


19

14-Jun-13 14-Jun-13 57.07% 47.07% 52.07% 1.45%


18
7-Jun-13 7-Jun-13 55.62% 45.62% 50.62% 1.72%
17
31-May-13 31-May-13 53.90% 43.90% 48.90% 1.00%

16
24-May-13 24-May-13 52.90% 42.90% 47.90% 1.03%

15
17-May-13 17-May-13 51.86% 41.86% 46.86% 1.16%

14
10-May-13 10-May-13 50.71% 40.71% 45.71% 1.60%

13
3-May-13 3-May-13 49.10% 39.10% 44.10% 1.64%

12
26-Apr-13 26-Apr-13 47.46% 37.46% 42.46% 1.71%

11
19-Apr-13 19-Apr-13 45.75% 35.75% 40.75% 0.65%

10
12-Apr-13 12-Apr-13 45.11% 35.11% 40.11% 2.16%
5-Apr-13 42.95% 32.95% 37.95% 4.51%

9
5-Apr-13
29-Mar-13 38.44% 28.44% 33.44% 3.61%

8
29-Mar-13
22-Mar-13 34.83% 24.83% 29.83% 7.77%

7
22-Mar-13
15-Mar-13 27.06% 17.06% 22.06% 2.38%

6
15-Mar-13
8-Mar-13 24.68% 14.68% 19.68% 12.01%

5
8-Mar-13
1-Mar-13 9.67% 5.67% 7.67% 3.58%

4
1-Mar-13
22-Feb-13 6.08% 2.08% 4.08% 3.53%

3
22-Feb-13
15-Feb-13 2.56% 0.00% 0.56% 0.56%

2
15-Feb-13
8-Feb-13 0.00% 0.00% 0.00% 0.00%

1
8-Feb-13
Progress Cummulative
100.00%

90.00%

80.00%

70.00%

60.00%

50.00%

40.00%

30.00%

20.00%

10.00%

0.00%

Week No.

Period

% Actual Per Week


% Mean Plan Cum
% Early Plan Cum

% Plan Per Week


% Late Plan Cum

% Actual Cum

% Variance
56

28-Feb-14
28-Feb-14 100.00% 100.00% 100.00% 0.00%
55

21-Feb-14
21-Feb-14 100.00% 100.00% 100.00% 0.00%
54

14-Feb-14
14-Feb-14 100.00% 100.00% 100.00% 0.00%
53

7-Feb-14
7-Feb-14 100.00% 100.00% 100.00% 0.00%
31-Jan-14
52

31-Jan-14 100.00% 100.00% 100.00% 1.71%


24-Jan-14
51

24-Jan-14 99.29% 97.29% 98.29% 1.44%


17-Jan-14
50

17-Jan-14 98.85% 94.85% 96.85% 0.00%


10-Jan-14
49

10-Jan-14 98.85% 94.85% 96.85% 0.20%


3-Jan-14
48

3-Jan-14 98.65% 94.65% 96.65% 4.37%


27-Dec-13
47

27-Dec-13 95.78% 90.28% 92.28% 0.00%


20-Dec-13
46

20-Dec-13 95.28% 89.28% 92.28% 0.00%


13-Dec-13
45

13-Dec-13 94.78% 89.28% 92.28% 0.00%


6-Dec-13
44

6-Dec-13 94.28% 89.28% 92.28% 5.45%


29-Nov-13
43

29-Nov-13 89.83% 83.83% 86.83% 3.57%


22-Nov-13
42

22-Nov-13 86.26% 80.26% 83.26% 0.72%


15-Nov-13
41

15-Nov-13 85.54% 79.54% 82.54% 0.62%


8-Nov-13
40

8-Nov-13 84.93% 78.93% 81.93% 5.70%


1-Nov-13
39

1-Nov-13 79.23% 73.23% 76.23% 2.32%


25-Oct-13
38

25-Oct-13 76.91% 70.91% 73.91% 2.68%


18-Oct-13
37

18-Oct-13 74.22% 68.22% 71.22% 1.35%


11-Oct-13
36

11-Oct-13 73.48% 66.88% 69.88% 1.13%


4-Oct-13
35

4-Oct-13 72.75% 63.75% 68.75% 1.34%


27-Sep-13
34

27-Sep-13 71.40% 62.40% 67.40% 2.71%


33

20-Sep-13
Actual Cum

20-Sep-13 69.69% 59.69% 64.69% 2.03%


32

13-Sep-13
13-Sep-13 67.66% 57.66% 62.66% 1.24%
EPCC FOR TOPSIDES OF DMDP-A DRILLING PLATFORM

31

6-Sep-13
6-Sep-13 66.42% 56.42% 61.42% 3.82%
Procurement S-Curve for Topside (Rev 0)

30

30-Aug-13
30-Aug-13 62.59% 52.59% 57.59% 3.51%
Mean Plan Cum

29

23-Aug-13
23-Aug-13 59.08% 49.08% 54.08% 0.10%
DMDP-A DRILLING PLATFORM

28

16-Aug-13
16-Aug-13 58.98% 48.98% 53.98% 0.16%
27

9-Aug-13
9-Aug-13 58.83% 48.83% 53.83% 0.06%
26

2-Aug-13
2-Aug-13 58.77% 48.77% 53.77% 1.39%
Late Plan Cum

25

26-Jul-13 26-Jul-13 57.38% 47.38% 52.38% 0.12%


24

19-Jul-13 19-Jul-13 57.26% 47.26% 52.26% 0.33%


23

12-Jul-13 12-Jul-13 56.93% 46.93% 51.93% 0.34%


22

5-Jul-13 5-Jul-13 56.59% 46.59% 51.59% 1.62%


Series1

21

28-Jun-13 28-Jun-13 54.97% 44.97% 49.97% 0.51%


20

21-Jun-13 21-Jun-13 54.45% 44.45% 49.45% 2.93%


19

14-Jun-13 14-Jun-13 51.52% 41.52% 46.52% 0.43%


18 7-Jun-13 51.09% 41.09% 46.09% 1.80%
7-Jun-13
17
31-May-13 31-May-13 49.29% 39.29% 44.29% 0.92%

16
24-May-13 24-May-13 48.37% 38.37% 43.37% 4.52%

15
17-May-13 17-May-13 43.85% 33.85% 38.85% 1.36%

14
10-May-13 10-May-13 42.49% 32.49% 37.49% 1.23%

13
3-May-13 3-May-13 41.26% 31.26% 36.26% 0.63%

12
26-Apr-13 26-Apr-13 40.63% 30.63% 35.63% 1.86%

11
19-Apr-13 19-Apr-13 37.77% 29.77% 33.77% 1.81%

10
12-Apr-13 12-Apr-13 35.97% 27.97% 31.97% 2.77%
5-Apr-13 33.20% 25.20% 29.20% 0.56%

9
5-Apr-13
29-Mar-13 32.64% 24.64% 28.64% 0.46%

8
29-Mar-13
22-Mar-13 32.18% 24.18% 28.18% 3.48%

7
22-Mar-13
15-Mar-13 28.70% 20.70% 24.70% 3.44%

6
15-Mar-13
8-Mar-13 25.25% 18.25% 21.25% 0.33%

5
8-Mar-13
1-Mar-13 24.92% 17.67% 20.92% 0.25%

4
1-Mar-13
22-Feb-13 23.67% 17.67% 20.67% 0.33%

3
22-Feb-13
15-Feb-13 23.34% 17.34% 20.34% 0.02%

2
15-Feb-13
8-Feb-13 23.32% 17.32% 20.32% 20.32%

1
8-Feb-13
Progress Cummulative
100.00%

90.00%

80.00%

70.00%

60.00%

50.00%

40.00%

30.00%

20.00%

10.00%

0.00%

Week No.

Period

% Actual Per Week


% Mean Plan Cum
% Early Plan Cum

% Plan Per Week


% Late Plan Cum

% Actual Cum

% Variance
14-Mar-14
58

14-Mar-14 100.00% 100.00% 100.00% 0.77%


7-Mar-14
57

7-Mar-14 100.00% 97.23% 99.23% 6.05%


28-Feb-14
56

21-Feb-14 28-Feb-14 95.18% 91.18% 93.18% 2.66%


55

14-Feb-14 21-Feb-14 92.52% 88.52% 90.52% 1.84%


54

7-Feb-14 14-Feb-14 90.69% 86.69% 88.69% 1.36%


53

31-Jan-14 7-Feb-14 89.33% 85.33% 87.33% 1.65%


52

24-Jan-14 31-Jan-14 87.67% 83.67% 85.67% 1.66%


51

17-Jan-14 24-Jan-14 86.02% 82.02% 84.02% 2.37%


50

10-Jan-14 17-Jan-14 83.64% 79.64% 81.64% 1.88%


49

3-Jan-14 10-Jan-14 81.77% 77.77% 79.77% 2.96%


48

27-Dec-13 3-Jan-14 78.80% 74.80% 76.80% 2.79%


47

20-Dec-13 27-Dec-13 76.02% 72.02% 74.02% 1.93%


46

13-Dec-13 20-Dec-13 75.09% 69.09% 72.09% 2.79%


45

6-Dec-13 13-Dec-13 72.30% 66.30% 69.30% 2.53%


44

29-Nov-13 6-Dec-13 70.77% 62.77% 66.77% 2.47%


43

22-Nov-13 29-Nov-13 68.30% 60.30% 64.30% 3.64%


42

22-Nov-13 64.66% 56.66% 60.66% 2.72%


15-Nov-13
41

15-Nov-13 61.94% 53.94% 57.94% 2.93%


8-Nov-13
40

8-Nov-13 59.00% 51.00% 55.00% 2.73%


1-Nov-13
39

1-Nov-13 56.28% 48.28% 52.28% 3.14%


25-Oct-13
38

25-Oct-13 53.14% 45.14% 49.14% 2.22%


18-Oct-13
37

18-Oct-13 50.92% 42.92% 46.92% 2.53%


11-Oct-13
36

11-Oct-13 48.39% 40.39% 44.39% 1.71%


4-Oct-13
35

4-Oct-13 46.68% 38.68% 42.68% 1.50%


27-Sep-13
Actual Cum

34

27-Sep-13 45.18% 37.18% 41.18% 2.47%


20-Sep-13
33

20-Sep-13 42.71% 34.71% 38.71% 2.01%


13-Sep-13
32

13-Sep-13 40.69% 32.69% 36.69% 1.73%


Construction S-Curve for Topside (Rev 0)
EPCC FOR TOPSIDES OF DMDP-A DRILLING PLATFORM

6-Sep-13
31

6-Sep-13 38.96% 30.96% 34.96% 1.66%


Mean Plan Cum

30-Aug-13
30

30-Aug-13 37.30% 29.30% 33.30% 2.00%


23-Aug-13
29

23-Aug-13 35.30% 27.30% 31.30% 1.96%


DMDP-A DRILLING PLATFORM

16-Aug-13
28

16-Aug-13 33.34% 25.34% 29.34% 1.94%


9-Aug-13
27

9-Aug-13 31.40% 23.40% 27.40% 1.96%


Late Plan Cum

2-Aug-13
26

2-Aug-13 29.44% 21.44% 25.44% 2.05%


26-Jul-13
25

26-Jul-13 27.40% 19.40% 23.40% 1.31%


19-Jul-13
24

19-Jul-13 26.08% 18.08% 22.08% 1.31%


12-Jul-13
23

12-Jul-13 24.77% 16.77% 20.77% 1.64%


Series1

5-Jul-13
22

5-Jul-13 23.13% 15.13% 19.13% 2.13%


28-Jun-13
21

28-Jun-13 20.00% 14.00% 17.00% 2.47%


21-Jun-13
20

21-Jun-13 17.53% 11.53% 14.53% 2.36%


14-Jun-13
19

14-Jun-13 15.17% 9.17% 12.17% 0.96%


7-Jun-13
18
7-Jun-13 14.21% 8.21% 11.21% 0.63%
31-May-13 17
31-May-13 13.58% 7.58% 10.58% 0.20%
24-May-13

16
24-May-13 13.38% 7.38% 10.38% 1.20%
17-May-13

15
17-May-13 11.18% 7.18% 9.18% 2.15%
10-May-13

14
10-May-13 9.02% 5.02% 7.02% 0.71%
3-May-13

13
3-May-13 8.31% 4.31% 6.31% 0.50%
26-Apr-13

12
26-Apr-13 7.81% 3.81% 5.81% 0.21%
19-Apr-13

11
19-Apr-13 7.61% 3.61% 5.61% 0.40%
12-Apr-13

10
12-Apr-13 7.20% 3.20% 5.20% 0.18%
5-Apr-13
5-Apr-13 7.02% 3.02% 5.02% 0.28%

9
29-Mar-13
29-Mar-13 6.74% 2.74% 4.74% 0.05%

8
22-Mar-13
22-Mar-13 6.69% 2.69% 4.69% 0.04%

7
15-Mar-13
15-Mar-13 6.64% 2.64% 4.64% 0.48%

6
8-Mar-13
8-Mar-13 6.16% 2.16% 4.16% 0.60%

5
1-Mar-13
1-Mar-13 5.57% 1.57% 3.57% 1.40%

4
22-Feb-13 22-Feb-13 4.16% 0.16% 2.16% 1.47%

3
15-Feb-13 1.69% 0.00% 0.69% 0.69%

2
15-Feb-13
8-Feb-13 0.00% 0.00% 0.00% 0.00%

1
8-Feb-13
Progress Cummulative

90.00%

80.00%

70.00%

60.00%

50.00%

40.00%

30.00%

20.00%

10.00%

0.00%
100.00%

Week No.

% Actual Per Week


Period

% Mean Plan Cum


% Early Plan Cum

% Plan Per Week


% Late Plan Cum

% Actual Cum

% Variance
45

20-Jun-14 20-Jun-14 100.00% 100.00% 100.00% 0.02%


44

13-Jun-14 13-Jun-14 100.00% 99.48% 99.98% 0.03%


43

6-Jun-14 6-Jun-14 100.00% 99.45% 99.95% 0.04%


42

30-May-14 30-May-14 100.00% 99.41% 99.91% 0.05%


41

23-May-14 23-May-14 100.00% 99.36% 99.86% 0.05%


40

16-May-14 16-May-14 100.00% 99.30% 99.80% 0.09%


39

9-May-14 9-May-14 100.00% 98.62% 99.72% 0.08%


38

2-May-14 2-May-14 100.00% 98.14% 99.64% 0.07%


37

25-Apr-14 25-Apr-14 100.00% 97.08% 99.58% 4.09%


36

18-Apr-14 18-Apr-14 97.99% 92.99% 95.49% 21.55%


35

11-Apr-14 11-Apr-14 77.94% 69.94% 73.94% 35.77%


34

4-Apr-14 4-Apr-14 42.17% 34.17% 38.17% 14.61%


33

28-Mar-14 28-Mar-14 27.56% 19.56% 23.56% 4.47%


32

21-Mar-14 21.59% 16.59% 19.09% 2.35%


21-Mar-14
31

14-Mar-14 19.24% 14.24% 16.74% 4.00%


14-Mar-14
30

7-Mar-14 15.24% 10.24% 12.74% 1.98%


7-Mar-14
29
EPCC FOR TOPSIDES OF DMDP-A DRILLING PLATFORM

28-Feb-14 13.27% 8.27% 10.77% 0.65%


28-Feb-14
28

21-Feb-14 12.11% 8.11% 10.11% 0.61%


21-Feb-14
Actual Cum

27

14-Feb-14 11.50% 7.50% 9.50% 0.29%


14-Feb-14
DMDP-A DRILLING PLATFORM

26

7-Feb-14 11.21% 7.21% 9.21% 0.21%


7-Feb-14
25

31-Jan-14 11.00% 7.00% 9.00% 0.21%


31-Jan-14
24

24-Jan-14 10.78% 6.78% 8.78% 0.28%


HUC S-Curve for Topside (Rev 0)

Mean Plan Cum

24-Jan-14
23

17-Jan-14 10.50% 6.50% 8.50% 0.43%


17-Jan-14
22

10-Jan-14 10.07% 6.07% 8.07% 0.43%


10-Jan-14
21

3-Jan-14 9.64% 5.64% 7.64% 0.43%


3-Jan-14
20

27-Dec-13 9.21% 5.21% 7.21% 0.42%


Late Plan Cum

27-Dec-13
19

20-Dec-13 8.79% 4.79% 6.79% 0.42%


20-Dec-13
18

13-Dec-13 8.38% 4.38% 6.38% 0.41%


13-Dec-13
17
6-Dec-13 7.96% 3.96% 5.96% 0.28%
6-Dec-13 16
29-Nov-13 7.68% 3.68% 5.68% 0.22%
Series1
29-Nov-13

15
22-Nov-13 7.47% 3.47% 5.47% 0.21%
22-Nov-13

14
15-Nov-13 7.26% 3.26% 5.26% 0.29%

13
15-Nov-13
8-Nov-13 6.97% 2.97% 4.97% 0.54%

12
8-Nov-13
1-Nov-13 6.43% 2.43% 4.43% 0.52%

11
1-Nov-13 25-Oct-13 5.91% 2.41% 3.91% 0.50%

10
25-Oct-13 18-Oct-13 5.41% 1.91% 3.41% 0.50%
11-Oct-13 4.91% 1.91% 2.91% 0.50%

9
18-Oct-13
4-Oct-13 3.41% 1.41% 2.41% 0.50%

8
11-Oct-13
27-Sep-13 2.91% 0.91% 1.91% 0.50%

7
4-Oct-13
20-Sep-13 2.41% 0.41% 1.41% 0.50%

6
27-Sep-13
13-Sep-13 1.91% 0.00% 0.91% 0.50%

5
20-Sep-13
6-Sep-13 1.41% 0.00% 0.41% 0.31%

4
13-Sep-13
30-Aug-13 1.10% 0.00% 0.10% 0.07%

3
6-Sep-13
23-Aug-13 1.03% 0.00% 0.03% 0.03%

2
30-Aug-13
16-Aug-13 0.00% 0.00% 0.00% 0.00%

1
23-Aug-13
Progress Cummulative
16-Aug-13

Week No.
100.00%

90.00%

80.00%

70.00%

60.00%

50.00%

40.00%

30.00%

20.00%

10.00%

0.00%

% Actual Per Week


Period

% Mean Plan Cum


% Early Plan Cum

% Plan Per Week


% Late Plan Cum

% Actual Cum

% Variance
ATTACHMENT 7
Manhour Histogram, Manpower resource loading & Equipment
resource loading (Topside)
Riggers

Electrician
Scaffolders

Piping Fitters

Riggers
Electric Fitters

Piping Helpers

Week No
Piping Welders

Electrician
Manpower
Piping Pre-com

Scaffolders
Electric Helpers

Electric Welders
Electric Pre-com

Piping Fitters
Structural Fitters

Electric Fitters
Piping Helpers
Piping Welders

Piping Pre-com

Total Man-day
Electric Helpers
Electric Welders
Structural Fitters

Electric Pre-com

Total Man-hour
Structural Helpers

Structural Helpers
Structural Welders

Structural Welders
Blaster and Painter

Blaster and Painter

Topside:
10000
15000
20000
25000
30000
35000

5000

0
780 1040 0 0 0 0 0 0 0 0 0 1040 2080 2600 17-May-13

6
7540 145 0

780 1040 0 0 0 0 0 0 0 0 0 1040 2080 2600 24-May-13

7
7540 145 0

Total Direct Man-hour for Onshore Fabrication of


780 1040 0 0 0 0 0 0 0 0 0 1040 2080 2600 31-May-13

8
7540 145 0

780 1040 0 0 0 0 0 0 0 0 0 1820 2080 3900 7-Jun-13

9
9620 185 0

780 1040 0 0 0 0 0 0 520 520 1040 1820 3120 4576 14-Jun-13

10
13416 258 0

759,616
780 1040 0 0 0 0 0 0 520 520 1040 1820 2704 4680 21-Jun-13

11
13104 252 0

780 1040 0 0 0 0 0 0 520 520 1040 1820 3380 4784 28-Jun-13

12
13884 267 0

780 1040 0 0 0 0 0 0 520 1820 1560 1820 3432 4992 5-Jul-13

13
15964 307 0

780 1040 0 416 416 520 520 0 520 2080 1560 1820 4004 5148 12-Jul-13

14
18824 362 0

780 1040 0 416 260 520 520 0 520 2080 1560 1820 4004 5460 19-Jul-13

15
18980 365 0

780 1040 0 416 260 520 520 0 520 2080 1560 1820 4108 5616 26-Jul-13
16
20280 390 1040

780 1040 0 416 260 520 520 0 520 2080 1560 1820 4264 5980 2-Aug-13
17

20800 400 1040

780 1040 0 416 260 520 520 0 520 2340 1560 1820 4420 6084 9-Aug-13
18

21320 410 1040

780 1040 0 416 260 520 520 0 520 2340 1560 1820 4576 6448 16-Aug-13
19

21840 420 1040

780 1560 0 416 260 520 520 0 520 2340 1560 1820 4576 6656 23-Aug-13
20

22568 434 1040

780 1560 0 416 260 520 520 0 520 2340 1560 1820 4784 6864 30-Aug-13
21

22984 442 1040

780 1560 0 416 260 520 520 0 520 2704 1560 1820 4784 7228 6-Sep-13
22

23712 456 1040

780 1560 0 416 260 312 416 0 520 3016 1560 1040 4940 7384 13-Sep-13
23

23244 447 1040

780 1560 0 416 260 312 416 0 520 3016 1560 1040 5096 7696 20-Sep-13
24

23712 456 1040

780 1560 0 416 260 312 416 0 520 3016 1560 1040 5252 8060 27-Sep-13
25

24232 466 1040

780 2080 0 416 260 312 416 0 520 3276 1560 1040 5408 8112 4-Oct-13
26

25220 485 1040

Page 1 of 1
780 2080 0 416 260 312 416 0 780 3276 2340 1040 5616 8320 11-Oct-13
27

26676 513 1040

780 2080 0 416 260 312 416 0 780 3276 2340 1040 5772 8580 18-Oct-13
28

27092 521 1040


EPCC DIAMOND DRILLING PLATFORM

780 2080 0 416 260 312 416 0 780 3276 2340 1040 5928 8944 25-Oct-13
29

27612 531 1040

780 2080 0 416 1300 312 416 0 780 3276 2340 1040 5928 8944 1-Nov-13
30

28652 551 1040


TOPSIDE DIRECT MAN-HOURS HISTOGRAM (ONSHORE FABRICATION)

780 2080 0 416 1300 312 416 0 780 2340 2340 1040 5928 8944 8-Nov-13
31

27716 533 1040

780 2080 0 416 1300 312 416 0 780 2340 2340 1040 5928 8944 15-Nov-13
32

27716 533 1040

780 2080 0 416 1300 312 416 0 780 2340 2340 1040 5928 8944 22-Nov-13
33

27716 533 1040

780 2080 0 416 1300 312 416 0 780 2340 2340 1040 5928 8944 29-Nov-13
34

27716 533 1040

780 2080 0 416 1300 312 416 0 780 1820 2340 1040 5824 8736 6-Dec-13
35

26884 517 1040

780 1560 0 416 1300 312 416 0 780 1820 3120 1040 5616 7800 13-Dec-13
36

25480 490 520

780 1560 0 416 1300 312 416 0 780 1300 3120 1040 5096 7592 20-Dec-13
37

24232 466 520

780 1560 0 416 1300 312 416 0 780 1300 3120 1040 4784 7280 27-Dec-13
38

23608 454 520

780 1560 416 416 1300 312 416 0 780 1300 3120 1040 4212 6864 3-Jan-14
39

23036 443 520

780 1560 416 416 1300 312 416 0 520 0 3120 780 4108 6448 10-Jan-14
40

20696 398 520

780 1560 416 416 1300 312 416 0 520 0 1560 780 3744 6136 17-Jan-14
41

18460 355 520

780 1560 416 416 1300 312 416 520 520 0 1560 780 3536 5512 24-Jan-14
42

18148 349 520

780 1560 416 416 1300 0 416 520 520 0 1560 780 3224 5200 31-Jan-14
43

17212 331 520

0 0 0 0 0 0 0 0 0 0 0 0 0 0 7-Feb-14
44

0 0 0

780 1560 416 416 1300 0 416 520 520 0 1560 780 2444 4264 14-Feb-14
45

15496 298 520

780 1040 780 416 1300 0 416 520 520 0 1560 780 2444 4264 21-Feb-14
46

15340 295 520

780 1040 0 0 0 0 0 0 0 0 1560 780 2704 4264 28-Feb-14


47

11128 214 0

1040 0 0 0 0 0 0 0 0 1560 780 2704 4264 7-Mar-14


48

11128 214 0 780

1040 0 0 0 0 0 0 0 0 1560 780 2704 4056 14-Mar-14


49

10920 210 0 780


Safety

QA/QC

Foremen
Procurment

Supervisors
1000
2000
3000
4000
5000
6000
7000
8000

Engineering

Total Man-day

Total Man-hour
8-Feb-13
15-Feb-13

Project Management Team


Manpower/ Week No
22-Feb-13

1-Mar-13
672 14 0 0 0 0 192 240 240 8-Feb-13 8-Mar-13

672 14 0 0 0 0 192 240 240 15-Feb-13 15-Mar-13

672 14 0 0 0 0 192 240 240 22-Feb-13 22-Mar-13

672 14 0 0 0 0 192 240 240 1-Mar-13 29-Mar-13

720 15 0 0 48 0 192 240 240 8-Mar-13 5-Apr-13

720 15 0 0 48 0 192 240 240 15-Mar-13 12-Apr-13

Total Indirect Man-hour for Onshore Fabrication of Topside


720 15 0 0 48 0 192 240 240 22-Mar-13 19-Apr-13

720 15 0 0 48 0 192 240 240 29-Mar-13 26-Apr-13

720 15 0 0 48 0 192 240 240 5-Apr-13 3-May-13

720 15 0 0 48 0 192 240 240 12-Apr-13 10-May-13

720 15 0 0 48 0 192 240 240 19-Apr-13 17-May-13

720 15 0 0 48 0 192 240 240 26-Apr-13 24-May-13

720 15 0 0 48 0 192 240 240 3-May-13 31-May-13

720 15 0 0 48 0 192 240 240 10-May-13 7-Jun-13

1533 32 333 288 48 192 192 240 240 17-May-13 14-Jun-13


21-Jun-13
1533 32 333 288 48 192 192 240 240 24-May-13
28-Jun-13
1533 32 333 288 48 192 192 240 240 31-May-13
5-Jul-13
2589 54 333 288 384 192 384 432 576 7-Jun-13
12-Jul-13
2589 54 333 288 384 192 384 432 576 14-Jun-13
19-Jul-13
2647 55 391 288 384 192 384 432 576 21-Jun-13
26-Jul-13
3005 63 461 576 384 192 384 432 576 28-Jun-13
2-Aug-13
3065 64 521 576 384 192 384 432 576 5-Jul-13
9-Aug-13
3097 65 553 576 384 192 384 432 576 12-Jul-13
16-Aug-13
3320 69 776 576 384 192 384 432 576 19-Jul-13
23-Aug-13
3352 70 808 576 384 192 384 432 576 26-Jul-13
30-Aug-13
3692 77 812 576 384 192 384 768 576 2-Aug-13
6-Sep-13
3736 78 856 576 384 192 384 768 576 9-Aug-13
13-Sep-13
216,907

3812 79 932 576 384 192 384 768 576 16-Aug-13


20-Sep-13
3810 79 930 576 384 192 384 768 576 23-Aug-13
27-Sep-13
5448 114 120 1008 1200 432 576 1056 1056 30-Aug-13
4-Oct-13

Page 1 of 1
6248 130 920 1008 1200 432 576 1056 1056 6-Sep-13
11-Oct-13
EPCC DIAMOND DRILLING PLATFORM

6239 130 911 1008 1200 432 576 1056 1056 13-Sep-13
18-Oct-13
6288 131 960 1008 1200 432 576 1056 1056 20-Sep-13
25-Oct-13
6358 132 1030 1008 1200 432 576 1056 1056 27-Sep-13
1-Nov-13
6429 134 1101 1008 1200 432 576 1056 1056 4-Oct-13
8-Nov-13
6512 136 1184 1008 1200 432 576 1056 1056 11-Oct-13
TOPSIDE INDIRECT MAN-HOURS HISTOGRAM (ONHORE FABRICATION)

15-Nov-13
6579 137 1251 1008 1200 432 576 1056 1056 18-Oct-13
22-Nov-13
6651 139 1323 1008 1200 432 576 1056 1056 25-Oct-13
29-Nov-13
6705 140 1377 1008 1200 432 576 1056 1056 1-Nov-13
6-Dec-13
6782 141 1454 1008 1200 432 576 1056 1056 8-Nov-13
13-Dec-13
6861 143 1533 1008 1200 432 576 1056 1056 15-Nov-13
20-Dec-13

6896 144 1568 1008 1200 432 576 1056 1056 22-Nov-13 27-Dec-13
3-Jan-14
6896 144 1568 1008 1200 432 576 1056 1056 29-Nov-13
10-Jan-14
6896 144 1568 1008 1200 432 576 1056 1056 6-Dec-13
17-Jan-14
6815 142 1487 1008 1200 432 576 1056 1056 13-Dec-13 24-Jan-14

6724 140 1396 1008 1200 432 576 1056 1056 20-Dec-13 31-Jan-14

7-Feb-14
6646 138 1318 1008 1200 432 576 1056 1056 27-Dec-13
14-Feb-14
5040 105 1248 576 576 432 384 768 1056 3-Jan-14
21-Feb-14
4910 102 1118 576 576 432 384 768 1056 10-Jan-14 28-Feb-14

7-Mar-14
4829 101 1037 576 576 432 384 768 1056 17-Jan-14
14-Mar-14
4790 100 998 576 576 432 384 768 1056 24-Jan-14

4725 98 933 576 576 432 384 768 1056 31-Jan-14

3857 80 881 576 576 432 192 480 720 7-Feb-14

3753 78 777 576 576 432 192 480 720 14-Feb-14


Safety
QA/QC
Foremen

Supervisors

Engineering
Procurment

3456 72 480 576 576 432 192 480 720 21-Feb-14

3456 72 480 576 576 432 192 480 720 28-Feb-14

3456 72 480 576 576 432 192 480 720 7-Mar-14


Project Management Team

3456 72 480 576 576 432 192 480 720 14-Mar-14


EQUIPMENT RESOURCE LOADING FOR DMDP-A TOPSIDE

Aug-13
May-13

Nov-13
Sep-13

Dec-13
Jun-13

Feb-14
Jan-14
Oct-13
Jul-13
No DESCRIPTION

6 Arc Welding M/C (Plan) 5 10 10 12 16 16 16 16 12 12

1 6 Arc Welding M/C (Actual)

Single Arc Welding M/C (Plan) 10 20 20 20 28 28 28 28 28 28

2 Single Arc Welding M/C (Actual)

Forklift 5 ton (Plan) 2 2 2 2 2 2 2 2 2 2

3 Forklift 5 ton (Actual)

Forklift 25 ton (Plan) 1 1 1 1 1 1 1 1 1 1

4 Forklift 25 ton (Actual)

Lorry 15 ton (Plan) 1 1 1 1 1 1 1 1 1 1

5 Lorry 15 ton (Actual)

Lorry 40 ton (Plan) 2 2 2 2 2 2 2 2 2 2

6 Lorry 40 ton (Actual)

Crane 50 ton (Plan) 1 1 1 1 1 1 1 1 1 1

7 Crane 50 ton (Actual)

Crane 70 ton (Plan) 1 1 1 1 1 1 1 1 1 1

8 Crane 70 ton (Actual)

Crane 135 ton (Plan) 1 1 1 1 1 1 1 1 1 1

9 Crane 135 ton (Actual)


Crane 250 ton (Plan) 1 1 1 1 1 1 1 1 1 1

10 Crane 250 ton (Actual)

Crane 275 ton (Plan) 1 1 1 1 1 1 1 1 1 1

11 Crane 275 ton (Actual)

Crane 600 ton (Plan) 1 1 1

12 Crane 600 ton (Actual)

Welding Quiver (Plan) 1 1 1 1 1 1 1 1 1 1

13 Welding Quiver (Actual)

Air Comp. (Plan) 2 2 3 3 3 3 3 3 3 3

14 Air Comp. (Actual)

Genset (Plan) 2 2 2 2 2 2 2 2 2 2

15 Genset (Actual)
MANPOWER OF ALL TRADES FOR DMDP-A
HOOK UP& COMMISSIONING

No. Manpower of All Trades Quantity

1 HUC Manager 1

2 HUC Superintendent 4

3 Construction supervisor 10

4 Commissioning Engineer 7

5 Hook up Engineer 6

6 QC Inspector 10

7 HSE & Scaffolder Supervisor 8

8 Insulation Technician 6

9 Heat treatment Technician 4

10 NDT Technician 4

11 Bolt Tensioning & Leak Test Technician 8

12 Hydrotest Tech. 8

13 Welder 38

14 Fitter 56

15 Scaffolder 18

16 Rigger 8

17 E&I Technician 15

18 Blaster& Painter 8

19 Helper 30

Total 249
MANHOURS & MANPOWER RESOURCE LOADING FOR DMDP-A TOPSIDE

ORIGINAL BUGGETED NO.


No. ACTIVITY START FINISH RESOURCE NAME
DURATION LABOR UNIT PERSONNEL
FABRICATION 265 21-May-13 28-Feb-14 759,616
I STRUCTURAL 213 21-May-13 25-Jan-14 272,974
I.1 FABRICATION OF TUBULARS 63 1-Jun-13 13-Aug-13 9,554
I.1.1 FABRICATION OF PIPE LEGS 37 1-Jun-13 13-Jul-13 3,822
1,911 Structural Fitters 6
1,146 Structural Welders 4
573 Structural Helpers 2
191 Rigger 1
I.1.2 FABRICATION OF BRACING 33 6-Jul-13 13-Aug-13 5,732 -
2,866 Structural Fitters 11
1,720 Structural Welders 7
860 Structural Helpers 3
287 Rigger 1
I.2 FABRICATION OF STRUCTURAL MEMBERS 191 21-May-13 30-Dec-13 152,865 -
I.2.1 FABRICATION OF CELLAR DECK FRAME 88 21-May-13 30-Aug-13 45,860 -
I.2.1.1 FABRICATION WF BEAMS OF CELLAR DECK 13 1-Jun-13 15-Jun-13 2,293 -
917 Structural Fitters 9
688 Structural Welders 7
344 Structural Helpers 3
115 Rigger 1
229 Scaffolders 2
I.2.1.2 FABRICATION OF CELLAR DECK PART II 72 21-May-13 12-Aug-13 16,051 -
I.2.1.2.1 FABRICATION OF PRIMARY FRAME PART II 44 21-May-13 10-Jul-13 6,420 -
2,761 Structural Fitters 8
1,733 Structural Welders 5
963 Structural Helpers 3
321 Rigger 1
642 Scaffolders 2
I.2.1.2.2 FABRICATION OF SECONDARY FRAME PART II 33 13-Jun-13 20-Jul-13 4,815 -
2,071 Structural Fitters 8
1,300 Structural Welders 5
722 Structural Helpers 3
241 Rigger 1
482 Scaffolders 2
I.2.1.2.3 FABRICATION OF JOINT DETAIL PART II 43 5-Jun-13 24-Jul-13 1,605 -
722 Structural Fitters 2
562 Structural Welders 2
241 Structural Helpers 1
80 Rigger 1
- -
I.2.1.2.4 FABRICATION OF DECK PLATING PART II 40 27-Jun-13 12-Aug-13 3,210 -
1,284 Structural Fitters 4
963 Structural Welders 3
482 Structural Helpers 2
161 Rigger 1
321 Scaffolders 1
I.2.1.3 FABRICATION OF CELLAR DECK PART III 75 27-May-13 21-Aug-13 13,758 -
I.2.1.3.1 FABRICATION OF PRIMARY FRAME PART III 41 27-May-13 12-Jul-13 5,503 -
2,366 Structural Fitters 7
1,486 Structural Welders 5
825 Structural Helpers 3
275 Rigger 1
550 Scaffolders 2
I.2.1.3.2 FABRICATION OF SECONDARY FRAME PART III 40 14-Jun-13 30-Jul-13 4,127 -
1,775 Structural Fitters 6
1,114 Structural Welders 3
619 Structural Helpers 2
206 Rigger 1
413 Scaffolders 1
I.2.1.3.3 FABRICATION OF JOINT DETAIL PART III 35 14-Jun-13 24-Jul-13 1,376 -
619 Structural Fitters 2
482 Structural Welders 2
206 Structural Helpers 1
69 Rigger 1
- -
I.2.1.3.4 FABRICATION OF DECK PLATING PART III 44 2-Jul-13 21-Aug-13 2,752 -
1,101 Structural Fitters 3
825 Structural Welders 2
413 Structural Helpers 1
138 Rigger 1
275 Scaffolders 1
I.2.1.4 FABRICATION OF CELLAR DECK PART I 83 27-May-13 30-Aug-13 13,758 -
I.2.1.4.1 FABRICATION OF PRIMARY FRAME PART I 46 27-May-13 18-Jul-13 5,503 -
2,366 Structural Fitters 6
1,486 Structural Welders 4
825 Structural Helpers 2
275 Rigger 1
550 Scaffolders 1
-
I.2.1.4.2 FABRICATION OF SECONDARY FRAME PART I 44 19-Jun-13 8-Aug-13 4,127 -
1,775 Structural Fitters 5
1,114 Structural Welders 3
619 Structural Helpers 2
206 Rigger 1
413 Scaffolders 1

1
I.2.1.4.3 FABRICATION OF JOINT DETAIL PART I 35 17-Jun-13 26-Jul-13 1,376 -
619 Structural Fitters 2
482 Structural Welders 2
206 Structural Helpers 1
69 Rigger 1
- -
I.2.1.4.4 FABRICATION OF DECK PLATING PART I 48 6-Jul-13 30-Aug-13 2,752 -
1,101 Structural Fitters 3
825 Structural Welders 2
413 Structural Helpers 1
138 Rigger 1
275 Scaffolders 1
I.2.2 FABRICATION OF CLOSED DRAIN VESSEL FRAME 28 31-Aug-13 3-Oct-13 3,057 -
1,529 Structural Fitters 7
764 Structural Welders 3
459 Structural Helpers 2
153 Rigger 1
153 Scaffolders 1
I.2.3 FABRICATION OF MAIN DECK FRAME 115 17-Jun-13 29-Oct-13 45,860 -
I.2.3.1 FABRICATION WF BEAMS OF MAIN DECK 29 17-Jun-13 19-Jul-13 4,586 -
1,834 Structural Fitters 8
1,376 Structural Welders 6
688 Structural Helpers 3
229 Rigger 1
459 Scaffolders 2
I.2.3.2 FABRICATION OF MAIN DECK PART II 83 9-Jul-13 14-Oct-13 16,051 -
I.2.3.2.1 FABRICATION OF PRIMARY FRAME PART II 46 9-Jul-13 30-Aug-13 6,420 -
2,761 Structural Fitters 8
1,733 Structural Welders 5
963 Structural Helpers 3
321 Rigger 1
642 Scaffolders 2
I.2.3.2.2 FABRICATION OF SECONDARY FRAME PART II 46 20-Jul-13 12-Sep-13 4,815 -
2,071 Structural Fitters 6
1,300 Structural Welders 4
722 Structural Helpers 2
241 Rigger 1
482 Scaffolders 1
I.2.3.2.3 FABRICATION OF JOINT DETAIL PART II 54 17-Jul-13 18-Sep-13 1,605 -
722 Structural Fitters 2
562 Structural Welders 1
241 Structural Helpers 1
80 Rigger 1
- -
I.2.3.2.4 FABRICATION OF DECK PLATING PART II 58 7-Aug-13 14-Oct-13 3,210 -
1,284 Structural Fitters 3
963 Structural Welders 2
482 Structural Helpers 1
161 Rigger 1
321 Scaffolders 1
I.2.3.3 FABRICATION OF MAIN DECK PART III 74 26-Jul-13 21-Oct-13 16,051 -
I.2.3.3.1 FABRICATION OF PRIMARY FRAME PART III 36 26-Jul-13 6-Sep-13 6,420 -
2,761 Structural Fitters 10
1,733 Structural Welders 6
963 Structural Helpers 3
321 Rigger 1
642 Scaffolders 2
-
I.2.3.3.2 FABRICATION OF SECONDARY FRAME PART III 34 7-Aug-13 16-Sep-13 4,815 -
2,071 Structural Fitters 8
1,300 Structural Welders 5
722 Structural Helpers 3
241 Rigger 1
482 Scaffolders 2
I.2.3.3.3 FABRICATION OF JOINT DETAIL PART III 39 13-Aug-13 27-Sep-13 1,605 -
722 Structural Fitters 2
562 Structural Welders 2
241 Structural Helpers 1
80 Rigger 1
- -
I.2.3.3.4 FABRICATION OF DECK PLATING PART III 49 24-Aug-13 21-Oct-13 3,210 -
1,284 Structural Fitters 3
963 Structural Welders 2
482 Structural Helpers 1
161 Rigger 1
321 Scaffolders 1
I.2.3.4 FABRICATION OF MAIN DECK PART I 71 7-Aug-13 29-Oct-13 9,172 -
I.2.3.4.1 FABRICATION OF PRIMARY FRAME PART I 48 7-Aug-13 2-Oct-13 3,669 -
1,578 Structural Fitters 4
991 Structural Welders 3
550 Structural Helpers 1
183 Rigger 1
367 Scaffolders 1
I.2.3.4.2 FABRICATION OF SECONDARY FRAME PART I 48 19-Aug-13 14-Oct-13 3,669 -
1,578 Structural Fitters 4
991 Structural Welders 3
550 Structural Helpers 1
183 Rigger 1
367 Scaffolders 1
I.2.3.4.3 FABRICATION OF JOINT DETAIL PART I 56 24-Aug-13 29-Oct-13 1,834 -

2
825 Structural Fitters 2
642 Structural Welders 1
275 Structural Helpers 1
92 Rigger 1
- -
I.2.4 FABRICATION OF HELI DECK 20 5-Dec-13 27-Dec-13 4,586 -
2,522 Structural Fitters 16
688 Structural Helpers 4
459 Rigger 3
917 Scaffolders 6
I.2.5 FABRICATION OF VENT BOOM 68 12-Oct-13 30-Dec-13 15,287 -
7,643 Structural Fitters 14
3,822 Structural Welders 7
2,293 Structural Helpers 4
764 Rigger 1
764 Scaffolders 1
I.2.6 FABRICATION OF OTHER ITEMS 72 11-Sep-13 4-Dec-13 38,216 -
I.2.6.1 FABRICATION HANDRAIL 48 9-Oct-13 4-Dec-13 5,045 -
2,018 Structural Fitters 5
1,513 Structural Welders 4
1,513 Structural Helpers 4
-
-
I.2.6.2 FABRICATION LADDER 48 9-Oct-13 3-Dec-13 764 -
306 Structural Fitters 1
229 Structural Welders 1
229 Structural Helpers 1
- -
- -
I.2.6.3 FABRICATION STAIRWAY 48 9-Oct-13 3-Dec-13 3,363 -
1,345 Structural Fitters 4
1,009 Structural Welders 3
1,009 Structural Helpers 3
- -
- -
I.2.6.4 FABRICATION DECK DRAIN 48 9-Oct-13 3-Dec-13 1,445 -
578 Structural Fitters 2
433 Structural Welders 1
433 Structural Helpers 1
- -
- -
I.2.6.5 FABRICATION EQUIPMENT MOUNTING 48 9-Oct-13 3-Dec-13 382 -
153 Structural Fitters 1
115 Structural Welders 1
115 Structural Helpers 1
- -
- -
I.2.6.6 FABRICATION LIFE RAFT SUPPORT 48 9-Oct-13 3-Dec-13 382 -
153 Structural Fitters 1
115 Structural Welders 1
115 Structural Helpers 1
- -
- -
I.2.6.7 FABRICATION LIFTING PADEYE 48 9-Oct-13 3-Dec-13 1,804 -
722 Structural Fitters 2
541 Structural Welders 1
541 Structural Helpers 1
- -
- -
I.2.6.8 FABRICATION VENT BOOM SUPPORT 48 9-Oct-13 3-Dec-13 1,926 -
770 Structural Fitters 2
578 Structural Welders 2
578 Structural Helpers 2
- -
- -
I.2.6.9 FABRICATION MONORAIL 48 9-Oct-13 3-Dec-13 699 -
280 Structural Fitters 1
210 Structural Welders 1
210 Structural Helpers 1
- -
- -
I.2.6.10 FABRICATION SECURITY GATE AND WALL 48 9-Oct-13 3-Dec-13 5,847 -
2,339 Structural Fitters 6
1,754 Structural Welders 5
1,754 Structural Helpers 5
- -
- -
I.2.6.11 FABRICATION CONDUCTOR GUIDE 24 9-Oct-13 5-Nov-13 6,566 -
2,955 Structural Fitters 15
2,298 Structural Welders 12
985 Structural Helpers 5
328 Rigger 2
- -
I.2.6.12 FABRICATION HATCH COVER 24 9-Oct-13 5-Nov-13 1,685 -
758 Structural Fitters 4
590 Structural Welders 3
253 Structural Helpers 1
84 Rigger 1
- -
I.2.6.13 FABRICATION CRANE ACCESS PLATFORM 24 15-Oct-13 11-Nov-13 627 -

3
282 Structural Fitters 1
219 Structural Welders 1
94 Structural Helpers 1
31 Rigger 1
- -
I.2.6.14 FABRICATION FIRE & BLASTWALL 24 11-Sep-13 8-Oct-13 6,669 -
2,668 Structural Fitters 14
2,001 Structural Welders 10
1,334 Structural Helpers 7
667 Rigger 3
- -
I.2.6.15 FABRICATION PLATFORM NAME PLATE 12 1-Nov-13 14-Nov-13 382 -
153 Structural Fitters 2
115 Structural Welders 1
115 Structural Helpers 1
- -
- -
I.2.6.16 FABRICATION CONES (4 PCS) 12 16-Sep-13 28-Sep-13 627 -
282 Structural Fitters 3
219 Structural Welders 2
94 Structural Helpers 1
31 Rigger 1
- -
I.3 ERECTION 156 6-Aug-13 17-Feb-14 101,000 -
I.3.1 LAYOUT/ERECTION SUPPORTS & LOAD OUT BEAMS TO FINAL POSITION
7 22-Aug-13 29-Aug-13 8,080 -
2,020 Structural Fitters 36
1,616 Structural Welders 29
2,020 Structural Helpers 36
808 Rigger 14
1,616 Scaffolders 29
I.3.2 CELLAR DECK PART I STACK UP 7 03-Sep-13* 10-Sep-13 6,060 -
1,515 Structural Fitters 27
1,212 Structural Welders 22
1,515 Structural Helpers 27
606 Rigger 11
1,212 Scaffolders 22
I.3.3 CELLAR DECK PART II STACK UP 7 12-Sep-13 19-Sep-13 5,050 -
1,263 Structural Fitters 23
1,010 Structural Welders 18
1,263 Structural Helpers 23
505 Rigger 9
1,010 Scaffolders 18
I.3.4 CELLAR DECK PART III STACK UP 7 21-Sep-13 28-Sep-13 4,040 -
1,010 Structural Fitters 18
808 Structural Welders 14
1,010 Structural Helpers 18
404 Rigger 7
808 Scaffolders 14
I.3.5 CLOSE DRAIN FRAME STACK UP 5 10-Oct-13 15-Oct-13 1,010 -
253 Structural Fitters 6
202 Structural Welders 5
253 Structural Helpers 6
101 Rigger 3
202 Scaffolders 5
I.3.6 PIPE LEGS ERECTION 15 30-Sep-13 16-Oct-13 3,030 -
758 Structural Fitters 6
606 Structural Welders 5
758 Structural Helpers 6
303 Rigger 3
606 Scaffolders 5
I.3.7 BRACING PIPE ERECTION (PART 1) 20 30-Sep-13 22-Oct-13 8,080 -
2,020 Structural Fitters 13
1,616 Structural Welders 10
2,020 Structural Helpers 13
1,212 Rigger 8
1,212 Scaffolders 8
I.3.8 BLAST WALL ERECTION (PART 1) 10 9-Oct-13 19-Oct-13 6,060 -
1,212 Structural Fitters 15
1,515 Structural Welders 19
1,212 Structural Helpers 15
909 Rigger 11
1,212 Scaffolders 15
I.3.9 MAIN DECK PART I (AXIS 1/2) STACK UP 10 5-Nov-13 15-Nov-13 6,060 -
1,515 Structural Fitters 19
1,212 Structural Welders 15
1,515 Structural Helpers 19
606 Rigger 8
1,212 Scaffolders 15
I.3.10 MAIN DECK PART II (AXIS 2/2a) STACK UP 8 11-Nov-13 19-Nov-13 5,050 -
1,263 Structural Fitters 20
1,010 Structural Welders 16
1,263 Structural Helpers 20
505 Rigger 8
1,010 Scaffolders 16
I.3.11 MAIN DECK PART III (AXIS 1a/1) STACK UP 7 20-Nov-13 27-Nov-13 4,040 -
1,010 Structural Fitters 18
808 Structural Welders 14
1,010 Structural Helpers 18
404 Rigger 7
808 Scaffolders 14

4
I.3.12 HELI DECK ERECTION 6 28-Dec-13 4-Jan-14 2,020 -
505 Structural Fitters 11
404 Structural Welders 8
505 Structural Helpers 11
202 Rigger 4
404 Scaffolders 8
I.3.13 BRACING ERECTION (REMAINING PART) 15 4-Dec-13 20-Dec-13 9,090 -
2,273 Structural Fitters 19
1,818 Structural Welders 15
2,273 Structural Helpers 19
1,364 Rigger 11
1,364 Scaffolders 11
I.3.14 BLAST WALL ERECTION (REMAINING PART) 12 4-Dec-13 17-Dec-13 8,080 -
1,616 Structural Fitters 17
2,020 Structural Welders 21
1,616 Structural Helpers 17
1,212 Rigger 13
1,616 Scaffolders 17
I.3.15 ERECTION OTHER ITEMS 21 20-Dec-13 14-Jan-14 25,250 -
10,858 Structural Fitters 65
6,818 Structural Welders 41
3,788 Structural Helpers 23
1,263 Rigger 8
2,525 Scaffolders 15
I.4 TRIAL FIT AND WEIGHING 23 30-Dec-13 25-Jan-14 9,554 -
I.4.1 VENT BOOM TRIAL FIT 6 20-Jan-14 25-Jan-14 3,344 -
1,672 Structural Helpers 35
669 Rigger 14
1,003 Scaffolders 21
I.4.2 FABRICATE/ ERECTION PADEYES 14 30-Dec-13 15-Jan-14 955 -
411 Structural Fitters 4
258 Structural Welders 2
143 Structural Helpers 1
I.4.3 TRIAL FIT/ LAYOUT T&I SLINGS 7 16-Jan-14 23-Jan-14 1,433 -
334 Structural Helpers 6
134 Rigger 2
201 Scaffolders 4
I.4.4 TOPSIDE WEIGHING 2 30-Dec-13* 2-Jan-14 3,822 -
3,822 Structural Helpers 239
II PIPING/ PLUMBING 199 15-Jun-13 10-Feb-14 269,618 -
II.1 FABRICATION OF PIPE/PLUMBING SUPPORTS 122.8 15-Jun-13 6-Nov-13 107,847 -
II.1.1 FABRICATE PIPE SUPPORT 60 15-Jun-13 23-Aug-13 13,481 -
2,022 Piping Fitters 4
1,348 Piping Welders 3
1,348 Piping Helpers 3
4,718 Structural Fitters 10
4,044 Structural Welders 8
II.1.2 FABRICATE PIPE SPOOL 105 5-Jul-13 6-Nov-13 94,366 -
47,183 Piping Fitters 56
28,310 Piping Welders 34
18,873 Piping Helpers 22
II.2 INSTALLATION OF PIPE/PLUMBING SUPPORTS 105 10-Sep-13 10-Jan-14 97,062 -
II.2.1 INSTALL PIPE SUPPORT 100 10-Sep-13 4-Jan-14 12,133 -
1,820 Piping Fitters 2
1,213 Piping Welders 2
4,246 Structural Fitters 5
3,640 Structural Welders 5
1,213 Scaffolders 2
II.2.2 INSTALL PIPE SPOOL 100 16-Sep-13 10-Jan-14 84,930 -
21,232 Piping Fitters 27
33,972 Piping Welders 42
8,493 Piping Helpers 11
8,493 Rigger 11
12,739 Scaffolders 16
II.3 INSTALLATION OF VALVES 40 10-Dec-13 25-Jan-14 12,133 -
4,853 Piping Fitters 15
1,820 Piping Helpers 6
1,820 Rigger 6
3,640 Scaffolders 11
II.4 LEAK TEST OF VALVES 35 24-Dec-13 8-Feb-14 9,437 -
3,303 Piping Fitters 12
4,246 Piping Helpers 15
1,887 Scaffolders 7
II.5 FLUSHING, HYDROTESTING AND ACID CLEANING 63 22-Nov-13 10-Feb-14 26,962 -
9,437 Piping Fitters 19
9,437 Piping Helpers 19
8,089 Scaffolders 16
II.6 INSULATION 60 22-Nov-13 6-Feb-14 16,177 -
4,044 Piping Fitters 8
6,471 Piping Welders 13
1,618 Piping Helpers 3
1,618 Rigger 3
2,427 Scaffolders 5
III MECHANICAL 98 30-Sep-13 22-Jan-14 33,584 -
III.1 SETTING UP EQUIPMENT ON DECK 88 30-Sep-13 10-Jan-14 11,754 -
III.1.1 SETTING UP EQUIPMENT ON CELLAR DECK 88 30-Sep-13 10-Jan-14 6,112 -
1,528 Structural Fitters 2
1,222 Structural Welders 2
1,528 Structural Helpers 2
611 Rigger 1

5
1,222 Scaffolders 2
III.1.2 SETTING UP EQUIPMENT ON MAIN DECK 40 20-Nov-13 6-Jan-14 5,642 -
1,411 Structural Fitters 4
1,128 Structural Welders 4
1,411 Structural Helpers 4
564 Rigger 2
1,128 Scaffolders 4
III.2 MECHANICAL COMPLETION (TIE-IN) 84 16-Oct-13 22-Jan-14 21,830 -
III.2.1 TIE-IN EQUIPMENT ON CELLAR DECK 84 16-Oct-13 22-Jan-14 11,351 -
2,838 Piping Fitters 4
2,270 Piping Welders 3
2,270 Structural Helpers 3
568 Rigger 1
1,703 Electrician 3
1,703 Scaffolders 3
III.2.2 TIE-IN EQUIPMENT ON MAIN DECK 50 22-Nov-13 21-Jan-14 10,478 -
2,620 Piping Fitters 7
2,096 Piping Welders 5
2,096 Structural Helpers 5
524 Rigger 1
1,572 Electrician 4
1,572 Scaffolders 4
IV INSTRUMENT 175 11-Jul-13 7-Feb-14 66,988 -
IV.1 FABRICATE INSTRUMENT SUPPORTS 40 11-Jul-13 26-Aug-13 5,359 -
804 Electric Fitters 3
536 Electric Welders 2
536 Electric Helpers 2
1,876 Structural Fitters 6
1,608 Structural Welders 5
IV.2 INSTALLATION OF INSTRUMENT SUPPORTS 55 11-Oct-13 13-Dec-13 7,369 -
1,105 Electric Fitters 3
737 Electric Welders 2
2,579 Structural Fitters 6
2,211 Structural Welders 5
737 Scaffolders 2
IV.3 TUBING TRAY I CABLE TRAY I LADDER INSTALLATION 55 19-Oct-13 21-Dec-13 6,699 -
1,005 Electric Fitters 2
670 Electric Welders 2
1,340 Electrician 3
2,010 Structural Fitters 5
1,675 Scaffolders 4
IV.4 CALIBRATE INSTRUMENT 55 11-Oct-13 13-Dec-13 670 -
670 Electrician 2
IV.5 INSTRUMENT EQUIPMENT INSTALLATION 78 23-Oct-13 22-Jan-14 7,369 -
1,105 Electric Fitters 2
1,842 Electric Helpers 3
2,579 Electrician 4
1,842 Scaffolders 3
IV.6 CABLE PULLING 50 12-Nov-13 9-Jan-14 10,048 -
1,507 Electric Fitters 4
1,507 Electric Helpers 4
3,014 Structural Helpers 8
4,019 Scaffolders 10
IV.7 DRESSING, GLANDING, TAGGING AND TERMINATION 50 5-Dec-13 7-Feb-14 22,776 -
11,388 Electrician 28
5,694 Scaffolders 14
5,694 Structural Helpers 14
IV.8 PULL AND HOOK-UP TUBING 30 26-Dec-13 5-Feb-14 6,699 -
3,349 Electrician 14
1,675 Scaffolders 7
1,675 Structural Helpers 7
V ELECTRICAL 173 11-Jul-13 5-Feb-14 82,391 -
V.1 ELECTRICAL SUPPORT 128 11-Jul-13 7-Dec-13 17,302 -
V.1.1 FABRICATION OF ELECTRICAL SUPPORT 50 11-Jul-13 7-Sep-13 6,921 -
1,038 Electric Fitters 3
692 Electric Welders 2
692 Electric Helpers 2
2,422 Structural Fitters 6
2,076 Structural Welders 5
V.1.2 INSTALLATION OF ELECTRICAL SUPPORT 55 5-Oct-13 7-Dec-13 10,381 -
1,557 Electric Fitters 4
1,038 Electric Welders 2
3,633 Structural Fitters 8
3,114 Structural Welders 7
1,038 Scaffolders 2
V.2 CABLE TRAY I CABLE LADDER INSTALLATION 55 11-Oct-13 13-Dec-13 14,006 -
2,101 Electric Fitters 5
2,801 Electrician 6
5,603 Structural Fitters 13
3,502 Scaffolders 8
V.3 CALIBRATE ELECTRICAL EQUIPMENT 50 23-Oct-13 19-Dec-13 824 -
824 Electrician 2
V.4 ELECTRICAL EQUIPMENT INSTALLATION 80 22-Oct-13 23-Jan-14 4,120 -
618 Electric Fitters 1
1,030 Electric Helpers 2
1,442 Electrician 2
1,030 Scaffolders 2
V.5 DRESSING, GLANCING, TAGGING AND TERMINATION 50 3-Dec-13 5-Feb-14 28,013 -
14,006 Electrician 35
7,003 Scaffolders 18

6
7,003 Structural Helpers 18
V.6 MCT INSTALLATION 7 28-Nov-13 5-Dec-13 824 -
124 Electric Fitters 2
165 Electrician 3
330 Structural Fitters 6
206 Scaffolders 4
V.7 EARTHING BOSS INSTALLATION 7 7-Jan-14 14-Jan-14 824 -
124 Electric Fitters 2
82 Electric Welders 1
288 Structural Fitters 5
247 Structural Welders 4
82 Scaffolders 1
VI BLASTING / PAINTING 221 20-Apr-13 7-Jan-14 12,669 -
VI.1 STRUCTURAL ITEMS 138 22-Apr-13 7-Jan-14 7,601 -
2,534 Blaster and Painter 8
158 Rigger 1
475 Scaffolders 1
VI.2 PIPING SUPPORTS/SPOOLS 127 22-Jun-13 18-Nov-13 3,167 -
2,534 Blaster and Painter 8
158 Rigger 1
475 Scaffolders 1
VI.3 PIPING VALVES 25 28-Nov-13 26-Dec-13 380 -
304 Blaster and Painter 2
19 Rigger 1
57 Scaffolders 1
VI.4 INSTRUMENT SUPPORTS 12 21-Aug-13 4-Sep-13 760 -
608 Blaster and Painter 6
38 Rigger 1
114 Scaffolders 1
VI.5 ELECTRICAL SUPPORTS 50 18-Jul-13 14-Sep-13 760 -
608 Blaster and Painter 2
38 Rigger 1
114 Scaffolders 1
VII ARCHITECTURAL 48 17-Oct-13 11-Dec-13 21,392 -
VII.1 SETTING UP FIRE RATED DOORS 9 26-Nov-13 5-Dec-13 2,139 -
749 Structural Fitters 10
428 Structural Welders 6
535 Structural Helpers 7
107 Rigger 1
321 Scaffolders 4
VII.2 SETTING UP TEMPORARY SHELTER 48 17-Oct-13 11-Dec-13 19,253 -
6,738 Structural Fitters 18
3,851 Structural Welders 10
4,813 Structural Helpers 13
963 Rigger 3
2,888 Scaffolders 8

7
ATTACHMENT 8
Progress Measurement Format
DMDP-A DRILLING PLATFORM
EPCC FOR TOPSIDES OF DMDP-A DRILLING PLATFORM
PROGRESS MEASUREMENT AND REPORTING FORMAT (REV.0)

Cut off date:


Week No. 06/28/13

MEASURE METHOD 06/28/13 06/28/13


PLAN
CUM THIS WEEK
Wtg
ACTIVITY ID ACTIVITY NAME Act. 1 Act. 2 Act. 3 Act. 4
(%) Act. 1 Act. 2 Act. 3 Act. 4 ACTUAL PLAN VAR
Weight Weight Weight Weight START FINISH
PROGRESS (5) PROGRESS (6) PROGRESS

EPCC DIAMOND PROJECT (TOPSIDES)


A 100.00% 33.22% 30.64% 2.58% 5-Sep-13 18-Jun-14
1 PROJECT MILESTONE 4-Feb-13 24-Mar-14
2 ENGINEERING 6.00% 59.82% 55.69% 4.13% 18-Feb-13 18-Jan-14
2.1 DETAIL DESIGN (to incorporate with RNZ/PVE schedule) 50.00% Prep/ Submit Accept/ Approve 78.81% 79.35% -0.54% 18-Feb-13 30-Sep-13
AFC 70.00% 100.00% 100.00% 18-Feb-13 5-Apr-13
POST-AFC 30.00% 29.38% 31.17% 25-Mar-13 30-Sep-13
2.2 CONSTRUCTION ENGINEERING 50.00% Prep/ Submit Accept/ Approve 40.82% 32.03% 8.80% 28-Mar-13 29-Jan-14
2.2.1 SHOP DRAWINGS 83.00% Prep/ Submit Accept/ Approve 30.87% 23.19% 7.68% 28-Mar-13 25-Dec-13
2.2.1.1 STRUCTURAL 30.00% Prep/ Submit Accept/ Approve 45.04% 54.07% -9.03% 28-Mar-13 16-Sep-13
C1000 PREPARATION/ SUBMISSION/ APPROVAL SHOP DRAWINGS FOR STRUCTURAL 100.00% 249 80.00% 238 20% 45.04% 54.07% -9.03% 28-Mar-13 16-Sep-13
2.2.1.2 PIPING/PLUMBING MECHANICAL 30.00% Prep/ Submit Accept/ Approve 27.69% 18.57% 9.12% 3-Jun-13 21-Oct-13
C1010 PREPARATION/ SUBMISSION/ APPROVAL SHOP DRAWINGS FOR PIPING/ PLUMBING MECHANICAL
100.00% 529 80.00% 99 20% 27.69% 18.57% 9.12% 3-Jun-13 21-Oct-13
2.2.1.3 ELECTRICAL 20.00% Prep/ Submit Accept/ Approve 29.47% 6.20% 23.27% 21-Jun-13 28-Oct-13
C1020 PREPARATION/ SUBMISSION/ APPROVAL SHOP DRAWINGS FOR ELECTRICAL 100.00% 53 80.00% 9 20% 29.47% 6.20% 23.27% 21-Jun-13 28-Oct-13
2.2.1.4 INSTRUMENT 10.00% Prep/ Submit Accept/ Approve 31.60% 1.56% 30.04% 27-Jun-13 2-Nov-13
C1030 PREPARATION/ SUBMISSION/ APPROVAL SHOP DRAWINGS FOR INSTRUMENT 100.00% 49 80.00% 41 20% 31.60% 1.56% 30.04% 27-Jun-13 2-Nov-13
2.2.1.5 HVAC/DUCTING 5.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 18-Sep-13 19-Dec-13
C1040 PREPARATION/ SUBMISSION/ APPROVAL SHOP DRAWINGS FOR HVAC/ DUCTING 100.00% 80.00% 20% 0.00% 0.00% 0.00% 18-Sep-13 19-Dec-13
2.2.1.6 ARCHITECTURAL 5.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 18-Sep-13 25-Dec-13
C1050 PREPARATION/ SUBMISSION/ APPROVAL SHOP DRAWINGS FOR ARCHITECTUAL 100.00% 80.00% 20% 0.00% 0.00% 0.00% 18-Sep-13 25-Dec-13
2.2.2 MATERIAL TAKE-OFF (MTO) 13.00% Prep/ Submit Accept/ Approve 90.00% 90.00% 0.00% 28-Mar-13 7-Sep-13
2.2.2.1 STRUCTURAL 25.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 28-Mar-13 10-Apr-13
C1060 PREPARATION/ SUBMISSION/ APPROVAL MTO FOR STRUTURAL 100.00% 6 80.00% 6 20% 100.00% 100.00% 0.00% 28-Mar-13 10-Apr-13
2.2.2.2 PIPING/PLUMBING 20.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 28-Mar-13 10-Apr-13
C1070 PREPARATION/ SUBMISSION/ APPROVAL MTO FOR PIPING/ PLUMBING 100.00% 12 80.00% 12 20% 100.00% 100.00% 0.00% 28-Mar-13 10-Apr-13
2.2.2.3 MECHANICAL 10.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 20-Apr-13 6-May-13
C1080 PREPARATION/ SUBMISSION/ APPROVAL MTO FOR MECHANICAL 100.00% 12 80.00% 12 20% 100.00% 100.00% 0.00% 20-Apr-13 6-May-13
3.2.2.4 ELECTRICAL 15.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 22-Apr-13 7-May-13
C1090 PREPARATION/ SUBMISSION/ APPROVAL MTO FOR ELECTRICAL 100.00% 14 80.00% 14 20% 100.00% 100.00% 0.00% 22-Apr-13 7-May-13
3.2.2.5 INSTRUMENT 10.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 6-May-13 18-May-13
C1100 PREPARATION/ SUBMISSION/ APPROVAL MTO FOR INSTRUMENT 100.00% 13 80.00% 13 20% 100.00% 100.00% 0.00% 6-May-13 18-May-13
3.2.2.6 ARCHITECTURAL 5.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 23-May-13 5-Jun-13
C1110 PREPARATION/ SUBMISSION/ APPROVAL MTO FOR ARCHITECTUAL 100.00% 2 80.00% 2 20% 100.00% 100.00% 0.00% 23-May-13 5-Jun-13
3.2.2.7 HVAC/DUCTING 5.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 23-May-13 5-Jun-13
C1120 PREPARATION/ SUBMISSION/ APPROVAL MTO FOR HVAC/ DUCTING 100.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 23-May-13 5-Jun-13
3.2.2.8 OTHER MATERIAL 10.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 17-Jul-13 7-Sep-13
C1130 PREPARATION/ SUBMISSION/ APPROVAL MTO FOR PAINT ...ECT 0.00% 80.00% 20% 0.00% 0.00% 0.00% 17-Jul-13 7-Sep-13
C1135 PREPARATION/ SUBMISSION/ APPROVAL MTO FOR PAINTTOP UP MATERIAL 100.00% 80.00% 20% 0.00% 0.00% 0.00% 17-Jul-13 7-Sep-13
2.2.3 PROCEDURES 4.00% Prep/ Submit Accept/ Approve 87.51% 26.98% 60.53% 18-Apr-13 18-Jan-14
C1140 PREPARATION/ SUBMISSION/ APPROVAL PROCEDURES 100.00% 57 80.00% 47 24% 87.51% 26.98% 60.53% 15-Apr-13 18-Jan-14
3 PROCURMENT 40.00% 51.98% 49.97% 2.01% 5-Sep-12 29-Jan-14
3.1 PCVL-SUPPLIED MATERIALS 19.00% Prep/ Submit Accept/ Approve 36.00% 36.00% 0.00% 17-Dec-12 29-Jan-14
3.1.1 STRUCTURAL STEEL (ETA) 36.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 17-Dec-12 15-Apr-13
D1000 DELIVERY ON SITE FIRST SHIPMENT(7-Jan-13) 40.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 17-Dec-12 18-Dec-12
D1005 DELIVERY ON SITE 2ND SHIPMENT(4-Feb-13) 40.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 24-Dec-12 26-Dec-12
D1007 DELIVERY ON SITE LAST SHIPMENT 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 15-Apr-13 15-Apr-13
3.1.2 MECHANICAL ITEMS/EQUIMENT (ETA) 30.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 15-Aug-13 29-Jan-14
3.1.2.1 MATERIAL HANDLING - PEDESTAL CRANE 24.11% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 23-Jan-14 23-Jan-14
D1010 DELIVERY ON SITE MATERIAL HANDLING - PEDESTAL CRANE BD-7301 (MAIN DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 23-Jan-14 23-Jan-14

1
3.1.2.2 CRUDE HEATER UNIT 26.59% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 7-Nov-13 7-Nov-13
D1020 DELIVERY ON SITE CRUDE HEATER UNIT A-1510 (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 7-Nov-13 7-Nov-13
3.1.2.3 CRUDE OIL TRANSFER PUMP 1.24% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 23-Jan-14 23-Jan-14
D1030 DELIVERY ON SITE CRUDE OIL TRANSFER PUMP (COTP) P-1310A/B (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 23-Jan-14 23-Jan-14
3.1.2.4 BOOSTER COMPRESSOR 4.08% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 29-Jan-14 29-Jan-14
D1040 DELIVERY ON SITE BOOSTER COMPRESSOR A-2410 (MAIN DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 29-Jan-14 29-Jan-14
3.1.2.5 GAS LIFT COMPRESSOR 25.84% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 29-Jan-14 29-Jan-14
D1050 DELIVERY ON SITE GAS LIFT COMPRESSOR A-0610 (MAIN DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 29-Jan-14 29-Jan-14
3.1.2.6 FUEL GAS SKID 10.93% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 26-Sep-13 26-Sep-13
D1060 DELIVERY ON SITE FUEL GAS SKID A-5800 (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 26-Sep-13 26-Sep-13
3.1.2.7 CHEMICAL INJECTION SKID 2.49% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 26-Sep-13 26-Sep-13
D1070 DELIVERY ON SITE CHEMICAL INJECTION PUMP SKID A-6800 (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 26-Sep-13 26-Sep-13
3.1.2.8 LAUNCHER 0.99% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 15-Aug-13 15-Aug-13
D1090 DELIVERY ON SITE LAUNCHER L-1330 (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 15-Aug-13 15-Aug-13
3.1.2.9 CLOSE DRAIN VESSEL 3.73% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 18-Oct-13 18-Oct-13
D1100 DELIVERY ON SITE CLOSE DRAIN VESSEL V-6400 100.00% 80.00% 20% 0.00% 0.00% 0.00% 18-Oct-13 18-Oct-13
3.1.3 ELECTRICAL ITEMS/EQUIMENT (ETA) 19.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 8-Nov-13 3-Jan-14
3.1.3.1 DIESEL ENGINE GENERATOR (DEG) 36.99% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 8-Nov-13 8-Nov-13
D1110 DELIVERY ON SITE DIESEL ENGINE GENERATOR (DEG) A-7740 (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 8-Nov-13 8-Nov-13
3.1.3.2 GAS ENGINE GENERATOR A-7700 63.01% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 3-Jan-14 3-Jan-14
D1120 DELIVERY ON SITE GAS ENGINE GENERATOR A-7700 (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 3-Jan-14 3-Jan-14
3.1.4 INSTRUMENT/ TELECOMMUNICATION ITEMS/EQUIMENT (ETA) 15.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 2-Aug-13 29-Nov-13
3.1.4.1 MULTIPHASE FLOW METER 11.18% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 20-Sep-13 20-Sep-13
D1130 DELIVERY ON SITE MULTIPHASE FLOW METER A-1210 (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 20-Sep-13 20-Sep-13
3.1.4.2 PMCS/SIS/FIELD TRANSMITTER/ FGS 6.21% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 6-Sep-13 6-Sep-13
D1140 DELIVERY ON SITE PMCS/SIS/FIELD TRANSMITTER/ FGS 100.00% 80.00% 20% 0.00% 0.00% 0.00% 6-Sep-13 6-Sep-13
3.1.4.3 WELL HEAD CONTROL PANEL 17.39% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 2-Aug-13 2-Aug-13
D1150 DELIVERY ON SITE WELL HEAD CONTROL PANEL WHCP-0100 (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 2-Aug-13 2-Aug-13
3.1.4.4 ACTUATED BALL VALVES 31.06% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 29-Nov-13 29-Nov-13
D1160 DELIVERY ON SITE ACTUATED BALL VALVES 100.00% 80.00% 20% 0.00% 0.00% 0.00% 29-Nov-13 29-Nov-13
3.1.4.5 CHOKE VAVLES 31.06% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 4-Oct-13 4-Oct-13
D1170 DELIVERY ON SITE CHOKE VAVLES 100.00% 80.00% 20% 0.00% 0.00% 0.00% 4-Oct-13 4-Oct-13
3.1.4.6 TELECOMUNICATION EQUIPMENT 3.11% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 13-Oct-13 13-Oct-13
D1180 DELIVERY ON SITE TELECOMUNICATION EQUIPMENT 100.00% 80.00% 20% 0.00% 0.00% 0.00% 13-Oct-13 13-Oct-13
3.2 PVCMS-SUPPLIED MATERIALS 81.00% Prep/ Submit Accept/ Approve 55.73% 53.25% 2.48% 5-Sep-12 3-Jan-14
3.2.1 STRUCTURAL STEEL (ROS) 18.00% Prep/ Submit Accept/ Approve 56.75% 62.00% -5.25% 5-Sep-12 4-Dec-13
3.2.1.1 ALUMINIUM HELIDECK 45.00% Prep/ Submit Accept/ Approve 44.00% 50.00% -6.00% 5-Sep-12 4-Dec-13
A5330 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A5410 PO ISSUE DATE 30.00% 1 80.00% 20% 80.00% 100.00% -20.00% 23-May-13 23-May-13
D1190 DELIVERY ON SITE (ALUMINIUM HELIDECK) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 29-Nov-13 2-Dec-13
D1195 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 3-Dec-13 4-Dec-13
3.2.1.2 STRUCTURE STEEL 20.00% Prep/ Submit Accept/ Approve 100.00% 84.00% 16.00% 5-Sep-12 3-Jul-13
A5450 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A5530 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 19-Mar-13 19-Mar-13
D1200 DELIVERY ON SITE (STRUCTURE STEEL) 30.00% 2 80.00% 2 20% 100.00% 100.00% 0.00% 17-Jun-13 20-Jun-13
D1205 MATERIAL ACCEPTANCE 20.00% 2 80.00% 2 20% 100.00% 20.00% 80.00% 28-Jun-13 3-Jul-13
3.2.1.3 MISCELLANEOUS 11.00% Prep/ Submit Accept/ Approve 75.00% 100.00% -25.00% 10-Sep-12 6-Jun-13
A5570 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 10-Sep-12 10-Sep-12
A5650 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 13-Mar-13 13-Mar-13
D1210 DELIVERY ON SITE (MISCELANCENEOUS) 30.00% 1 80.00% 1 20% 50.00% 100.00% -50.00% 3-Jun-13 4-Jun-13
D1215 MATERIAL ACCEPTANCE 20.00% 1 80.00% 1 20% 50.00% 100.00% -50.00% 5-Jun-13 6-Jun-13
3.2.1.4 GRATING 7.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 7-Sep-12 13-Sep-13
A5690 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 7-Sep-12 7-Sep-12
A5770 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 19-Mar-13 19-Mar-13
D1220 DELIVERY ON SITE (GRATING) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 10-Sep-13 11-Sep-13
D1225 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 12-Sep-13 13-Sep-13
3.2.1.5 M CLIP (INCL. MATERIAL) 6.00% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 27-Sep-12 11-Jun-13
A5810 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 27-Sep-12 27-Sep-12
A5890 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 12-Apr-13 12-Apr-13
A5915 DELIVERY ON SITE (M CLIP) 30.00% 80.00% 20% 0.00% 100.00% -100.00% 6-Jun-13 7-Jun-13
A5917 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 100.00% -100.00% 10-Jun-13 11-Jun-13
3.2.1.6 FIRE BLAST WALL 11.00% Prep/ Submit Accept/ Approve 20.00% 20.00% 0.00% 11-Apr-13 29-Aug-13

2
A5930 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 11-Apr-13 11-Apr-13
A6010 PO ISSUE DATE 30.00% 80.00% 20% 0.00% 0.00% 0.00% 3-Jul-13 3-Jul-13
D1230 DELIVERY ON SITE (FIRE BLAST WALL) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 26-Aug-13 27-Aug-13
D1235 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 28-Aug-13 29-Aug-13
3.2.2 ARCHITECTURAL (ROS) 3.00% Prep/ Submit Accept/ Approve 47.00% 50.00% -3.00% 5-Sep-12 25-Oct-13
3.2.2.1 FIRE RATED DOORS 50.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 6-Sep-12 25-Oct-13
A6050 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 6-Sep-12 6-Sep-12
A6130 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 23-May-13 23-May-13
D1800 DELIVERY ON SITE (FIRE RATED DOORS) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 21-Oct-13 23-Oct-13
D1805 MANUFACTURE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 23-Oct-13 25-Oct-13
3.2.2.2 TEMPORARY SHELTER AND BATHROOM 50.00% Prep/ Submit Accept/ Approve 44.00% 50.00% -6.00% 5-Sep-12 6-Sep-13
A6530 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A6610 PO ISSUE DATE 30.00% 1 80.00% 20% 80.00% 100.00% -20.00% 31-May-13 31-May-13
D1820 DELIVERY ON SITE (TEMPORARY SHELTER) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 3-Sep-13 4-Sep-13
D1825 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 5-Sep-13 6-Sep-13
3.2.3 PIPING (ROS) 25.00% Prep/ Submit Accept/ Approve 58.50% 57.23% 1.27% 13-Sep-12 27-Nov-13
3.2.3.1 PIPING BULKS 30.00% Prep/ Submit Accept/ Approve 75.00% 70.78% 4.22% 14-Sep-12 11-Sep-13
A4010 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 78.90% 21.10% 14-Sep-12 14-Sep-13
A4090 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 18-Mar-13 18-Mar-13
D1250 DELIVERY ON SITE 1st SHIPMENT (PIPING BULKS) 15.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 17-Jun-13 18-Jun-13
D1252 DELIVERY ON SITE 2nd SHIPMENT (PIPING BULKS) 15.00% 80.00% 20% 0.00% 0.00% 0.00% 5-Sep-13 7-Sep-13
D1255 MATERIAL ACCEPTANCE 1st SHIPMENT 10.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 19-Jun-13 20-Jun-13
D1257 MATERIAL ACCEPTANCE 2nd SHIPMENT 10.00% 80.00% 20% 0.00% 0.00% 0.00% 9-Sep-13 11-Sep-13
3.2.3.2 MANUAL VALVES 25.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 14-Sep-12 27-Nov-13
A4130 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 14-Sep-12 14-Sep-12
A4210 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 12-Mar-13 12-Mar-13
D1260 DELIVERY ON SITE (MANUAL VALVES) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 22-Nov-13 25-Nov-13
D1265 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 26-Nov-13 27-Nov-13
3.2.3.3 ACCESS FITTINGS (SAMPLING CONNECTION, CHEMICAL INJECTION, CORROSION COUPON) 5.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 13-Sep-12 29-Aug-13
A4250 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 13-Sep-12 13-Sep-12
A4330 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 14-Mar-13 14-Mar-13
D1270 DELIVERY ON SITE (ACCESS FITTINGS (SAMPLING CONNECTION, CHEMICAL INJECTION, CORROSION COUPON)
30.00% 80.00% 20% 0.00% 0.00% 0.00% 26-Aug-13 27-Aug-13
D1275 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 27-Aug-13 29-Aug-13
3.2.3.4 ADDITIONAL ITEMS FOR SAMPLING CONNECTION 5.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 4-Jan-13 3-Sep-13
A11170 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 4-Jan-13 4-Jan-13
A11180 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 7-May-13 7-May-13
A11185 DELIVERY ON SITE (ADDITIONAL ITEMS FOR SAMPLING CONNECTION) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 28-Aug-13 29-Aug-13
A11190 MATERIAL ACCEPTANCE (ADDITIONAL ITEMS FOR SAMPLING CONNECTION) 20.00% 80.00% 20% 0.00% 0.00% 0.00% 30-Aug-13 3-Sep-13
3.2.3.5 HOSES AND COUPLINGS 5.00% Prep/ Submit Accept/ Approve 20.00% 20.00% 0.00% 14-Sep-12 5-Nov-13
A4370 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 14-Sep-12 14-Sep-12
A4450 PO ISSUE DATE 30.00% 80.00% 20% 0.00% 0.00% 0.00% 19-Jul-13 19-Jul-13
D1280 DELIVERY ON SITE (HOSES AND COUPLINGS) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 31-Oct-13 1-Nov-13
D1285 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 4-Nov-13 5-Nov-13
3.2.3.6 BUG SCREEN 5.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 19-Sep-12 2-Aug-13
A4490 RFP TO VENDOR 20.00% 1.0 80.00% 1 20% 100.00% 100.00% 0.00% 19-Sep-12 19-Sep-12
A4570 PO ISSUE DATE 30.00% 1.0 80.00% 1 20% 100.00% 100.00% 0.00% 12-Mar-13 12-Mar-13
D1290 DELIVERY ON SITE (BUG SCREEN) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 30-Jul-13 30-Jul-13
D1295 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 1-Aug-13 2-Aug-13
3.2.3.7 STRAINER 5.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 19-Sep-12 6-Sep-13
A4610 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 19-Sep-12 19-Sep-12
A4690 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 3-May-13 3-May-13
D1300 DELIVERY ON SITE (STRAINER) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 3-Sep-13 4-Sep-13
D1305 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 5-Sep-13 6-Sep-13
3.2.3.8 CONTINUOUS DRAINERS 5.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 14-Sep-12 29-Aug-13
A4730 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 14-Sep-12 14-Sep-12
A4810 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 24-May-13 24-May-13
D1310 DELIVERY ON SITE (CONTINUOUS DRAINERS) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 26-Aug-13 27-Aug-13
D1315 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 28-Aug-13 29-Aug-13
3.2.3.10 SIGHT GLASS 5.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 17-Sep-12 20-Sep-13
A4970 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 17-Sep-12 17-Sep-12
A5050 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 2-Apr-13 2-Apr-13
D1340 DELIVERY ON SITE (SIGN GLASS) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 17-Sep-13 18-Sep-13

3
A5170 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 10-May-13 10-May-13
D1350 DELIVERY ON SITE (FLAME ARESTOR) 30.00% 80.00% 20% 0.00% 100.00% -100.00% 26-Aug-13 27-Aug-13
D1355 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 100.00% -100.00% 28-Aug-13 29-Aug-13
3.2.3.12 PIPING SUPPORT 5.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 18-Sep-12 4-Jun-13
A5210 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 18-Sep-12 18-Sep-12
A5290 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 22-Feb-13 22-Feb-13
A5310 DELIVERY ON SITE (PIPING SUPPORT) 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 30-May-13 31-May-13
A5315 MATERIAL ACCEPTANCE 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 3-Jun-13 4-Jun-13
3.2.4 MECHANICAL (ROS) 20.00% Prep/ Submit Accept/ Approve 47.62% 100.00% -52.38% 5-Sep-12 3-Jan-14
3.2.4.1 GAS OPERATED PUMP 8.32% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 5-Sep-12 26-Sep-13
A7010 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A7090 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 15-Apr-13 15-Apr-13
D1360 DELIVERY ON SITE (PORTABLE CHEMICAL TRANSFER PUMP P-6835) 15.00% 80% 20% 0.00% 100.00% -100.00% 23-Sep-13 24-Sep-13
D1370 DELIVERY ON SITE (OPEN DRAIN PUMP P-6510) 15.00% 80% 20% 0.00% 100.00% -100.00% 23-Sep-13 24-Sep-13
D1375 MATERIAL ACCEPTANCE 20.00% 80% 20% 0.00% 100.00% -100.00% 25-Sep-13 26-Sep-13
3.2.4.2 RECIPROCATING PUMPS 7.71% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 5-Sep-12 3-Jan-14
A7130 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A7210 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 15-May-13 15-May-13
D1380 DELIVERY ON SITE (SCSSV EQUALIZATION INJECTION PUMP P-6720) 15.00% 80% 20% 0.00% 100.00% -100.00% 30-Dec-13 31-Dec-13
D1390 DELIVERY ON SITE (PORTABLE PIPELINE DIESEL INJECTION PUMP P-6730) 15.00% 80% 20% 0.00% 100.00% -100.00% 30-Dec-13 31-Dec-13
D1395 MATERIAL ACCEPTANCE ( PUMP P-6720/ PUMP P-6730) 20.00% 80% 20% 0.00% 100.00% -100.00% 2-Jan-14 3-Jan-14
3.2.4.3 CENTRIFUGAL PUMP (MISC) 7.71% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 5-Sep-12 3-Jan-14
A7250 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A7330 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 15-May-13 15-May-13
D1400 DELIVERY ON SITE (DIESEL TRANSFER PUMP P-6710) 15.00% 80% 20% 0.00% 100.00% -100.00% 30-Dec-13 31-Dec-13
D1410 DELIVERY ON SITE (WASH WATER PUMP P-5110) 15.00% 80% 20% 0.00% 100.00% -100.00% 30-Dec-13 31-Dec-13
D1415 MATERIAL ACCEPTANCE (PUMP P-6710/ PUMP P-5110) 20.00% 80% 20% 0.00% 100.00% -100.00% 2-Jan-14 3-Jan-14
3.2.4.4 TOTE TANKS 6.53% Prep/ Submit Accept/ Approve 44.00% 100.00% -56.00% 5-Sep-12 13-Oct-13
A7370 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A7450 PO ISSUE DATE 30.00% 1 80% 20% 80.00% 100.00% -20.00% 4-Jul-13 4-Jul-13
D1420 DELIVERY ON SITE (PORTABLE CHEMICAL TOTE TANK) 10.00% 80% 20% 0.00% 100.00% -100.00% 8-Nov-13 8-Nov-13
D1430 DELIVERY ON SITE (WAX DISSOLVER STANDARD TOTE TANK T-6850) 10.00% 80% 20% 0.00% 100.00% -100.00% 8-Nov-13 8-Nov-13
D1440 DELIVERY ON SITE (GENERAL PURPOSE TOTE TANK T-5300) 10.00% 80% 20% 0.00% 100.00% -100.00% 8-Nov-13 8-Nov-13
D1445 MATERIAL ACCEPTANCE (TOTE TANKS) 20.00% 80% 20% 0.00% 100.00% -100.00% 12-Nov-13 13-Nov-13
3.2.4.5 RECTANGULAR TANKS 8.27% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 5-Sep-12 29-Oct-13
A7490 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A7570 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 14-May-13 14-May-13
D1450 DELIVERY ON SITE (WASH WATER STORAGE TANK T-5100A/B) 10.00% 80% 20% 0.00% 100.00% -100.00% 24-Oct-13 25-Oct-13
D1460 DELIVERY ON SITE (PORTABLE WATER TANK T-5200) 10.00% 80% 20% 0.00% 100.00% -100.00% 21-Oct-13 22-Oct-13
D1470 DELIVERY ON SITE (OPEN DRAIN TANK T-6500) 5.00% 80% 20% 0.00% 100.00% -100.00% 21-Oct-13 22-Oct-13
D1480 DELIVERY ON SITE (OPEN DRAIN HEATER E-6520) 5.00% 80% 20% 0.00% 100.00% -100.00% 21-Oct-13 22-Oct-13
D1485 MATERIAL ACCEPTANCE (RECTANGULAR TANKS) 20.00% 80% 20% 0.00% 100.00% -100.00% 28-Oct-13 29-Oct-13
3.2.4.6 CLOSED DRAIN TRANSFER PUMP 9.76% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 5-Sep-12 5-Dec-13
A7610 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A7690 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 8-Apr-13 8-Apr-13
D1490 DELIVERY ON SITE (CLOSED DRAIN TRANSFER PUMP P-6410A/B) 30.00% 80% 20% 0.00% 100.00% -100.00% 2-Dec-13 3-Dec-13
D1495 MATERIAL ACCEPTANCE (CLOSED DRAIN TRANSFER PUMP P-6410A/B) 20.00% 80% 20% 0.00% 100.00% -100.00% 4-Dec-13 5-Dec-13
3.2.4.7 SEPATATOR SKID 12.28% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 5-Sep-12 5-Dec-13
A7730 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A7810 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 8-Apr-13 8-Apr-13
D1500 DELIVERY ON SITE (HP SEPARATOR SKID A-1020) 15.00% 80% 20% 0.00% 100.00% -100.00% 2-Dec-13 3-Dec-13
D1510 DELIVERY ON SITE (LP SEPARATOR SKID A-1010) 15.00% 80% 20% 0.00% 100.00% -100.00% 2-Dec-13 3-Dec-13
D1515 MATERIAL ACCEPTANCE (HP SEPARATOR SKID A-1020/ A-1010) 20.00% 80% 20% 0.00% 100.00% -100.00% 4-Dec-13 5-Dec-13
3.2.4.8 NITROGEN BOTTLES 7.91% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 6-Sep-12 30-Sep-13
A7850 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 6-Sep-12 6-Sep-12
A7930 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 25-Apr-13 25-Apr-13
D1520 DELIVERY ON SITE (NITROGEN BOTTLES A-5900) 30.00% 80% 20% 0.00% 100.00% -100.00% 25-Sep-13 26-Sep-13
D1525 MATERIAL ACCEPTANCE (NITROGEN BOTTLES A-5900) 20.00% 80% 20% 0.00% 100.00% -100.00% 27-Sep-13 30-Sep-13
3.2.4.9 CO2 VENT SNUFFING 8.84% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 6-Sep-12 1-Oct-13
A7970 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 6-Sep-12 6-Sep-12
A8050 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 8-Apr-13 9-Apr-13
D1530 DELIVERY ON SITE (CO2 VENT SNUFFING A-8600) 30.00% 80% 20% 0.00% 100.00% -100.00% 26-Sep-13 27-Sep-13
D1535 MATERIAL ACCEPTANCE (CO2 VENT SNUFFING A-8600) 20.00% 80% 20% 0.00% 100.00% -100.00% 30-Sep-13 1-Oct-13

4
3.2.4.10 HANDLING & LIFTING EQUIPMENT 6.17% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 6-Sep-12 29-Oct-13
A8090 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 6-Sep-12 6-Sep-12
A8170 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 29-Apr-13 29-Apr-13
D1540 DELIVERY ON SITE (HANDLING & LIFTING EQUIPMENT) 30.00% 80% 20% 0.00% 100.00% -100.00% 2-Jan-14 3-Jan-14
D1545 MATERIAL ACCEPTANCE (HANDLING & LIFTING EQUIPMENT) 20.00% 80% 20% 0.00% 100.00% -100.00% 4-Jan-14 5-Jan-14
3.2.4.11 SAFETY & FIRE FIGHTING, LIFE SAVING EQUIPMENT 6.63% Prep/ Submit Accept/ Approve 20.00% 100.00% -80.00% 11-Mar-13 24-Oct-13
A8210 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Mar-13 11-Mar-13
A8290 PO ISSUE DATE 30.00% 80% 20% 0.00% 100.00% -100.00% 9-Jul-13 9-Jul-13
D1550 DELIVERY ON SITE (SAFETY & FIRE FIGHTING, LIFE SAVING EQUIPMENT) 30.00% 80% 20% 0.00% 100.00% -100.00% 14-Nov-13 15-Nov-13
D1555 MATERIAL ACCEPTANCE (SAFETY & FIRE FIGHTING, LIFE SAVING EQUIPMENT) 20.00% 80% 20% 0.00% 100.00% -100.00% 18-Nov-13 19-Nov-13
3.2.4.12 AIR CONDITIONING & VENTILATION SYSTEM 9.87% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 7-Sep-12 6-Nov-13
A8330 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 7-Sep-12 7-Sep-12
A8410 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 26-Apr-13 26-Apr-13
D1560 DELIVERY ON SITE (AIR CONDITIONING & VENTILATION SYSTEM) 30.00% 80% 20% 0.00% 100.00% -100.00% 1-Nov-13 4-Nov-13
D1565 MATERIAL ACCEPTANCE (AIR CONDITIONING & VENTILATION SYSTEM) 20.00% 80% 20% 0.00% 100.00% -100.00% 5-Nov-13 6-Nov-13
3.2.5 ELECTRICAL (ROS) 19.00% Prep/ Submit Accept/ Approve 65.57% 100.00% -34.43% 5-Sep-12 5-Dec-13
3.4.5.1 JUCTION BOX AND RCU 9.50% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 10-Sep-12 19-Sep-13
A8450 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 10-Sep-12 10-Sep-12
A8530 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 8-Apr-13 8-Apr-13
D1570 DELIVERY ON SITE (JUCTION BOX AND RCU) 30.00% 80% 20% 0.00% 100.00% -100.00% 16-Sep-13 17-Sep-13
D1575 MATERIAL ACCEPTANCE (JUCTION BOX AND RCU) 20.00% 80% 20% 0.00% 100.00% -100.00% 18-Sep-13 19-Sep-13
3.4.5.2 CABLE GLAND 5.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 10-Sep-12 19-Sep-13
A8560 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 10-Sep-12 10-Sep-12
A8640 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 30-May-13 30-May-13
D1580 DELIVERY ON SITE (CABLE GLAND) 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 16-Sep-13 17-Sep-13
D1585 MATERIAL ACCEPTANCE (CABLE GLAND) 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 18-Sep-13 19-Sep-13
3.4.5.3 CABLES E&I 6.00% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 5-Sep-12 25-Sep-13
A1130 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A1210 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 8-May-13 8-May-13
D1590 DELIVERY ON SITE (CABLE E&I) 30.00% 80% 20% 0.00% 100.00% -100.00% 20-Sep-13 23-Sep-13
D1595 MATERIAL ACCEPTANCE (CABLE E&I) 20.00% 80% 20% 0.00% 100.00% -100.00% 24-Sep-13 25-Sep-13
3.4.5.4 CABLE TRAY AND LADDER 6.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 10-Sep-12 6/31/2013
A1250 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 10-Sep-12 10-Sep-12
A1330 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Mar-13 11-Mar-13
A1335 DELIVERY ON SITE (CABLE TRAY AND LADDER) 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 26-Jul-13 29-Jul-13
D1600 MATERIAL ACCEPTANCE (CABLE TRAY AND LADDER) 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 30-Jul-13 31-Jul-13
3.4.5.5 TUBING AND FITTING 6.00% Prep/ Submit Accept/ Approve 75.00% 100.00% -25.00% 11-Sep-12 6-Sep-13
A1370 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Sep-12 11-Sep-12
A1450 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 24-Apr-13 24-Apr-13
A1460 DELIVERY ON SITE (TUBING AND FITTING) 30.00% 2 80% 2 20% 50.00% 100.00% -50.00% 3-Sep-13 4-Sep-13
D1610 MATERIAL ACCEPTANCE (TUBING AND FITTING) 20.00% 2 80% 2 20% 50.00% 100.00% -50.00% 5-Sep-13 6-Sep-13
3.4.5.6 EARTHING BOSS 5.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 11-Sep-12 27-Jun-13
A1490 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Sep-12 11-Sep-12
A1570 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 27-Feb-13 27-Feb-13
A1580 DELIVERY ON SITE (EARTHING BOSS) 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 24-Jun-13 25-Jun-13
D1620 MATERIAL ACCEPTANCE (EARTHING BOSS) 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 26-Jun-13 27-Jun-13
3.4.5.7 SOCKET AND OUTLET 5.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 11-Sep-12 6-Sep-13
A1610 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Sep-12 11-Sep-12
A1690 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 14-Jun-13 14-Jun-13
A1700 DELIVERY ON SITE (SOCKET AND OUTLET) 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 3-Sep-13 4-Sep-13
D1630 MATERIAL ACCEPTANCE (SOCKET AND OUTLET) 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-13 6-Sep-13
3.4.5.8 HEAT TRACING 6.00% Prep/ Submit Accept/ Approve 44.00% 100.00% -56.00% 10-Sep-12 28-Oct-13
A1730 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 10-Sep-12 10-Sep-12
A1810 PO ISSUE DATE 30.00% 1 80% 20% 80.00% 100.00% -20.00% 17-Jun-13 17-Jun-13
A1820 DELIVERY ON SITE (HEAT TRACING) 30.00% 80% 20% 0.00% 100.00% -100.00% 23-Oct-13 24-Oct-13
D1640 MATERIAL ACCEPTANCE (HEAT TRACING) 20.00% 80% 20% 0.00% 100.00% -100.00% 25-Oct-13 28-Oct-13
3.4.5.9 LIGHTING & FIXTURES 6.00% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 10-Sep-12 3-Oct-13
A1850 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 10-Sep-12 10-Sep-12
A1930 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 23-May-13 23-May-13
A1940 DELIVERY ON SITE (LIGHTING FITTING) 30.00% 80% 20% 0.00% 100.00% -100.00% 4-Nov-13 5-Nov-13
D1650 MATERIAL ACCEPTANCE (LIGHTING FITTING) 20.00% 80% 20% 0.00% 100.00% -100.00% 6-Nov-13 7-Nov-13
3.4.5.10 MULTI CABLE TRANSIT 5.00% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 12-Sep-12 4-Sep-13
A1970 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 12-Sep-12 12-Sep-12

5
A1930 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 23-May-13 23-May-13
A1940 DELIVERY ON SITE (LIGHTING FITTING) 30.00% 80% 20% 0.00% 0.00% 0.00% 4-Nov-13 5-Nov-13
D1650 MATERIAL ACCEPTANCE (LIGHTING FITTING) 20.00% 80% 20% 0.00% 0.00% 0.00% 6-Nov-13 7-Nov-13
3.4.5.10 MULTI CABLE TRANSIT 5.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 12-Sep-12 4-Sep-13
A1970 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 12-Sep-12 12-Sep-12
A2050 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 22-May-13 22-May-13
A2060 DELIVERY ON SITE (MULTI CABLE TRANSIT) 30.00% 80% 20% 0.00% 0.00% 0.00% 29-Aug-13 30-Aug-13
D1660 MATERIAL ACCEPTANCE (MULTI CABLE TRANSIT) 20.00% 80% 20% 0.00% 0.00% 0.00% 3-Sep-13 4-Sep-13
3.4.5.11 MISCELLANEOUS 5.00% Prep/ Submit Accept/ Approve 83.33% 50.00% 33.33% 14-Sep-12 20-Aug-13
A2090 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 14-Sep-12 14-Sep-12
A2170 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 9-Apr-13 9-Apr-13
A2180 DELIVERY ON SITE (MISCELLANOUES) 30.00% 2 80% 2 20% 66.67% 0.00% 66.67% 7-Aug-13 28-Aug-13
D1670 MATERIAL ACCEPTANCE (MISCELLANOUES) 20.00% 2 80% 2 20% 66.67% 0.00% 66.67% 29-Aug-13 30-Aug-13
3.4.5.12 CONTROL VALVES (PCV, LCV, FCV, ADV) 9.50% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 6-Sep-12 21-Nov-13
A2210 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 6-Sep-12 6-Sep-12
A2290 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 25-Mar-13 25-Mar-13
A2300 DELIVERY ON SITE (CONTROL VALVES (PCV, LCV, FCV, ADV)) 30.00% 80% 20% 0.00% 0.00% 0.00% 2-Dec-13 3-Dec-13
D1680 MATERIAL ACCEPTANCE (CONTROL VALVES (PCV, LCV, FCV, ADV)) 20.00% 80% 20% 0.00% 0.00% 0.00% 4-Dec-13 5-Dec-13
3.4.5.13 NAVIGATION AIDS 5.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 10-Sep-12 22-Oct-13
A2570 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 10-Sep-12 10-Sep-12
A2650 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 4-Apr-13 4-Apr-13
A2660 DELIVERY ON SITE (NAVIGATION AIDS) 30.00% 80% 20% 0.00% 0.00% 0.00% 17-Oct-13 18-Oct-13
D1690 MATERIAL ACCEPTANCE (NAVIGATION AIDS) 20.00% 80% 20% 0.00% 0.00% 0.00% 21-Oct-13 22-Oct-13
3.4.5.14 PUSH BUTTON 5.00% Prep/ Submit Accept/ Approve 100.00% 50.00% 50.00% 14-Sep-12 9-Sep-13
A2930 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 14-Sep-12 14-Sep-12
A3010 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 17-Jun-13 17-Jun-13
A3020 DELIVERY ON SITE (PUSH BUTTON) 30.00% 1 80% 1 20% 100.00% 0.00% 100.00% 4-Sep-13 5-Sep-13
D1700 MATERIAL ACCEPTANCE (PUSH BUTTON) 20.00% 1 80% 1 20% 100.00% 0.00% 100.00% 6-Sep-13 9-Sep-13
3.2.6.10 400V AC LV SWICH BOARD 4.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 17-Sep-12 15-Oct-13
A3650 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 17-Sep-12 17-Sep-12
A3730 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 23-Apr-13 23-Apr-13
A3740 DELIVERY ON SITE (400V AC LV SWICH BOARD) 30.00% 80% 20% 0.00% 0.00% 0.00% 10-Oct-13 11-Oct-13
A3750 MATERIAL ACCEPTANCE (400V AC LV SWICH BOARD) 20.00% 80% 20% 0.00% 0.00% 0.00% 14-Oct-13 15-Oct-13
3.2.6.11 UPS 4.00% Prep/ Submit Accept/ Approve 44.00% 50.00% -6.00% 27-Sep-12 5-Dec-13
A3770 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 27-Sep-12 27-Sep-12
A3850 PO ISSUE DATE 30.00% 1 80% 20% 80.00% 100.00% -20.00% 13-May-13 13-May-13
A3860 DELIVERY ON SITE (UPS) 30.00% 80% 20% 0.00% 0.00% 0.00% 2-Dec-13 3-Dec-13
A3870 MATERIAL ACCEPTACE (UPS) 20.00% 80% 20% 0.00% 0.00% 0.00% 4-Dec-13 5-Dec-13
3.2.6.12 DISTRIBUTION BOARD 4.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 28-Sep-12 25-Oct-13
A3890 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 28-Sep-12 28-Sep-12
A3970 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 24-Apr-13 24-Apr-13
A3980 DELIVERY ON SITE (DISTRIBUTION BOARD) 30.00% 80% 20% 0.00% 0.00% 0.00% 22-Oct-13 23-Oct-13
A3990 MATERIAL ACCEPTANCE (DISTRIBUTION BOARD) 20.00% 80% 20% 0.00% 0.00% 0.00% 24-Oct-13 25-Oct-13
3.2.6.13 HELIDECK LIGHTING 4.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 21-Mar-13 11-Nov-13
A11120 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 21-Mar-13 21-Mar-13
A11130 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 3-Jun-13 3-Jun-13
A11140 DELIVERY ON SITE (HELIDECK LIGHTING) 30.00% 80% 20% 0.00% 0.00% 0.00% 6-Nov-13 7-Nov-13
A11150 MATERIAL ACCEPTANCE (HELIDECK LIGHTING) 20.00% 80% 20% 0.00% 0.00% 0.00% 8-Nov-13 11-Nov-13
3.2.6 INSTRUMENT (ROS) 15.00% 50.00% 47.30% 2.70% 10-Sep-12 3-Jan-14
3.2.6.1 TURBINE FLOWMETTER (GF AND LF) 28.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 12-Sep-12 4-Nov-13
A2330 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 12-Sep-12 12-Sep-12
A2410 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 23-May-13 23-May-13
A2420 DELIVERY ON SITE (TURBINE FLOW TRANSMITTER (GF AND LF)) 30.00% 80% 20% 0.00% 0.00% 0.00% 30-Oct-13 31-Oct-13
D1710 MATERIAL ACCEPTANCE (TURBINE FLOW TRANSMITTER (GF AND LF)) 20.00% 80% 20% 0.00% 0.00% 0.00% 1-Nov-13 4-Nov-13
3.2.6.2 FUSIBLE PLUG LOOP PANEL 9.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 11-Sep-12 3-Sep-13
A2450 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Sep-12 11-Sep-12
A2530 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 8-Mar-13 8-Mar-13
A2540 DELIVERY ON SITE (FUSIBLE PLUG LOOP PANEL) 30.00% 80% 20% 0.00% 0.00% 0.00% 28-Aug-13 29-Aug-13
D1720 MATERIAL ACCEPTANCE (FUSIBLE PLUG LOOP PANEL) 20.00% 80% 20% 0.00% 0.00% 0.00% 30-Aug-13 3-Sep-13
3.2.6.3 PIG SIGNALLER 9.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 10-Sep-12 3-Jan-14
A2690 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 10-Sep-12 10-Sep-12
A2770 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 22-Apr-13 22-Apr-13

6
A2780 DELIVERY ON SITE (PIG SIGNALLER) 30.00% 80% 20% 0.00% 0.00% 0.00% 30-Dec-13 31-Dec-13
D1730 MATERIAL ACCEPTANCE (PIG SIGNALLER) 20.00% 80% 20% 0.00% 0.00% 0.00% 2-Jan-14 3-Jan-14
3.2.6.4 SAFETY RELIEF VALVE 9.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 11-Sep-12 7-Nov-13
A2810 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Sep-12 11-Sep-12
A2890 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 18-Mar-13 18-Mar-13
A2900 DELIVERY ON SITE (SAFETY RELIEF VALVE) 30.00% 80% 20% 0.00% 0.00% 0.00% 4-Nov-13 5-Nov-13
D1740 MATERIAL ACCEPTANCE (SAFETY RELIEF VALVE) 20.00% 80% 20% 0.00% 0.00% 0.00% 6-Nov-13 7-Nov-13
3.2.6.5 RESTRICTION ORIFICES, ORIFICES PLATE AND FLANGES 9.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 14-Sep-12 11-Oct-13
A3050 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 14-Sep-12 14-Sep-12
A3130 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 24-May-13 24-May-13
A3140 DELIVERY ON SITE (RESTRICTION ORIFICES, ORIFICES PLATE AND FLANGES) 30.00% 80% 20% 0.00% 0.00% 0.00% 8-Oct-13 9-Oct-13
D1750 MATERIAL ACCEPTANCE (RESTRICTION ORIFICES, ORIFICES PLATE AND FLANGES) 20.00% 80% 20% 0.00% 0.00% 0.00% 10-Oct-13 11-Oct-13
3.2.6.6 SAND MONITORING 9.00% Prep/ Submit Accept/ Approve 50.00% 20.00% 30.00% 12-Sep-12 19-Sep-13
A3170 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 12-Sep-12 12-Sep-12
A3250 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 0.00% 100.00% 4-Jul-13 4-Jul-13
A3260 DELIVERY ON SITE (SAND MONITORING) 30.00% 80% 20% 0.00% 0.00% 0.00% 9-Oct-13 10-Oct-13
D1760 MATERIAL ACCEPTANCE (SAND MONITORING) 20.00% 80% 20% 0.00% 0.00% 0.00% 11-Oct-13 14-Oct-13
3.2.6.7 PRESSURE GAUGES 9.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 11-Sep-12 24-Oct-13
A3290 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Sep-12 11-Sep-12
A3370 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 3-Jun-13 3-Jun-13
A3380 DELIVERY ON SITE (PRESSURE GAUGES (PG, PDG, TG)) 30.00% 80% 20% 0.00% 0.00% 0.00% 21-Oct-13 22-Oct-13
D1780 MATERIAL ACCEPTANCE (PRESSURE GAUGES (PG, PDG, TG)) 20.00% 80% 20% 0.00% 0.00% 0.00% 23-Oct-13 24-Oct-13
3.2.6.8 PRESSURE REGULATOR VALVES 9.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 11-Sep-12 18-Oct-13
A3410 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Sep-12 11-Sep-12
A3490 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 9-May-13 9-May-13
A3500 DELIVERY ON SITE (PRESSURE REGULATOR VALVES) 30.00% 80% 20% 0.00% 0.00% 0.00% 15-Oct-13 16-Oct-13
A3510 MATERIAL ACCEPTANCE (PRESSURE REGULATOR VALVES) 20.00% 80% 20% 0.00% 0.00% 0.00% 17-Oct-13 18-Oct-13
3.2.6.9 LEVEL GAUGES 9.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 14-Sep-12 27-Oct-13
A3530 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 14-Sep-12 14-Sep-12
A3610 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 15-Mar-13 15-Mar-13
A3620 DELIVERY ON SITE (LEVEL GAUGES) 30.00% 80% 20% 0.00% 0.00% 0.00% 22-Oct-13 25-Oct-13
D1790 MATERIAL ACCEPTANCE (LEVEL GAUGES) 20.00% 80% 20% 0.00% 0.00% 0.00% 26-Oct-13 27-Oct-13
4 CONSTRUCTION 43.00% 20.55% 17.00% 3.55% 4-Jan-13 10-Mar-14
4.1 FRONT-END ACTIVITIES/ MOBILIZATION 20.00% 70.33% 65.52% 4.81% 4-Jan-13 8-Jan-14
4.1.1 MOBILIZATION OF PROJECT MANAGEMENT TEAM (PER APPROVED ORGANISATION CHART) 8.00%Prep/ Submit Accept 100.00% 100.00% 0.00% 19-Feb-13 26-Feb-13
B1000 MOBILISATION OF PROJECT MANAGEMENT TEAM 100.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 19-Feb-13 26-Feb-13
4.1.2 PROJECT PLANNING AND MONITORING FORMAT 3.00%Prep/ Submit Accept 95.00% 100.00% -5.00% 30-Mar-13 21-May-13
B1010 60 DAYS SCHEDULE 50.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 30-Mar-13 9-Apr-13
B1015 PLANING PACKAGE 50.00% 2 80.00% 1 20% 90.00% 100.00% -10.00% 10-Apr-13 21-May-13
4.1.3 YARD PREPARATIONS 15.00%Prep/ Submit Accept 100.00% 100.00% 0.00% 30-Jan-13 15-Mar-13
B1020 FABRICATION YARD PREPARATION 33.77% 1 80.00% 1 20% 100.00% 100.00% 0.00% 20-Feb-13 15-Mar-13
B1030 SITE OFFICE PREPARATION 19.38% 1 80.00% 1 20% 100.00% 100.00% 0.00% 6-Feb-13 15-Mar-13
B1040 BUILD UP MATERIAL AND EQUIPMENT STORAGE AND FENCE PREPARATION 19.38% 1 80.00% 1 20% 100.00% 100.00% 0.00% 30-Jan-13 1-Mar-13
B1050 WORKSHOP AND FACILITIES PREPARATION 27.47% 1 80.00% 1 20% 100.00% 100.00% 0.00% 8-Feb-13 12-Mar-13
4.1.4 CONCRETE FOUNDATION / TEMPORARY SUPPORT FABRICATION 52.00%COMPLETED ACCEPTED 66.00% 59.61% 6.39% 9-May-13 11-Oct-13
4.1.4.1 CONCRETE FOUNDATION/ TEMPORARY SUPPORTS AT FINAL POSITION FABRICATION 30.00% COMPLETED ACCEPTED 20.00% 0.00% 20.00% 6-Jul-13 21-Aug-13
4.1.4.1.1 TEMPORARY SUPPORTS AT FINAL POSITION FABRICATION 80.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 24-Jul-13 21-Aug-13
A8940 MARK/ CUT TEMPORARY SUPPORTS AT FINAL POSITION 15.00% 80.00% 20% 0.00% 0.00% 0.00% 24-Jul-13 3-Aug-13
A8950 FIT UP TEMPORARY SUPPORTS AT FINAL POSITION 40.00% 80.00% 20% 0.00% 0.00% 0.00% 26-Jul-13 12-Aug-13
A8960 WELDING TEMPORARY SUPPORTS AT FINAL POSITION 30.00% 80.00% 20% 0.00% 0.00% 0.00% 29-Jul-13 17-Aug-13
A8970 NDT TEMPORARY SUPPORTS AT FINAL POSITION 15.00% 80.00% 20% 0.00% 0.00% 0.00% 3-Aug-13 21-Aug-13
4.1.4.1.2 CONCRETE FOUNDATION SUPPORTS AT FINAL POSITION FABRICATION 20.00% COMPLETED ACCEPTED 100.00% 0.00% 100.00% 6-Jul-13 9-Aug-13
A8980 CONCRETE FOUNDATION SUPPORTS AT FINAL POSITION 100.00% 4 80.00% 4 20% 100.00% 0.00% 100.00% 6-Jul-13 9-Aug-13
4.1.4.2 CONCRETE FOUNDATION/ TEMPORARY SUPPORTS CELLAR DECK FABRICATION 30.00% COMPLETED ACCEPTED 100.00% 100.00% 0.00% 9-May-13 25-May-13
4.1.4.2.1 TEMPORARY SUPPORTS CELLAR DECK FABRICATION 80.00% COMPLETED ACCEPTED 100.00% 100.00% 0.00% 9-May-13 25-May-13
A8840 MARK/ CUT TEMPORARY SUPPORTS CELLAR DECK 15.00% 119 80.00% 119 20% 100.00% 100.00% 0.00% 9-May-13 18-May-13
A8850 FIT UP TEMPORARY SUPPORTS CELLAR DECK 40.00% 119 80.00% 119 20% 100.00% 100.00% 0.00% 11-May-13 21-May-13
A8860 WELDING TEMPORARY SUPPORTS CELLAR DECK 30.00% 119 80.00% 119 20% 100.00% 100.00% 0.00% 14-May-13 23-May-13
A8870 NDT TEMPORARY SUPPORTS CELLAR DECK 15.00% 119 80.00% 119 20% 100.00% 100.00% 0.00% 16-May-13 25-May-13
4.1.4.2.2 CONCRETE FOUNDATION SUPPORTS CELLAR DECK FABRICATION 20.00% COMPLETED ACCEPTED 100.00% 100.00% 0.00% 9-May-13 18-May-13
A8880 CONCRETE FOUNDATION SUPPORTS CELLAR DECK FABRICATION 100.00% 4 80.00% 4 20% 100.00% 100.00% 0.00% 9-May-13 18-May-13
4.1.4.3 CONCRETE FOUNDATION/ TEMPORARY SUPPORTS MAIN DECK FABRICATION 30.00% COMPLETED ACCEPTED 100.00% 75.55% 24.45% 10-Jun-13 9-Jul-13

7
4.1.4.3.1 TEMPORARY SUPPORTS MAIN DECK FABRICATION 80.00% COMPLETED ACCEPTED 100.00% 69.44% 30.56% 13-Jun-13 9-Jul-13
A8990 MARK/ CUT TEMPORARY SUPPORTS MAIN DECK 15.00% 122 80.00% 122 20% 100.00% 100.00% 0.00% 13-Jun-13 24-Jun-13
A9000 FIT UP TEMPORARY SUPPORTS MAIN DECK 40.00% 122 80.00% 122 20% 100.00% 82.35% 17.65% 15-Jun-13 2-Jul-13
A9010 WELDING TEMPORARY SUPPORTS MAIN DECK 30.00% 122 80.00% 122 20% 100.00% 55.00% 45.00% 18-Jun-13 8-Jul-13
A9020 NDT TEMPORARY SUPPORTS MAIN DECK 15.00% 122 80.00% 122 20% 100.00% 33.33% 66.67% 24-Jun-13 9-Jul-13
4.1.4.3.2 CONCRETE FOUNDATION SUPPORTS MAIN DECK FABRICATION 20.00% COMPLETED ACCEPTED 100.00% 100.00% 0.00% 10-Jun-13 26-Jun-13
A9030 CONCRETE FOUNDATION SUPPORTS MAIN DECK 100.00% 4 80.00% 4 20% 100.00% 100.00% 0.00% 10-Jun-13 26-Jun-13
4.1.4.4 TEMPORARY SUPPORTS VENT BOOM FABRICATION 10.00% COMPLETED ACCEPTED 0.00% 69.44% -69.44% 16-Sep-13 11-Oct-13
A9040 MARK/ CUT TEMPORARY SUPPORTS MAIN DECK 15.00% 80.00% 20% 0.00% 100.00% -100.00% 13-Jun-13 24-Jun-13
A9050 FIT UP TEMPORARY SUPPORTS MAIN DECK 40.00% 80.00% 20% 0.00% 82.35% -82.35% 15-Jun-13 2-Jul-13
A9060 WELDING TEMPORARY SUPPORTS MAIN DECK 30.00% 80.00% 20% 0.00% 55.00% -55.00% 18-Jun-13 8-Jul-13
A9070 NDT TEMPORARY SUPPORTS MAIN DECK 15.00% 80.00% 20% 0.00% 33.33% -33.33% 24-Jun-13 9-Jul-13
4.1.5 MOBILISATION OF SUB-CONTRACTOR 18.00%Prep/ Submit Accept 36.40% 30.00% 6.40% 4-Jan-13 19-Dec-13
4.1.5.1 MOBILISATION OF DETAIL ENGINEEING SUB-CONTRACTOR 10.00% Prep/ Submit Accept 100.00% 100.00% 0.00% 9-Mar-13 6-May-13
B11360 TENDER D.E SUB-CONTRACTOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 9-Mar-13 12-Apr-13
B11370 AWARD D.E SUB-CONTRACTOR 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 13-Apr-13 16-Apr-13
B11380 MOBILISE D.E SUB-CONTRACTOR (READY TO COMMENCE WORK) 50.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 2-May-13 6-May-13
4.1.5.2 MOBILISATION OF NDT SUB-CONTRACTOR 20.00% Prep/ Submit Accept 100.00% 100.00% 0.00% 9-Mar-13 6-May-13
B1130 TENDERING SUB-CONTRACTOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 9-Mar-13 12-Apr-13
B1140 AWARD TO SUB-CONTRACTOR 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 13-Apr-13 16-Apr-13
B1150 MOBILISE SUB-CONTRACTOR (READY TO COMMENCE WORK) 50.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 2-May-13 6-May-13
4.1.5.3 MOBILISATION OF HEAT TREATMENT SUB-CONTRACTOR 20.00% Prep/ Submit Accept 16.00% 0.00% 16.00% 16-Sep-13 18-Nov-13
B11390 TENDER HEAT TREATMENT SUB-CONTRACTOR 20.00% 1 80.00% 20% 80.00% 0.00% 80.00% 16-Sep-13 19-Oct-13
B11400 AWARD HEAT TREATMENT SUB-CONTRACTOR 30.00% 80.00% 20% 0.00% 0.00% 0.00% 29-Oct-13 31-Oct-13
B11410 MOBILISE HEAT TREATMENT SUB-CONTRACTOR (READY TO COMMENCE WORK) 50.00% 80.00% 20% 0.00% 0.00% 0.00% 14-Nov-13 18-Nov-13
4.1.5.4 MOBILISATION OF LEAK TEST & BOLT TENSIONING SUB-CONTRACTOR 20.00% Prep/ Submit Accept 16.00% 0.00% 16.00% 16-Sep-13 18-Nov-13
B1160 TENDERING SUB-CONTRACTOR 20.00% 1 80.00% 20% 80.00% 0.00% 80.00% 16-Sep-13 19-Oct-13
B1170 AWARD TO SUB-CONTRACTOR 30.00% 80.00% 20% 0.00% 0.00% 0.00% 29-Oct-13 31-Oct-13
B1180 MOBILISE SUB-CONTRACTOR (READY TO COMMENCE WORK) 50.00% 80.00% 20% 0.00% 0.00% 0.00% 14-Nov-13 18-Nov-13
4.1.5.5 MOBILISATION OF INSULATION SUB-CONTRACTOR 20.00% Prep/ Submit Accept 0.00% 0.00% 0.00% 24-Oct-13 19-Dec-13
B11420 TENDERING INSULATION SUB-CONTRACTOR 20.00% 80.00% 20% 0.00% 0.00% 0.00% 24-Oct-13 20-Nov-13
B11430 AWARD INSULATION SUB-CONTRACTOR 30.00% 80.00% 20% 0.00% 0.00% 0.00% 21-Nov-13 4-Dec-13
B11440 MOBILISE INSULATION SUB-CONTRACTOR (READY TO COMMENCE WORK) 50.00% 80.00% 20% 0.00% 0.00% 0.00% 18-Dec-13 19-Dec-13
4.1.5.6 MOBILISATION OF WEIGHING & LOAD OUT SUB-CONTRACTOR 10.00% Prep/ Submit Accept 0.00% 0.00% 0.00% 24-Oct-13 19-Dec-13
B1190 TENDER SUB-CONTRACTOR 20.00% 80.00% 20% 0.00% 0.00% 0.00% 24-Oct-13 20-Nov-13
B1200 AWARD SUB-CONTRACTOR 30.00% 80.00% 20% 0.00% 0.00% 0.00% 21-Nov-13 4-Dec-13
B1210 MOBILISE SUB-CONTRACTOR (READY TO COMMENCE WORK) 50.00% 80.00% 20% 0.00% 0.00% 0.00% 18-Dec-13 19-Dec-13
4.1.6 WQT & WPS 3.00%Prep/ Submit Accept 87.00% 70.67% 16.33% 28-Mar-13 11-Jun-13
B1220 PREPARATION PQR/ WPS FOR STRUCTURAL 25.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 28-Mar-13 4-May-13
B1230 PRE-QUALITIFICATION STRUCTURE WELDER 25.00% 3 80.00% 3 20% 100.00% 100.00% 0.00% 6-May-13 23-May-13
B1240 PREPARATION PQR/ WPS FOR PIPING 25.00% 10 80.00% 4 20% 88.00% 82.69% 5.31% 17-May-13 8-Jul-13
B1250 PREPARATION WQT FOR PIPING 25.00% 2 80.00% 1 20% 60.00% 0.00% 60.00% 2-Jul-13 30-Jul-13
4.1.7 PANEL COATING SYSTEM QUALIFICATION TEST 1.00%Prep/ Submit Accept 100.00% 100.00% 0.00% 15-May-13 11-Jun-13
B1260 PANEL TEST/ COATING SYSTEM QUALIFICATION TEST 100.00% 1 70.00% 1 30% 100.00% 100.00% 0.00% 15-May-13 11-Jun-13
4.2 ONSHORE FABRICATION 64.00% 9.65% 5.60% 4.05% 20-Apr-13 28-Feb-14
4.2.1 STRUCTURAL 50.00% 15.79% 8.96% 6.83% 21-May-13 27-Jan-14
4.2.1.1 FABRICATION OF TUBULARS 5.00% ACCEPTED 100.00% 26.54% 73.46% 1-Jun-13 13-Aug-13
4.2.1.1.1 FABRICATION OF PIPE LEGS 40.00% COMPLETED ACCEPTED 100.00% 66.35% 33.65% 1-Jun-13 13-Jul-13
E1550 MARK/ CUT PIPE LEGS 15.00% COMPLETED ACCEPTED 100.00% 100.00% 0.00% 1-Jun-13 21-Jun-13
TRA-05 3.13% 1 80% 1.0 20% 100.00%
TRA-06 8.97% 1 80% 1.0 20% 100.00%
TRA-07 8.19% 1 80% 1.0 20% 100.00%
TRA-11 3.13% 1 80% 1.0 20% 100.00%
TRA-12 5.63% 1 80% 1.0 20% 100.00%
TRA-13 4.21% 1 80% 1.0 20% 100.00%
TRA-14 11.65% 1 80% 1.0 20% 100.00%

TRB-05 3.76% 1 80% 1.0 20% 100.00%


TRB-06 8.35% 1 80% 1.0 20% 100.00%
TRB-07 8.19% 1 80% 1.0 20% 100.00%
TRB-11/1 4.39% 1 80% 1.0 20% 100.00%
TRB-11/2 4.43% 1 80% 1.0 20% 100.00%

8
TRB-12 4.54% 1 80% 1.0 20% 100.00%
TRB-13 10.72% 1 80% 1.0 20% 100.00%
TRB-14 10.72% 1 80% 1.0 20% 100.00%
E1560 FIT UP PIPE LEGS 40.00% COMPLETED ACCEPTED 100.00% 72.73% 27.27% 13-Jun-13 5-Jul-13
TRA-05 3.13% 1 80% 1 20% 100.00%
TRA-06 8.97% 1 80% 1 20% 100.00%
TRA-07 8.19% 1 80% 1 20% 100.00%
TRA-11 3.13% 1 80% 1 20% 100.00%
TRA-12 5.63% 1 80% 1 20% 100.00%
TRA-13 4.21% 1 80% 1 20% 100.00%
TRA-14 11.65% 1 80% 1 20% 100.00%
0.00% 80% 20% 0.00%
TRB-05 3.76% 1 80% 1 20% 100.00%
TRB-06 8.35% 1 80% 1 20% 100.00%
TRB-07 8.19% 1 80% 1 20% 100.00%
TRB-11/1 4.39% 1 80% 1 20% 100.00%
TRB-11/2 4.43% 1 80% 1 20% 100.00%
TRB-12 4.54% 1 80% 1 20% 100.00%
TRB-13 10.72% 1 80% 1 20% 100.00%
TRB-14 10.72% 1 80% 1 20% 100.00%
E1570 WELDING PIPE LEGS 30.00% COMPLETED ACCEPTED 100.00% 56.00% 44.00% 15-Jun-13 10-Jul-13
TRA-05 3.13% 1 80% 1 20% 100.00%
TRA-06 8.97% 1 80% 1 20% 100.00%
TRA-07 8.19% 1 80% 1 20% 100.00%
TRA-11 3.13% 1 80% 1 20% 100.00%
TRA-12 5.63% 1 80% 1 20% 100.00%
TRA-13 4.21% 1 80% 1 20% 100.00%
TRA-14 11.65% 1 80% 1 20% 100.00%
0.00% 80% 20% 0.00%
TRB-05 3.76% 1 80% 1 20% 100.00%
TRB-06 8.35% 1 80% 1 20% 100.00%
TRB-07 8.19% 1 80% 1 20% 100.00%
TRB-11/1 4.39% 1 80% 1 20% 100.00%
TRB-11/2 4.43% 1 80% 1 20% 100.00%
TRB-12 4.54% 1 80% 1 20% 100.00%
TRB-13 10.72% 1 80% 1 20% 100.00%
TRB-14 10.72% 1 80% 1 20% 100.00%
E1580 NDT PIPE LEGS 15.00% COMPLETED ACCEPTED 100.00% 36.36% 63.64% 21-Jun-13 13-Jul-13
TRA-05 3.13% 1 80% 1 20% 100.00%
TRA-06 8.97% 1 80% 1 20% 100.00%
TRA-07 8.19% 1 80% 1 20% 100.00%
TRA-11 3.13% 1 80% 1 20% 100.00%
TRA-12 5.63% 1 80% 1 20% 100.00%
TRA-13 4.21% 1 80% 1 20% 100.00%
TRA-14 11.65% 1 80% 1 20% 100.00%
0.00% 80% 20% 0.00%
TRB-05 3.76% 1 80% 1 20% 100.00%
TRB-06 8.35% 1 80% 1 20% 100.00%
TRB-07 8.19% 1 80% 1 20% 100.00%
TRB-11/1 4.39% 1 80% 1 20% 100.00%
TRB-11/2 4.43% 1 80% 1 20% 100.00%
TRB-12 4.54% 1 80% 1 20% 100.00%
TRB-13 10.72% 1 80% 1 20% 100.00%
TRB-14 10.72% 1 80% 1 20% 100.00%
4.2.1.1.2 FABRICATION OF BRACING 60.00% COMPLETED ACCEPTED 100.00% 0.00% 100.00% 6-Jul-13 13-Aug-13
E1670 MARK/ CUT BRACING PIPE 15.00% COMPLETED ACCEPTED 100.00% 0.00% 100.00% 6-Jul-13 19-Jul-13
TRA-01 1.12% 1.0 80% 1.0 20% 100.00%
TRA-02 1.89% 1.0 80% 1.0 20% 100.00%
TRA-03/1 0.88% 1.0 80% 1.0 20% 100.00%
TRA-03/2 0.44% 1.0 80% 1.0 20% 100.00%
TRA-04 1.84% 1.0 80% 1.0 20% 100.00%
TRA-08 8.27% 1.0 80% 1.0 20% 100.00%

9
TRA-09 1.25% 1.0 80% 1.0 20% 100.00%
TRA-10 8.16% 1.0 80% 1.0 20% 100.00%
TRA-15 2.34% 1.0 80% 1.0 20% 100.00%
TRA-16/1 0.61% 1.0 80% 1.0 20% 100.00%
TRA-16/2 0.20% 1.0 80% 1.0 20% 100.00%
TRA-16/3 0.43% 1.0 80% 1.0 20% 100.00%
TRA-17/1 0.81% 1.0 80% 1.0 20% 100.00%
TRA-17/2 1.62% 1.0 80% 1.0 20% 100.00%
TRA-18/1 0.17% 1.0 80% 1.0 20% 100.00%
TRA-18/2 0.88% 1.0 80% 1.0 20% 100.00%

TRB-01 1.12% 1.0 80% 1.0 20% 100.00%


TRB-02 2.11% 1.0 80% 1.0 20% 100.00%
TRB-03 1.33% 1.0 80% 1.0 20% 100.00%
TRB-04 2.06% 1.0 80% 1.0 20% 100.00%
TRB-08 8.27% 1.0 80% 1.0 20% 100.00%
TRB-09 1.25% 1.0 80% 1.0 20% 100.00%
TRB-10 8.16% 1.0 80% 1.0 20% 100.00%
TRB-15 2.83% 1.0 80% 1.0 20% 100.00%
TRB-16 1.39% 1.0 80% 1.0 20% 100.00%
TRB-17/1 0.33% 1.0 80% 1.0 20% 100.00%
TRB-17/2 0.33% 1.0 80% 1.0 20% 100.00%
TRB-18/1 0.72% 1.0 80% 1.0 20% 100.00%
TRB-18/2 0.38% 1.0 80% 1.0 20% 100.00%

TR1-01 4.14% 1.0 80% 1.0 20% 100.00%


TR1-02 1.05% 1.0 80% 1.0 20% 100.00%
TR1-03 4.97% 1.0 80% 1.0 20% 100.00%

TR2-01 3.99% 1.0 80% 1.0 20% 100.00%


TR2-02 1.05% 1.0 80% 1.0 20% 100.00%
TR2-03 4.91% 1.0 80% 1.0 20% 100.00%

TR1 a-01 1.65% 1.0 80% 1.0 20% 100.00%


TR1 a-02 1.65% 1.0 80% 1.0 20% 100.00%
TR1 a-03 1.37% 1.0 80% 1.0 20% 100.00%
TR1 a-04 1.65% 1.0 80% 1.0 20% 100.00%
TR1 a-05 1.65% 1.0 80% 1.0 20% 100.00%
0.00%
TR2 a-01 1.58% 1.0 80% 1.0 20% 100.00%
TR2 a-02 1.59% 1.0 80% 1.0 20% 100.00%
TR2 a-03 1.33% 1.0 80% 1.0 20% 100.00%
TR2 a-04 1.61% 1.0 80% 1.0 20% 100.00%
TR2 a-05 1.61% 1.0 80% 1.0 20% 100.00%

SV-A 0.98% 1.0 80% 1.0 20% 100.00%


SV-B 1.01% 1.0 80% 1.0 20% 100.00%
SV-C 1.01% 1.0 80% 1.0 20% 100.00%
E1680 FIT UP BRACING PIPE 40.00% COMPLETED ACCEPTED 100.00% 0.00% 100.00% 12-Jul-13 29-Jul-13
TRA-01 1.12% 1.0 80% 1.0 20% 100.00%
TRA-02 1.89% 1.0 80% 1.0 20% 100.00%
TRA-03/1 0.88% 1.0 80% 1.0 20% 100.00%
TRA-03/2 0.44% 1.0 80% 1.0 20% 100.00%
TRA-04 1.84% 1.0 80% 1.0 20% 100.00%
TRA-08 8.27% 1.0 80% 1.0 20% 100.00%
TRA-09 1.25% 1.0 80% 1.0 20% 100.00%
TRA-10 8.16% 1.0 80% 1.0 20% 100.00%
TRA-15 2.34% 1.0 80% 1.0 20% 100.00%
TRA-16/1 0.61% 1.0 80% 1.0 20% 100.00%
TRA-16/2 0.20% 1.0 80% 1.0 20% 100.00%
TRA-16/3 0.43% 1.0 80% 1.0 20% 100.00%
TRA-17/1 0.81% 1.0 80% 1.0 20% 100.00%

10
TRA-17/2 1.62% 1.0 80% 1.0 20% 100.00%
TRA-18/1 0.17% 1.0 80% 1.0 20% 100.00%
TRA-18/2 0.88% 1.0 80% 1.0 20% 100.00%

TRB-01 1.12% 1.0 80% 1.0 20% 100.00%


TRB-02 2.11% 1.0 80% 1.0 20% 100.00%
TRB-03 1.33% 1.0 80% 1.0 20% 100.00%
TRB-04 2.06% 1.0 80% 1.0 20% 100.00%
TRB-08 8.27% 1.0 80% 1.0 20% 100.00%
TRB-09 1.25% 1.0 80% 1.0 20% 100.00%
TRB-10 8.16% 1.0 80% 1.0 20% 100.00%
TRB-15 2.83% 1.0 80% 1.0 20% 100.00%
TRB-16 1.39% 1.0 80% 1.0 20% 100.00%
TRB-17/1 0.33% 1.0 80% 1.0 20% 100.00%
TRB-17/2 0.33% 1.0 80% 1.0 20% 100.00%
TRB-18/1 0.72% 1.0 80% 1.0 20% 100.00%
TRB-18/2 0.38% 1.0 80% 1.0 20% 100.00%

TR1-01 4.14% 1.0 80% 1.0 20% 100.00%


TR1-02 1.05% 1.0 80% 1.0 20% 100.00%
TR1-03 4.97% 1.0 80% 1.0 20% 100.00%

TR2-01 3.99% 1.0 80% 1.0 20% 100.00%


TR2-02 1.05% 1.0 80% 1.0 20% 100.00%
TR2-03 4.91% 1.0 80% 1.0 20% 100.00%

TR1 a-01 1.65% 1.0 80% 1.0 20% 100.00%


TR1 a-02 1.65% 1.0 80% 1.0 20% 100.00%
TR1 a-03 1.37% 1.0 80% 1.0 20% 100.00%
TR1 a-04 1.65% 1.0 80% 1.0 20% 100.00%
TR1 a-05 1.65% 1.0 80% 1.0 20% 100.00%
0.00%
TR2 a-01 1.58% 1.0 80% 1.0 20% 100.00%
TR2 a-02 1.59% 1.0 80% 1.0 20% 100.00%
TR2 a-03 1.33% 1.0 80% 1.0 20% 100.00%
TR2 a-04 1.61% 1.0 80% 1.0 20% 100.00%
TR2 a-05 1.61% 1.0 80% 1.0 20% 100.00%

SV-A 0.98% 1.0 80% 1.0 20% 100.00%


SV-B 1.01% 1.0 80% 1.0 20% 100.00%
SV-C 1.01% 1.0 80% 1.0 20% 100.00%
E1690 WELDING BRACING PIPE 30.00% COMPLETED ACCEPTED 100.00% 0.00% 100.00% 18-Jul-13 7-Aug-13
TRA-01 1.12% 1.0 80% 1.0 20% 100.00%
TRA-02 1.89% 1.0 80% 1.0 20% 100.00%
TRA-03/1 0.88% 1.0 80% 1.0 20% 100.00%
TRA-03/2 0.44% 1.0 80% 1.0 20% 100.00%
TRA-04 1.84% 1.0 80% 1.0 20% 100.00%
TRA-08 8.27% 1.0 80% 1.0 20% 100.00%
TRA-09 1.25% 1.0 80% 1.0 20% 100.00%
TRA-10 8.16% 1.0 80% 1.0 20% 100.00%
TRA-15 2.34% 1.0 80% 1.0 20% 100.00%
TRA-16/1 0.61% 1.0 80% 1.0 20% 100.00%
TRA-16/2 0.20% 1.0 80% 1.0 20% 100.00%
TRA-16/3 0.43% 1.0 80% 1.0 20% 100.00%
TRA-17/1 0.81% 1.0 80% 1.0 20% 100.00%
TRA-17/2 1.62% 1.0 80% 1.0 20% 100.00%
TRA-18/1 0.17% 1.0 80% 1.0 20% 100.00%
TRA-18/2 0.88% 1.0 80% 1.0 20% 100.00%

TRB-01 1.12% 1.0 80% 1.0 20% 100.00%


TRB-02 2.11% 1.0 80% 1.0 20% 100.00%
TRB-03 1.33% 1.0 80% 1.0 20% 100.00%

11
TRB-04 2.06% 1.0 80% 1.0 20% 100.00%
TRB-08 8.27% 1.0 80% 1.0 20% 100.00%
TRB-09 1.25% 1.0 80% 1.0 20% 100.00%
TRB-10 8.16% 1.0 80% 1.0 20% 100.00%
TRB-15 2.83% 1.0 80% 1.0 20% 100.00%
TRB-16 1.39% 1.0 80% 1.0 20% 100.00%
TRB-17/1 0.33% 1.0 80% 1.0 20% 100.00%
TRB-17/2 0.33% 1.0 80% 1.0 20% 100.00%
TRB-18/1 0.72% 1.0 80% 1.0 20% 100.00%
TRB-18/2 0.38% 1.0 80% 1.0 20% 100.00%

TR1-01 4.14% 1.0 80% 1.0 20% 100.00%


TR1-02 1.05% 1.0 80% 1.0 20% 100.00%
TR1-03 4.97% 1.0 80% 1.0 20% 100.00%

TR2-01 3.99% 1.0 80% 1.0 20% 100.00%


TR2-02 1.05% 1.0 80% 1.0 20% 100.00%
TR2-03 4.91% 1.0 80% 1.0 20% 100.00%

TR1 a-01 1.65% 1.0 80% 1.0 20% 100.00%


TR1 a-02 1.65% 1.0 80% 1.0 20% 100.00%
TR1 a-03 1.37% 1.0 80% 1.0 20% 100.00%
TR1 a-04 1.65% 1.0 80% 1.0 20% 100.00%
TR1 a-05 1.65% 1.0 80% 1.0 20% 100.00%
0.00%
TR2 a-01 1.58% 1.0 80% 1.0 20% 100.00%
TR2 a-02 1.59% 1.0 80% 1.0 20% 100.00%
TR2 a-03 1.33% 1.0 80% 1.0 20% 100.00%
TR2 a-04 1.61% 1.0 80% 1.0 20% 100.00%
TR2 a-05 1.61% 1.0 80% 1.0 20% 100.00%

SV-A 0.98% 1.0 80% 1.0 20% 100.00%


SV-B 1.01% 1.0 80% 1.0 20% 100.00%
SV-C 1.01% 1.0 80% 1.0 20% 100.00%
E1700 NDT BRACING PIPE 15.00% COMPLETED ACCEPTED 100.00% 0.00% 100.00% 24-Jul-13 13-Aug-13
TRA-01 1.12% 1.0 80% 1.0 20% 100.00%
TRA-02 1.89% 1.0 80% 1.0 20% 100.00%
TRA-03/1 0.88% 1.0 80% 1.0 20% 100.00%
TRA-03/2 0.44% 1.0 80% 1.0 20% 100.00%
TRA-04 1.84% 1.0 80% 1.0 20% 100.00%
TRA-08 8.27% 1.0 80% 1.0 20% 100.00%
TRA-09 1.25% 1.0 80% 1.0 20% 100.00%
TRA-10 8.16% 1.0 80% 1.0 20% 100.00%
TRA-15 2.34% 1.0 80% 1.0 20% 100.00%
TRA-16/1 0.61% 1.0 80% 1.0 20% 100.00%
TRA-16/2 0.20% 1.0 80% 1.0 20% 100.00%
TRA-16/3 0.43% 1.0 80% 1.0 20% 100.00%
TRA-17/1 0.81% 1.0 80% 1.0 20% 100.00%
TRA-17/2 1.62% 1.0 80% 1.0 20% 100.00%
TRA-18/1 0.17% 1.0 80% 1.0 20% 100.00%
TRA-18/2 0.88% 1.0 80% 1.0 20% 100.00%

TRB-01 1.12% 1.0 80% 1.0 20% 100.00%


TRB-02 2.11% 1.0 80% 1.0 20% 100.00%
TRB-03 1.33% 1.0 80% 1.0 20% 100.00%
TRB-04 2.06% 1.0 80% 1.0 20% 100.00%
TRB-08 8.27% 1.0 80% 1.0 20% 100.00%
TRB-09 1.25% 1.0 80% 1.0 20% 100.00%
TRB-10 8.16% 1.0 80% 1.0 20% 100.00%
TRB-15 2.83% 1.0 80% 1.0 20% 100.00%
TRB-16 1.39% 1.0 80% 1.0 20% 100.00%
TRB-17/1 0.33% 1.0 80% 1.0 20% 100.00%

12
TRB-17/2 0.33% 1.0 80% 1.0 20% 100.00%
TRB-18/1 0.72% 1.0 80% 1.0 20% 100.00%
TRB-18/2 0.38% 1.0 80% 1.0 20% 100.00%

TR1-01 4.14% 1.0 80% 1.0 20% 100.00%


TR1-02 1.05% 1.0 80% 1.0 20% 100.00%
TR1-03 4.97% 1.0 80% 1.0 20% 100.00%

TR2-01 3.99% 1.0 80% 1.0 20% 100.00%


TR2-02 1.05% 1.0 80% 1.0 20% 100.00%
TR2-03 4.91% 1.0 80% 1.0 20% 100.00%

TR1 a-01 1.65% 1.0 80% 1.0 20% 100.00%


TR1 a-02 1.65% 1.0 80% 1.0 20% 100.00%
TR1 a-03 1.37% 1.0 80% 1.0 20% 100.00%
TR1 a-04 1.65% 1.0 80% 1.0 20% 100.00%
TR1 a-05 1.65% 1.0 80% 1.0 20% 100.00%
0.00%
TR2 a-01 1.58% 1.0 80% 1.0 20% 100.00%
TR2 a-02 1.59% 1.0 80% 1.0 20% 100.00%
TR2 a-03 1.33% 1.0 80% 1.0 20% 100.00%
TR2 a-04 1.61% 1.0 80% 1.0 20% 100.00%
TR2 a-05 1.61% 1.0 80% 1.0 20% 100.00%

SV-A 0.98% 1.0 80% 1.0 20% 100.00%


SV-B 1.01% 1.0 80% 1.0 20% 100.00%
SV-C 1.01% 1.0 80% 1.0 20% 100.00%
4.2.1.2 FABRICATION OF STRUCTURAL MEMBERS 55.00% COMPLETED ACCEPTED 19.62% 13.87% 5.74% 21-May-13 30-Dec-13
4.2.1.2.1 FABRICATION OF CELLAR DECK FRAME 30.00% COMPLETED ACCEPTED 43.78% 41.45% 2.33% 21-May-13 30-Aug-13
4.2.1.2.1.1 FABRICATION WF BEAMS OF CELLAR DECK 10.00% COMPLETED ACCEPTED 100.00% 100.00% 0.00% 1-Jun-13 15-Jun-13
A11280 MARK/ CUT PLATE STEEL FOR WF CELLAR DECK 15.00% COMPLETED ACCEPTED 100.00% 100.00% 0.00% 1-Jun-13 4-Jun-13
CP-107/1 13.21% 1.0 80% 1.0 20% 100.00%
CP-107/2 24.95% 1.0 80% 1.0 20% 100.00%
CP-107/3 8.96% 1.0 80% 1.0 20% 100.00%
CP-107/4A 1.76% 1.0 80% 1.0 20% 100.00%
CP-107/4B 1.76% 1.0 80% 1.0 20% 100.00%
CP-108/1 12.88% 1.0 80% 1.0 20% 100.00%
CP-108/2 24.31% 1.0 80% 1.0 20% 100.00%
CP-108/3 8.63% 1.0 80% 1.0 20% 100.00%
CP-108/4A 1.76% 1.0 80% 1.0 20% 100.00%
CP-108/4B 1.76% 1.0 80% 1.0 20% 100.00%
A11290 FIT UP PLATE STEEL FOR WF CELLAR DECK 40.00% COMPLETED ACCEPTED 100.00% 100.00% 0.00% 3-Jun-13 8-Jun-13
CP-107/1 13.21% 1.0 80% 1.0 20% 100.00%
CP-107/2 24.95% 1.0 80% 1.0 20% 100.00%
CP-107/3 8.96% 1.0 80% 1.0 20% 100.00%
CP-107/4A 1.76% 1.0 80% 1.0 20% 100.00%
CP-107/4B 1.76% 1.0 80% 1.0 20% 100.00%
CP-108/1 12.88% 1.0 80% 1.0 20% 100.00%
CP-108/2 24.31% 1.0 80% 1.0 20% 100.00%
CP-108/3 8.63% 1.0 80% 1.0 20% 100.00%
CP-108/4A 1.76% 1.0 80% 1.0 20% 100.00%
CP-108/4B 1.76% 1.0 80% 1.0 20% 100.00%
A11300 WELDING WF FOR CELLAR DECK 30.00% COMPLETED ACCEPTED 100.00% 100.00% 0.00% 6-Jun-13 13-Jun-13
CP-107/1 13.21% 1 80% 1 20% 100.00%
CP-107/2 24.95% 1 80% 1 20% 100.00%
CP-107/3 8.96% 1 80% 1 20% 100.00%
CP-107/4A 1.76% 1 80% 1 20% 100.00%
CP-107/4B 1.76% 1 80% 1 20% 100.00%
CP-108/1 12.88% 1 80% 1 20% 100.00%
CP-108/2 24.31% 1 80% 1 20% 100.00%
CP-108/3 8.63% 1 80% 1 20% 100.00%
CP-108/4A 1.76% 1 80% 1 20% 100.00%

13
CP-108/4B 1.76% 1 80% 1 20% 100.00%
A11310 NDT WF FOR CELLAR DECK 15.00% COMPLETED ACCEPTED 100.00% 100.00% 0.00% 11-Jun-13 15-Jun-13
CP-107/1 13.21% 1 80% 1 20% 100.00%
CP-107/2 24.95% 1 80% 1 20% 100.00%
CP-107/3 8.96% 1 80% 1 20% 100.00%
CP-107/4A 1.76% 1 80% 1 20% 100.00%
CP-107/4B 1.76% 1 80% 1 20% 100.00%
CP-108/1 12.88% 1 80% 1 20% 100.00%
CP-108/2 24.31% 1 80% 1 20% 100.00%
CP-108/3 8.63% 1 80% 1 20% 100.00%
CP-108/4A 1.76% 1 80% 1 20% 100.00%
CP-108/4B 1.76% 1 80% 1 20% 100.00%
4.2.1.2.1.2 FABRICATION OF CELLAR DECK PART II 35.00% COMPLETED ACCEPTED 33.41% 40.11% -6.70% 21-May-13 12-Aug-13
4.2.1.2.1.2.1 FABRICATION OF PRIMARY FRAME PART II 40.00% 60.00% 72.00% -12.00% 21-May-13 10-Jul-13
A9078 LAYOUT TEMPORARY SUPPORTS FOR CELLAR DECK PART II 5.00% 40.0 80% 40.0 20% 100.00% 100.00% 0.00% 21-May-13 27-May-13
A9079 INSTALL PIPE LEGS FOR CELLAR DECK PART II 5.00% 4.0 80% 4.0 20% 100.00% 100.00% 0.00% 5-Jun-13 8-Jun-13
A9080 MARK/ CUT PRIMARY FRAME FOR CELLAR DECK PART II 10.00% 100.00% 100.00% 0.00% 1-Jun-13 14-Jun-13
A9090 FIT UP PRIMARY FRAME FOR CELLAR DECK PART II 40.00% 100.00% 100.00% 0.00% 10-Jun-13 26-Jun-13
A9100 WELDING PRIMARY FRAME FOR CELLAR DECK PART II 30.00% 0.00% 40.00% -40.00% 25-Jun-13 5-Jul-13
A9110 NDT PRIMARY FRAME FOR CELLAR DECK PART II 10.00% 0.00% 0.00% 0.00% 29-Jun-13 10-Jul-13
4.2.1.2.1.2.2 FABRICATION OF SECONDARY FRAME PART II 30.00% COMPLETED ACCEPTED 22.57% 22.50% 0.07% 13-Jun-13 20-Jul-13
A9120 MARK/ CUT SECONDARY FRAME FOR CELLAR DECK PART II 15.00% 100.00% 100.00% 0.00% 13-Jun-13 26-Jun-13
A9130 FIT UP SECONDARY FRAME FOR CELLAR DECK PART II 40.00% 18.92% 18.75% 0.17% 26-Jun-13 12-Jul-13
A9140 WELDING SECONDARY FRAME FOR CELLAR DECK PART II 30.00% 0.00% 0.00% 0.00% 1-Jul-13 17-Jul-13
A9150 NDT SECONDARY FRAME FOR CELLAR DECK PART II 15.00% 0.00% 0.00% 0.00% 4-Jul-13 20-Jul-13
4.2.1.2.1.2.3 FABRICATION OF JOINT DETAIL PART II 10.00% COMPLETED ACCEPTED 26.40% 41.82% -15.42% 5-Jun-13 24-Jul-13
A9160 MARK/ CUT JOINT DETAIL FOR CELLAR DECK PART II 15.00% 78.83% 100.00% -21.17% 5-Jun-13 21-Jun-13
A9170 FIT UP JOINT DETAIL FOR CELLAR DECK PART II 40.00% 36.44% 50.00% -13.56% 15-Jun-13 13-Jul-13
A9180 WELDING JOINT DETAIL FOR CELLAR DECK PART II 30.00% 0.00% 22.73% -22.73% 24-Jun-13 16-Jul-13
A9190 NDT JOINT DETAIL FOR CELLAR DECK PART II 15.00% 0.00% 0.00% 0.00% 2-Jul-13 24-Jul-13
4.2.1.2.1.2.4 FABRICATION OF DECK PLATING PART II 20.00% COMPLETED ACCEPTED 0.00% 1.88% -1.88% 27-Jun-13 12-Aug-13
A9200 MARK/ CUT DECK PLATING FOR CELLAR DECK PART II 15.00% 80% 20% 0.00% 12.50% -12.50% 27-Jun-13 13-Jul-13
A9210 FIT UP DECK PLATING FOR CELLAR DECK PART II 40.00% 80% 20% 0.00% 0.00% 0.00% 9-Jul-13 31-Jul-13
A9220 WELDING DECK PLATING FOR CELLAR DECK PART II 30.00% 80% 20% 0.00% 0.00% 0.00% 15-Jul-13 6-Aug-13
A9230 NDT DECK PLATING FOR CELLAR DECK PART II 15.00% 80% 20% 0.00% 0.00% 0.00% 20-Jul-13 12-Aug-13
4.2.1.2.1.3 FABRICATION OF CELLAR DECK PART III 30.00% COMPLETED ACCEPTED 28.63% 34.65% -6.02% 27-May-13 21-Aug-13
4.2.1.2.1.3.1 FABRICATION OF PRIMARY FRAME PART III 40.00% COMPLETED ACCEPTED 70.29% 65.45% 4.83% 27-May-13 12-Jul-13
A9778 LAYOUT TEMPORARY SUPPORTS FOR CELLAR DECK PART III 10.00% 40.0 80% 40.0 20% 100.00% 100.00% 0.00% 27-May-13 1-Jun-13
A9780 MARK/ CUT PRIMARY FRAME FOR CELLAR DECK PART III 10.00% 100.00% 100.00% 0.00% 5-Jun-13 18-Jun-13
A9790 FIT UP PRIMARY FRAME FOR CELLAR DECK PART III 40.00% 96.11% 100.00% -3.89% 12-Jun-13 28-Jun-13
A9800 WELDING PRIMARY FRAME FOR CELLAR DECK PART III 30.00% 39.49% 18.18% 21.31% 27-Jun-13 8-Jul-13
A9810 NDT PRIMARY FRAME FOR CELLAR DECK PART III 10.00% 0.00% 0.00% 0.00% 2-Jul-13 12-Jul-13
4.2.1.2.1.3.2 FABRICATION OF SECONDARY FRAME PART III 30.00% COMPLETED ACCEPTED 1.06% 17.00% -15.94% 14-Jun-13 30-Jul-13
A9840 MARK/ CUT SECONDARY FRAME FOR CELLAR DECK PART III 15.00% 7.07% 100.00% -92.93% 14-Jun-13 27-Jun-13
A9850 FIT UP SECONDARY FRAME FOR CELLAR DECK PART III 40.00% 0.00% 5.00% -5.00% 28-Jun-13 18-Jul-13
A9860 WELDING SECONDARY FRAME FOR CELLAR DECK PART III 30.00% 0.00% 0.00% 0.00% 4-Jul-13 24-Jul-13
A9870 NDT SECONDARY FRAME FOR CELLAR DECK PART III 15.00% 0.00% 0.00% 0.00% 10-Jul-13 30-Jul-13
4.2.1.2.1.3.3 FABRICATION OF JOINT DETAIL PART III 10.00% COMPLETED ACCEPTED 1.93% 33.69% -31.76% 14-Jun-13 24-Jul-13
A9880 MARK/ CUT JOINT DETAIL FOR CELLAR DECK PART III 15.00% 12.90% 88.24% -75.34% 14-Jun-13 1-Jul-13
A9890 FIT UP JOINT DETAIL FOR CELLAR DECK PART III 40.00% 0.00% 40.91% -40.91% 20-Jun-13 12-Jul-13
A9900 WELDING JOINT DETAIL FOR CELLAR DECK PART III 30.00% 0.00% 13.64% -13.64% 26-Jun-13 18-Jul-13
A9910 NDT JOINT DETAIL FOR CELLAR DECK PART III 15.00% 0.00% 0.00% 0.00% 2-Jul-13 24-Jul-13
4.2.1.2.1.3.4 FABRICATION OF DECK PLATING PART III 20.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 2-Jul-13 21-Aug-13
A9920 MARK/ CUT DECK PLATING FOR CELLAR DECK PART III 15.00% 80% 20% 0.00% 0.00% 0.00% 2-Jul-13 18-Jul-13
A9930 FIT UP DECK PLATING FOR CELLAR DECK PART III 40.00% 80% 20% 0.00% 0.00% 0.00% 16-Jul-13 7-Aug-13
A9940 WELDING DECK PLATING FOR CELLAR DECK PART III 30.00% 80% 20% 0.00% 0.00% 0.00% 22-Jul-13 15-Aug-13
A9950 NDT DECK PLATING FOR CELLAR DECK PART III 15.00% 80% 20% 0.00% 0.00% 0.00% 27-Jul-13 21-Aug-13
4.2.1.2.1.4 FABRICATION OF CELLAR DECK PART I 25.00% COMPLETED ACCEPTED 54.00% 28.06% 25.94% 27-May-13 30-Aug-13
4.2.1.2.1.4.1 FABRICATION OF PRIMARY FRAME PART I 40.00% COMPLETED ACCEPTED 90.00% 55.29% 34.71% 27-May-13 18-Jul-13
A10468 LAYOUT TEMPORARY SUPPORTS FOR CELLAR DECK PART I 10.00% 39.0 80% 39.0 20% 100.00% 100.00% 0.00% 27-May-13 1-Jun-13
A10470 MARK/ CUT PRIMARY FRAME FOR CELLAR DECK PART I 10.00% 100.00% 100.00% 0.00% 7-Jun-13 20-Jun-13
A10480 FIT UP PRIMARY FRAME FOR CELLAR DECK PART I 40.00% 100.00% 88.24% 11.76% 14-Jun-13 1-Jul-13

14
A10490 WELDING PRIMARY FRAME FOR CELLAR DECK PART I 30.00% 100.00% 0.00% 100.00% 2-Jul-13 12-Jul-13
A10500 NDT PRIMARY FRAME FOR CELLAR DECK PART I 10.00% 0.00% 0.00% 0.00% 8-Jul-13 18-Jul-13
4.2.1.2.1.4.2 FABRICATION OF SECONDARY FRAME PART I 30.00% COMPLETED ACCEPTED 55.00% 11.54% 43.46% 19-Jun-13 8-Aug-13
A10520 MARK/ CUT SECONDARY FRAME FOR CELLAR DECK PART I 15.00% 100.00% 76.92% 23.08% 19-Jun-13 2-Jul-13
A10530 FIT UP SECONDARY FRAME FOR CELLAR DECK PART I 40.00% 100.00% 0.00% 100.00% 8-Jul-13 20-Jul-13
A10540 WELDING SECONDARY FRAME FOR CELLAR DECK PART I 30.00% 0.00% 0.00% 0.00% 13-Jul-13 2-Aug-13
A10550 NDT SECONDARY FRAME FOR CELLAR DECK PART I 15.00% 0.00% 0.00% 0.00% 19-Jul-13 8-Aug-13
4.2.1.2.1.4.3 FABRICATION OF JOINT DETAIL PART I 10.00% COMPLETED ACCEPTED 15.00% 24.79% -9.79% 17-Jun-13 26-Jul-13
A10560 MARK/ CUT JOINT DETAIL FOR CELLAR DECK PART I 15.00% 67.37% 75.00% -7.63% 17-Jun-13 3-Jul-13
A10570 FIT UP JOINT DETAIL FOR CELLAR DECK PART I 40.00% 10.40% 30.43% -20.03% 22-Jun-13 15-Jul-13
A10580 WELDING JOINT DETAIL FOR CELLAR DECK PART I 30.00% 2.44% 4.55% -2.11% 28-Jun-13 20-Jul-13
A10590 NDT JOINT DETAIL FOR CELLAR DECK PART I 15.00% 0.00% 0.00% 0.00% 4-Jul-13 26-Jul-13
4.2.1.2.1.4.4 FABRICATION OF DECK PLATING PART I 20.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 6-Jul-13 30-Aug-13
A10600 MARK/ CUT DECK PLATING FOR CELLAR DECK PART I 15.00% 80% 20% 0.00% 0.00% 0.00% 6-Jul-13 23-Jul-13
A10610 FIT UP DECK PLATING FOR CELLAR DECK PART I 40.00% 80% 20% 0.00% 0.00% 0.00% 25-Jul-13 16-Aug-13
A10620 WELDING DECK PLATING FOR CELLAR DECK PART I 30.00% 80% 20% 0.00% 0.00% 0.00% 31-Jul-13 24-Aug-13
A10630 NDT DECK PLATING FOR CELLAR DECK PART I 15.00% 80% 20% 0.00% 0.00% 0.00% 6-Aug-13 30-Aug-13
4.2.1.2.2 FABRICATION OF MAIN DECK FRAME 32.00% COMPLETED ACCEPTED 20.26% 4.50% 15.76% 17-Jun-13 29-Oct-13
4.2.1.2.2.1 FABRICATION WF BEAMS OF MAIN DECK 10.00% COMPLETED ACCEPTED 100.00% 45.00% 55.00% 17-Jun-13 19-Jul-13
A11320 MARK/ CUT PLATE STEEL FOR WF MAIN DECK 15.00% 100.00% 100.00% 0.00% 17-Jun-13 24-Jun-13
A11330 FIT UP PLATE STEEL FOR WF MAIN DECK 40.00% 100.00% 69.23% 30.77% 20-Jun-13 3-Jul-13
A11340 WELDING WF FOR MAIN DECK 30.00% 100.00% 7.69% 92.31% 28-Jun-13 11-Jul-13
A11350 NDT WF FOR MAIN DECK 15.00% 100.00% 0.00% 100.00% 6-Jul-13 19-Jul-13
4.2.1.2.2.2 FABRICATION OF MAIN DECK PART II 35.00% COMPLETED ACCEPTED 20.75% 0.00% 20.75% 9-Jul-13 14-Oct-13
4.2.1.2.2.2.1 FABRICATION OF PRIMARY FRAME PART II 40.00% COMPLETED ACCEPTED 51.85% 0.00% 51.85% 9-Jul-13 30-Aug-13
A10636 LAYOUT TEMPORARY SUPPORTS FOR MAIN DECK PART II 5.00% 41.0 80% 41 20% 100.00% 0.00% 100.00% 10-Jul-13 16-Jul-13
A10638 INSTALL PIPE LEGS FOR MAIN DECK PART II 5.00% 4.0 80% 4 20% 100.00% 0.00% 100.00% 17-Jul-13 22-Jul-13
A10640 MARK/ CUT PRIMARY FRAME FOR MAIN DECK PART II 10.00% 91.56% 0.00% 91.56% 9-Jul-13 19-Jul-13
A10650 FIT UP PRIMARY FRAME FOR MAIN DECK PART II 40.00% 81.73% 0.00% 81.73% 23-Jul-13 8-Aug-13
A10660 WELDING PRIMARY FRAME FOR MAIN DECK PART II 30.00% 0.00% 0.00% 0.00% 8-Aug-13 24-Aug-13
A10670 NDT PRIMARY FRAME FOR MAIN DECK PART III 10.00% 0.00% 0.00% 0.00% 20-Aug-13 6-Sep-13
4.2.1.2.2.2.2 FABRICATION OF SECONDARY FRAME PART II 30.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 20-Jul-13 12-Sep-13
A10700 MARK/ CUT SECONDARY FRAME FOR MAIN DECK PART II 15.00% 0.00% 0.00% 0.00% 20-Jul-13 2-Aug-13
A10710 FIT UP SECONDARY FRAME FOR MAIN DECK PART II 40.00% 0.00% 0.00% 0.00% 10-Aug-13 27-Aug-13
A10720 WELDING SECONDARY FRAME FOR MAIN DECK PART II 30.00% 0.00% 0.00% 0.00% 16-Aug-13 6-Sep-13
A10730 NDT SECONDARY FRAME FOR MAIN DECK PART II 15.00% 0.00% 0.00% 0.00% 22-Aug-13 12-Sep-13
4.2.1.2.2.2.3 FABRICATION OF JOINT DETAIL PART II 10.00% COMPLETED ACCEPTED 0.11% 0.00% 0.11% 17-Jul-13 18-Sep-13
A10740 MARK/ CUT JOINT DETAIL FOR MAIN DECK PART II 15.00% 0.77% 0.00% 0.77% 17-Jul-13 8-Aug-13
A10750 FIT UP JOINT DETAIL FOR MAIN DECK PART II 40.00% 0.00% 0.00% 0.00% 10-Aug-13 9-Sep-13
A10760 WELDING JOINT DETAIL FOR MAIN DECK PART II 30.00% 0.00% 0.00% 0.00% 14-Aug-13 12-Sep-13
A10770 NDT JOINT DETAIL FOR MAIN DECK PART II 15.00% 0.00% 0.00% 0.00% 20-Aug-13 18-Sep-13
4.2.1.2.2.2.4 FABRICATION OF DECK PLATING PART II 20.00% 0.00% 0.00% 0.00% 7-Aug-13 14-Oct-13
A10780 MARK/ CUT DECK PLATING FOR MAIN DECK PART II 15.00% 80% 20% 0.00% 0.00% 0.00% 7-Aug-13 29-Aug-13
A10790 FIT UP DECK PLATING FOR MAIN DECK PART II 40.00% 80% 20% 0.00% 0.00% 0.00% 28-Aug-13 20-Sep-13
A10800 WELDING DECK PLATING FOR MAIN DECK PART II 30.00% 80% 20% 0.00% 0.00% 0.00% 10-Sep-13 8-Oct-13
A10810 NDT DECK PLATING FOR MAIN DECK PART II 15.00% 80% 20% 0.00% 0.00% 0.00% 16-Sep-13 14-Oct-13
4.2.1.2.2.3 FABRICATION OF MAIN DECK PART III 27.50% COMPLETED ACCEPTED 8.39% 0.00% 8.39% 26-Jul-13 21-Oct-13
4.2.1.2.2.3.1 FABRICATION OF PRIMARY FRAME PART III 40.00% COMPLETED ACCEPTED 20.97% 0.00% 20.97% 26-Jul-13 6-Sep-13
A10818 LAYOUT TEMPORARY SUPPORTS FOR MAIN DECK PART III 10.00% 20.0 80% 20 20% 48.78% 0.00% 48.78% 29-Jul-13 1-Aug-13
A10820 MARK/ CUT PRIMARY FRAME FOR MAIN DECK PART III 10.00% 63.68% 0.00% 63.68% 26-Jul-13 3-Aug-13
A10830 FIT UP PRIMARY FRAME FOR MAIN DECK PART III 40.00% 24.31% 0.00% 24.31% 2-Aug-13 15-Aug-13
A10840 WELDING PRIMARY FRAME FOR MAIN DECK PART III 30.00% 0.00% 0.00% 0.00% 14-Aug-13 30-Aug-13
A10850 NDT PRIMARY FRAME FOR MAIN DECK PART III 10.00% 0.00% 0.00% 0.00% 20-Aug-13 6-Sep-13
4.2.1.2.2.3.2 FABRICATION OF SECONDARY FRAME PART III 30.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 7-Aug-13 16-Sep-13
A10870 MARK/ CUT SECONDARY FRAME FOR MAIN DECK PART III 15.00% 0.00% 0.00% 0.00% 7-Aug-13 17-Aug-13
A10880 FIT UP SECONDARY FRAME FOR MAIN DECK PART III 40.00% 0.00% 0.00% 0.00% 14-Aug-13 27-Aug-13
A10890 WELDING SECONDARY FRAME FOR MAIN DECK PART III 30.00% 0.00% 0.00% 0.00% 20-Aug-13 10-Sep-13
A10900 NDT SECONDARY FRAME FOR MAIN DECK PART III 15.00% 0.00% 0.00% 0.00% 26-Aug-13 16-Sep-13
4.2.1.2.2.3.3 FABRICATION OF JOINT DETAIL PART I 10.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 13-Aug-13 27-Sep-13
A10910 MARK/ CUT JOINT DETAIL FOR MAIN DECK PART III 15.00% 0.00% 0.00% 0.00% 13-Aug-13 29-Aug-13
A10920 FIT UP JOINT DETAIL FOR MAIN DECK PART III 40.00% 0.00% 0.00% 0.00% 20-Aug-13 12-Sep-13
A10930 WELDING JOINT DETAIL FOR MAIN DECK PART III 30.00% 0.00% 0.00% 0.00% 23-Aug-13 21-Sep-13

15
A10940 NDT JOINT DETAIL FOR MAIN DECK PART III 15.00% 0.00% 0.00% 0.00% 29-Aug-13 27-Sep-13
4.2.1.2.2.3.4 FABRICATION OF DECK PLATING PART III 20.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 24-Aug-13 21-Oct-13
A10950 MARK/ CUT DECK PLATING FOR MAIN DECK PART III 15.00% 80% 20% 0.00% 0.00% 0.00% 24-Aug-13 14-Sep-13
A10960 FIT UP DECK PLATING FOR MAIN DECK PART III 40.00% 80% 20% 0.00% 0.00% 0.00% 5-Sep-13 30-Sep-13
A10970 WELDING DECK PLATING FOR MAIN DECK PART III 30.00% 80% 20% 0.00% 0.00% 0.00% 17-Sep-13 15-Oct-13
A10980 NDT DECK PLATING FOR MAIN DECK PART III 15.00% 80% 20% 0.00% 0.00% 0.00% 23-Sep-13 21-Oct-13
4.2.1.2.2.4 FABRICATION OF MAIN DECK PART I 27.50% COMPLETED ACCEPTED 2.50% 0.00% 2.50% 7-Aug-13 29-Oct-13
4.2.1.2.2.4.1 FABRICATION OF PRIMARY FRAME PART I 50.00% COMPLETED ACCEPTED 5.00% 0.00% 5.00% 7-Aug-13 2-Oct-13
A10988 LAYOUT TEMPORARY SUPPORTS FOR MAIN DECK PART I 10.00% 20.0 80% 20 20% 50.00% 0.00% 50.00% 29-Aug-13 3-Sep-13
A10990 MARK/ CUT PRIMARY FRAME FOR MAIN DECK PART I 10.00% 0.00% 0.00% 0.00% 7-Aug-13 15-Aug-13
A11000 FIT UP PRIMARY FRAME FOR MAIN DECK PART I 40.00% 0.00% 0.00% 0.00% 4-Sep-13 17-Sep-13
A11010 WELDING PRIMARY FRAME FOR MAIN DECK PART I 30.00% 0.00% 0.00% 0.00% 16-Sep-13 26-Sep-13
A11020 NDT PRIMARY FRAME FOR MAIN DECK PART I 10.00% 0.00% 0.00% 0.00% 21-Sep-13 2-Oct-13
4.2.1.2.2.4.2 FABRICATION OF SECONDARY FRAME PART I 40.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 19-Aug-13 14-Oct-13
A11040 MARK/ CUT SECONDARY FRAME FOR MAIN DECK PART I 15.00% 0.00% 0.00% 0.00% 19-Aug-13 29-Aug-13
A11050 FIT UP SECONDARY FRAME FOR MAIN DECK PART I 40.00% 0.00% 0.00% 0.00% 16-Sep-13 28-Sep-13
A11060 WELDING SECONDARY FRAME FOR MAIN DECK PART I 30.00% 0.00% 0.00% 0.00% 21-Sep-13 8-Oct-13
A11070 NDT SECONDARY FRAME FOR MAIN DECK PART I 15.00% 0.00% 0.00% 0.00% 27-Sep-13 14-Oct-13
4.2.1.2.2.4.3 FABRICATION OF JOINT DETAIL PART I 10.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 24-Aug-13 29-Oct-13
A11080 MARK/ CUT JOINT DETAIL FOR MAIN DECK PART I 15.00% 0.00% 0.00% 0.00% 24-Aug-13 11-Sep-13
A11090 FIT UP JOINT DETAIL FOR MAIN DECK PART I 40.00% 0.00% 0.00% 0.00% 21-Sep-13 14-Oct-13
A11100 WELDING JOINT DETAIL FOR MAIN DECK PART I 30.00% 0.00% 0.00% 0.00% 25-Sep-13 23-Oct-13
A11110 NDT JOINT DETAIL FOR MAIN DECK PART I 15.00% 0.00% 0.00% 0.00% 1-Oct-13 29-Oct-13
4.2.1.2.3 FABRICATION OF HELI DECK 3.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 5-Dec-13 27-Dec-13
E1300 INSTALL HELI DECK FRAME 100.00% 80% 20% 0.00% 0.00% 0.00% 5-Dec-13 27-Dec-13
4.2.1.2.4 FABRICATIN OF VENT BOOM 10.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 12-Oct-13 30-Dec-13
E1310 LAYOUT SUPPORTS FOR VENT BOOM 10.00% 80% 20% 0.00% 0.00% 0.00% 12-Oct-13 15-Oct-13
E1320 MARK/ CUTTING FRAME FOR VENT BOOM 10.00% 80% 20% 0.00% 0.00% 0.00% 16-Oct-13 29-Oct-13
E1330 FIT UP FRAME FOR VENT BOOM 40.00% 80% 20% 0.00% 0.00% 0.00% 24-Oct-13 27-Nov-13
E1340 WELDING FRAME FOR VENT BOOM 30.00% 80% 20% 0.00% 0.00% 0.00% 9-Nov-13 20-Dec-13
E1350 NDT FRAME FOR VENT BOOM 10.00% 80% 20% 0.00% 0.00% 0.00% 26-Nov-13 30-Dec-13
4.2.1.2.5 FABRICATION OF OTHER ITEMS 25.00% Mark/Cut Fit up/ Accept Weld/ Accept NDT/ Accept 0.00% 0.00% 0.00% 11-Sep-13 20-Dec-13
E1360 FABRICATION HANDRAIL 13.20% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 7-Dec-13
E1370 FABRICATION LADDER 0.60% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 6-Dec-13
E1380 FABRICATION STAIRWAY 8.80% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 26-Oct-13 20-Dec-13
E1390 FABRICATION DECK DRAIN 3.78% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 6-Dec-13
E1400 FABRICATION EQUIPMENT MOUNTING 0.30% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 6-Dec-13
E1410 FABRICATION LIFE RAFT SUPPORT 0.30% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 6-Dec-13
E1430 FABRICATION LIFTING PADEYE 4.72% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 6-Dec-13
E1440 FABRICATION VENT BOOM SUPPORT 5.04% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 1-Oct-13 25-Nov-13
E1450 FABRICATION MONORAIL 1.83% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 6-Dec-13
E1480 FABRICATION SECURITY GATE AND WALL 23.30% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 6-Dec-13
E1500 FABRICATION CONDUCTOR GUIDE 20.78% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 8-Nov-13
E1510 FABRICATION HATCH COVER 4.41% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 8-Nov-13
E1520 FABRICATION CRANE ACCESS PLATFORM 1.64% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 18-Oct-13 14-Nov-13
E1530 FABRICATION FIRE & BLASTWALL 9.45% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 11-Sep-13 8-Oct-13
E1540 FABRICATION PLATFORM NAME PLATE 0.21% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 5-Nov-13 18-Nov-13
E1545 FABRICATION CONES (4 PCS) 1.64% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 16-Sep-13 28-Sep-13
4.2.1.3 ERECTION 35.00% Fit up/ Accept Weld/Accept NDT/Accept 0.00% 0.00% 0.00% 22-Aug-13 17-Jan-14
E1730 LAYOUT/ERECTION SUPPORTS & LOAD OUT BEAMS TO FINAL POSITION 8.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 22-Aug-13 29-Aug-13
E1750 CELLAR DECK PART II STACK UP 6.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 3-Sep-13 10-Sep-13
E1760 CELLAR DECK PART III STACK UP 5.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 12-Sep-13 19-Sep-13
E1765 CELLAR DECK PART I STACK UP 4.50% 50% 35% 15.00% 0.00% 0.00% 0.00% 21-Sep-13 28-Sep-13
E1770 PIPE LEGS ERECTION 3.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 30-Sep-13 16-Oct-13
E1775 BRACING PIPE ERECTION (PART 1) 8.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 30-Sep-13 22-Oct-13
E1780 BLAST WALL ERECTION (PART 1) 6.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 9-Oct-13 19-Oct-13
E1790 MAIN DECK PART II (AXIS 1/2) STACK UP 6.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 5-Nov-13 15-Nov-13
E1810 MAIN DECK PART III (AXIS 2/2a) STACK UP 5.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 19-Nov-13 27-Nov-13
E1820 MAIN DECK PART I (AXIS 1a/1) STACK UP 4.50% 50% 35% 15.00% 0.00% 0.00% 0.00% 23-Nov-13 30-Nov-13
E1825 HELI DECK ERECTION 2.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 28-Dec-13 4-Jan-14
E1830 BRACING ERECTION (REMAINING PART) 9.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 7-Dec-13 24-Dec-13
E1833 BLAST WALL ERECTION (REMAINING PART) 8.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 7-Dec-13 20-Dec-13

16
E1835 ERECTION OTHER ITEMS 25.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 24-Dec-13 17-Jan-14
4.2.1.4 TRIAL FIT AND WEIGHING 5.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 3-Jan-14 27-Jan-14
E1840 VENT BOOM TRIAL FIT 35.00% 80% 20% 0.00% 0.00% 0.00% 16-Jan-14 22-Jan-14
E1850 FABRICATE/ ERECTION PADEYES 10.00% 80% 20% 0.00% 0.00% 0.00% 3-Jan-14 18-Jan-14
E1855 TRIAL FIT/ LAYOUT T&I SLINGS 15.00% 80% 20% 0.00% 0.00% 0.00% 20-Jan-14 27-Jan-14
E1860 TOPSIDE WEIGHING 40.00% 80% 20% 0.00% 0.00% 0.00% 9-Jan-14 10-Jan-14
4.2.2 PIPING/ PLUMBING 19.00% COMPLETED ACCEPTED 1.80% 1.22% 0.58% 15-Jun-13 14-Feb-14
4.2.2.1 FABRICATION OF PIPE/PLUMBING SUPPORTS 48.00% COMPLETED ACCEPTED 3.74% 2.54% 1.21% 15-Jun-13 6-Dec-13
E1870 FABRICATE PIPE SUPPORT 12.50% 0.2 80% 0 20% 15.94% 20.29% -4.35% 15-Jun-13 23-Aug-13
E2280 FABRICATE PIPE SPOOL 87.50% 0.0 80% 0 20% 2.00% 0.00% 2.00% 6-Aug-13 6-Dec-13
4.2.2.2 INSTALLATION OF PIPE/PLUMBING SUPPORTS 32.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 10-Sep-13 10-Jan-14
E2690 INSTALL PIPE SUPPORT 12.50% 80% 20% 0.00% 0.00% 0.00% 10-Sep-13 4-Jan-14
E3100 INSTALL PIPE SPOOL 87.50% 80% 20% 0.00% 0.00% 0.00% 16-Sep-13 10-Jan-14
4.2.2.3 INSTALLATION OF VALVES (NUMBER OF VALVES) 5.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 10-Dec-13 25-Jan-14
E3520 INSTALL VALVES 100.00% 80% 20% 0.00% 0.00% 0.00% 10-Dec-13 25-Jan-14
4.2.2.4 LEAK TEST OF VALVES (NUMBER OF VALVES) 3.50% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 24-Dec-13 13-Feb-14
E3510 LEAK TEST VALVES 100.00% 80% 20% 0.00% 0.00% 0.00% 24-Dec-13 13-Feb-14
4.2.2.5 FLUSHING, HYDROTESTING AND ACID CLEANING 6.50% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 23-Nov-13 14-Feb-14
E3530 FLUSHING 15.00% 80% 20% 0.00% 0.00% 0.00% 23-Nov-13 15-Jan-14
E3540 HYDROTEST 70.00% 80% 20% 0.00% 0.00% 0.00% 22-Nov-13 20-Jan-14
E3550 ACID CLEANING 15.00% 80% 20% 0.00% 0.00% 0.00% 25-Dec-13 14-Feb-14
4.2.2.6 INSULATION 5.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 22-Nov-13 11-Feb-14
E3560 INSULATION OF PIPING 100.00% 80% 20% 0.00% 0.00% 0.00% 22-Nov-13 11-Feb-14
4.2.3 MECHANICAL 3.00%COMPLETED ACCEPTED 0.00% 0.00% 0.00% 30-Sep-13 24-Feb-14
4.2.3.1 SETTING UP EQUIPMENT ON DECK 65.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 30-Sep-13 12-Feb-14
4.2.3.1.1 SETTING UP EQUIPMENT ON CELLAR DECK 48.41% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 30-Sep-13 28-Jan-14
E3570 SETTING UP CLOSE DRAIN VESSEL V-6400 SKID 29.86% 80% 20% 0.00% 0.00% 0.00% 26-Oct-13 31-Oct-13
E3600 SETTING UP CRUDE HEATER UNIT A-1510 (CELLAR DECK PART III) 21.30% 80% 20% 0.00% 0.00% 0.00% 13-Nov-13 16-Nov-13
E3610 SETTING UP PMCS/SIS/FIELD TRANSMITTER/ FGS (CELLAR DECK PART I) 1.00% 80% 20% 0.00% 0.00% 0.00% 9-Nov-13 18-Nov-13
E3620 SETTING UP CRUDE OIL TRANSFER PUMP P-1310A/B (CELLAR DECK PART II) 8.76% 80% 20% 0.00% 0.00% 0.00% 23-Jan-14 28-Jan-14
E3630 SETTING UP FUEL GAS SKID A-5800 (CELLAR DECK PART III) 1.99% 80% 20% 0.00% 0.00% 0.00% 30-Sep-13 3-Oct-13
E3640 SETTING UP CHEMICAL INJECTION PUMP SKID A-6800 (CELLAR DECK PART III) 0.80% 80% 20% 0.00% 0.00% 0.00% 4-Oct-13 8-Oct-13
E3650 SETTING UP LAUNCHER L-1330 (CELLAR DECK PART III) 10.75% 80% 20% 0.00% 0.00% 0.00% 9-Oct-13 12-Oct-13
E3660 SETTING UP DIESEL ENGINE GENERATOR (DEG) A-7740 (CELLAR DECK PART I) 18.31% 80% 20% 0.00% 0.00% 0.00% 14-Nov-13 19-Nov-13
E3670 SETTING UP GAS ENGINE GENERATOR A-7700 (CELLAR DECK PART I) 0.72% 80% 20% 0.00% 0.00% 0.00% 3-Jan-14 8-Jan-14
E3680 SETTING UP MULTIPHASE FLOW METER A-1210 (CELLAR DECK PART II) 1.11% 80% 20% 0.00% 0.00% 0.00% 5-Oct-13 9-Oct-13
E3690 SETTING UP WELL HEAD CONTROL PANEL WHCP-0100 (CELLAR DECK PART II) 1.63% 80% 20% 0.00% 0.00% 0.00% 10-Oct-13 14-Oct-13
E3700 SETTING UP TEST/ PRODUCTION/ GASLIFT HEADER (CELLAR DECK PART II) 0.28% 80% 20% 0.00% 0.00% 0.00% 15-Oct-13 18-Oct-13
E3710 SETTING UP WASH WATER PUMP P-5110 (CELLAR DECK PART III) 0.48% 80% 20% 0.00% 0.00% 0.00% 4-Jan-14 8-Jan-14
E3720 SETTING UP CO2 VENT SNUFFING A-8600 (VENT BOOM) 0.28% 80% 20% 0.00% 0.00% 0.00% 3-Jan-14 7-Jan-14
E3730 SETTING UP DIESEL TRANSFER PUMP P-6710 (CELLAR DECK PART II) 1.15% 80% 20% 0.00% 0.00% 0.00% 4-Jan-14 8-Jan-14
E3740 SETTING UP NITROGEN BOTTLES A-5900 (CELLAR DECK PART III) 0.60% 80% 20% 0.00% 0.00% 0.00% 1-Oct-13 4-Oct-13
E3750 SETTING UP SCSSV EQUALIZATION PUMP P-6720 (CELLAR DECK PART II) 0.20% 80% 20% 0.00% 0.00% 0.00% 4-Jan-14 8-Jan-14
E3760 SETTING UP PIPELINE DIESEL INJECTION PUMP P-6730 (CELLAR DECK PART II) 0.80% 80% 20% 0.00% 0.00% 0.00% 7-Jan-14 10-Jan-14
4.2.3.1.2 SETTING UP EQUIPMENT ON MAIN DECK 51.59% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 28-Dec-13 12-Feb-14
E3800 SETTING UP MATERIAL HANDLING - PEDESTAL CRANE BD-7301 (MAIN DECK) 18.12% 80% 20% 0.00% 0.00% 0.00% 27-Jan-14 12-Feb-14
E3810 SETTING UP BOOSTER COMPRESSOR A-2410 (MAIN DECK) 30.63% 80% 20% 0.00% 0.00% 0.00% 29-Jan-14 11-Feb-14
E3820 SETTING UP GAS LIFT COMPRESSOR A-0610 (MAIN DECK) 19.42% 80% 20% 0.00% 0.00% 0.00% 29-Jan-14 11-Feb-14
E3830 SETTING UP DIESEL STORAGE TANK T-6700 0.37% 80% 20% 0.00% 0.00% 0.00% 28-Nov-13 29-Nov-13
E3840 SETTING UP WASH WATER STORAGE STANK T-5100A/B 0.60% 80% 20% 0.00% 0.00% 0.00% 30-Nov-13 2-Dec-13
E3850 SETTING UP POTABLE WATER TANK T-5200 0.64% 80% 20% 0.00% 0.00% 0.00% 3-Dec-13 4-Dec-13
E3860 SETTING UP GENERAL PURPOSE TOTE TANK T-5300 0.19% 80% 20% 0.00% 0.00% 0.00% 5-Dec-13 6-Dec-13
E3890 SETTING UP PORTABLE CHEMICAL TRANSFER PUMP P-6835 0.15% 80% 20% 0.00% 0.00% 0.00% 7-Dec-13 9-Dec-13
E3900 SETTING UP HP SEPARATOR SKID A-1020 17.93% 80% 20% 0.00% 0.00% 0.00% 10-Dec-13 11-Dec-13
E3910 SETTING UP LP SEPARATOR SKID A-1010 11.95% 80% 20% 0.00% 0.00% 0.00% 12-Dec-13 13-Dec-13
4.2.3.2 MECHANICAL COMPLETION (TIE-IN) 35.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 16-Oct-13 24-Feb-14
4.2.3.2.1 TIE-IN EQUIPMENT ON CELLAR DECK 48.46% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 16-Oct-13 24-Jan-14
E3940 TIE-IN CLOSE DRAIN VESSEL V-6400 29.80% 80% 20% 0.00% 0.00% 0.00% 8-Nov-13 25-Dec-13
E3950 TIE-IN CRUDE HEATER UNIT A-1510 21.26% 80% 20% 0.00% 0.00% 0.00% 28-Nov-13 2-Jan-14
E3960 TIE-IN PMCS/SIS/FIELD TRANSMITTER/ FGS 0.40% 80% 20% 0.00% 0.00% 0.00% 29-Nov-13 3-Jan-14
E3970 TIE-IN CRUDE OIL TRANSFER PUMP P-1310A/B 0.99% 80% 20% 0.00% 0.00% 0.00% 15-Feb-14 24-Feb-14
E3980 TIE-IN FUEL GAS SKID A-5800 8.74% 80% 20% 0.00% 0.00% 0.00% 25-Nov-13 28-Dec-13

17
E3990 TIE-IN CHEMICAL INJECTION PUMP SKID A-6800 1.99% 80% 20% 0.00% 0.00% 0.00% 16-Nov-13 10-Dec-13
E4000 TIE-IN LAUNCHER L-1330 0.79% 80% 20% 0.00% 0.00% 0.00% 24-Oct-13 14-Dec-13
E4010 TIE-IN DIESEL ENGINE GENERATOR (DEG) A-7740 10.73% 80% 20% 0.00% 0.00% 0.00% 2-Dec-13 12-Dec-13
E4020 TIE-IN GAS ENGINE GENERATOR A-7700 18.28% 80% 20% 0.00% 0.00% 0.00% 14-Jan-14 22-Jan-14
E4030 TIE-IN MULTIPHASE FLOW METER A-1210 0.72% 80% 20% 0.00% 0.00% 0.00% 21-Oct-13 23-Nov-13
E4040 TIE-IN WELL HEAD CONTROL PANEL WHCP-0100 1.11% 80% 20% 0.00% 0.00% 0.00% 25-Oct-13 28-Nov-13
E4050 TIE-IN TEST/ PRODUCTION/ GASLIFT HEADTER 1.63% 80% 20% 0.00% 0.00% 0.00% 30-Oct-13 3-Dec-13
E4060 TIE-IN WASH WATER PUMP P-5110 0.28% 80% 20% 0.00% 0.00% 0.00% 9-Jan-14 16-Jan-14
E4070 TIE-IN CO2 VENT SNUFFING A-8600 0.48% 80% 20% 0.00% 0.00% 0.00% 8-Jan-14 15-Jan-14
E4080 TIE-IN DIESEL TRANSFER PUMP P-6710 0.28% 80% 20% 0.00% 0.00% 0.00% 9-Jan-14 16-Jan-14
E4090 TIE-IN NITROGEN BOTTLES A-5900 1.15% 80% 20% 0.00% 0.00% 0.00% 16-Oct-13 19-Nov-13
E4100 TIE-IN SCSSV EQUALIZATION PUMP P-6720 0.60% 80% 20% 0.00% 0.00% 0.00% 9-Jan-14 16-Jan-14
E4110 TIE-IN PIPELINE DIESEL INJECTION PUMP P-6730 0.79% 80% 20% 0.00% 0.00% 0.00% 11-Jan-14 18-Jan-14
4.2.3.2.2 TIE-IN EQUIPMENT ON MAIN DECK 51.54% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 30-Nov-13 20-Feb-14
E4160 TIE-IN PORTABLE CHEMICAL TRANSFER PUMP P-6835 18.12% 80% 20% 0.00% 0.00% 0.00% 10-Dec-13 20-Dec-13
E4170 TIE-IN HP SEPARATOR SKID A-1020 30.63% 80% 20% 0.00% 0.00% 0.00% 12-Dec-13 23-Dec-13
E4180 TIE-IN LP SEPARATOR SKID A-1010 19.42% 80% 20% 0.00% 0.00% 0.00% 14-Dec-13 25-Dec-13
E4190 TIE-IN MATERIAL HANDLING - PEDESTAL CRANE BD-7301 0.37% 80% 20% 0.00% 0.00% 0.00% 12-Feb-14 20-Feb-14
E4200 TIE-IN BOOSTER COMPRESSOR A-2410 0.60% 80% 20% 0.00% 0.00% 0.00% 11-Feb-14 19-Feb-14
E4210 TIE-IN GAS LIFT COMPRESSOR A-0610 0.64% 80% 20% 0.00% 0.00% 0.00% 11-Feb-14 19-Feb-14
E4220 TIE-IN DIESEL STORAGE TANK T-6700 0.19% 80% 20% 0.00% 0.00% 0.00% 30-Nov-13 13-Dec-13
E4230 TIE-IN WASH WATER STORAGE STANK T-5100A/B 0.15% 80% 20% 0.00% 0.00% 0.00% 3-Dec-13 16-Dec-13
E4240 TIE-IN POTABLE WATER TANK T-5200 17.93% 80% 20% 0.00% 0.00% 0.00% 5-Dec-13 18-Dec-13
E4250 TIE-IN GENERAL PURPOSE TOTE TANK T-5300 11.95% 80% 20% 0.00% 0.00% 0.00% 7-Dec-13 20-Dec-13
4.2.4 INSTRUMENT 9.00% COMPLETED ACCEPTED 0.95% 0.00% 0.95% 11-Jul-13 10-Feb-14
4.2.4.1 FABRICATE INSTRUMENT SUPPORTS 8.00% Mark/Cut Fit Weld Accept 11.86% 0.00% 11.86% 11-Jul-13 26-Aug-13
E4270 FABRICATE SUPPORT FOR FIRE AND GAS SYSTEM 26.00% 15% 40% 30.00% 15% 5.80% 0.00% 5.80% 11-Jul-13 20-Aug-13
E4280 FABRICATE SUPPORT FOR INSTRUMENT EQUIPMENT 11.00% 15% 40% 30.00% 15% 9.97% 0.00% 9.97% 11-Jul-13 20-Aug-13
E4290 FABRICATE SUPPORT FOR TELECOM EQUIPMENT 8.00% 15% 40% 30.00% 15% 0.00% 0.00% 0.00% 11-Jul-13 20-Aug-13
E4300 FABRICATE SUPPORT FOR INSTRUMENT JBs 16.00% 15% 40% 30.00% 15% 40.74% 0.00% 40.74% 11-Jul-13 20-Aug-13
E4310 FABRICATE SUPPORT FOR CABLE TRAY AND TUBING TRAY 36.00% 15% 40% 30.00% 15% 7.60% 0.00% 7.60% 11-Jul-13 20-Aug-13
E4320 FABRICATE SUPPORT FOR BULKEAD 3.00% 15% 40% 30.00% 15% 0.00% 0.00% 0.00% 17-Jul-13 26-Aug-13
4.2.4.2 INSTALLATION OF INSTRUMENT SUPPORTS 11.00% Fit up/ Accept Weld/Accept NDT/Accept 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
E4330 INSTALL SUPPORT FOR FIRE AND GAS SYSTEM 26.00% 50% 35% 15% 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
E4340 INSTALL SUPPORT FOR INSTRUMENT EQUIPMENT 11.00% 50% 35% 15% 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
E4350 INSTALL SUPPORT FOR TELECOM EQUIPMENT 8.00% 50% 35% 15% 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
E4360 INSTALL SUPPORT FOR INSTRUMENT JBs 16.00% 50% 35% 15% 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
E4370 INSTALL SUPPORT FOR CABLE TRAY AND TUBING TRAY 36.00% 50% 35% 15% 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
E4380 INSTALL SUPPORT FOR BULKEAD 3.00% 50% 35% 15% 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
4.2.4.3 TUBING TRAY I CABLE TRAY I LADDER INSTALLATION 17.00% Fit up/ Accept Weld/Accept NDT/Accept 0.00% 0.00% 0.00% 19-Oct-13 21-Dec-13
E4390 INSTALL CABLE LADDER/ TRAY FOR INSTRUMENT 100.00% 50% 35% 15% 0.00% 0.00% 0.00% 19-Oct-13 21-Dec-13
4.2.4.4 CALIBRATE INSTRUMENT 1.00% Accept 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
E4400 CALIBRATE INSTRUMENT EQUIPMENTS 100.00% 100% 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
4.2.4.5 INSTRUMENT EQUIPMENT INSTALLATION 4.00% Fit up Accept 0.00% 0.00% 0.00% 23-Oct-13 22-Jan-14
E4410 INSTALL INSTRUMENT JBs AND BULKEAD 20.00% 85% 15% 0.00% 0.00% 0.00% 29-Oct-13 31-Dec-13
E4420 INSTALL GAUGE EQUIPMENTS 5.00% 85% 15% 0.00% 0.00% 0.00% 6-Dec-13 22-Jan-14
E4430 INSTALL TELECOM EQUIPMENTS 25.00% 85% 15% 0.00% 0.00% 0.00% 23-Oct-13 25-Dec-13
E4440 INSTALL TRANSMITER EQUIPMENTS 20.00% 85% 15% 0.00% 0.00% 0.00% 23-Oct-13 25-Dec-13
E4450 INSTALL FIRE & GAS EQUIPMENTS 30.00% 85% 15% 0.00% 0.00% 0.00% 23-Oct-13 25-Dec-13
4.2.4.6 CABLE PULLING 20.00% Pulling Accept 0.00% 0.00% 0.00% 12-Nov-13 4-Jan-14
E4460 CABLE PULLING FIRE & GAS CABLE (FROM EQUIPMENT TO JB) 25.00% 85% 15% 0.00% 0.00% 0.00% 20-Nov-13 30-Dec-13
E4470 CABLE PULLING MULTICORE CABLE FROM PACKAGES TO E-HOUSE 45.00% 85% 15% 0.00% 0.00% 0.00% 25-Nov-13 4-Jan-14
E4480 CABLE PULLING FOR TELECOM 15.00% 85% 15% 0.00% 0.00% 0.00% 3-Dec-13 25-Dec-13
E4490 CABLE PULLING FOR FIELD INSTRUMENT DEVICES (FROM EQUIPMENT TO JB) 15.00% 85% 15% 0.00% 0.00% 0.00% 12-Nov-13 27-Dec-13
4.2.4.7 DRESSING, GLANDING, TAGGING AND TERMINATION 34.00% Terminate Accept 0.00% 0.00% 0.00% 9-Dec-13 10-Feb-14
E4500 DRESSING, GLANDING FOR MULTICORE CABLE FROM PACKAGES TO E-HOUSE 25.00% 85% 15% 0.00% 0.00% 0.00% 18-Dec-13 28-Jan-14
E4510 DRESSING, GLANDING FOR CABLE FOR TELECOM 45.00% 85% 15% 0.00% 0.00% 0.00% 9-Dec-13 18-Jan-14
E4520 DRESSING, GLANDING FOR FIELD DEVICES (FROM EQUIPMENT TO JB) 15.00% 85% 15% 0.00% 0.00% 0.00% 17-Dec-13 15-Jan-14
E4530 DRESSING, GLANDING FOR FIRE & GAS CABLE (FROM EQUIPMENT TO JB) 15.00% 85% 15% 0.00% 0.00% 0.00% 20-Dec-13 10-Feb-14
4.2.4.8 PULL AND HOOK-UP TUBING 5.00% Pulling Hook-up Accept 0.00% 0.00% 0.00% 26-Dec-13 10-Feb-14
E4540 PULL AN D HOOK-UP TUBING FROM WHCP TO BULKEAD PLATE 40.00% 35% 50% 15% 0.00% 0.00% 0.00% 26-Dec-13 10-Feb-14
E4550 PULL AN D HOOK-UP TUBING FROM PIPING TO INSTRUMENT DEVICES 20.00% 35% 50% 15% 0.00% 0.00% 0.00% 26-Dec-13 10-Feb-14

18
E4560 PULL AN D HOOK-UP TUBING FROM CHEMICAL INJECTION TO PIPING 40.00% 35% 50% 15% 0.00% 0.00% 0.00% 3-Jan-14 25-Jan-14
4.2.5 ELECTRICAL/ HVAC/ Ducting 9.00% COMPLETED ACCEPTED 0.16% 0.00% 0.16% 11-Jul-13 19-Feb-14
4.2.5.1 FABRICATION OF ELECTRICAL SUPPORT 9.00% Mark/Cut Fit Weld Accept 1.80% 0.00% 1.80% 11-Jul-13 7-Sep-13
E4570 FABRICATE SUPPORT FOR LIGHTING SYSTEM 35.00% 15% 40% 30.00% 15% 0.00% 0.00% 0.00% 11-Jul-13 7-Sep-13
E4580 FABRICATE SUPPORT FOR ELECTRICAL JBs 20.00% 15% 40% 30.00% 15% 0.00% 0.00% 0.00% 23-Jul-13 26-Aug-13
E4590 FABRICATE SUPPORT FOR CABLE TRAY/LADDER 45.00% 15% 40% 30.00% 15% 4.00% 0.00% 4.00% 11-Jul-13 7-Sep-13
4.2.5.2 INSTALLATION OF ELECTRICAL SUPPORT 12.00% Mark Fit up Weld Accept 0.00% 0.00% 0.00% 9-Oct-13 11-Dec-13
E4600 INSTALL SUPPORT FOR CABLE TRAY/LADDER 35.00% 15% 40% 30.00% 15% 0.00% 0.00% 0.00% 9-Oct-13 11-Dec-13
E4610 INSTALL SUPPORT FOR LIGHTING SYSTEM 20.00% 15% 40% 30.00% 15% 0.00% 0.00% 0.00% 9-Oct-13 11-Dec-13
E4620 INSTALL SUPPORT FOR ELECTRICAL JBs 45.00% 15% 40% 30.00% 15% 0.00% 0.00% 0.00% 9-Oct-13 11-Dec-13
4.2.5.3 CABLE TRAY I CABLE LADDER INSTALLATION 17.00% Fit up/ Accept Weld/Accept NDT/Accept 0.00% 0.00% 0.00% 15-Oct-13 17-Dec-13
E4630 INSTALL CABLE LADDER/ TRAY FOR ELECTRICAL 100.00% 50% 35% 15% 0.00% 0.00% 0.00% 15-Oct-13 17-Dec-13
4.2.5.4 CALIBRATE ELECTRICAL EQUIPMENT 1.00% Accept 0.00% 0.00% 0.00% 8-Nov-13 6-Jan-14
E4640 CALIBRATE ELECTRICAL EQUIPMENTS 100.00% 100% 0.00% 0.00% 0.00% 8-Nov-13 6-Jan-14
4.2.5.5 ELECTRICAL EQUIPMENT INSTALLATION 5.00% Fit up Accept 0.00% 0.00% 0.00% 25-Oct-13 23-Jan-14
E4650 INSTALL ELECTRICAL JBs 16.00% 85% 15% 0.00% 0.00% 0.00% 25-Oct-13 27-Dec-13
E4660 INSTALL NAVIGATION AID EQUIPMENTS 16.00% 85% 15% 0.00% 0.00% 0.00% 7-Jan-14 13-Jan-14
E4670 INSTALL HEATRACING EQUIPMENTS 26.00% 85% 15% 0.00% 0.00% 0.00% 16-Dec-13 23-Jan-14
E4680 INSTALL SMALL POWER EQUIPMENTS 6.00% 85% 15% 0.00% 0.00% 0.00% 23-Nov-13 27-Dec-13
E4690 INSTALL LIGHTING EQUIPMENTS 36.00% 85% 15% 0.00% 0.00% 0.00% 20-Nov-13 17-Jan-14
4.2.5.6 CABLE PULLING 20.00% Pulling Accept 0.00% 0.00% 0.00% 20-Nov-13 14-Feb-14
E4700 CABE PULLING FOR MAIN EARTHING 3.00% 85% 15% 0.00% 0.00% 0.00% 16-Jan-14 12-Feb-14
E4710 CABE PULLING FOR SKID 25.00% 85% 15% 0.00% 0.00% 0.00% 24-Dec-13 14-Feb-14
E4720 CABE PULLING FOR HELI DECK 9.00% 85% 15% 0.00% 0.00% 0.00% 11-Jan-14 24-Jan-14
E4730 CABE PULLING FOR GENERATOR 14.00% 85% 15% 0.00% 0.00% 0.00% 11-Dec-13 16-Jan-14
E4740 CABE PULLING FOR HEATRACING 14.00% 85% 15% 0.00% 0.00% 0.00% 30-Dec-13 23-Jan-14
E4750 CABE PULLING FOR SMALL POWER 8.00% 85% 15% 0.00% 0.00% 0.00% 20-Nov-13 17-Jan-14
E4760 CABE PULLING FOR LIGHTING 19.00% 85% 15% 0.00% 0.00% 0.00% 5-Dec-13 27-Dec-13
E4770 CABE PULLING FOR BETTERY (FROM E-HOUSE TO) 8.00% 85% 15% 0.00% 0.00% 0.00% 17-Dec-13 27-Dec-13
4.2.5.7 DRESSING, GLANCING, TAGGING AND TERMINATION 34.00% Terminate Accept 0.00% 0.00% 0.00% 11-Dec-13 19-Feb-14
E4780 DRESSING, GLANDING FOR SMALL POWER CABLE 3.00% 85% 15% 0.00% 0.00% 0.00% 14-Jan-14 27-Jan-14
E4790 DRESSING, GLANDING FOR MAIN EARTHING CABLE 25.00% 85% 15% 0.00% 0.00% 0.00% 22-Jan-14 15-Feb-14
E4800 DRESSING, GLANDING FOR SKID CABLE 9.00% 85% 15% 0.00% 0.00% 0.00% 4-Jan-14 19-Feb-14
E4810 DRESSING, GLANDING FOR HELI DECK CABLE 14.00% 85% 15% 0.00% 0.00% 0.00% 17-Jan-14 10-Feb-14
E4820 DRESSING, GLANDING FOR GENERATOR CABLE 14.00% 85% 15% 0.00% 0.00% 0.00% 16-Jan-14 28-Jan-14
E4830 DRESSING, GLANDING FOR HEATRACING CABLE 8.00% 85% 15% 0.00% 0.00% 0.00% 9-Jan-14 29-Jan-14
E4840 DRESSING, GLANDING FOR LIGHTING CABLE 19.00% 85% 15% 0.00% 0.00% 0.00% 11-Dec-13 9-Jan-14
E4850 DRESSING, GLANDING FOR BATTERY (FROM E-HOUSE TO) 8.00% 85% 15% 0.00% 0.00% 0.00% 24-Dec-13 9-Jan-14
4.2.5.8 INSTALL MCT 1.00% Fit up/ Accept Weld/Accept Accept 0.00% 0.00% 0.00% 2-Dec-13 25-Dec-13
E4850 INSTALL MCT 100.00% 50% 35% 15% 0.00% 0.00% 0.00% 2-Dec-13 25-Dec-13
4.2.5.9 INSTALL ERATHING BOSS 1.00% Fit up/ Accept Weld/Accept Accept 0.00% 0.00% 0.00% 9-Jan-14 13-Feb-14
E4850 INSTALL ERATHING BOSS 100.00% 50% 35% 15% 0.00% 0.00% 0.00% 9-Jan-14 13-Feb-14
4.2.6 BLASTING / PAINTING 8.00% Clean/ Blast Paint Inspect/Accept 16.37% 11.07% 5.30% 20-Apr-13 7-Jan-14
4.2.6.1 STRUCTURE STEEL 90.94% Clean/ Blast Paint Inspect/Accept 18.00% 12.00% 6.00% 22-Apr-13 7-Jan-14
E4865 BLASTING/ PRIMER PAINTING PRIMARY STRUCTURE OF CELLAR DECK 6.00% 40.0 20.00% 40 65% 40 15.00% 100.00% 100.00% 0.00% 22-Apr-13 3-May-13
E4870 FINAL BLASTING/ PAINTING CELLAR DECK 31.50% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 13-Aug-13 9-Oct-13
E4885 BLASTING/ PAINTING PRIMARY STRUCTURE OF MAIN DECK 6.00% 40.0 20.00% 40 65% 40 15.00% 100.00% 100.00% 0.00% 4-May-13 20-May-13
E4890 FINAL BLASTING/ PRIMER PAINTING MAIN DECK 29.50% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 22-Oct-13 7-Nov-13
E4920 BLASTING/ PAINTING BRACING PIPES 12.00% 27.0 20.00% 27 65% 27 15.00% 50.00% 0.00% 50.00% 14-Aug-13 29-Aug-13
E4930 BLASTING/ PAINTING VENT BOOM 15.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 31-Dec-13 7-Jan-14
4.2.6.2 PIPING SUPPORTS/SPOOLS 6.88% Clean/ Blast Paint Inspect/Accept 0.00% 2.31% -2.31% 22-Jun-13 18-Dec-13
E4940 BLASTING/ PAINTING PIPE SUPPORTS 22.73% 20.00% 65% 15.00% 0.00% 10.14% -10.14% 22-Jun-13 30-Aug-13
E5350 BLASTING/ PAINTING PIPE SPOOL 77.27% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 23-Aug-13 18-Dec-13
4.2.6.3 PIPING VALVES 0.31% 80% 20% 0.00% 0.00% 0.00% 28-Nov-13 26-Dec-13
E5760 BLASTING/ PAINTING PIPING VALVES 100.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 28-Nov-13 26-Dec-13
4.2.6.4 INSTRUMENT SUPPORTS 0.94% Clean/ Blast Paint Inspect/Accept 0.00% 0.00% 0.00% 21-Aug-13 4-Sep-13
E5770 BLASTING/ PAINTING SUPPORT FOR FIRE AND GAS SYSTEM 18.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 21-Aug-13 28-Aug-13
E5780 BLASTING/ PAINTING SUPPORT FOR INSTRUMENT EQUIPMENT 14.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 21-Aug-13 28-Aug-13
E5790 BLASTING/ PAINTING SUPPORT FOR TELECOM EQUIPMENT 14.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 21-Aug-13 28-Aug-13
E5800 BLASTING/ PAINTING SUPPORT FOR INSTRUMENT JBs 18.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 21-Aug-13 28-Aug-13
E5810 BLASTING/ PAINTING SUPPORT FOR CABLE TRAY AND TUBING TRAY 33.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 21-Aug-13 31-Aug-13
E5820 BLASTING/ PAINTING SUPPORT FOR BULKEAD 3.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 27-Aug-13 4-Sep-13

19
4.2.6.5 ELECTRICAL SUPPORTS 0.94% Clean/ Blast Paint Inspect/Accept 0.00% 0.00% 0.00% 18-Jul-13 14-Sep-13
E5830 BLASTING/ PAINTING SUPPORT FOR LIGHTING SYSTEM 40.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 18-Jul-13 14-Sep-13
E5840 BLASTING/ PAINTING SUPPORT FOR ELECTRICAL JBs 20.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 30-Jul-13 3-Sep-13
E5850 BLASTING/ PAINTING SUPPORT FOR CABLE TRAY/LADDER 40.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 18-Jul-13 14-Sep-13
4.2.7 ARCHITECTURAL 2.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 21-Oct-13 14-Dec-13
E5860 SETTING UP FIRE RATED DOORS 50.00% 80% 20% 0.00% 0.00% 0.00% 29-Nov-13 9-Dec-13
E5880 SETTING UP TEMPORARY SHELTER 50.00% 80% 20% 0.00% 0.00% 0.00% 21-Oct-13 14-Dec-13
4.3 TESTTING & PRE-COMMISSIONING 7.00% 0.00% 0.00% 0.00% 31-Dec-13 28-Feb-14
4.3.1 PROCESS SYSTEM 15.00% COMPLETED 0.00% 0.00% 0.00% 31-Dec-13 26-Feb-14
F1000 100-PROCESS LIQUID 50.00% 100% 0.00% 0.00% 0.00% 31-Dec-13 6-Jan-14
F1010 110-PROCESS GAS 50.00% 100% 0.00% 0.00% 0.00% 19-Feb-14 26-Feb-14
4.3.2 POWER SYSTEM 15.00% COMPLETED 0.00% 0.00% 0.00% 7-Jan-14 20-Feb-14
F1090 510-POWER GENERATION 25.00% 100% 0.00% 0.00% 0.00% 7-Jan-14 17-Jan-14
F1100 520-MAIN POWER DISTRIBUTION 25.00% 100% 0.00% 0.00% 0.00% 18-Jan-14 29-Jan-14
F1110 530-DIRECT CURRENT 25.00% 100% 0.00% 0.00% 0.00% 24-Jan-14 14-Feb-14
F1120 540-MINOR POWER DISTRIBUTION 25.00% 100% 0.00% 0.00% 0.00% 10-Feb-14 20-Feb-14
4.3.3 PROCESS UTILITIES SYSTEM 15.00% COMPLETED 0.00% 0.00% 0.00% 18-Jan-14 27-Feb-14
F1030 230-BLOWDOWN AND RELIEF VENT 30.00% 100% 0.00% 0.00% 0.00% 18-Jan-14 22-Jan-14
F1040 250-PROCESS HEATING 35.00% 100% 0.00% 0.00% 0.00% 19-Feb-14 26-Feb-14
F1050 260-CHEMICAL INJECTION 35.00% 100% 0.00% 0.00% 0.00% 19-Feb-14 27-Feb-14
4.3.4 GENERAL UTILITIES SYSTEM 15.00% COMPLETED 0.00% 0.00% 0.00% 23-Jan-14 18-Feb-14
F1060 310-FUEL & LUBRICATION 30.00% 100% 0.00% 0.00% 0.00% 23-Jan-14 28-Jan-14
F1070 340-HVAC 35.00% 100% 0.00% 0.00% 0.00% 23-Jan-14 10-Feb-14
F1080 350-UTILITY/INSTRUMENT/FUEL GAS 35.00% 100% 0.00% 0.00% 0.00% 11-Feb-14 18-Feb-14
4.3.5 CONTROL SYSTEM 20.00% COMPLETED 0.00% 0.00% 0.00% 23-Jan-14 25-Feb-14
F1130 610-PROCESS CONTROL 30.00% 100% 0.00% 0.00% 0.00% 14-Feb-14 25-Feb-14
F1140 620-ALARM AND SHUTDOWN 35.00% 100% 0.00% 0.00% 0.00% 23-Jan-14 14-Feb-14
F1150 630-FIRE AND GAS DETECTION 35.00% 100% 0.00% 0.00% 0.00% 29-Jan-14 19-Feb-14
4.3.6 TELECOMMUNICATIONS SYSTEM 20.00% COMPLETED 0.00% 0.00% 0.00% 20-Feb-14 25-Feb-14
F1160 710-COMMUNICATION EQUIPMENT 100.00% 100% 0.00% 0.00% 0.00% 20-Feb-14 25-Feb-14
4.3.7 TOPSIDE ONSHORE MCD 0.00% 0.00% 0.00% 0.00% 28-Feb-14 28-Feb-14
F1020 TOPSIDE ONSHORE MCD 100.00% 100% 0.00% 0.00% 0.00% 28-Feb-14 28-Feb-14
4.4 LOAD-OUT AND SEAFASTENING 9.00% 3.50% 3.50% 0.00% 1-Jun-13 10-Mar-14
4.4.1 DRAWINGS 7.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 1-Jun-13 30-Jan-14
G1000 PREPARATION/ SUBMISSION/ APPROVAL DRAWINGS FOR LOAD OUT 50.00% 70% 30% 0.00% 100.00% -100.00% 1-Jun-13 25-Jun-13
G1001 PREPARATION/ SUBMISSION/ APPROVAL DRAWINGS FOR SEAFASTENING 50.00% 1.0 70% 1 30% 100.00% 0.00% 100.00% 3-Jan-14 30-Jan-14
4.4.2 LOAD-OUT BEAM FABRICATION 0.00% COMPLETED ACCEPTED 34.78% 3.25% 31.52% 26-Jun-13 16-Aug-13
A11210 MARK & CUT LOAD-OUT BEAM 15.00% COMPLETED ACCEPTED 70.02% 12.50% 57.52% 26-Jun-13 20-Jul-13
A11220 FIT UP LOAD-OUT BEAM 40.00% COMPLETED ACCEPTED 42.28% 3.45% 38.84% 28-Jun-13 27-Jul-13
A11230 WELDING LOAD-OUT BEAM 30.00% COMPLETED ACCEPTED 19.83% 0.00% 19.83% 3-Jul-13 11-Aug-13
A11240 NDT LOAD-OUT BEAM 15.00% COMPLETED ACCEPTED 9.42% 0.00% 9.42% 8-Jul-13 16-Aug-13
4.4.3 MATERIALS (TONNAGE) 4.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 6-Feb-14 6-Feb-14
G1010 RECEIPT MATERIAL 100.00% 80% 20% 0.00% 0.00% 0.00% 6-Feb-14 6-Feb-14
4.4.4 LOAD-OUT AND POSITIONING 42.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 5-Mar-14 5-Mar-14
G1020 LOAD-OUT AND POSITIONING 100.00% 80% 20% 0.00% 0.00% 0.00% 5-Mar-14 5-Mar-14
4.4.5 SEAFASTENING FABRICATION 17.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 7-Feb-14 10-Mar-14
G1030 MARK & CUT FRAME SEAFASTENING 15.00% 80% 20% 0.00% 0.00% 0.00% 7-Feb-14 20-Feb-14
G1040 FIT UP FRAME SEAFASTENING 40.00% 80% 20% 0.00% 0.00% 0.00% 6-Mar-14 8-Mar-14
G1050 WELDING FRAME SEAFASTENING 30.00% 80% 20% 0.00% 0.00% 0.00% 7-Mar-14 9-Mar-14
G1060 NDT FRAME SEAFASTENING 15.00% 80% 20% 0.00% 0.00% 0.00% 7-Mar-14 10-Mar-14
4.4.6 TIE-DOWN ARRANGEMENTS 30.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 24-Feb-14 10-Mar-14
G1070 TIE- DOWN/ SHIPLOOSE MATERIALS 100.00% 80% 20% 0.00% 0.00% 0.00% 24-Feb-14 10-Mar-14
5 HOOK UP & COMMISSIONING 11.00% 0.00% 0.00% 0.00% 3-Sep-13 18-Jun-14
5.1 ONSHORE PREPARATION ACTIVITIES 15.00% 0.00% 0.00% 0.00% 3-Sep-13 19-Mar-14
5.1.1 PREPARATION HUC PROCEDURES 40.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 3-Sep-13 20-Jan-14
H1010 PREPARE HSE PROCEDURE 25.00% 70% 30% 0.00% 0.00% 0.00% 3-Sep-13 11-Nov-13
H1020 PREPARE QA/QC PROCEDURE 35.00% 70% 30% 0.00% 0.00% 0.00% 3-Sep-13 11-Nov-13
H1030 PREPARE JOB CARDS 15.00% 70% 30% 0.00% 0.00% 0.00% 3-Sep-13 4-Dec-13
H1040 PREPARE PLANNING PROCEDURE 25.00% 70% 30% 0.00% 0.00% 0.00% 5-Dec-13 20-Jan-14
5.1.2 MOBILIZATION MANPOWER, MATERIAL 25.00% Prep/ Submit Accept 0.00% 0.00% 0.00% 14-Feb-14 17-Mar-14
H1050 MOBILIZATION MANPOWER 50.00% 80% 20% 0.00% 0.00% 0.00% 14-Feb-14 17-Mar-14

20
H1060 INSPECTION/PACKING SHIP-LOOSE MATERIAL ON WORK BARGE 50.00% 80% 20% 0.00% 0.00% 0.00% 28-Feb-14 17-Mar-14
5.1.3 MOBILIZATION TOOL & EQUIPMENT 25.00% Prep/ Submit Accept 0.00% 0.00% 0.00% 6-Mar-14 17-Mar-14
H1070 MOBILIZATION HUC TOOL&EQUIPMENT 100.00% 80% 20% 0.00% 0.00% 0.00% 6-Mar-14 17-Mar-14
5.1.4 MOBILIZATION HUC BARGE 10.00% Prep/ Submit Accept 0.00% 0.00% 0.00% 14-Mar-14 19-Mar-14
H1080 MOBILIZATION WORK BARGE TO PVCMS'S JETTY 100.00% 80% 20% 0.00% 0.00% 0.00% 14-Mar-14 19-Mar-14
5.2 OFFSHORE HOOK UP AND COMMISSIONING 80.00% 0.00% 0.00% 0.00% 24-Mar-14 23-Apr-14
5.2.1 HOOK UP 60.00% 0.00% 0.00% 0.00% 24-Mar-14 22-Apr-14
5.2.1.1 HOOK UP STRUCTURE 21.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 24-Mar-14 12-Apr-14
H1110 INSTALL GANWAY 4.00% 80% 20% 0.00% 0.00% 0.00% 24-Mar-14 25-Mar-14
H1120 ERECT TEMPORARY STAIR WAY TO CELLAR DECK & SERVICE PLATFORM 7.00% 80% 20% 0.00% 0.00% 0.00% 25-Mar-14 26-Mar-14
H1130 INSTALL STAIR WAY FROM OPEN& CLOSED DRAIN DECK TO CELLAR DECK 7.50% 80% 20% 0.00% 0.00% 0.00% 26-Mar-14 1-Apr-14
H1135 INSTALL STAIR WAY TO SERVICE PLATFORM 5.50% 80% 20% 0.00% 0.00% 0.00% 3-Apr-14 5-Apr-14
H1145 REMOVE 04 LIFTING PADEYES/ PROTECTION FRAME 11.00% 80% 20% 0.00% 0.00% 0.00% 28-Mar-14 1-Apr-14
H1150 INSTALL DECK PLATES, HANDRAILS 8.00% 80% 20% 0.00% 0.00% 0.00% 1-Apr-14 4-Apr-14
H1160 ERECT SCAFFOLDING FOR CORRECTING FLARE BOOM POSITION 6.00% 80% 20% 0.00% 0.00% 0.00% 4-Apr-14 6-Apr-14
H1170 INSTALL STRUSS ROWS 9.00% 80% 20% 0.00% 0.00% 0.00% 6-Apr-14 8-Apr-14
H1175 INSTALL RISER GUARD 10.00% 80% 20% 0.00% 0.00% 0.00% 8-Apr-14 10-Apr-14
H1180 CUT OFF TEMPORARY SUPPORT OF CRANE 7.00% 80% 20% 0.00% 0.00% 0.00% 1-Apr-14 3-Apr-14
H1190 TOUCH UP PAITING FOR STRUCTURE 12.50% 80% 20% 0.00% 0.00% 0.00% 6-Apr-14 12-Apr-14
H1200 TOUCH UP PAINTING FOR JOINTS OF TOPSIDE'S LEGS TO JACKET 12.50% 80% 20% 0.00% 0.00% 0.00% 27-Mar-14 2-Apr-14
5.2.1.2 INSTALL MECHANICAL ITEMS 2.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 27-Mar-14 31-Mar-14
A11550 SETTING UP/ INSTALL CLOSED DRAIN PUMPS 50.00% 80% 20% 0.00% 0.00% 0.00% 27-Mar-14 29-Mar-14
A11560 SETTING UP/ INSTALL OPEN DRAIN PUMPS 50.00% 80% 20% 0.00% 0.00% 0.00% 29-Mar-14 31-Mar-14
5.2.1.3 HOOK UP PIPING 45.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 25-Mar-14 20-Apr-14
5.2.1.3.1 HOOK UP RISER 15.00% 0.00% 0.00% 0.00% 25-Mar-14 2-Apr-14
H3875 HOOK UP RISER SPOOLS 100.00% 80% 20% 0.00% 0.00% 0.00% 25-Mar-14 2-Apr-14
5.2.1.3.2 HOOK UP FOR FLOWLINE 20.00% 0.00% 0.00% 0.00% 29-Mar-14 13-Apr-14
5.2.1.3.2.1 HOOK UP FOR SLOT 4P 25.00% 0.00% 0.00% 0.00% 29-Mar-14 7-Apr-14
H1290 INSTALL PL PIPE SPOOLS 50.00% 80% 20% 0.90% 0.00% 0.00% 0.00% 29-Mar-14 7-Apr-14
H1310 INSTALL PG PIPE SPOOLS 50.00% 80% 20% 0.00% 0.00% 0.00% 31-Mar-14 7-Apr-14
5.2.1.3.2.2 HOOK UP FOR SLOT 1P 25.00% 0.00% 0.00% 0.00% 31-Mar-14 9-Apr-14
H3885 INSTALL PL PIPE SPOOLS 50.00% 80% 20% 0.00% 0.00% 0.00% 31-Mar-14 9-Apr-14
H3895 INSTALL PG PIPE SPOOLS 50.00% 80% 20% 0.00% 0.00% 0.00% 2-Apr-14 9-Apr-14
5.2.1.3.2.3 HOOK UP FOR SLOT 2P 25.00% 0.00% 0.00% 0.00% 2-Apr-14 11-Apr-14
H3905 INSTALL PL PIPE SPOOLS 50.00% 80% 20% 0.00% 0.00% 0.00% 2-Apr-14 11-Apr-14
H3915 INSTALL PG PIPE SPOOLS 50.00% 80% 20% 0.00% 0.00% 0.00% 4-Apr-14 11-Apr-14
5.2.1.3.2.4 HOOK UP FOR SLOT 3P 25.00% 0.00% 0.00% 0.00% 4-Apr-14 13-Apr-14
H3925 INSTALL PL PIPE SPOOLS 50.00% 80% 20% 0.00% 0.00% 0.00% 4-Apr-14 13-Apr-14
H3935 INSTALL PG PIPE SPOOLS 50.00% 80% 20% 0.00% 0.00% 0.00% 6-Apr-14 13-Apr-14
5.2.1.3.3 HOOK UP FOR OTHER PIPING SYSTEMS 40.00% 0.00% 0.00% 0.00% 31-Mar-14 15-Apr-14
H3945 HOOK UP WP SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 31-Mar-14 5-Apr-14
H3965 HOOK UP DH SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 31-Mar-14 4-Apr-14
H3975 HOOK UP DN SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 5-Apr-14 9-Apr-14
H3985 HOOK UP DC SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 4-Apr-14 8-Apr-14
H3995 HOOK UP WI SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 9-Apr-14 11-Apr-14
H4005 HOOK UP VL SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 8-Apr-14 12-Apr-14
H4015 HOOK UP FD SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 11-Apr-14 15-Apr-14
H4025 HOOK UP UG SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 6-Apr-14 8-Apr-14
H4035 HOOK UP VT SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 11-Apr-14 15-Apr-14
H4045 HOOK UP FD SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 11-Apr-14 15-Apr-14
H4115 HOOK UP FW SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 11-Apr-14 15-Apr-14
H4125 HOOK UP VA SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 8-Apr-14 12-Apr-14
5.2.1.3.4 LEAK TEST PIPING 25.00% 0.00% 0.00% 0.00% 13-Apr-14 20-Apr-14
H4065 LEAK TEST FOR FLOWLINE 50.00% 80% 20% 0.00% 0.00% 0.00% 13-Apr-14 18-Apr-14
H4075 LEAK TEST FOR OTHER PIPING SYSTEM 50.00% 80% 20% 0.00% 0.00% 0.00% 15-Apr-14 20-Apr-14

21
5.2.1.4 HOOK UP ELECTRICAL 7.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 28-Mar-14 22-Apr-14
H1730 INSTALL ELECTRICAL SUPPORT 8.00% 80% 20% 0.00% 0.00% 0.00% 28-Mar-14 1-Apr-14
H1740 INSTALL CABLE TRAY 23.00% 80% 20% 0.00% 0.00% 0.00% 29-Mar-14 2-Apr-14
H1750 INSTALL LIGHTING EQUIPMENT 23.00% 80% 20% 0.00% 0.00% 0.00% 31-Mar-14 4-Apr-14
H1760 UNROLL, GLAND, TERMINATE CABLE FOR LIGHTING 23.00% 80% 20% 0.00% 0.00% 0.00% 4-Apr-14 8-Apr-14
H1770 UNROLL, GLAND, TERMINATE CABLE FOR MAIN EARTHING 9.00% 80% 20% 0.00% 0.00% 0.00% 6-Apr-14 8-Apr-14
H1780 INSTALL HEATRACING 8.00% 80% 20% 0.00% 0.00% 0.00% 9-Apr-14 20-Apr-14
H1790 TESTING 6.00% 80% 20% 0.00% 0.00% 0.00% 20-Apr-14 22-Apr-14
5.2.1.5 HOOK UP INSTRUMENT 20.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 4-Apr-14 20-Apr-14
H1810 HOOK UP INSTRUMENT FOR SLOT 4P 15.00% 80% 20% 0.00% 0.00% 0.00% 4-Apr-14 11-Apr-14
H1820 HOOK UP INSTRUMENT FOR SLOT 1P 25.00% 80% 20% 0.00% 0.00% 0.00% 6-Apr-14 13-Apr-14
H3855 HOOK UP INSTRUMENT FOR SLOT 2P 25.00% 80% 20% 0.00% 0.00% 0.00% 8-Apr-14 15-Apr-14
H3865 HOOK UP INSTRUMENT FOR SLOT 3P 15.00% 80% 20% 0.00% 0.00% 0.00% 10-Apr-14 17-Apr-14
H3868 HOOK UP INSTRUMENT FOR OTHER INSTRUMENT ITEMS 20.00% 80% 20% 0.00% 0.00% 0.00% 11-Apr-14 20-Apr-14
5.2.1.6 TOUCH UP PAINTING/ MARKING 5.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 17-Apr-14 22-Apr-14
H1880 TOUCH UP PAINTING & MARKING 100.00% 80% 20% 0.00% 0.00% 0.00% 17-Apr-14 22-Apr-14
5.2.2 COMMISSIONING 40.00% COMPLETED 0.00% 0.00% 0.00% 3-Apr-14 23-Apr-14
5.2.2.1 PROCESS SYSTEM 15.00% 0.00% 0.00% 0.00% 8-Apr-14 23-Apr-14
H6010 100-PROCESS LIQUID 50.00% 100% 0.00% 0.00% 0.00% 8-Apr-14 13-Apr-14
H6020 110-PROCESS GAS 50.00% 100% 0.00% 0.00% 0.00% 17-Apr-14 23-Apr-14
5.2.2.2 PROCESS UTILITIES SYSTEM 15.00% 0.00% 0.00% 0.00% 12-Apr-14 17-Apr-14
H6030 250-PROCESS HEATING 40.00% 100% 0.00% 0.00% 0.00% 12-Apr-14 17-Apr-14
H6040 260-CHEMICAL INJECTION 40.00% 100% 0.00% 0.00% 0.00% 13-Apr-14 16-Apr-14
H6160 230-BLOWDOWN AND RELIEF VENT 20.00% 100% 0.00% 0.00% 0.00% 12-Apr-14 14-Apr-14
5.2.2.3 GENERAL UTILITIES SYSTEM 15.00% 0.00% 0.00% 0.00% 8-Apr-14 13-Apr-14
H6050 310-FUEL & LUBRICATION 33.0% 100% 0.00% 0.00% 0.00% 8-Apr-14 12-Apr-14
H6060 340-HVAC 33.0% 100% 0.00% 0.00% 0.00% 8-Apr-14 12-Apr-14
H6070 350-UTILITY/INSTRUMENT/FUEL GAS 34.0% 100% 0.00% 0.00% 0.00% 8-Apr-14 13-Apr-14
5.2.2.4 POWER SYSTEM 20.00% 0.00% 0.00% 0.00% 3-Apr-14 8-Apr-14
H6080 510-POWER GENERATION 30.00% 100% 0.00% 0.00% 0.00% 3-Apr-14 8-Apr-14
H6090 520-MAIN POWER DISTRIBUTION 25.00% 100% 0.00% 0.00% 0.00% 3-Apr-14 8-Apr-14
H6100 530-DIRECT CURRENT 25.00% 100% 0.00% 0.00% 0.00% 3-Apr-14 8-Apr-14
H6110 540-MINOR POWER DISTRIBUTION 20.00% 100% 0.00% 0.00% 0.00% 3-Apr-14 8-Apr-14
5.2.2.5 CONTROL SYSTEM 20.00% 0.00% 0.00% 0.00% 5-Apr-14 12-Apr-14
H6120 610-PROCESS CONTROL 35.00% 100% 0.00% 0.00% 0.00% 8-Apr-14 12-Apr-14
H6130 620-ALARM AND SHUTDOWN 30.00% 100% 0.00% 0.00% 0.00% 5-Apr-14 8-Apr-14
H6140 630-FIRE AND GAS DETECTION 35.00% 100% 0.00% 0.00% 0.00% 5-Apr-14 10-Apr-14
5.2.2.6 TELECOMMUNICATIONS SYSTEM 15.00% 0.00% 0.00% 0.00% 10-Apr-14 15-Apr-14
H6150 710-COMMUNICATION EQUIPMENT 100.00% 100% 0.00% 0.00% 0.00% 10-Apr-14 15-Apr-14
TOPSIDE START UP 0.00% 0.00% 0.00% 0.00% 24-Apr-14 24-Apr-14
H6000 TOPSIDE START UP 100.00% 100% 0.00% 0.00% 0.00% 24-Apr-14
5.3 FINAL DOCUMENTATION 5.00% 0.00% 0.00% 0.00% 21-Aug-13 18-Jun-14
5.3.1 EQUIMENT DOSSIER 22.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 21-Aug-13 14-Apr-14
I1000 SUBMISSION EQUIMENT DOSSIER 65.00% 80% 20% 0.00% 0.00% 0.00% 21-Aug-13 18-Feb-14
I1010 APPROVAL EQUIMENT DOSSIER 25.00% 80% 20% 0.00% 0.00% 0.00% 30-Oct-13 28-Feb-14
I1020 FINAL SET EQUIMENT DOSSIER 10.00% 80% 20% 0.00% 0.00% 0.00% 3-Mar-14 14-Apr-14
5.3.2 QA/QC DOCUMENTATION 17.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 13-Nov-13 18-Jun-14
I1030 SUBMISSION QA/QC DOCUMENTATION 65.00% 80% 20% 0.00% 0.00% 0.00% 13-Nov-13 15-May-14
I1040 APPROVAL QA/QC DOCUMENTATION 25.00% 80% 20% 0.00% 0.00% 0.00% 10-Feb-14 4-Jun-14
I1050 FINAL SET QA/QC DOCUMENTATION 10.00% 80% 20% 0.00% 0.00% 0.00% 8-May-14 18-Jun-14
5.3.3 MATERIAL DOCUMENTATION 8.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 13-Nov-13 18-Jun-14
I1060 SUBMISSION MATERIAL DOCUMENTATION 65.00% 80% 20% 0.00% 0.00% 0.00% 13-Nov-13 15-May-14
I1070 APPROVAL MATERIAL DOCUMENTATION 25.00% 80% 20% 0.00% 0.00% 0.00% 10-Feb-14 4-Jun-14
I1080 FINAL SET MATERIAL DOCUMENTATION 10.00% 80% 20% 0.00% 0.00% 0.00% 8-May-14 18-Jun-14
5.3.4 TESTTING & PRECOMMISSIONING DOCUMENTATION 10.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 28-Nov-13 28-Mar-14
I1090 SUBMISSION TESTTING & PRECOMMISSIONING DOCUMENTATION 65.00% 80% 20% 0.00% 0.00% 0.00% 28-Nov-13 18-Feb-14

22
I1100 APPROVAL TESTTING & PRECOMMISSIONING DOCUMENTATION 25.00% 80% 20% 0.00% 0.00% 0.00% 25-Dec-13 28-Feb-14
I1110 FINAL SET TESTTING & PRECOMMISSIONING DOCUMENTATION 10.00% 80% 20% 0.00% 0.00% 0.00% 3-Mar-14 28-Mar-14
5.3.5 DESIGN DATA 3.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 13-Nov-13 18-Jun-14
I1120 SUBMISSION DESIGN DATA 65.00% 80% 20% 0.00% 0.00% 0.00% 13-Nov-13 15-May-14
I1130 APPROVAL DESIGN DATA 25.00% 80% 20% 0.00% 0.00% 0.00% 10-Feb-14 4-Jun-14
I1140 FINAL SET DESIGN DATA 10.00% 80% 20% 0.00% 0.00% 0.00% 8-May-14 18-Jun-14
5.3.6 AS-BUILT DRAWINGS 31.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 21-Aug-13 14-Apr-14
I1150 SUBMISSION AS-BUILT DRAWINGS 65.00% 80% 20% 0.00% 0.00% 0.00% 21-Aug-13 18-Feb-14
I1160 APPROVAL AS-BUILT DRAWINGS 25.00% 80% 20% 0.00% 0.00% 0.00% 30-Oct-13 28-Feb-14
I1170 FINAL SET AS-BUILT DRAWINGS 10.00% 80% 20% 0.00% 0.00% 0.00% 3-Mar-14 14-Apr-14
5.3.7 CLOSE-OUT REPORT 2.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 17-Mar-14 18-Jun-14
I1180 SUBMISSION CLOSE-OUT REPORT 65.00% 80% 20% 0.00% 0.00% 0.00% 17-Mar-14 15-May-14
I1190 APPROVAL CLOSE-OUT REPORT 25.00% 80% 20% 0.00% 0.00% 0.00% 8-May-14 4-Jun-14
I1200 FINAL SET CLOSE-OUT REPORT 10.00% 80% 20% 0.00% 0.00% 0.00% 5-Jun-14 18-Jun-14
5.3.8 SHIPLOOSE LIST 6.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 5-Dec-13 27-Feb-14
I1210 SUBMISSION SHIPLOOSE LIST 65.00% 80% 20% 0.00% 0.00% 0.00% 5-Dec-13 18-Feb-14
I1220 APPROVAL SHIPLOOSE LIST 25.00% 80% 20% 0.00% 0.00% 0.00% 16-Jan-14 24-Feb-14
I1230 FINAL SET SHIPLOOSE LIST 10.00% 80% 20% 0.00% 0.00% 0.00% 13-Feb-14 27-Feb-14
5.3.9 NDT RADIOGRAPHIC FILMS 1.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 11-Dec-13 18-Jun-14
I1240 SUBMISSION NDT RADIOGRAPHIC FILMS 65.00% 80% 20% 0.00% 0.00% 0.00% 11-Dec-13 15-May-14
I1250 APPROVAL NDT RADIOGRAPHIC FILMS 25.00% 80% 20% 0.00% 0.00% 0.00% 24-Feb-14 4-Jun-14
I1260 FINAL SET NDT RADIOGRAPHIC FILMS 10.00% 80% 20% 0.00% 0.00% 0.00% 8-May-14 18-Jun-14

23
ATTACHMENT 9
Sub-contracting Plan
DMDP-A DRILLING PLATFORM
EPCC FOR DMDP-A DRILLING PLATFORM
SUB-CONTRACTING PLAN (TOPSIDE)

No Sub-contracting Service Issue RFQ TBE CBE LOI PO Mobilization Remark

1 Non-destructive service 9-Mar-13 30-Mar-13 9-Apr-13 13-Apr-13 20-Apr-13 6-May-13

2 Heat treatment Service 9-Mar-13 30-Mar-13 9-Apr-13 13-Apr-13 20-Apr-13 6-May-13

3 Insulation Service 25-Jul-13 15-Aug-13 25-Aug-13 1-Sep-13 8-Sep-13 31-Oct-13

4 Bolt tensioning & Leak testing Service 16-Sep-13 7-Oct-13 17-Oct-13 24-Oct-13 31-Oct-13 18-Nov-13

5 Weighing & Load out Service 24-Oct-13 14-Nov-13 24-Nov-13 1-Dec-13 8-Dec-13 25-Dec-13
ATTACHMENT 10
Payment Schedule
DMDP-A DRILLING PLATFORM
EPCC FOR DMDP-A DRILLING PLATFORM

PAYMENT SCHEDULE

Committed Value Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14

ENGINEERING
1 1,564,686 - 62,587.44 641,521.26 704,108.70 156,468.60 - - - - - - -
(DETAIL ENGINEERING)

ENGINEERING
2 78,234 - 3,129.36 32,075.94 35,205.30 7,823.40 - - - - - - - - - - - - - -
(MANAGERMENT FEE)

3 PROCUREMENT 11,746,178 978,848.17 978,848.17 978,848.17 978,848.17 978,848.17 978,848.17 978,848.17 978,848.17 978,848.17 978,848.17 978,848.17 978,848.17

4 FABRICATION (JACKET) 9,077,721 - 363,108.84 1,497,823.97 953,160.71 771,606.29 1,225,492.34 1,588,601.18 2,677,927.70 - - - - - - - - - - -

5 FABRICATION (TOPSIDES) 17,789,257 - 711,570.28 1,838,223.22 948,760.37 948,760.37 592,975.23 770,867.80 592,975.23 592,975.23 770,867.80 2,371,900.93 1,660,330.65 1,482,438.08 592,975.23 - - 2,134,710.84 889,462.85 889,462.85

6 HUC 4,605,476 - 184,219.04 46,054.76 - - - - - - - - - - - - - 2,993,559.40 690,821.40 690,821.40

7 PROVISIONAL SUM COST PLUS 7,249,263 604,105.26 604,105.26 604,105.26 604,105.26 604,105.26 604,105.26 604,105.26 604,105.26 604,105.26 604,105.26 604,105.26 604,105.26

SUB-TOTAL 52,110,815 - 1,324,615 5,638,653 4,224,189 3,467,612 3,401,421 3,942,422 4,853,856 2,175,929 2,353,821 3,954,854 3,243,284 3,065,392 2,175,929 - - 5,128,270 1,580,284 1,580,284

VAT 10% 5,211,081.51 - 132,461.50 563,865.26 422,418.85 346,761.21 340,142.10 394,242.24 485,385.64 217,592.87 235,382.12 395,485.44 324,328.41 306,539.15 217,592.87 - - 512,827.02 158,028.43 158,028.43

TOTAL 57,321,896.60 - 1,457,076.46 6,202,517.83 4,646,607.35 3,814,373.29 3,741,563.09 4,336,664.64 5,339,241.99 2,393,521.52 2,589,203.35 4,350,339.79 3,567,612.49 3,371,930.66 2,393,521.52 - - 5,641,097.26 1,738,312.68 1,738,312.68
DMDP-A DRILLING PLATFORM
EPCC FOR DMDP-A DRILLING PLATFORM

Progress Cummulative Progress Payment S-curve Plan Progress Payment Actual Progress Payment

100.00%

90.00%

80.00%

70.00%

60.00%

50.00%

40.00%

30.00%

20.00%

10.00%

0.00%

13-Sep-13

14-Feb-14

14-Mar-14

14-Sep-14
13-Apr-13

13-Aug-13

13-Oct-13

14-Apr-14

14-Aug-14
13-Nov-13
4-Feb-13

13-Jun-13

13-Jul-13

14-Jan-14

14-Jun-14

14-Jul-14
13-Dec-13
13-May-13

14-May-14
No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
13-May-13

14-May-14
14-Mar-14
13-Nov-13
13-Aug-13

14-Aug-14
13-Dec-13
13-Sep-13

14-Feb-14

14-Sep-14
13-Apr-13

14-Apr-14
13-Jun-13

13-Oct-13

14-Jun-14
14-Jan-14
13-Jul-13

14-Jul-14
4-Feb-13

Period

Plan Detail Engineering 4.00% 41.00% 45.00% 10.00%


1
Actual Detail Engineering
Plan Engineering Managerment fee 4.00% 41.00% 45.00% 10.00%
2
Actual Engineering Managerment fee
Plan Procurement 0.00% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33%
3
Actual Procurement
Plan Fabrication Jacket 4.00% 16.50% 10.50% 8.50% 13.50% 17.50% 29.50%
4
Actual Fabrication Jacket
Plan Fabrication Topsides 4.00% 10.33% 5.33% 5.33% 3.33% 4.33% 3.33% 3.33% 4.33% 13.33% 9.33% 8.33% 3.33% 12.00% 5.00% 5.00%
5
Actual Fabrication Topsides
Plan HUC 4.00% 1.00% 65.00% 15.00% 15.00%
6
Actual HUC
Plan Provisional Sum Cost Plus 0.00% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33%
7
Actual Provisional Sum Cost Plus
Plan Progress Payment 0.00% 2.54% 13.36% 21.47% 28.12% 34.65% 42.22% 51.53% 55.71% 60.22% 67.81% 74.04% 79.92% 84.09% 84.09% 84.09% 93.93% 96.97% 100.00%
8
Actual Progress Payment