1.3.1 Level 1 (Single Line) Barchart
1.3.1 Level 1 (Single Line) Barchart
REVISION: 0
TOPSIDE
REVISION LIST
REVISION: 0
TOPSIDE PAGE 1 OF 21
TABLE OF CONTENTS
1. PURPOSE 2
2. SCOPE 2
3. REFERENCES 2
4. DEFINITIONS 2
5. PROCEDURE 4
5.2 General 5
5.3 Responsibility 5
6. SPECIAL REQUIREMENTS 21
7. RECORDS 21
ATTACHMENT
REVISION: 0
TOPSIDE PAGE 2 OF 21
1. PURPOSE
This procedure is developed to provide an auditable and reliable method for planning,
measuring project progress and monitoring and updating project schedule of the WORK as
required by EPCC Contract of Diamond project.
2. SCOPE
Regarding to the planning and scheduling of EPCC scope of Diamond Drilling Platform,
EPCC Contractor will develop the planning package of Jacket and Topside. The planning
package for Jacket was issued in April 2013. The planning package for Topside is developed
in this procedure. The scope of this procedure covers all activities from the initial Contract
Award up to Start up of Diamond Topside. This procedure will be used as reference to all
parties involved in executing the project meeting the project MCD and Start-up date which is
stated in Exhibit II of the Contract. The scope of work shall cover “Engineering, Procurement,
Construction and Commissioning” of Diamond Topside for Diamond Drilling Platform
Development Project.
3. REFERENCES
4. DEFINITIONS
REVISION: 0
TOPSIDE PAGE 3 OF 21
CPN (Critical Path A time related milestone and activity logic network that is
Network): developed with the Primavera.
Level 1 (Project A time scaled bar-chart indicating the major time blocks allocated
Master Schedule): to the major project contract packages. This schedule is
developed and controlled by PCVL Planner / Scheduler and will
not be revised without the approval of the PCVL Project Manager
Level 2 (Contract The Level 2 Contract Schedule is the link between PCVL’s and
Schedule) Contractor’s planning and scheduling. This level contains all key
activities and milestones.
Duration: The Time taken for an activity to complete its work or task in terms
of days.
EF (Early Finish): The earliest time an activity can finish starting from its ES and
completed within the specified duration.
LS (Late Start): The latest time an activity can start without delaying the scheduled
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02
REVISION: 0
TOPSIDE PAGE 4 OF 21
completion.
TF (Total Float): The amount of time (in days) an activity can be delayed or
deferred without affecting the project scheduled completion date.
Critical Path: Activities that must be started and completed on their ES and EF
for the project to complete within the scheduled duration. These
are activities with total float of Zero day and they are on the
longest duration in the network.
Milestone: An event selected for its importance in the project; achievement of
the planned milestone dates is a key management indicator of
progress on the project.
5. PROCEDURE
REVISION: 0
TOPSIDE PAGE 5 OF 21
5.2 General
The overall plan is generated based on agreed dates from various relevant department
i.e Engineering, Procurement, Contract, Construction, QA/QC and Pre-commissioning
Team.
The target plan for all activities are presented in the form of bar chart, S-curve and
critical network and support by histogram.
Once approved, this procedure will be issued to all relevant departments to follow. The
approved procedure will be a basis for developing progress measurement format,
milestone progress claims and all project progress reports.
5.3 Responsibility
The Project Planning Department is the custodian of this document and is responsible
for its review and reissue and for ensuring compliance with its contents.
It is responsibility of all distributed persons to ensure the most current revision of this
document is available at the work place and that the documents referenced in it are
applied to all aspects of the project.
This document will be subject to regular review and will be updated to reflect any
necessary changes.
The recipient of this document is responsible for distributing the procedure to other
parties working under his / her supervision to ensure the procedure is implemented by
all parties involved.
The Project Planning Engineer will report to the Planning Manager who is in turn
reports to the Project Manager. The Planning Manager is responsible for checking all
planning information prior to submitting to PCVL.
Issue of the Contract Schedule to all groups responsible for developing the
detailed schedule.
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02
REVISION: 0
TOPSIDE PAGE 6 OF 21
Update the actual progress of project against plan progress to support PMT
controlling and monitoring the project schedule.
CPN network is then drawn indicating the preceding activity (PA), the succeeding
activity (SA), the activity description (AD), the duration (DU) and the manpower
(resource).The network uses the precedence method of activity linking to establish the
project interdependencies across the major contributors.
The interdependencies will be based on the required hand over dates of such items as
drawings, materials or of physical access, collectively known as deliverables, which
allows the subsequent activities to continue within the project objectives. When it has
been proved that the defined interdependencies have been met within the individual
network sections of the project, the sections will be merged by activity constraint links
to form an integrated project network.
Through analysis of the integrated network, the critical path of the project will be
identified together with the total float on non-critical items. At the time of analysis all
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02
REVISION: 0
TOPSIDE PAGE 7 OF 21
required project milestones will be imposed to ensure that the project targets are being
maintained.
The schedule is structured in accordance with the project WBS and all activities in the
CBS will be assigned a WBS code that will allow for roll up to each and every WBS
level. The planning system contains the following WBS levels:
Level 1 Overall
Level 3 Phases
Level 2 Work Packs divides the scope of work into the following elements:
Each Work Pack is detailed by activity using the following activity codes:
C – Engineering.
D – Procurement.
E – Onshore Fabrication.
F – Testing& Pre-commissioning.
Activities Codes assigned for all activities are in line with the requirements of PCVL
Specification for Work Breakdown Structure. Each activity will be assigned at least four
(4) activity codes such as WP (Work pack code), PHAS (Phase code), AREA (Area
code) and DISC (Discipline code). Base on these activity codes, Planning Engineer
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02
REVISION: 0
TOPSIDE PAGE 8 OF 21
can easily identify and export all activities of the work scope and after that, the
progress will be updated for these activities base on the progress measurement
system. Finally, these activities will be imported back into the CSB. The CSB will be
resource loaded to allow the progress S-curves and progress information to be
generated by Primavera in line with the requirements of the Contract and Client
Planning and Progress Measurement Specification.
The Work activities shall be developed to the level 4 details, such that the activities
required to execute the work can be monitored on daily basis. The Level 4 schedule
shall clearly identify all the detailed activities along with all of the milestones in the
Contract. The detailed activities shall all be weighted. The Level 4 detailed network
shall also clearly identify and / or allow time for PCVL review activities. The activities in
respect of project management, supervision, planning administration and quality
assurance shall be shown as separate “hammock” activities without a specified
duration. Each activity in the network shall show as a minimum, the following:
Activity number;
Activity description;
Planned activity duration taking into account holiday, facility shutdowns and
the like;
Early / Late Start & Finish dates;
Total float;
Actual start, actual finish dates;
Percent Complete.
The project calendar adopted shall be based on a normal working hours of eight (8)
hours per day and six (6) days per week, except that for Load out and Sea-fastening
24 hours per day and seven (7) calendar working days per week is adopted. All
approved public holidays and Sundays are observed as holidays in the project
calendar except for Load out and Sea-fastening. See attachment 3.
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02
REVISION: 0
TOPSIDE PAGE 9 OF 21
REVISION: 0
TOPSIDE PAGE 10 OF 21
REVISION: 0
TOPSIDE PAGE 11 OF 21
Project Director/
Proposal Group Project Planning
Manager
Proposal group to Project planning to
Contributing groups
distribute all proposal issue the contract
will (each) generate a
document to all level 2 schedule to
schedule to maintain
contributing each operating
the project requirement
groups group
Ability and commitment
Level 2 schedule
schedule
Level 3 working
Individual schedule
schedule
Update the schedule if Operating groups
required to issue an
information list
Information list
Operating groups to revise
following project requirements Operating groups
to submit their
schedule to project
planning for
integration
No Yes Project manager
to authorize a
compromise or
corrective action
Level 2:
- Application
- Usability
- Timing
Submit Level 3:
integrated - Application
schedule to - Usability
PCVL - Timing
REVISION: 0
TOPSIDE PAGE 12 OF 21
It is understood that the weightage distribution will be used for the Diamond project
only. It has been discussed and agreed before applying. The CONTRACTOR shall use
the weightage given to develop Progress Measurement Format which is a basis for
identifying, planning and monitoring the actual work progress. See attachment 8 –
Progress Measurement Format.
The activities description and weightage assigned for identifying, planning and
monitoring the work progress is divided into three (3) parts:
REVISION: 0
TOPSIDE PAGE 13 OF 21
3 Construction 43.00%
4 Hook up and
11.00%
Commissioning
100.00%
Note: The weightage of Engineering, Procurement, Fabrication and Hock up &
Commissioning (HUC) are in accordance with their Contract’s value.
Topside
1 Front end activities and 20.00%
mobilization
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02
REVISION: 0
TOPSIDE PAGE 14 OF 21
Topside
1 Onshore Preparation 15.00%
2 Offshore Hook up and 80.00%
Commissioning
3 Final documentation 5.00%
100.00%
5.6.4 Weightage for Level 3 Activities
Level 3 activities give a detailed breakdown of Level 2 components. Weightages are
assigned in accordance with the quantity of work required for that activity:
5.6.4.1 Weightage Assignment for Engineering.
Engineering level 3 activities are sub-grouped as AFC, Post-AFC, shop drawings,
material take-off (MTO) and procedures with the weightage assigned as follows:
Topside
1. Detail Engineering 50.00%
1.1 AFC 70.00%
1.2 Post - AFC 30.00%
2. Construction Engineering 50.00%
2.1 Shop Drawings 83.00%
i) Structural 32.00%
ii) Piping/Plumbing
28.00%
Mechanical
iii) Electrical 9.00%
iv) Instrument 10.00%
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02
REVISION: 0
TOPSIDE PAGE 15 OF 21
v) HVAC/Ducting 2.00%
vi) Architectural 2.00%
2.2 Material Take-Off (MTO) 13.00%
i) Structural 2.00%
ii) Piping/Plumbing 2.00%
iii) Mechanical 2.00%
iv) Electrical 2.00%
v) Instrument 2.00%
vi) HVAC/Ducting 1.00%
vii) Architectural 1.00%
viii) Others (Paint, etc.) 1.00%
2.3 Procedures 4.00%
i) Procedures 4.00%
100.00%
5.6.4.2 Weightage Assignment for Procurement
For material procurement, the weightage adopted at Level 3 will essentially be
based on the estimated man-hours for the various tasks/activities such as bidding,
evaluation, meetings, expediting, inspection receipt and acceptance to complete
the identified procurement process, i.e. Issued RFQ, Issued P.O. Material Receipt
and Acceptance, etc.. The weightage assigned are sub-grouped into two (2)
categories:
Topside
CONTRACTOR Supplied Materials 81.00%
i) Structural Steel 15.00%
ii) Piping, Fitting & Valves 20.00%
iii) Mechanical Items/ 16.00%
Equipment
iv) Electrical 10.00%
v) Instrument Items 11.00%
vi) HVAC/Ducting 3.00%
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02
REVISION: 0
TOPSIDE PAGE 16 OF 21
Topside
Mobilization of Project
i) 9.00%
Management Team
ii) Project planning and monitoring
5.00%
format
iii) Yard Preparation 15.00%
REVISION: 0
TOPSIDE PAGE 17 OF 21
Topside
i) Structural 50.00%
ii) Piping/ Plumbing 19.00%
v) Instrument 8.00%
100.00%
Topside
i) Drawings 7.00%
100.00%
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02
REVISION: 0
TOPSIDE PAGE 18 OF 21
100.00%
100.00%
Topside
i) Equipment Dossier 22.00%
REVISION: 0
TOPSIDE PAGE 19 OF 21
100.00%
At the commencement of the project and prior to the development of the Level 3
schedule, a “60 days schedule” is prepared and issued to plan in detail all works
performed within that period by discipline. This schedule is updated weekly and used
for control until the level 3 schedule and the engineering and procurement progress
measurements are implemented.
Resource Loading
The detail schedule shall be fully resource loaded. Then, the project S-curves and
Manpower histogram will be generated. These S-curves and Manpower histogram will
be updated and monitoring weekly.
The CSB will be maintained on a day to day basis with details being incorporated as
and when they become available along with the re-allocating of resource loadings /
weightings from the higher level activities to the lower level activities.
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02
REVISION: 0
TOPSIDE PAGE 20 OF 21
Updating
The Document Controller will record the status of engineering deliverables in the
Document Register Database on a continuous basis and provide the Planning
Engineer with the status summary for deliverable based engineering activities on a
weekly basis.
Engineering Coordinator will provide the Planning Engineer with the status update for
non-deliverable bases engineering activities on a weekly basis.
The Construction Manager will provide the required progress information regarding to
Onshore Fabrication activities to the Planning Engineer on a daily basis.
For updating the CSB, the Planning Engineer will extract the dates from these Level 3
schedule, or base on the progress measurement system to update progress for each
activity and then all activities will imported to the Overall CSB level 3 – schedule base
on the activity ID that was assigned for each activity. This schedule shall be updated
and reissued every two (2) weeks using a “time now” line to emphasize progress
achieved, then Planning Engineer will analysis and issue a “two weeks look ahead”
control schedule for every updating period.
The Planning Engineer shall be responsible for this task. He shall liaise with all
concerned departments for information required for the preparation of weekly / monthly
progress report.
All concerned departments shall furnish their respective works status to the Planning
Engineer on the weekly/ monthly cut-off date for compilation. The weekly cutoff date is
every Friday. The monthly cut-off date is on 25th every month. PVC-MS shall issue the
Weekly Report within Tuesday every week and issue Monthly Reports on first Tuesday
of the following month to PCVL Representative.
PROCEDURE NO.:
PLANNING PACKAGE
PSP-DMDP-A-T02
REVISION: 0
TOPSIDE PAGE 21 OF 21
The Planning Engineer shall update the Level 4 progress in the spread sheet. The
calculated Level 4 progress percentage shall then be entered onto the CPN together
with actual start date and actual finish date of the activities. The percentage
completion of each activity will be calculated in accordance with particular
measurement factor stipulated in “Progress Measurement Format” as per
attachment 8.
Upon completion of the weekly updating, the Planning Engineer shall re-analyze the
CPN and prepare the weekly progress report. The analyzing schedule include the
following:
- Planned progress percentage vs. actual progress percentage for each of the major
work break-up as given in the progress report.
The Project Manager shall then be advised on any delay or potential delays. The root
cause of delays or potential delays shall be identified and the recommended remedial
actions proposed shall be included in the progress report. Consequently, appropriate
instructions will be transferred from Project Manager to specific relevant disciplines for
immediately resolving the problems. Planning Engineer then is responsible for
recording and reporting the performance of each discipline as assigned.
The Project Manager shall review the compiled progress reports prior to the
submission to PCVL for review and approval.
PVC-MS Planner will once a month meet with PCVL Planner to discuss the update
such as progress schedule, progress monitoring, etc.
Schedule Revisions
If during the course of the project both Client and Contractor agree that the CSB no
longer contains the proper relationship to the current status of the project, a schedule
re-baseline will take place and the re-baseline will become the revised CSB. However,
changes to Milestones will only be by Changer Oder Authorizations.
6. SPECIAL REQUIREMENTS
7. RECORDS
ATTACHMENT
ATTACHMENT 1
Project Organization Chart
ATTACHMENT 2
Fabrication Sequence & Yard Layout
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
PETROLEUM EQUIPMENT ASSEMBLY
& METAL STRUCTURE J.S.C
ATTACHMENT 3
Project’s Calendar and Report
1. REPORT
Monthly
Contractor Weekly Cut- Weekly Report Contractor Monthly Monthly Report
Week Report
off Delivered to Company Cut-off Delivered to Company
No
Weekly
Project
Report Day Date Day Date Day Date Day Date
week
No
1 1 Friday 22-Feb-13 Tuesday 26-Feb-13
2 2 Friday 1-Mar-13 Tuesday 5-Mar-13
3 3 Friday 8-Mar-13 Tuesday 12-Mar-13
4 4 Friday 15-Mar-13 Tuesday 19-Mar-13
5 5 Friday 22-Mar-13 Tuesday 26-Mar-13
6 6 Friday 29-Mar-13 Tuesday 2-Apr-13 1 Friday 29-Mar-13 Tuesday 2-Apr-13
7 7 Friday 5-Apr-13 Tuesday 9-Apr-13
8 8 Friday 12-Apr-13 Tuesday 16-Apr-13
9 9 Friday 19-Apr-13 Tuesday 23-Apr-13
10 10 Friday 26-Apr-13 Tuesday 30-Apr-13 2 Friday 26-Apr-13 Thusday 2-May-13
11 11 Friday 3-May-13 Tuesday 7-May-13
12 12 Friday 10-May-13 Tuesday 14-May-13
13 13 Friday 17-May-13 Tuesday 21-May-13
14 14 Friday 24-May-13 Tuesday 28-May-13
15 15 Friday 31-May-13 Tuesday 4-Jun-13 3 Friday 31-May-13 Tuesday 4-Jun-13
16 16 Friday 7-Jun-13 Tuesday 11-Jun-13
17 17 Friday 14-Jun-13 Tuesday 18-Jun-13
18 18 Friday 21-Jun-13 Tuesday 25-Jun-13
19 19 Friday 28-Jun-13 Tuesday 2-Jul-13 4 Friday 28-Jun-13 Tuesday 2-Jul-13
20 20 Friday 5-Jul-13 Tuesday 9-Jul-13
21 21 Friday 12-Jul-13 Tuesday 16-Jul-13
22 22 Friday 19-Jul-13 Tuesday 23-Jul-13
23 23 Friday 26-Jul-13 Tuesday 30-Jul-13 5 Friday 26-Jul-13 Tuesday 30-Jul-13
24 24 Friday 2-Aug-13 Tuesday 6-Aug-13
25 25 Friday 9-Aug-13 Tuesday 13-Aug-13
26 26 Friday 16-Aug-13 Tuesday 20-Aug-13
27 27 Friday 23-Aug-13 Tuesday 27-Aug-13
28 28 Friday 30-Aug-13 Tuesday 3-Sep-13 6 Friday 30-Aug-13 Tuesday 3-Sep-13
29 29 Friday 6-Sep-13 Tuesday 10-Sep-13
30 30 Friday 13-Sep-13 Tuesday 17-Sep-13
31 31 Friday 20-Sep-13 Tuesday 24-Sep-13
32 32 Friday 27-Sep-13 Tuesday 1-Oct-13 7 Friday 27-Sep-13 Tuesday 1-Oct-13
33 33 Friday 4-Oct-13 Tuesday 8-Oct-13
34 34 Friday 11-Oct-13 Tuesday 15-Oct-13
35 35 Friday 18-Oct-13 Tuesday 22-Oct-13
36 36 Friday 25-Oct-13 Tuesday 29-Oct-13 8 Friday 25-Oct-13 Tuesday 5-Nov-13
37 37 Friday 1-Nov-13 Tuesday 5-Nov-13
38 38 Friday 8-Nov-13 Tuesday 12-Nov-13
39 39 Friday 15-Nov-13 Tuesday 19-Nov-13
40 40 Friday 22-Nov-13 Tuesday 26-Nov-13
41 41 Friday 29-Nov-13 Tuesday 3-Dec-13 9 Friday 29-Nov-13 Tuesday 3-Dec-13
42 42 Friday 6-Dec-13 Tuesday 10-Dec-13
43 43 Friday 13-Dec-13 Tuesday 17-Dec-13
44 44 Friday 20-Dec-13 Tuesday 24-Dec-13
45 45 Friday 27-Dec-13 Tuesday 31-Dec-13 10 Friday 27-Dec-13 Tuesday 31-Dec-13
46 46 Friday 3-Jan-14 Tuesday 7-Jan-14
47 47 Friday 10-Jan-14 Tuesday 14-Jan-14
48 48 Friday 17-Jan-14 Tuesday 21-Jan-14
49 49 Friday 24-Jan-14 Tuesday 28-Jan-14
50 50 Wednesday 29-Jan-14 Wednesday 5-Feb-14 11 Wednesday 29-Jan-14 Wednesday 5-Feb-14
51 51 Friday 7-Feb-14 Tuesday 11-Feb-14
52 52 Friday 14-Feb-14 Tuesday 18-Feb-14
53 53 Friday 21-Feb-14 Tuesday 25-Feb-14
54 54 Friday 28-Feb-14 Tuesday 4-Mar-14 12 Friday 28-Feb-14 Tuesday 4-Mar-14
55 55 Friday 7-Mar-14 Tuesday 11-Mar-14
56 56 Friday 14-Mar-14 Tuesday 18-Mar-14
57 57 Friday 21-Mar-14 Tuesday 25-Mar-14
58 58 Friday 28-Mar-14 Tuesday 1-Apr-14 13 Friday 28-Mar-14 Tuesday 1-Apr-14
EPCC OVERALL SCHEDULE (TOPSIDE)
CRITICAL PATH NETWORK
Activity ID Activity Name Original Start Finish 2013 2014
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
359 01-Feb-13 24-Apr-14 01-Feb-13 24-Apr-14
DMDP-A OVERALL EPCC SCHEDULE TOPSIDE
333 04-Feb-13 24-Mar-14 04-Feb-13 24-Mar-14
PROJECT MILESTONE
GENERAL 0 04-Feb-13 04-Feb-13 04-Feb-13 04-Feb-13
A1000 LETTER OF AWARD ISSUED BY PCVL 0 04-Feb-13*
LETTER OF AWARD ISSUED BY PCVL
FABRICATION 223 01-Jun-13 28-Feb-14 01-Jun-13 28-Feb-14
A1005 START DATE FOR FABRICATION 0 01-Jun-13*
START DATE FOR FABRICATION
A1010 FINISH DATE FOR FABRICATION (MCD) 0 28-Feb-14*
FINISH DATE FOR FABRICATION (MCD)
LOAD OUT AND SEAFASTENING 0 10-Mar-14 10-Mar-14 10-Mar-14 10-Mar-14
A1020 FINISH DATE FOR LOAD OUT AND SEAFASTENING 0 10-Mar-14*
FINISH DATE FOR LOAD OUT AND SEAFASTENING
HOOK-UP AND COMMISSIONIN G (HUC ) 0 24-Mar-14 24-Mar-14 24-Mar-14 24-Mar-14
H4105 START OFFSHORE HUC 0 24-Mar-14*
START OFFSHORE HUC
ENGINEERING 0
DETAILED ENGINEERING 0
AFC STAGE 0
POST-AFC STAGE 0
SHOP DRAWINGS 0
STRUCTURAL 0
PIPING/PLUMBING MECHANICAL 0
ELECTRICAL 0
INSTRUMENT 0
HVAC/DUCTING 0
ARCHITECTURAL 0
MATERIAL TAKE-OFF (MTO) 0
STRUCTURAL 0
PIPING/PLUMBING 0
MECHANICAL 0
ELECTRICAL 0
INSTRUMENT 0
ARCHITECTURAL 0
HVAC/DUCTING 0
OTHER MATERIAL 0
PROCEDURES 0
291 01-Feb-13 29-Jan-14 01-Feb-13 29-Jan-14
PROCURMENT
PCVL-SUPPLIED MATERIALS 291 01-Feb-13 29-Jan-14 01-Feb-13 29-Jan-14
STRUCTURAL STEEL (ETA) 0
MECHANICAL ITEMS/EQUIMENT (ETA) 291 01-Feb-13 29-Jan-14 01-Feb-13 29-Jan-14
MATERIAL HANDLING - PEDESTAL CRANE 244 01-Feb-13 23-Jan-14 01-Feb-13 23-Jan-14
D1010 DELIVERY ON SITE MATERIAL HANDLING - PEDESTAL CRANE BD-7301 (MAIN DECK) 244 01-Feb-13* 23-Jan-14
CRUDE HEATER UNIT 191 01-Feb-13 07-Nov-13 01-Feb-13 07-Nov-13
D1020 DELIVERY ON SITE CRUDE HEATER UNIT A-1510 (CELLAR DECK) 191 01-Feb-13* 07-Nov-13
CRUDE OIL TRANSFER PUMP 244 01-Feb-13 23-Jan-14 01-Feb-13 23-Jan-14
D1030 DELIVERY ON SITE CRUDE OIL TRANSFER PUMP (COTP) P-1310A/B (CELLAR DECK) 244 01-Feb-13* 23-Jan-14
BOOSTER COMPRESSOR 248 01-Feb-13 29-Jan-14 01-Feb-13 29-Jan-14
D1040 DELIVERY ON SITE BOOSTER COMPRESSOR A-2410 (MAIN DECK) 248 01-Feb-13* 29-Jan-14
GAS LIFT COMPRESSOR 248 01-Feb-13 29-Jan-14 01-Feb-13 29-Jan-14
D1050 DELIVERY ON SITE GAS LIFT COMPRESSOR A-0610 (MAIN DECK) 248 01-Feb-13* 29-Jan-14
FUEL GAS SKID 0
CHEMICAL INJECTION SKID 0
LAUNCHER 0
CLOSE DRAIN VESSEL 0
ELECTRICAL ITEMS/EQUIMENT (ETA) 228 05-Feb-13 03-Jan-14 05-Feb-13 03-Jan-14
DIESEL ENGINE GENERATOR (DEG) 189 05-Feb-13 08-Nov-13 05-Feb-13 08-Nov-13
D1110 DELIVERY ON SITE DIESEL ENGINE GENERATOR (DEG) A-7740 (CELLAR DECK) 189 05-Feb-13* 08-Nov-13
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
CRITICAL PATH NETWORK
Activity ID Activity Name Original Start Finish 2013 2014
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
GAS ENGINE GENERATOR A-7700 228 05-Feb-13 03-Jan-14 05-Feb-13 03-Jan-14
D1120 DELIVERY ON SITE GAS ENGINE GENERATOR A-7700 (CELLAR DECK) 228 05-Feb-13* 03-Jan-14
INSTRUMENT/ TELECOMMUNICATION ITEMS/EQUIMENT (ETA ) 241 01-Feb-13 29-Nov-13 01-Feb-13 29-Nov-13
MULTIPHASE FLOW METER 0
PMCS/SIS/FIELD TRANSMITTER/ FGS 0
WELL HEAD CONTROL PANEL 0
ACTUATED BALL VALVES 206 01-Feb-13 29-Nov-13 01-Feb-13 29-Nov-13
D1160 DELIVERY ON SITE ACTUATED BALL VALVES 206 01-Feb-13* 29-Nov-13
CHOKE VAVLES 167 01-Feb-13 04-Oct-13 01-Feb-13 04-Oct-13
D1170 DELIVERY ON SITE CHOKE VAVLES 167 01-Feb-13* 04-Oct-13
TELECOMUNICATION EQUIPMENT 0
PVCMS-SUPPLIED MATERIALS 0
STRUCTURAL STEEL (ETA) 0
ALUMINIUM HELIDECK 0
STRUCTURE STEEL 0
MISCELANCENEOUS 0
GRATING 0
M CLIP (INCL. MATERIAL) 0
FIRE BLAST WALL 0
ARCHITECTURAL (ETA) 0
FIRE RATED DOORS 0
TEMPORARY SHELTER AND BATHROOM 0
PIPING (ETA) 0
PIPING BULKS 0
MANUAL VALVES 0
ACCESS FITTINGS (SAMPLING CONNECTION, CHEMICAL INJECTION, CORROSION COUPON) 0
ADDITIONAL ITEMS FOR SAMPLING CONNECTION 0
HOSES AND COUPLINGS 0
BUG SCREEN 0
STRAINER 0
CONTINUOUS DRAINERS 0
SIGHT GLASS 0
FLAME ARESTOR 0
PIPING SUPPORT 0
MECHANICAL (ETA) 0
GAS OPERATED PUMP 0
RECIPROCATING PUMPS 0
CENTRIFUGAL PUMP (MISC) 0
TOTE TANKS 0
RECTANGULAR TANKS 0
CLOSED DRAIN TRANSFER PUMP 0
SEPATATOR SKID 0
NITROGEN BOTTLES 0
CO2 VENT SNUFFING 0
HANDLING & LIFTING EQUIPMENT 0
SAFETY & FIRE FIGHTING, LIFE SAVING EQUIPMENT 0
AIR CONDITIONING & VENTILATION SYSTEM 0
ELECTRICAL (ETA) 0
JUCTION BOX AND RCU 0
CABLE GLAND 0
CABLE E&I 0
CABLE TRAY AND LADDER 0
TUBING AND FITTING 0
EARTHING BOSS 0
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
CRITICAL PATH NETWORK
Activity ID Activity Name Original Start Finish 2013 2014
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
SOCKET AND OUTLET 0
HEAT TRACING 0
LIGHTING & FIXTURES 0
MULTI CABLE TRANSIT 0
MISCELLANEOUS 0
CONTROL VALVES (PCV, LCV, FCV, ADV) 0
NAVIGATION AIDS 0
PUSH BUTTON 0
400V AC LV SWICH BOARD 0
UPS 0
DISTRIBUTION BOARD 0
HELIDECK LIGHTING 0
INSTRUMENT (ETA) 0
FLOW METTER 0
FUSIBLE PLUG LOOP PANEL 0
PIG SIGNALLER 0
SAFETY RELIEF VALVE 0
RESTRICTION ORIFICES, ORIFICES PLATE AND FLANGES 0
SAND MONITORING 0
PRESSURE GAUGES 0
PRESSURE REGULATOR VALVES 0
LEVEL GAUGES 0
146 03-Sep-13 28-Feb-14 03-Sep-13 28-Feb-14
CONSTRUCTION
FRONT-END ACTIVITIES/ MOBILIZATION 0
MOBILIZATION OF PROJECT MANAGEMENT TEAM 0
PROJECT PLANNING AND MONITO RING F ORMAT 0
YARD PREPARATIONS 0
CONCRETE FOUNDATION / TEMPORARY SUPPORT FABRICATION 0
CONCRETE FOUNDATION/ TEMPORARY SUPPORTS AT FINAL POSITION FABRICATION 0
TEMPORARY SUPPORTS AT FINAL POSITION FABRICATION 0
CONCRETE FOUNDATION SUPPORTS AT FINAL POSITION FABRICATION 0
CONCRETE FOUNDATION/ TEMPORARY SUPPORTS CELLAR DECK FABRICATION 0
TEMPORARY SUPPORTS CELLAR DECK FABRICATION 0
CONCRETE FOUNDATION SUPPORTS CELLAR DECK FABRICATION 0
CONCRETE FOUNDATION/ TEMPORARY SUPPORTS MAIN DECK FABRICATION 0
TEMPORARY SUPPORTS MAIN DECK FABRICATION 0
CONCRETE FOUNDATION SUPPORTS MAIN DECK FABRICATION 0
TEMPORARY SUPPORTS VENT BOOM FABRICATION 0
MOBILISATION OF SUB-CONTRACTOR 0
MOBILISATION OF DETAIL ENGINEEING SUB-CONTRACTOR 0
MOBILISATION OF NDT SUB-CONTRACTOR 0
MOBILISATION OF HEAT TREATMENT SUB-CONTRACTOR 0
MOBILISATION OF LEAK TEST & BOLT TENSIO NING SUB-CO NTRACTOR 0
MOBILISATION OF INSULATION SUB-CONTRACTOR 0
MOBILISATION OF WEIGHING & LOAD OUT SUB-CONTRACTOR 0
WQT & WPS 0
PANEL COATING SYSTEM QUALIFICATION TEST 0
ONSHORE FABRICATION 7 03-Sep-13 10-Sep-13 03-Sep-13 10-Sep-13
STRUCTURAL 7 03-Sep-13 10-Sep-13 03-Sep-13 10-Sep-13
FABRICATION OF TUBULARS 0
FABRICATION OF PIPE LEGS 0
FABRICATION OF BRACING 0
FABRICATION OF STRUCTURAL MEMBERS 0
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
CRITICAL PATH NETWORK
Activity ID Activity Name Original Start Finish 2013 2014
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
FABRICATION OF CELLAR DECK FRAME 0
FABRICATION WF BEAMS OF CELLAR DECK 0
FABRICATION OF CELLAR DECK PART II 0
FABRICATION OF PRIMARY FRAME PART II 0
FABRICATION OF SECONDARY FRAME PART II 0
FABRICATION OF JOINT DETAIL PART II 0
FABRICATION OF DECK PLATING PART II 0
FABRICATION OF CELLAR DECK PART III 0
FABRICATION OF PRIMARY FRAME PART III 0
FABRICATION OF SECONDARY FRAME PART III 0
FABRICATION OF JOINT DETAIL PART III 0
FABRICATION OF DECK PLATING PART III 0
FABRICATION OF CELLAR DECK PART I 0
FABRICATION OF PRIMARY FRAME PART I 0
FABRICATION OF SECONDARY FRAME PART I 0
FABRICATION OF JOINT DETAIL PART I 0
FABRICATION OF DECK PLATING PART I 0
FABRICATION OF MAIN DECK FRAME 0
FABRICATION WF BEAMS OF MAIN DECK 0
FABRICATION OF MAIN DECK PART II 0
FABRICATION OF PRIMARY FRAME PART II 0
FABRICATION OF SECONDARY FRAME PART II 0
FABRICATION OF JOINT DETAIL PART II 0
FABRICATION OF DECK PLATING PART II 0
FABRICATION OF MAIN DECK PART III 0
FABRICATION OF PRIMARY FRAME PART III 0
FABRICATION OF SECONDARY FRAME PART III 0
FABRICATION OF JOINT DETAIL PART III 0
FABRICATION OF DECK PLATING PART III 0
FABRICATION OF MAIN DECK PART I 0
FABRICATION OF PRIMARY FRAME PART I 0
FABRICATION OF SECONDARY FRAME PART I 0
FABRICATION OF JOINT DETAIL PART I 0
FABRICATION OF HELI DECK 0
FABRICATIN OF VENT BOOM 0
FABRICATION OF OTHER ITEMS 0
ERECTION 7 03-Sep-13 10-Sep-13 03-Sep-13 10-Sep-13
E1750 CELLAR DECK PART II STACK UP 7 03-Sep-13* 10-Sep-13
TRIAL FIT AND WEIGH ING 0
PIPING/ PLUMBING 0
FABRICATION OF PIPE/PLUMBING SUPPORTS 0
INSTALLATIO N O F PIPE/PLUMBIN G SUPPORTS 0
INSTALLATIO N O F VALVES (NUMBER OF VALVES) 0
LEAK TEST OF VALVES (NUMB ER OF VALVES) 0
FLUSHING, HYDROTESTING AND ACID CLEANING 0
INSULATION 0
MECHANICAL 0
SETTING UP EQUIPMENT ON DECK 0
SETTING UP EQUIPMENT ON CELLAR DECK 0
SETTING UP EQUIPMENT ON MAIN DECK 0
MECHANICAL COMPLETION (TIE-IN) 0
TIE-IN EQUIPMENT ON CELLAR DECK 0
TIE-IN EQUIPMENT ON MAIN DECK 0
INSTRUMENT 0
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
CRITICAL PATH NETWORK
Activity ID Activity Name Original Start Finish 2013 2014
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
FABRICATE INSTRUMENT SUPPORTS 0
INSTALLATIO N O F INSTRUMENT SUPPO RTS 0
TUBING TRAY I CABLE TRAY I LADDER INSTALLATION 0
CALIBRATE INSTRUMENT 0
INSTRUMENT EQUIPMENT INSTALLATION 0
CABLE PULLING 0
DRESSING, GLANDING, TAGGING AND TERMINATION 0
PULL AND HOOK-UP TUBING 0
ELECTRICAL 0
FABRICATION OF ELECTRICAL SUPPO RT 0
INSTALLATIO N O F ELECTRICA L SUPPORT 0
CABLE TRAY I CABLE LADDER INSTALLATION 0
CALIBRATE ELECTRICAL EQUIPMENT 0
ELECTRICAL EQUIPMENT INSTALLATION 0
CABLE PULLING 0
DRESSING, GLANCING, TAGGING AND TERMINATION 0
MCT INSTALLATION 0
EARTHING BOSS INSTALLATION 0
BLASTING / PAINTING 0
STRUCTURE STEEL 0
PIPING SUPPORTS/SPOOLS 0
PIPING VALVES 0
INSTRUMENT SUPPORTS 0
ELECTRICAL SUPPORTS 0
ARCHITECTURAL 0
TESTTING & PRE-COMMISSIONING 9 19-Feb-14 28-Feb-14 19-Feb-14 28-Feb-14
PROCESS SYSTEM 7 19-Feb-14 26-Feb-14 19-Feb-14 26-Feb-14
F1010 110-PROCESS GAS 7 19-Feb-14 26-Feb-14
POWER SYSTEM 0
PROCESS UTILITIES SYSTEM 0
GENERAL UTILITIES SYSTEM 0
CONTROL SYSTEM 0
TELECOMMUNICATIONS SYSTEM 0
TOPSIDE ONSHORE MCD 0 28-Feb-14 28-Feb-14 28-Feb-14 28-Feb-14
F1020 TOPSIDE ONSHORE MCD 0 28-Feb-14*
TOPSIDE ONSHORE MCD
LOAD-OUT AND SEAFASTENING 0
DRAWINGS 0
LOAD-OUT BEAM FABRICATION 0
MATERIALS (TONNAGE) 0
LOAD-OUT AND POSITIONING 0
SEAFASTENING FABRICATION 0
TIE-DOWN ARRANGEMENTS 0
0 24-Apr-14 24-Apr-14 24-Apr-14 24-Apr-14
HOOK UP & COMMISSIONING
ONSHORE PREPARATION ACTIVITIES 0
PREPARATION HUC PROCEDURES 0
MOBILIZATION MANPOWER, MATERIAL 0
MOBILIZATION TOOL & EQUIPMENT 0
MOBILIZATION HUC BARGE 0
OFFSHORE HOOK UP AND COMMISSIONIN G 0 24-Apr-14 24-Apr-14 24-Apr-14 24-Apr-14
HOOK UP 0
HOOK UP STRUCTURE 0
INSTALL MECHANICAL ITEMS 0
HOOK UP PIPING 0
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
CRITICAL PATH NETWORK
Activity ID Activity Name Original Start Finish 2013 2014
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
HOOK UP RISER 0
HOOK UP FOR FLOWLINE 0
HOOK UP FOR SLOT 4P 0
HOOK UP FOR SLOT 1P 0
HOOK UP FOR SLOT 2P 0
HOOK UP FOR SLOT 3P 0
HOOK UP FOR OTHER PIPING SYSTEMS 0
LEAK TEST PIPING 0
HOOK UP ELECTRICAL 0
HOOK UP INSTRUMENT 0
TOUCH UP PAINTING/ MARKING 0
COMMISSIONING 0
PROCESS SYSTEM 0
PROCESS UTILITIES SYSTEM 0
GENERAL UTILITIES SYSTEM 0
POWER SYSTEM 0
CONTROL SYSTEM 0
TELECOMMUNICATIONS SYSTEM 0
TOPSIDE START UP 0 24-Apr-14 24-Apr-14 24-Apr-14 24-Apr-14
H6000 TOPSIDE START UP 0 24-Apr-14*
TOPSIDE START UP
FINAL DOCUMENTATION 0
EQUIMENT DOSSIER 0
QA/QC DOCUMENTATION 0
MATERIAL DOCUMENTATION 0
TESTTING & PRECOMMISSIONING DOCUMENTATION 0
DESIGN DATA 0
AS-BUILT DRAWINGS 0
CLOSE-OUT REPORT 0
SHIPLOOSE LIST 0
NDT RADIOGRAPHIC FILMS 0
Remaining Work Milestone
ATTACHMENT 5
Overall Schedule (Topside)
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
EPCC DIAMOND DRILLING PLATFORM
EPCC OVERALL SCHEDULE (TOPSIDE)
Remaining Work Milestone
ATTACHMENT 6
S-Curves (Topside)
72
13-Jun-14
6-Jun-14 100.00% 99.49% 99.99% 0.00%
69
6-Jun-14
30-May-14 100.00% 99.49% 99.99% 0.01%
30-May-14
68
14-Feb-14
14-Feb-14 86.18% 84.18% 85.18% 0.62%
53
7-Feb-14
7-Feb-14 85.56% 83.56% 84.56% 0.73%
31-Jan-14
52
15-Nov-13
41
Actual Cum
38
37
16-Aug-13
28
20
14-Jun-13 21-Jun-13 31.25% 27.25% 29.25% 2.28%
19
7-Jun-13 14-Jun-13 28.97% 24.97% 26.97% 0.67%
18
31-May-13 7-Jun-13 28.30% 24.30% 26.30% 1.10%
17
24-May-13 31-May-13 27.20% 23.20% 25.20% 0.53%
16
17-May-13 24-May-13 26.68% 22.68% 24.68% 2.37%
15
10-May-13 17-May-13 23.30% 21.30% 22.30% 1.55%
14
3-May-13 10-May-13 21.76% 19.76% 20.76% 0.90%
13
26-Apr-13 3-May-13 20.86% 18.86% 19.86% 0.56%
12
19-Apr-13 26-Apr-13 20.30% 18.30% 19.30% 0.94%
11
12-Apr-13 19-Apr-13 19.35% 17.35% 18.35% 0.95%
10
5-Apr-13 12-Apr-13 18.40% 16.40% 17.40% 1.29%
29-Mar-13 5-Apr-13 17.12% 15.12% 16.12% 0.62%
9
22-Mar-13
29-Mar-13 16.50% 14.50% 15.50% 0.42%
8
15-Mar-13
22-Mar-13 16.08% 14.08% 15.08% 1.88%
7
8-Mar-13
15-Mar-13 14.20% 12.20% 13.20% 1.72%
6
1-Mar-13
8-Mar-13 12.48% 10.48% 11.48% 1.12%
5
22-Feb-13
1-Mar-13 11.36% 9.86% 10.36% 0.92%
4
15-Feb-13
22-Feb-13 10.44% 8.94% 9.44% 0.98%
3
8-Feb-13
15-Feb-13 9.47% 7.97% 8.47% 0.23%
2
Progress Cummulative
100.00%
0.00%
90.00%
80.00%
70.00%
60.00%
50.00%
40.00%
30.00%
20.00%
10.00%
8-Feb-13 9.24% 7.74% 8.24% 8.24%
1
Week No.
% Actual Cum
% Variance
56
28-Feb-14
28-Feb-14 100.00% 100.00% 100.00% 0.00%
55
21-Feb-14
21-Feb-14 100.00% 100.00% 100.00% 0.00%
54
14-Feb-14
14-Feb-14 100.00% 100.00% 100.00% 0.00%
53
7-Feb-14
7-Feb-14 100.00% 100.00% 100.00% 0.00%
31-Jan-14
52
29-Nov-13
29-Nov-13 100.69% 96.69% 98.69% 0.36%
42
22-Nov-13
22-Nov-13 100.33% 96.33% 98.33% 0.36%
41
15-Nov-13
15-Nov-13 99.98% 95.98% 97.98% 0.36%
40
8-Nov-13
8-Nov-13 99.62% 95.62% 97.62% 0.36%
39
1-Nov-13
1-Nov-13 99.26% 95.26% 97.26% 0.71%
38
25-Oct-13
25-Oct-13 99.55% 93.55% 96.55% 1.21%
37
18-Oct-13
18-Oct-13 98.34% 92.34% 95.34% 1.66%
36
11-Oct-13
11-Oct-13 96.68% 90.68% 93.68% 1.66%
35
4-Oct-13
4-Oct-13 95.03% 89.03% 92.03% 1.82%
34
32
30
30-Aug-13
Mean Plan Cum
29
28
25
21
16
24-May-13 24-May-13 52.90% 42.90% 47.90% 1.03%
15
17-May-13 17-May-13 51.86% 41.86% 46.86% 1.16%
14
10-May-13 10-May-13 50.71% 40.71% 45.71% 1.60%
13
3-May-13 3-May-13 49.10% 39.10% 44.10% 1.64%
12
26-Apr-13 26-Apr-13 47.46% 37.46% 42.46% 1.71%
11
19-Apr-13 19-Apr-13 45.75% 35.75% 40.75% 0.65%
10
12-Apr-13 12-Apr-13 45.11% 35.11% 40.11% 2.16%
5-Apr-13 42.95% 32.95% 37.95% 4.51%
9
5-Apr-13
29-Mar-13 38.44% 28.44% 33.44% 3.61%
8
29-Mar-13
22-Mar-13 34.83% 24.83% 29.83% 7.77%
7
22-Mar-13
15-Mar-13 27.06% 17.06% 22.06% 2.38%
6
15-Mar-13
8-Mar-13 24.68% 14.68% 19.68% 12.01%
5
8-Mar-13
1-Mar-13 9.67% 5.67% 7.67% 3.58%
4
1-Mar-13
22-Feb-13 6.08% 2.08% 4.08% 3.53%
3
22-Feb-13
15-Feb-13 2.56% 0.00% 0.56% 0.56%
2
15-Feb-13
8-Feb-13 0.00% 0.00% 0.00% 0.00%
1
8-Feb-13
Progress Cummulative
100.00%
90.00%
80.00%
70.00%
60.00%
50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
Week No.
Period
% Actual Cum
% Variance
56
28-Feb-14
28-Feb-14 100.00% 100.00% 100.00% 0.00%
55
21-Feb-14
21-Feb-14 100.00% 100.00% 100.00% 0.00%
54
14-Feb-14
14-Feb-14 100.00% 100.00% 100.00% 0.00%
53
7-Feb-14
7-Feb-14 100.00% 100.00% 100.00% 0.00%
31-Jan-14
52
20-Sep-13
Actual Cum
13-Sep-13
13-Sep-13 67.66% 57.66% 62.66% 1.24%
EPCC FOR TOPSIDES OF DMDP-A DRILLING PLATFORM
31
6-Sep-13
6-Sep-13 66.42% 56.42% 61.42% 3.82%
Procurement S-Curve for Topside (Rev 0)
30
30-Aug-13
30-Aug-13 62.59% 52.59% 57.59% 3.51%
Mean Plan Cum
29
23-Aug-13
23-Aug-13 59.08% 49.08% 54.08% 0.10%
DMDP-A DRILLING PLATFORM
28
16-Aug-13
16-Aug-13 58.98% 48.98% 53.98% 0.16%
27
9-Aug-13
9-Aug-13 58.83% 48.83% 53.83% 0.06%
26
2-Aug-13
2-Aug-13 58.77% 48.77% 53.77% 1.39%
Late Plan Cum
25
21
16
24-May-13 24-May-13 48.37% 38.37% 43.37% 4.52%
15
17-May-13 17-May-13 43.85% 33.85% 38.85% 1.36%
14
10-May-13 10-May-13 42.49% 32.49% 37.49% 1.23%
13
3-May-13 3-May-13 41.26% 31.26% 36.26% 0.63%
12
26-Apr-13 26-Apr-13 40.63% 30.63% 35.63% 1.86%
11
19-Apr-13 19-Apr-13 37.77% 29.77% 33.77% 1.81%
10
12-Apr-13 12-Apr-13 35.97% 27.97% 31.97% 2.77%
5-Apr-13 33.20% 25.20% 29.20% 0.56%
9
5-Apr-13
29-Mar-13 32.64% 24.64% 28.64% 0.46%
8
29-Mar-13
22-Mar-13 32.18% 24.18% 28.18% 3.48%
7
22-Mar-13
15-Mar-13 28.70% 20.70% 24.70% 3.44%
6
15-Mar-13
8-Mar-13 25.25% 18.25% 21.25% 0.33%
5
8-Mar-13
1-Mar-13 24.92% 17.67% 20.92% 0.25%
4
1-Mar-13
22-Feb-13 23.67% 17.67% 20.67% 0.33%
3
22-Feb-13
15-Feb-13 23.34% 17.34% 20.34% 0.02%
2
15-Feb-13
8-Feb-13 23.32% 17.32% 20.32% 20.32%
1
8-Feb-13
Progress Cummulative
100.00%
90.00%
80.00%
70.00%
60.00%
50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
Week No.
Period
% Actual Cum
% Variance
14-Mar-14
58
34
6-Sep-13
31
30-Aug-13
30
16-Aug-13
28
2-Aug-13
26
5-Jul-13
22
16
24-May-13 13.38% 7.38% 10.38% 1.20%
17-May-13
15
17-May-13 11.18% 7.18% 9.18% 2.15%
10-May-13
14
10-May-13 9.02% 5.02% 7.02% 0.71%
3-May-13
13
3-May-13 8.31% 4.31% 6.31% 0.50%
26-Apr-13
12
26-Apr-13 7.81% 3.81% 5.81% 0.21%
19-Apr-13
11
19-Apr-13 7.61% 3.61% 5.61% 0.40%
12-Apr-13
10
12-Apr-13 7.20% 3.20% 5.20% 0.18%
5-Apr-13
5-Apr-13 7.02% 3.02% 5.02% 0.28%
9
29-Mar-13
29-Mar-13 6.74% 2.74% 4.74% 0.05%
8
22-Mar-13
22-Mar-13 6.69% 2.69% 4.69% 0.04%
7
15-Mar-13
15-Mar-13 6.64% 2.64% 4.64% 0.48%
6
8-Mar-13
8-Mar-13 6.16% 2.16% 4.16% 0.60%
5
1-Mar-13
1-Mar-13 5.57% 1.57% 3.57% 1.40%
4
22-Feb-13 22-Feb-13 4.16% 0.16% 2.16% 1.47%
3
15-Feb-13 1.69% 0.00% 0.69% 0.69%
2
15-Feb-13
8-Feb-13 0.00% 0.00% 0.00% 0.00%
1
8-Feb-13
Progress Cummulative
90.00%
80.00%
70.00%
60.00%
50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
100.00%
Week No.
% Actual Cum
% Variance
45
27
26
24-Jan-14
23
27-Dec-13
19
15
22-Nov-13 7.47% 3.47% 5.47% 0.21%
22-Nov-13
14
15-Nov-13 7.26% 3.26% 5.26% 0.29%
13
15-Nov-13
8-Nov-13 6.97% 2.97% 4.97% 0.54%
12
8-Nov-13
1-Nov-13 6.43% 2.43% 4.43% 0.52%
11
1-Nov-13 25-Oct-13 5.91% 2.41% 3.91% 0.50%
10
25-Oct-13 18-Oct-13 5.41% 1.91% 3.41% 0.50%
11-Oct-13 4.91% 1.91% 2.91% 0.50%
9
18-Oct-13
4-Oct-13 3.41% 1.41% 2.41% 0.50%
8
11-Oct-13
27-Sep-13 2.91% 0.91% 1.91% 0.50%
7
4-Oct-13
20-Sep-13 2.41% 0.41% 1.41% 0.50%
6
27-Sep-13
13-Sep-13 1.91% 0.00% 0.91% 0.50%
5
20-Sep-13
6-Sep-13 1.41% 0.00% 0.41% 0.31%
4
13-Sep-13
30-Aug-13 1.10% 0.00% 0.10% 0.07%
3
6-Sep-13
23-Aug-13 1.03% 0.00% 0.03% 0.03%
2
30-Aug-13
16-Aug-13 0.00% 0.00% 0.00% 0.00%
1
23-Aug-13
Progress Cummulative
16-Aug-13
Week No.
100.00%
90.00%
80.00%
70.00%
60.00%
50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
% Actual Cum
% Variance
ATTACHMENT 7
Manhour Histogram, Manpower resource loading & Equipment
resource loading (Topside)
Riggers
Electrician
Scaffolders
Piping Fitters
Riggers
Electric Fitters
Piping Helpers
Week No
Piping Welders
Electrician
Manpower
Piping Pre-com
Scaffolders
Electric Helpers
Electric Welders
Electric Pre-com
Piping Fitters
Structural Fitters
Electric Fitters
Piping Helpers
Piping Welders
Piping Pre-com
Total Man-day
Electric Helpers
Electric Welders
Structural Fitters
Electric Pre-com
Total Man-hour
Structural Helpers
Structural Helpers
Structural Welders
Structural Welders
Blaster and Painter
Topside:
10000
15000
20000
25000
30000
35000
5000
0
780 1040 0 0 0 0 0 0 0 0 0 1040 2080 2600 17-May-13
6
7540 145 0
7
7540 145 0
8
7540 145 0
9
9620 185 0
10
13416 258 0
759,616
780 1040 0 0 0 0 0 0 520 520 1040 1820 2704 4680 21-Jun-13
11
13104 252 0
12
13884 267 0
13
15964 307 0
780 1040 0 416 416 520 520 0 520 2080 1560 1820 4004 5148 12-Jul-13
14
18824 362 0
780 1040 0 416 260 520 520 0 520 2080 1560 1820 4004 5460 19-Jul-13
15
18980 365 0
780 1040 0 416 260 520 520 0 520 2080 1560 1820 4108 5616 26-Jul-13
16
20280 390 1040
780 1040 0 416 260 520 520 0 520 2080 1560 1820 4264 5980 2-Aug-13
17
780 1040 0 416 260 520 520 0 520 2340 1560 1820 4420 6084 9-Aug-13
18
780 1040 0 416 260 520 520 0 520 2340 1560 1820 4576 6448 16-Aug-13
19
780 1560 0 416 260 520 520 0 520 2340 1560 1820 4576 6656 23-Aug-13
20
780 1560 0 416 260 520 520 0 520 2340 1560 1820 4784 6864 30-Aug-13
21
780 1560 0 416 260 520 520 0 520 2704 1560 1820 4784 7228 6-Sep-13
22
780 1560 0 416 260 312 416 0 520 3016 1560 1040 4940 7384 13-Sep-13
23
780 1560 0 416 260 312 416 0 520 3016 1560 1040 5096 7696 20-Sep-13
24
780 1560 0 416 260 312 416 0 520 3016 1560 1040 5252 8060 27-Sep-13
25
780 2080 0 416 260 312 416 0 520 3276 1560 1040 5408 8112 4-Oct-13
26
Page 1 of 1
780 2080 0 416 260 312 416 0 780 3276 2340 1040 5616 8320 11-Oct-13
27
780 2080 0 416 260 312 416 0 780 3276 2340 1040 5772 8580 18-Oct-13
28
780 2080 0 416 260 312 416 0 780 3276 2340 1040 5928 8944 25-Oct-13
29
780 2080 0 416 1300 312 416 0 780 3276 2340 1040 5928 8944 1-Nov-13
30
780 2080 0 416 1300 312 416 0 780 2340 2340 1040 5928 8944 8-Nov-13
31
780 2080 0 416 1300 312 416 0 780 2340 2340 1040 5928 8944 15-Nov-13
32
780 2080 0 416 1300 312 416 0 780 2340 2340 1040 5928 8944 22-Nov-13
33
780 2080 0 416 1300 312 416 0 780 2340 2340 1040 5928 8944 29-Nov-13
34
780 2080 0 416 1300 312 416 0 780 1820 2340 1040 5824 8736 6-Dec-13
35
780 1560 0 416 1300 312 416 0 780 1820 3120 1040 5616 7800 13-Dec-13
36
780 1560 0 416 1300 312 416 0 780 1300 3120 1040 5096 7592 20-Dec-13
37
780 1560 0 416 1300 312 416 0 780 1300 3120 1040 4784 7280 27-Dec-13
38
780 1560 416 416 1300 312 416 0 780 1300 3120 1040 4212 6864 3-Jan-14
39
780 1560 416 416 1300 312 416 0 520 0 3120 780 4108 6448 10-Jan-14
40
780 1560 416 416 1300 312 416 0 520 0 1560 780 3744 6136 17-Jan-14
41
780 1560 416 416 1300 312 416 520 520 0 1560 780 3536 5512 24-Jan-14
42
780 1560 416 416 1300 0 416 520 520 0 1560 780 3224 5200 31-Jan-14
43
0 0 0 0 0 0 0 0 0 0 0 0 0 0 7-Feb-14
44
0 0 0
780 1560 416 416 1300 0 416 520 520 0 1560 780 2444 4264 14-Feb-14
45
780 1040 780 416 1300 0 416 520 520 0 1560 780 2444 4264 21-Feb-14
46
11128 214 0
QA/QC
Foremen
Procurment
Supervisors
1000
2000
3000
4000
5000
6000
7000
8000
Engineering
Total Man-day
Total Man-hour
8-Feb-13
15-Feb-13
1-Mar-13
672 14 0 0 0 0 192 240 240 8-Feb-13 8-Mar-13
Page 1 of 1
6248 130 920 1008 1200 432 576 1056 1056 6-Sep-13
11-Oct-13
EPCC DIAMOND DRILLING PLATFORM
6239 130 911 1008 1200 432 576 1056 1056 13-Sep-13
18-Oct-13
6288 131 960 1008 1200 432 576 1056 1056 20-Sep-13
25-Oct-13
6358 132 1030 1008 1200 432 576 1056 1056 27-Sep-13
1-Nov-13
6429 134 1101 1008 1200 432 576 1056 1056 4-Oct-13
8-Nov-13
6512 136 1184 1008 1200 432 576 1056 1056 11-Oct-13
TOPSIDE INDIRECT MAN-HOURS HISTOGRAM (ONHORE FABRICATION)
15-Nov-13
6579 137 1251 1008 1200 432 576 1056 1056 18-Oct-13
22-Nov-13
6651 139 1323 1008 1200 432 576 1056 1056 25-Oct-13
29-Nov-13
6705 140 1377 1008 1200 432 576 1056 1056 1-Nov-13
6-Dec-13
6782 141 1454 1008 1200 432 576 1056 1056 8-Nov-13
13-Dec-13
6861 143 1533 1008 1200 432 576 1056 1056 15-Nov-13
20-Dec-13
6896 144 1568 1008 1200 432 576 1056 1056 22-Nov-13 27-Dec-13
3-Jan-14
6896 144 1568 1008 1200 432 576 1056 1056 29-Nov-13
10-Jan-14
6896 144 1568 1008 1200 432 576 1056 1056 6-Dec-13
17-Jan-14
6815 142 1487 1008 1200 432 576 1056 1056 13-Dec-13 24-Jan-14
6724 140 1396 1008 1200 432 576 1056 1056 20-Dec-13 31-Jan-14
7-Feb-14
6646 138 1318 1008 1200 432 576 1056 1056 27-Dec-13
14-Feb-14
5040 105 1248 576 576 432 384 768 1056 3-Jan-14
21-Feb-14
4910 102 1118 576 576 432 384 768 1056 10-Jan-14 28-Feb-14
7-Mar-14
4829 101 1037 576 576 432 384 768 1056 17-Jan-14
14-Mar-14
4790 100 998 576 576 432 384 768 1056 24-Jan-14
Supervisors
Engineering
Procurment
Aug-13
May-13
Nov-13
Sep-13
Dec-13
Jun-13
Feb-14
Jan-14
Oct-13
Jul-13
No DESCRIPTION
Genset (Plan) 2 2 2 2 2 2 2 2 2 2
15 Genset (Actual)
MANPOWER OF ALL TRADES FOR DMDP-A
HOOK UP& COMMISSIONING
1 HUC Manager 1
2 HUC Superintendent 4
3 Construction supervisor 10
4 Commissioning Engineer 7
5 Hook up Engineer 6
6 QC Inspector 10
8 Insulation Technician 6
10 NDT Technician 4
12 Hydrotest Tech. 8
13 Welder 38
14 Fitter 56
15 Scaffolder 18
16 Rigger 8
17 E&I Technician 15
18 Blaster& Painter 8
19 Helper 30
Total 249
MANHOURS & MANPOWER RESOURCE LOADING FOR DMDP-A TOPSIDE
1
I.2.1.4.3 FABRICATION OF JOINT DETAIL PART I 35 17-Jun-13 26-Jul-13 1,376 -
619 Structural Fitters 2
482 Structural Welders 2
206 Structural Helpers 1
69 Rigger 1
- -
I.2.1.4.4 FABRICATION OF DECK PLATING PART I 48 6-Jul-13 30-Aug-13 2,752 -
1,101 Structural Fitters 3
825 Structural Welders 2
413 Structural Helpers 1
138 Rigger 1
275 Scaffolders 1
I.2.2 FABRICATION OF CLOSED DRAIN VESSEL FRAME 28 31-Aug-13 3-Oct-13 3,057 -
1,529 Structural Fitters 7
764 Structural Welders 3
459 Structural Helpers 2
153 Rigger 1
153 Scaffolders 1
I.2.3 FABRICATION OF MAIN DECK FRAME 115 17-Jun-13 29-Oct-13 45,860 -
I.2.3.1 FABRICATION WF BEAMS OF MAIN DECK 29 17-Jun-13 19-Jul-13 4,586 -
1,834 Structural Fitters 8
1,376 Structural Welders 6
688 Structural Helpers 3
229 Rigger 1
459 Scaffolders 2
I.2.3.2 FABRICATION OF MAIN DECK PART II 83 9-Jul-13 14-Oct-13 16,051 -
I.2.3.2.1 FABRICATION OF PRIMARY FRAME PART II 46 9-Jul-13 30-Aug-13 6,420 -
2,761 Structural Fitters 8
1,733 Structural Welders 5
963 Structural Helpers 3
321 Rigger 1
642 Scaffolders 2
I.2.3.2.2 FABRICATION OF SECONDARY FRAME PART II 46 20-Jul-13 12-Sep-13 4,815 -
2,071 Structural Fitters 6
1,300 Structural Welders 4
722 Structural Helpers 2
241 Rigger 1
482 Scaffolders 1
I.2.3.2.3 FABRICATION OF JOINT DETAIL PART II 54 17-Jul-13 18-Sep-13 1,605 -
722 Structural Fitters 2
562 Structural Welders 1
241 Structural Helpers 1
80 Rigger 1
- -
I.2.3.2.4 FABRICATION OF DECK PLATING PART II 58 7-Aug-13 14-Oct-13 3,210 -
1,284 Structural Fitters 3
963 Structural Welders 2
482 Structural Helpers 1
161 Rigger 1
321 Scaffolders 1
I.2.3.3 FABRICATION OF MAIN DECK PART III 74 26-Jul-13 21-Oct-13 16,051 -
I.2.3.3.1 FABRICATION OF PRIMARY FRAME PART III 36 26-Jul-13 6-Sep-13 6,420 -
2,761 Structural Fitters 10
1,733 Structural Welders 6
963 Structural Helpers 3
321 Rigger 1
642 Scaffolders 2
-
I.2.3.3.2 FABRICATION OF SECONDARY FRAME PART III 34 7-Aug-13 16-Sep-13 4,815 -
2,071 Structural Fitters 8
1,300 Structural Welders 5
722 Structural Helpers 3
241 Rigger 1
482 Scaffolders 2
I.2.3.3.3 FABRICATION OF JOINT DETAIL PART III 39 13-Aug-13 27-Sep-13 1,605 -
722 Structural Fitters 2
562 Structural Welders 2
241 Structural Helpers 1
80 Rigger 1
- -
I.2.3.3.4 FABRICATION OF DECK PLATING PART III 49 24-Aug-13 21-Oct-13 3,210 -
1,284 Structural Fitters 3
963 Structural Welders 2
482 Structural Helpers 1
161 Rigger 1
321 Scaffolders 1
I.2.3.4 FABRICATION OF MAIN DECK PART I 71 7-Aug-13 29-Oct-13 9,172 -
I.2.3.4.1 FABRICATION OF PRIMARY FRAME PART I 48 7-Aug-13 2-Oct-13 3,669 -
1,578 Structural Fitters 4
991 Structural Welders 3
550 Structural Helpers 1
183 Rigger 1
367 Scaffolders 1
I.2.3.4.2 FABRICATION OF SECONDARY FRAME PART I 48 19-Aug-13 14-Oct-13 3,669 -
1,578 Structural Fitters 4
991 Structural Welders 3
550 Structural Helpers 1
183 Rigger 1
367 Scaffolders 1
I.2.3.4.3 FABRICATION OF JOINT DETAIL PART I 56 24-Aug-13 29-Oct-13 1,834 -
2
825 Structural Fitters 2
642 Structural Welders 1
275 Structural Helpers 1
92 Rigger 1
- -
I.2.4 FABRICATION OF HELI DECK 20 5-Dec-13 27-Dec-13 4,586 -
2,522 Structural Fitters 16
688 Structural Helpers 4
459 Rigger 3
917 Scaffolders 6
I.2.5 FABRICATION OF VENT BOOM 68 12-Oct-13 30-Dec-13 15,287 -
7,643 Structural Fitters 14
3,822 Structural Welders 7
2,293 Structural Helpers 4
764 Rigger 1
764 Scaffolders 1
I.2.6 FABRICATION OF OTHER ITEMS 72 11-Sep-13 4-Dec-13 38,216 -
I.2.6.1 FABRICATION HANDRAIL 48 9-Oct-13 4-Dec-13 5,045 -
2,018 Structural Fitters 5
1,513 Structural Welders 4
1,513 Structural Helpers 4
-
-
I.2.6.2 FABRICATION LADDER 48 9-Oct-13 3-Dec-13 764 -
306 Structural Fitters 1
229 Structural Welders 1
229 Structural Helpers 1
- -
- -
I.2.6.3 FABRICATION STAIRWAY 48 9-Oct-13 3-Dec-13 3,363 -
1,345 Structural Fitters 4
1,009 Structural Welders 3
1,009 Structural Helpers 3
- -
- -
I.2.6.4 FABRICATION DECK DRAIN 48 9-Oct-13 3-Dec-13 1,445 -
578 Structural Fitters 2
433 Structural Welders 1
433 Structural Helpers 1
- -
- -
I.2.6.5 FABRICATION EQUIPMENT MOUNTING 48 9-Oct-13 3-Dec-13 382 -
153 Structural Fitters 1
115 Structural Welders 1
115 Structural Helpers 1
- -
- -
I.2.6.6 FABRICATION LIFE RAFT SUPPORT 48 9-Oct-13 3-Dec-13 382 -
153 Structural Fitters 1
115 Structural Welders 1
115 Structural Helpers 1
- -
- -
I.2.6.7 FABRICATION LIFTING PADEYE 48 9-Oct-13 3-Dec-13 1,804 -
722 Structural Fitters 2
541 Structural Welders 1
541 Structural Helpers 1
- -
- -
I.2.6.8 FABRICATION VENT BOOM SUPPORT 48 9-Oct-13 3-Dec-13 1,926 -
770 Structural Fitters 2
578 Structural Welders 2
578 Structural Helpers 2
- -
- -
I.2.6.9 FABRICATION MONORAIL 48 9-Oct-13 3-Dec-13 699 -
280 Structural Fitters 1
210 Structural Welders 1
210 Structural Helpers 1
- -
- -
I.2.6.10 FABRICATION SECURITY GATE AND WALL 48 9-Oct-13 3-Dec-13 5,847 -
2,339 Structural Fitters 6
1,754 Structural Welders 5
1,754 Structural Helpers 5
- -
- -
I.2.6.11 FABRICATION CONDUCTOR GUIDE 24 9-Oct-13 5-Nov-13 6,566 -
2,955 Structural Fitters 15
2,298 Structural Welders 12
985 Structural Helpers 5
328 Rigger 2
- -
I.2.6.12 FABRICATION HATCH COVER 24 9-Oct-13 5-Nov-13 1,685 -
758 Structural Fitters 4
590 Structural Welders 3
253 Structural Helpers 1
84 Rigger 1
- -
I.2.6.13 FABRICATION CRANE ACCESS PLATFORM 24 15-Oct-13 11-Nov-13 627 -
3
282 Structural Fitters 1
219 Structural Welders 1
94 Structural Helpers 1
31 Rigger 1
- -
I.2.6.14 FABRICATION FIRE & BLASTWALL 24 11-Sep-13 8-Oct-13 6,669 -
2,668 Structural Fitters 14
2,001 Structural Welders 10
1,334 Structural Helpers 7
667 Rigger 3
- -
I.2.6.15 FABRICATION PLATFORM NAME PLATE 12 1-Nov-13 14-Nov-13 382 -
153 Structural Fitters 2
115 Structural Welders 1
115 Structural Helpers 1
- -
- -
I.2.6.16 FABRICATION CONES (4 PCS) 12 16-Sep-13 28-Sep-13 627 -
282 Structural Fitters 3
219 Structural Welders 2
94 Structural Helpers 1
31 Rigger 1
- -
I.3 ERECTION 156 6-Aug-13 17-Feb-14 101,000 -
I.3.1 LAYOUT/ERECTION SUPPORTS & LOAD OUT BEAMS TO FINAL POSITION
7 22-Aug-13 29-Aug-13 8,080 -
2,020 Structural Fitters 36
1,616 Structural Welders 29
2,020 Structural Helpers 36
808 Rigger 14
1,616 Scaffolders 29
I.3.2 CELLAR DECK PART I STACK UP 7 03-Sep-13* 10-Sep-13 6,060 -
1,515 Structural Fitters 27
1,212 Structural Welders 22
1,515 Structural Helpers 27
606 Rigger 11
1,212 Scaffolders 22
I.3.3 CELLAR DECK PART II STACK UP 7 12-Sep-13 19-Sep-13 5,050 -
1,263 Structural Fitters 23
1,010 Structural Welders 18
1,263 Structural Helpers 23
505 Rigger 9
1,010 Scaffolders 18
I.3.4 CELLAR DECK PART III STACK UP 7 21-Sep-13 28-Sep-13 4,040 -
1,010 Structural Fitters 18
808 Structural Welders 14
1,010 Structural Helpers 18
404 Rigger 7
808 Scaffolders 14
I.3.5 CLOSE DRAIN FRAME STACK UP 5 10-Oct-13 15-Oct-13 1,010 -
253 Structural Fitters 6
202 Structural Welders 5
253 Structural Helpers 6
101 Rigger 3
202 Scaffolders 5
I.3.6 PIPE LEGS ERECTION 15 30-Sep-13 16-Oct-13 3,030 -
758 Structural Fitters 6
606 Structural Welders 5
758 Structural Helpers 6
303 Rigger 3
606 Scaffolders 5
I.3.7 BRACING PIPE ERECTION (PART 1) 20 30-Sep-13 22-Oct-13 8,080 -
2,020 Structural Fitters 13
1,616 Structural Welders 10
2,020 Structural Helpers 13
1,212 Rigger 8
1,212 Scaffolders 8
I.3.8 BLAST WALL ERECTION (PART 1) 10 9-Oct-13 19-Oct-13 6,060 -
1,212 Structural Fitters 15
1,515 Structural Welders 19
1,212 Structural Helpers 15
909 Rigger 11
1,212 Scaffolders 15
I.3.9 MAIN DECK PART I (AXIS 1/2) STACK UP 10 5-Nov-13 15-Nov-13 6,060 -
1,515 Structural Fitters 19
1,212 Structural Welders 15
1,515 Structural Helpers 19
606 Rigger 8
1,212 Scaffolders 15
I.3.10 MAIN DECK PART II (AXIS 2/2a) STACK UP 8 11-Nov-13 19-Nov-13 5,050 -
1,263 Structural Fitters 20
1,010 Structural Welders 16
1,263 Structural Helpers 20
505 Rigger 8
1,010 Scaffolders 16
I.3.11 MAIN DECK PART III (AXIS 1a/1) STACK UP 7 20-Nov-13 27-Nov-13 4,040 -
1,010 Structural Fitters 18
808 Structural Welders 14
1,010 Structural Helpers 18
404 Rigger 7
808 Scaffolders 14
4
I.3.12 HELI DECK ERECTION 6 28-Dec-13 4-Jan-14 2,020 -
505 Structural Fitters 11
404 Structural Welders 8
505 Structural Helpers 11
202 Rigger 4
404 Scaffolders 8
I.3.13 BRACING ERECTION (REMAINING PART) 15 4-Dec-13 20-Dec-13 9,090 -
2,273 Structural Fitters 19
1,818 Structural Welders 15
2,273 Structural Helpers 19
1,364 Rigger 11
1,364 Scaffolders 11
I.3.14 BLAST WALL ERECTION (REMAINING PART) 12 4-Dec-13 17-Dec-13 8,080 -
1,616 Structural Fitters 17
2,020 Structural Welders 21
1,616 Structural Helpers 17
1,212 Rigger 13
1,616 Scaffolders 17
I.3.15 ERECTION OTHER ITEMS 21 20-Dec-13 14-Jan-14 25,250 -
10,858 Structural Fitters 65
6,818 Structural Welders 41
3,788 Structural Helpers 23
1,263 Rigger 8
2,525 Scaffolders 15
I.4 TRIAL FIT AND WEIGHING 23 30-Dec-13 25-Jan-14 9,554 -
I.4.1 VENT BOOM TRIAL FIT 6 20-Jan-14 25-Jan-14 3,344 -
1,672 Structural Helpers 35
669 Rigger 14
1,003 Scaffolders 21
I.4.2 FABRICATE/ ERECTION PADEYES 14 30-Dec-13 15-Jan-14 955 -
411 Structural Fitters 4
258 Structural Welders 2
143 Structural Helpers 1
I.4.3 TRIAL FIT/ LAYOUT T&I SLINGS 7 16-Jan-14 23-Jan-14 1,433 -
334 Structural Helpers 6
134 Rigger 2
201 Scaffolders 4
I.4.4 TOPSIDE WEIGHING 2 30-Dec-13* 2-Jan-14 3,822 -
3,822 Structural Helpers 239
II PIPING/ PLUMBING 199 15-Jun-13 10-Feb-14 269,618 -
II.1 FABRICATION OF PIPE/PLUMBING SUPPORTS 122.8 15-Jun-13 6-Nov-13 107,847 -
II.1.1 FABRICATE PIPE SUPPORT 60 15-Jun-13 23-Aug-13 13,481 -
2,022 Piping Fitters 4
1,348 Piping Welders 3
1,348 Piping Helpers 3
4,718 Structural Fitters 10
4,044 Structural Welders 8
II.1.2 FABRICATE PIPE SPOOL 105 5-Jul-13 6-Nov-13 94,366 -
47,183 Piping Fitters 56
28,310 Piping Welders 34
18,873 Piping Helpers 22
II.2 INSTALLATION OF PIPE/PLUMBING SUPPORTS 105 10-Sep-13 10-Jan-14 97,062 -
II.2.1 INSTALL PIPE SUPPORT 100 10-Sep-13 4-Jan-14 12,133 -
1,820 Piping Fitters 2
1,213 Piping Welders 2
4,246 Structural Fitters 5
3,640 Structural Welders 5
1,213 Scaffolders 2
II.2.2 INSTALL PIPE SPOOL 100 16-Sep-13 10-Jan-14 84,930 -
21,232 Piping Fitters 27
33,972 Piping Welders 42
8,493 Piping Helpers 11
8,493 Rigger 11
12,739 Scaffolders 16
II.3 INSTALLATION OF VALVES 40 10-Dec-13 25-Jan-14 12,133 -
4,853 Piping Fitters 15
1,820 Piping Helpers 6
1,820 Rigger 6
3,640 Scaffolders 11
II.4 LEAK TEST OF VALVES 35 24-Dec-13 8-Feb-14 9,437 -
3,303 Piping Fitters 12
4,246 Piping Helpers 15
1,887 Scaffolders 7
II.5 FLUSHING, HYDROTESTING AND ACID CLEANING 63 22-Nov-13 10-Feb-14 26,962 -
9,437 Piping Fitters 19
9,437 Piping Helpers 19
8,089 Scaffolders 16
II.6 INSULATION 60 22-Nov-13 6-Feb-14 16,177 -
4,044 Piping Fitters 8
6,471 Piping Welders 13
1,618 Piping Helpers 3
1,618 Rigger 3
2,427 Scaffolders 5
III MECHANICAL 98 30-Sep-13 22-Jan-14 33,584 -
III.1 SETTING UP EQUIPMENT ON DECK 88 30-Sep-13 10-Jan-14 11,754 -
III.1.1 SETTING UP EQUIPMENT ON CELLAR DECK 88 30-Sep-13 10-Jan-14 6,112 -
1,528 Structural Fitters 2
1,222 Structural Welders 2
1,528 Structural Helpers 2
611 Rigger 1
5
1,222 Scaffolders 2
III.1.2 SETTING UP EQUIPMENT ON MAIN DECK 40 20-Nov-13 6-Jan-14 5,642 -
1,411 Structural Fitters 4
1,128 Structural Welders 4
1,411 Structural Helpers 4
564 Rigger 2
1,128 Scaffolders 4
III.2 MECHANICAL COMPLETION (TIE-IN) 84 16-Oct-13 22-Jan-14 21,830 -
III.2.1 TIE-IN EQUIPMENT ON CELLAR DECK 84 16-Oct-13 22-Jan-14 11,351 -
2,838 Piping Fitters 4
2,270 Piping Welders 3
2,270 Structural Helpers 3
568 Rigger 1
1,703 Electrician 3
1,703 Scaffolders 3
III.2.2 TIE-IN EQUIPMENT ON MAIN DECK 50 22-Nov-13 21-Jan-14 10,478 -
2,620 Piping Fitters 7
2,096 Piping Welders 5
2,096 Structural Helpers 5
524 Rigger 1
1,572 Electrician 4
1,572 Scaffolders 4
IV INSTRUMENT 175 11-Jul-13 7-Feb-14 66,988 -
IV.1 FABRICATE INSTRUMENT SUPPORTS 40 11-Jul-13 26-Aug-13 5,359 -
804 Electric Fitters 3
536 Electric Welders 2
536 Electric Helpers 2
1,876 Structural Fitters 6
1,608 Structural Welders 5
IV.2 INSTALLATION OF INSTRUMENT SUPPORTS 55 11-Oct-13 13-Dec-13 7,369 -
1,105 Electric Fitters 3
737 Electric Welders 2
2,579 Structural Fitters 6
2,211 Structural Welders 5
737 Scaffolders 2
IV.3 TUBING TRAY I CABLE TRAY I LADDER INSTALLATION 55 19-Oct-13 21-Dec-13 6,699 -
1,005 Electric Fitters 2
670 Electric Welders 2
1,340 Electrician 3
2,010 Structural Fitters 5
1,675 Scaffolders 4
IV.4 CALIBRATE INSTRUMENT 55 11-Oct-13 13-Dec-13 670 -
670 Electrician 2
IV.5 INSTRUMENT EQUIPMENT INSTALLATION 78 23-Oct-13 22-Jan-14 7,369 -
1,105 Electric Fitters 2
1,842 Electric Helpers 3
2,579 Electrician 4
1,842 Scaffolders 3
IV.6 CABLE PULLING 50 12-Nov-13 9-Jan-14 10,048 -
1,507 Electric Fitters 4
1,507 Electric Helpers 4
3,014 Structural Helpers 8
4,019 Scaffolders 10
IV.7 DRESSING, GLANDING, TAGGING AND TERMINATION 50 5-Dec-13 7-Feb-14 22,776 -
11,388 Electrician 28
5,694 Scaffolders 14
5,694 Structural Helpers 14
IV.8 PULL AND HOOK-UP TUBING 30 26-Dec-13 5-Feb-14 6,699 -
3,349 Electrician 14
1,675 Scaffolders 7
1,675 Structural Helpers 7
V ELECTRICAL 173 11-Jul-13 5-Feb-14 82,391 -
V.1 ELECTRICAL SUPPORT 128 11-Jul-13 7-Dec-13 17,302 -
V.1.1 FABRICATION OF ELECTRICAL SUPPORT 50 11-Jul-13 7-Sep-13 6,921 -
1,038 Electric Fitters 3
692 Electric Welders 2
692 Electric Helpers 2
2,422 Structural Fitters 6
2,076 Structural Welders 5
V.1.2 INSTALLATION OF ELECTRICAL SUPPORT 55 5-Oct-13 7-Dec-13 10,381 -
1,557 Electric Fitters 4
1,038 Electric Welders 2
3,633 Structural Fitters 8
3,114 Structural Welders 7
1,038 Scaffolders 2
V.2 CABLE TRAY I CABLE LADDER INSTALLATION 55 11-Oct-13 13-Dec-13 14,006 -
2,101 Electric Fitters 5
2,801 Electrician 6
5,603 Structural Fitters 13
3,502 Scaffolders 8
V.3 CALIBRATE ELECTRICAL EQUIPMENT 50 23-Oct-13 19-Dec-13 824 -
824 Electrician 2
V.4 ELECTRICAL EQUIPMENT INSTALLATION 80 22-Oct-13 23-Jan-14 4,120 -
618 Electric Fitters 1
1,030 Electric Helpers 2
1,442 Electrician 2
1,030 Scaffolders 2
V.5 DRESSING, GLANCING, TAGGING AND TERMINATION 50 3-Dec-13 5-Feb-14 28,013 -
14,006 Electrician 35
7,003 Scaffolders 18
6
7,003 Structural Helpers 18
V.6 MCT INSTALLATION 7 28-Nov-13 5-Dec-13 824 -
124 Electric Fitters 2
165 Electrician 3
330 Structural Fitters 6
206 Scaffolders 4
V.7 EARTHING BOSS INSTALLATION 7 7-Jan-14 14-Jan-14 824 -
124 Electric Fitters 2
82 Electric Welders 1
288 Structural Fitters 5
247 Structural Welders 4
82 Scaffolders 1
VI BLASTING / PAINTING 221 20-Apr-13 7-Jan-14 12,669 -
VI.1 STRUCTURAL ITEMS 138 22-Apr-13 7-Jan-14 7,601 -
2,534 Blaster and Painter 8
158 Rigger 1
475 Scaffolders 1
VI.2 PIPING SUPPORTS/SPOOLS 127 22-Jun-13 18-Nov-13 3,167 -
2,534 Blaster and Painter 8
158 Rigger 1
475 Scaffolders 1
VI.3 PIPING VALVES 25 28-Nov-13 26-Dec-13 380 -
304 Blaster and Painter 2
19 Rigger 1
57 Scaffolders 1
VI.4 INSTRUMENT SUPPORTS 12 21-Aug-13 4-Sep-13 760 -
608 Blaster and Painter 6
38 Rigger 1
114 Scaffolders 1
VI.5 ELECTRICAL SUPPORTS 50 18-Jul-13 14-Sep-13 760 -
608 Blaster and Painter 2
38 Rigger 1
114 Scaffolders 1
VII ARCHITECTURAL 48 17-Oct-13 11-Dec-13 21,392 -
VII.1 SETTING UP FIRE RATED DOORS 9 26-Nov-13 5-Dec-13 2,139 -
749 Structural Fitters 10
428 Structural Welders 6
535 Structural Helpers 7
107 Rigger 1
321 Scaffolders 4
VII.2 SETTING UP TEMPORARY SHELTER 48 17-Oct-13 11-Dec-13 19,253 -
6,738 Structural Fitters 18
3,851 Structural Welders 10
4,813 Structural Helpers 13
963 Rigger 3
2,888 Scaffolders 8
7
ATTACHMENT 8
Progress Measurement Format
DMDP-A DRILLING PLATFORM
EPCC FOR TOPSIDES OF DMDP-A DRILLING PLATFORM
PROGRESS MEASUREMENT AND REPORTING FORMAT (REV.0)
1
3.1.2.2 CRUDE HEATER UNIT 26.59% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 7-Nov-13 7-Nov-13
D1020 DELIVERY ON SITE CRUDE HEATER UNIT A-1510 (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 7-Nov-13 7-Nov-13
3.1.2.3 CRUDE OIL TRANSFER PUMP 1.24% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 23-Jan-14 23-Jan-14
D1030 DELIVERY ON SITE CRUDE OIL TRANSFER PUMP (COTP) P-1310A/B (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 23-Jan-14 23-Jan-14
3.1.2.4 BOOSTER COMPRESSOR 4.08% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 29-Jan-14 29-Jan-14
D1040 DELIVERY ON SITE BOOSTER COMPRESSOR A-2410 (MAIN DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 29-Jan-14 29-Jan-14
3.1.2.5 GAS LIFT COMPRESSOR 25.84% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 29-Jan-14 29-Jan-14
D1050 DELIVERY ON SITE GAS LIFT COMPRESSOR A-0610 (MAIN DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 29-Jan-14 29-Jan-14
3.1.2.6 FUEL GAS SKID 10.93% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 26-Sep-13 26-Sep-13
D1060 DELIVERY ON SITE FUEL GAS SKID A-5800 (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 26-Sep-13 26-Sep-13
3.1.2.7 CHEMICAL INJECTION SKID 2.49% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 26-Sep-13 26-Sep-13
D1070 DELIVERY ON SITE CHEMICAL INJECTION PUMP SKID A-6800 (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 26-Sep-13 26-Sep-13
3.1.2.8 LAUNCHER 0.99% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 15-Aug-13 15-Aug-13
D1090 DELIVERY ON SITE LAUNCHER L-1330 (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 15-Aug-13 15-Aug-13
3.1.2.9 CLOSE DRAIN VESSEL 3.73% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 18-Oct-13 18-Oct-13
D1100 DELIVERY ON SITE CLOSE DRAIN VESSEL V-6400 100.00% 80.00% 20% 0.00% 0.00% 0.00% 18-Oct-13 18-Oct-13
3.1.3 ELECTRICAL ITEMS/EQUIMENT (ETA) 19.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 8-Nov-13 3-Jan-14
3.1.3.1 DIESEL ENGINE GENERATOR (DEG) 36.99% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 8-Nov-13 8-Nov-13
D1110 DELIVERY ON SITE DIESEL ENGINE GENERATOR (DEG) A-7740 (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 8-Nov-13 8-Nov-13
3.1.3.2 GAS ENGINE GENERATOR A-7700 63.01% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 3-Jan-14 3-Jan-14
D1120 DELIVERY ON SITE GAS ENGINE GENERATOR A-7700 (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 3-Jan-14 3-Jan-14
3.1.4 INSTRUMENT/ TELECOMMUNICATION ITEMS/EQUIMENT (ETA) 15.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 2-Aug-13 29-Nov-13
3.1.4.1 MULTIPHASE FLOW METER 11.18% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 20-Sep-13 20-Sep-13
D1130 DELIVERY ON SITE MULTIPHASE FLOW METER A-1210 (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 20-Sep-13 20-Sep-13
3.1.4.2 PMCS/SIS/FIELD TRANSMITTER/ FGS 6.21% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 6-Sep-13 6-Sep-13
D1140 DELIVERY ON SITE PMCS/SIS/FIELD TRANSMITTER/ FGS 100.00% 80.00% 20% 0.00% 0.00% 0.00% 6-Sep-13 6-Sep-13
3.1.4.3 WELL HEAD CONTROL PANEL 17.39% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 2-Aug-13 2-Aug-13
D1150 DELIVERY ON SITE WELL HEAD CONTROL PANEL WHCP-0100 (CELLAR DECK) 100.00% 80.00% 20% 0.00% 0.00% 0.00% 2-Aug-13 2-Aug-13
3.1.4.4 ACTUATED BALL VALVES 31.06% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 29-Nov-13 29-Nov-13
D1160 DELIVERY ON SITE ACTUATED BALL VALVES 100.00% 80.00% 20% 0.00% 0.00% 0.00% 29-Nov-13 29-Nov-13
3.1.4.5 CHOKE VAVLES 31.06% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 4-Oct-13 4-Oct-13
D1170 DELIVERY ON SITE CHOKE VAVLES 100.00% 80.00% 20% 0.00% 0.00% 0.00% 4-Oct-13 4-Oct-13
3.1.4.6 TELECOMUNICATION EQUIPMENT 3.11% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 13-Oct-13 13-Oct-13
D1180 DELIVERY ON SITE TELECOMUNICATION EQUIPMENT 100.00% 80.00% 20% 0.00% 0.00% 0.00% 13-Oct-13 13-Oct-13
3.2 PVCMS-SUPPLIED MATERIALS 81.00% Prep/ Submit Accept/ Approve 55.73% 53.25% 2.48% 5-Sep-12 3-Jan-14
3.2.1 STRUCTURAL STEEL (ROS) 18.00% Prep/ Submit Accept/ Approve 56.75% 62.00% -5.25% 5-Sep-12 4-Dec-13
3.2.1.1 ALUMINIUM HELIDECK 45.00% Prep/ Submit Accept/ Approve 44.00% 50.00% -6.00% 5-Sep-12 4-Dec-13
A5330 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A5410 PO ISSUE DATE 30.00% 1 80.00% 20% 80.00% 100.00% -20.00% 23-May-13 23-May-13
D1190 DELIVERY ON SITE (ALUMINIUM HELIDECK) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 29-Nov-13 2-Dec-13
D1195 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 3-Dec-13 4-Dec-13
3.2.1.2 STRUCTURE STEEL 20.00% Prep/ Submit Accept/ Approve 100.00% 84.00% 16.00% 5-Sep-12 3-Jul-13
A5450 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A5530 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 19-Mar-13 19-Mar-13
D1200 DELIVERY ON SITE (STRUCTURE STEEL) 30.00% 2 80.00% 2 20% 100.00% 100.00% 0.00% 17-Jun-13 20-Jun-13
D1205 MATERIAL ACCEPTANCE 20.00% 2 80.00% 2 20% 100.00% 20.00% 80.00% 28-Jun-13 3-Jul-13
3.2.1.3 MISCELLANEOUS 11.00% Prep/ Submit Accept/ Approve 75.00% 100.00% -25.00% 10-Sep-12 6-Jun-13
A5570 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 10-Sep-12 10-Sep-12
A5650 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 13-Mar-13 13-Mar-13
D1210 DELIVERY ON SITE (MISCELANCENEOUS) 30.00% 1 80.00% 1 20% 50.00% 100.00% -50.00% 3-Jun-13 4-Jun-13
D1215 MATERIAL ACCEPTANCE 20.00% 1 80.00% 1 20% 50.00% 100.00% -50.00% 5-Jun-13 6-Jun-13
3.2.1.4 GRATING 7.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 7-Sep-12 13-Sep-13
A5690 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 7-Sep-12 7-Sep-12
A5770 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 19-Mar-13 19-Mar-13
D1220 DELIVERY ON SITE (GRATING) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 10-Sep-13 11-Sep-13
D1225 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 12-Sep-13 13-Sep-13
3.2.1.5 M CLIP (INCL. MATERIAL) 6.00% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 27-Sep-12 11-Jun-13
A5810 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 27-Sep-12 27-Sep-12
A5890 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 12-Apr-13 12-Apr-13
A5915 DELIVERY ON SITE (M CLIP) 30.00% 80.00% 20% 0.00% 100.00% -100.00% 6-Jun-13 7-Jun-13
A5917 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 100.00% -100.00% 10-Jun-13 11-Jun-13
3.2.1.6 FIRE BLAST WALL 11.00% Prep/ Submit Accept/ Approve 20.00% 20.00% 0.00% 11-Apr-13 29-Aug-13
2
A5930 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 11-Apr-13 11-Apr-13
A6010 PO ISSUE DATE 30.00% 80.00% 20% 0.00% 0.00% 0.00% 3-Jul-13 3-Jul-13
D1230 DELIVERY ON SITE (FIRE BLAST WALL) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 26-Aug-13 27-Aug-13
D1235 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 28-Aug-13 29-Aug-13
3.2.2 ARCHITECTURAL (ROS) 3.00% Prep/ Submit Accept/ Approve 47.00% 50.00% -3.00% 5-Sep-12 25-Oct-13
3.2.2.1 FIRE RATED DOORS 50.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 6-Sep-12 25-Oct-13
A6050 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 6-Sep-12 6-Sep-12
A6130 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 23-May-13 23-May-13
D1800 DELIVERY ON SITE (FIRE RATED DOORS) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 21-Oct-13 23-Oct-13
D1805 MANUFACTURE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 23-Oct-13 25-Oct-13
3.2.2.2 TEMPORARY SHELTER AND BATHROOM 50.00% Prep/ Submit Accept/ Approve 44.00% 50.00% -6.00% 5-Sep-12 6-Sep-13
A6530 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A6610 PO ISSUE DATE 30.00% 1 80.00% 20% 80.00% 100.00% -20.00% 31-May-13 31-May-13
D1820 DELIVERY ON SITE (TEMPORARY SHELTER) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 3-Sep-13 4-Sep-13
D1825 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 5-Sep-13 6-Sep-13
3.2.3 PIPING (ROS) 25.00% Prep/ Submit Accept/ Approve 58.50% 57.23% 1.27% 13-Sep-12 27-Nov-13
3.2.3.1 PIPING BULKS 30.00% Prep/ Submit Accept/ Approve 75.00% 70.78% 4.22% 14-Sep-12 11-Sep-13
A4010 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 78.90% 21.10% 14-Sep-12 14-Sep-13
A4090 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 18-Mar-13 18-Mar-13
D1250 DELIVERY ON SITE 1st SHIPMENT (PIPING BULKS) 15.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 17-Jun-13 18-Jun-13
D1252 DELIVERY ON SITE 2nd SHIPMENT (PIPING BULKS) 15.00% 80.00% 20% 0.00% 0.00% 0.00% 5-Sep-13 7-Sep-13
D1255 MATERIAL ACCEPTANCE 1st SHIPMENT 10.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 19-Jun-13 20-Jun-13
D1257 MATERIAL ACCEPTANCE 2nd SHIPMENT 10.00% 80.00% 20% 0.00% 0.00% 0.00% 9-Sep-13 11-Sep-13
3.2.3.2 MANUAL VALVES 25.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 14-Sep-12 27-Nov-13
A4130 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 14-Sep-12 14-Sep-12
A4210 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 12-Mar-13 12-Mar-13
D1260 DELIVERY ON SITE (MANUAL VALVES) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 22-Nov-13 25-Nov-13
D1265 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 26-Nov-13 27-Nov-13
3.2.3.3 ACCESS FITTINGS (SAMPLING CONNECTION, CHEMICAL INJECTION, CORROSION COUPON) 5.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 13-Sep-12 29-Aug-13
A4250 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 13-Sep-12 13-Sep-12
A4330 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 14-Mar-13 14-Mar-13
D1270 DELIVERY ON SITE (ACCESS FITTINGS (SAMPLING CONNECTION, CHEMICAL INJECTION, CORROSION COUPON)
30.00% 80.00% 20% 0.00% 0.00% 0.00% 26-Aug-13 27-Aug-13
D1275 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 27-Aug-13 29-Aug-13
3.2.3.4 ADDITIONAL ITEMS FOR SAMPLING CONNECTION 5.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 4-Jan-13 3-Sep-13
A11170 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 4-Jan-13 4-Jan-13
A11180 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 7-May-13 7-May-13
A11185 DELIVERY ON SITE (ADDITIONAL ITEMS FOR SAMPLING CONNECTION) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 28-Aug-13 29-Aug-13
A11190 MATERIAL ACCEPTANCE (ADDITIONAL ITEMS FOR SAMPLING CONNECTION) 20.00% 80.00% 20% 0.00% 0.00% 0.00% 30-Aug-13 3-Sep-13
3.2.3.5 HOSES AND COUPLINGS 5.00% Prep/ Submit Accept/ Approve 20.00% 20.00% 0.00% 14-Sep-12 5-Nov-13
A4370 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 14-Sep-12 14-Sep-12
A4450 PO ISSUE DATE 30.00% 80.00% 20% 0.00% 0.00% 0.00% 19-Jul-13 19-Jul-13
D1280 DELIVERY ON SITE (HOSES AND COUPLINGS) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 31-Oct-13 1-Nov-13
D1285 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 4-Nov-13 5-Nov-13
3.2.3.6 BUG SCREEN 5.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 19-Sep-12 2-Aug-13
A4490 RFP TO VENDOR 20.00% 1.0 80.00% 1 20% 100.00% 100.00% 0.00% 19-Sep-12 19-Sep-12
A4570 PO ISSUE DATE 30.00% 1.0 80.00% 1 20% 100.00% 100.00% 0.00% 12-Mar-13 12-Mar-13
D1290 DELIVERY ON SITE (BUG SCREEN) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 30-Jul-13 30-Jul-13
D1295 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 1-Aug-13 2-Aug-13
3.2.3.7 STRAINER 5.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 19-Sep-12 6-Sep-13
A4610 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 19-Sep-12 19-Sep-12
A4690 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 3-May-13 3-May-13
D1300 DELIVERY ON SITE (STRAINER) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 3-Sep-13 4-Sep-13
D1305 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 5-Sep-13 6-Sep-13
3.2.3.8 CONTINUOUS DRAINERS 5.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 14-Sep-12 29-Aug-13
A4730 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 14-Sep-12 14-Sep-12
A4810 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 24-May-13 24-May-13
D1310 DELIVERY ON SITE (CONTINUOUS DRAINERS) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 26-Aug-13 27-Aug-13
D1315 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 0.00% 0.00% 28-Aug-13 29-Aug-13
3.2.3.10 SIGHT GLASS 5.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 17-Sep-12 20-Sep-13
A4970 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 17-Sep-12 17-Sep-12
A5050 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 2-Apr-13 2-Apr-13
D1340 DELIVERY ON SITE (SIGN GLASS) 30.00% 80.00% 20% 0.00% 0.00% 0.00% 17-Sep-13 18-Sep-13
3
A5170 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 10-May-13 10-May-13
D1350 DELIVERY ON SITE (FLAME ARESTOR) 30.00% 80.00% 20% 0.00% 100.00% -100.00% 26-Aug-13 27-Aug-13
D1355 MATERIAL ACCEPTANCE 20.00% 80.00% 20% 0.00% 100.00% -100.00% 28-Aug-13 29-Aug-13
3.2.3.12 PIPING SUPPORT 5.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 18-Sep-12 4-Jun-13
A5210 RFP TO VENDOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 18-Sep-12 18-Sep-12
A5290 PO ISSUE DATE 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 22-Feb-13 22-Feb-13
A5310 DELIVERY ON SITE (PIPING SUPPORT) 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 30-May-13 31-May-13
A5315 MATERIAL ACCEPTANCE 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 3-Jun-13 4-Jun-13
3.2.4 MECHANICAL (ROS) 20.00% Prep/ Submit Accept/ Approve 47.62% 100.00% -52.38% 5-Sep-12 3-Jan-14
3.2.4.1 GAS OPERATED PUMP 8.32% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 5-Sep-12 26-Sep-13
A7010 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A7090 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 15-Apr-13 15-Apr-13
D1360 DELIVERY ON SITE (PORTABLE CHEMICAL TRANSFER PUMP P-6835) 15.00% 80% 20% 0.00% 100.00% -100.00% 23-Sep-13 24-Sep-13
D1370 DELIVERY ON SITE (OPEN DRAIN PUMP P-6510) 15.00% 80% 20% 0.00% 100.00% -100.00% 23-Sep-13 24-Sep-13
D1375 MATERIAL ACCEPTANCE 20.00% 80% 20% 0.00% 100.00% -100.00% 25-Sep-13 26-Sep-13
3.2.4.2 RECIPROCATING PUMPS 7.71% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 5-Sep-12 3-Jan-14
A7130 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A7210 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 15-May-13 15-May-13
D1380 DELIVERY ON SITE (SCSSV EQUALIZATION INJECTION PUMP P-6720) 15.00% 80% 20% 0.00% 100.00% -100.00% 30-Dec-13 31-Dec-13
D1390 DELIVERY ON SITE (PORTABLE PIPELINE DIESEL INJECTION PUMP P-6730) 15.00% 80% 20% 0.00% 100.00% -100.00% 30-Dec-13 31-Dec-13
D1395 MATERIAL ACCEPTANCE ( PUMP P-6720/ PUMP P-6730) 20.00% 80% 20% 0.00% 100.00% -100.00% 2-Jan-14 3-Jan-14
3.2.4.3 CENTRIFUGAL PUMP (MISC) 7.71% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 5-Sep-12 3-Jan-14
A7250 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A7330 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 15-May-13 15-May-13
D1400 DELIVERY ON SITE (DIESEL TRANSFER PUMP P-6710) 15.00% 80% 20% 0.00% 100.00% -100.00% 30-Dec-13 31-Dec-13
D1410 DELIVERY ON SITE (WASH WATER PUMP P-5110) 15.00% 80% 20% 0.00% 100.00% -100.00% 30-Dec-13 31-Dec-13
D1415 MATERIAL ACCEPTANCE (PUMP P-6710/ PUMP P-5110) 20.00% 80% 20% 0.00% 100.00% -100.00% 2-Jan-14 3-Jan-14
3.2.4.4 TOTE TANKS 6.53% Prep/ Submit Accept/ Approve 44.00% 100.00% -56.00% 5-Sep-12 13-Oct-13
A7370 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A7450 PO ISSUE DATE 30.00% 1 80% 20% 80.00% 100.00% -20.00% 4-Jul-13 4-Jul-13
D1420 DELIVERY ON SITE (PORTABLE CHEMICAL TOTE TANK) 10.00% 80% 20% 0.00% 100.00% -100.00% 8-Nov-13 8-Nov-13
D1430 DELIVERY ON SITE (WAX DISSOLVER STANDARD TOTE TANK T-6850) 10.00% 80% 20% 0.00% 100.00% -100.00% 8-Nov-13 8-Nov-13
D1440 DELIVERY ON SITE (GENERAL PURPOSE TOTE TANK T-5300) 10.00% 80% 20% 0.00% 100.00% -100.00% 8-Nov-13 8-Nov-13
D1445 MATERIAL ACCEPTANCE (TOTE TANKS) 20.00% 80% 20% 0.00% 100.00% -100.00% 12-Nov-13 13-Nov-13
3.2.4.5 RECTANGULAR TANKS 8.27% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 5-Sep-12 29-Oct-13
A7490 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A7570 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 14-May-13 14-May-13
D1450 DELIVERY ON SITE (WASH WATER STORAGE TANK T-5100A/B) 10.00% 80% 20% 0.00% 100.00% -100.00% 24-Oct-13 25-Oct-13
D1460 DELIVERY ON SITE (PORTABLE WATER TANK T-5200) 10.00% 80% 20% 0.00% 100.00% -100.00% 21-Oct-13 22-Oct-13
D1470 DELIVERY ON SITE (OPEN DRAIN TANK T-6500) 5.00% 80% 20% 0.00% 100.00% -100.00% 21-Oct-13 22-Oct-13
D1480 DELIVERY ON SITE (OPEN DRAIN HEATER E-6520) 5.00% 80% 20% 0.00% 100.00% -100.00% 21-Oct-13 22-Oct-13
D1485 MATERIAL ACCEPTANCE (RECTANGULAR TANKS) 20.00% 80% 20% 0.00% 100.00% -100.00% 28-Oct-13 29-Oct-13
3.2.4.6 CLOSED DRAIN TRANSFER PUMP 9.76% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 5-Sep-12 5-Dec-13
A7610 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A7690 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 8-Apr-13 8-Apr-13
D1490 DELIVERY ON SITE (CLOSED DRAIN TRANSFER PUMP P-6410A/B) 30.00% 80% 20% 0.00% 100.00% -100.00% 2-Dec-13 3-Dec-13
D1495 MATERIAL ACCEPTANCE (CLOSED DRAIN TRANSFER PUMP P-6410A/B) 20.00% 80% 20% 0.00% 100.00% -100.00% 4-Dec-13 5-Dec-13
3.2.4.7 SEPATATOR SKID 12.28% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 5-Sep-12 5-Dec-13
A7730 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A7810 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 8-Apr-13 8-Apr-13
D1500 DELIVERY ON SITE (HP SEPARATOR SKID A-1020) 15.00% 80% 20% 0.00% 100.00% -100.00% 2-Dec-13 3-Dec-13
D1510 DELIVERY ON SITE (LP SEPARATOR SKID A-1010) 15.00% 80% 20% 0.00% 100.00% -100.00% 2-Dec-13 3-Dec-13
D1515 MATERIAL ACCEPTANCE (HP SEPARATOR SKID A-1020/ A-1010) 20.00% 80% 20% 0.00% 100.00% -100.00% 4-Dec-13 5-Dec-13
3.2.4.8 NITROGEN BOTTLES 7.91% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 6-Sep-12 30-Sep-13
A7850 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 6-Sep-12 6-Sep-12
A7930 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 25-Apr-13 25-Apr-13
D1520 DELIVERY ON SITE (NITROGEN BOTTLES A-5900) 30.00% 80% 20% 0.00% 100.00% -100.00% 25-Sep-13 26-Sep-13
D1525 MATERIAL ACCEPTANCE (NITROGEN BOTTLES A-5900) 20.00% 80% 20% 0.00% 100.00% -100.00% 27-Sep-13 30-Sep-13
3.2.4.9 CO2 VENT SNUFFING 8.84% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 6-Sep-12 1-Oct-13
A7970 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 6-Sep-12 6-Sep-12
A8050 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 8-Apr-13 9-Apr-13
D1530 DELIVERY ON SITE (CO2 VENT SNUFFING A-8600) 30.00% 80% 20% 0.00% 100.00% -100.00% 26-Sep-13 27-Sep-13
D1535 MATERIAL ACCEPTANCE (CO2 VENT SNUFFING A-8600) 20.00% 80% 20% 0.00% 100.00% -100.00% 30-Sep-13 1-Oct-13
4
3.2.4.10 HANDLING & LIFTING EQUIPMENT 6.17% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 6-Sep-12 29-Oct-13
A8090 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 6-Sep-12 6-Sep-12
A8170 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 29-Apr-13 29-Apr-13
D1540 DELIVERY ON SITE (HANDLING & LIFTING EQUIPMENT) 30.00% 80% 20% 0.00% 100.00% -100.00% 2-Jan-14 3-Jan-14
D1545 MATERIAL ACCEPTANCE (HANDLING & LIFTING EQUIPMENT) 20.00% 80% 20% 0.00% 100.00% -100.00% 4-Jan-14 5-Jan-14
3.2.4.11 SAFETY & FIRE FIGHTING, LIFE SAVING EQUIPMENT 6.63% Prep/ Submit Accept/ Approve 20.00% 100.00% -80.00% 11-Mar-13 24-Oct-13
A8210 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Mar-13 11-Mar-13
A8290 PO ISSUE DATE 30.00% 80% 20% 0.00% 100.00% -100.00% 9-Jul-13 9-Jul-13
D1550 DELIVERY ON SITE (SAFETY & FIRE FIGHTING, LIFE SAVING EQUIPMENT) 30.00% 80% 20% 0.00% 100.00% -100.00% 14-Nov-13 15-Nov-13
D1555 MATERIAL ACCEPTANCE (SAFETY & FIRE FIGHTING, LIFE SAVING EQUIPMENT) 20.00% 80% 20% 0.00% 100.00% -100.00% 18-Nov-13 19-Nov-13
3.2.4.12 AIR CONDITIONING & VENTILATION SYSTEM 9.87% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 7-Sep-12 6-Nov-13
A8330 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 7-Sep-12 7-Sep-12
A8410 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 26-Apr-13 26-Apr-13
D1560 DELIVERY ON SITE (AIR CONDITIONING & VENTILATION SYSTEM) 30.00% 80% 20% 0.00% 100.00% -100.00% 1-Nov-13 4-Nov-13
D1565 MATERIAL ACCEPTANCE (AIR CONDITIONING & VENTILATION SYSTEM) 20.00% 80% 20% 0.00% 100.00% -100.00% 5-Nov-13 6-Nov-13
3.2.5 ELECTRICAL (ROS) 19.00% Prep/ Submit Accept/ Approve 65.57% 100.00% -34.43% 5-Sep-12 5-Dec-13
3.4.5.1 JUCTION BOX AND RCU 9.50% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 10-Sep-12 19-Sep-13
A8450 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 10-Sep-12 10-Sep-12
A8530 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 8-Apr-13 8-Apr-13
D1570 DELIVERY ON SITE (JUCTION BOX AND RCU) 30.00% 80% 20% 0.00% 100.00% -100.00% 16-Sep-13 17-Sep-13
D1575 MATERIAL ACCEPTANCE (JUCTION BOX AND RCU) 20.00% 80% 20% 0.00% 100.00% -100.00% 18-Sep-13 19-Sep-13
3.4.5.2 CABLE GLAND 5.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 10-Sep-12 19-Sep-13
A8560 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 10-Sep-12 10-Sep-12
A8640 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 30-May-13 30-May-13
D1580 DELIVERY ON SITE (CABLE GLAND) 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 16-Sep-13 17-Sep-13
D1585 MATERIAL ACCEPTANCE (CABLE GLAND) 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 18-Sep-13 19-Sep-13
3.4.5.3 CABLES E&I 6.00% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 5-Sep-12 25-Sep-13
A1130 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-12 5-Sep-12
A1210 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 8-May-13 8-May-13
D1590 DELIVERY ON SITE (CABLE E&I) 30.00% 80% 20% 0.00% 100.00% -100.00% 20-Sep-13 23-Sep-13
D1595 MATERIAL ACCEPTANCE (CABLE E&I) 20.00% 80% 20% 0.00% 100.00% -100.00% 24-Sep-13 25-Sep-13
3.4.5.4 CABLE TRAY AND LADDER 6.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 10-Sep-12 6/31/2013
A1250 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 10-Sep-12 10-Sep-12
A1330 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Mar-13 11-Mar-13
A1335 DELIVERY ON SITE (CABLE TRAY AND LADDER) 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 26-Jul-13 29-Jul-13
D1600 MATERIAL ACCEPTANCE (CABLE TRAY AND LADDER) 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 30-Jul-13 31-Jul-13
3.4.5.5 TUBING AND FITTING 6.00% Prep/ Submit Accept/ Approve 75.00% 100.00% -25.00% 11-Sep-12 6-Sep-13
A1370 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Sep-12 11-Sep-12
A1450 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 24-Apr-13 24-Apr-13
A1460 DELIVERY ON SITE (TUBING AND FITTING) 30.00% 2 80% 2 20% 50.00% 100.00% -50.00% 3-Sep-13 4-Sep-13
D1610 MATERIAL ACCEPTANCE (TUBING AND FITTING) 20.00% 2 80% 2 20% 50.00% 100.00% -50.00% 5-Sep-13 6-Sep-13
3.4.5.6 EARTHING BOSS 5.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 11-Sep-12 27-Jun-13
A1490 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Sep-12 11-Sep-12
A1570 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 27-Feb-13 27-Feb-13
A1580 DELIVERY ON SITE (EARTHING BOSS) 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 24-Jun-13 25-Jun-13
D1620 MATERIAL ACCEPTANCE (EARTHING BOSS) 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 26-Jun-13 27-Jun-13
3.4.5.7 SOCKET AND OUTLET 5.00% Prep/ Submit Accept/ Approve 100.00% 100.00% 0.00% 11-Sep-12 6-Sep-13
A1610 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Sep-12 11-Sep-12
A1690 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 14-Jun-13 14-Jun-13
A1700 DELIVERY ON SITE (SOCKET AND OUTLET) 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 3-Sep-13 4-Sep-13
D1630 MATERIAL ACCEPTANCE (SOCKET AND OUTLET) 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 5-Sep-13 6-Sep-13
3.4.5.8 HEAT TRACING 6.00% Prep/ Submit Accept/ Approve 44.00% 100.00% -56.00% 10-Sep-12 28-Oct-13
A1730 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 10-Sep-12 10-Sep-12
A1810 PO ISSUE DATE 30.00% 1 80% 20% 80.00% 100.00% -20.00% 17-Jun-13 17-Jun-13
A1820 DELIVERY ON SITE (HEAT TRACING) 30.00% 80% 20% 0.00% 100.00% -100.00% 23-Oct-13 24-Oct-13
D1640 MATERIAL ACCEPTANCE (HEAT TRACING) 20.00% 80% 20% 0.00% 100.00% -100.00% 25-Oct-13 28-Oct-13
3.4.5.9 LIGHTING & FIXTURES 6.00% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 10-Sep-12 3-Oct-13
A1850 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 10-Sep-12 10-Sep-12
A1930 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 23-May-13 23-May-13
A1940 DELIVERY ON SITE (LIGHTING FITTING) 30.00% 80% 20% 0.00% 100.00% -100.00% 4-Nov-13 5-Nov-13
D1650 MATERIAL ACCEPTANCE (LIGHTING FITTING) 20.00% 80% 20% 0.00% 100.00% -100.00% 6-Nov-13 7-Nov-13
3.4.5.10 MULTI CABLE TRANSIT 5.00% Prep/ Submit Accept/ Approve 50.00% 100.00% -50.00% 12-Sep-12 4-Sep-13
A1970 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 12-Sep-12 12-Sep-12
5
A1930 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 23-May-13 23-May-13
A1940 DELIVERY ON SITE (LIGHTING FITTING) 30.00% 80% 20% 0.00% 0.00% 0.00% 4-Nov-13 5-Nov-13
D1650 MATERIAL ACCEPTANCE (LIGHTING FITTING) 20.00% 80% 20% 0.00% 0.00% 0.00% 6-Nov-13 7-Nov-13
3.4.5.10 MULTI CABLE TRANSIT 5.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 12-Sep-12 4-Sep-13
A1970 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 12-Sep-12 12-Sep-12
A2050 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 22-May-13 22-May-13
A2060 DELIVERY ON SITE (MULTI CABLE TRANSIT) 30.00% 80% 20% 0.00% 0.00% 0.00% 29-Aug-13 30-Aug-13
D1660 MATERIAL ACCEPTANCE (MULTI CABLE TRANSIT) 20.00% 80% 20% 0.00% 0.00% 0.00% 3-Sep-13 4-Sep-13
3.4.5.11 MISCELLANEOUS 5.00% Prep/ Submit Accept/ Approve 83.33% 50.00% 33.33% 14-Sep-12 20-Aug-13
A2090 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 14-Sep-12 14-Sep-12
A2170 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 9-Apr-13 9-Apr-13
A2180 DELIVERY ON SITE (MISCELLANOUES) 30.00% 2 80% 2 20% 66.67% 0.00% 66.67% 7-Aug-13 28-Aug-13
D1670 MATERIAL ACCEPTANCE (MISCELLANOUES) 20.00% 2 80% 2 20% 66.67% 0.00% 66.67% 29-Aug-13 30-Aug-13
3.4.5.12 CONTROL VALVES (PCV, LCV, FCV, ADV) 9.50% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 6-Sep-12 21-Nov-13
A2210 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 6-Sep-12 6-Sep-12
A2290 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 25-Mar-13 25-Mar-13
A2300 DELIVERY ON SITE (CONTROL VALVES (PCV, LCV, FCV, ADV)) 30.00% 80% 20% 0.00% 0.00% 0.00% 2-Dec-13 3-Dec-13
D1680 MATERIAL ACCEPTANCE (CONTROL VALVES (PCV, LCV, FCV, ADV)) 20.00% 80% 20% 0.00% 0.00% 0.00% 4-Dec-13 5-Dec-13
3.4.5.13 NAVIGATION AIDS 5.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 10-Sep-12 22-Oct-13
A2570 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 10-Sep-12 10-Sep-12
A2650 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 4-Apr-13 4-Apr-13
A2660 DELIVERY ON SITE (NAVIGATION AIDS) 30.00% 80% 20% 0.00% 0.00% 0.00% 17-Oct-13 18-Oct-13
D1690 MATERIAL ACCEPTANCE (NAVIGATION AIDS) 20.00% 80% 20% 0.00% 0.00% 0.00% 21-Oct-13 22-Oct-13
3.4.5.14 PUSH BUTTON 5.00% Prep/ Submit Accept/ Approve 100.00% 50.00% 50.00% 14-Sep-12 9-Sep-13
A2930 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 14-Sep-12 14-Sep-12
A3010 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 17-Jun-13 17-Jun-13
A3020 DELIVERY ON SITE (PUSH BUTTON) 30.00% 1 80% 1 20% 100.00% 0.00% 100.00% 4-Sep-13 5-Sep-13
D1700 MATERIAL ACCEPTANCE (PUSH BUTTON) 20.00% 1 80% 1 20% 100.00% 0.00% 100.00% 6-Sep-13 9-Sep-13
3.2.6.10 400V AC LV SWICH BOARD 4.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 17-Sep-12 15-Oct-13
A3650 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 17-Sep-12 17-Sep-12
A3730 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 23-Apr-13 23-Apr-13
A3740 DELIVERY ON SITE (400V AC LV SWICH BOARD) 30.00% 80% 20% 0.00% 0.00% 0.00% 10-Oct-13 11-Oct-13
A3750 MATERIAL ACCEPTANCE (400V AC LV SWICH BOARD) 20.00% 80% 20% 0.00% 0.00% 0.00% 14-Oct-13 15-Oct-13
3.2.6.11 UPS 4.00% Prep/ Submit Accept/ Approve 44.00% 50.00% -6.00% 27-Sep-12 5-Dec-13
A3770 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 27-Sep-12 27-Sep-12
A3850 PO ISSUE DATE 30.00% 1 80% 20% 80.00% 100.00% -20.00% 13-May-13 13-May-13
A3860 DELIVERY ON SITE (UPS) 30.00% 80% 20% 0.00% 0.00% 0.00% 2-Dec-13 3-Dec-13
A3870 MATERIAL ACCEPTACE (UPS) 20.00% 80% 20% 0.00% 0.00% 0.00% 4-Dec-13 5-Dec-13
3.2.6.12 DISTRIBUTION BOARD 4.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 28-Sep-12 25-Oct-13
A3890 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 28-Sep-12 28-Sep-12
A3970 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 24-Apr-13 24-Apr-13
A3980 DELIVERY ON SITE (DISTRIBUTION BOARD) 30.00% 80% 20% 0.00% 0.00% 0.00% 22-Oct-13 23-Oct-13
A3990 MATERIAL ACCEPTANCE (DISTRIBUTION BOARD) 20.00% 80% 20% 0.00% 0.00% 0.00% 24-Oct-13 25-Oct-13
3.2.6.13 HELIDECK LIGHTING 4.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 21-Mar-13 11-Nov-13
A11120 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 21-Mar-13 21-Mar-13
A11130 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 3-Jun-13 3-Jun-13
A11140 DELIVERY ON SITE (HELIDECK LIGHTING) 30.00% 80% 20% 0.00% 0.00% 0.00% 6-Nov-13 7-Nov-13
A11150 MATERIAL ACCEPTANCE (HELIDECK LIGHTING) 20.00% 80% 20% 0.00% 0.00% 0.00% 8-Nov-13 11-Nov-13
3.2.6 INSTRUMENT (ROS) 15.00% 50.00% 47.30% 2.70% 10-Sep-12 3-Jan-14
3.2.6.1 TURBINE FLOWMETTER (GF AND LF) 28.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 12-Sep-12 4-Nov-13
A2330 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 12-Sep-12 12-Sep-12
A2410 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 23-May-13 23-May-13
A2420 DELIVERY ON SITE (TURBINE FLOW TRANSMITTER (GF AND LF)) 30.00% 80% 20% 0.00% 0.00% 0.00% 30-Oct-13 31-Oct-13
D1710 MATERIAL ACCEPTANCE (TURBINE FLOW TRANSMITTER (GF AND LF)) 20.00% 80% 20% 0.00% 0.00% 0.00% 1-Nov-13 4-Nov-13
3.2.6.2 FUSIBLE PLUG LOOP PANEL 9.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 11-Sep-12 3-Sep-13
A2450 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Sep-12 11-Sep-12
A2530 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 8-Mar-13 8-Mar-13
A2540 DELIVERY ON SITE (FUSIBLE PLUG LOOP PANEL) 30.00% 80% 20% 0.00% 0.00% 0.00% 28-Aug-13 29-Aug-13
D1720 MATERIAL ACCEPTANCE (FUSIBLE PLUG LOOP PANEL) 20.00% 80% 20% 0.00% 0.00% 0.00% 30-Aug-13 3-Sep-13
3.2.6.3 PIG SIGNALLER 9.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 10-Sep-12 3-Jan-14
A2690 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 10-Sep-12 10-Sep-12
A2770 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 22-Apr-13 22-Apr-13
6
A2780 DELIVERY ON SITE (PIG SIGNALLER) 30.00% 80% 20% 0.00% 0.00% 0.00% 30-Dec-13 31-Dec-13
D1730 MATERIAL ACCEPTANCE (PIG SIGNALLER) 20.00% 80% 20% 0.00% 0.00% 0.00% 2-Jan-14 3-Jan-14
3.2.6.4 SAFETY RELIEF VALVE 9.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 11-Sep-12 7-Nov-13
A2810 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Sep-12 11-Sep-12
A2890 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 18-Mar-13 18-Mar-13
A2900 DELIVERY ON SITE (SAFETY RELIEF VALVE) 30.00% 80% 20% 0.00% 0.00% 0.00% 4-Nov-13 5-Nov-13
D1740 MATERIAL ACCEPTANCE (SAFETY RELIEF VALVE) 20.00% 80% 20% 0.00% 0.00% 0.00% 6-Nov-13 7-Nov-13
3.2.6.5 RESTRICTION ORIFICES, ORIFICES PLATE AND FLANGES 9.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 14-Sep-12 11-Oct-13
A3050 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 14-Sep-12 14-Sep-12
A3130 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 24-May-13 24-May-13
A3140 DELIVERY ON SITE (RESTRICTION ORIFICES, ORIFICES PLATE AND FLANGES) 30.00% 80% 20% 0.00% 0.00% 0.00% 8-Oct-13 9-Oct-13
D1750 MATERIAL ACCEPTANCE (RESTRICTION ORIFICES, ORIFICES PLATE AND FLANGES) 20.00% 80% 20% 0.00% 0.00% 0.00% 10-Oct-13 11-Oct-13
3.2.6.6 SAND MONITORING 9.00% Prep/ Submit Accept/ Approve 50.00% 20.00% 30.00% 12-Sep-12 19-Sep-13
A3170 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 12-Sep-12 12-Sep-12
A3250 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 0.00% 100.00% 4-Jul-13 4-Jul-13
A3260 DELIVERY ON SITE (SAND MONITORING) 30.00% 80% 20% 0.00% 0.00% 0.00% 9-Oct-13 10-Oct-13
D1760 MATERIAL ACCEPTANCE (SAND MONITORING) 20.00% 80% 20% 0.00% 0.00% 0.00% 11-Oct-13 14-Oct-13
3.2.6.7 PRESSURE GAUGES 9.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 11-Sep-12 24-Oct-13
A3290 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Sep-12 11-Sep-12
A3370 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 3-Jun-13 3-Jun-13
A3380 DELIVERY ON SITE (PRESSURE GAUGES (PG, PDG, TG)) 30.00% 80% 20% 0.00% 0.00% 0.00% 21-Oct-13 22-Oct-13
D1780 MATERIAL ACCEPTANCE (PRESSURE GAUGES (PG, PDG, TG)) 20.00% 80% 20% 0.00% 0.00% 0.00% 23-Oct-13 24-Oct-13
3.2.6.8 PRESSURE REGULATOR VALVES 9.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 11-Sep-12 18-Oct-13
A3410 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 11-Sep-12 11-Sep-12
A3490 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 9-May-13 9-May-13
A3500 DELIVERY ON SITE (PRESSURE REGULATOR VALVES) 30.00% 80% 20% 0.00% 0.00% 0.00% 15-Oct-13 16-Oct-13
A3510 MATERIAL ACCEPTANCE (PRESSURE REGULATOR VALVES) 20.00% 80% 20% 0.00% 0.00% 0.00% 17-Oct-13 18-Oct-13
3.2.6.9 LEVEL GAUGES 9.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 14-Sep-12 27-Oct-13
A3530 RFP TO VENDOR 20.00% 1 80% 1 20% 100.00% 100.00% 0.00% 14-Sep-12 14-Sep-12
A3610 PO ISSUE DATE 30.00% 1 80% 1 20% 100.00% 100.00% 0.00% 15-Mar-13 15-Mar-13
A3620 DELIVERY ON SITE (LEVEL GAUGES) 30.00% 80% 20% 0.00% 0.00% 0.00% 22-Oct-13 25-Oct-13
D1790 MATERIAL ACCEPTANCE (LEVEL GAUGES) 20.00% 80% 20% 0.00% 0.00% 0.00% 26-Oct-13 27-Oct-13
4 CONSTRUCTION 43.00% 20.55% 17.00% 3.55% 4-Jan-13 10-Mar-14
4.1 FRONT-END ACTIVITIES/ MOBILIZATION 20.00% 70.33% 65.52% 4.81% 4-Jan-13 8-Jan-14
4.1.1 MOBILIZATION OF PROJECT MANAGEMENT TEAM (PER APPROVED ORGANISATION CHART) 8.00%Prep/ Submit Accept 100.00% 100.00% 0.00% 19-Feb-13 26-Feb-13
B1000 MOBILISATION OF PROJECT MANAGEMENT TEAM 100.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 19-Feb-13 26-Feb-13
4.1.2 PROJECT PLANNING AND MONITORING FORMAT 3.00%Prep/ Submit Accept 95.00% 100.00% -5.00% 30-Mar-13 21-May-13
B1010 60 DAYS SCHEDULE 50.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 30-Mar-13 9-Apr-13
B1015 PLANING PACKAGE 50.00% 2 80.00% 1 20% 90.00% 100.00% -10.00% 10-Apr-13 21-May-13
4.1.3 YARD PREPARATIONS 15.00%Prep/ Submit Accept 100.00% 100.00% 0.00% 30-Jan-13 15-Mar-13
B1020 FABRICATION YARD PREPARATION 33.77% 1 80.00% 1 20% 100.00% 100.00% 0.00% 20-Feb-13 15-Mar-13
B1030 SITE OFFICE PREPARATION 19.38% 1 80.00% 1 20% 100.00% 100.00% 0.00% 6-Feb-13 15-Mar-13
B1040 BUILD UP MATERIAL AND EQUIPMENT STORAGE AND FENCE PREPARATION 19.38% 1 80.00% 1 20% 100.00% 100.00% 0.00% 30-Jan-13 1-Mar-13
B1050 WORKSHOP AND FACILITIES PREPARATION 27.47% 1 80.00% 1 20% 100.00% 100.00% 0.00% 8-Feb-13 12-Mar-13
4.1.4 CONCRETE FOUNDATION / TEMPORARY SUPPORT FABRICATION 52.00%COMPLETED ACCEPTED 66.00% 59.61% 6.39% 9-May-13 11-Oct-13
4.1.4.1 CONCRETE FOUNDATION/ TEMPORARY SUPPORTS AT FINAL POSITION FABRICATION 30.00% COMPLETED ACCEPTED 20.00% 0.00% 20.00% 6-Jul-13 21-Aug-13
4.1.4.1.1 TEMPORARY SUPPORTS AT FINAL POSITION FABRICATION 80.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 24-Jul-13 21-Aug-13
A8940 MARK/ CUT TEMPORARY SUPPORTS AT FINAL POSITION 15.00% 80.00% 20% 0.00% 0.00% 0.00% 24-Jul-13 3-Aug-13
A8950 FIT UP TEMPORARY SUPPORTS AT FINAL POSITION 40.00% 80.00% 20% 0.00% 0.00% 0.00% 26-Jul-13 12-Aug-13
A8960 WELDING TEMPORARY SUPPORTS AT FINAL POSITION 30.00% 80.00% 20% 0.00% 0.00% 0.00% 29-Jul-13 17-Aug-13
A8970 NDT TEMPORARY SUPPORTS AT FINAL POSITION 15.00% 80.00% 20% 0.00% 0.00% 0.00% 3-Aug-13 21-Aug-13
4.1.4.1.2 CONCRETE FOUNDATION SUPPORTS AT FINAL POSITION FABRICATION 20.00% COMPLETED ACCEPTED 100.00% 0.00% 100.00% 6-Jul-13 9-Aug-13
A8980 CONCRETE FOUNDATION SUPPORTS AT FINAL POSITION 100.00% 4 80.00% 4 20% 100.00% 0.00% 100.00% 6-Jul-13 9-Aug-13
4.1.4.2 CONCRETE FOUNDATION/ TEMPORARY SUPPORTS CELLAR DECK FABRICATION 30.00% COMPLETED ACCEPTED 100.00% 100.00% 0.00% 9-May-13 25-May-13
4.1.4.2.1 TEMPORARY SUPPORTS CELLAR DECK FABRICATION 80.00% COMPLETED ACCEPTED 100.00% 100.00% 0.00% 9-May-13 25-May-13
A8840 MARK/ CUT TEMPORARY SUPPORTS CELLAR DECK 15.00% 119 80.00% 119 20% 100.00% 100.00% 0.00% 9-May-13 18-May-13
A8850 FIT UP TEMPORARY SUPPORTS CELLAR DECK 40.00% 119 80.00% 119 20% 100.00% 100.00% 0.00% 11-May-13 21-May-13
A8860 WELDING TEMPORARY SUPPORTS CELLAR DECK 30.00% 119 80.00% 119 20% 100.00% 100.00% 0.00% 14-May-13 23-May-13
A8870 NDT TEMPORARY SUPPORTS CELLAR DECK 15.00% 119 80.00% 119 20% 100.00% 100.00% 0.00% 16-May-13 25-May-13
4.1.4.2.2 CONCRETE FOUNDATION SUPPORTS CELLAR DECK FABRICATION 20.00% COMPLETED ACCEPTED 100.00% 100.00% 0.00% 9-May-13 18-May-13
A8880 CONCRETE FOUNDATION SUPPORTS CELLAR DECK FABRICATION 100.00% 4 80.00% 4 20% 100.00% 100.00% 0.00% 9-May-13 18-May-13
4.1.4.3 CONCRETE FOUNDATION/ TEMPORARY SUPPORTS MAIN DECK FABRICATION 30.00% COMPLETED ACCEPTED 100.00% 75.55% 24.45% 10-Jun-13 9-Jul-13
7
4.1.4.3.1 TEMPORARY SUPPORTS MAIN DECK FABRICATION 80.00% COMPLETED ACCEPTED 100.00% 69.44% 30.56% 13-Jun-13 9-Jul-13
A8990 MARK/ CUT TEMPORARY SUPPORTS MAIN DECK 15.00% 122 80.00% 122 20% 100.00% 100.00% 0.00% 13-Jun-13 24-Jun-13
A9000 FIT UP TEMPORARY SUPPORTS MAIN DECK 40.00% 122 80.00% 122 20% 100.00% 82.35% 17.65% 15-Jun-13 2-Jul-13
A9010 WELDING TEMPORARY SUPPORTS MAIN DECK 30.00% 122 80.00% 122 20% 100.00% 55.00% 45.00% 18-Jun-13 8-Jul-13
A9020 NDT TEMPORARY SUPPORTS MAIN DECK 15.00% 122 80.00% 122 20% 100.00% 33.33% 66.67% 24-Jun-13 9-Jul-13
4.1.4.3.2 CONCRETE FOUNDATION SUPPORTS MAIN DECK FABRICATION 20.00% COMPLETED ACCEPTED 100.00% 100.00% 0.00% 10-Jun-13 26-Jun-13
A9030 CONCRETE FOUNDATION SUPPORTS MAIN DECK 100.00% 4 80.00% 4 20% 100.00% 100.00% 0.00% 10-Jun-13 26-Jun-13
4.1.4.4 TEMPORARY SUPPORTS VENT BOOM FABRICATION 10.00% COMPLETED ACCEPTED 0.00% 69.44% -69.44% 16-Sep-13 11-Oct-13
A9040 MARK/ CUT TEMPORARY SUPPORTS MAIN DECK 15.00% 80.00% 20% 0.00% 100.00% -100.00% 13-Jun-13 24-Jun-13
A9050 FIT UP TEMPORARY SUPPORTS MAIN DECK 40.00% 80.00% 20% 0.00% 82.35% -82.35% 15-Jun-13 2-Jul-13
A9060 WELDING TEMPORARY SUPPORTS MAIN DECK 30.00% 80.00% 20% 0.00% 55.00% -55.00% 18-Jun-13 8-Jul-13
A9070 NDT TEMPORARY SUPPORTS MAIN DECK 15.00% 80.00% 20% 0.00% 33.33% -33.33% 24-Jun-13 9-Jul-13
4.1.5 MOBILISATION OF SUB-CONTRACTOR 18.00%Prep/ Submit Accept 36.40% 30.00% 6.40% 4-Jan-13 19-Dec-13
4.1.5.1 MOBILISATION OF DETAIL ENGINEEING SUB-CONTRACTOR 10.00% Prep/ Submit Accept 100.00% 100.00% 0.00% 9-Mar-13 6-May-13
B11360 TENDER D.E SUB-CONTRACTOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 9-Mar-13 12-Apr-13
B11370 AWARD D.E SUB-CONTRACTOR 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 13-Apr-13 16-Apr-13
B11380 MOBILISE D.E SUB-CONTRACTOR (READY TO COMMENCE WORK) 50.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 2-May-13 6-May-13
4.1.5.2 MOBILISATION OF NDT SUB-CONTRACTOR 20.00% Prep/ Submit Accept 100.00% 100.00% 0.00% 9-Mar-13 6-May-13
B1130 TENDERING SUB-CONTRACTOR 20.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 9-Mar-13 12-Apr-13
B1140 AWARD TO SUB-CONTRACTOR 30.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 13-Apr-13 16-Apr-13
B1150 MOBILISE SUB-CONTRACTOR (READY TO COMMENCE WORK) 50.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 2-May-13 6-May-13
4.1.5.3 MOBILISATION OF HEAT TREATMENT SUB-CONTRACTOR 20.00% Prep/ Submit Accept 16.00% 0.00% 16.00% 16-Sep-13 18-Nov-13
B11390 TENDER HEAT TREATMENT SUB-CONTRACTOR 20.00% 1 80.00% 20% 80.00% 0.00% 80.00% 16-Sep-13 19-Oct-13
B11400 AWARD HEAT TREATMENT SUB-CONTRACTOR 30.00% 80.00% 20% 0.00% 0.00% 0.00% 29-Oct-13 31-Oct-13
B11410 MOBILISE HEAT TREATMENT SUB-CONTRACTOR (READY TO COMMENCE WORK) 50.00% 80.00% 20% 0.00% 0.00% 0.00% 14-Nov-13 18-Nov-13
4.1.5.4 MOBILISATION OF LEAK TEST & BOLT TENSIONING SUB-CONTRACTOR 20.00% Prep/ Submit Accept 16.00% 0.00% 16.00% 16-Sep-13 18-Nov-13
B1160 TENDERING SUB-CONTRACTOR 20.00% 1 80.00% 20% 80.00% 0.00% 80.00% 16-Sep-13 19-Oct-13
B1170 AWARD TO SUB-CONTRACTOR 30.00% 80.00% 20% 0.00% 0.00% 0.00% 29-Oct-13 31-Oct-13
B1180 MOBILISE SUB-CONTRACTOR (READY TO COMMENCE WORK) 50.00% 80.00% 20% 0.00% 0.00% 0.00% 14-Nov-13 18-Nov-13
4.1.5.5 MOBILISATION OF INSULATION SUB-CONTRACTOR 20.00% Prep/ Submit Accept 0.00% 0.00% 0.00% 24-Oct-13 19-Dec-13
B11420 TENDERING INSULATION SUB-CONTRACTOR 20.00% 80.00% 20% 0.00% 0.00% 0.00% 24-Oct-13 20-Nov-13
B11430 AWARD INSULATION SUB-CONTRACTOR 30.00% 80.00% 20% 0.00% 0.00% 0.00% 21-Nov-13 4-Dec-13
B11440 MOBILISE INSULATION SUB-CONTRACTOR (READY TO COMMENCE WORK) 50.00% 80.00% 20% 0.00% 0.00% 0.00% 18-Dec-13 19-Dec-13
4.1.5.6 MOBILISATION OF WEIGHING & LOAD OUT SUB-CONTRACTOR 10.00% Prep/ Submit Accept 0.00% 0.00% 0.00% 24-Oct-13 19-Dec-13
B1190 TENDER SUB-CONTRACTOR 20.00% 80.00% 20% 0.00% 0.00% 0.00% 24-Oct-13 20-Nov-13
B1200 AWARD SUB-CONTRACTOR 30.00% 80.00% 20% 0.00% 0.00% 0.00% 21-Nov-13 4-Dec-13
B1210 MOBILISE SUB-CONTRACTOR (READY TO COMMENCE WORK) 50.00% 80.00% 20% 0.00% 0.00% 0.00% 18-Dec-13 19-Dec-13
4.1.6 WQT & WPS 3.00%Prep/ Submit Accept 87.00% 70.67% 16.33% 28-Mar-13 11-Jun-13
B1220 PREPARATION PQR/ WPS FOR STRUCTURAL 25.00% 1 80.00% 1 20% 100.00% 100.00% 0.00% 28-Mar-13 4-May-13
B1230 PRE-QUALITIFICATION STRUCTURE WELDER 25.00% 3 80.00% 3 20% 100.00% 100.00% 0.00% 6-May-13 23-May-13
B1240 PREPARATION PQR/ WPS FOR PIPING 25.00% 10 80.00% 4 20% 88.00% 82.69% 5.31% 17-May-13 8-Jul-13
B1250 PREPARATION WQT FOR PIPING 25.00% 2 80.00% 1 20% 60.00% 0.00% 60.00% 2-Jul-13 30-Jul-13
4.1.7 PANEL COATING SYSTEM QUALIFICATION TEST 1.00%Prep/ Submit Accept 100.00% 100.00% 0.00% 15-May-13 11-Jun-13
B1260 PANEL TEST/ COATING SYSTEM QUALIFICATION TEST 100.00% 1 70.00% 1 30% 100.00% 100.00% 0.00% 15-May-13 11-Jun-13
4.2 ONSHORE FABRICATION 64.00% 9.65% 5.60% 4.05% 20-Apr-13 28-Feb-14
4.2.1 STRUCTURAL 50.00% 15.79% 8.96% 6.83% 21-May-13 27-Jan-14
4.2.1.1 FABRICATION OF TUBULARS 5.00% ACCEPTED 100.00% 26.54% 73.46% 1-Jun-13 13-Aug-13
4.2.1.1.1 FABRICATION OF PIPE LEGS 40.00% COMPLETED ACCEPTED 100.00% 66.35% 33.65% 1-Jun-13 13-Jul-13
E1550 MARK/ CUT PIPE LEGS 15.00% COMPLETED ACCEPTED 100.00% 100.00% 0.00% 1-Jun-13 21-Jun-13
TRA-05 3.13% 1 80% 1.0 20% 100.00%
TRA-06 8.97% 1 80% 1.0 20% 100.00%
TRA-07 8.19% 1 80% 1.0 20% 100.00%
TRA-11 3.13% 1 80% 1.0 20% 100.00%
TRA-12 5.63% 1 80% 1.0 20% 100.00%
TRA-13 4.21% 1 80% 1.0 20% 100.00%
TRA-14 11.65% 1 80% 1.0 20% 100.00%
8
TRB-12 4.54% 1 80% 1.0 20% 100.00%
TRB-13 10.72% 1 80% 1.0 20% 100.00%
TRB-14 10.72% 1 80% 1.0 20% 100.00%
E1560 FIT UP PIPE LEGS 40.00% COMPLETED ACCEPTED 100.00% 72.73% 27.27% 13-Jun-13 5-Jul-13
TRA-05 3.13% 1 80% 1 20% 100.00%
TRA-06 8.97% 1 80% 1 20% 100.00%
TRA-07 8.19% 1 80% 1 20% 100.00%
TRA-11 3.13% 1 80% 1 20% 100.00%
TRA-12 5.63% 1 80% 1 20% 100.00%
TRA-13 4.21% 1 80% 1 20% 100.00%
TRA-14 11.65% 1 80% 1 20% 100.00%
0.00% 80% 20% 0.00%
TRB-05 3.76% 1 80% 1 20% 100.00%
TRB-06 8.35% 1 80% 1 20% 100.00%
TRB-07 8.19% 1 80% 1 20% 100.00%
TRB-11/1 4.39% 1 80% 1 20% 100.00%
TRB-11/2 4.43% 1 80% 1 20% 100.00%
TRB-12 4.54% 1 80% 1 20% 100.00%
TRB-13 10.72% 1 80% 1 20% 100.00%
TRB-14 10.72% 1 80% 1 20% 100.00%
E1570 WELDING PIPE LEGS 30.00% COMPLETED ACCEPTED 100.00% 56.00% 44.00% 15-Jun-13 10-Jul-13
TRA-05 3.13% 1 80% 1 20% 100.00%
TRA-06 8.97% 1 80% 1 20% 100.00%
TRA-07 8.19% 1 80% 1 20% 100.00%
TRA-11 3.13% 1 80% 1 20% 100.00%
TRA-12 5.63% 1 80% 1 20% 100.00%
TRA-13 4.21% 1 80% 1 20% 100.00%
TRA-14 11.65% 1 80% 1 20% 100.00%
0.00% 80% 20% 0.00%
TRB-05 3.76% 1 80% 1 20% 100.00%
TRB-06 8.35% 1 80% 1 20% 100.00%
TRB-07 8.19% 1 80% 1 20% 100.00%
TRB-11/1 4.39% 1 80% 1 20% 100.00%
TRB-11/2 4.43% 1 80% 1 20% 100.00%
TRB-12 4.54% 1 80% 1 20% 100.00%
TRB-13 10.72% 1 80% 1 20% 100.00%
TRB-14 10.72% 1 80% 1 20% 100.00%
E1580 NDT PIPE LEGS 15.00% COMPLETED ACCEPTED 100.00% 36.36% 63.64% 21-Jun-13 13-Jul-13
TRA-05 3.13% 1 80% 1 20% 100.00%
TRA-06 8.97% 1 80% 1 20% 100.00%
TRA-07 8.19% 1 80% 1 20% 100.00%
TRA-11 3.13% 1 80% 1 20% 100.00%
TRA-12 5.63% 1 80% 1 20% 100.00%
TRA-13 4.21% 1 80% 1 20% 100.00%
TRA-14 11.65% 1 80% 1 20% 100.00%
0.00% 80% 20% 0.00%
TRB-05 3.76% 1 80% 1 20% 100.00%
TRB-06 8.35% 1 80% 1 20% 100.00%
TRB-07 8.19% 1 80% 1 20% 100.00%
TRB-11/1 4.39% 1 80% 1 20% 100.00%
TRB-11/2 4.43% 1 80% 1 20% 100.00%
TRB-12 4.54% 1 80% 1 20% 100.00%
TRB-13 10.72% 1 80% 1 20% 100.00%
TRB-14 10.72% 1 80% 1 20% 100.00%
4.2.1.1.2 FABRICATION OF BRACING 60.00% COMPLETED ACCEPTED 100.00% 0.00% 100.00% 6-Jul-13 13-Aug-13
E1670 MARK/ CUT BRACING PIPE 15.00% COMPLETED ACCEPTED 100.00% 0.00% 100.00% 6-Jul-13 19-Jul-13
TRA-01 1.12% 1.0 80% 1.0 20% 100.00%
TRA-02 1.89% 1.0 80% 1.0 20% 100.00%
TRA-03/1 0.88% 1.0 80% 1.0 20% 100.00%
TRA-03/2 0.44% 1.0 80% 1.0 20% 100.00%
TRA-04 1.84% 1.0 80% 1.0 20% 100.00%
TRA-08 8.27% 1.0 80% 1.0 20% 100.00%
9
TRA-09 1.25% 1.0 80% 1.0 20% 100.00%
TRA-10 8.16% 1.0 80% 1.0 20% 100.00%
TRA-15 2.34% 1.0 80% 1.0 20% 100.00%
TRA-16/1 0.61% 1.0 80% 1.0 20% 100.00%
TRA-16/2 0.20% 1.0 80% 1.0 20% 100.00%
TRA-16/3 0.43% 1.0 80% 1.0 20% 100.00%
TRA-17/1 0.81% 1.0 80% 1.0 20% 100.00%
TRA-17/2 1.62% 1.0 80% 1.0 20% 100.00%
TRA-18/1 0.17% 1.0 80% 1.0 20% 100.00%
TRA-18/2 0.88% 1.0 80% 1.0 20% 100.00%
10
TRA-17/2 1.62% 1.0 80% 1.0 20% 100.00%
TRA-18/1 0.17% 1.0 80% 1.0 20% 100.00%
TRA-18/2 0.88% 1.0 80% 1.0 20% 100.00%
11
TRB-04 2.06% 1.0 80% 1.0 20% 100.00%
TRB-08 8.27% 1.0 80% 1.0 20% 100.00%
TRB-09 1.25% 1.0 80% 1.0 20% 100.00%
TRB-10 8.16% 1.0 80% 1.0 20% 100.00%
TRB-15 2.83% 1.0 80% 1.0 20% 100.00%
TRB-16 1.39% 1.0 80% 1.0 20% 100.00%
TRB-17/1 0.33% 1.0 80% 1.0 20% 100.00%
TRB-17/2 0.33% 1.0 80% 1.0 20% 100.00%
TRB-18/1 0.72% 1.0 80% 1.0 20% 100.00%
TRB-18/2 0.38% 1.0 80% 1.0 20% 100.00%
12
TRB-17/2 0.33% 1.0 80% 1.0 20% 100.00%
TRB-18/1 0.72% 1.0 80% 1.0 20% 100.00%
TRB-18/2 0.38% 1.0 80% 1.0 20% 100.00%
13
CP-108/4B 1.76% 1 80% 1 20% 100.00%
A11310 NDT WF FOR CELLAR DECK 15.00% COMPLETED ACCEPTED 100.00% 100.00% 0.00% 11-Jun-13 15-Jun-13
CP-107/1 13.21% 1 80% 1 20% 100.00%
CP-107/2 24.95% 1 80% 1 20% 100.00%
CP-107/3 8.96% 1 80% 1 20% 100.00%
CP-107/4A 1.76% 1 80% 1 20% 100.00%
CP-107/4B 1.76% 1 80% 1 20% 100.00%
CP-108/1 12.88% 1 80% 1 20% 100.00%
CP-108/2 24.31% 1 80% 1 20% 100.00%
CP-108/3 8.63% 1 80% 1 20% 100.00%
CP-108/4A 1.76% 1 80% 1 20% 100.00%
CP-108/4B 1.76% 1 80% 1 20% 100.00%
4.2.1.2.1.2 FABRICATION OF CELLAR DECK PART II 35.00% COMPLETED ACCEPTED 33.41% 40.11% -6.70% 21-May-13 12-Aug-13
4.2.1.2.1.2.1 FABRICATION OF PRIMARY FRAME PART II 40.00% 60.00% 72.00% -12.00% 21-May-13 10-Jul-13
A9078 LAYOUT TEMPORARY SUPPORTS FOR CELLAR DECK PART II 5.00% 40.0 80% 40.0 20% 100.00% 100.00% 0.00% 21-May-13 27-May-13
A9079 INSTALL PIPE LEGS FOR CELLAR DECK PART II 5.00% 4.0 80% 4.0 20% 100.00% 100.00% 0.00% 5-Jun-13 8-Jun-13
A9080 MARK/ CUT PRIMARY FRAME FOR CELLAR DECK PART II 10.00% 100.00% 100.00% 0.00% 1-Jun-13 14-Jun-13
A9090 FIT UP PRIMARY FRAME FOR CELLAR DECK PART II 40.00% 100.00% 100.00% 0.00% 10-Jun-13 26-Jun-13
A9100 WELDING PRIMARY FRAME FOR CELLAR DECK PART II 30.00% 0.00% 40.00% -40.00% 25-Jun-13 5-Jul-13
A9110 NDT PRIMARY FRAME FOR CELLAR DECK PART II 10.00% 0.00% 0.00% 0.00% 29-Jun-13 10-Jul-13
4.2.1.2.1.2.2 FABRICATION OF SECONDARY FRAME PART II 30.00% COMPLETED ACCEPTED 22.57% 22.50% 0.07% 13-Jun-13 20-Jul-13
A9120 MARK/ CUT SECONDARY FRAME FOR CELLAR DECK PART II 15.00% 100.00% 100.00% 0.00% 13-Jun-13 26-Jun-13
A9130 FIT UP SECONDARY FRAME FOR CELLAR DECK PART II 40.00% 18.92% 18.75% 0.17% 26-Jun-13 12-Jul-13
A9140 WELDING SECONDARY FRAME FOR CELLAR DECK PART II 30.00% 0.00% 0.00% 0.00% 1-Jul-13 17-Jul-13
A9150 NDT SECONDARY FRAME FOR CELLAR DECK PART II 15.00% 0.00% 0.00% 0.00% 4-Jul-13 20-Jul-13
4.2.1.2.1.2.3 FABRICATION OF JOINT DETAIL PART II 10.00% COMPLETED ACCEPTED 26.40% 41.82% -15.42% 5-Jun-13 24-Jul-13
A9160 MARK/ CUT JOINT DETAIL FOR CELLAR DECK PART II 15.00% 78.83% 100.00% -21.17% 5-Jun-13 21-Jun-13
A9170 FIT UP JOINT DETAIL FOR CELLAR DECK PART II 40.00% 36.44% 50.00% -13.56% 15-Jun-13 13-Jul-13
A9180 WELDING JOINT DETAIL FOR CELLAR DECK PART II 30.00% 0.00% 22.73% -22.73% 24-Jun-13 16-Jul-13
A9190 NDT JOINT DETAIL FOR CELLAR DECK PART II 15.00% 0.00% 0.00% 0.00% 2-Jul-13 24-Jul-13
4.2.1.2.1.2.4 FABRICATION OF DECK PLATING PART II 20.00% COMPLETED ACCEPTED 0.00% 1.88% -1.88% 27-Jun-13 12-Aug-13
A9200 MARK/ CUT DECK PLATING FOR CELLAR DECK PART II 15.00% 80% 20% 0.00% 12.50% -12.50% 27-Jun-13 13-Jul-13
A9210 FIT UP DECK PLATING FOR CELLAR DECK PART II 40.00% 80% 20% 0.00% 0.00% 0.00% 9-Jul-13 31-Jul-13
A9220 WELDING DECK PLATING FOR CELLAR DECK PART II 30.00% 80% 20% 0.00% 0.00% 0.00% 15-Jul-13 6-Aug-13
A9230 NDT DECK PLATING FOR CELLAR DECK PART II 15.00% 80% 20% 0.00% 0.00% 0.00% 20-Jul-13 12-Aug-13
4.2.1.2.1.3 FABRICATION OF CELLAR DECK PART III 30.00% COMPLETED ACCEPTED 28.63% 34.65% -6.02% 27-May-13 21-Aug-13
4.2.1.2.1.3.1 FABRICATION OF PRIMARY FRAME PART III 40.00% COMPLETED ACCEPTED 70.29% 65.45% 4.83% 27-May-13 12-Jul-13
A9778 LAYOUT TEMPORARY SUPPORTS FOR CELLAR DECK PART III 10.00% 40.0 80% 40.0 20% 100.00% 100.00% 0.00% 27-May-13 1-Jun-13
A9780 MARK/ CUT PRIMARY FRAME FOR CELLAR DECK PART III 10.00% 100.00% 100.00% 0.00% 5-Jun-13 18-Jun-13
A9790 FIT UP PRIMARY FRAME FOR CELLAR DECK PART III 40.00% 96.11% 100.00% -3.89% 12-Jun-13 28-Jun-13
A9800 WELDING PRIMARY FRAME FOR CELLAR DECK PART III 30.00% 39.49% 18.18% 21.31% 27-Jun-13 8-Jul-13
A9810 NDT PRIMARY FRAME FOR CELLAR DECK PART III 10.00% 0.00% 0.00% 0.00% 2-Jul-13 12-Jul-13
4.2.1.2.1.3.2 FABRICATION OF SECONDARY FRAME PART III 30.00% COMPLETED ACCEPTED 1.06% 17.00% -15.94% 14-Jun-13 30-Jul-13
A9840 MARK/ CUT SECONDARY FRAME FOR CELLAR DECK PART III 15.00% 7.07% 100.00% -92.93% 14-Jun-13 27-Jun-13
A9850 FIT UP SECONDARY FRAME FOR CELLAR DECK PART III 40.00% 0.00% 5.00% -5.00% 28-Jun-13 18-Jul-13
A9860 WELDING SECONDARY FRAME FOR CELLAR DECK PART III 30.00% 0.00% 0.00% 0.00% 4-Jul-13 24-Jul-13
A9870 NDT SECONDARY FRAME FOR CELLAR DECK PART III 15.00% 0.00% 0.00% 0.00% 10-Jul-13 30-Jul-13
4.2.1.2.1.3.3 FABRICATION OF JOINT DETAIL PART III 10.00% COMPLETED ACCEPTED 1.93% 33.69% -31.76% 14-Jun-13 24-Jul-13
A9880 MARK/ CUT JOINT DETAIL FOR CELLAR DECK PART III 15.00% 12.90% 88.24% -75.34% 14-Jun-13 1-Jul-13
A9890 FIT UP JOINT DETAIL FOR CELLAR DECK PART III 40.00% 0.00% 40.91% -40.91% 20-Jun-13 12-Jul-13
A9900 WELDING JOINT DETAIL FOR CELLAR DECK PART III 30.00% 0.00% 13.64% -13.64% 26-Jun-13 18-Jul-13
A9910 NDT JOINT DETAIL FOR CELLAR DECK PART III 15.00% 0.00% 0.00% 0.00% 2-Jul-13 24-Jul-13
4.2.1.2.1.3.4 FABRICATION OF DECK PLATING PART III 20.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 2-Jul-13 21-Aug-13
A9920 MARK/ CUT DECK PLATING FOR CELLAR DECK PART III 15.00% 80% 20% 0.00% 0.00% 0.00% 2-Jul-13 18-Jul-13
A9930 FIT UP DECK PLATING FOR CELLAR DECK PART III 40.00% 80% 20% 0.00% 0.00% 0.00% 16-Jul-13 7-Aug-13
A9940 WELDING DECK PLATING FOR CELLAR DECK PART III 30.00% 80% 20% 0.00% 0.00% 0.00% 22-Jul-13 15-Aug-13
A9950 NDT DECK PLATING FOR CELLAR DECK PART III 15.00% 80% 20% 0.00% 0.00% 0.00% 27-Jul-13 21-Aug-13
4.2.1.2.1.4 FABRICATION OF CELLAR DECK PART I 25.00% COMPLETED ACCEPTED 54.00% 28.06% 25.94% 27-May-13 30-Aug-13
4.2.1.2.1.4.1 FABRICATION OF PRIMARY FRAME PART I 40.00% COMPLETED ACCEPTED 90.00% 55.29% 34.71% 27-May-13 18-Jul-13
A10468 LAYOUT TEMPORARY SUPPORTS FOR CELLAR DECK PART I 10.00% 39.0 80% 39.0 20% 100.00% 100.00% 0.00% 27-May-13 1-Jun-13
A10470 MARK/ CUT PRIMARY FRAME FOR CELLAR DECK PART I 10.00% 100.00% 100.00% 0.00% 7-Jun-13 20-Jun-13
A10480 FIT UP PRIMARY FRAME FOR CELLAR DECK PART I 40.00% 100.00% 88.24% 11.76% 14-Jun-13 1-Jul-13
14
A10490 WELDING PRIMARY FRAME FOR CELLAR DECK PART I 30.00% 100.00% 0.00% 100.00% 2-Jul-13 12-Jul-13
A10500 NDT PRIMARY FRAME FOR CELLAR DECK PART I 10.00% 0.00% 0.00% 0.00% 8-Jul-13 18-Jul-13
4.2.1.2.1.4.2 FABRICATION OF SECONDARY FRAME PART I 30.00% COMPLETED ACCEPTED 55.00% 11.54% 43.46% 19-Jun-13 8-Aug-13
A10520 MARK/ CUT SECONDARY FRAME FOR CELLAR DECK PART I 15.00% 100.00% 76.92% 23.08% 19-Jun-13 2-Jul-13
A10530 FIT UP SECONDARY FRAME FOR CELLAR DECK PART I 40.00% 100.00% 0.00% 100.00% 8-Jul-13 20-Jul-13
A10540 WELDING SECONDARY FRAME FOR CELLAR DECK PART I 30.00% 0.00% 0.00% 0.00% 13-Jul-13 2-Aug-13
A10550 NDT SECONDARY FRAME FOR CELLAR DECK PART I 15.00% 0.00% 0.00% 0.00% 19-Jul-13 8-Aug-13
4.2.1.2.1.4.3 FABRICATION OF JOINT DETAIL PART I 10.00% COMPLETED ACCEPTED 15.00% 24.79% -9.79% 17-Jun-13 26-Jul-13
A10560 MARK/ CUT JOINT DETAIL FOR CELLAR DECK PART I 15.00% 67.37% 75.00% -7.63% 17-Jun-13 3-Jul-13
A10570 FIT UP JOINT DETAIL FOR CELLAR DECK PART I 40.00% 10.40% 30.43% -20.03% 22-Jun-13 15-Jul-13
A10580 WELDING JOINT DETAIL FOR CELLAR DECK PART I 30.00% 2.44% 4.55% -2.11% 28-Jun-13 20-Jul-13
A10590 NDT JOINT DETAIL FOR CELLAR DECK PART I 15.00% 0.00% 0.00% 0.00% 4-Jul-13 26-Jul-13
4.2.1.2.1.4.4 FABRICATION OF DECK PLATING PART I 20.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 6-Jul-13 30-Aug-13
A10600 MARK/ CUT DECK PLATING FOR CELLAR DECK PART I 15.00% 80% 20% 0.00% 0.00% 0.00% 6-Jul-13 23-Jul-13
A10610 FIT UP DECK PLATING FOR CELLAR DECK PART I 40.00% 80% 20% 0.00% 0.00% 0.00% 25-Jul-13 16-Aug-13
A10620 WELDING DECK PLATING FOR CELLAR DECK PART I 30.00% 80% 20% 0.00% 0.00% 0.00% 31-Jul-13 24-Aug-13
A10630 NDT DECK PLATING FOR CELLAR DECK PART I 15.00% 80% 20% 0.00% 0.00% 0.00% 6-Aug-13 30-Aug-13
4.2.1.2.2 FABRICATION OF MAIN DECK FRAME 32.00% COMPLETED ACCEPTED 20.26% 4.50% 15.76% 17-Jun-13 29-Oct-13
4.2.1.2.2.1 FABRICATION WF BEAMS OF MAIN DECK 10.00% COMPLETED ACCEPTED 100.00% 45.00% 55.00% 17-Jun-13 19-Jul-13
A11320 MARK/ CUT PLATE STEEL FOR WF MAIN DECK 15.00% 100.00% 100.00% 0.00% 17-Jun-13 24-Jun-13
A11330 FIT UP PLATE STEEL FOR WF MAIN DECK 40.00% 100.00% 69.23% 30.77% 20-Jun-13 3-Jul-13
A11340 WELDING WF FOR MAIN DECK 30.00% 100.00% 7.69% 92.31% 28-Jun-13 11-Jul-13
A11350 NDT WF FOR MAIN DECK 15.00% 100.00% 0.00% 100.00% 6-Jul-13 19-Jul-13
4.2.1.2.2.2 FABRICATION OF MAIN DECK PART II 35.00% COMPLETED ACCEPTED 20.75% 0.00% 20.75% 9-Jul-13 14-Oct-13
4.2.1.2.2.2.1 FABRICATION OF PRIMARY FRAME PART II 40.00% COMPLETED ACCEPTED 51.85% 0.00% 51.85% 9-Jul-13 30-Aug-13
A10636 LAYOUT TEMPORARY SUPPORTS FOR MAIN DECK PART II 5.00% 41.0 80% 41 20% 100.00% 0.00% 100.00% 10-Jul-13 16-Jul-13
A10638 INSTALL PIPE LEGS FOR MAIN DECK PART II 5.00% 4.0 80% 4 20% 100.00% 0.00% 100.00% 17-Jul-13 22-Jul-13
A10640 MARK/ CUT PRIMARY FRAME FOR MAIN DECK PART II 10.00% 91.56% 0.00% 91.56% 9-Jul-13 19-Jul-13
A10650 FIT UP PRIMARY FRAME FOR MAIN DECK PART II 40.00% 81.73% 0.00% 81.73% 23-Jul-13 8-Aug-13
A10660 WELDING PRIMARY FRAME FOR MAIN DECK PART II 30.00% 0.00% 0.00% 0.00% 8-Aug-13 24-Aug-13
A10670 NDT PRIMARY FRAME FOR MAIN DECK PART III 10.00% 0.00% 0.00% 0.00% 20-Aug-13 6-Sep-13
4.2.1.2.2.2.2 FABRICATION OF SECONDARY FRAME PART II 30.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 20-Jul-13 12-Sep-13
A10700 MARK/ CUT SECONDARY FRAME FOR MAIN DECK PART II 15.00% 0.00% 0.00% 0.00% 20-Jul-13 2-Aug-13
A10710 FIT UP SECONDARY FRAME FOR MAIN DECK PART II 40.00% 0.00% 0.00% 0.00% 10-Aug-13 27-Aug-13
A10720 WELDING SECONDARY FRAME FOR MAIN DECK PART II 30.00% 0.00% 0.00% 0.00% 16-Aug-13 6-Sep-13
A10730 NDT SECONDARY FRAME FOR MAIN DECK PART II 15.00% 0.00% 0.00% 0.00% 22-Aug-13 12-Sep-13
4.2.1.2.2.2.3 FABRICATION OF JOINT DETAIL PART II 10.00% COMPLETED ACCEPTED 0.11% 0.00% 0.11% 17-Jul-13 18-Sep-13
A10740 MARK/ CUT JOINT DETAIL FOR MAIN DECK PART II 15.00% 0.77% 0.00% 0.77% 17-Jul-13 8-Aug-13
A10750 FIT UP JOINT DETAIL FOR MAIN DECK PART II 40.00% 0.00% 0.00% 0.00% 10-Aug-13 9-Sep-13
A10760 WELDING JOINT DETAIL FOR MAIN DECK PART II 30.00% 0.00% 0.00% 0.00% 14-Aug-13 12-Sep-13
A10770 NDT JOINT DETAIL FOR MAIN DECK PART II 15.00% 0.00% 0.00% 0.00% 20-Aug-13 18-Sep-13
4.2.1.2.2.2.4 FABRICATION OF DECK PLATING PART II 20.00% 0.00% 0.00% 0.00% 7-Aug-13 14-Oct-13
A10780 MARK/ CUT DECK PLATING FOR MAIN DECK PART II 15.00% 80% 20% 0.00% 0.00% 0.00% 7-Aug-13 29-Aug-13
A10790 FIT UP DECK PLATING FOR MAIN DECK PART II 40.00% 80% 20% 0.00% 0.00% 0.00% 28-Aug-13 20-Sep-13
A10800 WELDING DECK PLATING FOR MAIN DECK PART II 30.00% 80% 20% 0.00% 0.00% 0.00% 10-Sep-13 8-Oct-13
A10810 NDT DECK PLATING FOR MAIN DECK PART II 15.00% 80% 20% 0.00% 0.00% 0.00% 16-Sep-13 14-Oct-13
4.2.1.2.2.3 FABRICATION OF MAIN DECK PART III 27.50% COMPLETED ACCEPTED 8.39% 0.00% 8.39% 26-Jul-13 21-Oct-13
4.2.1.2.2.3.1 FABRICATION OF PRIMARY FRAME PART III 40.00% COMPLETED ACCEPTED 20.97% 0.00% 20.97% 26-Jul-13 6-Sep-13
A10818 LAYOUT TEMPORARY SUPPORTS FOR MAIN DECK PART III 10.00% 20.0 80% 20 20% 48.78% 0.00% 48.78% 29-Jul-13 1-Aug-13
A10820 MARK/ CUT PRIMARY FRAME FOR MAIN DECK PART III 10.00% 63.68% 0.00% 63.68% 26-Jul-13 3-Aug-13
A10830 FIT UP PRIMARY FRAME FOR MAIN DECK PART III 40.00% 24.31% 0.00% 24.31% 2-Aug-13 15-Aug-13
A10840 WELDING PRIMARY FRAME FOR MAIN DECK PART III 30.00% 0.00% 0.00% 0.00% 14-Aug-13 30-Aug-13
A10850 NDT PRIMARY FRAME FOR MAIN DECK PART III 10.00% 0.00% 0.00% 0.00% 20-Aug-13 6-Sep-13
4.2.1.2.2.3.2 FABRICATION OF SECONDARY FRAME PART III 30.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 7-Aug-13 16-Sep-13
A10870 MARK/ CUT SECONDARY FRAME FOR MAIN DECK PART III 15.00% 0.00% 0.00% 0.00% 7-Aug-13 17-Aug-13
A10880 FIT UP SECONDARY FRAME FOR MAIN DECK PART III 40.00% 0.00% 0.00% 0.00% 14-Aug-13 27-Aug-13
A10890 WELDING SECONDARY FRAME FOR MAIN DECK PART III 30.00% 0.00% 0.00% 0.00% 20-Aug-13 10-Sep-13
A10900 NDT SECONDARY FRAME FOR MAIN DECK PART III 15.00% 0.00% 0.00% 0.00% 26-Aug-13 16-Sep-13
4.2.1.2.2.3.3 FABRICATION OF JOINT DETAIL PART I 10.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 13-Aug-13 27-Sep-13
A10910 MARK/ CUT JOINT DETAIL FOR MAIN DECK PART III 15.00% 0.00% 0.00% 0.00% 13-Aug-13 29-Aug-13
A10920 FIT UP JOINT DETAIL FOR MAIN DECK PART III 40.00% 0.00% 0.00% 0.00% 20-Aug-13 12-Sep-13
A10930 WELDING JOINT DETAIL FOR MAIN DECK PART III 30.00% 0.00% 0.00% 0.00% 23-Aug-13 21-Sep-13
15
A10940 NDT JOINT DETAIL FOR MAIN DECK PART III 15.00% 0.00% 0.00% 0.00% 29-Aug-13 27-Sep-13
4.2.1.2.2.3.4 FABRICATION OF DECK PLATING PART III 20.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 24-Aug-13 21-Oct-13
A10950 MARK/ CUT DECK PLATING FOR MAIN DECK PART III 15.00% 80% 20% 0.00% 0.00% 0.00% 24-Aug-13 14-Sep-13
A10960 FIT UP DECK PLATING FOR MAIN DECK PART III 40.00% 80% 20% 0.00% 0.00% 0.00% 5-Sep-13 30-Sep-13
A10970 WELDING DECK PLATING FOR MAIN DECK PART III 30.00% 80% 20% 0.00% 0.00% 0.00% 17-Sep-13 15-Oct-13
A10980 NDT DECK PLATING FOR MAIN DECK PART III 15.00% 80% 20% 0.00% 0.00% 0.00% 23-Sep-13 21-Oct-13
4.2.1.2.2.4 FABRICATION OF MAIN DECK PART I 27.50% COMPLETED ACCEPTED 2.50% 0.00% 2.50% 7-Aug-13 29-Oct-13
4.2.1.2.2.4.1 FABRICATION OF PRIMARY FRAME PART I 50.00% COMPLETED ACCEPTED 5.00% 0.00% 5.00% 7-Aug-13 2-Oct-13
A10988 LAYOUT TEMPORARY SUPPORTS FOR MAIN DECK PART I 10.00% 20.0 80% 20 20% 50.00% 0.00% 50.00% 29-Aug-13 3-Sep-13
A10990 MARK/ CUT PRIMARY FRAME FOR MAIN DECK PART I 10.00% 0.00% 0.00% 0.00% 7-Aug-13 15-Aug-13
A11000 FIT UP PRIMARY FRAME FOR MAIN DECK PART I 40.00% 0.00% 0.00% 0.00% 4-Sep-13 17-Sep-13
A11010 WELDING PRIMARY FRAME FOR MAIN DECK PART I 30.00% 0.00% 0.00% 0.00% 16-Sep-13 26-Sep-13
A11020 NDT PRIMARY FRAME FOR MAIN DECK PART I 10.00% 0.00% 0.00% 0.00% 21-Sep-13 2-Oct-13
4.2.1.2.2.4.2 FABRICATION OF SECONDARY FRAME PART I 40.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 19-Aug-13 14-Oct-13
A11040 MARK/ CUT SECONDARY FRAME FOR MAIN DECK PART I 15.00% 0.00% 0.00% 0.00% 19-Aug-13 29-Aug-13
A11050 FIT UP SECONDARY FRAME FOR MAIN DECK PART I 40.00% 0.00% 0.00% 0.00% 16-Sep-13 28-Sep-13
A11060 WELDING SECONDARY FRAME FOR MAIN DECK PART I 30.00% 0.00% 0.00% 0.00% 21-Sep-13 8-Oct-13
A11070 NDT SECONDARY FRAME FOR MAIN DECK PART I 15.00% 0.00% 0.00% 0.00% 27-Sep-13 14-Oct-13
4.2.1.2.2.4.3 FABRICATION OF JOINT DETAIL PART I 10.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 24-Aug-13 29-Oct-13
A11080 MARK/ CUT JOINT DETAIL FOR MAIN DECK PART I 15.00% 0.00% 0.00% 0.00% 24-Aug-13 11-Sep-13
A11090 FIT UP JOINT DETAIL FOR MAIN DECK PART I 40.00% 0.00% 0.00% 0.00% 21-Sep-13 14-Oct-13
A11100 WELDING JOINT DETAIL FOR MAIN DECK PART I 30.00% 0.00% 0.00% 0.00% 25-Sep-13 23-Oct-13
A11110 NDT JOINT DETAIL FOR MAIN DECK PART I 15.00% 0.00% 0.00% 0.00% 1-Oct-13 29-Oct-13
4.2.1.2.3 FABRICATION OF HELI DECK 3.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 5-Dec-13 27-Dec-13
E1300 INSTALL HELI DECK FRAME 100.00% 80% 20% 0.00% 0.00% 0.00% 5-Dec-13 27-Dec-13
4.2.1.2.4 FABRICATIN OF VENT BOOM 10.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 12-Oct-13 30-Dec-13
E1310 LAYOUT SUPPORTS FOR VENT BOOM 10.00% 80% 20% 0.00% 0.00% 0.00% 12-Oct-13 15-Oct-13
E1320 MARK/ CUTTING FRAME FOR VENT BOOM 10.00% 80% 20% 0.00% 0.00% 0.00% 16-Oct-13 29-Oct-13
E1330 FIT UP FRAME FOR VENT BOOM 40.00% 80% 20% 0.00% 0.00% 0.00% 24-Oct-13 27-Nov-13
E1340 WELDING FRAME FOR VENT BOOM 30.00% 80% 20% 0.00% 0.00% 0.00% 9-Nov-13 20-Dec-13
E1350 NDT FRAME FOR VENT BOOM 10.00% 80% 20% 0.00% 0.00% 0.00% 26-Nov-13 30-Dec-13
4.2.1.2.5 FABRICATION OF OTHER ITEMS 25.00% Mark/Cut Fit up/ Accept Weld/ Accept NDT/ Accept 0.00% 0.00% 0.00% 11-Sep-13 20-Dec-13
E1360 FABRICATION HANDRAIL 13.20% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 7-Dec-13
E1370 FABRICATION LADDER 0.60% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 6-Dec-13
E1380 FABRICATION STAIRWAY 8.80% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 26-Oct-13 20-Dec-13
E1390 FABRICATION DECK DRAIN 3.78% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 6-Dec-13
E1400 FABRICATION EQUIPMENT MOUNTING 0.30% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 6-Dec-13
E1410 FABRICATION LIFE RAFT SUPPORT 0.30% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 6-Dec-13
E1430 FABRICATION LIFTING PADEYE 4.72% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 6-Dec-13
E1440 FABRICATION VENT BOOM SUPPORT 5.04% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 1-Oct-13 25-Nov-13
E1450 FABRICATION MONORAIL 1.83% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 6-Dec-13
E1480 FABRICATION SECURITY GATE AND WALL 23.30% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 6-Dec-13
E1500 FABRICATION CONDUCTOR GUIDE 20.78% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 8-Nov-13
E1510 FABRICATION HATCH COVER 4.41% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 12-Oct-13 8-Nov-13
E1520 FABRICATION CRANE ACCESS PLATFORM 1.64% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 18-Oct-13 14-Nov-13
E1530 FABRICATION FIRE & BLASTWALL 9.45% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 11-Sep-13 8-Oct-13
E1540 FABRICATION PLATFORM NAME PLATE 0.21% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 5-Nov-13 18-Nov-13
E1545 FABRICATION CONES (4 PCS) 1.64% 15% 40% 30.00% 15.00% 0.00% 0.00% 0.00% 16-Sep-13 28-Sep-13
4.2.1.3 ERECTION 35.00% Fit up/ Accept Weld/Accept NDT/Accept 0.00% 0.00% 0.00% 22-Aug-13 17-Jan-14
E1730 LAYOUT/ERECTION SUPPORTS & LOAD OUT BEAMS TO FINAL POSITION 8.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 22-Aug-13 29-Aug-13
E1750 CELLAR DECK PART II STACK UP 6.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 3-Sep-13 10-Sep-13
E1760 CELLAR DECK PART III STACK UP 5.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 12-Sep-13 19-Sep-13
E1765 CELLAR DECK PART I STACK UP 4.50% 50% 35% 15.00% 0.00% 0.00% 0.00% 21-Sep-13 28-Sep-13
E1770 PIPE LEGS ERECTION 3.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 30-Sep-13 16-Oct-13
E1775 BRACING PIPE ERECTION (PART 1) 8.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 30-Sep-13 22-Oct-13
E1780 BLAST WALL ERECTION (PART 1) 6.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 9-Oct-13 19-Oct-13
E1790 MAIN DECK PART II (AXIS 1/2) STACK UP 6.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 5-Nov-13 15-Nov-13
E1810 MAIN DECK PART III (AXIS 2/2a) STACK UP 5.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 19-Nov-13 27-Nov-13
E1820 MAIN DECK PART I (AXIS 1a/1) STACK UP 4.50% 50% 35% 15.00% 0.00% 0.00% 0.00% 23-Nov-13 30-Nov-13
E1825 HELI DECK ERECTION 2.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 28-Dec-13 4-Jan-14
E1830 BRACING ERECTION (REMAINING PART) 9.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 7-Dec-13 24-Dec-13
E1833 BLAST WALL ERECTION (REMAINING PART) 8.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 7-Dec-13 20-Dec-13
16
E1835 ERECTION OTHER ITEMS 25.00% 50% 35% 15.00% 0.00% 0.00% 0.00% 24-Dec-13 17-Jan-14
4.2.1.4 TRIAL FIT AND WEIGHING 5.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 3-Jan-14 27-Jan-14
E1840 VENT BOOM TRIAL FIT 35.00% 80% 20% 0.00% 0.00% 0.00% 16-Jan-14 22-Jan-14
E1850 FABRICATE/ ERECTION PADEYES 10.00% 80% 20% 0.00% 0.00% 0.00% 3-Jan-14 18-Jan-14
E1855 TRIAL FIT/ LAYOUT T&I SLINGS 15.00% 80% 20% 0.00% 0.00% 0.00% 20-Jan-14 27-Jan-14
E1860 TOPSIDE WEIGHING 40.00% 80% 20% 0.00% 0.00% 0.00% 9-Jan-14 10-Jan-14
4.2.2 PIPING/ PLUMBING 19.00% COMPLETED ACCEPTED 1.80% 1.22% 0.58% 15-Jun-13 14-Feb-14
4.2.2.1 FABRICATION OF PIPE/PLUMBING SUPPORTS 48.00% COMPLETED ACCEPTED 3.74% 2.54% 1.21% 15-Jun-13 6-Dec-13
E1870 FABRICATE PIPE SUPPORT 12.50% 0.2 80% 0 20% 15.94% 20.29% -4.35% 15-Jun-13 23-Aug-13
E2280 FABRICATE PIPE SPOOL 87.50% 0.0 80% 0 20% 2.00% 0.00% 2.00% 6-Aug-13 6-Dec-13
4.2.2.2 INSTALLATION OF PIPE/PLUMBING SUPPORTS 32.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 10-Sep-13 10-Jan-14
E2690 INSTALL PIPE SUPPORT 12.50% 80% 20% 0.00% 0.00% 0.00% 10-Sep-13 4-Jan-14
E3100 INSTALL PIPE SPOOL 87.50% 80% 20% 0.00% 0.00% 0.00% 16-Sep-13 10-Jan-14
4.2.2.3 INSTALLATION OF VALVES (NUMBER OF VALVES) 5.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 10-Dec-13 25-Jan-14
E3520 INSTALL VALVES 100.00% 80% 20% 0.00% 0.00% 0.00% 10-Dec-13 25-Jan-14
4.2.2.4 LEAK TEST OF VALVES (NUMBER OF VALVES) 3.50% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 24-Dec-13 13-Feb-14
E3510 LEAK TEST VALVES 100.00% 80% 20% 0.00% 0.00% 0.00% 24-Dec-13 13-Feb-14
4.2.2.5 FLUSHING, HYDROTESTING AND ACID CLEANING 6.50% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 23-Nov-13 14-Feb-14
E3530 FLUSHING 15.00% 80% 20% 0.00% 0.00% 0.00% 23-Nov-13 15-Jan-14
E3540 HYDROTEST 70.00% 80% 20% 0.00% 0.00% 0.00% 22-Nov-13 20-Jan-14
E3550 ACID CLEANING 15.00% 80% 20% 0.00% 0.00% 0.00% 25-Dec-13 14-Feb-14
4.2.2.6 INSULATION 5.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 22-Nov-13 11-Feb-14
E3560 INSULATION OF PIPING 100.00% 80% 20% 0.00% 0.00% 0.00% 22-Nov-13 11-Feb-14
4.2.3 MECHANICAL 3.00%COMPLETED ACCEPTED 0.00% 0.00% 0.00% 30-Sep-13 24-Feb-14
4.2.3.1 SETTING UP EQUIPMENT ON DECK 65.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 30-Sep-13 12-Feb-14
4.2.3.1.1 SETTING UP EQUIPMENT ON CELLAR DECK 48.41% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 30-Sep-13 28-Jan-14
E3570 SETTING UP CLOSE DRAIN VESSEL V-6400 SKID 29.86% 80% 20% 0.00% 0.00% 0.00% 26-Oct-13 31-Oct-13
E3600 SETTING UP CRUDE HEATER UNIT A-1510 (CELLAR DECK PART III) 21.30% 80% 20% 0.00% 0.00% 0.00% 13-Nov-13 16-Nov-13
E3610 SETTING UP PMCS/SIS/FIELD TRANSMITTER/ FGS (CELLAR DECK PART I) 1.00% 80% 20% 0.00% 0.00% 0.00% 9-Nov-13 18-Nov-13
E3620 SETTING UP CRUDE OIL TRANSFER PUMP P-1310A/B (CELLAR DECK PART II) 8.76% 80% 20% 0.00% 0.00% 0.00% 23-Jan-14 28-Jan-14
E3630 SETTING UP FUEL GAS SKID A-5800 (CELLAR DECK PART III) 1.99% 80% 20% 0.00% 0.00% 0.00% 30-Sep-13 3-Oct-13
E3640 SETTING UP CHEMICAL INJECTION PUMP SKID A-6800 (CELLAR DECK PART III) 0.80% 80% 20% 0.00% 0.00% 0.00% 4-Oct-13 8-Oct-13
E3650 SETTING UP LAUNCHER L-1330 (CELLAR DECK PART III) 10.75% 80% 20% 0.00% 0.00% 0.00% 9-Oct-13 12-Oct-13
E3660 SETTING UP DIESEL ENGINE GENERATOR (DEG) A-7740 (CELLAR DECK PART I) 18.31% 80% 20% 0.00% 0.00% 0.00% 14-Nov-13 19-Nov-13
E3670 SETTING UP GAS ENGINE GENERATOR A-7700 (CELLAR DECK PART I) 0.72% 80% 20% 0.00% 0.00% 0.00% 3-Jan-14 8-Jan-14
E3680 SETTING UP MULTIPHASE FLOW METER A-1210 (CELLAR DECK PART II) 1.11% 80% 20% 0.00% 0.00% 0.00% 5-Oct-13 9-Oct-13
E3690 SETTING UP WELL HEAD CONTROL PANEL WHCP-0100 (CELLAR DECK PART II) 1.63% 80% 20% 0.00% 0.00% 0.00% 10-Oct-13 14-Oct-13
E3700 SETTING UP TEST/ PRODUCTION/ GASLIFT HEADER (CELLAR DECK PART II) 0.28% 80% 20% 0.00% 0.00% 0.00% 15-Oct-13 18-Oct-13
E3710 SETTING UP WASH WATER PUMP P-5110 (CELLAR DECK PART III) 0.48% 80% 20% 0.00% 0.00% 0.00% 4-Jan-14 8-Jan-14
E3720 SETTING UP CO2 VENT SNUFFING A-8600 (VENT BOOM) 0.28% 80% 20% 0.00% 0.00% 0.00% 3-Jan-14 7-Jan-14
E3730 SETTING UP DIESEL TRANSFER PUMP P-6710 (CELLAR DECK PART II) 1.15% 80% 20% 0.00% 0.00% 0.00% 4-Jan-14 8-Jan-14
E3740 SETTING UP NITROGEN BOTTLES A-5900 (CELLAR DECK PART III) 0.60% 80% 20% 0.00% 0.00% 0.00% 1-Oct-13 4-Oct-13
E3750 SETTING UP SCSSV EQUALIZATION PUMP P-6720 (CELLAR DECK PART II) 0.20% 80% 20% 0.00% 0.00% 0.00% 4-Jan-14 8-Jan-14
E3760 SETTING UP PIPELINE DIESEL INJECTION PUMP P-6730 (CELLAR DECK PART II) 0.80% 80% 20% 0.00% 0.00% 0.00% 7-Jan-14 10-Jan-14
4.2.3.1.2 SETTING UP EQUIPMENT ON MAIN DECK 51.59% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 28-Dec-13 12-Feb-14
E3800 SETTING UP MATERIAL HANDLING - PEDESTAL CRANE BD-7301 (MAIN DECK) 18.12% 80% 20% 0.00% 0.00% 0.00% 27-Jan-14 12-Feb-14
E3810 SETTING UP BOOSTER COMPRESSOR A-2410 (MAIN DECK) 30.63% 80% 20% 0.00% 0.00% 0.00% 29-Jan-14 11-Feb-14
E3820 SETTING UP GAS LIFT COMPRESSOR A-0610 (MAIN DECK) 19.42% 80% 20% 0.00% 0.00% 0.00% 29-Jan-14 11-Feb-14
E3830 SETTING UP DIESEL STORAGE TANK T-6700 0.37% 80% 20% 0.00% 0.00% 0.00% 28-Nov-13 29-Nov-13
E3840 SETTING UP WASH WATER STORAGE STANK T-5100A/B 0.60% 80% 20% 0.00% 0.00% 0.00% 30-Nov-13 2-Dec-13
E3850 SETTING UP POTABLE WATER TANK T-5200 0.64% 80% 20% 0.00% 0.00% 0.00% 3-Dec-13 4-Dec-13
E3860 SETTING UP GENERAL PURPOSE TOTE TANK T-5300 0.19% 80% 20% 0.00% 0.00% 0.00% 5-Dec-13 6-Dec-13
E3890 SETTING UP PORTABLE CHEMICAL TRANSFER PUMP P-6835 0.15% 80% 20% 0.00% 0.00% 0.00% 7-Dec-13 9-Dec-13
E3900 SETTING UP HP SEPARATOR SKID A-1020 17.93% 80% 20% 0.00% 0.00% 0.00% 10-Dec-13 11-Dec-13
E3910 SETTING UP LP SEPARATOR SKID A-1010 11.95% 80% 20% 0.00% 0.00% 0.00% 12-Dec-13 13-Dec-13
4.2.3.2 MECHANICAL COMPLETION (TIE-IN) 35.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 16-Oct-13 24-Feb-14
4.2.3.2.1 TIE-IN EQUIPMENT ON CELLAR DECK 48.46% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 16-Oct-13 24-Jan-14
E3940 TIE-IN CLOSE DRAIN VESSEL V-6400 29.80% 80% 20% 0.00% 0.00% 0.00% 8-Nov-13 25-Dec-13
E3950 TIE-IN CRUDE HEATER UNIT A-1510 21.26% 80% 20% 0.00% 0.00% 0.00% 28-Nov-13 2-Jan-14
E3960 TIE-IN PMCS/SIS/FIELD TRANSMITTER/ FGS 0.40% 80% 20% 0.00% 0.00% 0.00% 29-Nov-13 3-Jan-14
E3970 TIE-IN CRUDE OIL TRANSFER PUMP P-1310A/B 0.99% 80% 20% 0.00% 0.00% 0.00% 15-Feb-14 24-Feb-14
E3980 TIE-IN FUEL GAS SKID A-5800 8.74% 80% 20% 0.00% 0.00% 0.00% 25-Nov-13 28-Dec-13
17
E3990 TIE-IN CHEMICAL INJECTION PUMP SKID A-6800 1.99% 80% 20% 0.00% 0.00% 0.00% 16-Nov-13 10-Dec-13
E4000 TIE-IN LAUNCHER L-1330 0.79% 80% 20% 0.00% 0.00% 0.00% 24-Oct-13 14-Dec-13
E4010 TIE-IN DIESEL ENGINE GENERATOR (DEG) A-7740 10.73% 80% 20% 0.00% 0.00% 0.00% 2-Dec-13 12-Dec-13
E4020 TIE-IN GAS ENGINE GENERATOR A-7700 18.28% 80% 20% 0.00% 0.00% 0.00% 14-Jan-14 22-Jan-14
E4030 TIE-IN MULTIPHASE FLOW METER A-1210 0.72% 80% 20% 0.00% 0.00% 0.00% 21-Oct-13 23-Nov-13
E4040 TIE-IN WELL HEAD CONTROL PANEL WHCP-0100 1.11% 80% 20% 0.00% 0.00% 0.00% 25-Oct-13 28-Nov-13
E4050 TIE-IN TEST/ PRODUCTION/ GASLIFT HEADTER 1.63% 80% 20% 0.00% 0.00% 0.00% 30-Oct-13 3-Dec-13
E4060 TIE-IN WASH WATER PUMP P-5110 0.28% 80% 20% 0.00% 0.00% 0.00% 9-Jan-14 16-Jan-14
E4070 TIE-IN CO2 VENT SNUFFING A-8600 0.48% 80% 20% 0.00% 0.00% 0.00% 8-Jan-14 15-Jan-14
E4080 TIE-IN DIESEL TRANSFER PUMP P-6710 0.28% 80% 20% 0.00% 0.00% 0.00% 9-Jan-14 16-Jan-14
E4090 TIE-IN NITROGEN BOTTLES A-5900 1.15% 80% 20% 0.00% 0.00% 0.00% 16-Oct-13 19-Nov-13
E4100 TIE-IN SCSSV EQUALIZATION PUMP P-6720 0.60% 80% 20% 0.00% 0.00% 0.00% 9-Jan-14 16-Jan-14
E4110 TIE-IN PIPELINE DIESEL INJECTION PUMP P-6730 0.79% 80% 20% 0.00% 0.00% 0.00% 11-Jan-14 18-Jan-14
4.2.3.2.2 TIE-IN EQUIPMENT ON MAIN DECK 51.54% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 30-Nov-13 20-Feb-14
E4160 TIE-IN PORTABLE CHEMICAL TRANSFER PUMP P-6835 18.12% 80% 20% 0.00% 0.00% 0.00% 10-Dec-13 20-Dec-13
E4170 TIE-IN HP SEPARATOR SKID A-1020 30.63% 80% 20% 0.00% 0.00% 0.00% 12-Dec-13 23-Dec-13
E4180 TIE-IN LP SEPARATOR SKID A-1010 19.42% 80% 20% 0.00% 0.00% 0.00% 14-Dec-13 25-Dec-13
E4190 TIE-IN MATERIAL HANDLING - PEDESTAL CRANE BD-7301 0.37% 80% 20% 0.00% 0.00% 0.00% 12-Feb-14 20-Feb-14
E4200 TIE-IN BOOSTER COMPRESSOR A-2410 0.60% 80% 20% 0.00% 0.00% 0.00% 11-Feb-14 19-Feb-14
E4210 TIE-IN GAS LIFT COMPRESSOR A-0610 0.64% 80% 20% 0.00% 0.00% 0.00% 11-Feb-14 19-Feb-14
E4220 TIE-IN DIESEL STORAGE TANK T-6700 0.19% 80% 20% 0.00% 0.00% 0.00% 30-Nov-13 13-Dec-13
E4230 TIE-IN WASH WATER STORAGE STANK T-5100A/B 0.15% 80% 20% 0.00% 0.00% 0.00% 3-Dec-13 16-Dec-13
E4240 TIE-IN POTABLE WATER TANK T-5200 17.93% 80% 20% 0.00% 0.00% 0.00% 5-Dec-13 18-Dec-13
E4250 TIE-IN GENERAL PURPOSE TOTE TANK T-5300 11.95% 80% 20% 0.00% 0.00% 0.00% 7-Dec-13 20-Dec-13
4.2.4 INSTRUMENT 9.00% COMPLETED ACCEPTED 0.95% 0.00% 0.95% 11-Jul-13 10-Feb-14
4.2.4.1 FABRICATE INSTRUMENT SUPPORTS 8.00% Mark/Cut Fit Weld Accept 11.86% 0.00% 11.86% 11-Jul-13 26-Aug-13
E4270 FABRICATE SUPPORT FOR FIRE AND GAS SYSTEM 26.00% 15% 40% 30.00% 15% 5.80% 0.00% 5.80% 11-Jul-13 20-Aug-13
E4280 FABRICATE SUPPORT FOR INSTRUMENT EQUIPMENT 11.00% 15% 40% 30.00% 15% 9.97% 0.00% 9.97% 11-Jul-13 20-Aug-13
E4290 FABRICATE SUPPORT FOR TELECOM EQUIPMENT 8.00% 15% 40% 30.00% 15% 0.00% 0.00% 0.00% 11-Jul-13 20-Aug-13
E4300 FABRICATE SUPPORT FOR INSTRUMENT JBs 16.00% 15% 40% 30.00% 15% 40.74% 0.00% 40.74% 11-Jul-13 20-Aug-13
E4310 FABRICATE SUPPORT FOR CABLE TRAY AND TUBING TRAY 36.00% 15% 40% 30.00% 15% 7.60% 0.00% 7.60% 11-Jul-13 20-Aug-13
E4320 FABRICATE SUPPORT FOR BULKEAD 3.00% 15% 40% 30.00% 15% 0.00% 0.00% 0.00% 17-Jul-13 26-Aug-13
4.2.4.2 INSTALLATION OF INSTRUMENT SUPPORTS 11.00% Fit up/ Accept Weld/Accept NDT/Accept 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
E4330 INSTALL SUPPORT FOR FIRE AND GAS SYSTEM 26.00% 50% 35% 15% 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
E4340 INSTALL SUPPORT FOR INSTRUMENT EQUIPMENT 11.00% 50% 35% 15% 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
E4350 INSTALL SUPPORT FOR TELECOM EQUIPMENT 8.00% 50% 35% 15% 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
E4360 INSTALL SUPPORT FOR INSTRUMENT JBs 16.00% 50% 35% 15% 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
E4370 INSTALL SUPPORT FOR CABLE TRAY AND TUBING TRAY 36.00% 50% 35% 15% 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
E4380 INSTALL SUPPORT FOR BULKEAD 3.00% 50% 35% 15% 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
4.2.4.3 TUBING TRAY I CABLE TRAY I LADDER INSTALLATION 17.00% Fit up/ Accept Weld/Accept NDT/Accept 0.00% 0.00% 0.00% 19-Oct-13 21-Dec-13
E4390 INSTALL CABLE LADDER/ TRAY FOR INSTRUMENT 100.00% 50% 35% 15% 0.00% 0.00% 0.00% 19-Oct-13 21-Dec-13
4.2.4.4 CALIBRATE INSTRUMENT 1.00% Accept 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
E4400 CALIBRATE INSTRUMENT EQUIPMENTS 100.00% 100% 0.00% 0.00% 0.00% 11-Oct-13 13-Dec-13
4.2.4.5 INSTRUMENT EQUIPMENT INSTALLATION 4.00% Fit up Accept 0.00% 0.00% 0.00% 23-Oct-13 22-Jan-14
E4410 INSTALL INSTRUMENT JBs AND BULKEAD 20.00% 85% 15% 0.00% 0.00% 0.00% 29-Oct-13 31-Dec-13
E4420 INSTALL GAUGE EQUIPMENTS 5.00% 85% 15% 0.00% 0.00% 0.00% 6-Dec-13 22-Jan-14
E4430 INSTALL TELECOM EQUIPMENTS 25.00% 85% 15% 0.00% 0.00% 0.00% 23-Oct-13 25-Dec-13
E4440 INSTALL TRANSMITER EQUIPMENTS 20.00% 85% 15% 0.00% 0.00% 0.00% 23-Oct-13 25-Dec-13
E4450 INSTALL FIRE & GAS EQUIPMENTS 30.00% 85% 15% 0.00% 0.00% 0.00% 23-Oct-13 25-Dec-13
4.2.4.6 CABLE PULLING 20.00% Pulling Accept 0.00% 0.00% 0.00% 12-Nov-13 4-Jan-14
E4460 CABLE PULLING FIRE & GAS CABLE (FROM EQUIPMENT TO JB) 25.00% 85% 15% 0.00% 0.00% 0.00% 20-Nov-13 30-Dec-13
E4470 CABLE PULLING MULTICORE CABLE FROM PACKAGES TO E-HOUSE 45.00% 85% 15% 0.00% 0.00% 0.00% 25-Nov-13 4-Jan-14
E4480 CABLE PULLING FOR TELECOM 15.00% 85% 15% 0.00% 0.00% 0.00% 3-Dec-13 25-Dec-13
E4490 CABLE PULLING FOR FIELD INSTRUMENT DEVICES (FROM EQUIPMENT TO JB) 15.00% 85% 15% 0.00% 0.00% 0.00% 12-Nov-13 27-Dec-13
4.2.4.7 DRESSING, GLANDING, TAGGING AND TERMINATION 34.00% Terminate Accept 0.00% 0.00% 0.00% 9-Dec-13 10-Feb-14
E4500 DRESSING, GLANDING FOR MULTICORE CABLE FROM PACKAGES TO E-HOUSE 25.00% 85% 15% 0.00% 0.00% 0.00% 18-Dec-13 28-Jan-14
E4510 DRESSING, GLANDING FOR CABLE FOR TELECOM 45.00% 85% 15% 0.00% 0.00% 0.00% 9-Dec-13 18-Jan-14
E4520 DRESSING, GLANDING FOR FIELD DEVICES (FROM EQUIPMENT TO JB) 15.00% 85% 15% 0.00% 0.00% 0.00% 17-Dec-13 15-Jan-14
E4530 DRESSING, GLANDING FOR FIRE & GAS CABLE (FROM EQUIPMENT TO JB) 15.00% 85% 15% 0.00% 0.00% 0.00% 20-Dec-13 10-Feb-14
4.2.4.8 PULL AND HOOK-UP TUBING 5.00% Pulling Hook-up Accept 0.00% 0.00% 0.00% 26-Dec-13 10-Feb-14
E4540 PULL AN D HOOK-UP TUBING FROM WHCP TO BULKEAD PLATE 40.00% 35% 50% 15% 0.00% 0.00% 0.00% 26-Dec-13 10-Feb-14
E4550 PULL AN D HOOK-UP TUBING FROM PIPING TO INSTRUMENT DEVICES 20.00% 35% 50% 15% 0.00% 0.00% 0.00% 26-Dec-13 10-Feb-14
18
E4560 PULL AN D HOOK-UP TUBING FROM CHEMICAL INJECTION TO PIPING 40.00% 35% 50% 15% 0.00% 0.00% 0.00% 3-Jan-14 25-Jan-14
4.2.5 ELECTRICAL/ HVAC/ Ducting 9.00% COMPLETED ACCEPTED 0.16% 0.00% 0.16% 11-Jul-13 19-Feb-14
4.2.5.1 FABRICATION OF ELECTRICAL SUPPORT 9.00% Mark/Cut Fit Weld Accept 1.80% 0.00% 1.80% 11-Jul-13 7-Sep-13
E4570 FABRICATE SUPPORT FOR LIGHTING SYSTEM 35.00% 15% 40% 30.00% 15% 0.00% 0.00% 0.00% 11-Jul-13 7-Sep-13
E4580 FABRICATE SUPPORT FOR ELECTRICAL JBs 20.00% 15% 40% 30.00% 15% 0.00% 0.00% 0.00% 23-Jul-13 26-Aug-13
E4590 FABRICATE SUPPORT FOR CABLE TRAY/LADDER 45.00% 15% 40% 30.00% 15% 4.00% 0.00% 4.00% 11-Jul-13 7-Sep-13
4.2.5.2 INSTALLATION OF ELECTRICAL SUPPORT 12.00% Mark Fit up Weld Accept 0.00% 0.00% 0.00% 9-Oct-13 11-Dec-13
E4600 INSTALL SUPPORT FOR CABLE TRAY/LADDER 35.00% 15% 40% 30.00% 15% 0.00% 0.00% 0.00% 9-Oct-13 11-Dec-13
E4610 INSTALL SUPPORT FOR LIGHTING SYSTEM 20.00% 15% 40% 30.00% 15% 0.00% 0.00% 0.00% 9-Oct-13 11-Dec-13
E4620 INSTALL SUPPORT FOR ELECTRICAL JBs 45.00% 15% 40% 30.00% 15% 0.00% 0.00% 0.00% 9-Oct-13 11-Dec-13
4.2.5.3 CABLE TRAY I CABLE LADDER INSTALLATION 17.00% Fit up/ Accept Weld/Accept NDT/Accept 0.00% 0.00% 0.00% 15-Oct-13 17-Dec-13
E4630 INSTALL CABLE LADDER/ TRAY FOR ELECTRICAL 100.00% 50% 35% 15% 0.00% 0.00% 0.00% 15-Oct-13 17-Dec-13
4.2.5.4 CALIBRATE ELECTRICAL EQUIPMENT 1.00% Accept 0.00% 0.00% 0.00% 8-Nov-13 6-Jan-14
E4640 CALIBRATE ELECTRICAL EQUIPMENTS 100.00% 100% 0.00% 0.00% 0.00% 8-Nov-13 6-Jan-14
4.2.5.5 ELECTRICAL EQUIPMENT INSTALLATION 5.00% Fit up Accept 0.00% 0.00% 0.00% 25-Oct-13 23-Jan-14
E4650 INSTALL ELECTRICAL JBs 16.00% 85% 15% 0.00% 0.00% 0.00% 25-Oct-13 27-Dec-13
E4660 INSTALL NAVIGATION AID EQUIPMENTS 16.00% 85% 15% 0.00% 0.00% 0.00% 7-Jan-14 13-Jan-14
E4670 INSTALL HEATRACING EQUIPMENTS 26.00% 85% 15% 0.00% 0.00% 0.00% 16-Dec-13 23-Jan-14
E4680 INSTALL SMALL POWER EQUIPMENTS 6.00% 85% 15% 0.00% 0.00% 0.00% 23-Nov-13 27-Dec-13
E4690 INSTALL LIGHTING EQUIPMENTS 36.00% 85% 15% 0.00% 0.00% 0.00% 20-Nov-13 17-Jan-14
4.2.5.6 CABLE PULLING 20.00% Pulling Accept 0.00% 0.00% 0.00% 20-Nov-13 14-Feb-14
E4700 CABE PULLING FOR MAIN EARTHING 3.00% 85% 15% 0.00% 0.00% 0.00% 16-Jan-14 12-Feb-14
E4710 CABE PULLING FOR SKID 25.00% 85% 15% 0.00% 0.00% 0.00% 24-Dec-13 14-Feb-14
E4720 CABE PULLING FOR HELI DECK 9.00% 85% 15% 0.00% 0.00% 0.00% 11-Jan-14 24-Jan-14
E4730 CABE PULLING FOR GENERATOR 14.00% 85% 15% 0.00% 0.00% 0.00% 11-Dec-13 16-Jan-14
E4740 CABE PULLING FOR HEATRACING 14.00% 85% 15% 0.00% 0.00% 0.00% 30-Dec-13 23-Jan-14
E4750 CABE PULLING FOR SMALL POWER 8.00% 85% 15% 0.00% 0.00% 0.00% 20-Nov-13 17-Jan-14
E4760 CABE PULLING FOR LIGHTING 19.00% 85% 15% 0.00% 0.00% 0.00% 5-Dec-13 27-Dec-13
E4770 CABE PULLING FOR BETTERY (FROM E-HOUSE TO) 8.00% 85% 15% 0.00% 0.00% 0.00% 17-Dec-13 27-Dec-13
4.2.5.7 DRESSING, GLANCING, TAGGING AND TERMINATION 34.00% Terminate Accept 0.00% 0.00% 0.00% 11-Dec-13 19-Feb-14
E4780 DRESSING, GLANDING FOR SMALL POWER CABLE 3.00% 85% 15% 0.00% 0.00% 0.00% 14-Jan-14 27-Jan-14
E4790 DRESSING, GLANDING FOR MAIN EARTHING CABLE 25.00% 85% 15% 0.00% 0.00% 0.00% 22-Jan-14 15-Feb-14
E4800 DRESSING, GLANDING FOR SKID CABLE 9.00% 85% 15% 0.00% 0.00% 0.00% 4-Jan-14 19-Feb-14
E4810 DRESSING, GLANDING FOR HELI DECK CABLE 14.00% 85% 15% 0.00% 0.00% 0.00% 17-Jan-14 10-Feb-14
E4820 DRESSING, GLANDING FOR GENERATOR CABLE 14.00% 85% 15% 0.00% 0.00% 0.00% 16-Jan-14 28-Jan-14
E4830 DRESSING, GLANDING FOR HEATRACING CABLE 8.00% 85% 15% 0.00% 0.00% 0.00% 9-Jan-14 29-Jan-14
E4840 DRESSING, GLANDING FOR LIGHTING CABLE 19.00% 85% 15% 0.00% 0.00% 0.00% 11-Dec-13 9-Jan-14
E4850 DRESSING, GLANDING FOR BATTERY (FROM E-HOUSE TO) 8.00% 85% 15% 0.00% 0.00% 0.00% 24-Dec-13 9-Jan-14
4.2.5.8 INSTALL MCT 1.00% Fit up/ Accept Weld/Accept Accept 0.00% 0.00% 0.00% 2-Dec-13 25-Dec-13
E4850 INSTALL MCT 100.00% 50% 35% 15% 0.00% 0.00% 0.00% 2-Dec-13 25-Dec-13
4.2.5.9 INSTALL ERATHING BOSS 1.00% Fit up/ Accept Weld/Accept Accept 0.00% 0.00% 0.00% 9-Jan-14 13-Feb-14
E4850 INSTALL ERATHING BOSS 100.00% 50% 35% 15% 0.00% 0.00% 0.00% 9-Jan-14 13-Feb-14
4.2.6 BLASTING / PAINTING 8.00% Clean/ Blast Paint Inspect/Accept 16.37% 11.07% 5.30% 20-Apr-13 7-Jan-14
4.2.6.1 STRUCTURE STEEL 90.94% Clean/ Blast Paint Inspect/Accept 18.00% 12.00% 6.00% 22-Apr-13 7-Jan-14
E4865 BLASTING/ PRIMER PAINTING PRIMARY STRUCTURE OF CELLAR DECK 6.00% 40.0 20.00% 40 65% 40 15.00% 100.00% 100.00% 0.00% 22-Apr-13 3-May-13
E4870 FINAL BLASTING/ PAINTING CELLAR DECK 31.50% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 13-Aug-13 9-Oct-13
E4885 BLASTING/ PAINTING PRIMARY STRUCTURE OF MAIN DECK 6.00% 40.0 20.00% 40 65% 40 15.00% 100.00% 100.00% 0.00% 4-May-13 20-May-13
E4890 FINAL BLASTING/ PRIMER PAINTING MAIN DECK 29.50% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 22-Oct-13 7-Nov-13
E4920 BLASTING/ PAINTING BRACING PIPES 12.00% 27.0 20.00% 27 65% 27 15.00% 50.00% 0.00% 50.00% 14-Aug-13 29-Aug-13
E4930 BLASTING/ PAINTING VENT BOOM 15.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 31-Dec-13 7-Jan-14
4.2.6.2 PIPING SUPPORTS/SPOOLS 6.88% Clean/ Blast Paint Inspect/Accept 0.00% 2.31% -2.31% 22-Jun-13 18-Dec-13
E4940 BLASTING/ PAINTING PIPE SUPPORTS 22.73% 20.00% 65% 15.00% 0.00% 10.14% -10.14% 22-Jun-13 30-Aug-13
E5350 BLASTING/ PAINTING PIPE SPOOL 77.27% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 23-Aug-13 18-Dec-13
4.2.6.3 PIPING VALVES 0.31% 80% 20% 0.00% 0.00% 0.00% 28-Nov-13 26-Dec-13
E5760 BLASTING/ PAINTING PIPING VALVES 100.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 28-Nov-13 26-Dec-13
4.2.6.4 INSTRUMENT SUPPORTS 0.94% Clean/ Blast Paint Inspect/Accept 0.00% 0.00% 0.00% 21-Aug-13 4-Sep-13
E5770 BLASTING/ PAINTING SUPPORT FOR FIRE AND GAS SYSTEM 18.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 21-Aug-13 28-Aug-13
E5780 BLASTING/ PAINTING SUPPORT FOR INSTRUMENT EQUIPMENT 14.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 21-Aug-13 28-Aug-13
E5790 BLASTING/ PAINTING SUPPORT FOR TELECOM EQUIPMENT 14.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 21-Aug-13 28-Aug-13
E5800 BLASTING/ PAINTING SUPPORT FOR INSTRUMENT JBs 18.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 21-Aug-13 28-Aug-13
E5810 BLASTING/ PAINTING SUPPORT FOR CABLE TRAY AND TUBING TRAY 33.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 21-Aug-13 31-Aug-13
E5820 BLASTING/ PAINTING SUPPORT FOR BULKEAD 3.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 27-Aug-13 4-Sep-13
19
4.2.6.5 ELECTRICAL SUPPORTS 0.94% Clean/ Blast Paint Inspect/Accept 0.00% 0.00% 0.00% 18-Jul-13 14-Sep-13
E5830 BLASTING/ PAINTING SUPPORT FOR LIGHTING SYSTEM 40.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 18-Jul-13 14-Sep-13
E5840 BLASTING/ PAINTING SUPPORT FOR ELECTRICAL JBs 20.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 30-Jul-13 3-Sep-13
E5850 BLASTING/ PAINTING SUPPORT FOR CABLE TRAY/LADDER 40.00% 20.00% 65% 15.00% 0.00% 0.00% 0.00% 18-Jul-13 14-Sep-13
4.2.7 ARCHITECTURAL 2.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 21-Oct-13 14-Dec-13
E5860 SETTING UP FIRE RATED DOORS 50.00% 80% 20% 0.00% 0.00% 0.00% 29-Nov-13 9-Dec-13
E5880 SETTING UP TEMPORARY SHELTER 50.00% 80% 20% 0.00% 0.00% 0.00% 21-Oct-13 14-Dec-13
4.3 TESTTING & PRE-COMMISSIONING 7.00% 0.00% 0.00% 0.00% 31-Dec-13 28-Feb-14
4.3.1 PROCESS SYSTEM 15.00% COMPLETED 0.00% 0.00% 0.00% 31-Dec-13 26-Feb-14
F1000 100-PROCESS LIQUID 50.00% 100% 0.00% 0.00% 0.00% 31-Dec-13 6-Jan-14
F1010 110-PROCESS GAS 50.00% 100% 0.00% 0.00% 0.00% 19-Feb-14 26-Feb-14
4.3.2 POWER SYSTEM 15.00% COMPLETED 0.00% 0.00% 0.00% 7-Jan-14 20-Feb-14
F1090 510-POWER GENERATION 25.00% 100% 0.00% 0.00% 0.00% 7-Jan-14 17-Jan-14
F1100 520-MAIN POWER DISTRIBUTION 25.00% 100% 0.00% 0.00% 0.00% 18-Jan-14 29-Jan-14
F1110 530-DIRECT CURRENT 25.00% 100% 0.00% 0.00% 0.00% 24-Jan-14 14-Feb-14
F1120 540-MINOR POWER DISTRIBUTION 25.00% 100% 0.00% 0.00% 0.00% 10-Feb-14 20-Feb-14
4.3.3 PROCESS UTILITIES SYSTEM 15.00% COMPLETED 0.00% 0.00% 0.00% 18-Jan-14 27-Feb-14
F1030 230-BLOWDOWN AND RELIEF VENT 30.00% 100% 0.00% 0.00% 0.00% 18-Jan-14 22-Jan-14
F1040 250-PROCESS HEATING 35.00% 100% 0.00% 0.00% 0.00% 19-Feb-14 26-Feb-14
F1050 260-CHEMICAL INJECTION 35.00% 100% 0.00% 0.00% 0.00% 19-Feb-14 27-Feb-14
4.3.4 GENERAL UTILITIES SYSTEM 15.00% COMPLETED 0.00% 0.00% 0.00% 23-Jan-14 18-Feb-14
F1060 310-FUEL & LUBRICATION 30.00% 100% 0.00% 0.00% 0.00% 23-Jan-14 28-Jan-14
F1070 340-HVAC 35.00% 100% 0.00% 0.00% 0.00% 23-Jan-14 10-Feb-14
F1080 350-UTILITY/INSTRUMENT/FUEL GAS 35.00% 100% 0.00% 0.00% 0.00% 11-Feb-14 18-Feb-14
4.3.5 CONTROL SYSTEM 20.00% COMPLETED 0.00% 0.00% 0.00% 23-Jan-14 25-Feb-14
F1130 610-PROCESS CONTROL 30.00% 100% 0.00% 0.00% 0.00% 14-Feb-14 25-Feb-14
F1140 620-ALARM AND SHUTDOWN 35.00% 100% 0.00% 0.00% 0.00% 23-Jan-14 14-Feb-14
F1150 630-FIRE AND GAS DETECTION 35.00% 100% 0.00% 0.00% 0.00% 29-Jan-14 19-Feb-14
4.3.6 TELECOMMUNICATIONS SYSTEM 20.00% COMPLETED 0.00% 0.00% 0.00% 20-Feb-14 25-Feb-14
F1160 710-COMMUNICATION EQUIPMENT 100.00% 100% 0.00% 0.00% 0.00% 20-Feb-14 25-Feb-14
4.3.7 TOPSIDE ONSHORE MCD 0.00% 0.00% 0.00% 0.00% 28-Feb-14 28-Feb-14
F1020 TOPSIDE ONSHORE MCD 100.00% 100% 0.00% 0.00% 0.00% 28-Feb-14 28-Feb-14
4.4 LOAD-OUT AND SEAFASTENING 9.00% 3.50% 3.50% 0.00% 1-Jun-13 10-Mar-14
4.4.1 DRAWINGS 7.00% Prep/ Submit Accept/ Approve 50.00% 50.00% 0.00% 1-Jun-13 30-Jan-14
G1000 PREPARATION/ SUBMISSION/ APPROVAL DRAWINGS FOR LOAD OUT 50.00% 70% 30% 0.00% 100.00% -100.00% 1-Jun-13 25-Jun-13
G1001 PREPARATION/ SUBMISSION/ APPROVAL DRAWINGS FOR SEAFASTENING 50.00% 1.0 70% 1 30% 100.00% 0.00% 100.00% 3-Jan-14 30-Jan-14
4.4.2 LOAD-OUT BEAM FABRICATION 0.00% COMPLETED ACCEPTED 34.78% 3.25% 31.52% 26-Jun-13 16-Aug-13
A11210 MARK & CUT LOAD-OUT BEAM 15.00% COMPLETED ACCEPTED 70.02% 12.50% 57.52% 26-Jun-13 20-Jul-13
A11220 FIT UP LOAD-OUT BEAM 40.00% COMPLETED ACCEPTED 42.28% 3.45% 38.84% 28-Jun-13 27-Jul-13
A11230 WELDING LOAD-OUT BEAM 30.00% COMPLETED ACCEPTED 19.83% 0.00% 19.83% 3-Jul-13 11-Aug-13
A11240 NDT LOAD-OUT BEAM 15.00% COMPLETED ACCEPTED 9.42% 0.00% 9.42% 8-Jul-13 16-Aug-13
4.4.3 MATERIALS (TONNAGE) 4.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 6-Feb-14 6-Feb-14
G1010 RECEIPT MATERIAL 100.00% 80% 20% 0.00% 0.00% 0.00% 6-Feb-14 6-Feb-14
4.4.4 LOAD-OUT AND POSITIONING 42.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 5-Mar-14 5-Mar-14
G1020 LOAD-OUT AND POSITIONING 100.00% 80% 20% 0.00% 0.00% 0.00% 5-Mar-14 5-Mar-14
4.4.5 SEAFASTENING FABRICATION 17.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 7-Feb-14 10-Mar-14
G1030 MARK & CUT FRAME SEAFASTENING 15.00% 80% 20% 0.00% 0.00% 0.00% 7-Feb-14 20-Feb-14
G1040 FIT UP FRAME SEAFASTENING 40.00% 80% 20% 0.00% 0.00% 0.00% 6-Mar-14 8-Mar-14
G1050 WELDING FRAME SEAFASTENING 30.00% 80% 20% 0.00% 0.00% 0.00% 7-Mar-14 9-Mar-14
G1060 NDT FRAME SEAFASTENING 15.00% 80% 20% 0.00% 0.00% 0.00% 7-Mar-14 10-Mar-14
4.4.6 TIE-DOWN ARRANGEMENTS 30.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 24-Feb-14 10-Mar-14
G1070 TIE- DOWN/ SHIPLOOSE MATERIALS 100.00% 80% 20% 0.00% 0.00% 0.00% 24-Feb-14 10-Mar-14
5 HOOK UP & COMMISSIONING 11.00% 0.00% 0.00% 0.00% 3-Sep-13 18-Jun-14
5.1 ONSHORE PREPARATION ACTIVITIES 15.00% 0.00% 0.00% 0.00% 3-Sep-13 19-Mar-14
5.1.1 PREPARATION HUC PROCEDURES 40.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 3-Sep-13 20-Jan-14
H1010 PREPARE HSE PROCEDURE 25.00% 70% 30% 0.00% 0.00% 0.00% 3-Sep-13 11-Nov-13
H1020 PREPARE QA/QC PROCEDURE 35.00% 70% 30% 0.00% 0.00% 0.00% 3-Sep-13 11-Nov-13
H1030 PREPARE JOB CARDS 15.00% 70% 30% 0.00% 0.00% 0.00% 3-Sep-13 4-Dec-13
H1040 PREPARE PLANNING PROCEDURE 25.00% 70% 30% 0.00% 0.00% 0.00% 5-Dec-13 20-Jan-14
5.1.2 MOBILIZATION MANPOWER, MATERIAL 25.00% Prep/ Submit Accept 0.00% 0.00% 0.00% 14-Feb-14 17-Mar-14
H1050 MOBILIZATION MANPOWER 50.00% 80% 20% 0.00% 0.00% 0.00% 14-Feb-14 17-Mar-14
20
H1060 INSPECTION/PACKING SHIP-LOOSE MATERIAL ON WORK BARGE 50.00% 80% 20% 0.00% 0.00% 0.00% 28-Feb-14 17-Mar-14
5.1.3 MOBILIZATION TOOL & EQUIPMENT 25.00% Prep/ Submit Accept 0.00% 0.00% 0.00% 6-Mar-14 17-Mar-14
H1070 MOBILIZATION HUC TOOL&EQUIPMENT 100.00% 80% 20% 0.00% 0.00% 0.00% 6-Mar-14 17-Mar-14
5.1.4 MOBILIZATION HUC BARGE 10.00% Prep/ Submit Accept 0.00% 0.00% 0.00% 14-Mar-14 19-Mar-14
H1080 MOBILIZATION WORK BARGE TO PVCMS'S JETTY 100.00% 80% 20% 0.00% 0.00% 0.00% 14-Mar-14 19-Mar-14
5.2 OFFSHORE HOOK UP AND COMMISSIONING 80.00% 0.00% 0.00% 0.00% 24-Mar-14 23-Apr-14
5.2.1 HOOK UP 60.00% 0.00% 0.00% 0.00% 24-Mar-14 22-Apr-14
5.2.1.1 HOOK UP STRUCTURE 21.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 24-Mar-14 12-Apr-14
H1110 INSTALL GANWAY 4.00% 80% 20% 0.00% 0.00% 0.00% 24-Mar-14 25-Mar-14
H1120 ERECT TEMPORARY STAIR WAY TO CELLAR DECK & SERVICE PLATFORM 7.00% 80% 20% 0.00% 0.00% 0.00% 25-Mar-14 26-Mar-14
H1130 INSTALL STAIR WAY FROM OPEN& CLOSED DRAIN DECK TO CELLAR DECK 7.50% 80% 20% 0.00% 0.00% 0.00% 26-Mar-14 1-Apr-14
H1135 INSTALL STAIR WAY TO SERVICE PLATFORM 5.50% 80% 20% 0.00% 0.00% 0.00% 3-Apr-14 5-Apr-14
H1145 REMOVE 04 LIFTING PADEYES/ PROTECTION FRAME 11.00% 80% 20% 0.00% 0.00% 0.00% 28-Mar-14 1-Apr-14
H1150 INSTALL DECK PLATES, HANDRAILS 8.00% 80% 20% 0.00% 0.00% 0.00% 1-Apr-14 4-Apr-14
H1160 ERECT SCAFFOLDING FOR CORRECTING FLARE BOOM POSITION 6.00% 80% 20% 0.00% 0.00% 0.00% 4-Apr-14 6-Apr-14
H1170 INSTALL STRUSS ROWS 9.00% 80% 20% 0.00% 0.00% 0.00% 6-Apr-14 8-Apr-14
H1175 INSTALL RISER GUARD 10.00% 80% 20% 0.00% 0.00% 0.00% 8-Apr-14 10-Apr-14
H1180 CUT OFF TEMPORARY SUPPORT OF CRANE 7.00% 80% 20% 0.00% 0.00% 0.00% 1-Apr-14 3-Apr-14
H1190 TOUCH UP PAITING FOR STRUCTURE 12.50% 80% 20% 0.00% 0.00% 0.00% 6-Apr-14 12-Apr-14
H1200 TOUCH UP PAINTING FOR JOINTS OF TOPSIDE'S LEGS TO JACKET 12.50% 80% 20% 0.00% 0.00% 0.00% 27-Mar-14 2-Apr-14
5.2.1.2 INSTALL MECHANICAL ITEMS 2.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 27-Mar-14 31-Mar-14
A11550 SETTING UP/ INSTALL CLOSED DRAIN PUMPS 50.00% 80% 20% 0.00% 0.00% 0.00% 27-Mar-14 29-Mar-14
A11560 SETTING UP/ INSTALL OPEN DRAIN PUMPS 50.00% 80% 20% 0.00% 0.00% 0.00% 29-Mar-14 31-Mar-14
5.2.1.3 HOOK UP PIPING 45.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 25-Mar-14 20-Apr-14
5.2.1.3.1 HOOK UP RISER 15.00% 0.00% 0.00% 0.00% 25-Mar-14 2-Apr-14
H3875 HOOK UP RISER SPOOLS 100.00% 80% 20% 0.00% 0.00% 0.00% 25-Mar-14 2-Apr-14
5.2.1.3.2 HOOK UP FOR FLOWLINE 20.00% 0.00% 0.00% 0.00% 29-Mar-14 13-Apr-14
5.2.1.3.2.1 HOOK UP FOR SLOT 4P 25.00% 0.00% 0.00% 0.00% 29-Mar-14 7-Apr-14
H1290 INSTALL PL PIPE SPOOLS 50.00% 80% 20% 0.90% 0.00% 0.00% 0.00% 29-Mar-14 7-Apr-14
H1310 INSTALL PG PIPE SPOOLS 50.00% 80% 20% 0.00% 0.00% 0.00% 31-Mar-14 7-Apr-14
5.2.1.3.2.2 HOOK UP FOR SLOT 1P 25.00% 0.00% 0.00% 0.00% 31-Mar-14 9-Apr-14
H3885 INSTALL PL PIPE SPOOLS 50.00% 80% 20% 0.00% 0.00% 0.00% 31-Mar-14 9-Apr-14
H3895 INSTALL PG PIPE SPOOLS 50.00% 80% 20% 0.00% 0.00% 0.00% 2-Apr-14 9-Apr-14
5.2.1.3.2.3 HOOK UP FOR SLOT 2P 25.00% 0.00% 0.00% 0.00% 2-Apr-14 11-Apr-14
H3905 INSTALL PL PIPE SPOOLS 50.00% 80% 20% 0.00% 0.00% 0.00% 2-Apr-14 11-Apr-14
H3915 INSTALL PG PIPE SPOOLS 50.00% 80% 20% 0.00% 0.00% 0.00% 4-Apr-14 11-Apr-14
5.2.1.3.2.4 HOOK UP FOR SLOT 3P 25.00% 0.00% 0.00% 0.00% 4-Apr-14 13-Apr-14
H3925 INSTALL PL PIPE SPOOLS 50.00% 80% 20% 0.00% 0.00% 0.00% 4-Apr-14 13-Apr-14
H3935 INSTALL PG PIPE SPOOLS 50.00% 80% 20% 0.00% 0.00% 0.00% 6-Apr-14 13-Apr-14
5.2.1.3.3 HOOK UP FOR OTHER PIPING SYSTEMS 40.00% 0.00% 0.00% 0.00% 31-Mar-14 15-Apr-14
H3945 HOOK UP WP SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 31-Mar-14 5-Apr-14
H3965 HOOK UP DH SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 31-Mar-14 4-Apr-14
H3975 HOOK UP DN SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 5-Apr-14 9-Apr-14
H3985 HOOK UP DC SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 4-Apr-14 8-Apr-14
H3995 HOOK UP WI SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 9-Apr-14 11-Apr-14
H4005 HOOK UP VL SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 8-Apr-14 12-Apr-14
H4015 HOOK UP FD SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 11-Apr-14 15-Apr-14
H4025 HOOK UP UG SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 6-Apr-14 8-Apr-14
H4035 HOOK UP VT SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 11-Apr-14 15-Apr-14
H4045 HOOK UP FD SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 11-Apr-14 15-Apr-14
H4115 HOOK UP FW SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 11-Apr-14 15-Apr-14
H4125 HOOK UP VA SYSTEM 8.33% 80% 20% 0.00% 0.00% 0.00% 8-Apr-14 12-Apr-14
5.2.1.3.4 LEAK TEST PIPING 25.00% 0.00% 0.00% 0.00% 13-Apr-14 20-Apr-14
H4065 LEAK TEST FOR FLOWLINE 50.00% 80% 20% 0.00% 0.00% 0.00% 13-Apr-14 18-Apr-14
H4075 LEAK TEST FOR OTHER PIPING SYSTEM 50.00% 80% 20% 0.00% 0.00% 0.00% 15-Apr-14 20-Apr-14
21
5.2.1.4 HOOK UP ELECTRICAL 7.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 28-Mar-14 22-Apr-14
H1730 INSTALL ELECTRICAL SUPPORT 8.00% 80% 20% 0.00% 0.00% 0.00% 28-Mar-14 1-Apr-14
H1740 INSTALL CABLE TRAY 23.00% 80% 20% 0.00% 0.00% 0.00% 29-Mar-14 2-Apr-14
H1750 INSTALL LIGHTING EQUIPMENT 23.00% 80% 20% 0.00% 0.00% 0.00% 31-Mar-14 4-Apr-14
H1760 UNROLL, GLAND, TERMINATE CABLE FOR LIGHTING 23.00% 80% 20% 0.00% 0.00% 0.00% 4-Apr-14 8-Apr-14
H1770 UNROLL, GLAND, TERMINATE CABLE FOR MAIN EARTHING 9.00% 80% 20% 0.00% 0.00% 0.00% 6-Apr-14 8-Apr-14
H1780 INSTALL HEATRACING 8.00% 80% 20% 0.00% 0.00% 0.00% 9-Apr-14 20-Apr-14
H1790 TESTING 6.00% 80% 20% 0.00% 0.00% 0.00% 20-Apr-14 22-Apr-14
5.2.1.5 HOOK UP INSTRUMENT 20.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 4-Apr-14 20-Apr-14
H1810 HOOK UP INSTRUMENT FOR SLOT 4P 15.00% 80% 20% 0.00% 0.00% 0.00% 4-Apr-14 11-Apr-14
H1820 HOOK UP INSTRUMENT FOR SLOT 1P 25.00% 80% 20% 0.00% 0.00% 0.00% 6-Apr-14 13-Apr-14
H3855 HOOK UP INSTRUMENT FOR SLOT 2P 25.00% 80% 20% 0.00% 0.00% 0.00% 8-Apr-14 15-Apr-14
H3865 HOOK UP INSTRUMENT FOR SLOT 3P 15.00% 80% 20% 0.00% 0.00% 0.00% 10-Apr-14 17-Apr-14
H3868 HOOK UP INSTRUMENT FOR OTHER INSTRUMENT ITEMS 20.00% 80% 20% 0.00% 0.00% 0.00% 11-Apr-14 20-Apr-14
5.2.1.6 TOUCH UP PAINTING/ MARKING 5.00% COMPLETED ACCEPTED 0.00% 0.00% 0.00% 17-Apr-14 22-Apr-14
H1880 TOUCH UP PAINTING & MARKING 100.00% 80% 20% 0.00% 0.00% 0.00% 17-Apr-14 22-Apr-14
5.2.2 COMMISSIONING 40.00% COMPLETED 0.00% 0.00% 0.00% 3-Apr-14 23-Apr-14
5.2.2.1 PROCESS SYSTEM 15.00% 0.00% 0.00% 0.00% 8-Apr-14 23-Apr-14
H6010 100-PROCESS LIQUID 50.00% 100% 0.00% 0.00% 0.00% 8-Apr-14 13-Apr-14
H6020 110-PROCESS GAS 50.00% 100% 0.00% 0.00% 0.00% 17-Apr-14 23-Apr-14
5.2.2.2 PROCESS UTILITIES SYSTEM 15.00% 0.00% 0.00% 0.00% 12-Apr-14 17-Apr-14
H6030 250-PROCESS HEATING 40.00% 100% 0.00% 0.00% 0.00% 12-Apr-14 17-Apr-14
H6040 260-CHEMICAL INJECTION 40.00% 100% 0.00% 0.00% 0.00% 13-Apr-14 16-Apr-14
H6160 230-BLOWDOWN AND RELIEF VENT 20.00% 100% 0.00% 0.00% 0.00% 12-Apr-14 14-Apr-14
5.2.2.3 GENERAL UTILITIES SYSTEM 15.00% 0.00% 0.00% 0.00% 8-Apr-14 13-Apr-14
H6050 310-FUEL & LUBRICATION 33.0% 100% 0.00% 0.00% 0.00% 8-Apr-14 12-Apr-14
H6060 340-HVAC 33.0% 100% 0.00% 0.00% 0.00% 8-Apr-14 12-Apr-14
H6070 350-UTILITY/INSTRUMENT/FUEL GAS 34.0% 100% 0.00% 0.00% 0.00% 8-Apr-14 13-Apr-14
5.2.2.4 POWER SYSTEM 20.00% 0.00% 0.00% 0.00% 3-Apr-14 8-Apr-14
H6080 510-POWER GENERATION 30.00% 100% 0.00% 0.00% 0.00% 3-Apr-14 8-Apr-14
H6090 520-MAIN POWER DISTRIBUTION 25.00% 100% 0.00% 0.00% 0.00% 3-Apr-14 8-Apr-14
H6100 530-DIRECT CURRENT 25.00% 100% 0.00% 0.00% 0.00% 3-Apr-14 8-Apr-14
H6110 540-MINOR POWER DISTRIBUTION 20.00% 100% 0.00% 0.00% 0.00% 3-Apr-14 8-Apr-14
5.2.2.5 CONTROL SYSTEM 20.00% 0.00% 0.00% 0.00% 5-Apr-14 12-Apr-14
H6120 610-PROCESS CONTROL 35.00% 100% 0.00% 0.00% 0.00% 8-Apr-14 12-Apr-14
H6130 620-ALARM AND SHUTDOWN 30.00% 100% 0.00% 0.00% 0.00% 5-Apr-14 8-Apr-14
H6140 630-FIRE AND GAS DETECTION 35.00% 100% 0.00% 0.00% 0.00% 5-Apr-14 10-Apr-14
5.2.2.6 TELECOMMUNICATIONS SYSTEM 15.00% 0.00% 0.00% 0.00% 10-Apr-14 15-Apr-14
H6150 710-COMMUNICATION EQUIPMENT 100.00% 100% 0.00% 0.00% 0.00% 10-Apr-14 15-Apr-14
TOPSIDE START UP 0.00% 0.00% 0.00% 0.00% 24-Apr-14 24-Apr-14
H6000 TOPSIDE START UP 100.00% 100% 0.00% 0.00% 0.00% 24-Apr-14
5.3 FINAL DOCUMENTATION 5.00% 0.00% 0.00% 0.00% 21-Aug-13 18-Jun-14
5.3.1 EQUIMENT DOSSIER 22.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 21-Aug-13 14-Apr-14
I1000 SUBMISSION EQUIMENT DOSSIER 65.00% 80% 20% 0.00% 0.00% 0.00% 21-Aug-13 18-Feb-14
I1010 APPROVAL EQUIMENT DOSSIER 25.00% 80% 20% 0.00% 0.00% 0.00% 30-Oct-13 28-Feb-14
I1020 FINAL SET EQUIMENT DOSSIER 10.00% 80% 20% 0.00% 0.00% 0.00% 3-Mar-14 14-Apr-14
5.3.2 QA/QC DOCUMENTATION 17.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 13-Nov-13 18-Jun-14
I1030 SUBMISSION QA/QC DOCUMENTATION 65.00% 80% 20% 0.00% 0.00% 0.00% 13-Nov-13 15-May-14
I1040 APPROVAL QA/QC DOCUMENTATION 25.00% 80% 20% 0.00% 0.00% 0.00% 10-Feb-14 4-Jun-14
I1050 FINAL SET QA/QC DOCUMENTATION 10.00% 80% 20% 0.00% 0.00% 0.00% 8-May-14 18-Jun-14
5.3.3 MATERIAL DOCUMENTATION 8.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 13-Nov-13 18-Jun-14
I1060 SUBMISSION MATERIAL DOCUMENTATION 65.00% 80% 20% 0.00% 0.00% 0.00% 13-Nov-13 15-May-14
I1070 APPROVAL MATERIAL DOCUMENTATION 25.00% 80% 20% 0.00% 0.00% 0.00% 10-Feb-14 4-Jun-14
I1080 FINAL SET MATERIAL DOCUMENTATION 10.00% 80% 20% 0.00% 0.00% 0.00% 8-May-14 18-Jun-14
5.3.4 TESTTING & PRECOMMISSIONING DOCUMENTATION 10.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 28-Nov-13 28-Mar-14
I1090 SUBMISSION TESTTING & PRECOMMISSIONING DOCUMENTATION 65.00% 80% 20% 0.00% 0.00% 0.00% 28-Nov-13 18-Feb-14
22
I1100 APPROVAL TESTTING & PRECOMMISSIONING DOCUMENTATION 25.00% 80% 20% 0.00% 0.00% 0.00% 25-Dec-13 28-Feb-14
I1110 FINAL SET TESTTING & PRECOMMISSIONING DOCUMENTATION 10.00% 80% 20% 0.00% 0.00% 0.00% 3-Mar-14 28-Mar-14
5.3.5 DESIGN DATA 3.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 13-Nov-13 18-Jun-14
I1120 SUBMISSION DESIGN DATA 65.00% 80% 20% 0.00% 0.00% 0.00% 13-Nov-13 15-May-14
I1130 APPROVAL DESIGN DATA 25.00% 80% 20% 0.00% 0.00% 0.00% 10-Feb-14 4-Jun-14
I1140 FINAL SET DESIGN DATA 10.00% 80% 20% 0.00% 0.00% 0.00% 8-May-14 18-Jun-14
5.3.6 AS-BUILT DRAWINGS 31.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 21-Aug-13 14-Apr-14
I1150 SUBMISSION AS-BUILT DRAWINGS 65.00% 80% 20% 0.00% 0.00% 0.00% 21-Aug-13 18-Feb-14
I1160 APPROVAL AS-BUILT DRAWINGS 25.00% 80% 20% 0.00% 0.00% 0.00% 30-Oct-13 28-Feb-14
I1170 FINAL SET AS-BUILT DRAWINGS 10.00% 80% 20% 0.00% 0.00% 0.00% 3-Mar-14 14-Apr-14
5.3.7 CLOSE-OUT REPORT 2.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 17-Mar-14 18-Jun-14
I1180 SUBMISSION CLOSE-OUT REPORT 65.00% 80% 20% 0.00% 0.00% 0.00% 17-Mar-14 15-May-14
I1190 APPROVAL CLOSE-OUT REPORT 25.00% 80% 20% 0.00% 0.00% 0.00% 8-May-14 4-Jun-14
I1200 FINAL SET CLOSE-OUT REPORT 10.00% 80% 20% 0.00% 0.00% 0.00% 5-Jun-14 18-Jun-14
5.3.8 SHIPLOOSE LIST 6.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 5-Dec-13 27-Feb-14
I1210 SUBMISSION SHIPLOOSE LIST 65.00% 80% 20% 0.00% 0.00% 0.00% 5-Dec-13 18-Feb-14
I1220 APPROVAL SHIPLOOSE LIST 25.00% 80% 20% 0.00% 0.00% 0.00% 16-Jan-14 24-Feb-14
I1230 FINAL SET SHIPLOOSE LIST 10.00% 80% 20% 0.00% 0.00% 0.00% 13-Feb-14 27-Feb-14
5.3.9 NDT RADIOGRAPHIC FILMS 1.00% Prep/ Submit Accept/ Approve 0.00% 0.00% 0.00% 11-Dec-13 18-Jun-14
I1240 SUBMISSION NDT RADIOGRAPHIC FILMS 65.00% 80% 20% 0.00% 0.00% 0.00% 11-Dec-13 15-May-14
I1250 APPROVAL NDT RADIOGRAPHIC FILMS 25.00% 80% 20% 0.00% 0.00% 0.00% 24-Feb-14 4-Jun-14
I1260 FINAL SET NDT RADIOGRAPHIC FILMS 10.00% 80% 20% 0.00% 0.00% 0.00% 8-May-14 18-Jun-14
23
ATTACHMENT 9
Sub-contracting Plan
DMDP-A DRILLING PLATFORM
EPCC FOR DMDP-A DRILLING PLATFORM
SUB-CONTRACTING PLAN (TOPSIDE)
4 Bolt tensioning & Leak testing Service 16-Sep-13 7-Oct-13 17-Oct-13 24-Oct-13 31-Oct-13 18-Nov-13
5 Weighing & Load out Service 24-Oct-13 14-Nov-13 24-Nov-13 1-Dec-13 8-Dec-13 25-Dec-13
ATTACHMENT 10
Payment Schedule
DMDP-A DRILLING PLATFORM
EPCC FOR DMDP-A DRILLING PLATFORM
PAYMENT SCHEDULE
Committed Value Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14
ENGINEERING
1 1,564,686 - 62,587.44 641,521.26 704,108.70 156,468.60 - - - - - - -
(DETAIL ENGINEERING)
ENGINEERING
2 78,234 - 3,129.36 32,075.94 35,205.30 7,823.40 - - - - - - - - - - - - - -
(MANAGERMENT FEE)
3 PROCUREMENT 11,746,178 978,848.17 978,848.17 978,848.17 978,848.17 978,848.17 978,848.17 978,848.17 978,848.17 978,848.17 978,848.17 978,848.17 978,848.17
4 FABRICATION (JACKET) 9,077,721 - 363,108.84 1,497,823.97 953,160.71 771,606.29 1,225,492.34 1,588,601.18 2,677,927.70 - - - - - - - - - - -
5 FABRICATION (TOPSIDES) 17,789,257 - 711,570.28 1,838,223.22 948,760.37 948,760.37 592,975.23 770,867.80 592,975.23 592,975.23 770,867.80 2,371,900.93 1,660,330.65 1,482,438.08 592,975.23 - - 2,134,710.84 889,462.85 889,462.85
7 PROVISIONAL SUM COST PLUS 7,249,263 604,105.26 604,105.26 604,105.26 604,105.26 604,105.26 604,105.26 604,105.26 604,105.26 604,105.26 604,105.26 604,105.26 604,105.26
SUB-TOTAL 52,110,815 - 1,324,615 5,638,653 4,224,189 3,467,612 3,401,421 3,942,422 4,853,856 2,175,929 2,353,821 3,954,854 3,243,284 3,065,392 2,175,929 - - 5,128,270 1,580,284 1,580,284
VAT 10% 5,211,081.51 - 132,461.50 563,865.26 422,418.85 346,761.21 340,142.10 394,242.24 485,385.64 217,592.87 235,382.12 395,485.44 324,328.41 306,539.15 217,592.87 - - 512,827.02 158,028.43 158,028.43
TOTAL 57,321,896.60 - 1,457,076.46 6,202,517.83 4,646,607.35 3,814,373.29 3,741,563.09 4,336,664.64 5,339,241.99 2,393,521.52 2,589,203.35 4,350,339.79 3,567,612.49 3,371,930.66 2,393,521.52 - - 5,641,097.26 1,738,312.68 1,738,312.68
DMDP-A DRILLING PLATFORM
EPCC FOR DMDP-A DRILLING PLATFORM
Progress Cummulative Progress Payment S-curve Plan Progress Payment Actual Progress Payment
100.00%
90.00%
80.00%
70.00%
60.00%
50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
13-Sep-13
14-Feb-14
14-Mar-14
14-Sep-14
13-Apr-13
13-Aug-13
13-Oct-13
14-Apr-14
14-Aug-14
13-Nov-13
4-Feb-13
13-Jun-13
13-Jul-13
14-Jan-14
14-Jun-14
14-Jul-14
13-Dec-13
13-May-13
14-May-14
No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
13-May-13
14-May-14
14-Mar-14
13-Nov-13
13-Aug-13
14-Aug-14
13-Dec-13
13-Sep-13
14-Feb-14
14-Sep-14
13-Apr-13
14-Apr-14
13-Jun-13
13-Oct-13
14-Jun-14
14-Jan-14
13-Jul-13
14-Jul-14
4-Feb-13
Period