RNZCH PDF
RNZCH PDF
RNZCH PDF
Introduction
Rentals
Comparative Costs
International Costs
Detailed Rates
Building Websites
Construction Management
Legislation
Tax
Index
CD-ROM Extras
Alfriston College – Manurewa Auckland University School of Engineering
Library and Student Centre
2008 NZIA Resene New Zealand Architecture Award
2007 NZIA Resene Local Award
2007 NZIA Resene Local Award
Whangaparaoa Library
2006 NZ Property Council Merit Award – Community
2005 NZIA Resene Local Award
Contents
0.1 Rawlinsons Directory 0-3 3.11 Interior Doors 3-85
0.2 Advertisers Index 0-4 3.12 Floor Finishes 3-87
0.3 Introduction 0-5 3.13 Wall Finishes 3-89
0.4 How to Use This Handbook 0-6 3.14 Ceiling Finishes 3-91
3.15 Sanitary Plumbing 3-92
Building Costs Per Square Metre 1-9
3.16 Heating and Ventilation 3-94
How to Use This Section 1-10 3.17 Fire Services 3-96
1.1 Administration, Civic 1-11 3.18 Electrical Services 3-97
1.2 Banks 1-13 3.19 Lifts and Escalators 3-99
1.3 Educational 1-14 3.20 Drainage 3-100
1.4 Entertainment 1-16 3.21 External Works 3-101
1.5 Hospitals, Health 1-17 3.22 Preliminaries 3-102
1.6 Hotels, Motels, Taverns 1-18
1.7 Industrial 1-20 Detailed Rates 4-103
1.8 Offices 1-22 How to Use this Section 4-109
1.9 Parking 1-23 4.1 Preliminaries 4-110
1.10 Primary Industry 1-24 4.2 Demolition and Alterations 4-128
1.11 Recreational Facilities 1-24 4.3 Excavation 4-133
1.12 Residential 1-26 4.4 Piling 4-137
1.13 Devotional Buildings 1-28 4.5 Concrete Work 4-142
1.14 Retail 1-29 4.6 Formwork 4-150
1.15 Miscellaneous Building Types 1-30 4.7 Sprayed Concrete 4-156
1.16 Worked Example 1-31 4.8 Precast Concrete 4-157
4.9 Reinforcing Steel 4-161
Elemental Costs of Buildings 2-33
4.10 Structural Steelwork 4-163
How to Use This Section 2-34 4.11 Waterproofing 4-173
Worked Example 2-35 4.12 Brickwork 4-175
Definition of Elements 2-36 4.13 Concrete Blockwork 4-179
2.1 Administration, Civic 2-38 4.14 Masonry 4-181
2.2 Banks 2-41 4.15 Metalwork 4-185
2.3 Educational 2-42 4.16 Carpentry 4-192
2.4 Entertainment 2-46 4.17 Hardware 4-223
2.5 Hospitals, Health 2-47 4.18 Laminated Timber 4-239
2.6 Hotels, Motels, Taverns 2-49 4.19 Joinery 4-243
2.7 Industrial 2-51 4.20 Windows 4-251
2.8 Offices 2-53 4.21 Doors 4-257
2.9 Parking 2-54 4.22 Partitions 4-269
2.10 Primary Industry 2-55 4.23 Insulating Panel Systems 4-277
2.11 Recreational 2-56 4.24 Proprietary Cladding Systems 4-279
Recreational, Residential 2-57 4.25 Roof Coverings 4-281
2.12 Residential 2-58 4.26 Plumbing 4-297
2.13 Devotional Buildings 2-59 4.27 Drainage 4-316
2.14 Retail 2-60 4.28 Mechanical Services 4-329
Comparative Costs 3-61 4.29 Fire Protection 4-349
Introduction 3-63 4.30 Lifts and Escalators 4-352
3.1 Site Preparation 3-64 4.31 Electrical Services 4-355
3.2 Substructure 3-65 4.32 Solid Plaster 4-384
3.3 Frame 3-67 4.33 Plasterboard Linings 4-387
3.4 Structural Walls 3-71 4.34 Suspended Ceilings 4-394
3.5 Upper Floors 3-72 4.35 Tiling 4-397
3.6 Roof 3-76 4.36 Resilient Flooring 4-400
3.7 Exterior Walls, Exterior Finish 3-77 4.37 Painting & Specialist Finishes 4-406
3.8 Windows and Exterior Doors 3-81 4.38 Glazing 4-413
3.9 Stairs and Balustrades 3-82 4.39 Fire Proofing 4-418
3.10 Interior Walls and Partitions 3-84 4.40 External Works 4-422
2008
Page i-ii
NZIQS
PO Box 10 469
Level 7, 108 The Terrace
Wellington, New Zealand
Freephone (0800 4 NZIQS
(0800 469 477)
Ph: x(64 4) 473 5521
Fax: (64 4) 473 2918
Email: [email protected]
Web: www.nziqs.co.nz
cost control
for your project
Rawlinsons provide a powerful combination of cost engineering,
value management, quantity surveying and contract financial administration
expertise throughout New Zealand, Australia and the Asia/Pacific region.
• Estimating
• Preparation of schedules of quantities
• Cost planning and feasibility studies
• Contract financial control and administration
• Cost engineering
• Independent progress measurement
• Value management
• Independent commercial project audits
• Contract preparation
www.rawlinsons.co.nz
Auckland 09 522 4780 • Christchurch 03 366 0371 • Dunedin 03 477 6369 • New Plymouth 06 758 0814 • Wellington 04 472 2516
2008
Rawlinsons Directory
New Zealand
Page 0-3
1 Rawlinsons Directory
New Zealand www.rawlinsons.co.nz
Auckland Christchurch Dunedin Wellington
Rawlinsons Limited Rawlinsons Limited Rawlinsons Limited Rawlinsons Limited
Level 4, 135 Broadway PriceWaterhouse Coopers Ctr 106 George Street 276-278 Lambton Quay
P O Box 9804, Newmarket Level 11, 119 Armagh Street P O Box 1449 P O Box 2919
Auckland P O Box 2796, Christchurch Dunedin Wellington
T: 64+9-522-4780 T: 64+3-366-0371 T: 64+3-477-6369 T: 64+4-472-2516
F: 64+9-524-4977 F: 64+3-365-4984 F: 64+3-477-6225 F: 64+4-472-5416
E: [email protected] E: [email protected] E: [email protected] E: [email protected]
Director Director Manager Director
Andrew Millard Peter Eggleton Mark Burrows Paul Bunkall
2 Advertisers Index
Advertiser Page No
Corus New Zealand Ltd 4-154, 3-74
Gibson O’Connor Ltd b
New Zealand Institute of Quantity Surveyors 0-1
Rawlinsons Limited 0-2
Rawlinsons Media—Managing Contractors Cashflow 0-7
Rawlinsons Media—A guide to the Construction Contracts Act 0-8
Winstone Wallboards Ltd 4-390
2008
Introduction
Your Suggestions
Page 0-5
3 Introduction
The aim of the Construction Handbook is to provide a comprehensive reference work on New
Zealand building costs and other related information, for those involved in the various disciplines of
the construction and property industries.
The Handbook has achieved a reputation as the leading authority on the various aspects of
construction costs in New Zealand, and is recognised as an authoritative text in the courts for cases
relating to disputes in respect of construction cost.
This edition, like previous editions, is committed to the dissemination of information necessary to
implement cost control, cost management and cost benefit studies effectively at all stages of
planning and construction.
It should be stressed that attention must be given to the particular circumstances and conditions of
the project being reviewed, when using the data contained in this Handbook.
Please read the “How to use this Handbook” section, and the introductory notes to each chapter, as
an essential part of using this handbook effectively.
3.1 Your Suggestions
We welcome suggestions and feedback. Fax, phone or email the editor.
If there are items you would like to see included, let us know. If you would like your products
featured or included, send the details to us.
If you can’t find something in the index, and you know it’s in the book, let us know and we’ll make
sure the entry is added.
3.2 Publisher’s Note
Whilst every effort has been made to ensure the accuracy of the information given to this
publication, neither the editors nor the publishers in any way accept liability for loss of any kind
resulting from the use made by any person of such information.
All prices exclude G.S.T. (unless stated otherwise).
We wish to record our appreciation of the many individuals and organisations in New Zealand and
overseas who have provided data and assisted in the compilation of this edition.
2008
How to Use This Handbook
Estimating—Building Costs Per Square Metre
Page 0-6
Adjudication
What you will experience if you get involved
• What is adjudication?
• Using the adjudication process – who does what,
consequences of not participating/co-operating
• The adjudicator’s powers and duties
• Avoiding disputes arising
AUTHOR
Peter Degerholm, FNZIQS, AAMINZ, Registered Quantity Surveyor
Peter is an adjudicator and arbitrator. He is currently Chief Executive of the Now $25,$including
45.00
NZ Building Subcontractors Federation, and was involved throughout the + post and packaging
post and packaging
development of this legislation.
An essential tool
for a wide range of professionals
AUTHORS
Geoff Bayley
FNZIQS, FAMINZ, Registered Quantity Surveyor
2008
How to Use This Section
Exclusions
Page 1-10
2008
Administration, Civic
Administrative
Page 1-11
1 Administration, Civic
1.1 Administrative
1.1.1 Administration Office, up to 2 storeys. m2 1,525-1,725 1,475-1,675 1,500-1,700 1,450-1,650
Sub-divisional partitions to offices,
common areas, amenities and reception.
Excludes HVAC and lifts. Medium
standard finishes.
1.1.2 Air conditioning ($/m2 of A/C area) m2 245-295 240-290 250-300 240-290
1.1.3 Administration Office, 3 to 5 storeys. m2 2,150-2,450 2,100-2,400 2,100-2,400 2,050-2,350
Sub-divisional partitions to offices,
common areas, amenities and reception.
Includes HVAC, sprinklers and lifts.
Medium standard finishes.
1.1.4 Town Hall, 1000–2000 seat capacity. m2 3,050-3,350 2,950-3,250 3,050-3,350 2,950-3,250
Main hall and seminar halls,
administration offices, kitchen and bar
facilities. Includes HVAC, sprinklers,
escalators. High standard finishes.
For Elemental Analysis, see page 2-38
1.2 Civic
1.2.1 Civic Centre, 500–750 seat capacity. m2 2,500-2,800 2,400-2,700 2,400-2,700 2,400-2,700
Main hall and smaller hall, administration
offices, kitchen and bar facilities. Includes
HVAC, sprinklers, escalators. Medium
standard finishes.
1.2.2 Community Centre and Library, single m2 2,450-2,750 2,450-2,750 2,500-2,800 2,450-2,750
storey. Meeting rooms, office, workrooms,
toilets. Includes HVAC, fire, security.
Medium standard finishes
1.2.3 Library, Suburban, up to 2 storeys. m2 1,675-1,875 1,625-1,825 1,675-1,875 1,625-1,825
Storage room, small office, amenities.
Includes partial ventilation, sprinklers.
Excludes heating, air-conditioning, lifts.
Medium standard finishes.
1.2.4 Air conditioning ($/m2 of A/C area) m2 245-295 240-290 250-300 240-290
1.2.5 Library, City, up to 5 storeys. m2 2,650-2,950 2,600-2,900 2,650-2,950 2,600-2,900
Archives, storage, offices, amenities.
Includes HVAC, sprinklers, slow lifts. High
standard finishes.
1.2.6 Art Gallery/Museum, City, up to 2 m2 3,750-4,050 3,650-3,950 3,750-4,050 3,650-3,950
storeys. Galleries, work areas, small
office, amenities. Includes HVAC,
sprinklers, slow lifts, security systems.
High standard finishes.
2008
Administration, Civic
Authorities
Page 1-12
1.3 Authorities
1.3.1 High Court, City, 5 to 10 storeys. Court m2 3,750-4,050 3,650-3,950 3,750-4,050 3,550-3,850
rooms and fit-out, small holding cell block,
offices, amenities. HVAC, sprinklers, lifts,
security systems. High standard finishes.
1.3.2 District Court, up to 2 storeys. Court m2 2,000-2,200 1,925-2,125 1,900-2,100 1,900-2,100
rooms and fit-out, offices, amenities.
Partial HVAC. Medium standard finishes.
1.3.3 Air conditioning ($/m2 of A/C area) m2 290-340 290-340 295-345 290-340
1.3.4 Fire Station, Staffed, up to 3 storeys. m2 1,750-1,950 1,700-1,900 1,725-1,925 1,700-1,900
Appliance bays, equipment stores,
cleaning area, station offices, watch room,
locker rooms, amenities. Partial HVAC,
emergency generator. Medium standard
finishes.
1.3.5 Fire Station, Volunteer, single storey. m2 1,600-1,800 1,575-1,775 1,600-1,800 1,575-1,775
Appliance bays, equipment stores,
cleaning area, station office, watch room,
locker rooms, amenities. Emergency
generator. Medium standard finishes
1.3.6 Police Station, City, 5 to 10 storeys. m2 2,600-2,900 2,500-2,800 2,550-2,850 2,500-2,800
Offices, holding cell block, watch rooms,
locker rooms, amenities. HVAC,
sprinklers, lifts, security systems. Medium
standard finishes.
1.3.7 Police Station, Suburban, single storey. m2 2,250-2,550 2,200-2,500 2,200-2,500 2,200-2,500
Offices, meeting rooms, watch and muster
area, locker rooms, staff amenities,
exhibits/armoury store, cell and secure
processing area. HVAC, security systems.
Medium standard finishes.
2008
Banks
Bank, Construction
Page 1-13
2 Banks
2.1 Bank, Construction
2.1.1 Bank, Suburban Branch, single storey. m2 1,975-2,175 1,925-2,125 1,975-2,175 1,900-2,100
Offices, small vault, amenities, banking
chamber and banking chamber fittings.
Includes partial HVAC and security. High
standard finishes.
2.1.2 Bank, City Branch, up to 2 storeys. m2 2,350-2,650 2,300-2,600 2,300-2,600 2,250-2,550
Offices, small vault, amenities, banking
chamber and banking chamber fittings.
Includes HVAC and security. High
standard finishes.
2.1.3 Bank, City, Head Office, 5 to 10 storeys. m2 3,100-3,400 3,000-3,300 3,050-3,350 3,000-3,300
Offices, large vault, amenities, banking
chamber and banking chamber fittings.
Includes HVAC, sprinklers, lifts and
security systems. High standard finishes.
2008
Educational
Schools–Teaching
Page 1-14
3 Educational
3.1 Schools–Teaching
3.1.1 Primary School, modern specification, m2 1,900-2,100 1,900-2,100 1,900-2,100 1,900-2,100
single storey. Includes built-in cupboards
and fittings, heating and ventilation,
sprinklers, data/IT wiring. Medium
standard finishes. Toilet facilities.
Secondary School, 1 to 2 storeys.
Includes built-in cupboards and fittings.
Includes heating. Medium standard
finishes. Toilet facilities.
3.1.2 Classrooms m2 1,850-2,050 1,800-2,000 1,825-2,025 1,800-2,000
3.1.3 Laboratories m2 2,300-2,600 2,250-2,550 2,250-2,550 2,250-2,550
3.1.4 Art and Photography Suite m2 1,950-2,150 1,900-2,100 1,925-2,125 1,900-2,100
3.1.5 Technology Workshops m2 2,300-2,600 2,300-2,600 2,300-2,600 2,250-2,550
For Elemental Analysis, see page 2-42
3.2 Schools–Support
Secondary School, 1 to 2 storeys.
Includes built-in cupboards and fittings.
Includes heating. Medium standard
finishes. Toilet facilities.
3.2.1 Administration m2 1,900-2,100 1,850-2,050 1,900-2,100 1,850-2,050
3.2.2 Gymnasium m2 1,775-1,975 1,750-1,950 1,775-1,975 1,725-1,925
3.2.3 Auditorium (theatre-style) m2 3,050-3,350 2,950-3,250 3,050-3,350 2,950-3,250
3.2.4 Dormitory for year 9-11 students, 2 m2 1,725-1,925 1,700-1,900 1,750-1,950 1,700-1,900
students per room
3.2.5 Dormitory for senior students, 1 m2 2,000-2,200 1,975-2175 2,000-2,200 1,975-2,175
student per room, full facilities for each
group of 6 students
3.2.6 Boiler House m2 2,250-2,550 2,250-2550 2,300-2,600 2,200-2,500
3.2.7 Dining Hall/Kitchen, with coolroom, m2 1,975-2,175 1,975-2175 1,975-2,175 1,950-2,150
staff facilities, toilets
Add extra for:
Covered ways, not enclosed
3.2.8 Basic finish m2 335-385 320-370 320-370 325-375
3.2.9 Medium/high standard finish m2 420-470 400-450 410-460 400-450
Balconies, reinforced concrete
3.2.10 Basic finish m2 370-420 370-420 380-430 370-420
3.2.11 Medium/high standard finish m2 455-505 450-500 460-510 450-500
3.2.12 External Works and siteworks— m2 175-225 165-215 165-215 165-215
playgrounds, playing fields, carparks
2008
Educational
Tertiary Institutions–Teaching
Page 1-15
2008
Entertainment
Cinemas and Theatres
Page 1-16
4 Entertainment
4.1 Cinemas and Theatres
4.1.1 Cinema Multiplex, up to 2 storeys. per 5,400-5,700 5,400-5,700 5,400-5,700 5,200-5,500
Four to eight cinemas, seating 200–400 seat
each, with common projection room and
ancillary facilities. Includes seats,
projectors, screens, sound equipment.
Includes HVAC, sprinklers and escalators.
Medium standard finishes.
4.1.2 Theatre/Auditorium. per 6,200-6,500 6,200-6,500 6,200-6,500 5,900-6,200
Main theatre and small theatre seating seat
500–750, dressing rooms and basic stage
equipment, bar and ancillary facilities.
Includes seats, sound and lighting
equipment. Includes HVAC and
escalators. Medium standard finishes.
4.3 Grandstands
4.3.1 Spectator Stand, open air, with tiered m2 1,300-1,500 1,300-1,500 1,300-1,500 1,300-1,500
concrete bleachers, and plastic fold-down per 650-750 650-750 650-750 650-750
seats. 0.5m2 per seat. seat
4.3.2 Spectator Stand, roofed, with tiered m2 1,150-1,350 1,125-1,325 1,125-1,325 1,100-1,300
concrete bleachers, plastic fold-down per 2,875-3,375 2,813-3,313 2,813-3,313 2,750-3,250
seats. Lifts. Lounges, facilities for teams, seat
first aid, concessions, catering. 2.5m2 per
seat.
4.3.3 Spectator Stand, roofed, with tiered m2 1,450-1,650 1,425-1,625 1,425-1,625 1,425-1,625
concrete bleachers, plastic fold-down per 4,350-4,950 4,275-4,875 4,275-4,875 4,275-4,875
seats. Lifts. Corporate boxes, facilities for seat
teams, event control, media, first aid,
concessions, catering. 3m2 per seat.
4.4 Aquaria
4.4.1 Aquarium. Includes life support system, m2 3,000-3,300 3,000-3,300 3,050-3,350 3,000-3,300
cool-rooms, data, security and sound
systems, acrylic tunnel, viewing
travellator, lift.
Building Costs Per Square Metre
2008
Hospitals, Health
Hospitals
Page 1-17
5 Hospitals, Health
5.1 Hospitals
5.1.1 District Hospital. m2 3,300-3,600 3,200-3,500 3,250-3,550 3,150-3,450
Single storey, 60 bed. Partial air- per 165,000 160,000 162,500 157,500
conditioning. Operating theatre. bed -180,000 -175,000 -177,500 -172,500
50m2 per bed
5.1.2 General Hospital. m2 3,900-4,200 3,800-4,100 3,850-4,150 3,800-4,100
Multi-storey, 200 bed. All facilities. per 292,500 285,000 288,750 285,000
Includes lifts, air-conditioning. bed -315,000 -307,500 -311,250 -307,500
75m2 per bed
5.1.3 Private Hospital. m2 2,650-3,150 2,600-2,900 2,650-2,950 2,600-2,900
Single storey, 40 bed. Operating theatre. per 132,500 130,000 132,500 130,000
Excludes air-conditioning. 50m2 per bed bed -147,500 -145,000 -147,500 -145,000
5.1.4 Private Hospital. m2 3,350-3,650 3,350-3,650 3,350-3,650 3,300-3,600
Multi-storey, 80-100 bed, 60% single per 167,500 167,500 167,500 165,000
rooms. All facilities, excluding operating bed -182,500 -182,500 -182,500 -180,000
theatres. Includes air-conditioning,
sprinklers, medical gases, lifts.
50m2 per bed
5.1.5 Psychiatric Unit. Medium Security. m2 3,600-3,900 3,600-3,900 3,650-3,950 3,600-3,900
Single storey, 20 bed, all facilities.
Includes sprinklers and air-conditioning.
For Elemental Analysis, see page 2-47
2008
Hotels, Motels, Taverns
Taverns, Liquor Outlets
Page 1-18
6.2 Hotels
6.2.1 2–3 Star Hotel, 4 to 8 storeys. m2 2,350-2,650 2,250-2,650 2,400-2,700 2,350-2,650
Basic building, includes reception, foyer,
bedrooms, bar, restaurant, kitchen,
laundry and gym. Includes HVAC, lifts.
Medium standard finishes. 45m2 of total
floor area per bedroom.
6.2.2 Furniture, Fittings, and Equipment m2 400-450 400-450 415-465 400-450
(Includes FF&E for total building, including
bedrooms, reception, foyer etc.)
6.2.3 All Inclusive Rate, including building, m2 2,750-3,050 2,750-3,050 2,850-3,150 2,750-3,050
services & FF&E.
6.2.4 3–4 Star Hotel, medium to high rise. m2 3,200-3,500 3,150-3,450 3,200-3,500 3,100-3,400
Basic building, includes reception, foyer,
bedrooms, bars, restaurants, kitchen,
service and plant facilities. Includes
HVAC, lifts, emergency generator, waste
compactor. Medium standard finishes.
57m2 of total floor area per bedroom.
6.2.5 Furniture, Fittings, and Equipment m2 530-630 520-620 530-630 520-620
6.2.6 All Inclusive Rate m2 3,700-4,000 3,650-3,950 3,750-4,050 3,650-3,950
6.2.7 4 Star Hotel, medium to high rise. m2 4,100-4,400 4,000-4,300 4,100-4,400 4,000-4,300
Basic building, includes reception, foyer,
bedrooms, ballrooms, bars, restaurants,
kitchen, service and plant facilities.
Includes HVAC, lifts, emergency
generator, waste compactor. High
standard finishes. 70m2 of total floor area
per bedroom.
6.2.8 Furniture, Fittings, and Equipment m2 730-830 730-830 750-850 720-820
6.2.9 All Inclusive Rate m2 4,800-5,100 4,750-5,050 4,850-5,150 4,700-5,000
For Elemental Analysis, see page 2-50
Building Costs Per Square Metre
2008
Hotels, Motels, Taverns
Motels
Page 1-19
6.3 Motels
6.3.1 Standard Quality Motel, up to 2 storeys. m2 1,575-1,775 1,525-1,725 1,550-1,750 1,525-1,725
Basic building, includes office, reception,
laundry, decks, verandahs and services.
Basic standard finishes. Excludes HVAC.
Accommodation units each with kitchen
and bathroom.
6.3.2 As last item, per accommodation unit, per 78,750 76,250 77,500 76,250
50m2 of total floor area per unit. unit -88,750 -86,250 -87,500 -86,250
6.3.3 Furniture, Fittings and Equipment. m2 160-210 155-205 160-210 155-205
(This figure includes FF&E for the total
building, including accommodation units,
reception, laundry etc.)
6.3.4 Per accommodation unit per 8,000 7,750 8,000 7,750
unit -10,500 -10,250 -10,500 -10,250
6.3.5 All Inclusive Rate including building, m2 1,725-1,925 1,675-1,875 1,700-1,900 1,675-1,875
services and FF&E.
6.3.6 Per accommodation unit per 86,750 84,000 85,500 84,000
unit -99,250 -96,500 -98,000 -96,500
6.3.7 High Quality Motel. Up to 2 storeys. m2 1,850-2,050 1,800-2,000 1,825-2,025 1,775-1,975
Basic building, includes office, reception,
restaurant, kitchen, bar, lounge, laundry
and service facilities, decks, verandahs
and services. Medium standard finishes.
Excludes HVAC. Accommodation units
each with tea making facilities and
bathroom.
6.3.8 As last item, per accommodation unit, per 111,000 108,000 109,500 106,500
60m2 of total floor area per bedroom. unit -123,000 -120,000 -121,500 -118,500
6.3.9 Furniture, Fittings and Equipment m2 230-280 230-280 230-280 230-280
6.3.10 Per accommodation unit per 13,800 13,800 13,800 13,800
unit -16,800 -16,800 -16,800 -16,800
6.3.11 All Inclusive Rate, including building, m2 2,050-2,350 2,050-2,350 2,050-2,350 2,000-2,200
services and FF&E.
6.3.12 Per accommodation unit per 124,800 121,800 123,300 120,300
unit -139,800 -136,800 -138,300 -135,300
For Elemental Analysis, see page 2-50
Building Costs Per Square Metre
2008
Industrial
Factories and Warehouses
Page 1-20
7 Industrial
7.1 Factories and Warehouses
Portal frame construction, concrete floor
slab. Nominal lighting, power supply, fire
hose reels. Colorsteel® roof and roller
shutter doors. Excludes plumbing, HVAC,
sprinklers.
Single storey, under 20m clear span.
7.1.1 Colorsteel® wall cladding m2 710-780 700-800 710-810 700-800
7.1.2 1200mm high precast or block walls. m2 730-830 720-820 730-830 720-820
Colorsteel® wall cladding above
As above, and includes small interior
office, toilet and amenities, and plumbing.
7.1.3 1200mm high precast or block walls. m2 800-900 770-870 790-890 780-880
Colorsteel® wall cladding above
7.1.4 Full height precast or block walls m2 780-880 760-860 770-870 760-860
Single storey, over 20m clear span.
7.1.5 1200mm high precast or block walls, m2 560-660 540-640 550-650 540-640
Colorsteel® wall cladding above
7.1.6 1200mm high precast or block walls, m2 590-690 560-660 570-670 570-670
Colorsteel® wall cladding above.
Includes small internal office, toilet and
amenities, and plumbing
2008
Industrial
Cold Stores
Page 1-21
7.4 Workshops
7.4.1 Light Industrial Workshop. Single storey m2 960-1,060 930-1,030 950-1,050 930-1,030
workshop, offices and small laboratory for
light industrial use, including amenities,
built in fittings, partial HVAC. Excludes
sprinklers, security, special equipment.
Basic standard finishes.
7.4.2 Heavy Industrial Workshop. Single m2 1,075-1,275 1,050-1,250 1,075-1,275 1,050-1,250
storey workshop, offices, service pits and
lubrication bay for heavy industrial use,
including amenities, built in fittings, partial
HVAC. Excludes sprinklers, security,
special equipment. Basic standard
finishes.
Add extra for
Cranes or gantries
Fuel storage and installations
7.4.3 LPG–Fuel Depot Buildings, up to 2 m2 1,975-2,175 1,900-2,100 1,900-2,100 1,900-2,100
storeys. Offices, switch and plant rooms,
including amenities, HVAC. Excludes
sprinklers, security, major site services.
Basic standard finishes.
For Elemental Analysis, see page 2-51
Building Costs Per Square Metre
2008
Offices
Base Building Cost
Page 1-22
8 Offices
Base building costs are for a “Lettable
Shell” building. Costs exclude sub-
divisional partitions, parking areas,
owners or tenants special requirements.
Add for fitout costs to standard required.
2008
Parking
Integral Parking
Page 1-23
9 Parking
9.1 Integral Parking
9.1.1 Ground Level Parking, Beneath m2 465-565 450-550 445-545 445-545
Offices. Open at ground or slightly
reduced ground level, including additional
excavation and substructure.
9.1.2 Partially Underground Parking. One m2 810-910 810-910 800-900 790-890
level, including additional excavation and
substructure, ramps, sprinklers, partial
mechanical ventilation, no roof over (as
included in office building).
9.1.3 Basement Parking. One level, including m2 1,425-1,625 1,425-1,625 1,450-1,650 1,425-1,625
full excavation, substructure and structural
walls, ramps, sprinklers, mechanical
ventilation, no roof over (as included in
building above)
2008
Primary Industry
Research Laboratories
Page 1-24
10 Primary Industry
10.1 Research Laboratories
Offices, Laboratories and Amenities
Includes sprinklers, special services, built-
in fittings. Medium standard finishes.
10.1.1 Research Centre, single storey, partial m2 2,450-2,750 2,400-2,700 2,450-2,750 2,400-2,700
HVAC
10.1.2 Laboratory, 3 to 5 storeys, HVAC m2 3,550-3,850 3,500-3,800 3,550-3,850 3,450-3,750
10.2 Meatworks
10.2.1 Abattoir, single storey, heavy duty m2 3,050-3,350 2,950-3,250 3,050-3,350 2,950-3,250
construction. Excludes sprinklers, special
services, HVAC.
High standard hygienic finishes.
Add extra for
10.2.2 Covered Yards. Metal roofing, concrete m2 385-435 380-430 390-440 375-425
slab, steel frame, open sides. Water
troughs, hose taps, cesspits, drainage.
Excludes steel grid flooring and catwalks.
For Elemental Analysis, see page 2-55
11 Recreational Facilities
11.1 Clubhouses and Gymnasia
11.1.1 Clubhouse and Changing Rooms. m2 2,000-2,200 1,950-2,150 1,950-2,150 1,925-2,125
Single storey, standard construction and
finishes. Large bar and lounge, small
kitchen, dining area, large changing
rooms, shower and toilets.
11.1.2 Changing Rooms and Toilets. m2 1,850-2,050 1,825-2,025 1,825-2,025 1,775-1,975
Single storey, standard construction and
basic finishes. Large change area and
adjoining showers and toilets.
11.1.3 Basketball Centre, with gallery. Single m2 1,650-1,850 1,500-1,700 1,550-1,750 1,500-1,700
storey, standard construction. Timber
sports floor to playing area. Changing
rooms and toilets.
11.1.4 Sports Hall/Gymnasium. m2 1,750-1,950 1,725-1,925 1,750-1,950 1,725-1,925
Single storey, standard construction. Vinyl
sports floor to playing area. Changing
rooms and toilets.
For Elemental Analysis, see page 2-56
Building Costs Per Square Metre
2008
Recreational Facilities
Squash Courts
Page 1-25
2008
Residential
House, 1-Storey
Page 1-26
12 Residential
12.1 House, 1-Storey
12.1.1 House, 90–130m2. m2 1,225-1,425 1,200-1,400 1,200-1,400 1,225-1,425
Pile foundations, particle board floor.
Kitchen, bathroom, WC. Fibre-cement
weather boards, galvanised steel roof.
Standard quality fittings.
House, 100–200m2.
Concrete floor slab, kitchen, bathroom,
WC, ensuite. Medium quality fittings.
Colorsteel® roof.
12.1.2 With cedar or pine weatherboards m2 1,650-1,850 1,575-1,775 1,575-1,775 1,500-1,700
12.1.3 With polystyrene or fibre cement cladding, m2 1,650-1,850 1,600-1,800 1,575-1,775 1,500-1,700
textured plaster or acrylic coatings.
12.1.4 Brick veneer, concrete tile roof. m2 1,725-1,925 1,675-1,875 1,650-1,850 1,550-1,750
12.1.5 Insulated concrete block, tile roof m2 1,725-1,925 1,675-1,875 1,650-1,850 1,550-1,750
2008
Residential
Multiple Units—Low Rise
Page 1-27
2008
Devotional Buildings
Garages
Page 1-28
12.7 Garages
Garage with concrete floor slab, timber
frame. Galvanised steel roof and roller
door.
12.7.1 Galvanised steel cladding m2 500-500 470-520 455-505 460-510
12.7.2 Fibre cement weatherboards m2 610-710 620-720 580-680 570-670
Garage with concrete floor slab, timber
frame, Gib® board lined. Automatic
opener to garage door.
12.7.3 Cedar or pine weatherboards, m2 770-870 780-880 730-830 700-800
Colorsteel® roof. Timber-clad tilting
door
12.7.4 Brick veneer, concrete tile roof. m2 820-920 800-900 800-900 790-890
Colorsteel® tilting door
12.7.5 Garage with concrete floor slab. Concrete m2 800-900 820-920 780-880 760-860
block walls, concrete tile roof. Colorsteel®
tilting door, automatic opener.
12.8 Carport
Carport with concrete floor slab, timber posts,
beams and rafters.
12.8.1 Flat galvanised steel roof m2 270-320 265-315 270-320 260-310
12.8.2 Pitched colour steel roof. m2 305-355 325-375 310-360 300-350
13 Devotional Buildings
13.1 Places of Worship
Devotional Building.
Small kitchen and toilets.
With construction and finishes to:
13.1.1 Basic standard m2 1,525-1,725 1,450-1,650 1,425-1,625 1,400-1,600
13.1.2 Medium standard m2 1,850-2,050 1,800-2,000 1,825-2,025 1,775-1,975
13.1.3 High standard m2 2,150-2,450 2,100-2,400 2,100-2,400 2,050-2,350
13.2 Halls
13.2.1 Hall or Community Building. m2 1,525-1,725 1,450-1,650 1,425-1,625 1,400-1,600
Single storey, small kitchen, toilets.
Excludes HVAC. With construction and
finishes to medium standard.
For Elemental Analysis, see page 2-59
Building Costs Per Square Metre
2008
Retail
Suburban Retail
Page 1-29
14 Retail
14.1 Suburban Retail
14.1.1 Neighbourhood Shop. Single storey. m2 910-1,010 880-980 870-970 860-960
Standard shell construction, including
shop-fronts, plasterboard ceilings.
Includes electrical service to board, cold
water supply to fixture point only,
drainage. Excludes fittings, hot water,
HVAC, sprinklers.
Add
14.1.2 Fit-out of shell. Includes finishes, shop m2 260-310 260-310 270-320 255-305
fittings and services
14.1.3 Air-conditioning (package unit) m2 155-205 155-205 160-210 155-205
14.1.4 Supermarket. Standard construction, m2 1,075-1,275 1,050-1,250 1,075-1,275 1,050-1,250
including shop fronts, standard finishes.
Includes all services, HVAC & sprinklers,
amenities and offices. Excludes cold
rooms, shop fittings.
Add
14.1.5 Shop fittings m2 335-385 330-380 340-390 325-375
14.1.6 Installation of cold and cool rooms
14.1.7 Shopping Centre. Standard shell m2 1,175-1,375 1,150-1,350 1,150-1,350 1,125-1,325
construction, including shop fronts,
plasterboard ceilings. Includes electrical
service to board, plumbing service only,
air conditioning. Excludes sprinklers, fit-
out and mall/arcade areas.
Add
14.1.8 Fully enclosed mall/arcade. Standard m2 1,700-1,900 1,600-1,800 1,550-1,750 1,500-1,700
finish, air conditioned
14.1.9 Trading area fit-out. Includes wall and m2 350-400 345-395 355-405 345-395
floor finishes, additional electrical,
plumbing services
2008
Miscellaneous Building Types
Commercial Buildings
Page 1-30
2008
Worked Example
Rural Buildings
Page 1-31
16 Worked Example
Project Details GFA $rate $value
• Name of Project
• Type of Project
• Total floor area (GFA) m2 1,500
• Base building cost item used from Handbook 8.1.1
• Is base building rate for shell only? If so, add fit
out cost. Yes
• Fitout item used from Handbook 8.3.2
Building Works Cost Calculation
• Base building cost m2 1,500 1,100 1,650,000
• Fit out cost m2 1,500 600 900,000
Subtotal for base building cost and fitout 2,550,000
Add for items excluded from base building cost,
See “How to Use This Section” on page 1-10.
• Demolition of existing building/removal of Item
excess site vegetation and debris
• Balconies, decks, covered ways, entrance Item
canopies
• External services from building to public
connection
Power Item say 15,000
Water Item say 5,000
Drainage Item say 8,000
Data Item say 3,000
• External works over and above those
immediately adjacent to the building
Parking areas m2 300 65 19,500
Landscaping m2
Other Item
Add for factors specific to this project, and not
included in base building cost
• Site factors—sloping site/latent site conditions Item
and other geotechnical issues
• Increased wall-to-floor ratios/unusual building Item
shape
• Change to standard of finishes—increase m2 1,500 150 225,000
• Small or cramped site/firewalls to boundaries Item
• Infrastructure upgrades to territorial authority Item say 50,000
services
• Remote locality Item
• Services not included in base rate, eg, lifts Item
• Any other items or factors deemed relevant to Item
this project and not allowed for above
Subtotal for building works, see over 2,875,500
Building Costs Per Square Metre
2008
Worked Example
Notes on Worked Example
Page 1-32
2008
How to Use This Section
Definitions
Page 2-34
1. p1, Elemental Analysis of Costs of Building Projects, published by the New Zealand Institute of Quantity Surveyors Inc. To purchase,
see www.nziqs.co.nz
Elemental Costs of Buildings
2008
Worked Example
GFA Costing
Page 2-35
Worked Example
A B
GFA Costing Office Building Office Building
Offices, Low and High rise Max 2 storey 6-15 storey
GFA 600m2 GFA 7500m2
2008
Definition of Elements
Structure
Page 2-36
Definition of Elements
Structure
Site Preparation. All work necessary to clear a site of existing structures, trees, etc. to create a
suitably benched surface as a working platform.
Substructure. All work below the underside of the lowest floor finish, including all work applicable
to the foundations, hardfilling beneath floor slabs, concrete floor slabs, service ducts, lift pits and
the like. Includes basement walls between different levels. Excludes excavation above lowest floor
level, plumbing, drainage and other services below lowest floor finish.
Frame. All load bearing column and beam framework above lowest floor finish, major roof framing
members such as rafters, joists. Excludes all profiled finishes and all applied finishes.
Structural Walls. Load bearing and diaphragm walls together with integral columns. Excludes non-
structural spandrel panels, linings and applied finishes and treatments, profiled finish.
Upper Floors. Suspended floors, mezzanine floors, balcony floors and roof slabs. Includes fairface
finish to concrete floor and roof slabs. Excludes floor support beams and soffit treatments.
External Fabric
Roof. Complete weatherproof covering of all types to roofs. Includes decks; diaphragm bracing,
sarking and screeds; roof support components such as roof purlins, battens; insulation to underside
of roof covering, verge and eaves facing and soffit; secret, parapet and eaves gutters, downpipes,
roof lights. Excludes support beams; in situ or precast concrete roof slabs; parapets and parapet
finishes, gable and gable finishes; canopies, balconies, covered ways, roof top structures.
External Walls. All work to exterior walls, including applied or in situ finishes. Includes gable ends,
parapets, spandrels and finishes; both skins of exterior cavity walls; applied exterior finishes to
exterior columns, beams, structural spandrels and walls. Excludes curtain walls.
Windows and External Doors. All windows and doors in exterior walls, including vertical or near
vertical glazing. Excludes roof lights, interior glazed screens, curtain pelmets, sun screens,
curtains, tracks and blinds.
Internal Finishing
Stairs and Balustrades. Flights and intermediate landings including integral finishings, handrails
and balustrades. Excludes applied finishes.
Partitions. All non-structural internal walls including glazed screens, demountable partitions and
sound and fire walls. Excludes fanlights and sidelights, folding or sliding doors forming partitions,
wall finishes, and fire stopping and sound barriers in ceiling spaces, where these are a continuation
of partitions below the ceiling line.
Internal Doors. All interior doors including frames, architraves, finishes, glazing, fanlights, side
lights, panels over doors, hardware and control systems. Excludes doors to proprietary partition
systems, fittings and fixtures.
Floor Finishes. Includes all preparatory work, screeds, surface finishes, matwells, threshold strips,
raised floors laid over structural floors.
Elemental Costs of Buildings
2008
Definition of Elements
Services
Page 2-37
Wall Finishes. Includes all preparatory work and finishes to interior walls, isolated columns, and to
interior faces of exterior walls. Excludes fairface finish to concrete, finishes to proprietary partition
systems. Includes skirtings, cornices, trims, dado rails and the like.
Ceiling Finishes. Includes all preparatory work and finishes, suspended ceilings and framing,
soffits of staircases and intermediate landings. Excludes ceiling framing forming part of roof
framing.
Fittings. Joinery fittings, whether built-in or fixed in position, includes glass, hardware and finishes.
Excludes sanitary fittings, electrical fittings, services to fittings and fixtures.
Services
Sanitary Plumbing. Hot and cold water supply, including hot water cylinder, sanitary fittings, soil,
waste and vent pipes. Excludes special kitchen equipment, laboratory equipment and services.
Heating and Ventilation (Mechanical Services). Heating, ventilation and air conditioning systems,
including all associated equipment. Excludes heating source to hot water system.
Fire Services. All fire services within a building, including all associated electrical work.
Electrical Services. All electrical services providing lighting and power. Excludes lighting and
power to external works; wiring to equipment and machinery which is covered in other elements.
Vertical and Horizontal Transportation. Vertical and horizontal moving equipment, including
associated electrical equipment and builders work.
Special Services. Special services, including associated electrical work and builders work.
Includes gas, liquids, fume extraction systems, pneumatic and vacuum tube systems, refrigeration,
disposal systems, kitchen, bar and laboratory equipment and fittings, communication systems,
protective systems (excluding fire), building management systems, traffic control systems.
Drainage. Sub-soil drainage, land drains, stormwater drains and soil drains, including excavation,
backfill, fittings and the like.
External Works and Sundries
External Works. Site works beyond the line of the exterior face of the building structure. Excludes
site preparation.
Sundries. Items not readily classified under other elements, e.g., verandahs, canopies, swimming
pools, small isolated structures such as pump houses.
P&G, Margins and Contingencies
Margins. All sums identifiable in a tender to cover the Main Contractor’s Profit and Overhead
Costs.
Preliminaries. Normal Builder's preliminaries, i.e., site establishment, temporary services, site
management and personnel, plant, equipment, scaffolding, on-site overheads, notices and fees,
indirect costs.
Contingencies. All contract contingency sums contained in the contract.
Elemental Costs of Buildings
2008
Administration, Civic
P&G, Margins and Contingencies
Page 2-38
1 Administration, Civic
1.1 Administrative 1.1.1 1.1.3 1.1.4 1.2.1
Administration Office Administration Office Town Hall Civic Centre
Refer to page 1-11 Max 2 storey 3–5 storey 1000–2000 500–750
capacity capacity
2008
Administration, Civic
P&G, Margins and Contingencies
Page 2-39
2008
Administration, Civic
P&G, Margins and Contingencies
Page 2-40
2008
Banks
P&G, Margins and Contingencies
Page 2-41
2 Banks
2.1 Bank, Construction 2.1.1 2.1.2 2.1.3
Bank Bank Bank
Refer to page 1-13 Suburban City City Head Office
Single storey Max 2 storey 5–10 storey
2008
Educational
P&G, Margins and Contingencies
Page 2-42
3 Educational
3.1 Schools–Teaching 3.1.1 3.1.2 3.1.4 3.1.5
Primary Secondary Secondary Secondary
Refer to page 1-14 Single storey Classrooms Art/Photo Suite Technology
Modern specification Max 2 storey Max 2 storey Workshop
2008
Educational
P&G, Margins and Contingencies
Page 2-43
2008
Educational
P&G, Margins and Contingencies
Page 2-44
2008
Educational
P&G, Margins and Contingencies
Page 2-45
2008
Entertainment
P&G, Margins and Contingencies
Page 2-46
4 Entertainment
4.3 Grandstands 4.3.1 4.3.3 4.4.1
Spectator Stand Spectator Stand Aquarium
4.4 Aquaria Open Roofed
2008
Hospitals, Health
P&G, Margins and Contingencies
Page 2-47
5 Hospitals, Health
5.1 Hospitals 5.1.1 5.1.2 5.1.3 5.1.4
Hospital Hospital Hospital Hospital
Refer to page 1-17 District General Private Private
Single storey Multi-storey Single storey Multi-storey
2008
Hospitals, Health
P&G, Margins and Contingencies
Page 2-48
2008
Hotels, Motels, Taverns
P&G, Margins and Contingencies
Page 2-49
2008
Hotels, Motels, Taverns
P&G, Margins and Contingencies
Page 2-50
2008
Industrial
P&G, Margins and Contingencies
Page 2-51
7 Industrial
7.1 Factories and Warehouses 7.1.1 7.1.2 7.1.3
Small Span Small Span Small Span
Refer to page 1-20 Portal Frame Concrete Office
Block Spandrels Amenities
2008
Industrial
P&G, Margins and Contingencies
Page 2-52
2008
Offices
P&G, Margins and Contingencies
Page 2-53
8 Offices
8.1 Base Building Cost 8.1.1 8.1.2 8.1.4 8.2.1
Office Building Office Building Office Building Office Building
8.2 High Rise No A/C or lift No A/C A/C A/C
Max 2 storey 3–5 storey 3–5 storey 6–15 storey
Refer to page 1-22
Element/Element Group $/m2 % $/m2 % $/m2 % $/m2 %
Site Preparation 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%
Substructure 84.66 6.6% 96.14 6.3% 96.16 5.4% 135.59 5.3%
Frame 109.35 8.6% 128.66 8.4% 127.13 7.2% 157.38 6.2%
Structural Walls 49.38 3.9% 56.55 3.7% 57.05 3.2% 53.27 2.1%
Upper Floors 81.13 6.4% 120.18 7.9% 132.02 7.4% 186.44 7.3%
Structure 324.52 25.5% 401.53 26.3% 412.36 23.2% 532.68 20.9%
Roof 88.18 6.9% 101.80 6.7% 102.68 5.8% 38.74 1.5%
External Walls } 177.54 13.9% 193.70 12.7% 193.96 10.9% 290.55 11.4%
Windows & Doors } 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%
External Fabric 265.72 20.8% 295.50 19.4% 296.64 16.7% 329.29 12.9%
Stairs 25.87 2.0% 29.69 1.9% 30.97 1.7% 29.05 1.1%
Internal Walls/Partitions 68.19 5.3% 14.14 0.9% 14.67 0.8% 104.11 4.1%
Internal Doors 27.04 2.1% 28.28 1.9% 27.71 1.6% 48.42 1.9%
Floor Finishes 84.66 6.6% 89.07 5.8% 89.64 5.1% 96.85 3.8%
Wall Finishes 43.50 3.4% 32.52 2.1% 32.60 1.8% 62.95 2.5%
Ceiling Finishes 76.43 6.0% 53.73 3.5% 53.79 3.0% 77.48 3.0%
Fittings & Fixtures 12.93 1.0% 14.14 0.9% 14.67 0.8% 21.79 0.9%
Internal Finishing 338.62 26.6% 261.57 17.2% 264.05 14.9% 440.65 17.3%
Sanitary Plumbing 50.56 4.0% 63.62 4.2% 63.57 3.6% 104.11 4.1%
Mechanical Services 10.58 0.8% 0.00 0.0% 200.48 11.3% 290.55 11.4%
Fire Services 12.93 1.0% 12.72 0.8% 13.04 0.7% 60.53 2.4%
Electrical Services 79.95 6.3% 107.45 7.0% 107.57 6.1% 152.54 6.0%
Lifts & Escalators 0.00 0.0% 149.87 9.8% 149.95 8.4% 251.81 9.9%
Special Services 0.00 0.0% 0.00 0.0% 0.00 0.0% 24.21 0.9%
Drainage 9.41 0.7% 7.07 0.5% 8.15 0.5% 2.42 0.1%
Services 163.43 12.8% 340.73 22.3% 542.76 30.6% 886.17 34.8%
External Works 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%
Sundries 10.58 0.8% 19.79 1.3% 19.56 1.1% 16.95 0.7%
Ext Works & Sundries 10.58 0.8% 19.79 1.3% 19.56 1.1% 16.95 0.7%
Preliminaries and General 153.00 12.0% 183.00 12.0% 213.00 12.0% 306.00 12.0%
Contingency 19.13 1.5% 22.88 1.5% 26.63 1.5% 38.25 1.5%
P&G, Contingency 172.13 13.5% 205.88 13.5% 239.63 13.5% 344.25 13.5%
Total 1,275.00 100% 1,525.00 100% 1,775.00 100% 2,550.00 100%
Cost Range
Auckland 1,175-1,375 1,425-1,625 1,675-1,875 2,400-2,700
Wellington 1,150-1,350 1,400-1,600 1,650-1,850 2,350-2,650
Christchurch 1,150-1,350 1,425-1,625 1,650-1,850 2,400-2,700
Dunedin 1,125-1,325 1,350-1,550 1,625-1,825 2,250-2,550
Elemental Costs of Buildings
2008
Parking
P&G, Margins and Contingencies
Page 2-54
9 Parking
9.1 Integral Parking 9.1.1 9.1.3 9.3.2 9.3.3
Ground Level Basement Parking Parking Building Parking Building
9.3 Parking Buildings Parking (Building Above) Ground plus Multi storey
(Building Above) 2 levels
Refer to page 1-23
Element/Element Group $/m2 % $/m2 % $/m2 % $/m2 %
Site Preparation 0.00 0.0% 12.68 0.8% 0.00 0.0% 0.00 0.0%
Substructure 102.65 19.9% 937.20 61.5% 53.27 9.3% 75.29 11.2%
Frame 111.37 21.6% 109.93 7.2% 89.84 15.8% 108.82 16.2%
Structural Walls 33.89 6.6% 35.23 2.3% 20.37 3.6% 24.68 3.7%
Upper Floors 0.00 0.0% 0.00 0.0% 94.01 16.5% 170.83 25.5%
Structure 247.91 48.1% 1095.04 71.8% 257.49 45.2% 379.62 56.7%
Roof 0.00 0.0% 0.00 0.0% 6.79 1.2% 1.90 0.3%
External Walls } 58.11 11.3% 8.46 0.6% 53.27 9.3% 64.54 9.6%
Windows & Doors } 0.00 0.0% 28.19 1.8% 0.00 0.0% 0.00 0.0%
External Fabric 58.11 11.3% 36.65 2.4% 60.06 10.5% 66.44 9.9%
Stairs 17.92 3.5% 21.14 1.4% 8.88 1.6% 15.82 2.4%
Internal Walls/Partitions 24.21 4.7% 0.00 0.0% 10.45 1.8% 7.59 1.1%
Internal Doors 9.68 1.9% 2.82 0.2% 4.70 0.8% 5.69 0.8%
Floor Finishes 9.68 1.9% 0.00 0.0% 10.45 1.8% 1.27 0.2%
Wall Finishes 7.75 1.5% 0.00 0.0% 6.79 1.2% 5.06 0.8%
Ceiling Finishes 9.20 1.8% 0.00 0.0% 5.75 1.0% 6.96 1.0%
Fittings & Fixtures 0.00 0.0% 0.00 0.0% 2.09 0.4% 2.53 0.4%
Internal Finishing 78.44 15.2% 23.96 1.6% 49.11 8.6% 44.92 6.7%
Sanitary Plumbing 3.87 0.8% 0.00 0.0% 7.83 1.4% 9.49 1.4%
Mechanical 14.53 2.8% 45.10 3.0% 24.03 4.2% 8.86 1.3%
Fire 9.68 1.9% 98.65 6.5% 53.27 9.3% 3.80 0.6%
Electrical 15.98 3.1% 18.32 1.2% 20.37 3.6% 24.68 3.7%
Lifts & Escalators 0.00 0.0% 0.00 0.0% 13.58 2.4% 35.43 5.3%
Special 4.84 0.9% 0.00 0.0% 0.00 0.0% 0.00 0.0%
Drainage 4.84 0.9% 1.41 0.1% 2.61 0.5% 1.27 0.2%
Services 53.74 10.4% 163.48 10.7% 121.69 21.4% 83.53 12.5%
External Works 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%
Sundries 7.26 1.4% 0.00 0.0% 4.70 0.8% 5.06 0.8%
Ext Works & Sundries 7.26 1.4% 0.00 0.0% 4.70 0.8% 5.06 0.8%
Preliminaries and General 61.80 12.0% 183.00 12.0% 68.40 12.0% 80.40 12.0%
Contingency 7.73 1.5% 22.88 1.5% 8.55 1.5% 10.05 1.5%
P&G, Contingency 69.53 13.5% 205.88 13.5% 76.95 13.5% 90.45 13.5%
Total 515.00 100% 1,525.00 100% 570.00 100% 670.00 100%
Cost Range
Auckland 465-565 1,425-1,625 530-630 620-720
Wellington 450-550 1,425-1,625 520-620 620-720
Christchurch 445-545 1,450-1,650 520-620 620-720
Dunedin 445-545 1,425-1,625 520-620 610-710
Elemental Costs of Buildings
2008
Primary Industry
P&G, Margins and Contingencies
Page 2-55
10 Primary Industry
10.1 Research Laboratories 10.1.1 10.1.2
Research Centre Laboratory
Refer to page 1-24 Single storey 3-5 storey
2008
Recreational
P&G, Margins and Contingencies
Page 2-56
11 Recreational
11.1 Clubhouses and 11.1.1 11.1.2 11.1.3 11.1.4
Clubhouse and Changing Rooms Basketball Gymnasium
Gymnasia
Change Rooms Toilet Building Centre
Refer to page 1-24 Single storey
Element/Element Group $/m2 % $/m2 % $/m2 % $/m2 %
Site Preparation 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%
Substructure 152.03 7.2% 193.03 9.9% 139.86 8.0% 147.21 8.0%
Frame 92.80 4.4% 48.71 2.5% 154.67 8.8% 183.58 9.9%
Structural Walls 69.11 3.3% 0.00 0.0% 41.13 2.4% 41.56 2.2%
Upper Floors 0.00 0.0% 0.00 0.0% 49.36 2.8% 0.00 0.0%
Structure 313.94 14.9% 241.74 12.4% 385.02 22.0% 372.35 20.1%
Roof 209.29 10.0% 137.10 7.0% 172.76 9.9% 190.51 10.3%
External Walls } 221.14 10.5% 225.50 11.6% 222.13 12.7% 242.46 13.1%
Windows & Doors } 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%
External Fabric 430.43 20.5% 362.60 18.6% 394.89 22.6% 432.97 23.4%
Stairs 0.00 0.0% 0.00 0.0% 32.91 1.9% 0.00 0.0%
Internal Walls/Partitions 173.75 8.3% 200.25 10.3% 65.82 3.8% 69.27 3.7%
Internal Doors 57.26 2.7% 48.71 2.5% 24.68 1.4% 31.17 1.7%
Floor Finishes 100.70 4.8% 27.06 1.4% 141.50 8.1% 159.33 8.6%
Wall Finishes 104.65 5.0% 99.22 5.1% 65.82 3.8% 77.93 4.2%
Ceiling Finishes 75.03 3.6% 61.34 3.1% 57.59 3.3% 60.62 3.3%
Fittings & Fixtures 152.03 7.2% 160.56 8.2% 82.27 4.7% 103.91 5.6%
Internal Finishing 663.42 31.6% 597.14 30.6% 470.59 26.9% 502.23 27.1%
Sanitary Plumbing 256.68 12.2% 322.92 16.6% 115.18 6.6% 124.69 6.7%
Mechanical Services 0.00 0.0% 0.00 0.0% 24.68 1.4% 20.78 1.1%
Fire Services 11.85 0.6% 0.00 0.0% 8.23 0.5% 10.39 0.6%
Electrical Services 94.77 4.5% 36.08 1.9% 90.50 5.2% 96.98 5.2%
Lifts & Escalators 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%
Special Services 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%
Drainage 9.87 0.5% 36.08 1.9% 6.58 0.4% 6.93 0.4%
Services 373.17 17.8% 395.08 20.3% 245.17 14.0% 259.77 14.0%
External Works 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%
Sundries 35.54 1.7% 90.20 4.6% 18.10 1.0% 32.91 1.8%
Ext Works & Sundries 35.54 1.7% 90.20 4.6% 18.10 1.0% 32.91 1.8%
Preliminaries and General 252.00 12.0% 234.00 12.0% 210.00 12.0% 222.00 12.0%
Contingency 31.50 1.5% 29.25 1.5% 26.25 1.5% 27.75 1.5%
P&G, Contingency 283.50 13.5% 263.25 13.5% 236.25 13.5% 249.75 13.5%
Total 2,100.00 100% 1,950.00 100% 1,750.00 100% 1,850.00 100%
Cost Range
Auckland 2,000-2,200 1,850-2,050 1,650-1,850 1,750-1,950
Wellington 1,950-2,150 1,825-2,025 1,950-2,150 1,825-2,025
Christchurch 1,950-2,150 1,825-2,025 1,950-2,150 1,825-2,025
Dunedin 1,925-2,125 1,775-1,975 1,925-2,125 1,775-1,975
Elemental Costs of Buildings
2008
Recreational, Residential
P&G, Margins and Contingencies
Page 2-57
Recreational, Residential
11.2 Squash Courts 11.2.1 11.2.2 12.1.4 12.3.1
Squash Courts Squash Courts House House
12.1 House, 1-Storey Basic Standard High Standard Single storey Large
Medium Quality Executive Quality
12.3 House, Large
Refer to page 1-25, page 1-26
Element/Element Group $/m2 % $/m2 % $/m2 % $/m2 %
Site Preparation 0.00 0.0% 0.00 0.0% 0.00 0.0% 20.60 0.6%
Substructure 120.45 9.1% 120.09 7.5% 116.70 6.4% 230.01 6.5%
Frame 49.88 3.8% 49.79 3.1% 134.66 7.4% 271.21 7.6%
Structural Walls 55.97 4.2% 54.19 3.4% 71.82 3.9% 44.63 1.3%
Upper Floors 0.00 0.0% 45.40 2.8% 0.00 0.0% 0.00 0.0%
Structure 226.30 17.1% 269.47 16.8% 323.18 17.7% 566.45 16.0%
Roof 147.22 11.1% 169.89 10.6% 113.11 6.2% 432.56 12.2%
External Walls } 212.92 16.1% 276.80 17.3% 100.54 5.5% 264.34 7.4%
Windows & Doors } 0.00 0.0% 0.00 0.0% 181.34 9.9% 528.69 14.9%
External Fabric 360.14 27.2% 446.69 27.9% 394.99 21.6% 1225.59 34.5%
Stairs 0.00 0.0% 35.15 2.2% 0.00 0.0% 0.00 0.0%
Internal Walls/Partitions 105.85 8.0% 115.70 7.2% 129.27 7.1% 61.79 1.7%
Internal Doors 14.60 1.1% 16.11 1.0% 71.82 3.9% 92.69 2.6%
Floor Finishes 184.94 14.0% 169.89 10.6% 91.57 5.0% 199.12 5.6%
Wall Finishes 74.22 5.6% 98.12 6.1% 134.66 7.4% 284.94 8.0%
Ceiling Finishes 64.48 4.9% 61.51 3.8% 71.82 3.9% 68.66 1.9%
Fittings & Fixtures 14.60 1.1% 27.83 1.7% 131.06 7.2% 250.61 7.1%
Internal Finishing 458.69 34.6% 524.31 32.8% 630.20 34.5% 957.81 27.0%
Sanitary Plumbing 36.50 2.8% 49.79 3.1% 132.86 7.3% 175.09 4.9%
Mechanical Services 0.00 0.0% 14.65 0.9% 0.00 0.0% 13.73 0.4%
Fire Services 2.43 0.2% 2.93 0.2% 0.00 0.0% 10.30 0.3%
Electrical Services 46.23 3.5% 58.58 3.7% 100.54 5.5% 226.58 6.4%
Lifts & Escalators 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%
Special Services 0.00 0.0% 0.00 0.0% 43.09 2.4% 0.00 0.0%
Drainage 3.65 0.3% 4.39 0.3% 17.95 1.0% 13.73 0.4%
Services 88.81 6.7% 130.34 8.1% 294.44 16.1% 439.43 12.4%
External Works 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%
Sundries 12.17 0.9% 13.18 0.8% 17.95 1.0% 41.20 1.2%
Ext Works & Sundries 12.17 0.9% 13.18 0.8% 17.95 1.0% 41.20 1.2%
Preliminaries and General 159.00 12.0% 192.00 12.0% 136.88 7.5% 266.25 7.5%
Contingency 19.88 1.5% 24.00 1.5% 27.38 1.5% 53.25 1.5%
P&G, Contingency 178.88 13.5% 216.00 13.5% 164.26 9.0% 319.50 9.0%
Total 1,325.00 100% 1,600.00 100% 1,825.00 100% 3,550.00 100%
Cost Range
Auckland 1,225-1,425 1,500-1,700 1,725-1,925 3,400-3,700
Wellington 1,200-1,400 1,450-1,650 1,675-1,875 3,400-3,700
Christchurch 1,200-1,400 1,475-1,675 1,650-1,850 3,500-3,800
Dunedin 1,175-1,375 1,450-1,650 1,550-1,750 3,400-3,700
Elemental Costs of Buildings
2008
Residential
P&G, Margins and Contingencies
Page 2-58
12 Residential
12.5 Multiple Units–High Rise 12.5.1 12.5.2 12.6.1
Apartments Apartments Retirement
12.6 Retirement Village Units Multi storey Multi storey Village Units
Medium Quality High Quality 2 storey
Refer to page 1-27
Element/Element Group $/m2 % $/m2 % $/m2 %
Site Preparation 0.00 0.0% 0.00 0.0% 0.00 0.0%
Substructure 138.97 5.7% 156.80 5.6% 114.99 5.0%
Frame 185.29 7.6% 182.00 6.5% 136.68 5.9%
Structural Walls 57.90 2.4% 64.40 2.3% 52.07 2.3%
Upper Floors 220.03 9.0% 224.00 8.0% 95.46 4.2%
Structure 602.19 24.6% 627.20 22.4% 399.20 17.4%
Roof 46.32 1.9% 53.20 1.9% 156.21 6.8%
External Walls } 347.42 14.2% 380.80 13.6% 310.25 13.5%
Windows & Doors } 0.00 0.0% 0.00 0.0% 0.00 0.0%
External Fabric 393.74 16.1% 434.00 15.5% 466.46 20.3%
Stairs 69.48 2.8% 92.40 3.3% 52.07 2.3%
Internal Walls/Partitions 150.55 6.1% 196.00 7.0% 130.17 5.7%
Internal Doors 57.90 2.4% 64.40 2.3% 49.90 2.2%
Floor Finishes 104.23 4.3% 142.80 5.1% 114.99 5.0%
Wall Finishes 81.06 3.3% 117.60 4.2% 80.27 3.5%
Ceiling Finishes 57.90 2.4% 78.40 2.8% 84.61 3.7%
Fittings & Fixtures 104.23 4.3% 184.80 6.6% 149.70 6.5%
Internal Finishing 625.35 25.5% 876.40 31.3% 661.71 28.8%
Sanitary Plumbing 173.71 7.1% 170.80 6.1% 190.92 8.3%
Mechanical Services 23.16 0.9% 25.20 0.9% 128.00 5.6%
Fire Services 23.16 0.9% 25.20 0.9% 10.85 0.5%
Electrical Services 92.64 3.8% 92.40 3.3% 106.31 4.6%
Lifts & Escalators 138.97 5.7% 103.60 3.7% 0.00 0.0%
Special Services 23.16 0.9% 39.20 1.4% 10.85 0.5%
Drainage 11.58 0.5% 14.00 0.5% 4.34 0.2%
Services 486.38 19.9% 470.40 16.8% 451.27 19.6%
External Works 0.00 0.0% 0.00 0.0% 0.00 0.0%
Sundries 11.58 0.5% 14.00 0.5% 10.85 0.5%
Ext Works & Sundries 11.58 0.5% 14.00 0.5% 10.85 0.5%
Preliminaries and General 294.00 12.0% 336.00 12.0% 276.00 12.0%
Contingency 36.75 1.5% 42.00 1.5% 34.50 1.5%
P&G, Contingency 330.75 13.5% 378.00 13.5% 310.50 13.5%
Total 2,450.00 100% 2,800.00 100% 2,300.00 100%
Cost Range
Auckland 2,300-2,600 2,650-2,950 2,300-2,600
Wellington 2,250-2,550 2,550-2,850 2,200-2,500
Christchurch 2,250-2,550 2,550-2,850 2,100-2,400
Dunedin 2,250-2,550 2,550-2,850 2,050-2,350
Elemental Costs of Buildings
2008
Devotional Buildings
P&G, Margins and Contingencies
Page 2-59
13 Devotional Buildings
13.1 Places of Worship 13.1.1 13.1.2 13.1.3 13.2.1
Devotional Devotional Devotional Hall
13.2 Halls Building Building Building
Basic Medium High Medium
Refer to page 1-28 Standard Standard Standard Standard
Element/Element Group $/m2 % $/m2 % $/m2 % $/m2 %
Site Preparation 3.09 0.2% 0.00 0.0% 0.00 0.0% 0.00 0.0%
Substructure 117.52 7.2% 153.50 7.9% 167.94 7.3% 159.16 9.8%
Frame 125.25 7.7% 119.59 6.1% 127.04 5.5% 72.88 4.5%
Structural Walls 154.63 9.5% 28.56 1.5% 36.60 1.6% 5.95 0.4%
Upper Floors 46.39 2.9% 0.00 0.0% 0.00 0.0% 0.00 0.0%
Structure 446.88 27.5% 301.65 15.5% 331.58 14.4% 237.99 14.6%
Roof 111.34 6.9% 219.55 11.3% 254.07 11.0% 206.75 12.7%
External Walls } 52.58 3.2% 410.53 21.1% 499.53 21.7% 290.05 17.8%
Windows & Doors } 91.23 5.6% 0.00 0.0% 0.00 0.0% 0.00 0.0%
External Fabric 255.15 15.7% 630.08 32.3% 753.60 32.8% 496.80 30.6%
Stairs 24.74 1.5% 0.00 0.0% 0.00 0.0% 0.00 0.0%
Internal Walls/Partitions 6.19 0.4% 37.48 1.9% 45.22 2.0% 96.68 5.9%
Internal Doors 40.20 2.5% 28.56 1.5% 30.14 1.3% 46.11 2.8%
Floor Finishes 35.57 2.2% 126.73 6.5% 135.65 5.9% 96.68 5.9%
Wall Finishes 75.77 4.7% 62.47 3.2% 75.36 3.3% 56.52 3.5%
Ceiling Finishes 60.31 3.7% 119.59 6.1% 163.64 7.1% 84.78 5.2%
Fittings & Fixtures 13.92 0.9% 183.85 9.4% 228.23 9.9% 74.37 4.6%
Internal Finishing 256.70 15.8% 558.68 28.7% 678.24 29.5% 455.14 28.0%
Sanitary Plumbing 4.64 0.3% 44.62 2.3% 53.83 2.3% 80.32 4.9%
Mechanical Services 0.00 0.0% 3.57 0.2% 8.61 0.4% 0.00 0.0%
Fire Services 112.88 6.9% 3.57 0.2% 6.46 0.3% 4.46 0.3%
Electrical Services 227.31 14.0% 91.03 4.7% 90.43 3.9% 84.78 5.2%
Lifts & Escalators 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%
Special Services 86.60 5.3% 28.56 1.5% 36.60 1.6% 19.34 1.2%
Drainage 7.73 0.5% 7.14 0.4% 8.61 0.4% 7.44 0.5%
Services 439.16 27.0% 178.49 9.2% 204.54 8.9% 196.34 12.1%
External Works 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%
Sundries 7.73 0.5% 17.85 0.9% 21.53 0.9% 19.34 1.2%
Ext Works & Sundries 7.73 0.5% 17.85 0.9% 21.53 0.9% 19.34 1.2%
Preliminaries and General 195.00 12.0% 234.00 12.0% 276.00 12.0% 195.00 12.0%
Contingency 24.38 1.5% 29.25 1.5% 34.50 1.5% 24.38 1.5%
P&G, Contingency 219.38 13.5% 263.25 13.5% 310.50 13.5% 219.38 13.5%
Total 1,625.00 100% 1,950.00 100% 2,300.00 100% 1,625.00 100%
Cost Range
Auckland 1,525-1,725 1,850-2,050 2,150-2,450 1,525-1,725
Wellington 1,450-1,650 1,800-2,000 2,100-2,400 1,450-1,650
Christchurch 1,425-1,625 1,825-2,025 2,100-2,400 1,425-1,625
Dunedin 1,400-1,600 1,775-1,975 2,050-2,350 1,400-1,600
Elemental Costs of Buildings
2008
Retail
P&G, Margins and Contingencies
Page 2-60
14 Retail
14.1 Suburban Retail 14.1.1 14.1.4 14.1.7 14.2.1
Suburban Suburban Suburban City
14.2 City Retail Neighbourhood Supermarket Shopping Centre Department
Shell Shell Store
Refer to page 1-29
Element/Element Group $/m2 % $/m2 % $/m2 % $/m2 %
Site Preparation 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%
Substructure 122.62 12.8% 104.61 8.9% 132.30 10.4% 126.45 5.7%
Frame 67.62 7.0% 55.06 4.7% 72.16 5.7% 159.62 7.3%
Structural Walls 57.70 6.0% 49.55 4.2% 54.12 4.2% 10.36 0.5%
Upper Floors 0.00 0.0% 0.00 0.0% 0.00 0.0% 155.47 7.1%
Structure 247.94 25.8% 209.22 17.8% 258.58 20.3% 451.90 20.5%
Roof 109.10 11.4% 115.62 9.8% 150.34 11.8% 55.97 2.5%
External Walls } 155.08 16.2% 154.16 13.1% 150.34 11.8% 279.85 12.7%
Windows & Doors } 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%
External Fabric 264.18 27.5% 269.78 23.0% 300.68 23.6% 335.82 15.3%
Stairs 0.00 0.0% 0.00 0.0% 0.00 0.0% 20.73 0.9%
Internal Walls/Partitions 101.88 10.6% 33.03 2.8% 90.20 7.1% 60.12 2.7%
Internal Doors 22.54 2.3% 16.52 1.4% 18.04 1.4% 16.58 0.8%
Floor Finishes 4.51 0.5% 82.59 7.0% 0.00 0.0% 89.14 4.1%
Wall Finishes 19.84 2.1% 38.54 3.3% 24.05 1.9% 47.68 2.2%
Ceiling Finishes 77.54 8.1% 60.56 5.2% 0.00 0.0% 82.92 3.8%
Fittings & Fixtures 7.21 0.8% 16.52 1.4% 6.01 0.5% 29.02 1.3%
Internal Finishing 233.52 24.3% 247.76 21.1% 138.30 10.8% 346.19 15.7%
Sanitary Plumbing 19.84 2.1% 27.53 2.3% 42.09 3.3% 35.24 1.6%
Mechanical Services 0.00 0.0% 143.15 12.2% 222.50 17.5% 331.68 15.1%
Fire Services 8.11 0.8% 33.03 2.8% 60.13 4.7% 76.70 3.5%
Electrical Services 35.16 3.7% 66.07 5.6% 66.15 5.2% 134.74 6.1%
Lifts & Escalators 0.00 0.0% 0.00 0.0% 0.00 0.0% 114.01 5.2%
Special Services 0.00 0.0% 0.00 0.0% 0.00 0.0% 51.82 2.4%
Drainage 5.41 0.6% 3.30 0.3% 2.41 0.2% 6.22 0.3%
Services 68.52 7.1% 273.08 23.2% 393.28 30.8% 750.41 34.1%
External Works 0.00 0.0% 0.00 0.0% 0.00 0.0% 0.00 0.0%
Sundries 16.23 1.7% 16.52 1.4% 12.03 0.9% 18.66 0.8%
Ext Works & Sundries 16.23 1.7% 16.52 1.4% 12.03 0.9% 18.66 0.8%
Preliminaries and General 115.20 12.0% 141.00 12.0% 153.00 12.0% 264.00 12.0%
Contingency 14.40 1.5% 17.63 1.5% 19.13 1.5% 33.00 1.5%
P&G, Contingency 129.60 13.5% 158.63 13.5% 172.13 13.5% 297.00 13.5%
Total 960.00 100% 1,175.00 100% 1,275.00 100% 2,200.00 100%
Cost Range
Auckland 910-1,010 1,075-1,275 1,175-1,375 2,050-2,350
Wellington 880-980 1,050-1,250 1,150-1,350 2,000-2,200
Christchurch 870-970 1,075-1,275 1,150-1,350 1,925-2,125
Dunedin 860-960 1,050-1,250 1,125-1,325 2,050-2,350
Comparative Costs
2008
Page 3-62
2008
Introduction
Purpose
Page 3-63
Introduction
Purpose
This section is intended as a guide to the ‘all-up’ unit costs of various materials, systems and
treatments that make up the various elements of a building. It can be used as a half-way step
between the ‘square metre’ estimating methods of the Building Costs per Square Metre section,
and a fully measured and priced estimate using the Detailed Rates section.
This section is particularly useful for budget estimating from preliminary sketch drawings, and with
care can give an accurate assessment of the cost of a final design.
Elements
An element is a component part of a building or a development that, irrespective of the design or
method of construction, tends to perform the same functions. For example, the Frame section
contains costs per metre for columns of reinforced in-situ concrete, precast concrete, and structural
steel. For a fuller explanation of elements, See “Definition of Elements” on page 2-36.
Rates
The rates given in this section assume an average size of structure, type of construction and level
of difficulty. As the average building rarely occurs, it is necessary to analyse where the building
under consideration differs from the average. Once the differences have been analysed, then
decide which of the various elements of the building will be affected by these differences, and make
due allowances for such differences.
It may be necessary to obtain full details for the ‘abnormal’ elements, in order that the whole
estimate should have some real meaning. If such details are not available, then make a suitable
allowance in the rates, for individual parts of the affected elements.
Some examples of differences, related to Elements, are as follows
Exclusions
Costs exclude
• land, demolition
• balconies, covered ways, parking areas
• external services more than 3m from the outside face of the building
• data and telephone services
• external works other than those immediately adjacent to the building
• loose Furniture, Fittings or Equipment (FF&E).
• legal and professional fees
• Goods and Services Tax (G.S.T.)
Comparative Costs
2008
Site Preparation
Demolition
Page 3-64
1 Site Preparation
1.1 Demolition
• Rates for demolition vary considerably. It is
always advisable to obtain a quotation from a
demolition contractor.
• Prices are for whole structures per square
metre of gross floor area
• For detailed rates, Refer to page 4-128
Demolish and remove
Factory/warehouse, light construction m2 50.00 50.00 50.00 50.00
Factory/warehouse, heavy construction m2 65.00 65.00 65.00 65.00
House, one or two storey, timber m2 60.00 60.00 60.00 60.00
House, one or two storey, concrete m2 65.00 65.00 65.00 65.00
Office building, two storey m2 85.00 85.00 85.00 85.00
Office building, five storey m2 385.00 385.00 385.00 385.00
1.5 Underpinning
Excavation and underpinning carried out in hit
and miss sections, excluding engineer's design
fees and excessive shoring.
300mm thick m2 1,200.00 1,200.00 1,200.00 1,200.00
600mm thick m2 1,600.00 1,600.00 1,600.00 1,600.00
Comparative Costs
2008
Substructure
Piling
Page 3-65
2 Substructure
2.1 Piling
• Prices vary considerably depending on
numbers, depths and ground conditions.
Concrete piles, bored and belled, including
reinforcing at 250kg/m3, setting up
600mm dia, in soil m 660.00 680.00 650.00 660.00
600mm dia, in soft rock m 760.00 780.00 740.00 750.00
900mm dia, in soil m 1,250.00 1,250.00 1,225.00 1,225.00
900mm dia, in soft rock m 1,400.00 1,425.00 1,375.00 1,400.00
900mm dia, in hard rock m 4,350.00 4,675.00 4,325.00 4,350.00
Temporary liner if required, 600mm dia m 116.00 131.00 116.00 116.00
Permanent liner if required, 600mm dia m 460.00 460.00 455.00 455.00
• For detailed rates, Refer to page 4-139
2008
Substructure
Column Pads
Page 3-66
2008
Frame
Columns
Page 3-67
3 Frame
• Based on common spans and loadings.
3.1 Columns
25 MPa reinforced in-situ concrete column,
with F3 formwork, 250kg/m3 reinforcing.
Includes pumping and cleaning.
Square column
250mm x 250mm m 245.00 240.00 235.00 235.00
400mm x 400mm m 480.00 470.00 460.00 465.00
600mm x 600mm m 900.00 880.00 865.00 870.00
750mm x 750mm m 1,295.00 1,270.00 1,245.00 1,250.00
Circular column, including single use
cardboard column formwork
150mm dia. m 100.00 98.00 96.00 97.00
250mm dia. m 166.00 164.00 158.00 161.00
300mm dia. m 200.00 200.00 194.00 197.00
450mm dia. m 365.00 360.00 350.00 360.00
600mm dia. m 645.00 635.00 620.00 630.00
710mm dia. m 765.00 760.00 740.00 750.00
800mm dia. m 940.00 930.00 905.00 925.00
900mm dia. m 1,155.00 1,140.00 1,110.00 1,130.00
Precast concrete column, 250kg/m3
reinforcing, including supply, transport up to
40km, erection, propping, grouting complete
250mm x 200mm m 225.00 225.00 197.00 335.00
300mm x 300mm m 295.00 300.00 275.00 555.00
400mm x 400mm m 420.00 430.00 395.00 555.00
600mm x 600mm m 735.00 770.00 770.00 905.00
Structural steel column, including supply,
fabrication, erection, end plates, connections,
abrasive blast and zinc silicate primer
150UC37 m 315.00 315.00 315.00 315.00
200UC59 m 485.00 485.00 485.00 485.00
250UC89 m 730.00 730.00 730.00 730.00
310UC97 m 795.00 795.00 795.00 795.00
310UC283 m 2,315.00 2,315.00 2,315.00 2,315.00
Add extra for hot dip galvanizing tonne 1,170.00 1,170.00 1,170.00 1,170.00
25 MPa concrete encased steel column,
including galvanising of steel
150UC37/250mm x 250mm concrete m 555.00 550.00 545.00 545.00
200UC59/300mm x 300mm concrete m 805.00 795.00 790.00 790.00
250UC89/350mm x 350mm concrete m 1,055.00 1,045.00 1,040.00 1,040.00
310UC97/400mm x 400mm concrete m 1,265.00 1,255.00 1,245.00 1,245.00
310UC283/450mm x 450mm concrete m 3,140.00 3,130.00 3,120.00 3,120.00
Comparative Costs
2008
Frame
Beams
Page 3-68
3.2 Beams
25 MPa reinforced in-situ concrete beam,
F4 formwork, 150kg/m3 reinforcing. Includes
pumping, cleaning, propping and access
scaffolds
200mm x 300mm deep m 240.00 230.00 225.00 230.00
300mm x 300mm deep m 280.00 275.00 265.00 270.00
300mm x 450mm deep m 385.00 375.00 365.00 365.00
400mm x 600mm deep m 575.00 560.00 550.00 550.00
450mm x 750mm deep m 740.00 725.00 710.00 710.00
450mm x 750mm beam rate breakdown
25 MPa concrete m 130.00 127.00 112.00 121.00
Formwork m 375.00 365.00 360.00 355.00
Reinforcing steel m 215.00 215.00 215.00 215.00
Propping and access scaffolds m 20.00 20.00 20.00 20.00
740.00 725.00 710.00 710.00
Precast concrete solid beam,
200kg/m3 reinforcing, including supply, transport
up to 40km, erection, propping, grouting
complete
350mm x 250mm deep m 285.00 290.00 275.00 355.00
350mm x 500mm deep m 410.00 415.00 455.00 500.00
450mm x 450mm deep m 435.00 445.00 465.00 535.00
450mm x 600mm deep m 520.00 535.00 580.00 645.00
Precast concrete shell beam,
including supply, transport up to 40km, erection,
propping, filling, reinforcing
400mm x 400mm deep m 315.00 325.00 305.00 -
400mm x 600mm deep m 375.00 390.00 370.00 -
Structural steel beam,
including supply, fabrication, erection, end
plates, connections, abrasive blast and zinc
silicate primer
Plain steel beam
200UB25 m 200.00 200.00 200.00 200.00
250UB31 m 240.00 240.00 240.00 240.00
310UB40 m 325.00 325.00 325.00 325.00
360UB57 m 465.00 465.00 465.00 465.00
Add extra for hot dip galvanizing tonne 1,170.00 1,170.00 1,170.00 1,170.00
25 MPa concrete encased steel beam,
includes galvanising of steel
200UB25/250mm x 300mm concrete m 400.00 390.00 385.00 390.00
250UB31/250mm x 350mm concrete m 485.00 480.00 470.00 475.00
310UB40/300mm x 400mm concrete m 595.00 585.00 575.00 580.00
360UB57/350mm x 450mm concrete m 755.00 745.00 735.00 735.00
• Fire proofing, Refer to page 4-418
Comparative Costs
2008
Frame
Portal Frames—Steel
Page 3-69
2008
Frame
Roof—Timber Framed
Page 3-70
2008
Structural Walls
Walls—In-situ Concrete
Page 3-71
4 Structural Walls
4.1 Walls—In-situ Concrete
25 MPa reinforced in-situ concrete wall
F2 formwork, reinforcing 100 kg/m3
150mm thick m2 405.00 395.00 385.00 385.00
200mm thick m2 445.00 435.00 425.00 425.00
250mm thick m2 485.00 475.00 460.00 465.00
Add extra for 30MPa concrete
150mm thick wall m2 1.20 1.40 1.70 1.75
200mm thick wall m2 1.65 1.90 2.30 2.30
250mm thick wall m2 2.05 2.35 2.85 2.90
Add extra for additional reinforcing, at 10kg/m3
150mm thick wall m2 6.40 6.40 6.40 6.40
200mm thick wall m2 8.60 8.60 8.60 8.60
250mm thick wall m2 10.75 10.75 10.75 10.75
Add extra for higher standard of finish of
formwork
F3 standard, to one face m2 8.00 8.00 8.00 8.00
F4 standard, to one face m2 10.00 10.00 10.00 10.00
F5 standard, to one face m2 20.00 20.00 20.00 20.00
20 MPa reinforced in-situ concrete wall
with polystyrene block formwork, comprising
50mm thick high density polystyrene to both
faces of wall, with spacer ties for external screw
fixing to finished wall face, reinforcing 50kg/m3
200mm thick wall, 100mm concrete m2 158.00 157.00 152.00 155.00
250mm thick wall, 150mm concrete m2 187.00 185.00 179.00 183.00
300mm thick wall, 200mm concrete m2 215.00 215.00 205.00 210.00
2008
Upper Floors
Timber/Particle Board
Page 3-72
5 Upper Floors
5.1 Timber/Particle Board
20mm particle board on MSG8 timber framing
including lateral supports, nogging to sheet ends
and edges.
Framing at 450mm centres
150mm x 50mm joists, 2.6m span m2 116.00 104.00 110.00 111.00
200mm x 50mm joists, 3.45m span m2 126.00 113.00 120.00 121.00
250mm x 50mm joists, 4.3m span m2 140.00 124.00 134.00 134.00
300mm x 50mm joists, 5.05m span m2 175.00 132.00 145.00 150.00
Framing at 600mm centres
150mm x 50mm joists, 2.0m span m2 101.00 92.00 97.00 98.00
200mm x 50mm joists, 3.15m span m2 110.00 99.00 105.00 106.00
250mm x 50mm joists, 3.9m span m2 121.00 108.00 116.00 116.00
300mm x 50mm joists, 4.6m span m2 150.00 114.00 125.00 130.00
22mm Pynefloor™ Gold particle board on
MSG8 timber framing, including lateral supports,
nogging to sheet ends
Framing at 450mm centres
150mm x 50mm joists, 2.6m span m2 102.00 93.00 99.00 99.00
200mm x 50mm joists, 3.45m span m2 113.00 102.00 109.00 109.00
250mm x 50mm joists, 4.3m span m2 127.00 113.00 123.00 121.00
300mm x 50mm joists, 5.05m span m2 154.00 115.00 127.00 131.00
Framing at 600mm centres
150mm x 50mm joists, 2.0m span m2 92.00 84.00 89.00 89.00
200mm x 50mm joists, 3.15m span m2 101.00 91.00 97.00 97.00
250mm x 50mm joists, 3.9m span m2 112.00 100.00 108.00 108.00
300mm x 50mm joists, 4.6m span m2 141.00 107.00 117.00 121.00
2008
Upper Floors
Reinforced Insitu Concrete
Page 3-73
5
2 Large curved corners for longer spans.
5
3 1
3 Circular embossments for strong composite
2 1 4 2 3
4 action between concrete and steel.
4
Bottom stiffeners pushed apart allowing
4 4
studs to achieve full capacity.
2008
Upper Floors
Precast Concrete Floor Systems
Page 3-75
corus
2008
Roof
Concrete Roof Construction
Page 3-76
6 Roof
• Costs are based on flat plan area to overall Pitch % Pitch % Pitch % Pitch %
dimensions, with allowance for average 20° 6.5% 25° 10.5% 30° 15.5% 35° 22.0%
pitches. 40° 30.0% 45° 42.0% 50° 55.0% 55° 75.0%
• Add the percentages shown in the chart to 60°100.0%
roofing finishes, where pitch is 20° or more
6.3 Insulation
Fibreglass insulation, batts R3.6 Ultra m2 17.75 17.50 17.50 17.50
• For more insulation, Refer to page 4-203
Comparative Costs
2008
Exterior Walls, Exterior Finish
Finishes to Concrete Walls
Page 3-77
2008
Exterior Walls, Exterior Finish
Timber Walls with Cladding
Page 3-78
2008
Exterior Walls, Exterior Finish
Fire and Acoustic Systems
Page 3-79
2008
Exterior Walls, Exterior Finish
Exterior Insulation Finishing Systems
Page 3-80
Unit Ak/Wn/Ch/Dn $
2008
Windows and Exterior Doors
Windows
Page 3-81
8.1 Windows
Aluminium windows, commercial,
clear anodised framing
Single glazed windows
Fixed m2 520.00 515.00 515.00 515.00
Sliding, 25% opening m2 620.00 615.00 615.00 615.00
Awning, 50% opening m2 615.00 610.00 610.00 610.00
Double glazed windows
Fixed m2 655.00 650.00 650.00 650.00
Opening m2 750.00 745.00 745.00 745.00
Timber windows, casement
H3 finger-jointed pine
Less than 1m2 in area m2 1,160.00 1,155.00 1,155.00 1,155.00
More than 1m2 in area m2 780.00 775.00 775.00 775.00
H3 finger-jointed pine, cedar sashes
Less than 1m2 in area m2 1,230.00 1,225.00 1,225.00 1,225.00
More than 1m2 in area m2 840.00 840.00 840.00 840.00
2008
Stairs and Balustrades
Straight Stairs
Page 3-82
2008
Stairs and Balustrades
Spiral Stairs
Page 3-83
9.3 Handrails
• Refer to page 4-189
9.4 Balustrades
• Refer to page 4-188
Comparative Costs
2008
Interior Walls and Partitions
Timber Partitions
Page 3-84
2008
Interior Doors
Flush Timber Doors
Page 3-85
11 Interior Doors
• All door dimensions are given in millimetres, as
height x width
2008
Interior Doors
Framed, Ledged and Braced Doors
Page 3-86
2008
Floor Finishes
Masonry Flooring
Page 3-87
12 Floor Finishes
• Concrete finishing included with concrete slabs.
• $Value/m2 is indicative value for material to be
supplied. Adjust rates as necessary
2008
Floor Finishes
Sheet Flooring, Resilient
Page 3-88
12.5 Carpet
Commercial grade carpet, heavy duty
Synthetic m2 40.00 40.00 40.00 40.00
Wool—woven, includes smooth edge and m2 135.00 135.00 135.00 135.00
underlay, $70/m2
Wool—tufted, includes smooth edge and m2 70.00 70.00 70.00 70.00
underlay, $35/m2
Commercial grade carpet tiles
Wool/nylon, $78/m2 m2 105.00 105.00 105.00 105.00
Polypropylene, $22.50/m2 m2 40.00 40.00 40.00 40.00
Add extra for
Rubber underlay, if not included above m2 8.00 8.00 8.00 8.00
• For detailed rates, Refer to page 4-400
2008
Wall Finishes
Plasterboard and Fibrous Plaster
Page 3-89
13 Wall Finishes
13.1 Plasterboard and Fibrous Plaster
Plaster Board, F4 finish, fixed to timber
framing, with cornice, skirting, external angles
and painting
10mm thick Standard m2 55.00 55.00 54.00 55.00
10mm thick Aqualine m2 62.00 63.00 64.00 66.00
10mm thick Fyreline m2 56.00 56.00 56.00 57.00
10mm Ultraline m2 58.00 58.00 57.00 58.00
10mm Noiseline m2 59.00 59.00 59.00 60.00
13mm thick Standard m2 58.00 58.00 57.00 59.00
13mm thick Aqualine m2 70.00 70.00 71.00 73.00
13mm thick Fyreline m2 61.00 61.00 62.00 63.00
13mm Noiseline m2 61.00 62.00 62.00 64.00
13mm Toughline m2 65.00 64.00 64.00 64.00
Add for stopping to F5 finish m2 17.50 17.50 17.50 17.50
Cornice, skirting, external angles and painting to m2 26.50 26.00 25.50 25.50
any plaster board surface, excludes plaster board
Fibrous plaster, 12.5mm thick, fixed to timber m2 77.00 72.00 72.00 78.00
framing, with cornice, skirting, external angles
and painting
• For detailed rates, Refer to page 4-387
Strapping, 50mm x 25mm battens at 600crs m2 27.50 25.50 27.50 27.00
Strapping, 75mm x 40mm battens at 600crs, m2 53.00 50.00 43.00 47.00
with dpc and 40mm Polystyrene insulation
13.3 Timber
Medium Density Fibreboard—MDF, 16mm m2 48.00 46.50 45.75 45.75
thick, painted
Plywood, paint finish
9mm thick m2 65.00 61.00 60.00 62.00
7mm, grooved m2 83.00 82.00 82.00 82.00
12mm, grooved m2 70.00 66.00 66.00 67.00
13.4 Metal
Baby corrugate, 0.55mm thick, zincalume finish m2 47.75 47.75 47.75 47.75
13.5 Painting
• For detailed rates, Refer to page 4-406
Comparative Costs
2008
Wall Finishes
Tile and Sheet
Page 3-90
13.9 Plaster
• Costs include average allowance for narrow
widths and labours
Cement plaster, 2 coats m2 54.00 53.00 52.00 52.00
Hardwall plaster, 2 coats m2 54.00 53.00 51.00 51.00
Tyrolean plaster, sprayed finish m2 77.00 75.00 72.00 72.00
Galvanised steel expanded lathe m2 30.25 30.25 30.25 30.25
Seal and two coats enamel paint m2 14.50 14.25 14.25 14.25
Seal and two coats acrylic paint m2 13.50 13.25 13.25 13.25
• For detailed rates, Refer to page 4-384
Comparative Costs
2008
Ceiling Finishes
On Concrete Soffit
Page 3-91
14 Ceiling Finishes
• Costs include average allowance for narrow
widths, painting or clear finish as appropriate.
• Costs exclude allowance for cornices as these
have generally been included in Wall Finishes.
• For detailed rates for suspended ceilings,
Refer to page 4-394
• For floor/ceiling systems, Refer to page 3-72
2008
Sanitary Plumbing
Sanitary Fixtures
Page 3-92
15 Sanitary Plumbing
• Costs include sanitary fixtures, fully installed, with pipework, cisterns, taps or mixers, traps, wastes, floor
penetrations, waste stacks and vents, to the outside face of the building. Copper pipe for commercial
buildings, polybutylene and pvc for domestic. For detailed rates, Refer to page 4-297
2008
Sanitary Plumbing
Sanitary Fixtures
Page 3-93
2008
Heating and Ventilation
Mechanical Ventilation
Page 3-94
2008
Heating and Ventilation
Air Conditioning
Page 3-95
2008
Fire Services
Costs per square metre
Page 3-96
17 Fire Services
17.1 Costs per square metre
• For detailed rates, Refer to page 4-349 $/m2
Fire services with sprinklers, but excluding
pumps and tanks
Education
Primary Schools 66.00 - 88.00
Secondary Schools 51.00 - 77.00
Technical Colleges 51.00 - 77.00
University Arts 51.00 - 77.00
University Lecture Theatre 51.00 - 77.00
Hospitals
District, Private 45.75 - 66.00
General 51.00 - 77.00
Hotels and motels
City, three star 51.00 - 77.00
City, five star 51.00 - 77.00
Motel, standard 40.50 - 66.00
Industrial
Warehouse with small office 51.00 - 77.00
Factory with small office 40.50 - 66.00
Laboratory, workshop 40.50 - 66.00
Offices
Basic 1–3 storey 40.50 - 52.00
Serviced 1–3 storey 40.50 - 52.00
4–7 storey 40.50 - 52.00
8–20 storey 40.50 - 52.00
21–50 storey 45.75 - 66.00
Parking
Underground, low level 35.00 - 46.00
Multi-storey 35.00 - 46.00
Recreational
Clubhouse and change rooms 45.75 - 66.00
Community Recreation Centre, medium std 45.75 - 66.00
Squash Courts, high standard 45.75 - 66.00
Residential
Individual house, medium standard 76.00 - 99.00
Flats, 1–3 storey, medium standard 76.00 - 99.00
Multi storey, basic standard 51.00 - 77.00
Multi storey, prestige standard 51.00 - 77.00
Hostel or boarding house 51.00 - 77.00
Retail
Supermarket, suburban 40.50 - 52.00
Regional centre, prestige 51.00 - 66.00
Department store, city 51.00 - 66.00
Comparative Costs
2008
Electrical Services
Costs per square metre
Page 3-97
18 Electrical Services
18.1 Costs per square metre
• For detailed rates, Refer to page 4-355 $/m2
Education
Primary Schools 130.00 - 215.00
Secondary Schools 185.00 - 270.00
Technical Schools 210.00 - 290.00
University Arts 285.00 - 455.00
University Lecture Theatre 285.00 - 455.00
Hospitals
District, Private 320.00 - 500.00
General 350.00 - 600.00
Hotels and motels
City, three star 200.00 - 270.00
City, five star 210.00 - 280.00
Motel, standard 130.00 - 195.00
Industrial
Warehouse with small office 41.75 - 125.00
Factory with small office 41.75 - 125.00
Laboratory, workshop 185.00 - 250.00
Offices
Basic 1–3 storey 96.00 - 165.00
Serviced 1–3 storey 96.00 - 165.00
4–7 storey 140.00 - 205.00
8–20 storey 150.00 - 225.00
21–50 storey 155.00 - 230.00
Parking
Underground, low level 38.25 - 58.00
Multi-storey 24.75 - 46.50
Recreational
Clubhouse and change rooms 120.00 - 175.00
Community Recreation Centre, medium std 84.00 - 145.00
Squash Courts, high standard 64.00 - 125.00
Residential
Individual house, medium standard 29.50 - 58.00
Flats, 1–3 storey, medium standard 52.00 - 83.00
Multi storey, basic standard 64.00 - 93.00
Multi storey, prestige standard 130.00 - 165.00
Hostel or boarding house 75.00 - 105.00
Retail
Supermarket, suburban 96.00 - 135.00
Regional centre, prestige 120.00 - 155.00
Department store, city 96.00 - 155.00
Comparative Costs
2008
Electrical Services
Submains Sizing
Page 3-98
• Exclude hot water unit, stove/oven or air conditioning where not required.
• Divide the estimated maximum demand by 3 for three phase power supplies.
• The air conditioning allowance is based on providing a nominal 80m2 to 100m2 of air conditioned space
per dwelling by utilising room air conditioners with cooling capacity totalling 13kW net (44,400 BTU/hour
net) (i.e. 75% of total 24A load).
• Note: Minimum size for consumer mains is 4mm2.
Comparative Costs
2008
Lifts and Escalators
Criteria
Page 3-99
25
Number of Floors Serviced
6 7 8
20
5
15
4
10 3
2008
Drainage
Stormwater and Soil Drains
Page 3-100
Unit Ak/Wn/Ch/Dn $
20 Drainage
• For detailed rates, Refer to page 4-316
2008
External Works
Roading
Page 3-101
Unit Ak/Wn/Ch/Dn $
21 External Works
• For detailed rates, Refer to page 4-422
21.1 Roading
Sprayed bitumen and chip surfacing, with
150mm thick basecourse m2 21.00 - 24.25
250mm thick basecourse m2 24.75 - 30.00
Bituminous concrete
25mm thick on 150mm basecourse m2 35.50 - 36.75
25mm thick on 250mm basecourse m2 39.50 - 42.50
40mm thick on 150mm basecourse m2 45.00 - 46.25
40mm thick on 250mm basecourse m2 48.75 - 52.00
21.2 Paving
Insitu concrete paving, on 50mm compacted
sand bed, 150mm basecourse layer, with
broomed finish
75mm thick, unreinforced m2 53.00 - 60.00
100mm thick, reinforced m2 80.00 - 87.00
Insitu exposed aggregate concrete paving,
reinforced, on 50mm compacted sand bed,
150mm basecourse layer, with broomed finish
100mm thick, lower price range m2 84.00 - 95.00
100mm thick, higher price range m2 97.00 - 107.00
Precast concrete paving, on 50mm compacted
sand bed, 150mm basecourse layer
50mm thick brick paver m2 98.00 - 82.00
60mm thick cobblestone m2 87.00 - 85.00
Large format pavers, 450mm x 450mm m2 88.00 - 90.00
Large format pavers, 600mm x 600mm m2 119.00 - 121.00
Add extra for
Polythene underlay m2 2.40 - 3.00
Mortar bed 25mm thick m2 10.00 - 12.00
2008
Preliminaries
Approximate Percentages
Page 3-102
22 Preliminaries
• The following percentage allowances should be considered as an approximate guide only, to be used
when compiling elemental cost estimates of a project. Inclusions: all usual Builder's preliminaries, i.e.
insurance, setting out, plant and scaffolding, supervision, temporary services and facilities, cleaning and
handover, maintenance, etc., assuming normal site conditions and average contract period relative to
the value of the works.
• ADD to these percentage allowances when the value of work is below $250,000 or when the contract
period is longer than usually allowed, particular attention being paid to supervision, site peculiarities,
alteration work, temporary services, plant hire.
2008
Page 4-104
2008
Page 4-105
2008
Page 4-106
Steel and Aluminium Roofing 4-281 Directional Drilling and Micro-Tunnelling 4-318
Concrete and Clay Tiles and Shingles 4-283 Sewer Drains—PVC 4-318
Metal Tiles, Shakes and Shingles 4-283 Sewer Drains—Earthenware 4-320
Shingles and Shakes—Timber 4-284 Sewer Drains—Concrete 4-321
Shingles and Shakes—Synthetic 4-284 Stormwater Drains 4-323
Slate Roofing 4-284 Agricultural Drains 4-324
Translucent Roofing 4-284 Concrete Surrounds 4-325
Mastic Asphalt Roofing 4-285 Breaking Into Existing Pipelines 4-325
Butyl Rubber Membrane Roofing 4-285 Sumps 4-325
Bituminous and Acrylic Membranes 4-286 Cesspits 4-325
Deck and Carpark Membranes 4-286 Manholes 4-326
Finishes and Protection 4-286 Manhole Covers 4-326
Wall Cladding 4-287 Traps 4-327
Roofing Underlays 4-287 Septic Tanks 4-327
Roof Windows and Rooflights 4-288 Waste Water Diversion Systems 4-327
Rainwater Heads 4-291 Channel Drains and Gratings 4-328
Concealed Gutter Fascia System 4-291 Wing Walls 4-328
Box Gutters 4-292 4.28 Mechanical Services 4-329
Valley Gutters 4-292 Room Air Conditioners (RAC) 4-329
Eaves Gutters—Metal 4-292 Split System Type Air Conditioners 4-329
Eaves Gutters—PVC 4-293 Hydronic Air Conditioning Systems 4-330
Roof Drains 4-293 Fan Coil Units 4-331
Ventilators 4-293 Central Station Air Handling Units 4-331
Downpipes 4-294 Fans—Centrifugal 4-331
Flashings 4-295 Fans–Axial Flow 4-332
4.26 Plumbing 4-297 Air Filters 4-332
WC Pans—Vitreous China 4-297 Water Chillers 4-333
WC Pans—Stainless Steel 4-297 Cooling Towers 4-333
WC Suites—Vitreous China 4-298 Cooling and Heating Coils 4-334
WC Seats 4-298 Radiators 4-334
Bidets 4-298 Hot Water Boilers 4-335
Cisterns 4-299 Flues 4-336
Urinals—Slab, Stainless Steel 4-299 Pumps 4-336
Urinals—Stall 4-299 Pipework 4-338
Urinal Cisterns 4-299 Valves 4-340
Urinal Flushing Valves 4-300 Pipe Insulation 4-341
Flushing Valves 4-300 Ductwork—Rectangular 4-342
Pumped Waste System 4-300 Ductwork—Insulation 4-342
Baths—Acrylic 4-300 Ductwork—Spiral 4-343
Baths—Steel or Cast Iron 4-301 Ductwork—Flexible Aluminium 4-344
Spa Baths—Acrylic 4-301 Diffusers and Grilles 4-344
Shower Enclosures—Acrylic 4-301 Inlet Louvres 4-345
Shower Bases 4-301 Balancing and Commissioning 4-345
Basins—Wall 4-302 Powered Ventilation 4-346
Basins—Vanity 4-302 Natural Ventilation 4-348
Vanity Units 4-302 4.29 Fire Protection 4-349
Tubs 4-303 Extinguishers 4-349
Cleaners Sinks 4-303 Hose Reels 4-349
Kitchen Sink Benches 4-303 Hydrant Point/Landing Valves 4-349
Kitchen Sink Inserts 4-303 Pumps 4-350
Drinking Fountains 4-304 Standard Water Sprinklers 4-350
Saunas and Spa Pools 4-304 Dry Pipe Sprinklers 4-351
Sanitary Disposal Units 4-304 Detector and Alarm Systems 4-351
Taps and Cocks 4-305
Mixers 4-306 4.30 Lifts and Escalators 4-352
Traps 4-307 Passenger Lifts 4-352
Pipework—Soil, Waste and Vent 4-308 Escalators and Moving Walkways 4-354
Pipework—Water Supply 4-310 4.31 Electrical Services 4-355
Water Tanks 4-313 Cable Supply Prices 4-355
Water Heaters, Gas 4-314 General Note 4-356
Water Heaters, Electric 4-314 11KV Transformers/Switch Gear 4-356
4.27 Drainage 4-316 11KV High Voltage Cable 4-356
Trench Excavation 4-316 Service Mains—Overhead, Copper 4-356
Service Mains—Underground, Copper 4-357
Detailed Rates
2008
Page 4-107
2008
Page 4-108
2008
How to Use this Section
Overview
Page 4-109
2008
Preliminaries
Check List
Page 4-110
1 Preliminaries
1.1 Check List
Category Description Unit $ Rate $ Value
2008
Preliminaries
Charges, Levies, Consultants
Page 4-111
2008
Preliminaries
Temporary Works and Services
Page 4-112
2008
Preliminaries
Temporary Works and Services
Page 4-113
2008
Preliminaries
Temporary Works and Services
Page 4-114
Temporary Waterproofing
Project Requirements
Drying of building
before handover
during construction
Protection of Public and Private Property Services
Protect existing services
Water
Electricity
Gas
Other
Make good
General Expenses
Petty Cash month
Site Ceremonies
Topping off Ceremonies
First Aid
First Aid Kit
Refilling, etc.
Detailed Rates
2008
Preliminaries
Staff Costs
Page 4-115
2008
Preliminaries
Equipment
Page 4-116
Equipment
Cranes—Tower
Proposed Requirements Types
Period
Stationary Crane
Delivery to Site
Foundations
Excavation
Reinforcing concrete
Sundries
Base/Track
Erection
Labour
Crane Hire
Sundries
Testing
Removal
Labour
Crane hire
Sundries
Electrics
Tie Frames
Ballast
Raising
Rental
Repairs and Maintenance
Running Costs
Sundries
Platform Hoist
Site Requirements
Delivery to Site
Erection
Labour
Crane Hire
Sundries
Dismantling
Labour
Crane Hire
Sundries
Rental
Repairs and maintenance
Running Costs
Electrics
Sundries
Detailed Rates
2008
Preliminaries
Equipment
Page 4-117
2008
Preliminaries
Sundries
Page 4-118
Sundries
Attendance Upon Net Sums
Plant
Facilities
Supervision
Testing of Materials and Provision of Samples
Contract Requirements
Attendances
Cost Samples and Displays
Cleaning—Progressive
Rubbish Chute
Cost of erection
Hireage Day
Dismantle
Monthly Usage
Labour Hrs
Bins
Truck hire
Tip fees
Cleaning—Final
Internal commercial clean
External face commercial clean
Site labour
Bins
Fees
Truck hire
Maintenance
Refer to Contract requirements
Maintenance period ______months
Materials Cost
Labour Cost
Pumping/Dewatering
Check if allowed elsewhere, e.g. Excavator
Detailed Rates
2008
Preliminaries
Mobile Crane Hire
Page 4-119
2008
Preliminaries
Tower Cranes
Page 4-120
2008
Preliminaries
Temporary Telephones—Landlines
Page 4-121
Unit Ak/Wn/Ch/Dn $
2008
Preliminaries
Hoardings, Fences and Canopies
Page 4-122
Unit Ak/Wn/Ch/Dn $
2008
Preliminaries
Scaffolding
Page 4-123
Unit Ak/Wn/Ch/Dn $
Lunch Rooms, insulated panel construction
including tables, bench seating, vinyl floor
coverings, sink bench unit, heater
6m x 3m No 195.00
4.8m x 2.5m No 180.00
3.6m x 2.5m No 165.00
Large, 12m x 3.1m No 450.00
Toilets, insulated panel construction with
W.C.’s, urinals, basin, water inlet and sewer/
waste outlets ready for connections
One pan unit No 90.00
Two pan unit No 160.00
Three pan unit No 184.00
Four pan unit No 200.00
Add extra for
Water supply and sewer connections,
soap, towel and paper supplies.
Moulded Construction Portable Toilet with
separate urinal, 1.5m x 1.5m x 2.2m
1-3 months No 320.00 - 360.00
3 months and over No 180.00 - 220.00
Pumping out and cleaning No 120.00 - 160.00
1.10 Scaffolding
• Including erecting, dismantling, cartage etc.
Tubular Steel Scaffolding, 1st month m2 10.00 - 14.00
Add extra for
Hire, per month (after first month) m2 4.00 - 6.00
Hire timber planks, per week No 3.50
Frames and braces, set o f 2, per week Set 9.00
Protection netting (purchased) m2 2.00
Mobile Scaffold, 2.4 x 1.2 x 4m high No 90.00 - 120.00
2008
Preliminaries
Helicopter Hire
Page 4-124
Unit Ak/Wn/Ch/Dn $
2008
Preliminaries
Lift Inspections
Page 4-125
Unit Ak/Wn/Ch/Dn $
2008
Preliminaries
Building Consent Fees
Page 4-126
2008
Preliminaries
Insurances
Page 4-127
1.20 Insurances
Contractors All Risk Insurance
This type of policy provides cover to the Contractor during the construction of a building for
damages caused by fire, rain, wind, explosion, accidental or malicious damage, burglary and theft.
The extent of the policy should be checked and additional cover arranged to suit each particular
contract as necessary for items such as: plant, tools and equipment, vibration and removal of
support, piling work, temporary buildings and structures, plate glass fixing and removal, demolition
and clearance of site, indemnity to the principal, damage to underground installations
Blanket Cover—This is substantial annual cover which is pre-arranged and based on projected
turnover. It is adjusted retrospectively when actual turnover is calculated for the year. Cover can be
set at the anticipated maximum level or alternatively at a lower or average level and special
extensions applied for only when required.
Separate Cover—A separate cover for each contract is negotiated making allotment of costs per
project easier to establish.
Premium Rates
These vary considerably depending on the type of construction, duration of cover, builder’s track
record, amount of self insurance, etc. Insurance companies consider contract works under four
main categories. Rates shown as a percentage of contract value (including consultants fees,
temporary works, demolition and removal of debris) are a guide only, and more competitive rates
may be achieved on application.
Civil works Bridges, dams, roadwork 0.50–0.80%
Building works Commercial and industrial 0.20–0.50%
Building works Residential 0.15–0.20%
Engineering works Erection and installation of plant etc. 0.14–0.18%
Public Liability Insurance
This cover is calculated on the contract value for the project. In the case of sub-contractors and
labour only gangs, the Builder may effect cover OR require sub-contractors to provide evidence of
the existence of insurance cover which complies with the terms of the head contract.
The following are examples of the order of cost of this item.
Type of Contract Example One Example Two
Contract Cover $ Premium $ Contract Cover $ Premium $
Value $ 0.25% Value $ 0.30%
Civil 600,000 2,000,000 1,500 1,000,000 5,000,000 3,000
Commercial, Industrial 1,000,000 2,000,000 2,500 1,000,000 5,000,000 3,000
Commercial, Industrial 80,000,000 5,000,000 240,000
Residential 600,000 2,000,000 1,500 1,000,000 5,000,000 3,000
Engineering 600,000 2,000,000 1,500 1,000,000 5,000,000 3,000
Detailed Rates
2008
Demolition and Alterations
Demolition of Entire Structures
Page 4-128
Unit Ak/Wn/Ch/Dn $
2008
Demolition and Alterations
Refurbishment and Alterations
Page 4-129
Unit Ak/Wn/Ch/Dn $
2.3 Screens
Temporary Screens, comprising timber framing
covered one side with:
Building paper taped at joints and edges m2 30.00 - 33.00
Polythene sheet taped at joints and edges m2 28.00 - 31.00
7.5mm plywood (low grade), 4 uses m2 32.00 - 36.50
12mm Pinex insulation board m2 41.00 - 44.00
Orange plastic safety netting m2 28.00 - 32.50
Detailed Rates
2008
Demolition and Alterations
Protection
Page 4-130
Unit Ak/Wn/Ch/Dn $
2.4 Protection
Protect floors with polythene or hessian m2 2.50 - 3.50
Protect timber stair treads m 3.50 - 6.00
Mitech Self-Adhesive Carpet Film PF38 m2 2.50 - 3.00
Mitech Self-Adhesive Window Film PF15 m2 2.50 - 3.50
2008
Demolition and Alterations
Preparatory Work/Repairs
Page 4-131
Unit Ak/Wn/Ch/Dn $
2008
Demolition and Alterations
Work in Connection With Services
Page 4-132
Unit Ak/Wn/Ch/Dn $
2008
Excavation
Bulking Factors
Page 4-133
3 Excavation
• Prices for excavation and disposal relate to
volume before excavation, i.e. solid measure.
• Prices are based on a maximum quantity of
1000m3; where quantities are in excess of
1000m3, Refer to page 4-430.
• All excavation is by machine unless otherwise
stated.
• Prices are for excavation only. Backfilling and
removal of surplus material from site, and
planking and strutting, are given separately.
3.3 Excavation
Bulk Excavate Over Site to reduce levels, load into truck
in light soil or sand m3 3.90 3.90 3.90 5.20
in clay m3 6.50 5.20 5.20 6.50
in soft (rippable) rock m3 13.00 11.75 11.75 14.25
in hard rock m3 58.00 65.00 78.00 85.00
-91.00 -91.00 -104.00 -111.00
Detailed Rates
2008
Excavation
Excavation
Page 4-134
2008
Excavation
Disposal/Carting Away
Page 4-135
3.5 Filling
Indicative Supply Prices.
• Note, these vary widely depending on source
and distance to be carried
20mm aggregate (GAP20) m3 24.00 19.75 14.25 26.75
-47.00
40mm aggregate (GAP40) m3 23.00 16.50 13.00 25.00
-41.00
65mm aggregate (GAP65) m3 21.25 20.75 11.75 28.50
-41.00
TNZ40 basecourse m3 48.00 25.00 16.50 33.25
Sand, No 3 m3 40.50 39.25 33.75 30.50
Drainage fill, 40mm m3 33.75 17.50 14.25 25.75
• Prices below are for compacted quantities in
place, including cartage
Excavate Clay from stockpile, spread and m3 24.75 24.75 24.75 24.75
consolidate in layers
Excavated Material as backfilling m3 22.50 22.50 22.50 22.50
GAP65 Hardfill consolidated in layers m3 62.00 51.00 47.50 63.00
-85.00
Crushed Rock consolidated in layers m3 51.00 45.75 39.50 56.00
Bondor Polyrock® geotechnical lightweight fill
15kg/m3 nominal density m3 101.00 133.00 101.00 133.00
24kg/m3 nominal density m3 140.00 172.00 139.00 172.00
28kg/m3 nominal density m3 161.00 193.00 160.00 193.00
Drainage fill, behind retaining wall m3 44.75 35.25 31.25 44.25
• For working space rules, Refer to page 14-644
Detailed Rates
2008
Excavation
Sand
Page 4-136
3.6 Sand
Sand filling consolidated in layers m3 55.00 59.00 51.00 51.00
Sand blinding, 25mm thick m2 4.85 5.20 4.35 4.35
Sand blinding, 50mm thick m2 6.50 6.80 6.20 6.20
3.10 Shoring
Shoring comprising RSJ soldier piles in bored m2 500.00 500.00 500.00 500.00
pier hole including concrete base, infilling RSJ's -685.00 -685.00 -685.00 -685.00
with timber or precast waling and filling at back,
average 200mm thick
Detailed Rates
2008
Piling
Pile Drilling Only, Small Diameter
Page 4-137
4 Piling
• Prices are for piles in ground other than rock. Good
ground conditions and site access are assumed.
• Prices do not include dewatering.
• Prices include delivery up to 30km from supplier.
2008
Piling
Timber Piles, Bored
Page 4-138
2008
Piling
Precast Concrete Piles, Ordinary
Page 4-139
2008
Piling
Steel Sheet Piling
Page 4-140
2008
Piling
Steel Piles, Driven
Page 4-141
2008
Concrete Work
Supply Prices, Retail
Page 4-142
5 Concrete Work
• Prices for concrete include ready-mixed
concrete, delivery to site, discount, wastage
and loss, handling and placing in position.
2008
Concrete Work
Samples and Testing
Page 4-143
2008
Concrete Work
Concrete Additives, Admixtures
Page 4-144
2008
Concrete Work
Architectural Surface Finishes
Page 4-145
2008
Concrete Work
Waterstops In Concrete
Page 4-146
2008
Concrete Work
Joints In Concrete
Page 4-147
2008
Concrete Work
Concrete Cutting and Drilling
Page 4-148
2008
Concrete Work
Expansion Joint Covers
Page 4-149
2008
Formwork
Types Of Formwork
Page 4-150
6 Formwork
• Prices assume moderate quantities and five uses.
• Rates for formwork include circular and raking
cutting.
• Adjust prices given hereafter for:
Three uses + 15%
One use + 30%
One use, left in place + 25%
• Labour constants used shown in Hrs column
2008
Formwork
Formwork Sundries
Page 4-151
2008
Formwork
Polystyrene Block Formwork
Page 4-152
2008
Formwork
Metal Tray Formwork
Page 4-153
5
2 Large curved corners for longer spans.
5
3 1
3 Circular embossments for strong composite
2 1 4 2 3
4 action between concrete and steel.
4
Bottom stiffeners pushed apart allowing
4 4
studs to achieve full capacity.
2008
Formwork
Forming Holes and Openings
Page 4-155
6.12 Voids
Reinforced Kraft Tube Void Former
(Formavoid) laid horizontally in concrete
slab (Voids left in place)
249mm dia 0.60 m 43.00 42.25 40.75 41.50
296mm dia 0.60 m 44.50 43.50 42.00 42.75
356mm dia 0.60 m 57.00 56.00 54.00 55.00
368mm dia 0.70 m 58.00 57.00 55.00 56.00
406mm dia 0.70 m 58.00 57.00 55.00 56.00
Endcaps to Formavoid
249mm dia 0.10 No 10.50 10.25 10.25 10.25
296mm dia 0.10 No 10.25 10.00 10.00 10.00
356mm dia 0.10 No 11.25 11.25 11.00 11.00
368mm dia 0.10 No 12.25 12.00 12.00 12.00
406mm dia 0.10 No 11.50 11.25 11.25 11.25
Detailed Rates
2008
Sprayed Concrete
Supply Prices
Page 4-156
7 Sprayed Concrete
7.1 Supply Prices
Pumpmix
20 MPa, 10mm aggregate m3 230.00 210.00 177.00 208.00
25 MPa, 10mm aggregate m3 235.00 215.00 182.00 213.00
30 MPa, 10mm aggregate m3 241.00 221.00 187.00 219.00
20 MPa, 13–19mm aggregate m3 217.00 201.00 172.00 202.00
25 MPa, 13–19mm aggregate m3 222.00 212.00 178.00 211.00
Spraymix
25 MPa, 7mm aggregate m3 254.00 244.00 210.00 240.00
30 MPa, 7mm aggregate m3 264.00 247.00 225.00 260.00
• For standard mix concrete supply prices, Refer
to page 4-142
2008
Precast Concrete
Floor Systems
Page 4-157
8 Precast Concrete
• Prices for precast concrete are based on
reasonable quantities of a repetitive nature.
• Allow extra over rates given below when
numerous mould changes, negative or
expressed edge details, inserts, reduced
tolerances, and small quantities are involved
• Prices include supply, delivery, and labour to
place.
Add extra for tower crane or other crane costs
and propping unless otherwise stated.
2008
Precast Concrete
Beams and Columns
Page 4-158
2008
Precast Concrete
Wall and Cladding Panels
Page 4-159
2008
Precast Concrete
Joints In Concrete
Page 4-160
2008
Reinforcing Steel
Price Increases
Page 4-161
9 Reinforcing Steel
• For reinforcing steel weights, Refer to page 14-649
2008
Reinforcing Steel
Reinforcing Steel by Lengths
Page 4-162
9.5 Accessories
Combination Bar Chair Auck $ Wgtn $ Chch $ Dun $
Bar Chair 25/40 Loose 81044 No 0.35 0.35 0.40 0.35
Bar Chair 50/65 Loose 81045 No 0.35 0.35 0.40 0.35
Bar Chair 75/90 Loose 81047 No 0.40 0.40 0.45 0.40
Bar Chair 85/100 Loose 81049 No 0.50 0.50 0.55 0.50
Gross Number
PCP Concrete Spacer Blocks, supply only weight per drum $ per drum $ per each
25/35mm standard square block 250kg 1,900 445.00 0.25
35/40mm standard tapered block 250kg 1,400 435.00 0.30
40/50mm standard tapered block 250kg 1,025 430.00 0.40
60/75mm standard tapered block 250kg 440 345.00 0.80
100mm standard tapered block 250kg 280 350.00 0.90
2008
Structural Steelwork
Material Supply Prices
Page 4-163
Unit Ak/Wn/Ch/Dn $
10 Structural Steelwork
• For weights of structural steel, Refer to page 14-645
2008
Structural Steelwork
Supply and Erect
Page 4-164
Unit Ak/Wn/Ch/Dn $
2008
Structural Steelwork
HERA Costing, Connections
Page 4-165
Unit Ak/Wn/Ch/Dn $
Plate Connections, Stiffeners, Brackets
Base plates kg 6.00 - 14.50
Connection plates kg 5.70 - 20.00
Purlin cleats kg 11.25 - 24.00
Stiffeners and gussets kg 8.60 - 17.50
Brackets kg 8.00 - 26.00
2008
Structural Steelwork
HERA Costing, Connections
Page 4-166
Unit Ak/Wn/Ch/Dn $
WM Welded Moment
250 UB 31 No 200.00 - 200.00
410 UB 54 No 260.00 - 285.00
610 UB 101 No 370.00 - 370.00
200 UC 46 No 250.00 - 250.00
310 UC 97 No 355.00 - 355.00
310 UC 158 No 495.00 - 495.00
MEP Moment End Plate
250 UB 31 No 290.00 - 330.00
410 UB 54 No 385.00 - 440.00
610 UB 101 No 600.00 - 890.00
310 UC 97 No 655.00 - 900.00
310 UC 158 No 1,030.00 - 1,030.00
MEPS-G Moment End Plate Gussetted
250 UB 31 No 340.00 - 380.00
410 UB 54 No 420.00 - 550.00
610 UB 101 No 700.00 - 1,170.00
310 UC 97 No 695.00 - 985.00
310 UC 158 No 1,115.00 - 1,115.00
MEPS-F Moment End Plate Splice—Flush
250 UB 31 No 490.00 - 510.00
410 UB 54 No 650.00 - 890.00
610 UB 101 No 980.00 - 1,415.00
200 UC 46 No 585.00 - 585.00
310 UC 97 No 920.00 - 920.00
310 UC 158 No 1,355.00 - 1,355.00
MEPS Moment End Plate Splice
250 UB 31 No 520.00 - 550.00
410 UB 54 No 680.00 - 750.00
610 UB 101 No 1,020.00 - 1,440.00
310 UC 97 No 980.00 - 1,415.00
310 UC 158 No 1,360.00 - 1,680.00
MEPS-G Moment End Plate Splice—Gussetted
250 UB 31 No 595.00 - 665.00
410 UB 54 No 765.00 - 965.00
610 UB 101 No 1,090.00 - 1,470.00
310 UC 97 No 1,060.00 - 1,660.00
310 UC 158 No 1,610.00 - 1,925.00
BWBS Bolted Welded Beam Splice
250 UB 31 No 375.00 - 375.00
410 UB 54 No 410.00 - 480.00
610 UB 101 No 535.00 - 875.00
Detailed Rates
2008
Structural Steelwork
HERA Costing, Connections
Page 4-167
Unit Ak/Wn/Ch/Dn $
BCS Bolted Compression Splice
250 UB 31 No 350.00 - 355.00
410 UB 54 No 410.00 - 420.00
610 UB 101 No 575.00 - 740.00
200 UC 46 No 395.00 - 395.00
310 UC 97 No 490.00 - 545.00
310 UC 158 No 595.00 - 620.00
BTS Bolted Tension Splice
250 UB 31 No 400.00 - 415.00
410 UB 54 No 485.00 - 660.00
610 UB 101 No 655.00 - 870.00
200 UC 46 No 445.00 - 645.00
310 UC 97 No 540.00 - 860.00
310 UC 158 No 620.00 - 1,295.00
BPP Base Plate Pinned
250 UB 31 No 165.00 - 185.00
410 UB 54 No 210.00 - 265.00
610 UB 101 No 270.00 - 495.00
200 UC 46 No 175.00 - 220.00
310 UC 97 No 245.00 - 425.00
310 UC 158 No 265.00 - 570.00
EC End Cut
250 UB 31 No 43.00 - 47.00
410 UB 54 No 48.00 - 52.00
610 UB 101 No 63.00 - 67.00
200 UC 46 No 48.00 - 52.00
310 UC 97 No 63.00 - 67.00
310 UC 158 No 83.00 - 87.00
ST Stiffeners 6mm
250 UB 31 No 93.00 - 97.00
410 UB 54 No 107.00 - 113.00
610 UB 101 No 131.00 - 139.00
200 UC 46 No 92.00 - 98.00
310 UC 97 No 111.00 - 119.00
310 UC 158 No 111.00 - 119.00
ST Stiffeners 10mm
250 UB 31 No 97.00 - 103.00
410 UB 54 No 116.00 - 124.00
610 UB 101 No 146.00 - 154.00
200 UC 46 No 102.00 - 108.00
310 UC 97 No 131.00 - 139.00
310 UC 158 No 131.00 - 139.00
DNR Duct Notch Reinforced
410 UB 54 No 234.00 - 256.00
610 UB 101 No 257.00 - 283.00
Detailed Rates
2008
Structural Steelwork
Sundries
Page 4-168
Unit Ak/Wn/Ch/Dn $
FB Fly Brace -
250 UB 31 No 38.00 - 42.00
410 UB 54 No 43.00 - 47.00
610 UB 101 No 48.00 - 52.00
PH Pipe Holes
100mm diameter No 5.00 - 7.00
200mm diameter No 9.00 - 13.00
300mm diameter No 15.00 - 19.00
10.7 Sundries
Steel Wedge and Grout under steel with
cement and sand (1:2) well rammed in
25mm thick m2 200.00 - 300.00
50mm thick m2 250.00 - 350.00
Shop Drill Beam Bolt Holes
10 mm thick steel No 5.40 - 8.40
16 mm thick steel No 6.50 - 9.50
25 mm thick steel No 7.50 - 10.50
40 mm thick steel No 9.25 - 12.50
Add extra for site drilling
Shop Fillet Weld
5/6mm m 48.00 - 68.00
8/10mm m 68.00 - 100.00
Add extra for site fillet weld
2008
Structural Steelwork
Bolts
Page 4-169
Unit Ak/Wn/Ch/Dn $
10.9 Bolts
• Prices include nuts and washers
Black Mild Steel Bolt—grade 4.6
12mm dia x 40mm No 5.60
12mm dia x 100mm No 6.60
12mm dia x 150mm No 7.60
16mm dia x 100mm No 8.50
16mm dia x 150mm No 10.50
20mm dia x 100mm No 12.50
20mm dia x 150mm No 15.50
24mm dia x 100mm No 20.00
24mm dia x 150mm No 25.00
Galvanised Mild Steel Bolt—grade 4.6
12mm dia x 40mm No 5.70
12mm dia x 100mm No 6.70
12mm dia x 150mm No 7.70
12mm dia x 200mm No 9.00
16mm dia x 100mm No 9.00
16mm dia x 150mm No 11.00
16mm dia x 200mm No 13.75
16mm dia x 300mm No 17.00
20mm dia x 100mm No 13.00
20mm dia x 150mm No 16.00
20mm dia x 200mm No 19.00
20mm dia x 300mm No 24.00
24mm dia x 100mm No 20.00
24mm dia x 150mm No 25.00
High Strength Steel Friction Grip Bolt—grade
8.8
16mm dia x 50mm No 11.75
20mm dia x 50mm No 13.75
20mm dia x 75mm No 17.75
24mm dia x 50mm No 23.00
24mm dia x 80mm No 25.00
Stainless Steel Bolt—grade 316
12mm dia x 40mm No 9.75
12mm dia x 75mm No 11.50
12mm dia x 100mm No 13.00
16mm dia x 50mm No 18.00
20mm dia x 60mm No 30.00
24mm dia x 100mm No 55.00
Detailed Rates
2008
Structural Steelwork
Welded Concrete Anchors
Page 4-170
Unit Ak/Wn/Ch/Dn $
Galvanised Mild Steel Holding Down Bolt,
including setting in concrete and template
12mm dia x 150mm long No 18.50
16mm dia x 300mm long No 23.00
16mm dia x 400mm long No 27.00
16mm dia x 500mm long No 30.50
20mm dia x 300mm long No 27.25
20mm dia x 400mm long No 32.50
20mm dia x 500mm long No 37.50
24mm dia x 300mm long No 41.50
24mm dia x 400mm long No 51.00
24mm dia x 500mm long No 56.00
Galvanised Mild Steel Holding Down U Bolt,
including setting in concrete and template
16mm dia x 500mm girth No 40.00
16mm dia x 700mm girth No 47.50
16mm dia x 900mm girth No 55.00
20mm dia x 500mm girth No 52.00
20mm dia x 700mm girth No 57.00
20mm dia x 900mm girth No 66.00
24mm dia x 500mm girth No 61.00
24mm dia x 700mm girth No 74.00
24mm dia x 900mm girth No 85.00
Dynabolt anchor including drilling concrete
D10 100 No 7.00 - 8.00
D12 100 No 8.50 - 9.50
D16 150 No 10.50 - 11.50
D20 160 No 12.75 - 13.75
Rag bolt and nut, galvanised, cast in
M10 x 150mm No 6.75
M10 x 250mm No 8.00
M12 x 150mm No 7.25
M12 x 250mm No 9.00
2008
Structural Steelwork
Surface Treatments
Page 4-171
Unit Ak/Wn/Ch/Dn $
2008
Structural Steelwork
Steel Decking
Page 4-172
Unit Ak/Wn/Ch/Dn $
Abrasive Blast and Zinc Metalspray. System tonne 1,250.00 - 1,375.00
ZN175, life 25 to 40 years $/m2—surface area $/m—steel member
150UB14, 0.59m2/m, 14.0kg/m 29.75 - 32.75 17.50 - 19.25
250UB31, 1.06m2/m, 31.4kg/m 37.00 - 40.75 39.25 - 43.25
310UB40, 1.24m2/m, 40.4kg/m 40.75 - 44.75 51.00 - 56.00
410UB54, 1.48m2/m, 53.7kg/m 45.25 - 50.00 67.00 - 74.00
610UB125, 2.09m2/m, 125.0kg/m 75.00 82.00 156.00 - 172.00
Add extra for
One Coat of Colour Gloss, site applied tonne 550.00 - 675.00
Rate does not apply to hot dip galvanised
surfaces, which require degrease, etch
and prime, prior to application of top coat $/m2—surface area $/m—steel member
150UB14, 0.59m2/m, 14.0kg/m 13.00 - 16.00 7.70 9.50
250UB31, 1.06m2/m, 31.4kg/m 16.25 - 20.00 17.25 21.25
310UB40, 1.24m2/m, 40.4kg/m 18.00 - 22.00 22.25 27.25
410UB54, 1.48m2/m, 53.7kg/m 20.00 - 24.50 29.50 36.25
610UB125, 2.09m2/m, 125.0kg/m 33.00 - 40.25 69.00 84.00
Hot Dip Galvanising. System GZ, life 10 to 20 tonne 1,400.00 - 1,750.00
years $/m2—surface area $/m—steel member
150UB14, 0.59m2/m, 14.0kg/m 30.25 - 35.50 17.75 - 21.00
250UB31, 1.06m2/m, 31.4kg/m 37.75 - 44.50 40.00 - 47.00
310UB40, 1.24m2/m, 40.4kg/m 41.50 - 48.75 52.00 - 61.00
410UB54, 1.48m2/m, 53.7kg/m 46.25 - 54.00 68.00 - 81.00
610UB125, 2.09m2/m, 125.0kg/m 76.00 - 90.00 159.00 - 188.00
2008
Waterproofing
Waterproofing Protection
Page 4-173
11 Waterproofing
• Concrete Underlay, Refer to page 4-144
11.2 Tanking—Bentonite
Voltex® Bentonite Geotextile Waterproofing, m2 65.00 65.00 65.00 65.00
comprising 2 geotextile layers filled with sodium
bentonite
Swelltite® Bentonite Composite System, m2 65.00 65.00 65.00 65.00
comprising Volclay® sodium bentonite and butyl
rubber liner
11.4 Tanking—Permaliner™
Flexible Polypropylene Alloy Lining Membrane
Permaliner™ FPA 300 micron m2 13.50 13.50 13.25 13.25
Permaliner™ FPA 500 micron m2 17.00 17.50 16.75 16.75
Permaliner™ FPA 750 micron m2 21.75 21.50 21.50 21.50
Permaliner™ FPA 1000 micron m2 26.50 26.25 26.25 26.25
Detailed Rates
2008
Waterproofing
Waterproofing Membranes
Page 4-174
2008
Brickwork
70mm Brickwork
Page 4-175
12 Brickwork
• Prices are for new work only. For Demolition
and Alterations, Refer to page 4-128
• Prices for brickwork include plumbing angles,
normal straight cutting, openings, weepholes,
etc., raking out or leaving joints for plastering,
all normal bedding, building in ends of lintels
and all other sundry labours.
2008
Brickwork
90mm Brickwork
Page 4-176
2008
Brickwork
Sills, Copings
Page 4-177
12.9 Lintels
Steel Flat Arch Bars, galvanised
80mm x 6mm (3.77 kg/m) m 39.00 39.00 39.00 39.00
80mm x 12mm (7.54 kg/m) m 77.00 77.00 77.00 77.00
Steel Angle Lintel, galvanised
60mm x 60mm x 8mm (7.1 kg/m) m 75.00 75.00 75.00 75.00
80mm x 80mm x 8mm (9.65 kg/m) m 100.00 100.00 100.00 100.00
100mm x 75mm x 10mm (12.4 kg/m) m 128.00 128.00 128.00 128.00
150mm x 100mm x 10mm (18 kg/m) m 185.00 185.00 185.00 185.00
2008
Brickwork
Damp Proof Courses
Page 4-178
2008
Concrete Blockwork
Supply Prices
Page 4-179
13 Concrete Blockwork
• Prices are for new work only.
For alterations, Refer to page 4-128
• A distance of 30 kilometres has been assumed
for cartage of blocks
• Prices for blockwork include plumbing angles,
normal straight cutting, forming reveals,
openings, weepholes, etc., fractional corner
and end blocks, raking out or leaving joints for
plastering, all normal bedding, building in ends
of lintels and all other sundry labours.
2008
Concrete Blockwork
Labours on Blockwork
Page 4-180
2008
Masonry
Marble Facing
Page 4-181
14 Masonry
• Prices are for new work only. For Demolition
and Alterations, Refer to page 4-128
• Prices are based on quantities of more than
100m2. Prices include fixing, bedding,
pointing, ties, cramps, dowels, cutting to size
and setting out, but exclude making good to
unprepared surfaces.
• $Value/m2 given is indicative value for material
to be supplied. Adjust rates as necessary if
more or less expensive product to be used.
2008
Masonry
Granite Facing
Page 4-182
2008
Masonry
Slate
Page 4-183
14.5 Slate
Paving Tiles, 300mm x 300mm, laid in mortar
bed on concrete floor, 12mm nominal thickness
Low cost ($30/m2) m2 90.00 90.00 90.00 90.00
Medium cost ($45/m2) m2 105.00 105.00 105.00 105.00
High cost ($65/m2) m2 125.00 125.00 125.00 125.00
Add extra for
Laying as skirting or stair treads and risers Plus +50% +50% +50% +50%
Laying on timber floor including m2 10.00 10.00 10.00 10.00
separation membrane
Washing down with acid, and drying m2 5.00 5.00 5.00 5.00
Sealing m2 14.00 14.00 14.00 14.00
14.6 Schist
Alexandra ‘Crawford Hills Stone’ Schist
Veneer work m2 350.00 350.00 320.00 320.00
Paving work m2 230.00 230.00 200.00 200.00
Waitaha Schist veneer work m2 375.00 375.00 355.00 355.00
Alpine Schist
Veneer work m2 375.00 375.00 355.00 355.00
Paving work m2 180.00 180.00 180.00 180.00
2008
Masonry
Moss Rock
Page 4-184
14.12 Terrazzo
Terrazzo Tiles, in mortar bed on concrete floor
including grouting and polishing
300mm x 300mm x 25mm m2 130.00 130.00 130.00 130.00
-150.00 -150.00 -150.00 -150.00
400mm x 400mm x 35mm m2 150.00 150.00 150.00 150.00
-170.00 -170.00 -170.00 -170.00
Precast Terrazzo Closed Tread Type stair
tread and riser unit, 320mm x 170mm high x
50mm thick, fixed to steel framing
1000mm wide No 300.00 300.00 300.00 300.00
1200mm wide No 355.00 355.00 355.00 355.00
1500mm wide No 445.00 445.00 445.00 445.00
1800mm wide No 535.00 535.00 535.00 535.00
Precast Terrazzo Open Tread Type stair tread,
300mm tread x 50mm thick, fixed to steel
framing
1000mm wide No 175.00 175.00 175.00 175.00
1200mm wide No 210.00 210.00 210.00 210.00
1500mm wide No 260.00 260.00 260.00 260.00
1800mm wide No 305.00 305.00 305.00 305.00
Detailed Rates
2008
Metalwork
Material Supply Prices
Page 4-185
15 Metalwork
15.1 Material Supply Prices
• Prices are based on average trade prices and exclude G.S.T.
• At the time these figures were prepared, the following factors applied. $NZ1 = $US0.7040.
• London Metal Exchange Daily Metals prices: Copper $US7,500; Aluminium $US2,950
Bars, Tubes, Angles, Size kg/m $/m Bars, Tubes, Angles, Size kg/m $/m
Aluminium Stainless Steel
Equal Angles Equal Angles
19mm x 19mm x 3.0mm 0.285 4.90 20mm x 20mm x 3mm 0.91 13.75
25mm x 25mm x 3.0mm 0.381 7.30 25mm x 25mm x 3mm 1.15 17.50
32mm x 32mm x 3.0mm 0.494 9.50 40mm x 40mm x 3mm 1.88 28.50
40mm x 40mm x 3.0mm 0.624 10.75 50mm x 50mm x 5mm 3.87 59.00
50mm x 50mm x 3.0mm 0.786 13.50 Type 304 Flat Bar
Unequal Angles 25mm x 6mm 1.18 18.00
38mm x 25mm x 3.0mm 0.486 8.30 40mm x 9mm 2.90 44.00
65mm x 25mm x 3.0mm 0.726 12.50 50mm x 12mm 4.71 77.00
Square Tube 75mm x 12mm 7.14 107.00
25mm x 25mm x 1.8mm 0.443 7.80 Type 304 Tube, Polished
40mm x 40mm x 2mm 0.797 13.75 19mm dia x 1.2mm 0.539 15.00
51mm x 51mm x 3.25mm 1.619 26.25 25.4mm dia x 1.2mm 0.731 14.25
Round Tube 31.8mm dia x 1.2mm 0.925 18.00
25mm O/D x 3mm 0.560 9.60 38mm dia x 1.2mm 1.110 21.75
31.7mm O/D x 3mm 0.713 14.25 51mm dia x 1.2mm 1.499 29.50
38.1mm O/D x 3mm 0.888 15.25 Type 304 Square Tube, Polished
44.5mm O/D x 3mm 1.055 18.00 19.05mm x 1.2mm 0.691 14.75
Flat Bar 25.4mm x 1.2mm 0.933 18.50
25mm x 3mm 0.203 3.90 32mm x 1.2mm 1.185 25.00
38mm x 4.5mm 0.461 7.90 38.1mm x 1.2mm 1.425 28.50
25mm x 6mm 0.405 7.80
50mm x 6mm 0.810 14.00 Brass
100mm x 6mm 1.620 27.75 Flat Bar
50mm x 10mm 1.350 23.25 25.4mm x 3.18mm 0.68 13.25
75mm x 12mm 2.430 41.75 38.1mm x 3.18mm 1.02 20.00
Solid Square 50.8mm x 3.18mm 1.37 27.00
9.53mm 0.243 5.40 25.4mm x 4.76mm 1.02
25.4mm 1.741 29.75 38.1mm x 4.76mm 1.54
Solid Round 50.8mm x 4.76mm 2.05 30.00
12.7mm dia 0.342 5.40 25.4mm x 6.35mm 1.36 19.75
19.05mm dia 0.770 11.00 38.1mm x 6.35mm 2.04
25.4mm dia 1.366 19.50 50.8mm x 6.35mm 2.72
Channels Equal Angles
25mm x 25mm x 3mm 0.559 10.75 19mm x 19mm x 3.18mm 0.94 13.75
32mm x 25mm x 3mm 0.618 11.75 25mm x 25mm x 3.18mm 1.30
40mm x 20mm x 3mm 0.599 10.25 38mm x 38mm x 3.18mm 1.97
50mm x 25mm x 3mm 0.761 13.00 51mm x 51mm x 6.35mm 2.65 39.00
Detailed Rates
2008
Metalwork
Material Supply Prices
Page 4-186
Copper Lead
2400mm x 1000mm sheet 20kg/m2
0.55mm thick 235.00 150mm wide 51.00
0.70mm thick 365.00 300mm wide 102.00
0.90mm thick 455.00 450mm wide 153.00
1.20mm thick 610.00 600mm wide 205.00
1.50mm thick 760.00 900mm wide 305.00
2.00mm thick 955.00 15kg/m2
150mm wide 45.00
Stainless Steel 300mm wide 87.00
304 2B, 2400mm x 900mm sheet 450mm wide 130.00
0.5mm thick 600mm wide 175.00
0.55mm thick 255.00 Per kilogram 18.00
304 2B, 2400mm x 1200mm sheet
0.45mm thick
0.55mm thick 335.00
Brass
2000mm x 1000mm sheet
1.5mm thick 415.00
Detailed Rates
2008
Metalwork
Aluminium Trim
Page 4-187
Unit Ak/Wn/Ch/Dn $
15.4 Awnings
• Prices include brackets and support framing
Canvas Awnings, Fixed Type
First m2 of area m2 380.00 - 430.00
Subsequent area m2 255.00 - 290.00
Canvas Awnings, Roll-Up Type
First m2 of area m2 320.00 - 360.00
Subsequent area m2 132.00 - 150.00
2008
Metalwork
Balustrades
Page 4-188
Unit Ak/Wn/Ch/Dn $
15.6 Balustrades
Tubular Balustrade, 1000mm high, posts at
1200mm centres, fixed to timber or concrete
deck
Galvanized Steel, with 80mm dia posts, m 330.00 - 480.00
50mm dia top rail, flat bottom rail and
balusters at maximum 100mm crs
Add extra for painting, Refer to page 4-407
Stainless Steel, 1000mm high, 50mm dia m 375.00 - 450.00
posts, 50mm dia top rail, 50mm dia middle
rails
Stainless Steel, 1000mm high, 50mm dia m 330.00 - 400.00
posts, 50mm dia top rail, vertical stainless
steel wire rigging, including eyes and
turnbuckles
Polished Brass, Modular, 50mm dia m 500.00 - 650.00
posts, toughened glass infill
Add extra for lacquer finish Add +15%
Aluminium Balustrade, 1000mm high with
handrail, bottom rail, rectangular newel posts at
1800mm centres, fixed to timber or concrete
deck, with
Tubular balusters at 115mm centres
Mill finish m 265.00 - 350.00
Powder coated m 290.00 - 370.00
Toughened glass infill
Mill finish m 300.00 - 370.00
Powder coated m 320.00 - 395.00
Ornamental cast aluminium infill
Mill finish m 400.00 - 530.00
Powder coated m 425.00 - 530.00
Aluminium Balustrade, 1000mm high with
handrail, bottom rail, rectangular newel posts at
1600mm centres, perforated aluminium infill,
fixed to timber or concrete deck
Mill finish m 350.00 - 425.00
Powder coated m 380.00 - 450.00
Detailed Rates
2008
Metalwork
Handrails
Page 4-189
Unit Ak/Wn/Ch/Dn $
15.7 Handrails
• Prices include ramps and bends
50mm x 10mm Flat Steel Handrail, including
brackets at 1200mm centres fixed to wall
Zinc chromate primed m 90.00 - 110.00
Galvanised m 100.00 - 120.00
Tubular Handrail, including brackets at
2000mm centres fixed to wall
Galvanised Steel, 50mm dia pipe m 115.00 - 125.00
Stainless Steel, 50mm dia pipe m 150.00 - 180.00
Aluminium, 45mm dia tube, powder m 105.00 - 115.00
coated
Polished Brass, Modular, 50mm dia m 200.00 - 225.00
tube
Add extra for lacquer finish
15.8 Stairs
• Rates are for light construction, for heavy duty
stairs Refer to page 4-164
Straight Single Flight of Steel Stairs No 10,750.00 - 12,750.00
1000mm wide with steel plate treads and
risers, on steel stringers and supports to
rise 3000mm.
1,100 kg per 3m flight
Add extra for mid level landing, 5mm plate, No 1,925.00 - 2,325.00
approx 200kg
Spiral Staircase No 8,000.00 - 10,500.00
1500mm dia with steel treads to rise
3000mm, simple balustrade with plastic
covered handrail
2008
Metalwork
Cladding
Page 4-190
Unit Ak/Wn/Ch/Dn $
15.11 Cladding
Sheetmetal Cladding, fixed to framing
Galvanised steel sheet
0.75mm thick m2 80.00 - 90.00
0.95mm thick m2 85.00 - 95.00
Aluminium sheet, 1.6mm thick m2 110.00 - 120.00
Stainless steel sheet, Type 304, 0.9mm thick m2 175.00 - 185.00
Add extra for baked enamel finish
Perforated Aluminium Cladding, fixed to steel
frame (frame not included) as balustrade,
sunscreen, partition etc.
1.2mm thick m2 140.00 - 160.00
1.6mm thick m2 160.00 - 180.00
2mm thick m2 200.00 - 225.00
3mm thick m2 250.00 - 300.00
15.13 Flagpoles
Tapered Mill Finish Aluminium Flagpole, complete
with halyards, pulleys and nylon cleats
Wall or parapet mounted, including brackets
4m x 60mm dia No 735.00 - 815.00
5m x 75mm dia No 860.00 - 960.00
6m x 90mm dia No 1,045.00 - 1,150.00
Vertical freestanding, including base plate
5m x 75mm dia No 1,035.00 - 1,140.00
7.5m x 100mm dia No 1,380.00 - 1,800.00
12m x 125mm dia No 2,300.00 - 3,000.00
Detailed Rates
2008
Metalwork
Lockers
Page 4-191
Unit Ak/Wn/Ch/Dn $
Add extra for
Hideaway halyard system No 380.00 - 420.00
Hinged base plate No 98.00 - 126.00
Concrete base No 195.00 - 265.00
Anti-slap device No 52.00
Powder coating or anodising m 31.00
• Fencing, Refer to page 4-427
15.14 Lockers
Single Tier Locker, size 300mm wide x 450mm
x 1800mm high, with baked enamel finish,
keylocking type, assembled
Initial unit No 230.00 - 250.00
Add on unit No 200.00 - 220.00
Two Tier Locker, ditto
Initial unit No 275.00 - 300.00
Add on unit No 245.00 - 270.00
Four Tier Locker, ditto
Initial unit No 320.00 - 350.00
Add on unit No 295.00 - 325.00
Add extra for
Three point locking system to single tier No 40.25 - 54.00
lockers only
15.15 Ladders
Ladder, 450mm wide, comprising 50mm x 6mm
steel strings and 16mm dia bar rungs
Zinc chromate primed m 100.00 - 125.00
Galvanised m 110.00 - 140.00
2008
Carpentry
Damp Proof Courses
Page 4-192
16 Carpentry
• All linings are fixed to timber framing, unless
stated otherwise.
• Prices are for new work only. For Alterations and
Demolition, Refer to page 4-128.
• References in subheadings, eg, T6.3 or C6.8.3, are
to Tables and Clauses in NZS3604:1999, including
Amendment 2. Sizes given are generally those
nominated in NZS 3604.
• ‘100mm x 50mm/90mm x 45mm’ indicates
‘usual naming convention/new naming convention’
Abbreviations commonly used in this section
Framing/Finishing Timber
D Fir = Douglas Fir PG = Planer Gauged
FJ = Finger Jointed PP = Pre-Primed
KD = Kiln Dried RP = Radiata Pine
MSG8= Machine Stress Graded 8
Board Products
MDF = Medium Density Fibreboard MUF =Melamine Urea Formaldehyde
2008
Carpentry
Framing–SubFloor, H3.2
Page 4-193
2008
Carpentry
Framing–Wall, H1.2, KD, MSG8
Page 4-194
2008
Carpentry
Framing–Roof, H1.2, KD, MSG8
Page 4-195
2008
Carpentry
Framing–General, H3.2
Page 4-196
2008
Carpentry
Framing–External Steps, H3.2
Page 4-197
2008
Carpentry
Fixings
Page 4-198
16.14 Fixings
• Fixings to brick, block, concrete or steel
Drill and Plug for screw fixing
6.5 x 50mm nylon anchor round head No 2.80 2.65 2.65 2.65
6.5 x 56mm sleeve anchor hex head No 3.05 2.95 2.95 2.95
8 x 85mm sleeve anchor hex head No 4.50 4.35 4.35 4.35
Shot Fix 50mm timber No 1.35 1.30 1.30 1.30
Z Nails or wire dogs
Galvanised No 1.30 1.25 1.25 1.25
Stainless steel No 3.10 3.05 3.05 3.05
Galvanised Coach Bolt, with nut and washers,
including drilling timber
8mm x 100mm No 3.30 3.20 3.20 3.20
10mm x 100mm No 3.55 3.45 3.45 3.45
12mm x 100mm No 4.70 4.60 4.60 4.60
12mm x 150mm No 6.00 5.90 5.90 5.90
16mm x 100mm No 10.25 10.00 10.00 10.00
16mm x 150mm No 10.50 10.50 10.50 10.50
Galvanised Bolt and Terrier Insert, to fix 50mm
timber, including drilling concrete or blockwork
8mm x 85mm No 11.00 10.50 10.50 10.50
10mm x 102mm No 13.00 12.50 12.50 12.50
12mm x 129mm No 15.25 14.75 14.75 14.75
16mm x 147mm No 17.00 16.50 16.50 16.50
Tylok Nail Plates
2T5, 34mm x 60mm No 1.70 1.60 1.60 1.60
4T5, 34mm x 120mm No 1.90 1.85 1.85 1.85
8T5, 34mm x 240mm No 3.50 3.40 3.40 3.40
12T5, 34mm x 360mm No 4.95 4.80 4.80 4.80
4T10, 68mm x 120mm No 3.50 3.40 3.40 3.40
6T10, 68mm x 180mm No 4.00 3.90 3.90 3.90
10T10, 68mm x 300mm No 5.90 5.80 5.80 5.80
12T10, 68mm x 360mm No 6.60 6.40 6.40 6.40
16T10, 68mm x 460mm No 7.70 7.50 7.50 7.50
4T15, 102mm x 120mm No 4.00 3.90 3.90 3.90
6T15, 102mm x 180mm No 4.85 4.75 4.75 4.75
8T15, 102mm x 240mm No 5.60 5.50 5.50 5.50
10T15, 102mm x 300mm No 7.70 7.50 7.50 7.50
6T20, 136mm x 180mm No 6.60 6.40 6.40 6.40
8T20, 136mm x 240mm No 7.70 7.50 7.50 7.50
10T20, 136mm x 300mm No 8.80 8.60 8.60 8.60
Lumberlok Joist Hanger, galvanised
47mm x 90mm No 4.70 4.60 4.60 4.60
47mm x 120mm No 5.00 4.90 4.90 4.90
47mm x 190mm No 6.20 6.10 6.10 6.10
70mm x 180mm No 8.70 8.60 8.60 8.60
95mm x 165mm No 8.70 8.60 8.60 8.60
Detailed Rates
2008
Carpentry
Fixings
Page 4-199
2008
Carpentry
Trusses–Residential
Page 4-200
16.15 Trusses–Residential
• Prices are for supply and installation of
standard pre-fabricated trusses only.
• For specifically designed trusses, refer to a
local manufacturer or supplier
Truss for light weight roof, in gauged timber,
22° pitch, 600mm overhang each side.
6000mm span No 180.00 155.00 150.00 163.00
7000mm span No 200.00 165.00 165.00 180.00
8000mm span with mid support No 215.00 180.00 180.00 195.00
9000mm span with mid support No 290.00 240.00 260.00 265.00
10000mm span with mid support No 310.00 260.00 275.00 285.00
Truss for heavy weight roof, in gauged timber,
22° pitch, 600mm overhang each side.
6000mm span No 180.00 155.00 150.00 163.00
7000mm span No 200.00 165.00 165.00 180.00
8000mm span with mid support No 215.00 180.00 180.00 195.00
9000mm span with mid support No 290.00 240.00 260.00 265.00
10000mm span with mid support No 310.00 260.00 275.00 285.00
Attic roof truss for light weight roof, in
gauged timber, 45° pitch, 200mm overhang
each side. Internal ceiling height 2450mm.
3600mm wide internal room space
6000mm span No 305.00 305.00 305.00 305.00
7000mm span with mid support No 335.00 335.00 335.00 335.00
8000mm span with mid support No 365.00 365.00 365.00 365.00
4800mm wide internal room space
6000mm span No 330.00 330.00 330.00 330.00
7000mm span with mid support No 350.00 350.00 350.00 350.00
8000mm span with mid support No 445.00 445.00 445.00 445.00
Attic roof truss for heavy weight roof, in
gauged timber, 45° pitch, 200mm overhang
each side. Internal ceiling height 2450mm.
3600mm wide internal room space
6000mm span No 305.00 305.00 305.00 305.00
7000mm span with mid support No 335.00 335.00 335.00 335.00
8000mm span with mid support No 365.00 365.00 365.00 365.00
4800mm wide internal room space
6000mm span No 330.00 330.00 330.00 330.00
7000mm span with mid support No 350.00 350.00 350.00 350.00
8000mm span with mid support No 445.00 445.00 445.00 445.00
2008
Carpentry
Beams–Posi-Strut Trusses
Page 4-201
16.18 Beams–Twinaplate®
Composite Timber and Steel Beams
240mm x 67mm m 20.75 20.50 20.50 20.50
290mm x 67mm m 21.50 21.25 21.25 21.25
340mm x 67mm m 22.00 21.75 21.75 21.75
390mm x 67mm m 23.00 22.50 22.50 22.50
440mm x 67mm m 23.50 23.25 23.25 23.25
240mm x 92mm m 22.25 21.75 21.75 21.75
290mm x 92mm m 23.00 22.75 22.75 22.75
340mm x 92mm m 24.00 23.50 23.50 23.50
390mm x 92mm m 24.75 24.50 24.50 24.50
440mm x 92mm m 25.50 25.25 25.25 25.25
240mm x 140mm m 31.75 31.25 31.25 31.25
290mm x 140mm m 33.25 33.00 33.00 33.00
340mm x 140mm m 35.00 34.75 34.75 34.75
390mm x 140mm m 36.75 36.50 36.50 36.50
440mm x 140mm m 38.50 38.25 38.25 38.25
Composite Timber and Steel Beams, double
(laminated) chord
330mm x 92mm m 35.00 34.50 34.50 34.50
380mm x 92mm m 35.75 35.50 35.50 35.50
430mm x 92mm m 36.75 36.25 36.25 36.25
480mm x 92mm m 37.50 37.25 37.25 37.25
530mm x 92mm m 38.25 38.00 38.00 38.00
330mm x 140mm m 49.75 49.25 49.25 49.25
380mm x 140mm m 51.00 51.00 51.00 51.00
430mm x 140mm m 53.00 53.00 53.00 53.00
480mm x 140mm m 55.00 54.00 54.00 54.00
530mm x 140mm m 57.00 56.00 56.00 56.00
Add extra for joist hangers
TW67 No 3.45 3.45 3.45 3.45
TW92 No 3.75 3.75 3.75 3.75
TW140 No 4.10 4.10 4.10 4.10
Angle Cutting No 7.00 7.00 7.00 7.00
Detailed Rates
2008
Carpentry
Beams–LVL
Page 4-202
16.19 Beams–LVL
Hyspan® LVL beams—laminated veneer
lumber
150mm x 45mm, H3 m 32.75 32.50 32.50 32.50
170mm x 45mm, H3 m 37.00 36.50 36.50 36.50
240mm x 45mm, H3 m 50.00 49.50 49.50 49.50
300mm x 45mm, H3 m 62.00 61.00 61.00 61.00
360mm x 45mm, H3 m 72.00 72.00 72.00 72.00
200mm x 63mm, H3 m 57.00 57.00 57.00 57.00
360mm x 63mm, H3 m 99.00 98.00 98.00 98.00
450mm x 63mm, H3 m 122.00 121.00 121.00 121.00
600mm x 63mm, H3 m 140.00 139.00 139.00 139.00
150mm x 45mm, untreated m 27.25 27.00 27.00 27.00
240mm x 45mm, untreated m 41.00 40.75 40.75 40.75
300mm x 45mm, untreated m 50.00 50.00 50.00 50.00
For LVL Portal Frames, Refer to page 4-242
2008
Carpentry
Insulation–Polystyrene Sheet
Page 4-203
16.25 Insulation–Polyester
GreenStuf® polyester insulation between framing
R1.8 to walls m2 15.00 14.75 14.75 14.75
R2.2 to walls m2 18.25 18.00 18.00 18.00
R1.8 to ceilings m2 15.75 15.50 15.50 15.50
R2.2 to ceilings m2 18.25 18.00 18.00 18.00
R2.5 to ceilings m2 20.00 19.75 19.75 19.75
®
QuietStuf polyester insulation between framing
30mm m2 7.10 7.00 7.00 7.00
50mm m2 8.60 8.50 8.50 8.50
60mm m2 12.00 11.75 11.75 11.75
70mm m2 14.00 13.75 13.75 13.75
Baffle Block®, stacked 1m high and 600mm m 81.00 80.00 80.00 80.00
wide, for acoustic baffling above partition walls
Baffle Block®, 1 layer m2 16.00 16.00 16.00 16.00
®
GreenStuf Underfloor, fitted between floor joists
450 wide m2 14.50 14.25 14.25 14.25
600 wide m2 14.50 14.25 14.25 14.25
GreenStuf® Blanket
R2.5, laid over purlins m2 19.00 18.75 18.75 18.75
R3.0, laid over purlins m2 22.75 22.75 22.75 22.75
R3.2, laid over purlins m2 23.75 23.50 23.50 23.50
Detailed Rates
2008
Carpentry
Insulation–Fibreglass
Page 4-204
16.26 Insulation–Fibreglass
Bradford Comfortseal, between ceiling joists
R 2.2 m2 15.25 15.00 15.00 15.00
R 2.7 m2 17.25 17.00 17.00 17.00
R 3.2 m2 21.75 21.50 21.50 21.50
R 3.6 m2 24.75 24.50 24.50 24.50
R 4.0 m2 28.25 28.00 28.00 28.00
R 5.0 m2 46.00 46.00 46.00 46.00
Pink Batts®, fitted between ceiling joists
®
2008
Carpentry
Flooring–Particle Board
Page 4-205
16.29 Flooring–Plywood
Plywood Flooring Panels, H3, with tongued
and grooved edges fixed to timber joists
17mm thick m2 62.00 61.00 61.00 61.00
19mm thick m2 64.00 64.00 64.00 64.00
19mm thick, longspan m2 64.00 63.00 63.00 63.00
21mm thick m2 72.00 72.00 72.00 72.00
16.30 Flooring–Decking
Grip Tread Radiata Pine, H3 treated
100mm x 25mm, merchant grade m2 63.00 61.00 58.00 61.00
100mm x 25mm, premium m2 81.00 79.00 75.00 76.00
100mm x 40mm, merchant grade m2 71.00 69.00 70.00 71.00
100mm x 40mm, premium m2 84.00 82.00 83.00 84.00
Kwila hardwood, 100mm x 25mm m2 106.00 104.00 104.00 104.00
Balau hardwood, 100mm x 25mm m2 92.00 90.00 110.00 104.00
Fibre cement board, screw fixed, with 10mm x
9mm strip of Fosroc Silaflex sealant
9mm thick Titan® m2 76.00 76.00 77.00 78.00
18mm thick Hardipanel™ Compressed m2 147.00 150.00 153.00 156.00
Detailed Rates
2008
Carpentry
Flooring–Decorative Timber
Page 4-206
2008
Carpentry
Flooring–Sanding and Sealing
Page 4-207
2008
Carpentry
Cladding–TER Rainscreen Components
Page 4-208
2008
Carpentry
Cladding–Titan CLD Components
Page 4-209
2008
Carpentry
Cladding–Titan Facade Panel
Page 4-210
2008
Carpentry
Cladding–Titan Facade Panel
Page 4-211
2008
Carpentry
Cladding–Exotec® Facade Panel
Page 4-212
2008
Carpentry
Cladding–Cavities
Page 4-213
16.38 Cladding–Cavities
• General note for the avoidance of doubt. Some
cladding solutions have cavities specifically
detailed in the rate buildup.
• In all other cases, add for forming of cavities
where required.
• For m2 rates for forming cavities See page 4-
197.
Detailed Rates
2008
Carpentry
Cladding–Titan/CLD Facade Panel
Page 4-214
2008
Carpentry
Cladding–Fibre Cement, Monotek
Page 4-215
Fibre Cement
James Hardie Weatherboards, including back
soakers and sealant
150mm summit m2 92.00 92.00 95.00 95.00
180mm smooth m2 84.00 83.00 86.00 86.00
205mm colonial m2 87.00 88.00 92.00 92.00
205mm rusticated m2 87.00 88.00 92.00 92.00
205mm styleline m2 87.00 88.00 92.00 92.00
240mm smooth m2 74.00 74.00 79.00 79.00
245mm woodgrain m2 74.00 74.00 78.00 78.00
305mm smooth m2 72.00 72.00 74.00 74.00
310mm woodgrain m2 73.00 71.00 75.00 75.00
External Angles
PVC box m 11.25 11.00 11.00 11.00
Aluminium box m 21.75 21.75 21.75 21.75
Timber, H4 40mm x 40mm mould m 6.90 6.60 6.60 6.60
Galvanised soakers, 180mm board m 24.50 22.75 24.50 24.50
Galvanised soakers, 245/310mm board m 18.75 17.50 18.75 18.75
Internal Angle, PVC, W shape m 7.70 7.60 7.60 7.60
James Hardie Linea Weatherboards, including
sealant at joints. Labour—1.50hrs/m2
135 Linea Classic Smooth m2 130.00 129.00 133.00 133.00
180 Linea Classic Smooth m2 127.00 126.00 127.00 127.00
180 Linea Classic Reeded m2 128.00 127.00 131.00 131.00
Linea accessories
Corner soaker,135mm, aluminium m 30.75 28.50 30.75 30.75
Corner soaker,150mm, aluminium m 26.75 26.75 26.75 26.75
Corner soaker,180mm, aluminium m 24.50 22.50 24.50 24.50
Corner soaker,180mm, stainless steel m 25.50 25.50 25.50 25.50
Box corner, aluminium slim line m 35.50 35.25 35.25 35.25
Internal corner, W-section, aluminium m 28.25 28.00 28.00 28.00
Detailed Rates
2008
Carpentry
PVC/uPVC
Page 4-216
PVC/uPVC
Palliside PVC Weatherboards, rusticated or m2 133.00 126.00 130.00 130.00
bevel back, white or coloured, including PVC
mouldings and trim
Masada uPVC Weatherboards, rusticated m2 117.00 120.00 - -
profile, white or coloured, including PVC
mouldings and trim
Timber
Rusticated or Bevel back Profiles, fixed to
timber framing
RP, H3, pre-primed
150mm x 25mm, FJ m2 142.00 140.00 134.00 132.00
200mm x 25mm, FJ m2 136.00 129.00 128.00 42.25
Cedar, bandsawn, silicone bronze nails
150mm x 25mm HP67 m2 180.00 178.00 178.00 178.00
200mm x 25mm HP68 m2 168.00 166.00 166.00 166.00
Vertical Shiplap Profile, bandsawn, cedar No 2
Clears, fixed to timber framing
150mm x 25mm m2 180.00 178.00 178.00 178.00
200mm x 25mm m2 168.00 166.00 166.00 166.00
Vertical Board, 200mm x 25mm, and 50mm x m2 200.00 199.00 205.00 199.00
25mm battens to joints, cedar No 2 Clears
40mm x 40mm cedar external corner HP40 m 21.00 20.75 20.75 20.75
25mm x 9.5mm cedar plug to rusticated profile m 12.00 11.75 11.75 11.75
Add extra for diagonal fixing Add + 15% + 15% + 15% + 15%
Aluminium
Nu-Wall Aluminium, standard powdercoat
finish, includes aluminium mouldings
Classique and Shiplap profiles m2 180.00 180.00 180.00 180.00
Ripple 150 and Aero 70 profiles m2 178.00 178.00 178.00 178.00
Aero 115 profile m2 181.00 181.00 181.00 181.00
Louvre 60 profile m2 186.00 186.00 186.00 186.00
Ullos ridged profile m2 192.00 192.00 192.00 192.00
Nu-Wall Aluminium, premium powdercoat
finish, includes aluminium mouldings
Classique and Shiplap profiles m2 191.00 191.00 191.00 191.00
Ripple 150 and Aero 70 profiles m2 189.00 189.00 189.00 189.00
Aero 115 profile m2 193.00 193.00 193.00 193.00
Louvre 60 profile m2 198.00 198.00 198.00 198.00
Ullos ridged profile m2 205.00 205.00 205.00 205.00
Detailed Rates
2008
Carpentry
Cladding–Boarding and Sarking
Page 4-217
2008
Carpentry
Lining–MDF
Page 4-218
16.47 Lining–MDF
Medium Density Fibreboard fixed to timber
framing
3mm thick m2 17.75 17.00 17.00 17.00
4.75mm thick m2 20.25 19.75 19.75 19.75
6mm thick m2 23.25 22.50 22.50 22.50
9mm thick m2 27.75 26.75 26.75 26.75
12mm thick m2 31.50 30.25 29.00 29.00
16mm thick m2 33.75 32.50 31.75 31.75
18mm thick m2 36.00 34.75 33.75 33.75
25mm thick m2 49.50 47.75 45.75 45.75
16.48 Lining–Hardboard
Hardboard, standard
3mm thick m2 22.00 21.50 22.25 22.25
4.75mm thick m2 24.75 24.00 25.50 25.50
6mm thick m2 30.25 30.25 30.50 30.50
Hardboard, pegboard
4.75mm thick m2 32.25 32.25 31.50 31.50
Hardboard, tempered
4.75mm thick m2 35.25 34.00 33.50 33.50
16.49 Lining–Softboard
Flameguard 12mm thick m2 24.50 24.25 24.75 24.75
Hessian Covered Soft Board, 12mm thick, m2 51.00 50.00 50.00 50.00
wrapped 4 edges
2008
Carpentry
Lining–Soffit
Page 4-219
16.51 Lining–Soffit
Hardiflex Soffit Linings, 4.5mm thick, including m2 44.00 43.50 44.00 44.50
PVC mouldings to sheet joints
450mm wide m 18.25 18.25 18.50 18.50
600mm wide m 24.50 24.00 24.75 24.75
750mm wide m 30.50 30.00 31.00 31.00
Villaboard, 6mm thick, with tapered edges m2 41.25 41.00 41.75 42.50
ready for flushing
Eclipsa Prefinished Soffit Linings, 4.5mm m2 52.00 52.00 53.00 53.00
thick, fixed to timber frame, including PVC
mouldings to sheet joints
450mm wide m 21.25 21.25 22.00 22.00
600mm wide m 28.25 28.25 29.25 29.25
Scotia cornice, PVC two piece, to Eclipsa soffit m 6.90 6.80 6.80 6.80
Silkline Prefinished Soffit Linings, 4.5mm m2 61.00 61.00 62.00 62.00
thick, fixed to timber frame, including PVC
mouldings to sheet joints
450mm wide m 25.25 25.75 26.00 26.00
600mm wide m 33.75 33.50 34.50 34.50
Scotia cornice, PVC two piece, to Silkline soffit m 6.90 6.80 6.80 6.80
16.52 Lining–Ceiling
Wood Fibre Panels
13mm Michelangelo Tile wood fibre panels with
factory applied primer coat, fixed to ceiling
framing
Textured panel, 600mm x 400mm m2 32.00 31.25 31.75 31.75
Smooth acoustic panel, 600mm x 300mm, m2 38.75 38.00 39.25 39.25
with fire-retardant undercoat
Scotia cornice m 11.00 10.50 11.00 11.00
Add extra for fixing to soffit m2 2.00-4.00 2.00-4.00 2.00-4.00 2.00-4.00
• Other ceiling linings, as foregoing Wall Linings
• Plasterboard ceilings, Refer to page 4-387
• For suspended ceilings, Refer to page 4-394
Detailed Rates
2008
Carpentry
Fascias and Barge Boards
Page 4-220
2008
Carpentry
Interior Finishings
Page 4-221
2008
Carpentry
Interior Finishings
Page 4-222
2008
Hardware
Abbreviations
Page 4-223
17 Hardware
17.1 Abbreviations
AB = Antique Brass PB = Polished Brass
ABZ = Architectural Bronze SCP = Satin Chrome Plated
ALUM = Aluminium SE = Silver
BB = Bright Brass SNP = Satin Nickel Plate
BLK = Black SS = Stainless Steel
BZ = Oil Rubbed Bronze SSS = Satin Stainless Steel
CP = Chrome Plated PCS = Powder Coat Standard Colours
FB = Florentine Bronze
Vestibule Locks
Outside Key, Operates Bolts At All Times
Vestibule, V1/2 502/514 425.00 425.00 425.00 425.00 425.00
Exterior/exit, V7/8 502/511 430.00 430.00 430.00 430.00 430.00
Store room, V9/10 502/512 395.00 395.00 395.00 395.00 395.00
Single action, V11/12 506/512 405.00 405.00 405.00 405.00 405.00
Detailed Rates
2008
Hardware
Combination Locks
Page 4-224
Combination Locks
Outside Key, Operates Bolts At All Times
Entry, C1/2 502/514 430.00 430.00 430.00 430.00 430.00
Glass door, C7/8 502/511 440.00 440.00 440.00 440.00 440.00
Outside Key, Locks/Unlocks Both Handles
Entry, C21/22 502/514 400.00 400.00 400.00 400.00 400.00
Turn exit, C23/24 502/514 430.00 430.00 430.00 430.00 430.00
Glass door, C27/28 502/511 440.00 440.00 440.00 440.00 440.00
Glass door, C29/30 502/512 405.00 405.00 405.00 405.00 405.00
Privacy latch, C33/34 504/514 410.00 410.00 410.00 410.00 410.00
No Outside Key
Exterior privacy, C41/42 503/514 400.00 400.00 400.00 400.00 400.00
Exterior, C49/50 503/511 405.00 405.00 405.00 405.00 405.00
Passage latch, C57/58 503/512 355.00 355.00 355.00 355.00 355.00
Night Latches
Night latch, N1/2 22/23 265.00 265.00 265.00 265.00 265.00
Communicating door, N3 22/22 275.00 275.00 275.00 275.00 275.00
Cylinder latch, N5/6 22 215.00 215.00 215.00 215.00 215.00
Exit door, N7/8 23 205.00 205.00 205.00 205.00 205.00
Deadlocks
Outside Key, Operates Bolts At All Times
Entry, D1 22/23 290.00 290.00 290.00 290.00 290.00
Glass door, D3 22/22 290.00 290.00 290.00 290.00 290.00
Lockup shop, D5 22 235.00 235.00 235.00 235.00 235.00
Institutional, D9/D10 22/23 290.00 290.00 290.00 290.00 290.00
No Outside Key
Exit, D7 23 230.00 230.00 230.00 230.00 230.00
Detailed Rates
2008
Hardware
Sliding Door Locks
Page 4-225
Vestibule Locks
Outside Key, Operates Bolts At All Times
Vestibule, V1/2 5300/5303 530.00 530.00 530.00 530.00 530.00
Exterior/exit, V7/8 5300/5301 545.00 545.00 545.00 545.00 545.00
Store room, V9/10 5300/5306 510.00 510.00 510.00 510.00 510.00
Single action, V11/12 5310/5306 475.00 475.00 475.00 475.00 475.00
Outside Key, Locks/Unlocks Outside Handle
Vestibule, V21/22 5300/5303 540.00 540.00 540.00 540.00 540.00
Classroom, V29/30 5300/5306 520.00 520.00 520.00 520.00 520.00
No Outside Key
Exterior/exit, V41/42 5305/5303 505.00 505.00 505.00 505.00 505.00
Exterior/exit, V49/50 5305/5301 520.00 520.00 520.00 520.00 520.00
Exit latch, V55/56 5305/5306 485.00 485.00 485.00 485.00 485.00
Combination Locks
Outside Key, Operates Bolts At All Times
Entry, C1/2 5300/5303 540.00 540.00 540.00 540.00 540.00
Glass door, C7/8 5300/5301 550.00 550.00 550.00 550.00 550.00
Outside Key, Locks/Unlocks Both Handles
Entry, C21/22 5300/5303 540.00 540.00 540.00 540.00 540.00
Turn entry, C23/24 5300/5303 540.00 540.00 540.00 540.00 540.00
Glass door, C27/28 5300/5301 550.00 550.00 550.00 550.00 550.00
Glass door, C31/320 5300/5306 520.00 520.00 520.00 520.00 520.00
Detailed Rates
2008
Hardware
Cylinder Deadbolts
Page 4-226
17.7 Keying
Prices are per cylinder for standard profile keys
Keying alike/construction keying 16.00 - - - -
Master/Grandmaster keying 22.00 - - - -
Detailed Rates
2008
Hardware
Door Furniture Comparison
Page 4-227
2008
Hardware
Electromagnetic Locks
Page 4-228
2008
Hardware
Accessories to Electric Locks
Page 4-229
2008
Hardware
Panic Bolts/Exit Devices
Page 4-230
2008
Hardware
Pull Handles and Push Plates
Page 4-231
17.18 Bolts
Indicator Bolt - - - 66.00 -
Socket Bolt 8mm x 35mm 24.00 24.00 24.00 - -
8mm x 50mm 24.50 24.00 24.00 - -
8mm x 60mm 24.50 24.50 24.50 - -
8mm x 75mm 25.00 25.00 25.00 - -
8mm x 100mm 26.50 26.50 26.50 - -
10mm x 150mm 46.00 46.00 46.00 - -
Necked Bolt 8mm x 60mm 34.00 34.00 - 34.00 41.00
8mm x 75mm 35.00 35.00 - 35.00 42.00
8mm x 100mm 36.00 36.00 - 36.00 43.00
10mm x 150mm 56.00 56.00 - 56.00 70.00
Detailed Rates
2008
Hardware
Hooks
Page 4-232
17.19 Hooks
Cabin Hook
8mm x 50mm 20.50 - 20.50 20.50 -
8mm x 75mm 24.50 24.50 24.50 24.50 -
8mm x 100mm 22.50 - 22.50 22.50 -
10mm x 150mm 30.75 30.75 30.75 - -
Windsor brass, 75mm - - - 27.50 -
Windsor brass, 100mm - 30.50 - 28.50 -
Windsor brass, 150mm - - - 35.75 -
Coat Hook 15.75 16.25 15.75 15.75 -
Hat and Coat Hook - 18.50 - 18.50 -
2008
Hardware
Window Winding Equipment
Page 4-233
Unit Ak/Wn/Ch/Dn $
2008
Hardware
Illuminated Signs
Page 4-234
Unit Ak/Wn/Ch/Dn $
17.28 Mailboxes
Multi Apartment Mail System, rear opening for
mail delivery, keyed resident access
790mm x 805mm, 10 boxes No 2,000.00 2,000.00 2,000.00 2,000.00
1300mm x 805mm, 20 boxes No 2,750.00 2,750.00 2,750.00 2,750.00
1555mm x 905mm, 30 boxes No 3,500.00 3,500.00 3,500.00 3,500.00
1300mm x 1305mm, 40 boxes No 4,300.00 4,300.00 4,300.00 4,300.00
1555mm x 1305mm, 50 boxes No 5,100.00 5,100.00 5,100.00 5,100.00
1555mm x 1605mm, 65 boxes No 6,250.00 6,250.00 6,250.00 6,250.00
Add extra for mail collection facility. No 150.00 150.00 150.00 150.00
• Note that sizes differ when this facility included
Detailed Rates
2008
Hardware
Safety and Grab Rails
Page 4-235
2008
Hardware
Seats and Changing Tables
Page 4-236
2008
Hardware
Soap Dispenser
Page 4-237
2008
Hardware
Shower Curtains and Curtain Rails
Page 4-238
2008
Laminated Timber
Beams
Page 4-239
18 Laminated Timber
18.1 Beams
• Prices include fixing in position
Glulam Timber Beams in Radiata Pine, No 1
framing or better, sanded, melamine adhesive
industrial sealed, wrapped
42mm thick by
135mm deep m 26.00 25.75 25.75 25.75
180mm deep m 33.50 33.25 33.25 33.25
225mm deep m 41.50 41.25 41.25 41.25
270mm deep m 49.75 49.25 49.25 49.25
315mm deep m 58.00 58.00 58.00 58.00
360mm deep m 66.00 66.00 66.00 66.00
405mm deep m 74.00 74.00 74.00 74.00
450mm deep m 82.00 82.00 82.00 82.00
495mm deep m 91.00 90.00 90.00 90.00
540mm deep m 101.00 100.00 100.00 100.00
585mm deep m 109.00 108.00 108.00 108.00
630mm deep m 116.00 115.00 115.00 115.00
65mm thick by
135mm deep m 37.25 37.00 37.00 37.00
180mm deep m 47.75 47.25 47.25 47.25
225mm deep m 59.00 59.00 59.00 59.00
270mm deep m 71.00 71.00 71.00 71.00
315mm deep m 83.00 82.00 82.00 82.00
360mm deep m 95.00 94.00 94.00 94.00
405mm deep m 107.00 106.00 106.00 106.00
450mm deep m 119.00 118.00 118.00 118.00
495mm deep m 131.00 129.00 129.00 129.00
540mm deep m 143.00 142.00 142.00 142.00
585mm deep m 155.00 153.00 153.00 153.00
630mm deep m 167.00 165.00 165.00 165.00
90mm thick by
135mm deep m 49.50 49.00 49.00 49.00
180mm deep m 66.00 66.00 66.00 66.00
225mm deep m 82.00 82.00 82.00 82.00
270mm deep m 99.00 98.00 98.00 98.00
315mm deep m 115.00 114.00 114.00 114.00
360mm deep m 131.00 130.00 130.00 130.00
405mm deep m 148.00 146.00 146.00 146.00
450mm deep m 164.00 163.00 163.00 163.00
495mm deep m 181.00 179.00 179.00 179.00
540mm deep m 197.00 195.00 195.00 195.00
585mm deep m 215.00 210.00 210.00 210.00
630mm deep m 230.00 230.00 230.00 230.00
Detailed Rates
2008
Laminated Timber
Beams
Page 4-240
2008
Laminated Timber
Flooring
Page 4-241
18.2 Flooring
• Prices include fixing in position
Timberbond Structural Glulam Flooring in
Radiata Pine, melamine adhesive, sanded one
side, sealed and wrapped
300mm x 42mm thick m2 191.00 190.00 190.00 190.00
300mm x 65mm thick m2 275.00 275.00 275.00 275.00
300mm x 90mm thick m2 380.00 375.00 375.00 375.00
300mm x 115mm thick m2 480.00 475.00 475.00 475.00
300mm x 135mm thick m2 565.00 560.00 560.00 560.00
Add extra for H3 treatment, sanding both sides,
Douglas Fir, Refer to page 4-240
18.3 Posts
Laminated Timber Posts in Radiata Pine,
sanded, melamine adhesive industrial sealed
and wrapped
Interior grade
90mm x 90mm thick, 2 laminations m 39.25 38.50 38.50 38.50
90mm x 90mm thick, 5 laminations m 48.00 47.25 47.25 47.25
115mm x 115mm thick, 3 laminations m 65.00 64.00 64.00 64.00
135mm x 135mm thick, 3 laminations m 70.00 70.00 70.00 70.00
180mm x 180mm thick, 4 laminations m 115.00 114.00 114.00 114.00
Exterior grade
90mm x 90mm thick, 2 laminations m 43.50 42.75 42.75 42.75
90mm x 90mm thick, 5 laminations m 52.00 51.00 51.00 51.00
115mm x 115mm thick, 3 laminations m 73.00 73.00 73.00 73.00
135mm x 135mm thick, 3 laminations m 80.00 79.00 79.00 79.00
180mm x 180mm thick, 4 laminations m 132.00 131.00 131.00 131.00
Detailed Rates
2008
Laminated Timber
Portal Frames—LVL
Page 4-242
2008
Joinery
Timber Stairs
Page 4-243
Unit Ak/Wn/Ch/Dn $
19 Joinery
• Prices are average prices, which include
supply and installation.
; :
• Rates for stairs are given as metre of vertical
rise (m/rise), i.e., floor-to-floor height.
2008
Joinery
Timber Balustrades
Page 4-244
Unit Ak/Wn/Ch/Dn $
2008
Joinery
Kitchen Cupboards
Page 4-245
Unit Ak/Wn/Ch/Dn $
2008
Joinery
Kitchen Cupboards
Page 4-246
Unit Ak/Wn/Ch/Dn $
Overhead Cupboard Unit, 280mm deep x
720mm high, with intermediate shelf and hinged
doors. Price per lineal metre
• Note: price per metre is less for wider units. Bay widths
MDF carcass and doors 400mm 450mm 600mm 700mm
Paint finish m 565.00 525.00 435.00 405.00
Thermo-pressed finish m 575.00 540.00 445.00 410.00
Veneer finish m 680.00 635.00 525.00 480.00
Melamine carcass and
Melamine doors, white m 540.00 505.00 410.00 385.00
Solid Rimu doors m 805.00 755.00 625.00 585.00
Overhead Cupboard Unit, all as last item, but
price per bay.
MDF carcass and doors 400mm 450mm 600mm 700mm
Paint finish No 225.00 235.00 260.00 280.00
Thermo-pressed finish No 230.00 240.00 265.00 290.00
Veneer finish No 270.00 285.00 310.00 340.00
Melamine carcass and
Melamine doors, white No 215.00 225.00 250.00 270.00
Solid Rimu doors No 325.00 340.00 375.00 405.00
Pantry Unit, 560mm deep x 1950mm high, with
5 shelves and one hinged door
MDF carcass and doors
Paint finish No 710.00
Thermo-pressed finish No 730.00
Veneer finish No 845.00
Melamine carcass and
Melamine doors, white No 675.00
Solid Rimu doors No 1,050.00
Pantry Unit, 560mm deep x 1950mm high, with
5 shelves and two hinged doors
MDF carcass and doors 600mm 800mm 1000mm 1200mm
Paint finish No 830.00 990.00 1,075.00 1,125.00
Thermo-pressed finish No 850.00 1,000.00 1,075.00 1,125.00
Veneer finish No 990.00 1,175.00 1,275.00 1,325.00
Melamine carcass and
Melamine doors, white No 795.00 935.00 1,000.00 1,075.00
Solid Rimu doors No 1,175.00 1,400.00 1,475.00 1,650.00
Pantry Corner Unit, 1200mm x 1200mm x
1950mm high, with 5 shelves and hinged doors
MDF carcass and doors
Paint finish No 1,450.00
Thermo-pressed finish No 1,450.00
Veneer finish No 1,725.00
Melamine carcass and
Melamine doors, white No 1,350.00
Solid Rimu doors No 2,050.00
Detailed Rates
2008
Joinery
Kitchen Cupboards
Page 4-247
Unit Ak/Wn/Ch/Dn $
Wall Oven Unit, 800mm wide x 560mm deep x
1950mm high, with cupboards top and bottom
MDF carcass and doors
Paint finish No 990.00
Thermo-pressed finish No 1,000.00
Veneer finish No 1,175.00
Melamine carcass and
Melamine doors, white No 935.00
Solid Rimu doors No 1,400.00
Broom Cupboard, 600mm wide x 560mm deep
x 1950mm high, with shelf and hinged door
MDF carcass and doors
Paint finish No 710.00
Thermo-pressed finish No 725.00
Veneer finish No 845.00
Melamine carcass and
Melamine doors, white No 680.00
Solid Rimu doors No 1,025.00
Ironing Centre Cupboard, 300mm deep x
600mm wide x 1800mm high, including shelf,
fold down ironing board and hinged doors
MDF carcass and doors
Paint finish No 755.00
Thermo-pressed finish No 775.00
Veneer finish No 885.00
Melamine carcass and
Melamine doors, white No 700.00
Solid Rimu doors No 1,075.00
Add extra for
Bench tops, Refer to page 4-248
Door handles, Refer to page 4-232
Storage baskets
Towel racks, Refer to page 4-236
Detailed Rates
2008
Joinery
Bench Tops
Page 4-248
Unit Ak/Wn/Ch/Dn $
2008
Joinery
Vanity Units
Page 4-249
Unit Ak/Wn/Ch/Dn $
2008
Joinery
Reception Desk
Page 4-250
Unit Ak/Wn/Ch/Dn $
2008
Windows
Timber Windows
Page 4-251
20 Windows
20.1 Timber Windows
• Prices for windows are based on stock pattern
sections, single site glazing with clear glass,
fixed in position, complete with hardware,
unless otherwise stated.
Pine Windows, in H3 treated finger-jointed pine,
fixed light or opening sash
Standard Style, less than 0.5m2 in area m2 900.00 900.00 900.00 900.00
-1,165.00 -1,165.00 -1,165.00 -1,165.00
Over 0.5m2, less than 1.0m2 in area m2 715.00 715.00 715.00 715.00
-900.00 -900.00 -900.00 -900.00
Over 1.0m2, less than 3.0m2 in area m2 480.00 480.00 480.00 480.00
-745.00 -745.00 -745.00 -745.00
Over 3.0m2 in area m2 455.00 455.00 455.00 455.00
-480.00 -480.00 -480.00 -480.00
Colonial Style, less than 0.5m2 in area m2 1,010.00 1,010.00 1,010.00 1,010.00
-1,275.00 -1,275.00 -1,275.00 -1,275.00
Over 0.5m2, less than 1.0m2 in area m2 745.00 745.00 745.00 745.00
-960.00 -960.00 -960.00 -960.00
Over 1.0m2, less than 3.0m2 in area m2 530.00 530.00 530.00 530.00
-795.00 -795.00 -795.00 -795.00
Over 3.0m2 in area m2 480.00 480.00 480.00 480.00
-530.00 -530.00 -530.00 -530.00
Pine Windows, with cedar sashes and finger
jointed pine sills
Standard Style, less than 0.5m2 in area m2 1,035.00 1,035.00 1,035.00 1,035.00
-1,300.00 -1,300.00 -1,300.00 -1,300.00
Over 0.5m2, less than 1.0m2 in area m2 770.00 770.00 770.00 770.00
-985.00 -985.00 -985.00 -985.00
Over 1.0m2, less than 3.0m2 in area m2 530.00 530.00 530.00 530.00
-820.00 -820.00 -820.00 -820.00
Over 3.0m2 in area m2 505.00 505.00 505.00 505.00
-530.00 -530.00 -530.00 -530.00
Colonial Style, less than 0.5m2 in area m2 1,375.00 1,375.00 1,375.00 1,375.00
-1,640.00 -1,640.00 -1,640.00 -1,640.00
Over 0.5m2, less than 1.0m2 in area m2 845.00 845.00 845.00 845.00
-1,375.00 -1,375.00 -1,375.00 -1,375.00
Over 1.0m2, less than 3.0m2 in area m2 580.00 580.00 580.00 580.00
-845.00 -845.00 -845.00 -845.00
Over 3.0m2 in area m2 520.00 520.00 520.00 520.00
-580.00 -580.00 -580.00 -580.00
Timber framed glazed screen
10mm toughened glass m2 545.00 545.00 545.00 545.00
6mm toughened glass m2 455.00 455.00 455.00 455.00
Detailed Rates
2008
Windows
Aluminium Windows
Page 4-252
2008
Windows
Aluminium Curtain Walling
Page 4-253
2008
Windows
Glazing Bar System
Page 4-254
2008
Windows
Fire Rated Windows
Page 4-255
2008
Windows
Louvres—Window
Page 4-256
20.12 Louvres—Window
Fixed Louvre Window, 900mm x 1000mm, with No 330.00 330.00 330.00 330.00
eleven 150mm wide clear glass blades, in
aluminium louvre frame and timber surround
Adjustable Louvre Window, 900mm x No 350.00 350.00 350.00 350.00
1000mm, with six 150mm wide clear glass
blades, in adjustable aluminium louvre frame
and timber surround
20.13 Louvres—Air-conditioning
Louvre Panel, comprising fixed louvre blades
and frame, in aluminium
Mill finish m2 585.00 585.00 585.00 585.00
Clear anodised finish m2 660.00 660.00 660.00 660.00
Analok finish m2 715.00 715.00 715.00 715.00
Add extra for birdwire backing m2 40.00 40.00 40.00 40.00
20.14 Blinds
Venetian blinds
Slimline m2 60.00 60.00 60.00 60.00
-75.00 -75.00 -75.00 -75.00
Micro m2 70.00 70.00 70.00 70.00
-90.00 -90.00 -90.00 -90.00
Timber m2 90.00 90.00 90.00 90.00
-105.00 -105.00 -105.00 -105.00
Roller blinds, Standard Holland m2 65.00 65.00 65.00 65.00
-75.00 -75.00 -75.00 -75.00
Vertical blinds, heavy duty cotton m2 60.00 60.00 60.00 60.00
-100.00 -100.00 -100.00 -100.00
Pleated blinds m2 85.00 85.00 85.00 85.00
-110.00 -110.00 -110.00 -110.00
Add extra for blinds less than 1m2 in size % 15% 15% 15% 15%
Detailed Rates
2008
Doors
Door Frames, Timber, Exterior
Page 4-257
21 Doors
• All door dimensions are given in millimetres, as
height x width
• Prices for door frames are for frames only,
fixed in timber framing and exclude doors.
2008
Doors
Door Frames, Aluminium
Page 4-258
2008
Doors
Doors, Timber
Page 4-259
2008
Doors
Entrance Doors, Panelled and/or Glazed
Page 4-260
2008
Doors
Doors, Aluminium
Page 4-261
2008
Doors
Doors, Domestic Garage, Tilting
Page 4-262
2008
Doors
Doors, Industrial Roller Shutter
Page 4-263
2008
Doors
Doors, Industrial SlideOver
Page 4-264
2008
Doors
Shutters, Clearspan
Page 4-265
2008
Doors
Doors, Folding
Page 4-266
2008
Doors
Doors, Fire
Page 4-267
2008
Doors
Doors and Screens, Security
Page 4-268
2008
Partitions
General Notes
Page 4-269
22 Partitions
22.1 General Notes
• Timber framing is MSG8, KD, H1.2 RP
• All plasterboard rates allow for taped and
stopped joints to level 4 finish.
• For plasterboard linings without framing, Refer
to page 4-387
• M2 rates allow for 2.7m or 3m wall height.
• Rates for partitions with heights requiring non-
standard wallboard sizes may vary
considerably, due to greater wastage factors.
• No allowance for baffles in ceiling spaces.
• Lining requirements are indicated thus:
2/1/10mm GIB® =two faces/one layer/10mm GIB®, ie, each side of wall has one layer of GIB®
2/2/13mm GIB® =two faces/two layers/13mm GIB®, ie, each side of wall has two layers of GIB®
1/1/10mm GIB® =one face/one layer/10mm GIB®, with other face/two layers/13mm GIB®,
1/2/13mm GIB® ie, one side of wall has one layer of GIB®, the other side has two layers
• Refer to GIB® manuals for system details and
full descriptions. See www.gib.co.nz
2008
Partitions
GIB® Noise Control Systems—Timber
Page 4-270
2008
Partitions
GIB® Noise Control Systems—Steel
Page 4-271
2008
Partitions
GIB® Fire Rated Systems—Timber
Page 4-272
2008
Partitions
GIB® Fire Rated Systems—Steel
Page 4-273
2008
Partitions
GIB® Fire Rated Systems—Shaftwall
Page 4-274
2008
Partitions
James Hardie Systems
Page 4-275
2008
Partitions
Acoustic and Fire-Rated—Concrete
Page 4-276
2008
Insulating Panel Systems
Cool Rooms
Page 4-277
Unit Ak/Wn/Ch/Dn $
2008
Insulating Panel Systems
Coolroom and Cold Store Doors
Page 4-278
Unit Ak/Wn/Ch/Dn $
2008
Proprietary Cladding Systems
Exterior Insulation Finishing Systems
Page 4-279
Unit Ak/Wn/Ch/Dn $
2008
Proprietary Cladding Systems
Proprietary Wall Cladding Systems
Page 4-280
Unit Ak/Wn/Ch/Dn $
2008
Roof Coverings
Steel Supply Prices
Page 4-281
25 Roof Coverings
• Prices based on minimum quantity of 150m2.
• Add extra for small areas.
• Add extra for building paper if required.
• Add extra where roof shape more complex
2008
Roof Coverings
Steel and Aluminium Roofing
Page 4-282
2008
Roof Coverings
Concrete and Clay Tiles and Shingles
Page 4-283
2008
Roof Coverings
Shingles and Shakes—Timber
Page 4-284
2008
Roof Coverings
Mastic Asphalt Roofing
Page 4-285
2008
Roof Coverings
Bituminous and Acrylic Membranes
Page 4-286
2008
Roof Coverings
Wall Cladding
Page 4-287
2008
Roof Coverings
Roof Windows and Rooflights
Page 4-288
2008
Roof Coverings
Roof Windows and Rooflights
Page 4-289
2008
Roof Coverings
Roof Windows and Rooflights
Page 4-290
2008
Roof Coverings
Rainwater Heads
Page 4-291
2008
Roof Coverings
Box Gutters
Page 4-292
2008
Roof Coverings
Eaves Gutters—PVC
Page 4-293
25.24 Ventilators
Zincalume Rotary Ventilator, complete with
integral flashings, fixed to metal roof
185mm diameter x 230mm high No 350.00 350.00 350.00 350.00
425mm diameter x 380mm high No 450.00 450.00 450.00 450.00
650mm diameter x 550mm high No 1,050.00 1,050.00 1,050.00 1,050.00
Add extra for cord operated damper assembly
300mm diameter No 170.00 170.00 170.00 170.00
460mm to 600mm diameter No 300.00 300.00 300.00 300.00
Detailed Rates
2008
Roof Coverings
Downpipes
Page 4-294
25.25 Downpipes
• Prices include strap fixings or wall clips
Copper, 0.5mm
65mm dia pipe m 86.00 86.00 86.00 86.00
75mm dia pipe m 86.00 86.00 86.00 86.00
100mm dia pipe m 102.0 102.0 102.0 102.0
Bend, elbow or shoe
65mm dia No 30.00 30.00 30.00 30.00
75mm dia No 35.00 35.00 35.00 35.00
100mm dia No 40.00 40.00 40.00 40.00
Zincalume Steel, 0.55mm
65mm dia pipe m 44.75 44.25 44.25 44.25
75mm dia pipe m 45.00 44.25 44.25 44.25
100mm dia pipe m 51.00 50.00 50.00 50.00
150mm dia pipe m 61.00 60.00 60.00 60.00
100mm x 50mm rectangular pipe m 44.50 43.75 43.75 43.75
100mm x 75mm rectangular pipe m 46.25 45.50 45.50 45.50
Bend, elbow or shoe
65mm dia No 15.00 15.00 15.00 15.00
75mm dia, or 75mm x 75mm No 15.00 15.00 15.00 15.00
100mm dia, or 100mm x 50mm No 17.00 17.00 17.00 17.00
Stainless Steel, 0.5mm
75mm dia pipe m 62.00 61.00 61.00 61.00
100mm dia pipe m 107.00 106.00 106.00 106.00
Bend, elbow or shoe
75mm dia No 30.00 30.00 30.00 30.00
100mm dia No 50.00 50.00 50.00 50.00
PVC (labour constant reduced to 0.25hr/m)
65mm dia pipe m 29.50 29.00 29.00 29.00
80mm dia pipe m 30.25 29.75 29.75 29.75
Magnum 100mm dia pipe m 42.25 41.75 41.75 41.75
Eclipse half round m 32.75 32.25 32.25 32.25
65mm x 50mm rectangular pipe m 28.50 28.00 28.00 28.00
100mm x 50mm rectangular pipe m 34.50 34.00 34.00 34.00
Bend, elbow or shoe
65mm dia No 11.50 11.25 11.25 11.25
80mm dia No 12.50 12.25 12.25 12.25
Magnum 100mm dia No 15.25 15.00 15.00 15.00
Eclipse half round No 12.00 11.75 11.75 11.75
65mm x 50mm No 10.75 10.50 10.50 10.50
100mm x 50mm No 14.00 13.75 13.75 13.75
Detailed Rates
2008
Roof Coverings
Flashings
Page 4-295
25.26 Flashings
• Prices are based on two folds only
Extra folds m 1.15 1.15 1.15 1.15
Soft edging, add
63mm deep m 7.00 7.00 7.00 7.00
Aluminium, straight
0.7mm x 250mm girth m 28.00 26.75 26.75 26.75
0.7mm x 500mm girth m 36.50 35.25 35.25 35.25
0.7mm x 750mm girth m 43.75 42.50 42.50 42.50
0.9mm x 250mm girth m 35.25 33.75 33.75 33.75
0.9mm x 500mm girth m 47.25 45.50 45.50 45.50
0.9mm x 750mm girth m 59.00 57.00 57.00 57.00
Aluminium, stepped
0.7mm x 250mm girth m 40.50 38.50 38.50 38.50
0.7mm x 500mm girth m 49.25 47.25 47.25 47.25
0.7mm x 750mm girth m 61.00 59.00 59.00 59.00
0.9mm x 250mm girth m 43.00 41.00 41.00 41.00
0.9mm x 500mm girth m 54.00 52.00 52.00 52.00
0.9mm x 750mm girth m 68.00 66.00 66.00 66.00
Copper, straight
0.55mm x 250mm girth m 60.00 60.00 60.00 60.00
0.55mm x 500mm girth m 100.00 100.00 100.00 100.00
0.55mm x 750mm girth m 140.00 140.00 140.00 140.00
Copper, stepped
0.55mm x 250mm girth m 75.00 75.00 75.00 75.00
0.55mm x 500mm girth m 125.00 120.00 120.00 120.00
0.55mm x 750mm girth m 175.00 170.00 170.00 170.00
Stainless Steel, straight
0.5mm x 250mm girth m 47.25 46.00 46.00 46.00
0.5mm x 500mm girth m 75.00 75.00 75.00 75.00
0.5mm x 750mm girth m 100.00 100.00 100.00 100.00
Zincalume Steel, straight
0.55mm x 250mm girth m 26.25 25.00 25.00 25.00
0.55mm x 500mm girth m 33.00 31.75 31.75 31.75
0.55mm x 750mm girth m 38.50 37.25 37.25 37.25
Zincalume Steel, stepped
0.55mm x 250mm girth m 35.75 34.00 34.00 34.00
0.55mm x 500mm girth m 42.25 40.75 40.75 40.75
0.55mm x 750mm girth m 54.00 52.00 52.00 52.00
Prefinished Steel, Endura/ZR8, straight
0.55mm x 250mm girth m 28.25 27.00 27.00 27.00
0.55mm x 500mm girth m 37.00 37.00 37.00 37.00
0.55mm x 750mm girth m 44.50 43.25 43.25 43.25
Detailed Rates
2008
Roof Coverings
Flashings
Page 4-296
2008
Plumbing
WC Pans—Vitreous China
Page 4-297
26 Plumbing
• Prices for sanitary fixtures include installation,
complete with plugs, grated waste outlets,
brackets, all fixings and jointing to pipes.
• Prices do not include pipework, traps, cocks or
taps unless stated.
• Rates are intended to cover a reasonable
range of residential and commercial projects.
For projects with a higher specification, refer to
plumbing merchants for supply costs.
• For installed costs including pipework, taps &
traps, Refer to page 3-92
2008
Plumbing
WC Suites—Vitreous China
Page 4-298
26.4 WC Seats
WC seat
Dux Regent No 58.00 55.00 55.00 55.00
Dux Kindy, full ring, no cover No 167.00 165.00 165.00 165.00
Villeroy and Boch Omnia Pro Soft Close No 310.00 305.00 305.00 305.00
Fowler Colani, disabled No 405.00 405.00 405.00 405.00
Caroma Vintage jarrah timber seat No 465.00 460.00 460.00 460.00
26.5 Bidets
Vitreous China, including tapware
Bidet, floor mounted
Caroma Royale No 880.00 875.00 875.00 875.00
Villeroy & Boch Omnia Pro No 1,050.00 1,025.00 1,025.00 1,025.00
Caroma Caravelle No 1,050.00 1,025.00 1,025.00 1,025.00
Villeroy & Boch Century No 1,200.00 1,200.00 1,200.00 1,200.00
Caroma Leda 2000 No 1,225.00 1,215.00 1,215.00 1,215.00
Villeroy & Boch Editionals No 1,465.00 1,450.00 1,450.00 1,450.00
Bidet, wall hung
Villeroy & Boch Omnia Pro No 1,290.00 1,280.00 1,280.00 1,280.00
Villeroy & Boch Century No 1,500.00 1,500.00 1,500.00 1,500.00
Detailed Rates
2008
Plumbing
Cisterns
Page 4-299
26.6 Cisterns
• Prices include installation, single/dual flush,
flush pipe, flush pipe connector, stop valve and
braided hose supply pipe
Plastic, exposed flush pipe
Dux Centreflush or Loline No 265.00 255.00 255.00 255.00
Dux Twinline No 345.00 340.00 340.00 340.00
Plastic, low level, with integral seat
Caroma Slimline Smartflush No 340.00 335.00 335.00 335.00
Caroma Trident Smartflush No 370.00 365.00 365.00 365.00
Caroma Cosmo Smartflush, Caravelle No 420.00 415.00 415.00 415.00
2000 seat
Vitreous china, concealed flush pipe
Caroma Sovereign 2000 Smartflush No 520.00 515.00 515.00 515.00
Villeroy & Boch Omnia Pro No 405.00 400.00 400.00 400.00
• For WC flushing valves, Refer to page 4-300
26.8 Urinals—Stall
Single Stall Urinal, wall mounted, with
concealed support bracket and sparge pipe
Caroma Leda, with pedestal No 940.00 925.00 925.00 925.00
Caroma Torres No 1,175.00 1,150.00 1,150.00 1,150.00
Caroma Integra No 1,675.00 1,650.00 1,650.00 1,650.00
Caroma Cube 0.8L Smartflush No 1,950.00 1,950.00 1,950.00 1,950.00
Caroma Leda Electronic, with pedestal No 2,025.00 2,000.00 2,000.00 2,000.00
Mercer Classique, stainless steel No 985.00 965.00 965.00 965.00
Privacy divider, stainless steel No 630.00 630.00 630.00 630.00
Waterless Urinal, vitreous china, chemical trap
Geranium model No 885.00 865.00 865.00 865.00
Flax or Boronia models No 935.00 915.00 915.00 915.00
Caroma H2Zero Cube No 1,260.00 1,250.00 1,250.00 1,250.00
SealTrap chemical cartridge No 64.00 6400 6400 6400
2008
Plumbing
Urinal Flushing Valves
Page 4-300
26.13 Baths—Acrylic
Bath, 1525mm long
Clearlite Pacific, 725mm wide No 355.00 345.00 345.00 345.00
Englefield Sorrento, 730mm wide No 350.00 340.00 350.00 350.00
Englefield Delano, 760mm wide No 485.00 475.00 500.00 500.00
Bath, 1675mm long
Clearlite Gaugin, 762mm wide No 47.00 460.00 460.00 460.00
Englefield Delano, 760mm wide No 485.00 475.00 500.00 500.00
Englefield Delano, 900mm wide No 545.00 535.00 555.00 555.00
Bath, 1800mm long
Clearlite Monet, 950mm wide No 800.00 790.00 790.00 790.00
Englefield Sapphire, 900mm wide No 745.00 735.00 765.00 765.00
Shower Over Bath, Clearlite Dina
1200mm x 800mm shub No 535.00 530.00 530.00 530.00
1200mm x 800mm shub with wall liner No 1,100.00 1,075.00 1,075.00 1,075.00
Shower Over Bath, Englefield Duo
760mm bath, with 2 sided wall liner, No 940.00 925.00 925.00 925.00
1500mm or 1675mm long
Corner Bath, Clearlite Corniche
1300mm x 1300mm No 685.00 675.00 675.00 675.00
Detailed Rates
2008
Plumbing
Baths—Steel or Cast Iron
Page 4-301
2008
Plumbing
Basins—Wall
Page 4-302
26.18 Basins—Wall
• Prices include chrome waste outlet, plug, chain
and stay, and brackets.
Acrylic Wall Basin, with full skirt
Aqualine, Little Gem No 380.00 370.00 370.00 370.00
Stainless Steel Wall Basin
Mercer G3, 520mm x 400mm No 455.00 445.00 445.00 445.00
Vitreous China Wall Basin
Fowler Corner, 385mm x 385mm No 345.00 335.00 335.00 335.00
Fowler Mini, 515mm x 215mm No 385.00 375.00 375.00 375.00
Caroma Integra, 500mm x 430mm No 480.00 470.00 470.00 470.00
Vitreous China Basin, with full pedestal
Roca Victoria, all sizes No 425.00 415.00 415.00 415.00
Caroma Geo 400, 400mm x 470mm No 820.00 815.00 815.00 815.00
Caroma Vintage, 600mm x 500mm No 965.00 955.00 955.00 955.00
Vitreous China Basin, with full pedestal
Caroma Hospital, 600mm x 490mm No 850.00 825.00 825.00 825.00
26.19 Basins—Vanity
Acrylic Vanity Basin, Clearlite
VB7, 530mm x 400mm, undermount No 325.00 320.00 320.00 320.00
VB10, 530mm x 380mm, overmount No 380.00 370.00 370.00 370.00
Vitreous China Vanity Basin, Caroma
Caravelle, 550mm x 435mm No 360.00 350.00 350.00 350.00
Cameo, 545mm x 4250mm No 385.00 375.00 375.00 375.00
Geo, 400mm x 400mm No 590.00 580.00 580.00 580.00
2008
Plumbing
Tubs
Page 4-303
26.21 Tubs
Single Laundry Tub, stainless steel
Standard, pressed, 560mm x 450mm No 345.00 335.00 335.00 335.00
Standard, fabricated, 560mm x 450mm No 425.00 415.00 415.00 415.00
Large, pressed, 610mm x 560mm No 530.00 520.00 520.00 520.00
Add extra for
MDF cabinet No 120.00 120.00 120.00 120.00
Brackets Set 30.00 30.00 30.00 30.00
Double Laundry Tub, stainless steel
Fabricated, 1100mm x 450mm No 985.00 980.00 980.00 980.00
Pressed, 1100mm x 450mm No 1,025.00 1,000.00 1,000.00 1,000.00
Add extra for
Timber cabinet No 160.00 160.00 160.00 160.00
Brackets Set 60.00 60.00 60.00 60.00
Robinhood Supertub and Cabinet, tapware
included
ST3100, low pressure No 535.00 525.00 525.00 525.00
ST6000, mains pressure No 700.00 690.00 690.00 690.00
STSLIM, 350mm wide No 390.00 385.00 385.00 385.00
2008
Plumbing
Drinking Fountains
Page 4-304
2008
Plumbing
Taps and Cocks
Page 4-305
2008
Plumbing
Mixers
Page 4-306
26.29 Mixers
• Prices for mixers include chrome plated finish
and connection to pipework
Kitchen Sink Mixer, ceramic disk single lever
Foreno FMX1 No 245.00 240.00 240.00 240.00
Foreno FMX1T, slate finish No 440.00 435.00 435.00 435.00
Greens Starmix 5000 No 565.00 555.00 555.00 555.00
Greens Starmix 6000, stainless steel No 660.00 655.00 655.00 655.00
Methven Centique No 385.00 680.00 380.00 380.00
Methven Centique, with vege spray No 680.00 675.00 675.00 675.00
Methven Minimalist No 600.00 595.00 595.00 595.00
Basin Mixer, ceramic disk single lever
Foreno FBF7, star handle, ceramic No 295.00 290.00 290.00 290.00
Foreno FMB4 No 245.00 240.00 240.00 240.00
Greens Starmix 5000 No 550.00 545.00 545.00 545.00
Greens Starmix 6000, stainless steel No 620.00 610.00 610.00 610.00
Methven Minimalist No 410.00 405.00 405.00 405.00
Shower Mixer, ceramic disk single lever
Feltonmix with wall set and rose No 365.00 350.00 350.00 350.00
Foreno Equaliser FSMQ11 No 325.00 315.00 315.00 315.00
Greens Starmix 3000 No 460.00 450.00 450.00 450.00
Greens Starmix 5000 or 6000 No 545.00 535.00 535.00 535.00
Methven Futura Chrome No 505.00 495.00 495.00 495.00
Bath/Shower Mixer with Diverter, ceramic disk
single lever
Greens Starmix 3000 No 565.00 555.00 555.00 555.00
Greens Starmix 5000 No 655.00 645.00 645.00 645.00
Methven Futura Chrome No 560.00 545.00 545.00 545.00
Shower Rose
Greens all directional No 110.00 105.00 105.00 105.00
Greens Cosmos MultiFunction No 235.00 235.00 235.00 235.00
Methven Futura shower rose No 193.00 187.00 187.00 187.00
Slide Shower, with shower rose, flexible hose,
slide rail and elbow connector
Foreno Techno No 280.00 270.00 270.00 270.00
Methven Bella, all pressures No 210.00 205.00 205.00 205.00
Methven FU2011, all pressures No 360.00 355.00 355.00 355.00
Methven Minimalist No 450.00 445.00 445.00 445.00
Methven Satin Jet No 440.00 430.00 430.00 430.00
Detailed Rates
2008
Plumbing
Traps
Page 4-307
26.30 Traps
PVC P– or S–Trap
32mm dia, short inlet No 18.00 17.25 17.25 17.25
32mm dia, adjustable inlet No 22.00 21.25 21.25 21.25
32mm dia, bottle trap No 23.75 23.00 23.00 23.00
40mm dia, short inlet No 22.00 21.00 21.00 21.00
40mm dia, adjustable inlet No 26.00 24.75 24.75 24.75
40mm dia, bottle trap No 27.25 26.25 26.25 26.25
50mm dia, short inlet No 42.50 41.00 41.00 41.00
Copper P–Trap, short tail
32mm dia No 150.00 148.00 148.00 148.00
40mm dia No 158.00 157.00 157.00 157.00
50mm dia No 230.00 230.00 230.00 230.00
Copper P–Trap, long tail
32mm dia No 180.00 180.00 180.00 180.00
40mm dia No 225.00 225.00 225.00 225.00
50mm dia No 315.00 310.00 310.00 310.00
Copper S–Trap, short tail
32mm dia No 163.00 161.00 161.00 161.00
40mm dia No 177.00 175.00 175.00 175.00
50mm dia No 255.00 255.00 255.00 255.00
Copper S–Trap, long tail
32mm dia No 215.00 215.00 215.00 215.00
40mm dia No 235.00 230.00 230.00 230.00
50mm dia No 330.00 325.00 325.00 325.00
Chrome Plated Copper P–Trap, short tail
32mm dia No 205.00 205.00 205.00 205.00
40mm dia No 220.00 220.00 220.00 220.00
50mm dia No 310.00 310.00 310.00 310.00
Chrome Plated Copper P–Trap, long tail
32mm dia No 260.00 260.00 260.00 260.00
40mm dia No 310.00 310.00 310.00 310.00
50mm dia No 425.00 425.00 425.00 425.00
Chrome Plated Copper S–Trap, short tail
32mm dia No 215.00 215.00 215.00 215.00
40mm dia No 235.00 235.00 235.00 235.00
50mm dia No 350.00 345.00 345.00 345.00
Chrome Plated Copper S–Trap, long tail
32mm dia No 290.00 290.00 290.00 290.00
40mm dia No 325.00 320.00 320.00 320.00
50mm dia No 440.00 440.00 440.00 440.00
Easy Clean Trap, flat top or domed
40mm dia, standard No 160.00 160.00 160.00 160.00
50mm dia, standard No 180.00 180.00 180.00 180.00
65mm dia, standard No 245.00 245.00 245.00 245.00
75mm dia, standard No 280.00 280.00 280.00 280.00
Detailed Rates
2008
Plumbing
Pipework—Soil, Waste and Vent
Page 4-308
2008
Plumbing
Pipework—Soil, Waste and Vent
Page 4-309
2008
Plumbing
Pipework—Water Supply
Page 4-310
2008
Plumbing
Pipework—Water Supply
Page 4-311
2008
Plumbing
Pipework—Water Supply
Page 4-312
2008
Plumbing
Water Tanks
Page 4-313
2008
Plumbing
Water Heaters, Gas
Page 4-314
2008
Plumbing
Water Heaters, Electric
Page 4-315
2008
Drainage
Trench Excavation
Page 4-316
27 Drainage
27.1 Trench Excavation
• Prices for trench excavation include excavating by
machine, backfilling with excavated material,
maintaining sides of trench and removal of surplus
material up to 5km from site.
• Prices exclude any site problems, blasting or use of
pneumatic tools.
Excavate Trench for 100mm–150mm dia pipe,
Not Exceeding:
1.5m total depth, average depth 1m, in
Light soil m 22.50 - 37.50
Clay m 29.75 - 44.75
Soft rock rippable m 60.00 - 90.00
3m total depth, average depth 2m, in
Light soil m 85.00 - 115.00
Clay m 104.00 - 144.00
Soft rock rippable m 220.00 - 280.00
4.5m total depth, average depth 4m, in
Light soil m 180.00 - 220.00
Clay m 220.00 - 280.00
Soft rock, rippable m 470.00 - 530.00
Excavate Trench for 175mm–250mm dia pipe,
Not Exceeding:
1.5m total depth, average depth 1m, in
Light soil m 32.50 - 47.50
Clay m 42.00 - 57.00
Soft rock, rippable m 85.00 - 115.00
3m total depth, average depth 2m, in
Light soil m 90.00 - 125.00
Clay m 116.00 - 156.00
Soft rock, rippable m 245.00 - 305.00
4.5m total depth, average depth 4m, in
Light soil m 190.00 - 250.00
Clay m 245.00 - 305.00
Soft rock, rippable m 520.00 - 580.00
Excavate Trench for 300mm dia pipe,
Not Exceeding:
1.5m total depth, average depth 1m, in
Light soil m 42.50 - 58.00
Clay m 47.00 - 77.00
Soft rock, rippable m 105.00 - 145.00
3m total depth, average depth 2m, in
Light soil m 100.00 - 135.00
Clay m 129.00 - 169.00
Soft rock, rippable m 270.00 - 330.00
Detailed Rates
2008
Drainage
Trench Excavation
Page 4-317
2008
Drainage
Directional Drilling and Micro-Tunnelling
Page 4-318
2008
Drainage
Sewer Drains—PVC
Page 4-319
2008
Drainage
Sewer Drains—Earthenware
Page 4-320
2008
Drainage
Sewer Drains—Concrete
Page 4-321
2008
Drainage
Sewer Drains—Concrete
Page 4-322
2008
Drainage
Stormwater Drains
Page 4-323
2008
Drainage
Agricultural Drains
Page 4-324
2008
Drainage
Concrete Surrounds
Page 4-325
27.10 Sumps
• Prices include excavation, backfilling, lids and
connection to pipework.
• Prices for cast iron grates given separately.
Precast Concrete Sump, 600mm diameter,
with insitu concrete base and 100mm precast
concrete lid
300mm deep No 480.00 - 580.00
600mm deep No 540.00 - 640.00
900mm deep No 720.00 - 820.00
1200mm deep No 860.00 - 960.00
27.11 Cesspits
• Prices include excavation, backfilling and
connection to pipework.
• Prices for covers and grates given separately.
Precast Concrete Cesspit, with insitu concrete
base
450mm x 450mm x 600mm deep No 540.00 - 600.00
450mm x 450mm x 900mm deep No 660.00 - 760.00
675mm x 450mm x 600mm deep No 600.00 - 680.00
675mm x 450mm x 900mm deep No 720.00 - 820.00
675mm x 450mm x 1200mm deep No 820.00 - 900.00
Add extra for cast iron grate and frame
450mm x 450mm No 180.00 - 190.00
675mm x 450mm No 260.00 - 280.00
Base entry kerb block, 980mm x 230mm No 65.00 - 75.00
Detailed Rates
2008
Drainage
Manholes
Page 4-326
27.12 Manholes
• Prices include excavation, backfilling, benching,
channels, steps and connection to pipes.
• All dimensions are internal dimensions
Precast Concrete Manhole, with integral
concrete base and 150mm heavy duty
reinforced concrete lid, including galvanised
steel steps, clamps, sealant, haunching etc.
1050mm diameter
900mm deep No 1,950.00 - 2,050.00
1500mm deep No 1,975.00 - 2,075.00
2100mm deep No 3,000.00 - 3,100.00
3000mm deep No 4,050.00 - 4,150.00
1200mm diameter
1200mm deep No 2,800.00 - 2,900.00
2100mm deep No 3,800.00 - 3,900.00
3000mm deep No 5,000.00 - 5,100.00
3900mm deep No 6,400.00 - 6,500.00
1500mm diameter
1500mm deep No 4,250.00 - 4,350.00
2100mm deep No 5,100.00 - 5,200.00
3000mm deep No 6,700.00 - 6,800.00
3900mm deep No 8,400.00 - 8,500.00
1800mm diameter
1500mm deep No 6,000.00 - 6,200.00
2100mm deep No 7,200.00 - 7,400.00
3000mm deep No 9,000.00 - 9,200.00
3900mm deep No 11,000.00 - 11,500.00
2008
Drainage
Traps
Page 4-327
27.14 Traps
• Prices include excavation, backfilling and
connection to pipes
Grease Trap, precast concrete and concrete lid,
and cast iron manhole cover and frame
100 litre No 1,850.00 - 1,950.00
222 litre No 3,000.00 - 3,200.00
425 litre No 2,600.00 - 2,800.00
Grease Trap, polyethelene body and lid
125 litre No 1,850.00 - 1,950.00
150 litre No 1,200.00 - 1,300.00
200 litre No 1,500.00 - 1,600.00
500 litre No 3,500.00 - 3,700.00
Oil and Grit Interceptor, 2700 litre precast No 5,500.00 6,500.00
concrete, with manhole covers and frames
2008
Drainage
Channel Drains and Gratings
Page 4-328
2008
Mechanical Services
Room Air Conditioners (RAC)
Page 4-329
Unit Ak/Wn/Ch/Dn $
28 Mechanical Services
28.1 Room Air Conditioners (RAC)
Specification Notes
• RAC = Self Contained Reverse Cycle Packaged Type Room Air Conditioner.
• Manufacturers may state the cooling capacities of RAC units in Watts, BTU/Hr or HP, as a NOMINAL
rating (i.e. compressor rating) or a NET rating (the actual room cooling ability of the unit).
• NOMINAL capacities may have to be de-rated by up to 20% to obtain the actual cooling ability of the
unit.
• RAC units range between 1.5kW (net) and 14kW (net). To obtain full specifications for each unit, consult
the manufacturers and suppliers.
2008
Mechanical Services
Hydronic Air Conditioning Systems
Page 4-330
Unit Ak/Wn/Ch/Dn $
High Level Unit, non-ducted, wall mounted
2.6 kW (nom 125 litre/sec) No 2,925.00 - 3,150.00
3.3 kW (nom 130 litre/sec) No 3,025.00 - 3,275.00
5.2 kW (nom 227 litre/sec) No 3,850.00 - 4,100.00
Under Ceiling Unit, non-ducted, surface
mounted
4.7 kW No 5,500.00 - 6,900.00
8.5 kW No 7,600.00 - 7,950.00
9.9 kW No 9,100.00 - 9,450.00
13.6 kW No 10,650.00 - 11,000.00
Concealed Air Handling Unit, ducted, in ceiling
space, and external condenser unit
9 kW (nom 472 litre/sec) No 6,750.00 - 7,100.00
12 kW–2 units (nom 566 litre/sec) No 12,850.00 - 13,300.00
16 kW (nom 755 litre/sec) No 9,250.00 - 9,600.00
18 kW–2 units (nom 944 litre/sec) No 11,700.00 - 12,150.00
3 Phase Air Handling Unit
9 kW (nom 472 litre/sec) No 7,950.00 - 8,300.00
12 kW (nom 566 litre/sec) No 8,650.00 - 9,000.00
18 kW (nom 944 litre/sec) No 9,450.00 - 9,800.00
Add extra for
Condensate pipework (from internal unit)
Refrigerant pipework (internal/external
unit)—pipe run should not exceed 20m,
including 10m vertical separation
Ductwork, insulation, pipe penetration and
sealing
Prepared condenser unit plinth
Air diffuser, grilles
Electrical connections between inside and
outside units
2008
Mechanical Services
Fan Coil Units
Page 4-331
Unit Ak/Wn/Ch/Dn $
28.6 Fans—Centrifugal
• Prices include standard prime paint finish, inlet
guards, mounting frame, motor, drive gear, anti-
vibration mounts and installation, but exclude
electrical connections and controls.
SWSI—Single Width Single Inlet Fan, 3 phase
415v
2,300 litre/sec @ 500 Pa, 2.2 kW, 560mm No 6,300.00 - 7,900.00
diameter inlet,
540mm x 405mm outlet
5,000 litre/sec @ 750 Pa, 7.5 kW, 830mm No 8,150.00 - 11,500.00
diameter inlet,
805mm x 600mm outlet
9,000 litre/sec @ 900 Pa, 15 kW, 1205mm No 12,550.00 - 16,900.00
diameter inlet,
1080mm x 820mm outlet
DWDI—Double Width Double Inlet Fan,
3 phase 415v
10,000 litre/sec @ 1000 Pa, 18.5 kW, No 15,400.00 - 19,850.00
830mm diameter inlet,
805mm x 1200mm outlet
15,000 litre/sec @ 1250 Pa, 37 kW, No 20,600.00 - 24,350.00
1000mm diameter inlet,
980mm x 1470mm outlet
20,000 litre/sec @ 1500 Pa, 55 kW, No 27,450.00 - 33,050.00
1205mm diameter inlet,
1080mm x 1590mm outlet
Detailed Rates
2008
Mechanical Services
Fans–Axial Flow
Page 4-332
Unit Ak/Wn/Ch/Dn $
2008
Mechanical Services
Water Chillers
Page 4-333
Unit Ak/Wn/Ch/Dn $
2008
Mechanical Services
Cooling and Heating Coils
Page 4-334
Unit Ak/Wn/Ch/Dn $
28.12 Radiators
Single Panel Radiator, complete with wall
mounting brackets, standard finish, lockshield
and thermostatic valve, air cock, maximum
working pressure 350kPa.
500 Watt No 595.00 - 665.00
1000 Watt No 680.00 - 760.00
1500 Watt No 735.00 - 805.00
2000 Watt No 890.00 - 1,025.00
3000 Watt No 1,075.00 - 1,225.00
Detailed Rates
2008
Mechanical Services
Hot Water Boilers
Page 4-335
Unit Ak/Wn/Ch/Dn $
2008
Mechanical Services
Flues
Page 4-336
Unit Ak/Wn/Ch/Dn $
28.14 Flues
Boiler Flue, light duty, 0.55mm type 304 stainless
steel, pre-insulated with granular vermiculite, complete
with base plate, draught stabiliser, roof flashing, clean
out door, drain and test connections.
150mm diameter m 305.00 - 315.00
180mm diameter m 340.00 - 350.00
200mm diameter m 365.00 - 390.00
Add extra for roof penetrations, guide wires,
drain pipework
Bend to boiler flue
150mm diameter No 325.00 - 350.00
180mm diameter No 365.00 - 375.00
200mm diameter No 400.00 - 410.00
Commercial Boiler Flue, 0.75mm spiral stainless
steel, white wool insulation held in place with wire
netting, and heavy gauge aluminium cladding
200mm diameter m 365.00 - 390.00
250mm diameter m 450.00 - 460.00
300mm diameter m 580.00 - 605.00
400mm diameter m 690.00 - 725.00
450mm diameter m 790.00 - 825.00
Bend to commercial boiler flue
200mm diameter No 400.00 - 410.00
250mm diameter No 460.00 - 485.00
300mm diameter No 595.00 - 630.00
400mm diameter No 765.00 - 810.00
450mm diameter No 885.00 - 935.00
28.15 Pumps
• Prices include motor and installation but
exclude electrical connection, control gear,
piping and flexible head
Glandless Pump, cast iron, suitable for heating
and chilled water (closed) systems, multi-speed
operating temperature range from -10°C to
+130°C continuous duty
0.5 litre/sec @ 4m head No 490.00 - 585.00
2 litre/sec @ 2m head No 750.00 - 855.00
2 litre/sec @ 3m head No 890.00 - 995.00
3 litre/sec @ 5m head No 1,175.00 - 1,275.00
5 litre/sec @ 4m head No 1,250.00 - 1,350.00
6 litre/sec @ 6m head No 1,600.00 - 1,775.00
8 litre/sec @ 6m head No 1,700.00 - 1,900.00
12 litre/sec @ 6m head No 2,200.00 - 2,400.00
14 litre/sec @ 8m head No 3,175.00 - 3,525.00
Detailed Rates
2008
Mechanical Services
Pumps
Page 4-337
Unit Ak/Wn/Ch/Dn $
Inline Centrifugal Pump, with TEFC motor and
mechanical seal. Cast iron. Operating
temperature range from -10°C to +140°C
3 litre/sec @ 14m head No 1,900.00 - 2,175.00
3 litre/sec @ 20m head No 1,950.00 - 2,225.00
6 litre/sec @ 15m head No 2,025.00 - 2,325.00
6 litre/sec @ 20m head No 2,025.00 - 2,325.00
10 litre/sec @ 14m head No 2,400.00 - 2,700.00
10 litre/sec @ 20m head No 2,650.00 - 2,950.00
15 litre/sec @ 10m head No 2,500.00 - 2,800.00
15 litre/sec @ 14m head No 2,850.00 - 3,175.00
15 litre/sec @ 20m head No 3,325.00 - 3,650.00
20 litre/sec @ 14m head No 3,475.00 - 3,825.00
20 litre/sec @ 19m head No 2,400.00 - 4,025.00
30 litre/sec @ 10m head No 4,950.00 - 5,300.00
30 litre/sec @ 18m head No 5,300.00 - 5,700.00
30 litre/sec @ 25m head No 8,350.00 - 8,850.00
Baseplate Centrifugal Pump, with TEFC motor
and mechanical seal. Cast iron, bronze impeller,
mounted on common base, operating
temperature range -30°C to +140°C
14 litre/sec @ 13m head No 4,075.00 - 4,525.00
14 litre/sec @ 21m head No 4,700.00 - 5,150.00
22 litre/sec @ 13m head No 4,250.00 - 4,700.00
26 litre/sec @ 20m head No 4,875.00 - 5,350.00
26 litre/sec @ 35m head No 4,750.00 - 5,200.00
40 litre/sec @ 14m head No 4,800.00 - 5,250.00
40 litre/sec @ 20m head No 6,450.00 - 7,050.00
40 litre/sec @ 33m head No 6,950.00 - 7,550.00
60 litre/sec @ 15m head No 5,000.00 - 5,500.00
80 litre/sec @ 30m head No 8,000.00 - 8,750.00
100 litre/sec @ 14m head No 6,150.00 - 6,800.00
100 litre/sec @ 22m head No 6,400.00 - 7,050.00
130 litre/sec @ 35m head No 7,950.00 - 8,600.00
Add extra for
Inertia base to baseplate pump No 1,775.00 - 1,925.00
Isolating valves, strainer, check valve
Gauges, flexible pipe connection
Anchors and guides, concrete plinth,
holding down bolts
Submersible Sump Pump, with float switch
2 litre/sec @ 3m head (0.4 kW) No 830.00 - 925.00
3 litre/sec @ 5m head (0.5 kW) No 1,225.00 - 1,325.00
6 litre/sec @ 8m head (1.4 kW) No 2,650.00 - 2,950.00
Detailed Rates
2008
Mechanical Services
Pipework
Page 4-338
Unit Ak/Wn/Ch/Dn $
28.16 Pipework
Black Mild Steel Pipe, with welded joints,
installed complete with hangers and supports,
excludes insulation
25mm dia m 34.75 - 40.25
32mm dia m 43.00 - 47.25
40mm dia m 48.50 - 54.00
50mm dia m 56.00 - 61.00
65mm dia m 69.00 - 75.00
80mm dia m 87.00 - 97.00
100mm dia m 100.00 - 111.00
125mm dia m 146.00 - 160.00
150mm dia m 187.00 - 200.00
200mm dia m 265.00 - 290.00
250mm dia m 390.00 - 415.00
300mm dia m 530.00 - 555.00
350mm dia m 555.00 - 585.00
400mm dia m 655.00 - 695.00
Bend, long radius
25mm dia No 86.00 - 109.00
32mm dia No 108.00 - 137.00
40mm dia No 130.00 - 162.00
50mm dia No 172.00 - 215.00
65mm dia No 205.00 - 255.00
80mm dia No 220.00 - 275.00
100mm dia No 280.00 - 345.00
125mm dia No 340.00 - 415.00
150mm dia No 395.00 - 480.00
200mm dia No 560.00 - 670.00
250mm dia No 815.00 - 955.00
300mm dia No 1,050.00 - 1,225.00
350mm dia No 1,300.00 - 1,500.00
400mm dia No 1,625.00 - 1,850.00
Tee, equal
25mm x 25mm dia No 137.00 - 171.00
32mm x 32mm dia No 172.00 - 215.00
40mm x 40mm dia No 205.00 - 250.00
50mm x 50mm dia No 270.00 - 335.00
65mm x 65mm dia No 330.00 - 405.00
80mm x 80mm dia No 355.00 - 435.00
100mm x 100mm dia No 460.00 - 555.00
150mm x 150mm dia No 655.00 - 785.00
Detailed Rates
2008
Mechanical Services
Pipework
Page 4-339
Unit Ak/Wn/Ch/Dn $
Flanged ends, including gasket and bolts
25mm dia No 74.00 - 89.00
32mm dia No 84.00 - 101.00
40mm dia No 92.00 - 112.00
50mm dia No 113.00 - 139.00
65mm dia No 132.00 - 160.00
80mm dia No 139.00 - 168.00
100mm dia No 205.00 - 245.00
150mm dia No 255.00 - 305.00
Copper Pipe, installed complete with hangers
and supports. Excludes insulation.
Rates not applicable for residential use.
25mm dia m 98.00 - 118.00
32mm dia m 121.00 - 143.00
40mm dia m 133.00 - 152.00
50mm dia m 152.00 - 175.00
65mm dia m 184.00 - 205.00
80mm dia m 250.00 - 275.00
100mm dia m 355.00 - 390.00
Bend, swaged both ends, includes extra bracket
25mm dia No 79.00 - 98.00
32mm dia No 92.00 - 114.00
40mm dia No 102.00 - 127.00
50mm dia No 121.00 - 146.00
65mm dia No 245.00 - 285.00
80mm dia No 395.00 - 455.00
100mm dia No 500.00 - 570.00
Tee, equal, swaged all ends, includes extra bracket
25mm dia No 86.00 - 105.00
32mm dia No 118.00 - 140.00
40mm dia No 140.00 - 165.00
50mm dia No 187.00 - 215.00
65mm dia No 405.00 - 465.00
80mm dia No 525.00 - 590.00
100mm dia No 600.00 - 685.00
Climatherm SDR 11 HVAC Pipe Auck $ Wgtn $ Chch $ Dun $
20mm dia, including fittings m 35.00 32.75 32.75 32.75
25mm dia m 29.50 27.75 27.75 27.75
32mm dia m 40.00 38.00 38.00 38.00
40mm dia m 52.00 49.75 49.75 49.75
63mm dia m 77.00 75.00 75.00 75.00
75mm dia m 106.00 104.00 104.00 104.00
90mm dia m 148.00 145.00 145.00 145.00
110mm dia m 210.00 205.00 205.00 205.00
For bends and tees, Refer to page 4-313
For 125mm, 160mm, 200mm, and 250mm sizes,
refer Aquatherm, www.aquatherm.co.nz
Detailed Rates
2008
Mechanical Services
Valves
Page 4-340
Unit Ak/Wn/Ch/Dn $
28.17 Valves
Bronze Gate Valve, dezincification resistant
bronze body, integral seat, screwed ends.
Rating to 20 bar, 99°C
15mm dia No 39.50 -
48.50
20mm dia No 49.75 -
60.00
25mm dia No 61.00 -
73.00
32mm dia No 73.00 -
85.00
40mm dia No 93.00 - 108.00
50mm dia No 121.00 - 139.00
Cast Iron Gate Valve, flanged ends.
Rating to 14 bar, 80°C
50mm dia No 310.00 - 330.00
80mm dia No 440.00 - 470.00
100mm dia No 545.00 - 575.00
150mm dia No 935.00 - 975.00
Bronze Globe Valve, with integral seat and
renewable composition disc, screwed ends.
Rating to 24 bar, 200°C
15mm dia No 78.00 - 85.00
20mm dia No 104.00 - 113.00
25mm dia No 136.00 - 148.00
32mm dia No 230.00 - 240.00
40mm dia No 250.00 - 265.00
50mm dia No 420.00 - 440.00
Cast Iron Globe Valve, gunmetal trim flanged
ends. Rating to 21 bar, 220°C
50mm dia No 955.00 - 975.00
80mm dia No 1,275.00 - 1,325.00
100mm dia No 1,875.00 - 1,900.00
150mm dia No 3,325.00 - 3,375.00
Ball Valve, stainless steel body and ball,
screwed ends
15mm dia No 35.75 -
43.25
20mm dia No 43.25 -
53.00
25mm dia No 59.00 -
70.00
32mm dia No 78.00 -
92.00
40mm dia No 92.00 - 106.00
50mm dia No 127.00 - 145.00
Cast Iron Butterfly Valve, stainless steel disc,
lever operated for flanged ends.
Rating to 14 bar, 120°C
50mm dia No 330.00 - 355.00
80mm dia No 385.00 - 415.00
100mm dia No 425.00 - 455.00
150mm dia No 515.00 - 555.00
Detailed Rates
2008
Mechanical Services
Pipe Insulation
Page 4-341
Unit Ak/Wn/Ch/Dn $
2008
Mechanical Services
Ductwork—Rectangular
Page 4-342
Unit Ak/Wn/Ch/Dn $
25mm thick insulation to bend
65mm dia No 27.25 - 28.50
80mm dia No 31.75 - 33.00
100mm dia No 38.50 - 39.75
50mm thick insulation to -
150mm dia pipe m 240.00 - 240.00
150mm dia bend No 120.00 - 123.00
Add extra for
Aluminium Sheet Sheathing, 0.7mm thick, to:
25mm insulation over
15mm dia pipe m 36.25 - 39.75
20mm dia pipe m 38.50 - 39.75
25mm dia pipe m 38.50 - 39.75
32mm dia pipe m 46.50 - 50.00
38mm insulation over
40mm dia pipe m 48.75 - 51.00
50mm dia pipe m 50.00 - 53.00
65mm dia pipe m 61.00 - 65.00
80mm dia pipe m 64.00 - 66.00
100mm dia pipe m 67.00 - 68.00
150mm dia pipe m 74.00 - 76.00
28.19 Ductwork—Rectangular
• Prices include installation and hangers but
exclude insulation. Ducting is to SMACNA
Specification for Low Velocity installations.
Rectangular Ductwork, galvanised sheetmetal
In straight sections m2 64.00 - 72.00
In fitting m2 125.00 - 140.00
Fire Damper and Access Panel, fire damper -
vertically mounted, blades concealed. Includes
access panel in adjacent duct.
300mm x 300mm No 340.00 - 375.00
450mm x 300mm No 385.00 - 425.00
600mm x 300mm No 475.00 - 530.00
600mm x 450mm No 520.00 - 580.00
900mm x 300mm No 545.00 - 600.00
900mm x 600mm No 660.00 - 720.00
28.20 Ductwork—Insulation
Acoustic Fibreglass, with aluminium perforated
foil face, fitted inside ductwork
25mm thick, to
Straight duct m2 42.00 - 44.25
Ductwork fittings m2 42.00 - 44.25
50mm thick, to
Straight duct m2 53.00 - 56.00
Ductwork fittings m2 53.00 - 56.00
Detailed Rates
2008
Mechanical Services
Ductwork—Spiral
Page 4-343
Unit Ak/Wn/Ch/Dn $
Thermal Foil Backed Fibreglass, fitted
externally to ductwork
25mm thick, to
Straight duct m2 23.75 - 27.25
Ductwork fittings m2 23.75 - 27.25
50mm thick, to
Straight duct m2 30.75 - 34.00
Ductwork fittings m2 30.75 - 34.00
28.21 Ductwork—Spiral
Spiral Ductwork, galvanised mild steel,
including spin collar to joints, uninsulated
Straight duct
100mm dia m 23.25 - 28.25
150mm dia m 28.25 - 31.75
200mm dia m 31.75 - 36.75
250mm dia m 39.25 - 44.00
300mm dia m 45.25 - 53.00
350mm dia m 53.00 - 60.00
400mm dia m 60.00 - 69.00
450mm dia m 71.00 - 82.00
500mm dia m 93.00 - 105.00
600mm dia m 110.00 - 125.00
700mm dia m 144.00 - 160.00
800mm dia m 184.00 - 210.00
900mm dia m 205.00 - 230.00
Bend, 90°, self aligning, includes for mastic
sealing of joints
100mm dia No 34.25 - 39.25
150mm dia No 34.25 - 39.25
200mm dia No 44.00 - 47.75
250mm dia No 53.00 - 59.00
300mm dia No 73.00 - 80.00
350mm dia No 97.00 - 104.00
400mm dia No 122.00 - 130.00
450mm dia No 144.00 - 154.00
500mm dia No 148.00 - 160.00
600mm dia No 198.00 - 210.00
700mm dia No 235.00 - 250.00
800mm dia No 590.00 - 615.00
900mm dia No 745.00 - 770.00
Spigot saddle, 90°, no damper
100mm dia No 39.25 - 42.75
200mm dia No 42.75 - 47.75
300mm dia No 62.00 - 69.00
400mm dia No 80.00 - 88.00
Detailed Rates
2008
Mechanical Services
Ductwork—Flexible Aluminium
Page 4-344
Unit Ak/Wn/Ch/Dn $
2008
Mechanical Services
Inlet Louvres
Page 4-345
Unit Ak/Wn/Ch/Dn $
Sidewall Supply Register, baked enamel
finish, double deflection blades, integral OBD,
and including wall mounting.
300mm x 150mm No 149.00 - 170.00
450mm x 150mm No 186.00 - 210.00
450mm x 300mm No 235.00 - 260.00
600mm x 300mm No 285.00 - 315.00
600mm x 450mm No 350.00 - 380.00
Exhaust and Return Grille, aluminium finish,
egg crate type with 12.5mm x 12.5mm
aluminium core, mounted in ceiling.
150mm x 150mm No 83.00 - 98.00
200mm x 200mm No 91.00 - 105.00
300mm x 300mm No 114.00 - 130.00
450mm x 450mm No 155.00 - 174.00
600mm x 600mm No 215.00 - 235.00
Door Grilles, baked enamel finish, flanged
surround with sightproof core.
300mm x 200mm No 151.00 - 174.00
400mm x 300mm No 205.00 - 230.00
500mm x 300mm No 220.00 - 245.00
500mm x 450mm No 290.00 - 320.00
2008
Mechanical Services
Powered Ventilation
Page 4-346
Unit Ak/Wn/Ch/Dn $
2008
Mechanical Services
Electrical Installation Guide
Page 4-347
Unit Ak/Wn/Ch/Dn $
Roof Mounted High Velocity Vertical
Discharge Exhaust Ventilator, of three phase
single speed industrial type design with wind
baffles, butterfly dampers and aerofoil blade,
with nominal system resistance of 60 Pa. Sized
to suit areas where higher noise levels are
acceptable (e.g. commercial, industrial)
3.5 m3/second No 2,325.00 - 2,575.00
5.0 m3/second No 2,900.00 - 3,575.00
6.5 m3/second No 3,175.00 - 3,575.00
9.5 m3/second No 4,200.00 - 4,875.00
12 m3/second No 5,400.00 - 7,400.00
15 m3/second No 5,750.00 - 7,800.00
17 m3/second No 6,200.00 - 10,500.00
23 m3/second No 6,650.00 - 11,400.00
Add extra for
Smoke spill application
3.5–9.5 m3/second No 270.00 - 540.00
9.5–15 m3/second No 405.00 - 675.00
15–23 m3/second No 675.00 - 1,350.00
Dual speed smoke spill
3.5–9.5 m3/second No 270.00 - 540.00
9.5–15 m3/second No 540.00 - 1,000.00
15–23 m3/second No 1,200.00 - 2,425.00
Roof opening and prepared upstand for fan
0–5 m3/second No 305.00 - 365.00
5–9.5 m3/second No 490.00 - 550.00
9.5–12 m3/second No 890.00 - 950.00
15–23 m3/second No 1,225.00 - 1,475.00
• For cost of electrical installation of fans, Refer
to page 4-355
2008
Mechanical Services
Natural Ventilation
Page 4-348
Unit Ak/Wn/Ch/Dn $
2008
Fire Protection
Extinguishers
Page 4-349
Unit Ak/Wn/Ch/Dn $
29 Fire Protection
29.1 Extinguishers
Wall Mounted Extinguisher and bracket
Dry powder ABC type, capacity
2.25 kg No 180.00
4.50 kg No 225.00
9.00 kg No 300.00
CO2, capacity
2.00 kg No 300.00
3.50 kg No 335.00
5.00 kg No 370.00
2008
Fire Protection
Pumps
Page 4-350
Unit Ak/Wn/Ch/Dn $
29.4 Pumps
Primary Supply, with fuel tank and control No 43,500 - 50,000
panel, diesel driven booster pump
Secondary Supply, with motor and control No 25,000 - 31,000
panel, electric driven booster pump
Tank, 20,000 litres, including pipework No 4,975 - 7,475
2008
Fire Protection
Dry Pipe Sprinklers
Page 4-351
Unit Ak/Wn/Ch/Dn $
Junctions—reducing or equal size
25mm dia No 24.00 -
29.00
32mm dia No 29.00 -
35.00
40mm dia No 35.00 -
40.00
50mm dia No 55.00 -
60.00
65mm dia No 100.00 - 110.00
80mm dia No 150.00 - 160.00
100mm dia No 230.00 - 240.00
Gate Valve, including union, screwed joints to
pipework
25mm dia No 95.00 - 105.00
32mm dia No 150.00 - 160.00
40mm dia No 160.00 - 170.00
50mm dia No 245.00 - 255.00
Gate Valve, including flanged joints to pipework
65mm dia No 430.00 - 440.00
80mm dia No 450.00 - 460.00
100mm dia No 525.00 - 550.00
150mm dia No 850.00 - 875.00
Add extra for pumps, fire indicator boards, etc.
2008
Lifts and Escalators
Passenger Lifts
Page 4-352
2008
Lifts and Escalators
Goods/Service Lifts
Page 4-353
2008
Lifts and Escalators
Escalators and Moving Walkways
Page 4-354
Installation Additional
Cost $ Cost $
2008
Electrical Services
Cable Supply Prices
Page 4-355
31 Electrical Services
31.1 Cable Supply Prices
• Rates on following pages are based on
cable supply prices issued on
1 September 2008.
• Copper and aluminium prices increased again
during 2008. Here is a summary of published
increases since December 2005. Note, some
increases approximate. Copper Aluminium
1 December 2005 6.50% 6.50%
1 February 2006 9.25% 9.25%
1 March 2006 12.00% 8.20%
1 April 2006 7.25% -
1 May 2006 8.00% -
1 June 2006 15.00% 5.00%
1 July 2006 15.00% 5.00%
1 August 2006 9.75% -
1 September 2006 9.85% -
1 June 2007 15.00% -
1 October 2007 5.50% -
1 December 2007 5.00% -
1 April 2008 5.00% 7.50%
15 April 2008 4.50% -
1 May 2008 4.00% 4.00%
1 June 2008 4.00% -
7 July 2008 4.00% -
1 September 2008 4.00% 4.00%
1 October 2008 4.00% 4.00%
• And in case you were wondering. Jan 2005 May 2008 Aug 2008
Rio Tinto share price $AU40.00 $AU156.00 $AU125.00
2008
Electrical Services
General Note
Page 4-356
2008
Electrical Services
Service Mains—Underground, Copper
Page 4-357
2008
Electrical Services
Switchboards—Custom Built
Page 4-358
2008
Electrical Services
Switchboards—Proprietary
Page 4-359
31.9 Switchboards—Proprietary
• Recessed cabinet of sheet metal type, built-in.
Insulated panel and electrical components
given separately
Main Switchboards
Domestic Meterbox
Single phase No 490.00 - 590.00
Three phase No 730.00 - 875.00
House or strata title unit
Panel with rewirable fuses No 390.00 - 470.00
Panel with MCB No 425.00 - 510.00
Recessed cabinet, bare No 255.00 - 305.00
Pole mounted cabinet No 305.00 - 365.00
Small/light workshop
Panel with rewirable fuses No 305.00 - 365.00
Panel with MCB No 425.00 - 510.00
Recessed cabinet, bare No 255.00 - 305.00
MCB, 1 phase No 30.50 - 36.75
MCB, 3 phase No 170.00 - 205.00
Small block of home units (5 to 10 units)
Panel with rewirable fuses No 850.00 - 1,020.00
Recessed cabinet, bare No 765.00 - 915.00
MCB, 1 phase No 30.50 - 36.75
Distribution Switchboards
Small workshop unit
Panel with rewirable fuses No 270.00 - 325.00
Panel with MCB No 375.00 - 450.00
Detailed Rates
2008
Electrical Services
Submains
Page 4-360
31.10 Submains
• Prices can be ascertained from various
detailed prices, i.e.
Cable, Refer to page 4-362
Tray, Refer below
2008
Electrical Services
Conduits
Page 4-361
31.12 Conduits
• Prices include nominal number of fittings
PVC Conduit
Fixed to concrete masonry, cast into concrete or
installed in roof space
20mm diameter 0.22 m 14.75 - 16.25
25mm diameter 0.22 m 15.50 - 17.00
32mm diameter 0.22 m 16.75 - 18.50
Buried underground, including protection strip,
but excluding trench excavation and backfill
20mm diameter 0.24 m 16.00 - 18.00
25mm diameter 0.24 m 16.75 - 18.75
32mm diameter 0.24 m 18.25 - 20.00
50mm diameter 0.27 m 24.00 - 26.00
100mm diameter 0.27 m 25.50 - 27.50
Galvanised Steel Conduit
Fixed to concrete masonry, cast into
concrete or installed in roof space
20mm diameter 0.28 m 25.75 - 28.00
25mm diameter 0.28 m 28.00 - 30.25
32mm diameter 0.38 m 37.25 - 40.00
2008
Electrical Services
Cable—Generally
Page 4-362
31.14 Cable—Generally
• Cables are expressed as: conductor size in
mm2 (nominal overall diameter)
• Rates exclude conduits and trays
31.15 Cable—Aluminium
Set of Four Single Core XLPE/PVC Cables
drawn into conduit or fixed to cable tray
95mm2(13.7mm) 0.40 m 162.00 - 165.00
95mm2 (13.7mm)+16mm2 Cu earth 0.45 m 184.00 - 188.00
120mm2 (15.4mm) 0.40 m 215.00 - 220.00
120mm2 (15.4mm)+70mm2 Cu earth 0.45 m 295.00 - 300.00
150mm2 (17.3mm) 0.40 m 220.00 - 220.00
150mm2 (17.3mm)+70mm2 Cu earth 0.45 m 300.00 - 300.00
185mm2 (19.3mm) 0.60 m 285.00 - 290.00
185mm2 (19.3mm)+70mm2 Cu earth 0.66 m 365.00 - 370.00
240mm2 (22mm) 0.60 m 345.00 - 350.00
240mm2 (22mm)+70mm2 Cu earth 0.66 m 425.00 - 430.00
31.16 Cable—Copper
Set of Four Single Insulated XLPE/PVC
Cables drawn into conduit or fixed to cable tray
1.5mm2 (3.6mm) 0.04 m 14.50 - 14.75
1.5mm2 (3.6mm) + 2.5mm2 earth 0.05 m 19.25 - 19.75
2.5mm2 (3.7mm) 0.04 m 19.50 - 20.00
2.5mm2 (3.7mm) + 2.5mm2 earth 0.05 m 24.50 - 24.75
4mm2 (4.3mm) 0.08 m 26.50 - 27.25
4mm2 (4.3mm) + 2.5mm2 earth 0.09 m 31.50 - 32.00
6mm2 (4.8mm) 0.12 m 33.50 - 34.50
6mm2 (4.8mm) + 2.5mm2 earth 0.13 m 38.25 - 39.25
10mm2 (6.2mm) 0.12 m 82.00 - 83.00
10mm2 (6.2mm) + 4mm2 earth 0.13 m 88.00 - 89.00
16mm2 (7.0mm) 0.12 m 115.00 - 116.00
16mm2 (7.0mm) + 6mm2 earth 0.14 m 123.00 - 124.00
25mm2 (9.0mm) 0.16 m 131.00 - 132.00
25mm2 (9.0mm) + 10mm2 earth 0.18 m 148.00 - 149.00
35mm2 (10.2mm) 0.16 m 169.00 - 171.00
35mm2 (10.2mm) + 16mm2 earth 0.18 m 192.00 - 193.00
50mm2 (11.9mm) 0.20 m 220.00 - 220.00
50mm2 (11.9mm) + 25mm2 earth 0.23 m 255.00 - 255.00
70mm2 (13.7mm) 0.20 m 315.00 - 315.00
70mm2 (13.7mm) + 35mm2 earth 0.23 m 365.00 - 365.00
95mm2 (16.0mm) 0.20 m 410.00 - 415.00
95mm2 (16.0mm) + 50mm2 earth 0.23 m 470.00 - 475.00
120mm2 (16.3mm) 0.24 m 525.00 - 525.00
120mm2 (16.3mm) + 70mm2 earth 0.27 m 600.00 - 605.00
Detailed Rates
2008
Electrical Services
Cable—Copper
Page 4-363
2008
Electrical Services
Cable—Fire Rated
Page 4-364
2008
Electrical Services
Cable—Fire Rated
Page 4-365
2008
Electrical Services
Subcircuits—Lighting, Domestic
Page 4-366
2008
Electrical Services
Subcircuits—Power, Commercial
Page 4-367
31.22 Subcircuits—Heating
• Prices include accessories and wiring from
switch-board but exclude switchboard, carpet,
underlay
Storage Floor Heating (220 w/m2) cast in slab
Domestic 1.82 No 158.00 - 170.00 20.0
Commercial 2.70 No 420.00 - 440.00 34.0
Panel Heater including wall thermostat
Domestic No 450.00 - 540.00
Commercial No 480.00 - 580.00
2008
Electrical Services
Luminaires—Interior, Commercial
Page 4-368
2008
Electrical Services
Luminaires—Interior, Industrial
Page 4-369
2008
Electrical Services
Luminaires—Exterior, Floodlighting
Page 4-370
2008
Electrical Services
Lighting Columns
Page 4-371
2008
Electrical Services
Emergency Lighting
Page 4-372
2008
Electrical Services
Power Equipment—Sockets
Page 4-373
2008
Electrical Services
Power Equipment—Underfloor Heating
Page 4-374
2008
Electrical Services
Power Equipment—Control Equipment
Page 4-375
2008
Electrical Services
Power Equipment—Hospital Equipment
Page 4-376
2008
Electrical Services
Power Equipment–Hospital Call Stations
Page 4-377
2008
Electrical Services
As-Built and Maintenance Manuals
Page 4-378
2008
Electrical Services
Personal Paging
Page 4-379
2008
Electrical Services
Clocks
Page 4-380
31.45 Clocks
Master Clock Controller for up to 50 Sum 4,225.00 - 5,100.00
clocks
Relay, up to 50 additional clocks per relay Sum 515.00 - 615.00
Slave Clock
230mm diameter No 455.00 - 545.00
300mm diameter No 480.00 - 575.00
300mm diameter, double sided, No 950.00 - 1,145.00
ceiling suspended
Add extra for
Electrical control circuit to slave Point 75.00 - 90.00
clocks
Mains Clock
230mm diameter No 260.00 - 315.00
300mm diameter No 300.00 - 360.00
460mm diameter No 650.00 - 780.00
Add extra for
Electrical supply circuit to mains Point 65.00 - 79.00
clocks
Battery Clock
230mm diameter No 111.00 - 133.00
300mm diameter No 155.00 - 186.00
300mm diameter double sided, No 635.00 - 760.00
ceiling suspended
Job Costing/Attendance Recorder
Up to 30 employees No 3,900.00 - 4,700.00
Exceeding 30 employees No 4,875.00 - 5,850.00
Attendance and Payroll Recorder, No 6,500.00 - 7,800.00
electronic, maximum 200 employees
2008
Electrical Services
Background Music
Page 4-381
2008
Electrical Services
Access Control Systems
Page 4-382
2008
Electrical Services
Closed Circuit Television
Page 4-383
2008
Solid Plaster
Preparatory Work
Page 4-384
32 Solid Plaster
• Prices are for new work only. For alterations
and additions, Refer to page 4-129
• Prices for plaster include protection and
making good around pipes, etc.
2008
Solid Plaster
Tyrolean Plaster
Page 4-385
2008
Solid Plaster
Hardwall Plaster
Page 4-386
2008
Plasterboard Linings
Supply Prices—Retail
Page 4-387
33 Plasterboard Linings
• Rates are for supply, fixing and stopping to
level 4 finish, of plasterboard linings, on wall or
ceiling framing
• Stopping is included at a rate of $9 per m2.
2008
Plasterboard Linings
BPB Supply Prices—Trade
Page 4-388
2008
Plasterboard Linings
Fire-Rated, Walls, 2 Way FRR
Page 4-389
2008
Plasterboard Linings
Fire-Rated, Universal Walls, 1 Way FRR
Page 4-391
2008
Plasterboard Linings
Radiation Protection Linings
Page 4-392
33.13 Stopping
To level 4 finish, note this is included in m2 8.00 8.00 8.00 8.00
plasterboard rates given, at $9/m2 -12.00 -12.00 -12.00 -12.00
To level 5 finish m2 15.00 15.00 15.00 15.00
-19.00 -19.00 -19.00 -19.00
To metal angles etc m 4.00 4.00 5.25 4.00
Square, between walls and ceilings m 5.00 5.00 5.00 5.00
33.14 Labours
Add extra to labour costs for
Fixing to flat ceiling 3m–4m high % + 20% + 20% + 20% + 20%
10mm board m2 1.85 1.75 1.75 1.75
13mm board m2 2.30 2.20 2.20 2.20
Fixing to sloping ceiling 3m–5m high % + 25% + 25% + 25% + 25%
10mm board m2 2.30 2.20 2.20 2.20
13mm board m2 2.75 2.65 2.65 2.65
Raking cut to wall board m 2.00 2.00 2.00 2.00
33.15 Coves
Paper-Bound Plaster Cove
55mm classic m 8.30 8.30 8.00 8.00
50mm alto m 13.00 13.25 12.50 12.50
75mm classic m 9.50 9.40 8.80 8.90
75mm soprano m 14.25 14.50 13.25 13.75
90mm classic m 11.25 11.25 10.75 10.75
90mm treble m 14.50 15.50 14.00 14.25
2008
Plasterboard Linings
Fibrous Plaster
Page 4-393
2008
Suspended Ceilings
Concealed Grid Suspended Ceiling
Page 4-394
34 Suspended Ceilings
• Prices are based on a finished ceiling
height of 2.5m to 3m above floor level, a
minimum area of 250m2 and include
hangers, clips, edge trim and minor
labours.
• Prices are for new work only. Refer to page 4-128
2008
Suspended Ceilings
Open Cell Ceilings
Page 4-395
2008
Suspended Ceilings
Linear Ceilings
Page 4-396
2008
Tiling
Wall Tiling
Page 4-397
35 Tiling
• $Value/m2 is indicative value for material to be
supplied. Adjust rates as necessary if more or
less expensive product required
2008
Tiling
Floor Tiling
Page 4-398
35.3 Labours
Extra over for
Small areas m2 22.00 22.00 22.00 22.00
Laying with adhesive m2 0.00 0.00 0.00 0.00
Cutting and fitting around pipes etc No 5.50 5.50 5.50 5.50
Working in narrow widths generally m 13.75 13.75 13.75 13.75
2008
Tiling
Division Strips and Weather Bars
Page 4-399
2008
Resilient Flooring
Carpet—Woven
Page 4-400
36 Resilient Flooring
• Prime Cost Allowance column gives indicative
trade supply price for material. Adjust rates as
necessary if more or less expensive product
required
• Allow extra waste for small areas and where
room dimensions are not economical relative
to roll widths
• Floor levelling compounds, Refer to page 4-398
36.1 Carpet—Woven
• Prices are for laying by direct stick method.
• Prices are based on a minimum of 300m2
Wilton—100% wool
Heavy duty m2 105.00 - 115.00 70.00
Axminster —80% wool, 20% nylon
Medium duty m2 88.00 - 98.00 65.00
Heavy duty m2 110.00 - 120.00 75.00
36.2 Carpet—Tufted
Loop Pile, heavy duty
100% wool m2 45.00 - 50.00 35.00
100% nylon m2 30.00 - 33.00 25.00
Foam backed, 100% nylon m2 35.00 - 38.00 30.00
100% polypropylene m2 25.00 - 30.00 20.00
100% polypropylene m2 35.00 - 40.00 30.00
Loop Pile, extra heavy duty
100% nylon m2 35.00 - 39.00 30.00
100% wool m2 46.00 - 50.00 40.00
Cut Pile, heavy duty
100% wool m2 53.00 - 55.00 45.00
80% wool 20% nylon m2 53.00 - 55.00 45.00
100% nylon m2 42.00 - 45.00 35.00
Add extra for
Smooth edge m 2.75 - 3.25
Wall to wall fitting, including fixing strips, m2 5.50 - 6.50
protection and cleaning, excluding
underlay
Double stick method, including adhesive m2 13.25 - 15.50
and rubber underlay
Foam back tufted carpet m2 4.00 - 6.00
36.3 Underlay
Wool felt m2 4.00 - 6.00
Waffle back m2 6.00 - 8.00
Foam chip m2 4.00 - 6.00
Rubber slab m2 5.00 - 7.00
Detailed Rates
2008
Resilient Flooring
Carpet Tiles
Page 4-401
36.6 Linoleum
Linoleum, laid on prepared floor surfaces
Medium traffic, 2.5mm thick m2 63.00 - 73.00 42.50
2008
Resilient Flooring
Vinyl Sheet
Page 4-402
2008
Resilient Flooring
Rubber Flooring
Page 4-403
36.12 Skirtings
Carpet Skirting
100mm m 8.00 - 10.00
150mm m 10.00 - 12.00
Detailed Rates
2008
Resilient Flooring
Matting and Matwell Frames
Page 4-404
2008
Resilient Flooring
Stair Tread Nosings
Page 4-405
2008
Painting & Specialist Finishes
Interior Painting—Timber
Page 4-406
2008
Painting & Specialist Finishes
Interior Painting—Walls and Ceilings
Page 4-407
2008
Painting & Specialist Finishes
Preparation of Existing Surfaces
Page 4-408
2008
Painting & Specialist Finishes
Paper Hanging
Page 4-409
2008
Painting & Specialist Finishes
Specialist Finishes—Floors, Heavy Duty
Page 4-410
2008
Painting & Specialist Finishes
Specialist Finishes—Ceilings
Page 4-411
2008
Painting & Specialist Finishes
Specialist Finishes—Walls, Exterior
Page 4-412
2008
Glazing
Clear Float Glass
Page 4-413
38 Glazing
• Prices are for site glazing. For shop glazing,
labour content could reduce by 10 to 15%.
• Prices are based on dry glazing to aluminium,
with snap-on glazing beads in pane sizes of
0.2m2 to 2m2.
• Allow for additional labour as required
For pane sizes under 0.2m2 % +15%
For pane sizes 2m2 to 6m2 % +10%
For pane sizes over 6m2 % +30%
Glazing to colonial sashes % +50%
Non-rectangular shapes % +10%
Circles and ovals % +20%
Add extra for
Glazing to wood with putty m2 4.50 4.50 4.50 4.50
Glazing to metal with putty m2 6.70 6.70 6.70 6.70
Glazing with nailed beads m2 2.25 2.25 2.25 2.25
Glazing with screwed beads m2 4.50 4.50 4.50 4.50
2008
Glazing
Solar Control Glass
Page 4-414
2008
Glazing
Louvres
Page 4-415
38.9 Louvres
Louvre Blades, cut to size, rough arrised edges
Clear, 150mm wide
4mm m 13.50 13.50 13.50 13.50
5/6mm obscure or plain m 18.00 18.00 18.00 18.00
6mm Georgian wired polished m 31.50 31.50 31.50 31.50
6mm Georgian wired cast m 20.25 20.25 20.25 20.25
Tinted, 150mm wide
4mm m 15.75 15.75 15.75 15.75
5/6mm obscure or plain m 20.25 20.25 20.25 20.25
38.10 Mirrors
Clear Float Glass Mirror, 6mm x 1000mm x
1000mm, silvered and copper backed
Fixed with mirror screws No 215.00 215.00 215.00 215.00
Fixed in aluminium frame top/bottom No 235.00 235.00 235.00 235.00
Two Way Observation Mirror, in opening No 215.00 215.00 215.00 215.00
900mm x 600mm
Optically Designed Security Mirror, 600mm No 260.00 260.00 260.00 260.00
dia, for “blind spots”, complete with clamp fixings
Safety Mirror, 4mm vinyl backed, clear m2 118.00 118.00 118.00 118.00
Mirror Tiles, 300mm x 300mm, fixed to wall with
stick-on pads
Clear, plain edge m2 112.00 112.00 112.00 112.00
Clear, bevelled edge m2 135.00 135.00 135.00 135.00
Tinted, plain edge m2 144.00 144.00 144.00 144.00
Tinted, bevelled edge m2 157.00 157.00 157.00 157.00
2008
Glazing
Acrylic Sheet
Page 4-416
Thickness of Glass
Edge Processing 0-6mm 8-10mm 12mm over 12mm
• Prices are indicative for all centres
Rough arrised (arris = sharp edge) m 2.25 2.25 2.80
Smooth arrised
Straight m 5.60 10.00 18.00 39.25
Shaped, circles and ovals m 11.25 16.75 22.50 25.75
Round and polished
Straight m 11.25 20.25 37.00 62.00
Shaped circles and ovals m 16.75 31.50 45.00 76.00
Flat Polished
Straight m 5.60 10.00 18.00 39.25
Shaped circles and ovals m 6.70 12.25 21.25 47.25
Radiused polished corners No 5.60 5.60 6.70 6.70
Mitres, 22½° and 45° m 23.50 23.50 23.50 23.50
Detailed Rates
2008
Glazing
Curved Glass—Supply Only
Page 4-417
2008
Fire Proofing
Cementitious Sprayed Fire Proofing
Page 4-418
39 Fire Proofing
• Prices given are a guide for estimating
purposes. Specific requirements should be
discussed with the manufacturer
• The Hp/A ratio given hereafter is as follows
Hp/A =Heated perimeter of exposed steelwork in m
cross-sectional Area of steel member in m2
2008
Fire Proofing
Intumescent Coatings
Page 4-419
Unit Ak/Wn/Ch/Dn $
Add extra for
50 micron Zinc phosphate primer m2 15.00
Sealer for external work m2 10.00
• Abrasive blast, Refer to page 4-171
2008
Fire Proofing
Fire Stop Collars
Page 4-420
Unit Ak/Wn/Ch/Dn $
2008
Fire Proofing
Fire Resistant Seismic Floor Joints
Page 4-421
Unit Ak/Wn/Ch/Dn $
2008
External Works
Base Course
Page 4-422
40 External Works
• For major earthworks, roads and bridges and
large quantities, Refer to page 4-430
• For geotextiles, Refer to page 4-426
• Crash and guard rails, Refer to page 4-185
2008
External Works
Paving
Page 4-423
40.5 Paving
Large Format Pavers, on prepared foundations
Precast concrete, plain grey
450mm x 450mm x 40mm paving m2 72.00 72.00 57.00 62.00
600mm x 600mm x 40mm paving m2 68.00 68.00 46.75 51.00
Feature paver, various makes
450mm x 450mm or 500mm x 500mm x m2 70.00 70.00 70.00 70.00
40mm paving -100.00 -100.00 -100.00 -100.00
600mm x 600mm x 40mm paving m2 90.00 90.00 90.00 90.00
-120.00 -120.00 -120.00 -120.00
Small and Medium Format Pavers, on prepared
foundations
Cobblestones, 60mm thick (23/m2) m2 66.00 70.00 69.00 63.00
Concrete brick pavers, 50mm thick (50/m2) m2 63.00 71.00 80.00 70.00
Boulevard paver, 300mm x 300mm x 60mm m2 68.00 68.00 74.00 86.00
Open Cell Grass and Turf Pavers
Gobiblock paver, 200mm x 200mm m2 66.00 90.00 87.00 86.00
Grasspaver, 400mm x 400mm x 80mm thick m2 58.00 69.00 68.00 62.00
Turfblock, 600mm x 400mm x 84mm m2 52.00 52.00 51.00 51.00
Add for
Bidim A14 geotextile in 2 layers, wrapped m2 13.50 13.50 13.00 13.00
Basecourse, Refer to page 4-422
Sand bedding, Refer to page 4-422
Insitu Concrete Paving, including mesh reinforcing,
formwork to edges and broomed finish.
17.5MPa 19mm concrete
75mm thick, no reinforcing m2 41.75 40.25 36.75 39.00
100mm thick m2 68.00 67.00 62.00 65.00
150mm thick m2 85.00 83.00 76.00 81.00
200mm thick m2 102.00 99.00 90.00 96.00
200mm x 200mm edge thickening m 14.00 13.50 12.00 13.25
20MPa 19mm exposed aggregate concrete, at
lower end of supply price range
100mm thick m2 75.00 73.00 66.00 73.00
150mm thick m2 94.00 91.00 81.00 91.00
200mm thick m2 113.00 108.00 95.00 108.00
20MPa 19mm exposed aggregate concrete, at
upper end of supply price range
100mm thick m2 87.00 85.00 79.00 84.00
150mm thick m2 112.00 108.00 100.00 107.00
200mm thick m2 136.00 131.00 121.00 130.00
Kiln Fired Clay Paver, 230mm x 115mm x m2 61.00 63.00 59.00 61.00
60mm (38/m2) including sand bedding, cutting
and haunching
Detailed Rates
2008
External Works
Kerbs and Channels
Page 4-424
40.7 Culverts
• Prices include excavation, backfilling, and
disposal of surplus.
Precast Concrete Box Culvert, 600mm x m 120.00 120.00 120.00 120.00
450mm -170.00 -170.00 -170.00 -170.00
• For larger civil engineering culverts, Refer to
page 4-432
2008
External Works
Top Soil
Page 4-425
40.10 Grassing
Lawn Areas, 100mm layer of loam spread and m2 6.00 6.00 6.00 6.00
levelled, sown with approved couch grass seed -8.00 -8.00 -8.00 -8.00
at 0.7 kg/10m2, and maintaining for 6 months
Level, Grade, Prepare and Sow Grass Seed,
including preparatory fertilizing, watering and
maintaining for six months
Bowling greens and the like m2 8.00 8.00 8.00 8.00
-12.00 -12.00 -12.00 -12.00
Playing fields, golf courses and the like ha 8,000.00 8,000.00 8,000.00 8,000.00
-10,000.00 -10,000.00 -10,000.00 -10,000.00
Instant Lawn, including watering and m2 12.00 12.00 12.00 12.00
maintaining for six months
Bark in 100mm thick mulch layer m2 6.00 6.00 6.00 6.00
Hydro Mulch, sprayed seed, Refer to page 4-431
2008
External Works
Tree Grates
Page 4-426
2008
External Works
Fences—Timber
Page 4-427
40.14 Fences—Timber
• Prices include 100mm x 75mm H4 treated
posts, excavation and concrete footings, with
two 100mm x 50mm H3 treated rails.
Timber Paling Fence, posts at 2.4m centres
150mm x 19mm H3 treated palings
1500mm high m 92.00 92.00 92.00 92.00
1800mm high m 95.00 95.00 95.00 95.00
2400mm high m 110.00 110.00 110.00 110.00
150mm x 25mm H3 treated palings
1500mm high m 96.00 96.00 96.00 96.00
1800mm high m 101.00 101.00 101.00 101.00
2400mm high m 117.00 117.00 117.00 117.00
Timber Trellis Fence, trellis H3 treated, with
23mm x 23mm rebated edging, posts at 1.8m
centres
1800mm high, Venetian m 165.00 165.00 165.00 165.00
1800mm high, diagonal 70mm gap m 165.00 165.00 165.00 165.00
2400mm high, square 50mm gap m 190.00 190.00 190.00 190.00
2008
External Works
Retaining Walls—Interlocking Units
Page 4-428
2008
External Works
Street Furniture—Seats
Page 4-429
2008
Civil Engineering
Excavation
Page 4-430
Unit Ak/Wn/Ch/Dn $
41 Civil Engineering
• Prices are based on large quantities for work in
excess of 1000 m3.
• For small quantities, Refer to page 4-133.
• Prices do not include allowance for
Preliminaries
• Site preparation, Refer to page 4-133
41.1 Excavation
Strip Top Soil, average 150mm deep, deposit in m3 1.80 - 4.20
temporary stockpile within 500m
Excavate Top Soil from spoil heap, carry not
exceeding 500m, spread and level, average
150mm thick
On level areas m3 3.00 - 4.80
On battered areas m3 4.20 - 6.60
Balanced Cut To Fill over site, average 500mm m3 3.50 - 6.10
to 1m deep, including drying/wetting and
compaction
Cut and Remove to Stockpile, within 500m m3 1.80 - 4.20
Ripping/Discing, additional cost m2 0.35 - 0.50
Load and Cart unsuitable material to stockpile m3 6.00 - 9.20
Bulk Excavate to reduce levels and deposit
material in spoil heaps within 1 km, in
Sand m3 7.20 - 9.60
Light soil m3 7.20 - 9.00
Clay m3 8.40 - 12.00
Add extra for cartage, per additional km m3 1.20 - 2.40
Excavate to Reduce Levels, spread within
1km, in
Sand m3 9.00 - 10.25
Light soil m3 9.00 - 11.50
Clay m3 10.25 - 14.50
Add extra for
Cartage, per additional km m3 1.20 - 2.40
Compaction to 90% m3 2.40 - 3.00
Excavate From Pit and Deposit as Fill within m3 10.25 - 16.75
1km, including compaction
Excavate and Load For Foundations,
Retaining Wall Footing or the like, including
maintaining sides, working spaces allowance
Not exceeding 1.5m deep, in
Sand m3 7.80 - 9.60
Light soil m3 7.80 - 10.75
Clay m3 9.60 - 10.75
Detailed Rates
2008
Civil Engineering
Surface Treatments
Page 4-431
Unit Ak/Wn/Ch/Dn $
1.5/3.0m deep in
Sand m3 9.00 - 10.25
Light soil m3 9.00 - 11.50
Clay m3 10.75 - 12.50
Excavate in Rock and Load
Soft rock m3 65.00 - 108.00
Hard rock m3 90.00 and up
41.3 Filling
Imported Fill carted not more than 20km,
levelled and compacted
Clay filling m3 30.00 - 66.00
Hard filling, GAP65 m3 42.00 - 78.00
Hard filling, GAP40 m3 42.00 - 78.00
Add extra for
Cartage, per additional km m3 1.20 - 2.40
41.4 Stabilisation
Hydro Mulch, sprayed grass seed compound m2 1.10 - 1.45
Straw Mulch, sprayed straw and bitumen m2 3.70 - 4.20
application
• Geotextiles, Refer to page 4-426
• Soil and Grassing, Refer to page 4-425
41.5 Roadworks
Basecourse, including supply, grading, rolling
and compaction
NRB M/4
150mm thick m2 9.00 - 9.60
300mm thick m2 14.50 - 16.75
Lime stabilized
75mm thick m2 6.70 - 7.80
100mm thick m2 7.20 - 8.40
Lean concrete (18:1)
100mm thick m2 11.50 - 12.00
150mm thick m2 16.25 - 18.00
Chip Seal Paving, sprayed bitumen with first m2 10.75 - 13.50
coat grade 3 chip and second coat grade 5 chip
Asphalt
35mm thick m2 17.50 - 21.25
40mm thick m2 21.25 - 25.00
50mm thick m2 25.00 - 28.75
Detailed Rates
2008
Civil Engineering
Culverts
Page 4-432
Unit Ak/Wn/Ch/Dn $
Concrete (30MPa) including fabric
reinforcement
150mm thick m2 60.00 - 72.00
200mm thick m2 90.00 - 102.00
• Kerbs, Refer to page 4-424
• Stormwater Drainage, Refer to page 4-323
41.6 Culverts
Precast Concrete Box Culvert, laid on ground,
including minimal excavation, size
1500 x 1500mm m 1,500.00 - 2,050.00
2400 x 2400mm m 2,350.00 - 2,900.00
For smaller culverts, Refer to page 4-424
Precast Concrete Pipe Culvert, laid on ground,
including minimal excavation, pipe size
750mm dia m 475.00 - 540.00
1200mm dia m 865.00 - 945.00
1500mm dia m 1,335.00 - 1,350.00
2100mm dia m 2,200.00 - 2,450.00
Headwall to suit culvert, in reinforced concrete
Foundation including excavation m3 265.00 - 275.00
200mm thick wall including formwork m2 180.00 - 210.00
Aluminium Pipe, Helically Corrugated, with
coupling bands to joints laid on ground, including
minimal excavation, pipe size
300mm dia x 1.6mm gauge m 125.00 - 145.00
450mm dia x 1.6mm gauge m 190.00 - 210.00
600mm dia x 1.6mm gauge m 250.00 - 290.00
750mm dia x 1.6mm gauge m 355.00 - 395.00
1050mm dia x 1.6mm gauge m 550.00 - 600.00
1200mm dia x 1.6mm gauge m 625.00 - 675.00
1500mm dia x 2.5mm gauge m 1,220.00 - 1,320.00
2100mm dia x 2.5mm gauge m 1,525.00 - 1,625.00
Add extra for backfilling
Detailed Rates
2008
Specialist Fittings
Parking/Vehicle Equipment
Page 4-433
Unit Ak/Wn/Ch/Dn $
42 Specialist Fittings
42.1 Parking/Vehicle Equipment
Automatic Gate, 4500mm—3 seconds delay No 20,000
Traffic Detector No 250
Loop for detector (site-dependent) No 300
Barrier Gate No 3,200
Controller, for simple barrier control No 600
Proximity reader No 600
Card No 7
Ticket Printer and dispenser No 14,000
Fee Computer and ticket validator No 19,000
Add extra for
Electrical connection
Concrete apron
Attendant's booth
Vertical Stack Parking System
Power pack (suitable for up to 40 days) No 4,000
Starting bay (1 car) No 11,000
Additional bay (1 car) No 10,000
Add extra for
PVC parking blocks
PVC speed bumps
Bird Proofing
Car’ousel Vehicle Turntable, 4m diameter
Plywood deck, unmotorised No 17,000 - 18,000
Chequer plate deck, motorised No 25,000 - 27,000
2008
Specialist Fittings
Catering Facilities
Page 4-434
Unit Ak/Wn/Ch/Dn $
2008
Specialist Fittings
Laundry Equipment
Page 4-435
Unit Ak/Wn/Ch/Dn $
2008
Specialist Fittings
Cooking Equipment, Electric
Page 4-436
Unit Ak/Wn/Ch/Dn $
2008
Specialist Fittings
Dishwashers
Page 4-437
Unit Ak/Wn/Ch/Dn $
• Commercial units, including stainless steel
finish, with door locks and interior light
Vertical chiller unit
586 litre, 685mm wide, 2120mm high No 5,500.00 - 6,000.00
1300 litre, 1370mm wide, 2120mm high No 7,200.00 - 8,000.00
Vertical freezer unit
586 litre, 685mm wide, 2120mm high No 6,700.00 - 7,300.00
1300 litre, 1370mm wide, 2120mm high No 9,200.00 - 10,000.00
Horizontal chiller unit
560 litre, 2300mm wide, 4 door unit No 8,500.00 - 9,000.00
480 litre, 1750mm wide, 2 door unit No 5,800.00 - 6,500.00
Horizontal freezer unit
560 litre, 2300mm wide, 4 door unit No 10,000.00 - 10,500.00
480 litre, 1750mm wide, 2 door unit No 9,200.00 - 10,000.00
Backbar chiller, swing doors
580 litre, 2060mm wide, 3 door unit No 10,000.00 - 10,500.00
780 litre, 2620mm wide, 2 door unit No 9,200.00 - 10,000.00
Add for sliding door options No 200.00 - 300.00
Vertical display unit
1700 litre, 2 door, chiller No 10,500.00 - 11,100.00
1700 litre, 2 door, freezer No 16,200.00 - 16,800.00
42.9 Dishwashers
Dishwasher, automatic
Freestanding (Average) No 900.00 - 1,300.00
(De Luxe) No 1,300.00 - 2,400.00
Compact, 450mm wide No 1,350.00 - 1,450.00
Built-in (Average) No 1,000.00 - 1,300.00
(De Luxe) No 1,300.00 - 2,400.00
Mobile adaptor kit No 150.00
2008
Specialist Fittings
Bank Fit-Out
Page 4-438
Unit Ak/Wn/Ch/Dn $
2008
Specialist Fittings
Hotel Fit-Out
Page 4-439
Unit Ak/Wn/Ch/Dn $
Bars/Servery
Bar and Servery Equipment
Ice maker machine 94kg/hr capacity No 5,000.00
Bottle opener and cap container No 80.00
Spirit bowser and bracket No 160.00
Stainless steel ice bucket No 65.00
Ice bucket stand No 65.00
Automatic glass washer (1,500 per hr) No 2,970.00
Plastic coated glass trays No 27.00
Rapid cork remover No 315.00
Electric blender No 1,040.00
Cocktail shakers No 55.00
Cream whipper, 1 litre No 70.00
Cash register No 2,500.00
2008
Specialist Fittings
Bar Fitout General Items
Page 4-440
Unit Ak/Wn/Ch/Dn $
Tables
To seat four Medium standard No 100.00 - 300.00
High standard No 300.00 - 600.00
To seat six Medium standard No 150.00 - 450.00
High standard No 300.00 - 750.00
Outside tables, wrought iron (painted), No 100.00 - 400.00
timber, aluminium or zinc
Bedrooms
Wardrobe, fully fitted m 700.00 - 800.00
Case and Tray Rack m 300.00 - 400.00
Writing Desk/Bench m 400.00 - 500.00
Bed, including bed-head, mattress
Single No 750.00 - 900.00
Double No 1,000.00 - 1,250.00
Queen No 1,150.00 - 1,450.00
King No 1,250.00 - 1,550.00
Folding No 300.00 - 350.00
Mattress Protector
Single No 30.00 - 35.00
Double/Queen/King No 35.00 - 45.00
Pillow No 20.00 - 180.00
Luggage Rack—folding No 100.00
Add extra for
Call and communication system
Radio/TV
Refrigerator
Tables and chairs
Bottle Store
1400 litre tank, dispensing equipment No 4,000.00
Check-out counter No 800.00
Cleaning unit No 300.00
Flagon machine filler No 5,500.00
Shelf unit, free-standing 1.5m high x 2.2m No 500.00
Detailed Rates
2008
Specialist Fittings
Kitchen Equipment
Page 4-441
Unit Ak/Wn/Ch/Dn $
Kitchen Equipment
Prices are commercial quality catering
equipment and include installation but exclude
connection to services
Baker’s rack, for 16 trays No 850.00
Bench, stainless steel, with upstand
1200mm long No 1,200.00
1800mm long No 1,600.00
900mm x 90mm corner unit No 1,400.00
Sink bench, 900mm long No 1,800.00
Bread and roll moulder No 17,000.00
Can opener (heavy duty) No 100.00
Colander (Stainless steel) 350mm dia No 65.00
Extractor hood (stainless steel) No 22,000.00 - 32,000.00
Fire blanket No 70.00 - 100.00
Food mixer, 5 litre No 2,500.00
Food mixer, floor mounted No 20,000.00
Food processor No 1,600.00
Fryer, gas, 2 basket No 4,000.00
Grill plate, 530mm wide No 950.00
Heat lamp assembly No 750.00
Hot water urn—10 litre No 300.00
Hot water urn—30 litre No 400.00
Insect Control Unit No 500.00
Juice extractor No 400.00
Mobile food bench, stainless steel, No 2,500.00
2000 x 900 x 900mm
Oven, multi-deck, wheeled, 2 deck option No 15,000.00
Oven, combi-steamer, 10 tray, 3 function No 18,000.00
cooking
Oven, 6 gas hobs No 7,000.00
Oven, 4 gas hobs, 300mm griddle plate No 6,000.00
Oven microwave No 500.00
Potato peeler 7.5 kg No 2,250.00
Rubbish bin, galvanised No 40.00
Salamander No 2,250.00
Scales (digital) No 1,500.00
Scales 0–2 kg No 650.00
Soup warmer, 10 litre, electric No 450.00
Toasted sandwich maker/panini grill No 900.00
Toaster, automatic, 4 slice No 550.00
Toaster, automatic, 8 slice No 850.00
Toaster, conveyor No 2,800.00
Trolley, 2 tier No 750.00
Trolley, 3 tier No 800.00
Waste disposal unit, 50 to 100 covers No 2,800.00
Detailed Rates
2008
Specialist Fittings
Restaurant/Brasserie Equipment
Page 4-442
Unit Ak/Wn/Ch/Dn $
Restaurant/Brasserie Equipment
Automatic coffee maker No 500.00
Bain marie, bench top No 1,000.00
Bain marie, mobile, for 4 pans and lids, No 15,000.00
including canopy with lamps
Bain marie, 4 containers No 1,170.00
Bar blender No 500.00 - 750.00
Blender No 1,400.00 - 1,600.00
Cake stand No 25.00
Carving dish No 335.00
Chafing dish, oblong, 8.5 litre No 175.00
Chafing dish, roll top, 8.5 litre No 650.00
Chafing dish, electric, 13.5 litre No 350.00
Drinks dispenser, perspex, 5 containers No 1,600.00
Espresso coffee maker, 2 heads No 7,000.00
Folding table, 2400mm x 750mm No 250.00
Food display cabinet, 9 flap No 800.00
Hot food display, 4 container No 2,000.00
Hot food display, 8 container No 2,500.00
Milkshake maker, triple No 1,800.00
Pie warmer, 800mm wide No 800.00
Serviette dispenser No 40.00
Straw dispenser No 40.00
Toast rack, 4 slice No 8.00
Tray, rectangular No 20.00
Sundry
Ceiling fan, 1400mm, white No 280.00 - 310.00
Ceiling fan, 1200mm rattan/timber No 335.00 - 365.00
Coaster container No 15.00 - 30.00
Commercial vacuum cleaner No 550.00 - 1,000.00
Electronic cash register No 2,400.00 - 2,900.00
First aid kit No 115.00
Heater, outdoor, LPG patio type No 800.00
Large glass ashtray No 25.00
Menu boards No 200.00
Notice board No 190.00
Wall clock No 50.00 - 80.00
Wall mounted keyboard No 85.00 - 195.00
Add extra for
Glasses, handles, carafes, jugs etc.
Detailed Rates
2008
Specialist Fittings
Hospital and Nursing Home Equipment
Page 4-443
Unit Ak/Wn/Ch/Dn $
2008
Specialist Fittings
Emergency and Patient Trolleys
Page 4-444
Unit Ak/Wn/Ch/Dn $
Mortuary Trolleys
Mortuary type concealment trolley, with plastic No 5,700.00 - 5,900.00
tray, hydraulic high-low, hydraulic platform, with
firbreglass imitation mattress top
2008
Specialist Fittings
Safes and Strongrooms
Page 4-445
Unit Ak/Wn/Ch/Dn $
2008
Specialist Fittings
Retail Fit-Out
Page 4-446
Unit Ak/Wn/Ch/Dn $
2008
Specialist Fittings
Office Furniture
Page 4-447
Unit Ak/Wn/Ch/Dn $
Managing Director
Desk, L–shaped, 3.5 m2 of top, natural timber
Medium No 2,000.00 - 2,500.00
Prestige No 3,500.00 - 4,500.00
Mobile Pedestal, 3 drawer
Medium No 500.00 - 600.00
Prestige No 700.00 - 900.00
Credenza Medium No 900.00 - 1,000.00
Prestige No 1,200.00 - 1,500.00
Chair, swivel type Medium No 600.00 - 700.00
Prestige No 1,000.00 - 1,500.00
Chair, visitors, occasional
Medium No 350.00 - 400.00
Prestige No 700.00 - 1,000.00
Executive/Department Head
Desk, L–shaped, 3.5 m2 of top, natural timber
Medium No 1,800.00 - 2,200.00
Prestige No 3,000.00 - 4,000.00
Mobile Pedestal, 3 drawer Medium No 400.00 - 500.00
Prestige No 600.00 - 700.00
Credenza Medium No 700.00 - 800.00
Prestige No 1,000.00 - 1,200.00
Filing Cabinet, 4 drawer
Medium No 450.00 - 650.00
Prestige No 800.00 - 900.00
Chair, swivel type Medium No 600.00 - 800.00
Prestige No 1,000.00 - 1,500.00
Chair, visitors, occasional type
Medium No 300.00 - 350.00
Prestige No 500.00 - 700.00
Detailed Rates
2008
Specialist Fittings
General Staff
Page 4-448
Unit Ak/Wn/Ch/Dn $
General Staff
Desk, L–shaped Laminate No 700.00 - 1,500.00
Desk, rectangular Laminate No 400.00 - 750.00
Chair Swivel No 300.00 - 500.00
Upright No 200.00 - 250.00
Typist
Desk/Table Laminate No 400.00 - 750.00
Chair Swivel No 300.00 - 500.00
Reception
Chairs Medium No 350.00 - 550.00
High No 500.00 - 800.00
Prestige No 800.00 - 1,200.00
Low Table Medium No 200.00 - 300.00
High No 300.00 - 500.00
Prestige No 800.00 - 1,200.00
Counter Medium m 2,500.00
High m 5,000.00
Prestige m 7,000.00
Miscellaneous
Rubbish bins, ashtrays, in/out trays per person 75.00 - 100.00
Amenities
Tables, to seat 4 persons, laminated plastic top No 300.00 - 500.00
Chairs, stack type No 70.00 - 80.00
Ergonomic Furniture
Computer Workstation
Terminal table No 250.00 - 300.00
Keyboard adjustment type No 550.00 - 650.00
Returns, non-adjustable No 200.00 - 250.00
Monitor arm, adjustable No 250.00 - 500.00
Acoustic hood for printer No 700.00 - 1,000.00
Chairs
Typist No 350.00 - 455.00
Clerical No 400.00 - 650.00
Management No 800.00 - 1,000.00
Printer Table No 250.00 - 350.00
Computer trolley No 350.00 - 500.00
Document holder No 50.00 - 250.00
• For Office Storage System, Refer to page 4-449
Detailed Rates
2008
Specialist Fittings
Office Storage Systems
Page 4-449
Unit Ak/Wn/Ch/Dn $
2008
Specialist Fittings
Cleaning, Waste Disposal
Page 4-450
Unit Ak/Wn/Ch/Dn $
Hydestor double-faced free standing
shelving, powder coated steel posts, shelves
and brackets. Welded frames, canopy shelves,
diagonal bracing, accessorized shelves.
1375mm x 900mm wide x 300mm deep Bay 260.00
1575mm x 900mm wide x 300mm deep Bay 300.00
1775mm x 900mm wide x 300mm deep Bay 340.00
• For specialist coolroom and cold store shelving
installations, Refer to page 4-277
2008
Plant Hire Rates
Large Plant
Page 4-451
2008
Plant Hire Rates
Large Plant
Page 4-452
2008
Plant Hire Rates
General and Small Plant
Page 4-453
2008
Plant Hire Rates
General and Small Plant
Page 4-454
2008
Plant Hire Rates
Plant Hire Calculation
Page 4-455
2008
Vehicle Reimbursement Rates
Inland Revenue Guidelines
Page 4-456
2008
Demolition
Structure
Page 5-458
1 Demolition
1.1 Structure
Floors
Remove vinyl floor tiles or carpet m2 0.20
Break up and remove concrete floor topping
100mm thick m2 1.00
150mm thick m2 1.50
Scabble concrete to receive new screed m2 0.20
Walls
Demolish
Single skinned masonry wall m2 0.50
Timber framed partly glazed plasterboard wall m2 0.30
Remove ceramic wall tiles on solid plaster, make good to m2 1.00
receive paint finish
Cut and form opening in single skin masonry wall for single No 7.00
door, including teething and bonding, and making good to
render
Roofing/Ceilings
Take down suspended ceiling system m2 0.30
Remove asphalt roofing, make good m2 1.00
1.2 Joinery
Windows and Doors
Remove No 2.20
2400mm x 900mm steel window
3200mm x 2700mm roller shutter door No 4.00
Remove door, including hardware, frame and architrave
Pair of solid core doors No 1.25
Single hollow core door No 0.50
Miscellaneous
Remove
750mm high x 350mm deep wall shelving unit m 0.50
Timber handrails and fixing brackets m 0.15
1200mm high pipe balustrade m 0.25
Labour and Plant Constants
2008
Excavation
Disconnection of Plumbing Works
Page 5-459
2 Excavation
2.1 Site Clearance
Strip 50mm topsoil and remove from site (machine) m3 0.03
2008
Concrete Work, Formwork
Surface Treatments
Page 5-460
2.5 Membranes
Underlay, plastic film m2 0.03
3.3 Joints
Keyed construction joint in
150mm slab m 0.30
300mm slab m 0.35
Expansion joint in
150mm slab m 0.50
300mm slab m 0.60
150mm wall m 0.60
300mm wall m 0.70
3.4 Waterstops
Waterstop, double bulb, cast in, excluding angles and intersections
150mm wide m 0.25
200mm wide m 0.275
Labour and Plant Constants
2008
Concrete Work, Formwork
Formwork
Page 5-461
3.5 Formwork
Specification Notes
• Constants assume five uses of formwork.
• Where the number of uses is less, the constants should be adjusted by percentage shown:
Four uses Add +2.5%
Three uses Add +6.0%
Two uses Add +12.5%
One use Add +20.0%
• Rates include fabrication, fixing in place and striking.
Surface Finish
Formwork to sides of
Column/pier foundations F1 m2 1.20
Strip footing F1 m2 1.20
Attached beam F4 m2 2.45
F1 m2 2.20
Column F4 m2 2.90
F1 m2 2.65
Lintels and beams F4 m2 3.50
F1 m2 3.25
Wall F4 m2 2.60
F1 m2 2.20
Formwork to soffit of
Suspended slab F4 m2 2.35
F1 m2 2.00
Stairs and landings F4 m2 4.00
F1 m2 3.50
Formwork to edges, vertical or horizontal
0–100mm high F4 m 0.75
100–200mm high F4 m 0.75
200–300mm high F4 m 1.00
Form groove, 25mm x 25mm m 0.13 0.04
Form rebate, 100mm x 50mm m 0.20 0.07
Form hole/opening in concrete 100/200mm thick, size:
100mm x 100mm No 0.24 0.08
300mm x 300mm No 0.40 0.14
500mm x 500mm No 0.60 0.20
Form hole/opening in concrete 200/300mm thick, size:
100mm x 100mm No 0.30 0.10
300mm x 300mm No 0.50 0.17
500mm x 500mm No 0.65 0.22
Tube formers, cardboard, including stripping
300mm ID (internal diameter) m 0.95 0.32
500mm ID m 1.15 0.38
Spirally wound plastic tube, including stripping
300mm ID m 1.00 0.34
500mm ID m 1.20 0.40
Labour and Plant Constants
2008
Reinforcement
Brickwork
Page 5-462
4 Reinforcement
Mesh Reinforcement, placing and fixing in
Slabs, small areas m2 0.12
Slabs, large areas m2 0.08
Walls m2 0.12
Bar Reinforcement, placing and fixing
6mm–12mm stirrups tonne 30.00
16mm–32mm bars in slabs tonne 18.00
16mm–32mm bars in walls tonne 20.00
16mm–32mm bars in columns and beams tonne 20.00
5.2 Blockwork
Blockwork in walls, of hollow blocks
400mm x 200mm x 100mm m2 0.43 0.22
400mm x 200mm x 150mm m2 0.50 0.25
400mm x 200mm x 200mm m2 0.56 0.28
400mm x 200mm x 200mm hollow block threaded m2 0.96 0.28
over bar reinforcement
Pointing and cleaning down m2 0.10 0.10
2008
Structural Steelwork
Framing and Bracing
Page 5-463
6 Structural Steelwork
• Excludes on-site costs of craneage, cartage, etc
2008
Structural Steelwork
Workshop Fabrication
Page 5-464
Average Range
(Min–Max)
2008
Structural Steelwork
Workshop Fabrication
Page 5-465
Average Range
(Min–Max)
Labours to all sections
Drill bolt holes in structural sections hole 6.5 min 4.5–7.5 min
Form slotted bolt holes in structural sections slot 15 min
Gas cut and grind edges for cut outs, penetrations, straight metre 20 min
Same as last, circular metre 30 min
Assemble and tack portal frame knee, apex, or k-brace join join 1.25 hr 1–1.5 hr
Assemble secondary section frame joins join 30 min 20–45 min
Precambering; up to 310 UB or UC No 2.5 hr 1–3 hr
Precambering; over 310 UB or UC No 3.5 hr 3–6 hr
Cut, prepare and assemble corbels, tapers, haunchings etc No 1 hr 0.75–2 hr
max. 1m long
Assemble composite members, e.g. crane beam channel onto metre 30 min
UB
Truss cutting and assembly
Cut truss diagonals and struts piece 12 min 10–15 min
Extra Value mitre cut or notch ends end 7.5 min 6–9 min
Cut, prepare, join and weld chord, maximum 250 PFC or UB chord 1.5 hr 1.25–2 hr
x 12m long
Mark out and set up jig for truss assembly x 12m long No 4 hr 3–6 hr
Assemble truss top and bottom chords with diagonals and truss 4 hr 3–6 hr
struts x 12m long, in jig
Extra Value to precamber truss, x 12m long No 2 hr 1–3 hr
Diagonal bracing
Diagonal bracing rod cut, join, assemble turnbuckles, threaded No 40 min 20–60 min
ends
Diagonal bracing angle cut, join, drill bolted ends No 50 min 30–75 min
Welding—80% downhand, 20% vertical
5 and 6mm fillet weld m 18 min 15–22 min
8mm fillet weld—2 runs m 32 min
10mm fillet weld—3 runs m 46 min
12mm fillet weld—4–5 runs m 72 min
Vee prepare end of UB, UC, PFC, HS for butt weld, max end 8 min
300mm depth
Same as last, over 300mm end 12 min
Vee butt weld up to 12mm m 90 min
Vee butt weld over 12mm, up to 16mm m 150 min
Extra Value for backing strip to joins in SHS join 7.5 min
Extra Value for backing strip to joins in CHS join 30 min
Hit and miss stitch 6mm fillet weld m 10 min
Miscellaneous
H.D. bolt assembly into pairs pairs 6 min
Unload and stack inwards steel, and load out fabricated steel tonne 1.5 hr 1.25–2 hr
onto trucks
Labour and Plant Constants
2008
Metalwork
Stairs, Balustrades and Ladders
Page 5-466
Average Range
(Min–Max)
Productivity factors—against the constants above
General: market, complexity or regional 0.85–1.33
Site fabrication and welding 2.00–4.00
Notes
• The average constants are for high repetition portal frame and high rise type work. The ranges are for
differences in piece size, detail, repetition, and fabrication methods.
• These constants are based on conventional fabrication methods used by most fabricators,. ie manual
gas cutting and magnetic broach drilling, and semi-automatic "mig" or "flux core" welding.
• With semi-automated saw and drill lines output is much higher but machine costs are higher, and
generally the market does not differentiate costs because semi-automation affects only part of overall
fabrication.
• The constants include for reading fabrication drawings, stacking and sorting materials, marking out,
turning, grinding edges and welds, operator setting up, servicing gear such as welders and grinders,
and QA including average rework.
• These constants are "whole of job", and hence will differ from spot check times which will not be
representative of a complete job due to the tendancy not to include downtime and variances in
productivity.
• Repetition affects productivity in different ways, and for some labour operations can have a significant
impact on output, while other labours produce only slight improvements. A high degree of difficulty can
also have a large impact on output, for example, very detailed drawings, angled assembly, low repetition
of detail, complex set out.
• Welding output varies according to the length of welds and the amount of shifts to different pieces being
welded, and handling. Repetition alone has little impact on welding output, unless it is practical to use a
different welding method. Structural steel usually involves small runs, with greater attention to weld ends
around plate edges, and corners. Thus, where long runs of continuous welding are involved output is
generally higher, particularly if a different welding method can be used.
Unit Tradesman Labourer
Hours Hours
7 Metalwork
7.1 Stairs, Balustrades and Ladders
Ladder, 450mm wide, fully welded steel and shop primed tonne 100.00
Staircase, steel framed, including treads and shop treatment tonne 60.00
Balustrade, steel, 900mm high, balusters at 150mm centres tonne 140.00
2008
Carpentry
Gratings and Covers
Page 5-467
8 Carpentry
• Constants based on using No. 1 framing
• For small additions to buildings or for partitioning in commercial
contracts, add up to 50% to given rate
2008
Carpentry
Wall Framing
Page 5-468
8.4 Bracing
Metal angle diagonal bracing m 0.12
Plywood sheet bracing checked in flush m2 0.90
Plywood sheet bracing fixed over framing m2 0.40
2008
Carpentry
Exterior Linings and Trim
Page 5-469
2008
Carpentry
Interior Linings
Page 5-470
8.8 Flooring
Tongued and grooved flooring
100mm x 25mm m2 1.00–1.25
100mm x 25mm end matched m2 0.75–1.00
Particle board
2400mm x 1200mm x 20mm sheet m2 0.40
3600mm x 1200mm x 20mm sheet m2 0.38
3600mm x 1800mm x 20mm sheet m2 0.36
Labour and Plant Constants
2008
Carpentry
Interior Finishings
Page 5-471
8.12 Fixings
Drill brick wall for 12mm dia. masonry anchor No 0.10
Drill concrete wall for 12mm dia. masonry anchor No 0.13
Drill timber for 6/12mm dia. bolt No 0.05
Drill steel angle for 6/12mm dia. bolt No 0.13
Labour and Plant Constants
2008
Joinery
Staircases
Page 5-472
9 Joinery
9.1 Staircases
Timber staircase, comprising strings, treads, landing m/rise 8.00
supports and balustrades
Handrail, 150mm x 50mm fixed to steel, including ramps m 0.45
and wreaths
10 Roof Coverings
Tile Roofing
Standard pattern concrete tile on 40mm x 25mm battens m2 0.30 0.08
Ridge, hip verge tiles m 0.25 0.12
Standard pattern prefinished metal tile on 50mm x m2 0.20 0.12
50mm battens
Ridge hip, barge covers, etc m 0.15 0.12
Sheet Roofing
Corrugated translucent glass fibre reinforced sheet m2 0.20
Corrugated steel roofing on timber purlins m2 0.13
Ribbed steel/aluminium sheeting on timber purlins m2 0.30
Add extra for fixing to steel m2 0.02
2008
Solid Plaster
Underlay and Netting
Page 5-473
11 Solid Plaster
Render for wall tiling, cement and sand in one coat 13mm thick m2 0.20 0.10
Cement render, one coat 13mm thick on
Walls m2 0.25 0.11
Soffits m2 0.28 0.11
Columns m2 0.42 0.18
Beams m2 0.42 0.18
Hardwall plaster, two coats 16mm thick on
Walls m2 0.42 0.18
Soffits m2 0.50 0.20
Columns m2 0.55 0.25
Beams m2 0.55 0.25
Skim coat hardwall plaster on soffits m2 0.22 0.08
Plaster cove m 0.15
Plaster nosing m 0.15
13 Tiling
• Factors include pointing and cleaning
Wall tiles, ceramic/mosaic fixed with adhesive m2 0.90
Floor tiles, ceramic/mosaic including bedding m2 0.90
14 Floor Coverings
Carpet laying
Direct fixed carpet m2 0.20
Carpet and rubber underlay m2 0.20
Cork tiles and clear plastic finish m2 0.40
Linoleum or vinyl fixed with adhesive
2.5mm thick sheet m2 0.30
Foam backed sheet m2 0.40
Labour and Plant Constants
2008
Glazing
Sanitary Fixtures
Page 5-474
15 Glazing
Glazing in regular panes approx. 1000mm x 1000mm to
Timber with putty m2 0.90
Timber with beads m2 1.00
Metal with putty/mastic and/or neoprene strips m2 1.20
17 Plumbing
17.1 Sanitary Fixtures
• Fix only including brackets, fixings, etc
Vanity basin No 1.70
Wall basin No 1.75
Bath, pressed steel No 1.40
Bidet—excluding heater No 2.00
W.C. suite No 2.35
W.C. pan floor mounted No 1.00
wall mounted No 4.00
Cistern, wall type No 1.00
Cleaner's sink No 1.80
Kitchen sink No 1.50
Laundry trough No 1.00
Slop hopper No 5.00
Urinal single stall No 3.50
1800mm long No 5.00
3000mm long No 6.50
Labour and Plant Constants
2008
Plumbing
Hot Water Units
Page 5-475
2008
Plumbing
Water Pipes
Page 5-476
2008
Drainage
Sewer and Stormwater Drains
Page 5-477
18 Drainage
18.1 Sewer and Stormwater Drains
• Constants include laying, jointing and testing, but
exclude excavation and backfilling
Earthenware pipe, with rubber ring joints, diameter
Sewer 100mm m 0.50
150mm m 0.70
225mm m 1.00
Stormwater 100mm m 0.20
150mm m 0.37
225mm m 0.50
Bends, junctions 100mm No 0.25
150mm No 0.25
225mm No 0.50
PVC pipe, with solvent welded joints, diameter
Sewer 100mm m 0.25
150mm m 0.60
Stormwater 100mm m 0.20
150mm m 0.35
Bends, junctions 100mm No 0.25
150mm No 0.30
Labour and Plant Constants
2008
Electrical Services
Conduit
Page 5-478
19 Electrical Services
19.1 Conduit
• Constants include installing a nominal quantity of bends
and conduit fittings and saddling, to comply with wiring
regulations where required.
UPVC Conduit
Fixed to masonry maximum 4m above floor
20mm diameter m 0.15
32mm diameter m 0.18
50mm diameter m 0.22
Cast into suspended concrete slab
20mm diameter m 0.05
32mm diameter m 0.06
50mm diameter m 0.08
Fixed within suspended ceiling space
20mm diameter m 0.11
32mm diameter m 0.12
50mm diameter m 0.15
19.2 Cable
• Constants include drawing cabling in sets of four cables plus
approved size earth cable into adequately sized conduits, with
minimal long sweep bends, and for fixing cabling to top of
horizontal single side supported trays.
TPI cable in conduit
2.5mm2 m 0.03
6mm2 m 0.04
25mm2 m 0.05
35mm2 m 0.06
95mm2 m 0.09
Four core and earth PVC/PVC circular cable on tray
2.5mm2 m 0.08
6mm2 m 0.11
16mm2 m 0.17
35mm2 m 0.23
95mm2 m 0.42
150mm2 m 0.59
Labour and Plant Constants
2008
Mechanical Services
Pipework
Page 5-479
20 Mechanical Services
20.1 Pipework
• Constants exclude bends, junctions, tees and flanges
Copper piping with silver soldered joints, installed complete,
including standard supports but excluding insulation, diameter
15mm m 0.25
20mm m 0.28
25mm m 0.32
32mm m 0.37
40mm m 0.43
50mm m 0.50
65mm m 0.62
80mm m 0.75
100mm m 0.95
150mm m 1.50
Long sweep bend
15mm No 0.16
20mm No 0.16
25mm No 0.18
32mm No 0.23
40mm No 0.30
50mm No 0.37
65mm No 0.50
80mm No 0.70
100mm No 0.85
150mm No 1.00
Junction
15mm No 0.20
20mm No 0.20
25mm No 0.22
32mm No 0.27
40mm No 0.33
Labour and Plant Constants
2008
Mechanical Services
Pipework
Page 5-480
2008
Mechanical Services
Pipework
Page 5-481
2008
Mechanical Services
Pipework
Page 5-482
2008
Mechanical Services
Pipe Supports
Page 5-483
2008
Plant Constants
Density and Load Factors
Page 5-484
21 Plant Constants
The tables given hereafter are a guide only and apart from “Trucks and Haulage”, are based on
information given in the Reference Handbook issued by the “Caterpillar Tractor Co”. All plant
references are to “Caterpillar” equipment.
21.1 Density and Load Factors
Whilst measured quantities are generally ‘in situ’ or ‘in place’ quantities, the actual quantity to be
removed and/or spread and levelled is, in practical terms, the ‘loose’ volume.
The following table indicates the approximate density (weight) and load factor of common
materials.
21.2 Bulldozers
Production—Maximum Uncorrected
The “Dozing Production” curves, Refer to page 5-485, indicate maximum uncorrected production
for tracked machines with straight blades and based on the following conditions.
1 100% efficiency (60 minutes production achieved per hour)
2 Power shift machines with 0.5 min. fixed times
3 Machine cuts for 15m then drifts blade load to dump over a high wall.
4 Soil density of 1370 kg/m3 (loose)
5 Coefficient of traction—0.5 or better
6 Hydraulic controlled blades used.
Labour and Plant Constants
2008
Plant Constants
Bulldozers
Page 5-485
Dozing Production
1800
D10
1600 D9
1400
D8
Estimated Dozing Production Cum/Hour (loose)
1200
1000
800 D7
600
D6
400
D5
200 D4
D3
0
100
110
120
130
140
150
160
170
180
190
200
10
20
30
40
50
60
70
80
90
0
* Note: Angling and Cushioned blades are not considered to be production dozing tools.
Depending upon job conditions, the A-blade and C-blade will average 50-75% of straight blade
production.
Labour and Plant Constants
2008
Plant Constants
Excavators, Front Shovel
Page 5-486
2008
Plant Constants
Excavators, Backhoe
Page 5-487
2008
Plant Constants
Loaders
Page 5-488
2008
Plant Constants
Loaders
Page 5-489
2008
Trucks and Haulage
Truck Capacity
Page 5-490
Adjust for:
• Medium traffic + 20% on travelling time
• Heavy traffic + 40% to 50% on travelling time
• Waiting time at loading point
• Note: The above times are a very approximate guide only as location, route and time of day
can have an appreciable effect on the figures given.
Labour and Plant Constants
2008
Trade Ratios
On-Site Trade Ratios
Page 5-491
23 Trade Ratios
The following is a breakdown of average on-site costs into labour, material, and fixed cost
components. The on-site material content of precast concrete, structural steel and metal windows
and doors includes manufacture and prefabrication which normally takes place off-site. A
breakdown of these off-site labour and material ratios is also given below.
Labour Material Fixed Costs
23.1 On-Site Trade Ratios % % %
Preliminary and General 35 5 60
Demolition 25 - 75
Excavation 20 15 65
Insitu Concrete 15 80 5
Formwork 80 20 -
Precast Concrete (see below) 15 85 -
Reinforcing Steel 25 75 -
Structural Steelwork (see below) 10 90 -
Brickwork 50 50 -
Concrete Masonry 25 75 -
Metalwork 20 80 -
Metal Windows and Doors (see below) 10 90 -
Carpentry 45 55 -
Joinery 15 85 -
Suspended Ceilings 20 80 -
Metal Roofing 25 75 -
Butyl Roofing 35 65 -
Plumbing 50 50 -
Mechanical Services (air conditioning) 35 65 -
Sprinklers 40 60 -
Lifts 20 80 -
Electrical Services 25 75 -
Plasterboard Linings 45 55 -
Solid Plaster 80 20 -
Tiling 35 65 -
Vinyl Flooring 40 60 -
Carpet 10 90 -
Glazing 25 75 -
Painting 75 25 -
Vinyl Fabric (Wall Covering) 25 75 -
Wallpaper 45 55 -
2008
Indices
Explanation of Indices Used
Page 6-493
1 Indices
1.1 Explanation of Indices Used
Labour Cost Index—LCI
The LCI—Salary & Wages series measures movements in salary and ordinary time wage rates,
and overtime wage rates. Series represented:
• SE53E9–All Sectors Combined: Group 15—Construction
• SE43E9–Private Sector: Group 15—Construction
The latter is the index ‘L’ referred to in NZS 3910:2003—Appendix A, Cost Fluctuation Adjustment
by Indexation.
The SE59E9–LCI—All Costs Combined series includes non-wage labour-related costs: annual
leave and statutory holidays, superannuation, ACC employer premiums, medical insurance, motor
vehicles available for private use, and low interest loans, and is published as at June each year.
Consumer Price Index—CPI
The CPI provides a measure of the changes in the prices of goods and services to consumers, and,
in 2006, underwent a major review of method and items surveyed. Series represented:
• SE9A–All Groups
Capital Goods Price Index—CGPI
The CGPI records the average level of productive capital assets paid by New Zealand industries.
Series represented:
• S2BA–Non-Residential—Shops and Offices
• S2AA–Residential—Dwellings and Out-buildings
• SGC–Other Construction (includes transport ways, pipelines, electrical works, earthmoving
and sitework)
Producers Price Index—PPI
The PPI measures prices relating to the production sector of the economy.
Output indices measure changes in prices received by producers, input indices measure changes
in the cost of production, excluding labour and capital costs. Series represented:
• SNE–Construction Industry Group—Inputs
This is the index ‘M’ referred to in NZS 3910:2003—Appendix A, Cost Fluctuation Adjustment by
Indexation.
Opus Construction Cost Index—CCI
The Opus CCI was a civil engineering index produced by Opus International Consultants Ltd
(formerly Works Consultancy Services Ltd) and is now discontinued.
Contact Information
Statistics New Zealand www.stats.govt.nz
Auckland Tel: 09-358-4588 Wellington Tel: 04-495-4600
Christchurch Tel: 03-374-8700 Dunedin Tel: 03-477-7511
Construction Indices
2008
Indices
Labour and CCI Indices—Current
Page 6-494
2008
Indices
Key
Page 6-495
1.4 Key
• Note: Statistics New Zealand include the following statement for series S2BA.
“This index does not purport to reflect all price changes in building work because of
measurement difficulties, particularly with respect to margins and discounts on labour and
material prices.”
• * indicates pro rata calculation to convert indices for prior periods where base dates have
been updated. See “Compensating for Base Date Changes” on page 6-500.
• R indicates previously published figures have been revised. F indicates forecast.
1.5 Update Service
For updates of indices. For fax version, phone 0800-426-326 or 09-522-4780.
For a pdf version, email us at [email protected], or download from our website,
www.rawlinsons.co.nz/handbook.
Indices are also available at www.stats.govt.nz
Construction Indices
2008
Indices Archive
Labour and CCI Indices—Archive
Page 6-496
2 Indices Archive
2.1 Labour and CCI Indices—Archive
LCI CCI
Construction
Salary/Wages Base
All Costs Combined All Sectors Private Sector 200
Base Date Dec 1992 Jun 2001 Dec 1992 Jun 2001 Dec 1992 Jun 2001 Dec 1958
Year Quarter SA59P1 SE59E9 SA53P1 SE53E9 SA43P1 SE43E9
1995 March 1039 1029 1029 3640
June 1048 1034 1034 3640
Sept 1057 1042 1043 3650
Dec 1063 1048 1050 3680
1996 March 1067 1052 1054 3690
June 1081 1056 1057 3690
Sept 1087 1060 1061 3700
Dec 1092 1065 1066 3720
1997 March 1096 1069 1070 3730
June 1097 1074 1076 3740
Sept 1100 1077 1078 3750
Dec 1104 1080 1082 3760
1998 March 1102 1083 1084 3770
June 1099 1089 1090 3770
Sept 1101 1091 1092 3780
Dec 1103 1093 1094 3790
1999 March 1101 1095 1096 3770
June 1098 1097 1098 3800
Sept - 1101 1102 3850
Dec - 1105 1106 3930
2000 March - 1109 1110 4020
June 1112 1111 1112 4050
Sept - 1115 1115 4160
Dec - 1118 1119 4420
2001 March - 1122 1123 4330
June 1129 1000 1130 1000 1131 1000 4300
Sept - 1136 1007 1137 1007 4340
Dec - 1143 1012 1143 1011 4320
2002 March - - 1147 1016 1146 1016 4290
June - R1015 1152 1019 1152 1018 4400
Sept - - - 1027 - 1026 Discontinued
2008
Indices Archive
CPI, CGPI, PPI Indices—Archive
Page 6-497
LCI CCI
Construction
Salary/Wages Base
All Costs Combined All Sectors Private Sector 200
Base Date Dec 1992 Jun 2001 Dec 1992 Jun 2001 Dec 1992 Jun 2001 Dec 1958
Year Quarter SA59P1 SE59E9 SA53P1 SE53E9 SA43P1 SE43E9
2005 March - - - 1107 - 1107 -
June - 1108 - 1119 - 1118 -
Sept - - - 1136 - 1136 -
Dec - - - 1145 - 1145 -
2008
Indices Archive
CPI, CGPI, PPI Indices—Archive
Page 6-498
2008
Cost Indexation Formula
Indexation Formula
Page 6-499
1 1
0.4 ( L – L ) 0.6 ( M – M )
C = V ----------------------------- + ---------------------------------
1 1
L M
× 16 0.6 × 45
C = $1,550,000 x 0.4
--------------------- + ---------------------
1115 1085
2008
Cost Indexation Formula
Compensating for Base Date Changes
Page 6-500
1000
Expressed as an equation, thus: ------------- × 1082 = 986
1097
Note: this calculation should not be applied to the PPI index, which was redeveloped in 1998.
Statistics New Zealand provided back calculations for two years—included above (note that these
do not quite match the original figures—due to the redevelopment).
3.4 Indices Release Dates
Index Quarter Approximate Release Dates
Day of month Month
Capital Goods Price Index March 3rd Thursday May
June 3rd Thursday August
September 3rd Thursday November
December 3rd Thursday February
Consumers Price Index March 3rd Monday April
June 3rd Monday July
September 3rd Monday October
December 3rd Monday January
Labour Cost Index (Sals and Wages) March 1st or 2nd Thursday May
June 1st or 2nd Thursday August
September 1st or 2nd Thursday November
December 1st or 2nd Thursday February
Producers Price Index March 4th Thursday May
June 4th Thursday August
September 4th Thursday November
December 4th Thursday February
Construction Indices
2008
Regional Indices
Main Centres
Page 6-501
4 Regional Indices
4.1 Main Centres
City Index
Auckland 100.00
Wellington 98.40
Christchurch 97.80
Dunedin 98.00
4.2 Provincial
These indices are a broad indication only of cost variation between cities and towns within New
Zealand, and are applicable to the total project costs.
Please note that these indices are intended to be applied where the project is capable of being
carried out by local resources. If the nature or size of the project requires an ‘out-of-town’
contractor, then these indices will not necessarily apply.
7.1 Wage and Charge Rates 7-503 7.2 Labour Only—Residential 7-508
Employment Contracts 7-503 7.3 Accident Compensation 7-511
Employing a Labour-Only Contractor 7-503 IRPC Act 2001 7-511
Sample Wage Calculations 7-504 Before the IRPC 7-511
Hourly Paid Wage Rates 7-504 Levy Year 7-511
Labour Only Paid Rates 7-504 Invoicing for Levies 7-511
Tender or Contract Rate 7-505 Earner Levy 7-511
Productive Hours 7-505 Self Employed Persons 7-511
Daywork or Charge Out Hourly Rates 7-505 Employer Levy Rates 7-512
Labour Rate Build Up 7-506 Employer Levy Rates—Historic 7-513
Holidays and Sick Leave 7-507
Insurances and Levies 7-507
Charge Out Rates & ACC
2008
Wage and Charge Rates
Employment Contracts
Page 7-503
2008
Wage and Charge Rates
Sample Wage Calculations
Page 7-504
2008
Wage and Charge Rates
Tender or Contract Rate
Page 7-505
Note: Profit and overhead added is added on at the end of the estimate to produce a quotation or
tender amount.
1.7 Productive Hours
The contract rate is derived from the total weekly cost of employing an operative, divided by the
productive hours actually worked. These productive hours are less than the paid worked hours, due
to a paid morning and afternoon break, plus starting and stopping, totalling 8 times a day. Wet time
is also included as an average allowance.
Productive Hours
Item Minutes Times Days per Total Hours
per day week Minutes
Standard available hours per week 45.00
Deduct
Tea break 10 mins x 2 x 5 100 = -1.67
Lost time 5 mins x 8 x 5 400 = -3.33
Wet time allowance (this allows for 4 hours -2.00
per week wet weather, divided by 2 to allow
for 50% of under cover work.)
Productive Hours Per Week = 38.00
2008
Wage and Charge Rates
Labour Rate Build Up
Page 7-506
2008
Wage and Charge Rates
Holidays and Sick Leave
Page 7-507
Holidays, sick leave etc, expressed as percentage—4 weeks annual leave option, as from 2007
Working time = total weeks less non working time Days/days in week Weeks
Total weeks in year (total days in year, divided by 7) 365/7 52.14
less:
Annual holidays (total, divided by 5 working days) 20/5 4.00
Statutory holidays 11/5 2.20
Sick leave 5/5 1.00
Total non-working time = 7.20 7.20
Time worked in weeks = 44.94 44.94
7.2 100
--------------- × ---------- = 16.0 =16.0%
Percentage Calculation 44.94 1
2008
Labour Only—Residential
Insurances and Levies
Page 7-508
2 Labour Only—Residential
A regular query is ‘what is the going labour-only rate for house construction?’. Often the builder is
being asked to carry out the carpentry work for a $/m2 rate, and wants to know if the rate is fair.
Without knowing the scope of work, it is extremely difficult to agree or disagree with any given rate.
In all cases, we recommend that readers, before accepting any rate, calculate the cost of the
project, using established estimating principles and allowing for appropriate overhead and margin
amounts, in order to see for themselves if the proposed rate is fair.
Our only comment regarding actual rates is to state that in virtually every enquiry, that is, one to two
per year since 1995, the rate suggested has been between $55 and $65 per m2. In that same
period, the hourly charge out rate has increased significantly.
This section is intended to provide some tools for the reader to calculate their own rate for the
particular project being considered. The worked example allows for both $ per m2 and total $ per
project, whichever is preferred.
Method One—“Top Down”
Top Down—Working back from the offered rate Scenario One Scenario Two
Purpose: To work out if the rate is one you should Area 200 Area 300
accept, that is, can carry out the work for and make a Rate $60/m2 Rate $90 /m2
profit.
Step One Per m2 Per project Per m2 Per project
Enter proposed income A $60 $12,000 $90 $27,000
Decide on desired profit percentage, and deduct this 10% $6 $ 1,200 $ 9 $2,700
percentage from income ‘A’
This gives theoretical cost ‘B’ to carry out the work B $54 $10,800 $81 $24,300
Step Two
Enter the hourly charge out rate per person C $32 $32 $32 $32
Divide the cost rate ‘B’ by charge out rate ‘C’
This will show how many hours per m2 the offered D 1.69 2.53
rate allows to carry out the work hrs/m2 hrs/m2
Step Three
Multiply ‘D’ x project area to give project hours E 338 338 759 759
Step Four
Calculate hours that the work gang costs per week
Hours worked per week F 45 45
Number of staff in gang G 3 3
Multiply ‘F’ x ‘G’ to give hours per gang week H 135 135
Step Five
Divide project hours ‘E’ by gang week hours ‘H’ to weeks 2.5 5.6
give project duration in working weeks
Based on experience, decide if the resulting calculation of working weeks is a realistic time frame in
which to complete the project. If unsure, look back over records of previous jobs to assess how long
they took.
Other costs and factors to consider: Downtime, wet weather delays, waiting on subs/other
contractors, vehicles, cellphone charges, equipment costs such as tools and plant, either your own
or hired in.
Charge Out Rates & ACC
2008
Labour Only—Residential
Insurances and Levies
Page 7-509
It is good practice to do a full measure of the work and quantities involved, and rate out the labour
hours from established labour constants for residential work. On the other hand, if you have a
reliable feel for how many weeks or days a project will take a gang of say 2, 3 or 4 staff, then that is
an equally valid method of estimating. If you've done identical or similar projects in the past, then
you should have records that will give the likely manhours.
It is recommended practice to use one method as a cross-check for the other, ie, work out both
ways and see if you come up with the same answer.
For this example, we will assume you have already established the labour hours for the projects.
Method Two—“Bottom Up”
Bottom Up—Working out the cost, in order to establish the $/m2 Scenario Three Scenario Four
Purpose: To build up a labour schedule for the
project, establish the cost and then work out the
selling price for the work
Step One
Work out how long the project should take. For this A weeks 4 6
example, we will assume you have already B men 3 4
established the labour hours for the project, and C hrs/wk 45 50
checked it against similar projects from your files.
Multiply ‘A’ x ‘B’ x ‘C’ to give manhours for project D 540 1200
Step Two
Enter the hourly charge out rate E $32 $32
Multiply manhours ‘D’ by hourly charge out rate ‘E’ F $17,280 $38,400
Step Three
Add establishment, vehicle, supervision, overheads G $1,695 $2,543
See separate calculation in next table for ‘G’
Step Four
Add labour cost ‘F’ and establishment costs ‘G’ H $18,975 $40,943
Step Five
Calculate preferred profit margin J 10% $1,898 $4,094
Add ‘H’ and ‘J’ to give total including profit margin K $20,873 $45,037
Step Six
Divide the total ‘K’ by the m2 for the project. This will say say
give you the $ per m2 rate 250m2 $83/m2 400m2 $113/m2
• Please note, these demonstrate calculations for
arriving at a rate, and are not recommended or
‘going’ rates
• The labour hours used in this calculation are
merely examples, and not an indication of how long
a particular project will take.
Charge Out Rates & ACC
2008
Labour Only—Residential
Insurances and Levies
Page 7-510
Tip: your accountant, or person who pays the bills, should be able to supply a list of costs that
should be included in the establishment and overhead costs, based on the previous year’s
expenditure.
Charge Out Rates & ACC
2008
Accident Compensation
IRPC Act 2001
Page 7-511
3 Accident Compensation
3.1 IRPC Act 2001
• The Injury Prevention, Rehabilitation and Compensation Act 2001(IRPC) came into effect on
1 April 2002, and replaced the Accident Insurance Act 1998.
3.2 Before the IRPC
• 1999-2001: Accident Insurance Act 1998, with some aspects amended by Accident
Insurance Amendment Act 2000, Accident Insurance (Transitional Provisions) Act 2000.
ACC—the Accident Compensation Corporation—restored as the sole provider of workplace
accident insurance.
• 1998-1999: Accident Insurance Act 1998. Employers must have workplace accident
insurance cover for employees.
• 1992-1998: Accident Rehabilitation and Compensation Insurance Act 1992.
State versus private accident insurance is an area of fundamental policy difference for some
political parties, and the above changes follow changes of Government between 1992 to 2005.
3.3 Levy Year
Under the IRPC, all payments to ACC for accident cover are called levies (previously premiums).
Accident cover is provided for a levy year, which is a 12-month period running from 1 April to 31
March. ACC WorkPlace Cover levies pay for the current and future cost of work-related injury
claims that occur in the levy year.
At $2.95 per $100—the Levy plus Residual &HSE combined—the building rate has been reduced
from a combined rate of $3.23 in 2007/2008.
3.4 Invoicing for Levies
Employer levies are invoiced in two parts, firstly a provisional invoice for the current levy year, 1
April–31 March for the WorkPlace Cover levy. Secondly, an adjustment invoice for the previous
levy year, 1 April–31 March for the Residual Claims levy, incorporating the HSE levy, $0.05 per
$100 of liable earnings (Health and Safety in Employment).
In 2007, employers were contacted by ACC to confirm their classification. IRD can alter this
process, despite ACC confirmation, resulting in levy invoices based on incorrect rates.
3.5 Earner Levy
All employees must pay an ACC earner levy to cover the cost of non-work injuries, plus an earners’
account residual levy—to fund the cost of non-work injuries claimed from 1 April 1992 to 30 June
1999. These levies are incorporated into the PAYE tables, and collected by Inland Revenue on
behalf of ACC, and have been relatively stable at between $1.20 and $1.40 per $100 of earnings.
The maximum amount of earnings—per individual—liable for the combined earner levy deduction
is $102,922 for the 2008/09 financial year. This has increased every year, eg, the maximum liable
earnings in 2000 was $83,017, in 2004 it was $88,728, and in 2007/08 year it was $99,817. But it’s
not a tax!
• Earner levy—$1.40 per $100 of earnings—reduced from $1.403 in 2007/8 levy year.
• Earners’ account residual levy—included
3.6 Self Employed Persons
Self employed persons may choose between ACC CoverPlus or ACC CoverPlus Extra for all work
and non-work injuries, except for motor vehicle accidents which remain covered by ACC.
Charge Out Rates & ACC
2008
Accident Compensation
Employer Levy Rates
Page 7-512
2008
Accident Compensation
Employer Levy Rates—Historic
Page 7-513
2008
Rental Values
Residential
Page 8-515
1 Rental Values
This section is intended as a guide only to various rental values so that an approximate value can
be used in initial feasibility studies and the like.
To obtain more specific information it is recommended that a member of the New Zealand Property
Institute or the New Zealand Property Council be consulted.
1.1 Residential
Locality/Type Standard $/per week
Auckland Wellington Christchurch Dunedin
Central city and immediate vicinity
Studio—1 bedroom Medium 250–350 200–250 100–200 90–120
High 300–400 150–200 100–150 150–175
City apartment—2 bedroom Medium 250–450 210–280 200–300 200–250
High 350–650 230–440 250–400 250–350
House—3 bedroom Medium 350–550 230–300 180–240 150–180
High 450–800 260–450 250–400 180–300
Suburbs
House—3 bedroom Medium 250–350 210–260 180–240 180–230
High 300–600 270–320 250–350 220–300
Flat/Unit—2 bedroom Medium 200–300 140–180 130–170 120–180
High 250–400 190–220 170–200 150–230
1.2 Carparks
Locality/Type Standard $/park/per week
Auckland Wellington Christchurch Dunedin
Prime CBD Covered 55–120 45–85 25–45 30–35
Uncovered 35–60 25–35 15–40 20–25
Fringe CBD Covered 25–45 30–60 15–30 15–30
Uncovered 15–25 20–35 10–15 10–15
Suburbs, Uncovered 5–20 5- 20 5–10 5–10
• Rental levels stated are for permanent car
parking spaces and are all inclusive of
rates, etc
2008
Rental Values
Offices, Industrial, Retail
Page 8-516
• Rental values are exclusive of rates, insurances, air conditioning and electricity service costs and
maintenance.
• Area is net lettable area as defined by Property Council of New Zealand Inc ‘Recommended Guide for
the Floor Measurement of Commercial Buildings’. Refer to page 11-548.
• Add extra for outgoings, i.e. Power and cleaning etc, as applicable.
• The net rentals given reflect those achieved for new lettings and do not take into account rent reviews
with sitting tenants.
• The net rentals given ignore transactions involving unusual lease conditions or terms
Rental Review
2008
Land Agents Fees
Basic Scale Of Professional Charges
Page 8-517
In excess of 4 years • 10% of average annual rental including lessee's outgoings plus 1% for
each full year in excess of five years.
• Sale of chattels, key money or goodwill will be at the same rate as the
sale of the freehold property.
• The scale of charges shall be as for freehold sales, plus in addition the
auctioneer will charge the cost of advertising, flagging and
Auction sales disbursements.
• In the sale of leasehold interests in land, the freehold sale charge may be
Leasehold sales increased by 25% to 33%.
2008
Acknowledgements
Page 9-519
1 Acknowledgements
The editors wish to express their appreciation to the following organisations whose assistance
enabled the compilation of this section.
Country Company Contact Details
Australia Rawlinsons, Perth Telephone +61-8-9321-8951
+61-8-9481-1914
Facsimile
Canada Telephone +1-604-688-4262
Butterfield Development Consultants Ltd, +1-604-684-2678
Vancouver Facsimile
Fiji Rawlinson Jenkins Ltd, Fiji Telephone +679-330-0455
+679-330-0375
Facsimile
Hong Kong Franklin & Andrews Ltd, Hong Kong Telephone +852-2815-9411
+852-2815-9348
Facsimile
Japan Construction Research Institute, Japan Telephone +81-3-3663-2130
+81-3-3663-0966
Facsimile
Malaysia Juruukur Bahan Projek, Kuala Lumpur Telephone +60-3-4021-1775
+60-3-4023-3453
Facsimile
Papua New Guinea Fletcher Morobe Construction Ltd Telephone +675-325-3144
+675-325-0020
Facsimile
Singapore Consultants Sees Telephone +65-6316-0683
+65-6316-0684
Facsimile
South Africa Shenel & Simpson Quantity Surveyors Telephone +2721-465-8585
+2721-465-1349
Facsimile
Thailand Thai MM Ltd., Bangkok Telephone +66-2-643-1811
+66-2-643-8638
Facsimile
United Kingdom Franklin + Andrews, London Telephone +44-207-633-9966
+44-207-928-2471
Facsimile
United States Telephone +1-949-476-2094
O’Connor Construction Management Inc., +1-949-476-8294
Irvine, Los Angeles Facsimile
Vanuatu Rawlinson Jenkins Ltd, Fiji Telephone +679-330-0455
+679-330-0375
Facsimile
International Construction Costs
2008
Regional Variation Indices
Page 9-520
2008
Costs per Square Metre
Average Tender Wage
Page 9-521
Industrial
Factories or warehouses for letting m2 455 830 630 7,050 111,000
-525 -930 -850 -8,800 -118,000
Factories or warehouses for owner m2 590 925 650 7,800 165,000
occupation -675 -1,050 -900 -10,800 -183,000
International Construction Costs
2008
Costs per Square Metre
Building Costs per Square Metre
Page 9-522
2008
Costs per Square Metre
Building Costs per Square Metre
Page 9-523
Residential
Individual, excluding air-conditioning
Medium standard, 150/250 m2 m2 1,380 1,700 950 11,000 152,000
-1,490 -1,800 -1,275 -13,000 -232,000
High standard, 200/300 m2 m2 1,935 2,300 1,575 14,000 240,000
-2,080 -2,600 -2,350 -18,000 -302,000
Multi unit, 2/3 bedroom, excluding air-conditioning
Medium standard m2 1,815 1,600 1,300 9,000 152,000
-1,960 -1,800 -1,575 -18,000 -282,000
High standard m2 2,250 2,400 1,450 10,000 257,000
-2,425 -2,700 -2,100 -13,000 -275,000
Retail
‘Shell’ construction for letting m2 1,020 1,350 725 8,500 104,000
-1,080 -1,450 -1,000 -11,000 -122,000
Supermarkets, fully serviced, but excluding m2 1,280 1,700 950 11,000 142,000
cool rooms and shop fittings -1,380 -1,900 -1,250 -14,000 -163,000
International Construction Costs
2008
Costs per Square Metre
Building Costs per Square Metre
Page 9-524
2008
Estimating Rates
Excavation
Page 9-525
4 Estimating Rates
• Costs are ‘all-up’ estimating rates, i.e. they • Figures do not include GST and VAT
include allowance for labours and minor items. taxes
They are indicative average rates for
reasonable quantities of work, applicable to
commercial projects of 2,500 to 10,000 m2.
4.1 Excavation
Excavate over site to reduce levels in typical m3 26.50 52.00 12.00 132.00 610
ground conditions
Excavate trench not exceeding 1.00m deep in m3 52.50 64.00 45.00 190.00 710
typical ground conditions, including allowance for
planking and strutting
Sheet steel piling, including all supports
Temporary, 74 kg m2 269 485 300 2,000 12,300
4.2 Concrete
Concrete, 25 MPa (3500 p.s.i.) in
Foundations m3 235 224.00 245 900 13,300
Ground slab m3 252 230.00 245 900 13,500
Suspended slab and beams m3 248 242.00 250 900 13,300
Walls m3 255 242.00 250 900 13,300
Columns m3 282 255.00 250 900 13,300
Add extra for:
35 MPa (5000 p.s.i.) m3 8.00 10.50 46.00 90.00 2,750
50 MPa (7000 p.s.i.) m3 44.00 25.50 - 150.00 4,700
Formwork, average standard, (close tolerances,
surface with limited imperfections, not subject to close scrutiny)
Soffit of suspended slab m2 83.00 131.00 65.00 200 3,350
Sides of wall m2 109.00 155.00 60.00 170 3,350
Sides and soffit of attached beams m2 110.00 167.00 70.00 290 3,350
Sides of rectangular columns m2 97.00 180.00 60.00 195 3,350
2008
Estimating Rates
Concrete
Page 9-526
2008
Estimating Rates
Brickwork and Blockwork
Page 9-527
4.5 Carpentry
Steel stud framed wall, comprising 75mm framing m2 96.00 99.00 70.00 575.00 5,050
with 10mm plasterboard each face
Framing timber
100mm x 50mm rafter m 11.55 14.10 9.25 75.00 4,250
150mm x 50mm purlin m 19.00 16.20 14.40 115.00 5,500
100mm x 38mm stud m 10.60 9.25 58.00 3,350
100mm x 50mm stud m 12.25 13.80 9.25 75.00 -
2008
Estimating Rates
Window Joinery
Page 9-528
2008
Estimating Rates
Doors
Page 9-529
4.7 Doors
Standard internal flush door, 2040mm x 820mm,
excluding hardware and painting
Hollow core No 170 242 150 1,500 15,000
Solid core No 260 330 200 2,500 27,200
Door frame to suit 2040mm x 820mm door,
excluding painting
Timber, with architraves No 395 210 100 1,200 22,500
Welded steel No 150 242 300 1,500 12,500
Fire door, 2040mm x 820mm, two hour rated, No 1,200 1,080 3,900 8,200 100,000
including steel frame, average quality hardware
and closer, excluding painting
4.8 Roofing
Metal roofing fixed to steel purlins
0.53mm corrugated, zincalume coated m2 43.00 73.00 33.00 770 2,000
0.53mm ribbed, zincalume coated m2 47.00 75.00 33.00 770 2,200
0.53mm ribbed, colour coated one side m2 53.00 84.00 38.00 770 2,600
Three layer bituminous felt or butyl rubber roofing m2 83.00 84.00 65.00 215 2,800
finished with quartz or similar chips, including
upstands
Ceramic wall tiling, standard 150mm x 150mm, m2 98.00 135.00 70.00 285 6,350
white glazed, fixed with adhesive
International Construction Costs
2008
Estimating Rates
Wall Finishes
Page 9-530
2008
Estimating Rates
Flooring
Page 9-531
4.11 Flooring
Floor tiling laid with adhesive (base price tiles)
Mosaic, 50mm x 50mm, in sheets m2 105.00 240.00 80.00 210.00 5,200
Quarry, 200mm x 200mm m2 103.00 145.00 100.00 250.00 7,850
Vinyl sheet, 2mm standard flexible on m2 36.00 39.00 60.00 135.00 2,150
prepared surface
4.12 Painting
Prime, 1 undercoat and 2 top coats alkyd m2 17.15 25.00 10.00 55.00 1,650
enamel on woodwork
1 coat sealer and 2 coats acrylic latex/vinyl m2 11.40 29.00 9.00 45.00 1,100
emulsion paint on plastered walls
4.13 Plumbing
Sanitary fixtures, fully installed, including pipework
to outside face of building at ground level
WC suite, white vitreous china
Single or two storey office building No 2,725 1,970 1,250 4,700 225,000
Ten to thirty storey office building No 4,660 1,850 1,650 5,700
2008
Estimating Rates
Plumbing
Page 9-532
2008
Estimating Rates
Electrical
Page 9-533
4.14 Electrical
• The following are average costs for typical buildings,
including fire alarms, excluding sub-stations, PABX
units, significant site conditions
Hotels
Single/two storey resort m2 165.00 205.00 150.00 1,100.00 22,400
-200.00 -23,600
Three star, tourist m2 195.00 225.00 155.00 1,250.00 25,600
-210.00 -28,800
Five star, international m2 225.00 295.00 200.00 1,875.00 26,700
-275.00 -28,800
Industrial: factory or warehouse with small office m2 45.00 94.00 58.00 470.00 16,000
-120.00 -74.00 -18,100
Office, lettable
1/3 storey m2 100.00 182.00 65.00 19,900
-140.00 -120.00 -20,900
4/10 storey m2 115.00 194.00 65.00 580.00 20,900
-175.00 -120.00 -22,900
10/20 storey m2 135.00 205.00 70.00 580.00 19,700
-240.00 -125.00 -26,100
20/35 storey m2 170.00 215.00 580.00 15,700
-265.00 -32,300
Residential
Individual, medium standard m2 30.00 97.00 48.00 1,100.00 22,100
-50.00 -79.00 -24,200
Multi unit, medium standard m2 58.00 139.00 48.00 1,100.00 17,900
-90.00 -92.00 -20,000
Retail
Supermarket, fully serviced m2 80.00 160.00 60.00 600.00 20,400
-100.00 -110.00 -22,500
International Construction Costs
2008
Estimating Rates
Electrical
Page 9-534
2008
Estimating Rates
Air Conditioning
Page 9-535
4.16 Preliminaries
• Including insurance, plant, supervision, temporary
services, cleaning, maintenance, etc,. on:
Single storey project, suburbs Add 12% 20% 6% 11% 11%
-25% -12%
2/3 storey project, suburbs Add 13% 20% 7% 11% 12%
-25% -14%
4/10 storey project
City centre Add 16% 15% 11% 9.5% 14%
-20% -20%
Suburbs Add 13% 12% 9% 9.5% 13%
-14% -18%
10/20 storey project
City centre Add 20% 12% 11% 8.0% 14%
-14% -20%
Suburbs Add 17% 10% 11% 8.0% 11%
-12% -18%
20/35 storey project
City centre Add 22% 12% 8.0% 16%
-15%
Suburbs Add 19% 10% 8.0% 13%
-12%
International Construction Costs
2008
Estimating Rates
Preliminaries
Page 9-536
1 Websites
1.1 Standards
As promised for several years, the Editor has removed the entire standards section. The full
catalogue is freely available on Standards New Zealand’s website, and given that even the Editor’s
mum can surf the web now, the amount of work required to maintain this section is no longer felt to
be justified.
Standards New Zealand, 155 The Terrace, Private Bag 2439, Wellington 6020
Tel: 64+4-498-5990. Sales: 0800-782-632. Web: www.standards.co.nz.
1.2 Tips for using Standards Website
• Use the Search box, for the searchable catalogue, and some downloadable amendments and
updates. Tip: search by year in the keyword box for recent publications.
• Choose the ‘Catalogue by Industry Sector’ tab, ‘Building’ is at the top of the list on the left.
• Purchase on-line, look for the ‘Purchasing Standards’ tab. Also check out the On-line
Subscription Service for immediate downloads of standards upon payment.
• Look for the ‘Keep me up to date’ link, at the bottom of the website page. Enter your name
and email address, choose the categories you’re interested in, and as standards are updated
or published, you will receive an email keeping you informed.
1.3 Other Websites
Department of Building and Housing www.dbh.govt.nz
DBH—Building Code Compliance Documents www.dbh.govt.nz
BRANZ Ltd www.branz.co.nz
BRANZ—sustainable building www.level.org.nz
ConsumerBuild—partnership between DBH and Consumer www.consumerbuild.org.nz
Green Building Council www.greenbuild.co.nz
Building Research www.buildingresearch.org.nz
Masterspec www.masterspec.co.nz
Energy Efficiency and Conservation Authority www.eeca.govt.nz
Local Government Internet Portal—find a council www.localgovt.co.nz
Construction
Management
2008
Cost Planning Procedures
Introduction
Page 11-539
2008
Cost Planning Procedures
Cost Planning Procedure—Chart
Page 11-540
Determine approx.
Inception
Cost Target or Budget
Preliminary Cost
Preliminary
Plan Including
Sketch Plans
Elemental Costs
Budget Estimate
Final and Cost Plan
Sketch Plans including separate
Elemental Costs
Developed Cost
Design Cost Control Feed Back
Continuing Cost check &
Detail Design Cost Checks
taking remedial action
where necessary
to maintain overall
budget
Working Schedule
Final SoQ
Drawings of
Pricing by Q.S.
Quantities
2008
Design Documentation
Introduction
Page 11-541
2 Design Documentation
2.1 Introduction
For years the building sector has lacked a common language on the varying types of design
services available, as well as their applicability to particular building requirements. This has created
misunderstandings for designers and builders, and for their clients. From misunderstanding, costly
problems emerged.
The industry (through the Construction Industry Council) has picked up this challenge and
developed a set of guidelines, which clearly define the various design stages possible in a building
project, as well as comprehensive checklists on the range of services available. This will be of
immense benefit to clients who wish to discuss their particular needs with builders, architects,
engineers, or others involved in building projects.
2.2 Design Documentation Guidelines
The Guidelines are intended as a general checklist and benchmark for building projects, and have
been prepared primarily for building works, as distinguished from civil works, industrial processes
and infrastructure projects. They are intended to be tailored to the appropriate level of project
complexity and service agreed with the Client; the tick boxes can be used to define the service. The
purpose of the Guidelines is:
• to clearly define responsibilities from the outset and communicate these to all parties involved
in the project;
• to define the Scope of Service with the Client and communicate this to all parties to the
Design Process;
• to provide a level playing field in achieving appropriate remuneration for the standard of
service required; and
• to provide a Quality Assurance reference for users.
2.3 Use of the Guidelines
The Guidelines outline the design process that all building projects go through irrespective of the
procurement methodology or programme. The Guidelines differentiate the design process and
deliverables into the following five phases:
• Concept Design
• Preliminary Design
• Developed Design
• Detailed Design
• Construction Design
For a brief description of each phase, Refer to page 11-543. Download the guidelines from the
Construction Industry Council website, at http://www.nzcic.co.nz/Design.cfm
Design is an evolutionary process, developing from a set of client driven objectives. Within each of
the stages there often can be substantial changes. However, ideally the fundamental elements of
the previous stage should not be overturned.
The guidelines can be used to define the responsibilities of the various parties throughout the
design process. The level of service provided by a designer could be curtailed at any of the stages.
However, the parties completing the design process will need to carry out the remaining steps in a
coordinated manner to achieve an effective design.
The document has separate Guidelines for the primary design disciplines of architecture, structure,
mechanical and electrical engineering etc.
Construction Management
2008
Design Documentation
Use of the Guidelines
Page 11-542
Who has created the Guidelines? The document has been drafted by a working party endorsed
by the Construction Industry Council (CIC). The working party has consulted widely to ensure the
guidelines are workable and benefit the entire building industry, with representation from the
following bodies:
• ACENZ (Association of Consulting Engineers of New Zealand)
• HERA (Heavy Engineering Research Association)
• IPENZ (Institution of Professional Engineers New Zealand)
• NZIA (New Zealand Institute of Architects)
• NZIOB (New Zealand Institute of Building)
• NZ Property Council
• NZIQS (New Zealand Institute of Quantity Surveyors)
• NZBSF (New Zealand Building Subcontractors Federation)
• PMI (Project Management Institute)
• RMBF (Registered Master Builders Federation)
The guidelines have been co-ordinated in process and terminology to be consistent for all
participants in the building industry. The Guidelines have strong support from the professional
bodies listed above, and there is a shared intent that the Guidelines become an industry-wide
document.
How does the document relate to existing professional body documents? The principal
purpose of the document is to comprehensively define the Design Phases. As such, it is hoped that
the document can be integrated into existing professional body agreements for provision of design
services.
How does this document relate to the Management and Administration of the Design
Process? Design management and administration may be undertaken by any of the consultants;
Client, Project Manager, Contractor or specialist Design Manager. Because of the varied nature of
commission structure, the task of design management is not addressed in these guidelines.
However, the following comments are provided:
• Design management may overlap with some of the design processes listed, but may also
include the direction of consultants, the chairing and minuting of regular project meetings and
administration of the design delivery programme.
• The Design Manager may also assist in managing information flow from the Client.
• Responsibility for the Design Management role needs to be confirmed at the start of the
project and the scope of this role either included in the Consultant’s service or defined
separately.
Sample Guideline page, with checkboxes
Construction Management
2008
Design Documentation
Description of the Design Phases
Page 11-543
2008
Cost Management
Preliminary Cost Advice
Page 11-544
3 Cost Management
The control and allocation of monies on construction projects is generally the responsibility of the
professional quantity surveyor. Areas of service offered by the quantity surveyor are:
3.1 Preliminary Cost Advice
From the first concept, quantity surveyors
• give essential, practical advice on the cost of a project
• advise on feasibility and economics of construction projects, forms of contracts, methods of
construction
• prepare cash flow analyses.
3.2 Cost Planning
The prime objectives of cost planning are: to build a project which is economical within design
parameters, optimising value for money; to control cost within the agreed budget; and to achieve a
balance of expenditure between the various functional elements of the project.
3.3 Procurement
On completion of the cost plan, the project moves into the construction stage, which generally
begins with some form of competitive tendering if the building owner's interests are to be fully
protected.
There are many forms of contractual arrangement, each of which has its own advantages and
disadvantages. One role the quantity surveyor undertakes is to identify the form of contract which
best suits the building owner's requirement; for example, cost reimbursement; lump sum traditional
tendering; negotiated construction management; package deal and methods of fast tracking.
Professionally prepared schedules of quantities are an effective cost saving device. They relieve
each tenderer of the onus and therefore the cost of compiling their own, a cost which could
otherwise be passed on to the client in the tender price. Schedules can frequently provide a
greater spread of sub-contract prices, resulting in cost savings to the client.
Schedules also provide the necessary feedback to monitor cost over-runs and form the basis for
processing progress claims, variations to the contract and ultimately the final account. This
documentation process is the last but vital part of the pre-contract cost control service, in itself, it
produces significant savings for the client.
3.4 Post Contract Administration
The monitoring and reporting of actual cost outlays, unexpended monies, variations and regular
plotting of costs versus targets ensures that an up-to-date position can be known at all times. To
many clients a major under-run in time can be as problematical as a major over-run. Only by
regular monitoring can such events be properly identified and avoided.
3.5 Other Services
Quantity surveyors have diversified their activities into other related areas such as: project co-
ordination, project management, project planning, insurance valuations, research and statistics,
specified schedules, design-build evaluation, analysis for taxation purposes, arbitration advice,
market research and analysis on new products and systems, computer software development and
marketing, data collection and dissemination.
Construction Management
2008
Specifications
Different Ways to Specify
Page 11-545
4 Specifications
4.1 Different Ways to Specify
Common ways to produce project specifications are:
Using raw data. Creating every project specification from raw data would clearly be unwieldy,
unnecessary and expensive. However this approach still applies when specifying a new or unusual
product, system, or process.
Adapting a previous specification. Adapting a specification from a previous project is an
approach commonly employed. However this is unlikely to provide a specifier with the
comprehensive range of selections and options needed for specifying a new project. This approach
can also offer a false impression that the content is up-to-date, when it may not have been
independently reviewed for some time.
This approach is inherently flawed and should be avoided, except for projects which closely mirror
their predecessor. Even then, a better approach is to create an office master as a stable base for
each project type.
Using an office master. Most medium-sized and larger design practices maintain some form of
office master specification system. This may range from a system based on a series of standard
sections, designed to be interleaved with project-specific selections and clauses, through to
sophisticated computer-based systems containing a full range of clause and section options, for
individual customising by the project specifier.
Using a master specification system. A master specification system takes this structured
approach one step further. By maintaining access to a wide range of industry expertise, a master
specification system provider can offer greater certainty that the system’s database will accurately
reflect industry thinking. A further critical ingredient is the ongoing maintenance of the master
specification system’s reference base and technical content. Standards, codes, Acts of Parliament,
industry references and accepted construction practice are all subject to continuing development
and change.
4.2 Approaches to Specifying
Different approaches to specifying can be employed within a single master specification system.
The subtractive approach. Where the specifier deletes what doesn’t apply, using a series of
standard work sections. This approach is particularly suited to preparing specifications based on a
requirement to comply, or to confirm compliance with, a prescriptive code or universal standard.
Even under New Zealand’s performance-based approach to building controls, project specifications
will still contain a strong prescriptive element. Most projects will also require the addition of project-
specific data and/or instruction, making a purely subtractive approach unworkable.
The additive approach. Where selections are made from a library of standard clauses, with the
specifier adding project clauses and selections.
The additive approach allows the specifier to ‘mix and match’ clauses from the total specification
database to accurately reflect the project in hand. Being able to add project-specific selections and
project-based descriptive clauses, enhances the ability of a specifier to produce a truly customised
specification.
Recommended approach. Master specification systems such as MasterSpec®—particularly while
they are presented as a series of individual word processing files—are generally customised using
a mixture of subtractive and additive techniques.
Construction Management
2008
Specifications
MasterSpec® Systems
Page 11-546
2008
Specifications
Coordinated Building Information—CBI
Page 11-547
2008
Measurement of Buildings
Physical Content
Page 11-548
5 Measurement of Buildings
5.1 Physical Content
Schedule of Quantities. A schedule of quantities is a document which is procured when
measuring the physical content of a building. It is set out in sections either by trade, element or
physical location and describes the individual items of work which make up a complete building.
The quantity of each item is also given where applicable. Its main use is for tendering purposes,
assessment of variations and progress claims and cost analysis of building projects.
Schedule of Provisional Quantities. Similar to the above, a provisional schedule gives only an
assessment of the quantities involved as it may not be possible to determine them accurately at the
time of preparation. Actual quantities are then recorded when each item of work has been
completed.
Specified Schedule of Quantities. Accurate quantities are given in the normal manner as per the
normal schedule and are complemented by a detailed specification of the items, which is included
either as a preamble to each section or as a part of the description of each item.
Methods of Measurement. It is necessary for a standard to be employed when measuring the
quantities for each item. Standards New Zealand, in conjunction with the New Zealand Institute of
Quantity Surveyors, have produced NZS 4202—The Standard Method of Measurement of Building
Works—which is the most commonly used guideline for measurement of building works.
5.2 Gross Floor Area (GFA)
This method has been adopted for use by the New Zealand Institute of Quantity Surveyors for the
purpose of building cost analysis. A full explanation of the method is given in their “Elemental
Analysis of Costs of Building Projects”.
Unit of measurement: square metres (m2)
The gross floor area is measured over all the external walls of the building, over partitions,
columns, internal structural or party walls, stair wells, lift wells, ducts, enclosed roof top structures
and basement service areas. All exposed areas such as balconies, terraces, open floor areas and
the like are excluded.
Generally, projections beyond the outer face of the external walls of a building such as projecting
columns, floor slabs, beams, sunshades and the like shall be excluded from the calculation of gross
floor areas.
Where the outer face of the external walls of a building are not regular vertical surfaces, the overall
measurements shall be taken at floor levels and a note made of the vertical profile of the wall line.
Where mezzanine floors occur within a structure the gross floor area of this mezzanine shall be
added to all other complete floor areas and become a constituent part of the gross area.
Enquiries to:
• Executive Director, New Zealand Institute of Quantity Surveyors Inc.,
P. O. Box 10 469, The Terrace, Wellington. Tel 64+4-473-5521
5.3 Rentable Area
This method has been adopted for use by the Property Council of New Zealand Inc., for the
purpose of determining rental values, based on the publication “Guide for the Measurement of
Rentable Areas”. Portions of this guide are reproduced with the permission of Property Council of
New Zealand Inc.
The guide is primarily directed to the measurement of floor space in commercial, industrial and
retail buildings and may be used for such purposes as determining rentable areas, project
feasibility, building efficiency, operating and cost apportionment and other related matters.
Applicable throughout New Zealand, the guide is invaluable to property owners, developers,
investors, lessees and all those involved in the provision and utilisation of space.
Construction Management
2008
Measurement of Buildings
Rentable Area
Page 11-549
The method of measurement is broken down into four categories to simplify its application to
different building types and various lease arrangements.
Unit of measurement: square metres (m2). Measurements are generally taken at a height of 1.5
metres above the floor.
Enquiries to:
• National Office, Property Council of New Zealand Incorporated
P. O. Box 1033, Auckland. Tel 64+9-373-3086
Method of Measurement 1. Office Accommodation—Entire Building/Whole Floor
This category of accommodation is intended to apply to modern multi-storey office buildings. This
method of measurement can be applied to any office accommodation in an office building of similar
type. It may be used for measuring the rentable area of an entire building or the rentable area of a
whole floor. This recommended guide is based on the principle that any office building will have the
same total rentable area whether it is leased as an entire building, or on a whole floor or part floor
basis.
1.1 The rentable areas of a building is the total of all the rentable areas.
Method of Measurement 2. Office accommodation—Part Floor
This category of accommodation is found in modern multi-storey office buildings where one or more
floors are sub-divided to facilitate leasing to more than one lessee on any floor. The sum of the
rentable area for each part floor lessee shall equal the total rentable area of that particular floor,
had it been leased on a whole floor basis. In order to determine the rentable area for each part floor
suite, it is necessary to measure the nett area for each suite to which is added an apportioned pro
rata share of the total service area on that floor.
2.1 The nett area for each suite shall be measured to the centre of partition walls. Other wall
measurements shall be taken as for method 1.
Method of Measurement 3. Retail Premises
This method of measurement is intended to apply to all retail premises whether freestanding,
individual premises comprising a group of premises, or part of a shopping complex/shopping
centre, as well as those retail areas which may form a component of a commercial office building or
multiple use complex.
3.1 The rentable area is the floor space confined within the building and available for exclusive
use by the lessee.
Method of Measurement 4. Industrial Type Buildings
This category covers a wide section of commercial and industrial uses but the types of building
envisaged bear a similarity in that they are mostly, though not necessarily, a single storey
freestanding structure with office accommodation built in, attached or adjacent.
4.1 This category consists of those buildings or premises in which more than 50% of the total
rentable area is used for industrial, warehousing, storage or similar use.
Construction Management
2008
Feasibility Studies
Overview
Page 11-550
6 Feasibility Studies
6.1 Overview
The purpose of feasibility studies is to calculate the return which will be derived from a particular
project.
The return can be expressed as an annual percentage return, or as a terminal percentage return.
An annual percentage return will be used where the project will be generating rent for the owner,
while a terminal return is used when the project is to be sold.
The calculated returns are important only for comparisons, i.e., to compare one project with another
or to compare one project's return with the return that would be achieved by investing elsewhere.
6.2 Spreadsheet Versions
Spreadsheet versions of the following tables are included on the CD-ROM, there is a link on the
main CD-ROM Handbook navigation page.
6.3 Calculation Formats
The following tables represent suggested layouts to assist in calculating the return. Item 3 is shown
in alternative forms. The first alternative, 3a, is applicable to an annual return and the second, 3b,
to a terminal return.
1—Feasibility Study—Primary Information
Primary Information Qty/$ value/ Unit
time value
Cost Factors
• Land purchase price $
• Building cost $
2008
Feasibility Studies
Calculation Formats
Page 11-551
2008
Feasibility Studies
Calculation Formats
Page 11-552
2008
Contractual Systems
Traditional Tender System
Page 11-553
7 Contractual Systems
A brief commentary on the contractual arrangements commonly available to prospective building
owners considering property development or construction. Composite forms or variations of these
basic forms may be used.
• traditional tender
• competitive negotiation
• direct negotiation
• cost reimbursement
• design and build
• construction management. Refer to page 11-556.
The major determinants in selecting a particular contractual form are:
• Time available to complete the project, this includes the design period.
• Cost
• The extent of information which will be available at the time of selecting a form of contract.
It is often a balance of these constraints which determine which form of contract is best suited to
each particular project. As this decision is often critical to the success of a project, it is advisable to
seek advice from a professional or principal consultant before choosing the form of contract.
7.1 Traditional Tender System
Tenders may be called for the construction on either:
• a “selected” basis—where tenderers are restricted in number by a process of selection
according to their qualification and experience in the type of project in question.
• an “open” or public basis—where no such restriction exists and public accountability and total
market exposure is paramount, sometimes at the expense of suitability and selective
expertise.
The building owner appoints a project design team comprising an architect, structural engineer,
quantity surveyor, mechanical and electrical engineers and other specialist consultants as required,
depending on the nature and complexity of the project. The building owner commissions the full
design documentation of the project within the cost parameters set by the quantity surveyor’s cost
plan.
Tenders, usually “lump sum”, are then invited from building contractors to ascertain the price of the
works, prior to the final decision to proceed. This lump sum can be either a “fixed price” or may
make provision for fluctuations in material, plant and labour prices. The fixed price lump sum
contract will have no adjustment for price fluctuations.
On awarding the contract to the successful tenderer, the site is handed over to the building
contractor and the contract administered by the architect on behalf of the building owner in
accordance with the contract documents.
The construction work is carried out by the building contractor generally using sub-contract trades.
The design performance obligations rest with the design team and any risks are invariably
underwritten by the individual team members’ professional indemnity insurance. The construction
(contractual) risks rest with the building contractor.
The building owner is therefore reasonably well protected from risks inherent in design and
construction.
Construction Management
2008
Contractual Systems
Competitive Negotiation
Page 11-554
Key points
• price is known before building owner is committed to construction—allowing remedial action
to be taken if the price exceeds budget expectations.
• price is the “true competitive market” price.
• building owner is insulated, for the most part, from “risks”, or at least has contractual
recourse.
• design and tender documentation is complete before proceeding to tender, avoiding the
incidence of major cost variations.
7.2 Competitive Negotiation
The building owner appoints a consultant team to prepare schematic design drawings up to
preliminary working drawings stage, outline specification including a schedule of construction and
finishes, a provisional schedule of quantities and a form of a building contract.
Tenders are called from a selected list of building contractors, for the following elements:
• Preliminaries—i.e. Builders price for site mobilisation, day to day running and final
demobilisation, construction plant including cranes, scaffold, etc., builders insurances,
temporary and on-site services, water, phones, electricity, periodic and final clean-up, and
builder's site administration, including supervision.
• a tendered percentage or lump sum for margins to be based on the value of work when
known.
• a tendered percentage or lump sum for off-site overheads.
• a tendered percentage or lump sum for attendance on sub-trades.
• statement of the time required to complete the project accompanied by the builder's bar chart
or other programme scheduling.
Tenders, submitted in accordance with the above requirements, are evaluated by the consultant
team and a recommendation is made to the building owner. On a recommendation in favour of one
of the building contractors being accepted, that builder then joins the project team as a building
consultant and his practical building expertise is then used in final design documentation before he
proceeds to perform the building works.
The appointed builder prices documentation as it becomes available for final acceptance by the
building owner. This is usually done by the builder calling competitive bids from, say, three sub-
contractors for each trade package.
Key points
• this is essentially an accelerated system of procuring a contract, the main object being to
install a selected builder on site and working, before formal design documentation is
complete, resulting in an earlier completion and all the advantages stemming therefrom.
• the selected builder becomes a member of the team and is available to add his expertise to
the advantage of the project.
• sub-contract prices are tendered just prior to when needed, thereby obtaining current market
prices.
Construction Management
2008
Contractual Systems
Direct Negotiation
Page 11-555
2008
Contractual Systems
Definitions
Page 11-556
A general foreman supervises all on-site activities; a cost clerk and a limited number of carpenters
and labourers are also engaged to attend on other trades and execute minor sundry works.
Costs are controlled by the quantity surveyor, with a continuous audit of actual costs incurred.
Payments are made to trade contractors, suppliers and “on-site” employees by the client.
7.7 Definitions
Construction Management. The construction manager—an individual, consultancy firm, or a
builder—is selected and appointed by the proprietor, or the project manager on the proprietor's
behalf, and carries out the work normally performed by a builder in a traditional system.
S/he organises, manages and co-ordinates the construction of the project on a consultancy basis
for a fee. The construction manager does not have any direct commercial interest in the work
carried out by sub-contractors, as all sub-contracts are between proprietor and sub-contractor.
Thus s/he neither benefits nor suffers from the contractual risks attendant upon a traditional
contract.
Project Management. A project manager is an agent of the proprietor and assumes the role of the
proprietor in a construction project where the proprietor lacks the technical and organisational skills
for the task. The project manager becomes responsible for preparing a brief, and appointing and
co-ordinating the consultants.
The proprietor's requirements are conveyed to the project manager who ensures that they are
acted upon by the consultants and contractor. S/he may, if engaged for a total service, be
responsible for such matters as;
• site selection
• feasibility studies
• preparation of consultants briefs
• selection of consultancy team
• negotiation and documentation of conditions of engagement
• evaluation of design profiles
• supervision of documentation
• implementation of programme
• selection of contractual system
• contract financial control
• supervision of letting
• many other services.
It should be noted that the engagement of a project manager is not affected by the contractual
arrangement adopted. S/he can serve the client in virtually the same capacity whether it be a
traditional “tender” or a “construction management” contract.
Construction Management
2008
Contract Conditions
New Zealand Institute of Architects Inc
Page 11-557
8 Contract Conditions
A number of standard Conditions of Contract exist to cater for a variety of building and civil
engineering projects. This section outlines the type of project for which the particular conditions are
suited.
8.1 New Zealand Institute of Architects Inc
SCC 2007 conditions are copyright to NZIA, and can only be legitimately used if a licensed NZIA
member architect is involved in administering the contract works, and that architect also holds an
annual licence to use the document. Copies can be purchased at www.nzia.co.nz.
Standard Conditions of Contract—SCC 2007 1st Edition
The SCC 2007 document is intended to be suitable for any size of contract where an architect is
involved in the administration.
Schedules to the Standard Conditions of Contract SCC 2007 include:
A1 Contract Agreement and Contract Documents
B1 Specific conditions of Contract
B2 Special conditions of Contract
C1 Fluctuations in Cost
C2 Schedule of quantities
D1 Contractor’s performance bond
D2 Principal’s bond
D3 Contractor’s bond in lieu of retentions
E1 Contractor’s advice of achieving Practical Completion
E2 Producer statement – construction
F1 Contractor’s insurance information
F2 Contractor’s professional indemnity insurance
F3 Principal’s insurance information
G1 Warranty agreement
G2 Separate agreement to arbitration
G3 Security for off Site goods / materials
2008
Contract Conditions
Standards New Zealand
Page 11-558
2008
Retentions
NZIA SCC 2007
Page 11-559
9 Retentions
For worked example of retention formula, Refer to page 14-651
9.1 NZIA SCC 2007
Parts of the NZIA Standard Conditions of Contract SCC 2007 1st Edition relating to retentions are
reproduced herein with the express permission of the New Zealand Institute of Architects. All
copyright provisions contained in SCC 2007 apply equally to these reproduced clauses.
14.2 Architect’s assessment of Payment Claims
The Architect must deduct the following amounts from the amount the Architect
assesses:
(a) any retentions the Principal is entitled to retain;
(b) any other amounts which the Contract allows to be deducted;
14.2.3 (c) the total of the amounts previously certified for payment.
14.9 Retentions
The Principal is entitled to retain an amount to ensure performance and to cover
14.9.1 liability for any defects. This amount is stated in the Specific Conditions.
The Contractor is entitled to require that the amount retained by the Principal is
14.9.2 secured in a manner reasonably acceptable to the Contractor.
When the Architect certifies Practical Completion of the Contract Works or a
Separate Section, the Architect must at the same time issue a Payment Schedule
under Rule 14.6 showing the retentions payable as the Scheduled Amount. The
percentage of the retentions payable when Practical Completion has been
14.9.3 achieved is stated in the Specific Conditions.
When the Architect certifies that the Contractor has completed all omissions,
corrected all defects, completed all deferred work and the Defects Liability Period
for the Contract Works or a Separate Section of them has ended, the Architect
must at the same time issue a Payment Schedule under Rule 14.6 showing the
balance of the retentions as the Scheduled Amount. The percentage relating to
14.9.4 liability for any defects is stated in the Specific Conditions.
The issuing of a Practical Completion Certificate or a Defects Liability Period
certificate does not relieve the Contractor of any of the Contractor’s obligations
14.9.5 under the Contract which remain unperformed or not properly performed.
2008
Retentions
NZS 3910:2003
Page 11-560
2008
Retentions
Schedules to General Conditions of Contract
Page 11-561
2008
Construction Periods
Schedules to General Conditions of Contract
Page 11-562
10 Construction Periods
The time required for the construction of a building is so closely linked to the time required for
design and documentation, that project period is probably a better term than construction period.
There is, however, an important reason why the two are separated. During design and
documentation, the capital expenditure on a project is far less than during the construction phase,
and thus in commercial building projects, it is important that the construction phase is kept as short
as possible.
The time required for design and documentation is referred to as the pre-construction period and
this may, in some cases, exceed construction time. It is advisable to spend additional pre-
construction time planning and programming the project rather than to make a premature start on
construction.
An unrealistically short documentation period can result in an extended construction period,
attracting extra costs for variations, time extensions and finance holding charges. It can be argued
that a short documentation period results in savings due to the reduced period in which inflation can
occur.
The most effective financial situation for a commercial building would be sufficient documentation
period to enable an optimum construction period. In certain cases, the advantages and savings
given by sufficient documentation and optimum construction period, are outweighed by commercial
considerations. For example, a shopping centre which, regardless of cost, must open to take
advantage of the Christmas buying season.
The relationship between project cost and project period is affected by numerous factors, including
complexity, material choice and values, critical activities and techniques. The relationship, when
based on historical data, provides one of the most reliable methods of establishing project and
construction periods. For example, if records show that high rise multi-storey office blocks during
construction period average monthly payments of $750,000, then the total estimated cost of a
proposed building divided by the monthly amount will give an approximate construction period.
To establish the documentation period is considerably more difficult, as the design process is less
tangible and therefore less predictable than construction. Records concerning documentation
periods are also less precise and less plentiful than those concerning construction.
In the following guide, the documentation periods shown do not include delays caused by client or
committee approvals, rejections and modifications or industrial strikes. The times stated assume a
minimum of abortive time.
Building Type Value $m Approximate Duration in Weeks
Documentation Construction Total Project
Simple Projects 0.5–1 5–10 15–25 20–35
e.g. warehouses, etc. 2–3 8–12 40–50 48–52
2008
Construction Periods
Acceleration
Page 11-563
10.1 Acceleration
‘Acceleration’ is a term which is used when the project period—combined design and construction
time—has been deliberately shortened by intentional and detailed planning throughout the project.
For acceleration to achieve its optimum reduction in time, it is essential that every member of the
project team be involved and fully committed to the concept. It will require very high standards of
management, development of good working relationships, practical quality control procedures and
a lot of mutual trust. Trust is an exceptionally important ingredient as work often has to proceed in
anticipation of a definite decision.
There are many reasons why project periods need to be shortened. Shortened project periods can
sometimes mean extra cost to the client, and before embarking on a ‘accelerated project’, the client
should consider the possible additional costs versus the intended benefits of early completion/
occupancy.
Research shows that much of the difference in efficient and inefficient projects can depend on the
effectiveness of the client.
The chart is a guide to the differences in construction times between accelerated, medium
performance and traditionally managed contracts.
Note: times shown are for building structure and incorporated services only.
Allow extra time for tenancy fit-out and specialist services etc.
24
22
Accelerated
Medium
20
18
Traditional
Cost in $millions
16
14
12
10
8
6
4
2
0
12
15
18
21
24
27
30
33
36
0
2008
Cash Flow
Client’s View Point
Page 11-564
11 Cash Flow
11.1 Client’s View Point
Cash flow prediction is the forecasting of cash needed to be provided by the building owner at pre-
determined dates in a building construction programme, for the purpose of making progress
payments to the builder for work executed.
An accurate estimate of cash flow for project payments is essential to the organisation that will
provide funds for the project. It will give advance notice of the funds needed and the timing of draw-
downs.
Such an estimate is usually prepared before the contractor commences work and is obtained by
preparing a programme of construction activities for the project, costing these activities and
obtaining anticipated expenditure on a month to month basis.
11.2 Contractor’s View Point
Contractors may operate from a relatively thin capital base and the demise of many firms can be
directly related to poor or inadequate cash flow management.
Income and expenditure are combined to arrive at a net inflow or outflow of cash for each period. A
time related schedule of receipts and payments is prepared to give a cash flow statement.
A key factor in cash flow control for the contractor is to develop a system which will compare actual
with projected cashflow.
11.3 Example of Cashflow
An example is given of a simplified cashflow prepared for the client, for a two-storey hostel costing
$1,200,000 with a 10 month construction period.
The example assumes a fixed price lump sum contract with no provision for fluctuations and
assumes that a bank guarantee will be operating with no retentions being held.
It should also be noted that a delay of 20 days or so elapses between the end of a “construction
month” and the actual payment for the work done in that period. This delay should be allowed for in
any cash flow.
The example is for construction work only and excludes other periodic payments to which the client
may be committed, e.g. Consultants fees, land costs, finance costs, etc. Refer to page 11-565.
Construction Management
2008
Cash Flow
Cashflow—Worked Example
Page 11-565
2008
Cash Flow
S—Curve
Page 11-566
11.5 S—Curve
As an alternative, analysis has consistently shown that cash flows follow the “lazy S” curve for
construction purposes. This method is intended as a guide only and variations will apply according
to the total cost of the work and whether or not lifts, sprinklers, air conditioning and other specialist
services are involved.
After reading off the theoretical amount expended against the time scale, additions or adjustments
should be made to accommodate unusual or extraordinary items such as: interest, professional
fees, pre-ordering, retentions.
From the graph it can be seen that 50% of the contract value is expended at 60% of the contract
period.
100
90
80
70
Construction Cost - % Complete
60
50
40
30
20
10
0
100
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
0
C o n t r a c t C o n s t r u c t io n P e r io d - % C o m p le t e
2008
Property Insurance
Indemnity value
Page 11-567
12 Property Insurance
A property may be insured in one of two ways—either for “indemnity value” or for “replacement
value”.
12.1 Indemnity value
Provides the lesser cover—a building so insured provides cover for the value of the building as it
stands, i.e., Likely depreciated, outdated and not conforming to design regulations. If total loss
occurs, the insurer would pay the actual value of the property destroyed. If the loss is a partial one,
the insured may be required to contribute to the cost of repairs if remaining old construction is
replaced with new. The policy will only place the insured in the position he was in, prior to the loss—
no better, no worse.
12.2 Replacement value
An old building may have an indemnity value of $200,000 and a replacement value of $1,000,000.
Replacement involves the construction of a building having the same functional use and of the
same usable area as the old building, but complying with modern technology, and conforming to
regulations and by-laws which may have been adopted since the original building was constructed.
An existing building, of whatever age, adequately insured in this category, would absolve the owner
from undue expense in the event of building loss. An existing building constructed of, say, pipe
columns and metal cladding, if destroyed, could well be required to be replaced with a building of
reinforced concrete and block construction. If the insurance premiums covered this “extra cost”
element, in other words the building was adequately insured, then the owner would be subjected to
no expense if loss occurred.
At present in New Zealand the insurance industry recommends that properties of consequence
have reinstatement insurance. The average business or individual does not have the ready capital
to bridge the gap between indemnity value and full replacement cost.
Construction Management
2008
Insurance Valuations
Valuing Buildings for Insurance
Page 11-568
13 Insurance Valuations
13.1 Valuing Buildings for Insurance
The calculated value of a building comprises several elements:
• present rebuilding costs;
• allowance for cost escalation/reduction during the period of insurance and/or construction;
• professional fees;
• removal of debris;
• reinstatement costs—increased construction costs should the reinstatement period exceed
the period of insurance.
Some or all of these cost factors could be automatically included in the premium quoted by the
insurer, but it is extremely important to establish the extent of such inclusions.
Example Valuation for Insurance Purposes
Building Element Calculation Time % $ value
Estimated/calculated building value on acquired data, at rates current at the $1,500,000
time of estimate
Cost escalation for period
Design and documentation 3 months
Calling tenders and appraisal 1 month
Construction period and fit-out (mean cash point) 7 months
Total = 11 months
11 months escalation in building costs—say 0.33% per month = 3.63% $54,450
Sub-Total $1,554,450
Professional fees—say 10% $155,445
Cost of removal of debris, say $15,000
Sub-Total $1,724,895
Cost escalation in the lapse period possible between policy
renewal dates
(worst case assumed)—12 months @ 0.33% = 3.96% $68,305
Total insured $1,793,200
Such value represents building costs only, and excludes factors such as loss of revenue in the
period between building loss and reinstatement, cost of leasing alternative premises in the same
period, removal and upset expenses, etc.
The principal cost of any valuation, and one which affects all other on-costs, is the building cost. It
is advisable to obtain professional advice, through a quantity surveyor or the like, before the
insured commits himself to the payment of insurance premiums.
Above all, it is important that building owners protect their investments by periodic cost reviews of
their buildings, in terms of inflation and the cost effect of the introduction of statutory and other
building regulations, by-laws, etc.
Construction Management
2008
Operating Costs of Buildings
Cost Categories
Page 11-569
2008
Operating Costs of Buildings
Accounting for Operating Expenses
Page 11-570
2008
Life Cycle Costing
Summary
Page 11-571
Capital Cost
Maintenance/Energy Cost
Durability of Building
All past, present and future cash flows identified in an LCC analysis have to be converted to
present value dollars.
The normal method of dealing with these cash flows is to use a technique called discounted cash
flow (DCF).
Construction Management
2008
Life Cycle Costing
Discounted Cash Flow—DCF
Page 11-572
Where P = a present sum of money, F = a future sum of money (equivalent to P at the end of N
periods of time at an interest rate of i), i = interest rate, N = number of interest periods.
1
P = 2000 × -------------------------------
10
( 1 + 0.07 )
1
P = 2000 × ----------------------------
1.9671514
Assume an interest rate of 12% and investment period of 30 years. Refer to page 11-573, and
Refer to page 11-574.
Construction Management
2008
Life Cycle Costing
Example of LCC Analysis
Page 11-573
2008
Life Cycle Costing
Example of LCC Analysis
Page 11-574
2008
Life Cycle Costing
Alternative calculation method
Page 11-575
2008
Professional Fees
LCC Analysis Generally
Page 11-576
16 Professional Fees
Traditionally fees for professional services have been governed by a minimum scale of charges laid
down by the various professional institutes and organisations. Members who charged less than the
set fees were liable to be disciplined by their Institute.
The advent of the Commerce Act 1987 legislated that any scale of fees for professional services
would hence become non-mandatory, although some professionals pre-empted this decision and
had previously removed restrictions on scales of charges for their members. Fee scales are issued
only as a recommended document and a guide to the scope of services carried out by each
profession.
Removals of limitations on charges means that clients and consultants now openly negotiate the
conditions of engagement and fees on any terms or basis they deem appropriate. The
recommended scales however are still generally considered to represent the best interests of both
parties.
Aside from the above changes a more competitive market has resulted from decline in construction
activity. Other important factors to consider when determining professional fees are the building
type, i.e. its intended use, and the scope of the services required.
Further information and recommended fee documents are available from the professional bodies.
The following table is indicative of the likely range of fees for consultants engaged on a “full service”
basis.
Likely range of consultants fees on various project types
Building type Value $ Consultants Fee%
1–3 storey administration 1,500,000 a, se, ee, me, la, qs 11.0–12.5
City hall, 2,000 capacity 7,000,000 a, se, ee, me, sc, la, qs 10.0–13.0
Secondary school, laboratory building 950,000 a, se, ee, qs 10.0–12.0
Multi storey general hospital 60,000,000 a, se, ee, me, sc, qs 10.0–12.0
Warehouse 3,000,000 a, se, qs 7.0–9.0
Other building, 20 storey 18,000,000 a, se, ee, me, qs 9.0–11.5
Parking building, multi-storey 6,000,000 a, se, ee, me, qs 9.0–11.5
Residential—high quality house 750,000 a, se, qs 8.0–11.5
Residential—medium quality house 350,000 a, ad, se 6.0–8.0
Residential—medium quality house 200,000 a, ad, se 4.0–6.0
2008
Value Management
Introduction
Page 11-577
17 Value Management
17.1 Introduction
Value management is a disciplined procedure directed towards the achievement of required
function for minimum cost without detriment to quality, reliability, performance or delivery. In the
United States the procedure is known as value engineering.
The procedure is conducted through a workshop or series of workshops involving the client, the
design team and other relevant stakeholders (where appropriate). The workshops are led by a
value management facilitator who takes the participants through a structured problem solving
agenda intended to find creative solutions to the client's requirements.
Experience has shown that the value management procedure is extremely useful as a means of
reviewing a design proposal. However, it has been found that the decisions that have the greatest
impact on cost are made at the outset of the project when strategic decisions regarding the purpose
and required functions of the project are made. Current practice with value management is
therefore to break it into a two stage process—strategic value management and design value
management.
17.2 Strategic Value Management
Strategic value management is used to review the strategic intent of the project. It is most
commonly conducted during the pre brief stage. It is used to clarify the strategic intent of the project
and the functional requirements of the project. The use of a value management workshop enables
matters such as the project priorities and economic restraints to be fully examined and alternative
solutions considered.
Whilst cost savings cannot be clearly defined at this stage—as the project itself is not clearly
defined—experience suggests that conducting value management at this stage can have a very
significant impact on project cost.
17.3 Design Value Management
Design value management is used to review design proposals. During the workshop consideration
is given to whether all the client's requirements are being fulfilled, whether additional value can be
added to the project and whether cost savings are possible without detriment to quality, reliability,
performance or delivery.
Typically, cost savings achieved at a design value management workshop are in the order of 10%.
Legislation
1 Introduction
The purpose of this section is to draw attention to some of the more important Acts of Parliament
directly applicable to or affecting the construction industry in New Zealand.
A brief description of the main Acts is also given. For full details of contents of legislation, visit
www.legislation.govt.nz
Bills progressing through the House, may also be viewed or downloaded for free, at
www.clerk.parliament.govt.nz, look for the Parliamentary Business tab and look for the Bills
section.
Legislation
2008
Acts of Parliament
Page 12-579
2 Acts of Parliament
Name of Act Description of Act
Accident Compensation To promote safety, prevent accidents, provide rehabilitation and
Act 1982 compensation of persons in New Zealand who suffer injury by accident. No
right exists to sue for damages as result of personal injury.
Accident Insurance Act Effective 1 July 1999, employers must have workplace accident insurance
1998 cover for employees, that provides any injured employee with at least the
cover and entitlements provided for by legislation. This remains the
principal Act, with some aspects amended—see below.
Accident Insurance These Acts together amend arrangements so that ACC (the Accident
Amendment Act 2000, Compensation Corporation) is reinstated as the sole provider of workplace
Accident Insurance accident insurance. No new contracts may be issued by private insurers as
(Transitional Provisions) of April 1, 2000, and all businesses have their cover reverted to ACC as of
Act 2000 July 1, 2000.
See Injury Prevention, Rehabilitation and Compensation Act 2001, Refer to page 12-583
Acts Interpretation Act Sets out how Acts of Parliament are constructed. One important provision
1924 is that Acts of Parliament do not bind the Crown unless stated specifically
within the particular Act.
Anzac Day Act 1966 Public holiday on April 25. Observed up to 1.00 pm as a Sunday, thereafter
as a Saturday unless the day is a Sunday. Always observed on the actual
day and is not transferred to the nearest Monday.
Apprenticeship Act 1983 Purpose of this Act is encourage or help people to take up and complete
apprenticeship and training. It concerns the employment and training of
apprentices under contract with the involvement of apprenticeship
committees. Replaced by Modern Apprenticeship Training Act 2000.
Arbitration Act 1996 Disputes can be referred to arbitration instead of the courts. The arbitrators
(replacing Arbitration Act decision is final unless he has acted improperly or is in error on a point of
1908) law. Arbitration is private, does not create a precedent and the costs are
borne by the dissenting parties.
Architects Act 1963 Repealed. Refer to Registered Architects Act 2005 below
Boilers, Lifts, and Cranes An Act to make provision for the inspection and certification of boilers, lifts,
Act 1950 cranes and certain other machinery, for the safety of persons working with
boilers or machinery to which the Act applies, and for the qualification of
persons operating any such boilers or machinery.
Building Act 2004 and The purpose of this Act is to provide for the regulation of building work, the
amendments 2005 establishment of a licensing regime for building practitioners, and the
setting of performance standards for buildings, to ensure that; people who
use buildings can do so safely and without endangering their health;
buildings have attributes that contribute appropriately to the health, physical
independence, and well-being of the people who use them;
people who use a building can escape from the building if it is on fire; and
buildings are designed, constructed, and able to be used in ways that
promote sustainable development.
Building Research Levy Act To provide for research into improved techniques and materials for use in
1969 the building industry. It funds the Building Research Association of New
Zealand. A levy is payable at the rate of $1.00 per $1,000 ,or part thereof,
of contract value (minimum $20,000 contract value.) The levy is payable to
the local authority with the building consent.
Chartered Professional To reform the law relating to the registration of engineers and to establish
Engineers of New Zealand the title of chartered professional engineer as a mark of quality
Act 2002
Legislation
2008
Acts of Parliament
Page 12-580
2008
Acts of Parliament
Page 12-581
2008
Acts of Parliament
Page 12-582
2008
Acts of Parliament
Page 12-583
2008
Acts of Parliament
Page 12-584
2008
Acts of Parliament
Page 12-585
2008
Acts of Parliament
Page 12-586
2008
Arbitration Act 1996
Introduction
Page 12-587
2008
Arbitration Act 1996
Main Points—The Act itself
Page 12-588
2008
Arbitration Act 1996
Main Points—The Act itself
Page 12-589
2008
Building Act 2004
Acknowledgement
Page 12-590
2008
Building Act 2004
Key Dates
Page 12-591
2008
Building Act 2004
Key Dates
Page 12-592
2008
Building Act 2004
Scope Of Building Work Under The Act
Page 12-593
30 November 2009
Building consents
• Applications for building consents will have to include a list of the licensed building
practitioners who will be involved in the project.
Licensing of building practitioners
• The Act sets up a system for licensing building practitioners.
• Restricted work: Regulations will define certain work as having to be done or supervised by a
Licensed Building Practitioner. This work is called 'restricted work'.
• Categories of licences: Exactly what types of trade will be licensed will be set out in
regulations. The Department of Building and Housing will run the licensing system.
• Board: People will be able to make complaints about licensed building practitioners. These
complaints will be heard by an independent Board.
• A licensed building practitioner will have to do, or supervise, any restricted work from 30
November 2009.
Building consents (sections 40-52)
• From 2009 the consent process will include providing confirmation that a licensed building
practitioner is involved in the project. Licensed building practitioners will also be required to
notify the building consent authority of breaches to the building consent.
4.5 Scope Of Building Work Under The Act
Section 8 of the Building Act 2004 defines Building: what it means and includes
• temporary or permanent, movable or immovable, structure
• electrical/mechanical or other system attached to building structure
• fence as defined in section 2 of Fencing of Swimming Pools Act 1987
• vehicle or motor vehicle that is immovable and occupied by people on a permanent or long-
term basis
• mast pole or telecommunication aerial on or part of a building, and more than 7m in height
from point of attachment or base support
• any 2 or more buildings that, on completion of building work, are intended to be managed as
one building with a common use and a common set of ownership arrangements
• non-moving parts of cable car attached to or servicing a building, and, from 30 March 2008,
moving parts of those cable cars.
Section 9 of the Building Act 2004 defines Building: what it does not include
• a NUO (network utility operator) system, or part of a NUO system, external to the building,
connected to or intended to be connected to the building, and not a mast pole or
telecommunication aerial on or forming part of a building
• cranes
• ski tows or other similar stand-alone machinery systems
• any description of vessel, boat, ferry or craft used in navigation
• aircraft
• offshore installations to be used for petroleum mining
• containers as defined in section 2(1) of the Hazardous Substances and New Organisms Act
1996, ie, means any vessel or structure, whether moveable or fixed, in which hazardous
substances may be cased, covered, enclosed, contained, or packed
• magazines as defined in section 2(1) of the Hazardous Substances and New Organisms Act
1996, ie, means any building, chamber, cave, pit, cellar, hulk, floating vessel, or place in
which explosives or partly manufactured explosives are stored.
Legislation
2008
Building Act 2004
Licensed Building Practitioners
Page 12-594
2008
Building Act 2004
Useful Links
Page 12-595
Key facts
• The Building Code review will take three years. It is scheduled for completion by 30
November 2007.
• The review team will report to the Minister with a set of recommendations for changes to the
Building Code.
• Industry, government and consumer representatives are being engaged in the process.
• Implementation of any changes will be after 30 November 2007.
The review will look at the Building Code and Compliance Documents (currently called Approved
Documents).
This is a comprehensive review—the first since 1991. It will begin with a period of research into
both content and structure of the Building Code.
The entire content of the Building Code and Compliance Documents will be reviewed.
4.8 Useful Links
Department of Building and Housing website links (clickable on CD-ROM)
• Building Act 2004 Guidance
• Building Code Compliance Documents
• Building Controls Update
• Technical Reports published for DBH
Legislation
2008
Employment Relations
Introduction
Page 12-596
5 Employment Relations
5.1 Introduction
The Employment Relations Act 2000 had effect from 2 October 2000, when it replaced the
Employment Contracts Act 1991. From 2 October 2000, the legal requirements for employment
relationships have changed. Any new collective or individual employment agreement after this date
needs to comply with the requirements of the Employment Relations Act. The ERA has been
amended three times, in 2001 and 2004.
5.2 Objectives
The goal of the Act is to build productive employment relations between employers, employees and
unions.
Specifically, the Act:
• promotes good employment relationships and mutual respect and confidence between
employers, employees and unions.
• sets the environment for individual and collective employment relationships.
• sets out requirements for the negotiation and content of collective and individual employment
agreements.
• provides prompt and flexible options for resolving problems in employment relationships.
5.3 Existing Agreements
The terms and conditions of all existing individual or collective employment contracts remained the
same on 2 October 2000. Any disputes or grievances in existence at that date continue to be dealt
with under the rules of the Employment Contracts Act 1991.
5.4 Good Faith
The principle of good faith is an essential part of the Act. Good faith requires the parties to
employment relationships, including unions, employers and employees, to deal with each other on
the basis of fair dealing and mutual trust and confidence. This includes, but is not limited to, not
directly or indirectly misleading or deceiving each other.
In respect of collective bargaining, the core good faith duties include, but are not limited to, the
obligations to:
• meet, consider and respond to any proposals made.
• respect the role of the other party’s representative by not bargaining or communicating with
those for whom the representative acts, about employment conditions.
• fairly represent the other party’s position in the negotiations to those on whose behalf the
other party is acting.
• provide relevant information necessary for the purposes of negotiations.
5.5 Freedom of Association
The Bill provides for voluntary membership of unions, and not allowing any person to exert undue
influence in employment arrangements, in order to influence the choice of whether to belong to a
union or not.
5.6 Unions
Union membership is voluntary. Unions can represent both individuals and groups of employees.
To support their role, unions will be able to enter workplaces to:
• negotiate or enforce employment agreements.
• deal with safety and health matters affecting members.
• provide information about unions.
• recruit new members.
Legislation
2008
Employment Relations
Independent Contractors
Page 12-597
2008
Employment Relations
Access to Information
Page 12-598
Where strike action occurs, and normal work is unavailable as a result of the strike, an employer
may suspend non-striking employees without pay.
5.11 Access to Information
Claims made when bargaining for a collective agreement must be able to be backed up by
information. For example, if the union claims there is a risk of a labour shortage in the industry, the
employer can ask for evidence, or if an employer claims that profits are expected to be tight in the
coming year, the union can ask for evidence.
A request for evidence must be in writing, it has to identify specifically the information sought and
has to identify specifically the claim it relates to. A reasonable time frame must be given for the
information to be supplied.
If either party believe the information needs to be kept confidential, parties can agree on an
independent reviewer to protect the information and make a decision on the point in question.
If the reviewer agrees the information should be kept confidential, the reviewer will then report on
whether it backs up the claim.
If the reviewer decides that some or all of the information does not need to be kept confidential, the
reviewer will advise both parties and return the information to the party that provided it. That party
should then, in good faith, provide the information to the other party.
The information can only be used for the bargaining process. It cannot be shown to anyone else.
For more information, refer to the Employment Relations Service website, www.ers.dol.govt.nz
Legislation
2008
Historic Places Act 1993
Registration under the Act
Page 12-599
2008
Resource Management Act
Overview
Page 12-600
2008
Resource Management Act
Time Limits
Page 12-601
The documents by which central government can set policy and participate in the resource
management process are national policy statements, national environmental standards, and New
Zealand coastal policy statements.
National policy statements deal with matters of national significance and are binding on the plans of
regional and territorial authorities. National environmental standards set out more detailed and
technical requirements, particularly for standards of water, air and soil quality, and noise levels.
Regional councils are responsible for the regional effects of land use, soil conservation, activities
on the beds of lakes and rivers, other matters in respect of the quality and quantity of water,
pollution management generally (and the management of hazardous substances and discharges of
contaminants in particular), and the taking and use of geothermal energy.
Territorial authorities (i.e. District and City Councils) are obliged to prepare district plans and rules
which must be consistent with national and regional policy statements and regional plans.
The functions of territorial authorities extend only to the resources of that district or city, principally
land protection and controls of land use, subdivision, noise and the effects of activities on the
surface of rivers and lakes. Activities not referred to in the district plan are deemed to be non-
complying activities.
Any person is entitled to make submission to a consent authority, and following that appeal to the
planning tribunal, in respect of a notified application for consent. Objections to an application on the
sole basis of trade competition are not permitted.
7.5 Time Limits
A number of time limits are imposed at various stages of an application or the review of the
provisions of a district or regional plan. For example, where public notification of a resource consent
application is required, this must occur within 10 working days of receipt of the application;
submissions must be made no later than the 20th working day after notification; consent authorities
must notify decisions on consent applications within 15 working days after the conclusion of
hearings, and within 20 working days after receipt of applications for non-notified applications;
appeals from consent authority decisions must be lodged with the planning tribunal and served on
the authority within 15 working days from receipt of the decision.
There are provisions in the Act for streamlining the procedures by way of pre-hearing meetings
convened by consent authorities for mediation purposes, and for joint hearing where different
consent authorities are involved.
However, deadlines can be extended by consent authorities if it is decided more information in
respect of an application is required.
7.6 Information To Be Supplied
The Act imposes a high standard of supporting information to accompany applications, including a
detailed environmental impact assessment. How much detail is required will depend on the nature
of the activity for which consent is required. All possible effects of a proposed activity must be dealt
with in this assessment report, often requiring input from a multi-disciplinary team. If information is
omitted or inadequate, it could result in an application being significantly delayed, and/or being
turned down.
Regional and territorial authorities are empowered to fix charges for a range of activities including
plan changes, processing consent applications, information gathering and monitoring, and
providing information to applicants, consent holders and the general public.
In some circumstances, local authorities may also impose charges in order to recover their actual
and reasonable costs. These charges are in addition to resource contributions, bonds or other
financial contributions which may be required as conditions of resource consents.
While the aim of the legislation is to streamline the resource consent process, there are a number
of opportunities for increases in costs and delays, most of which are met by resource consent
Legislation
2008
Resource Management Act
Prosecutions and Remedies
Page 12-602
applicants.
7.7 Prosecutions and Remedies
Declarations can be made by the planning tribunal, on application by any person, in respect of
interpretation of the Act and whether or not a breach of the Act or rule in a plan has occurred.
Enforcement orders are obtainable by anyone from the tribunal, restraining activity in breach of the
Act or requiring compliance. These can be granted on an urgent, interim basis.
Abatement notices are issued by enforcement officers, requiring the cessation of an activity which
is in breach of the Act, a plan or resource consent, or which is environmentally dangerous.
7.8 Offences and Penalties
Strict liability is imposed in respect of offences for breach, or permitting a breach, of the duties and
restrictions created by the Act. This means that it is not necessary for the prosecution to prove an
intention to commit the offence. Defences may be available where adequate remediation has been
taken and;
• the action complained of was necessary to save or protect life, health, property or the
environment;
• the conduct of the defendant was reasonable in the circumstances;
• the action or event was due to an unforeseeable event beyond the defendant’s control.
If a prosecution for offences under the Act is successful, the maximum penalties are two years
imprisonment or a fine of $200,000, plus $10,000 a day for continuing offences. Principals are
liable for the acts of their agents, and there is no indemnity allowed for company directors.
Legislation
2008
Construction Contracts Act
Introduction
Page 12-603
Rawlinsons Media Limited have published two books on the Construction Contracts Act. These are:
“A guide to the Construction Contracts Act”
by Geoff Bayley and Tómas Kennedy-Grant. 2nd edition out December 2008.
“Managing Contractors Cashflow - making the Construction Contracts Act work for you”
by Peter Degerholm
• These books can be purchased by mailorder from Rawlinsons Media Limited, or from Techbooks,
378 Broadway, Newmarket, Auckland, ph 09-524-0132.
• See our website http://www.rawlinsons.co.nz to purchase online, or phone 0800-426-326.
• See also our advertisements on pages 0-7 and 0-8.
Legislation
2008
Weathertight Homes
WHRS Act 2002
Page 12-604
9 Weathertight Homes
9.1 WHRS Act 2002
The Weathertight Homes Resolution Services Act 2002 passed into law on 19 November 2002,
effective immediately. It was added to the Construction Contracts Bill as a supplementary order
paper, and passed under urgency. This Act was repealed by the WHRS Act 2006
9.2 Objectives of the 2002 Act
The purpose of this Act is to provide owners of dwellinghouses that are leaky buildings with access
to speedy, flexible, and cost-effective procedures for assessment and resolution of claims relating
to those buildings. In general terms, this Act provides for the following matters.
Assessment and evaluation of claims in relation to leaky buildings. Sections 7 to 12 provide a
mechanism for owners of dwellinghouses who consider that their dwellinghouse is a leaky building
to (i) submit their claim; and (ii) have it, and the nature of the particular problem, assessed and
evaluated; and (iii) be provided with an assessor's report.
Mediation of claims. Sections 13 to 21 make provision for access to a special mediation service
that is available to dwellinghouse owners with eligible claims. The claiming owner and any of the
other parties against whom the claim is made may agree to refer the claim to mediation, with
provision for binding settlements by agreement.
Compulsory adjudication of claims. Sections 22 to 55, and the Schedule, set up a mechanism
whereby dwellinghouse owners can have their eligible claims referred to adjudicators whose
powers and procedures are flexible and whose determinations, subject to appeal, are binding and
enforceable.
Miscellaneous provisions. Sections 56 to 64 set out various miscellaneous matters that underpin
the substantive provisions of this Act.
9.3 WHRS Act 2006
Changes to the WHRS were announced in July 2006, and passed into law on 18 December 2006,
with an effective date of 1 May 2007. This Act completely replaces the previous Act.
The measures, intended to benefit claimants and potential homebuyers, include:
• Requiring territorial authorities to place WHRS notices on affected property files, and to make
that information available on Land Information Memorandum (LIM) reports
• Changing the voting thresholds to make it easier for a class action approach to be taken by
owners of units within apartment blocks
• Setting statutory time limits on mediation
• Enhancing the power and authority of adjudicators, including new offence provisions for
failure to comply with a witness summons and intentionally disrupting proceedings
• Establishing a new specialist Weathertight Homes Tribunal administered by the Ministry of
Justice. Assessment and mediation remain with the Department of Building and Housing.
9.4 Weathertight Homes Resolution Services (Remedies) Amendment Act
This Act amends the Weathertight Homes Resolution Services Act 2006 to make clear the
remedies that may be claimed under that Act and ordered by the Weathertight Homes Tribunal in
determining a claim adjudicated by it under that Act.
Tax
2008
Revenue Recognition
Overview
Page 13-606
1 Revenue Recognition
1.1 Overview
The recognition of income and deductibility of expenditure on LTCC's—Long Term Construction
Contracts, i.e., those exceeding 12 months—has been an issue between Inland Revenue and
taxpayers for some time. There are currently no specific provisions on LTCC’s in the Income Tax
Act.
Generally, Inland Revenue will not accept a completed contracts method unless payment is only on
completion of the project.
The Valabh Committee was set up and considered inter alia this issue. It is interesting to note that
the Government agrees generally with the Committee's proposals on LTCC's but has decided that
retentions should not be excluded from the percentage of completion computation unless the
contractor has reasonable grounds for considering that such retentions will not be received.
Other proposals, such as thresholds below which no income should be recognised from the project,
are still under consideration.
1.2 Recommendations
The Committee's recommendations to Government include:
New Provision. A new provision be introduced dealing specifically with the costing and revenue
recognition on LTCC's.
Project Costs. The cost of a construction project include direct costs that can be specifically traced
to projects (such as direct materials and labour) and indirect costs that are related to the general
contract activity and can be objectively allocated to individual projects—such as insurance and
supervision costs.
The deductibility of project costs be governed by the capital or revenue classification of the project
and the timing of revenue recognition, and in particular:-
• the classification of projects between capital and revenue be in accordance with the
Committee's recommendations.
• the deductibility of the costs of capital projects only be through the depreciation tax
provisions; and
• the deductibility of revenue projects be based on the timing of revenue recognition.
Project Revenue. The revenue from a long-term construction project that is on revenue account
where there is a pre-determined sale, be determined in accordance with a percentage of
completion formulae, whereby the amount of project revenue that is recognised in an income year
is the total budgeted revenue to be received multiplied by the percentage completion of the project.
This is consistent with Financial Reporting Standard FRS-14.
• In revenue projects for which the percentage of completion basis is used, any actual costs
incurred in an income year be deductible as incurred;
• The revenue from all other long-term construction projects on revenue account be recognised
when the project is completed and a sale is made;
• In revenue projects for which revenue is recognised on sale, expenditure incurred be
deductible in the year in which the project revenue is recognised;
Tax
2008
Revenue Recognition
Summary
Page 13-607
Completion Calculations.
• The percentage of completion calculation would be based on the ratio that actual costs
incurred bears to total budgeted costs;
• In applying the percentage of completion method, revenue and expenditure not be
recognised until the project is 20% completed;
• In applying the percentage of completion method, retentions of project revenues by the
customer be excluded from revenues and be recognised only when receivable.
This recommendation as noted above has been rejected by the Government.
Miscellaneous. Where a project is undertaken via a special purpose company with a view to
disposal of the shares in the company, the profit on the shares is to be calculated on the same
basis as a percentage of completion method applying to the underlying project;
• A legislative definition of pre-determined sale should be introduced that focuses on the ability
of the contractor (or shareholder) to secure the project revenue. This would be subject to the
Commissioner's discretion to rule that there is no predetermined sale; and
• A two-way interest regime be introduced to calculate a compensating interest payment or
receipt by the taxpayer by a comparison with the pattern of income derivation based on actual
costs and revenues and the costs and revenues returned for tax purposes.
In addition to basing the percentage of completion formula on the ratio of actual costs to budgeted
costs, the Commissioner should be authorised to measure the percentage of completion by
reference to specialist reports based on site inspection.
When calculating income from year to year over a long term construction contract, there is no right
of deduction for any expenditure or loss which might arise for warranty expenditure until the
contractor actually paid the claim or became liable to do so: HW Coyle Ltd v CIR (1980) 4 NZTC
61,558; 4 TRNZ 1.
The Commissioner should be allowed to remit interest liabilities where the tax payer can show that
no additional tax would have been paid had returns of income been prepared on the basis of actual
cost and revenue flows.
A threshold percentage of completion should be able to be varied by the Commissioner in special
circumstances having regard to relevant facts—such as project size, variability of revenues and
costs and the like.
1.3 Summary
While the report has been around for several years, the Government has not yet given any clear
indication of when the new provisions on LTCC's will be enacted.
However, in the meantime, it is suggested that taxpayers in the construction industry should take
due note of the recommendations as the Commissioner would inevitably seek to apply the general
principles put forward to any given contract situation.
Also it is not known at this stage whether the rules to be enacted will apply to existing projects or
only those which commence on or after the date of enactment.
Tax
2008
Income Tax—Land Sales
Definition
Page 13-608
2008
Goods and Services Tax
How Does GST Work
Page 13-609
2008
Goods and Services Tax
Tax Invoices
Page 13-610
Hybrid Basis. Under this method output tax is accounted for on an invoice basis while input tax is
claimed on a payments basis. If a registered person has a six monthly accounting period, or is
accounting for GST on a payment basis, and ceases to satisfy the condition for adopting such
methods, then the registered person must inform Inland Revenue within 21 days.
3.5 Tax Invoices
Sales to another registered person require that a Tax Invoice be issued to enable the purchaser to
claim a credit for GST paid. These invoices must be retained by the purchasers for 10 years.
The issuing of Tax Invoices is subject to the following rules: For supplies in excess of $1,000, a Tax
Invoice must show:
• the words “Tax Invoice”
• the name and GST registration number of the supplier
• the name and address of the recipient
• the date when the Tax Invoice is issued
• a description of the supply
• quantity or volume of the supply
• either—the consideration of the supply excluding tax, the total tax charged, and the
consideration for the supply inclusive of tax
• or—the total consideration for the supply and a statement to the effect that this includes a
charge for GST.
Under this option the GST returned must be 1/9 of the total consideration. For supplies that do not
exceed $1,000, a less detailed invoice can be issued and must show:
• the words “Tax Invoice”
• the name and GST registration number of the supplier
• the date when the tax invoice is issued
• a description of the supply
• the consideration for the supply and a statement that GST is included.
For supplies that do not exceed $50, a Tax Invoice need not be issued and a Tax Invoice is not
required in order to recover GST charged. The following details will be required to support this
claim:
• the date of the supply
• a brief description of the supply
• the consideration for the supply
Tax
2008
Goods and Services Tax
GST Payments and Refunds
Page 13-611
2008
Goods and Services Tax
Credit and Debit Notes
Page 13-612
Using the “self billing” process, the time of supply will be when the amount of the claim is
determined. The advantage of the self billing method can be shown simply, in the following
example.
The subcontractor is now in the situation where he has a Tax Invoice showing $375.00 GST,
however, he has received only $337.50, with the balance due at some future date.
The subcontractor, assuming he accounts for GST on an invoice basis, must either pay $375 to
Inland Revenue or must issue a credit note. Under the self billing process this problem does not
arise.
The main contractor prepares the invoice as follows:
Subcontract work to date $12,000.00
Less previous claim—excluding GST $9,000.00
This progress claim $3,000.00
Less retention—say 10% $300.00
$2,700.00
Plus 12.5% GST $337.50
Total due this claim $3,037.50
The GST to be returned by the subcontractor is $337.50 and there is no need for a credit note.
When the retention is due to be paid, the main contractor will issue a further Tax Invoice, detailing
the GST. Again the time of supply for a retention is the earlier of the following:
• when the claim is sent
• payment is due
• payment is received
3.8 Credit and Debit Notes
If a credit or debit note is required it must show:
• the name, address and registration number of the supplier
• the name and address of the recipient
• the date on which the credit note was issued
• a brief explanation of the reason for the credit being given.
• EITHER—the original consideration, the correction consideration, the difference between
those two amounts and the tax on the difference. OR—where the tax charged is the tax
fraction of the consideration, the difference referred to above and a statement that the
difference includes GST.
Tax
2008
Goods and Services Tax
Increased Costs and Variations
Page 13-613
2008
Goods and Services Tax
Fringe Benefits—GST Implications
Page 13-614
2008
Goods and Services Tax
Private Use/Change of Use
Page 13-615
2008
Annual Warrants of Fitness
Tax Aspects of Compliance
Page 13-616
2008
Other Taxes
Expenditure on Improvements
Page 13-617
5 Other Taxes
5.1 PAYE Tax
Pay As You Earn (PAYE) tax was introduced in 1957 and provides a system in terms of which
those making certain types of payments must deduct tax from those payments. Salary and wages
are the common examples of payments which must have PAYE deducted.
Deductions must also be made from payments which are declared to be withholding payments.
Various rates apply depending on the type of payment being made. For labour only carpenters,
plumbers etc, and others engaged by the building industry, the rate is set at 20%.
5.2 Fringe Benefit Tax
FBT is payable by employers on specified benefits (e.g. motor vehicles and low interest loans)
provided to employees (including major shareholders), and payable quarterly for periods ending 30
June, 30 September, 31 December and 31 March.
The rate is 49% of the taxable value of each benefit provided. However, effective from the quarter
commencing 1 April 2000, the FBT rate increased to 64% for employees earning salary and wages
exceeding $60,000.
There is a ‘de minimis’ exemption for “unclassified benefits” of $75 per employee in the quarter or
limited to $450 to all employees in the quarter. ‘de minimis’ means small or trifling.
Significant changes to the FBT rules relating to motor vehicles were introduced effective 1 April
2006. For example, annual FBT on a vehicle costing $26,000 would be $2,548, or $3,328 where
the 64% FBT rate applies. For GST implications and a fuller example, Refer to page 13-614.
• $26,000 x 20% = $5,200 x 49% = $2,548, or $5,200 x 64% = $3,328
5.3 Accident Compensation
There are varying levies payable by employers, employees and self-employed people. Employers
pay levies and residual claim levies, depending on industry type. Rates and thresholds are issued
by Regulation.
For more information, Refer to page 7-511. ACC Business Helpline, 0800-222-766.
Tax
2008
Other Taxes
Resident Withholding Tax (RWT)
Page 13-618
* assumes total income is less than or equal to $60,000, otherwise rate of 39% applies.
5.7 Capital Gains Tax
There is presently no formal capital gains tax regime in New Zealand, but See “Definition” on
page 13-608.
5.8 Late Payment Penalties/Interest
Tax which is paid late is subject to a late payment penalty of 5%. A further penalty of 2% per month
will be charged on the outstanding amount. Use of money interest is also payable on outstanding
amounts.
Tax
2008
Tax Depreciation—Buildings
Tax Rules
Page 13-619
6 Tax Depreciation—Buildings
6.1 Tax Rules
The tax depreciation rules are contained in Section EE of the Income Tax Act 2004.
For depreciation purposes, a building comprises the outer walls including linings, outer doors, shop
fronts and windows, interior bearer walls, inner fixtures of brick and concrete, foundations, roof
ceilings, floors, cellar, chimneys, sewerage disposal systems, stairways, plumbing, water and
power supplies.
Special tax depreciation rules applying to buildings.
• Buildings cannot be pooled.
• Depreciation on buildings can be claimed in the year of sale.
• A loss on disposal of a building cannot be claimed as a deduction.
• Buildings do not qualify for increased rates, which are either the historic rate plus 25% of that
rate or the economic rate plus 20% of that rate. New assets purchased after the start of the
1995/1996 year may qualify for the 20% loading, e.g., moveable furniture but not fixed fittings.
• A special deduction for assets which are no longer used is not available for buildings.
• When a personal or non-business asset is introduced into a business, generally the market
value at the time is used to calculate depreciation. This rule does not apply to buildings.
• Depreciation on buildings acquired before the 1993-1994 income year is calculated using the
straight line (SL) method. From the 1993-1994 income year onwards you can decide each
year whether to use the straight line or diminishing value (DV) method.
• Depreciation on buildings is calculated on either the original cost or the adjusted tax value,
depending on which depreciation method you use.
• The first time you use the diminishing value method, calculate the adjusted tax value of the
building. Depreciation on the building is calculated on this amount. To work out the adjusted
tax value, deduct the amount of depreciation which has been claimed since purchase from
the original cost (excluding land).
• For rates for buildings and plant (including building fit-out, contractors and builders
equipment) acquired before 1 April 1993, Refer to page 13-621.
• For those acquired after 31 March 1993, Refer to page 13-640.
• A tax payer may elect not to depreciate property. This may be useful to avoid depreciation
recovery on residential lettings.
• Note the IRD’s revised views on residential rental chattels. Refer to page 13-641
• The low value asset threshold which allows taxpayers to write off assets immediately is $500.
Land and Buildings. Depreciation cannot be claimed on land. When land and building are
purchased and the price does not specify the cost of the building, the Government Valuation (at the
time of purchase) may be used to calculate the cost of the buildings:
Value of improvements (buildings) x purchase price
Capital value (land & buildings)
Sale of Buildings. When a building is sold for more than its adjusted tax value, the depreciation
recovered is assessable income. The amount of depreciation recovered is the smaller of: the
original cost price of the building, minus the adjusted tax value; or the sale price, minus the
adjusted tax value.
This ensures that any capital profit made on the sale of a building is not included as assessable
income. Losses made on the sale or disposal of buildings are not deductible.
Tax
2008
Tax Depreciation—Buildings
Depreciation Rates from 1 April 2005
Page 13-620
Depreciable Land Improvements. Depreciable Land Improvements and payments for the right to
use land, e.g. leasehold interest, are depreciable property. (17th Schedule of The Tax Act)
Depreciable Land Improvements include: Airport runways; Reservoirs; Bores and wells; Retaining
walls; Bridges; Roads; Dams; Chimneys; Spillways; Culverts; Swimming pools; Tanks; Fences;
Tunnels; Hardstanding; Wharves.
6.2 Depreciation Rates from 1 April 2005
New depreciation rules came into effect in 2005. Assets (other than buildings) acquired on or after
1 April 2005 and buildings acquired on or after 19 May 2005 can be depreciated at the new rates.
The current depreciation rate tables only apply to assets acquired before 1 April 2005 and buildings
acquired before 19 May 2005. These are now called the "old rates" (not to be confused with the
really old rates, pre–1993).
However, the new rates applicable to construction and property are contained in the tables on the
following pages. See “Tax Depreciation Schedules” on page 13-621.
For other rates not included in our tables, see the Depreciation Rate Finder table below. Look up
the “old rate” for the item in question, in the existing IRD tables, then consult the Rate Finder below
to find the corresponding %. Look across to the “New Rates” columns for the updated rate. Also,
See “Further Depreciation Rates from IRD” on page 13-641.
2008
Tax Depreciation—Buildings
Tax Depreciation Schedules
Page 13-621
2008
Tax Depreciation—Buildings
Buildings Acquired Prior to 1 April 1993
Page 13-622
2008
Tax Depreciation—Buildings
Buildings Acquired Prior to 1 April 1993
Page 13-623
2008
Tax Depreciation—Buildings
Buildings Acquired Prior to 1 April 1993
Page 13-624
2008
Tax Depreciation—Buildings
Buildings Acquired Prior to 1 April 1993
Page 13-625
2008
Tax Depreciation—Buildings
Buildings and Structures—“Old Rates” and “New Rates”
Page 13-626
2008
Tax Depreciation—Buildings
Building Fit-Out (when in books separately from building
cost)
Page 13-627
Buildings and Structures—“Old Rates” and “New Rates”.
Use the “Old Rates” column for assets acquired before 1 Life Asset Acquired from
April 2005 and buildings acquired before 19 May 2005. (Yrs) 1 April 1993 2005
“Old Rates” “New Rates”
Use the “New Rates” column for assets (other than DV SL DV SL
buildings) acquired on or after 1 April 2005, and buildings
acquired on or after 19 May 2005. % 20% % 20% % 20% % 20%
Reservoirs for water, other than concrete or lined 33.3 6 7.2 4 4.8 6 7.2 4 4.8
earth
Reservoirs, in-ground, concrete 100 2 2.4 1.5 1.8 2 2.4 1.5 1.8
Retaining walls, concrete 100 2 2.4 1.5 1.8 2 2.4 1.5 1.8
Retaining walls, wooden 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Roadways 50 4 4.8 3 3.6 4 4.8 3 3.6
Runways, for airports 33.3 6 7.2 4 4.8 6 7.2 4 4.8
Saleyards 33.3 6 7.2 4 4.8 6 7.2 4 4.8
Shade houses of glass or other construction 20 9.5 6.5 8.5 5
excluding PVC
Shade houses of PVC or similar construction 12.5 15 10 13.5 8
Signs, road 6.66 26 31.2 18 21.6 30 36 21 25.2
Signs, street nameplates 6.66 26 31.2 18 21.6 30 36 21 25.2
Stopbanks of earth construction 50 4 4.8 3 3.6 4 4.8 3 3.6
Swimming pools, in-ground 33.3 6 7.2 4 4.8 6 7.2 4 4.8
Tanneries 33.3 6 4 4.5 3.5
Taxiways airports 50 4 4.8 3 3.6 4 4.8 3 3.6
Towers for floodlights 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Tunnels, of block construction 100 2 2.4 1.5 1.8 2 2.4 1.5 1.8
Tunnels, of brick construction 100 2 2.4 1.5 1.8 2 2.4 1.5 1.8
Tunnels, of concrete construction 100 2 2.4 1.5 1.8 2 2.4 1.5 1.8
Valve chambers and the like 50 4 4.8 3 3.6 4 4.8 3 3.6
Wharf tarmac 50 4 4.8 3 3.6 4 4.8 3 3.6
Wharves, of block construction 100 2 2.4 1.5 1.8 2 2.4 1.5 1.8
Wharves, of brick construction 100 2 2.4 1.5 1.8 2 2.4 1.5 1.8
Wharves, of concrete construction 100 2 2.4 1.5 1.8 2 2.4 1.5 1.8
Wharves, of stone construction 100 2 2.4 1.5 1.8 2 2.4 1.5 1.8
Wharves, other than of block, brick, concrete and 50 4 4.8 3 3.6 4 4.8 3 3.6
stone
2008
Tax Depreciation—Buildings
Building Fit-Out (when in books separately from building
cost)
Page 13-628
Building Fit-Out (when in books separately from building cost).
Use the “Old Rates” column for assets acquired before 1 Life Asset Acquired from
April 2005. (Yrs) 1 April 1993 1 April 2005
“Old Rates” “New Rates”
Use the “New Rates” column for assets (other than
buildings) acquired on or after 1 April 2005. DV SL DV SL
(Note: 20% loading may apply) % 20% % 20% % 20% % 20%
Appliances, domestic type 8 22 26.4 15.5 18.6 25 30 17.5 21
Awnings 10 18 21.6 12.5 15 20 24 13.5 16.2
Blinds 8 22 26.4 15.5 18.6 25 30 17.5 21
Building fit-out 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Canopies 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Carpets—modular nylon tile construction 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Carpets—other 5 33 39.6 24 28.8 40 48 30 36
Ceilings, suspended 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Cleaners cradles 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Clotheslines 8 22 26.4 15.5 18.6 25 30 17.5 21
Cranes, overhead travelling 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Curtains 8 22 26.4 15.5 18.6 25 30 17.5 21
Delivery systems, for messages, other than tube 12.5 15 18 10 12 16 19.2 10.5 12.6
Delivery systems, for messages, tube type 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Delivery systems, for packages, other than tube 12.5 15 18 10 12 16 19.2 10.5 12.6
Delivery systems, for packages, tube type 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Dock levellers 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Door closers 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Doors, for strongrooms 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Doors, roller and the like 12.5 15 18 10 12 16 19.2 10.5 12.6
Drapes 8 22 26.4 15.5 18.6 25 30 17.5 21
Dry risers 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Electrical reticulation 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Escalators 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Fences 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Flagpoles 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Flooring, parquet 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Floors, for computer rooms 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Fume extraction systems, ducted 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Fume extraction systems, roof mounted 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Furniture, fitted 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Gas dowsing systems 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Generators, stand-by 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Grills, roller and the like 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Hand driers, air type 3 50 60 40 48 67 80.4 67 80.4
Hand soap dispensers 2 63.5 76.2 63.5 76.2 100 100 100 100
Handrails 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Heat detectors 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Heaters, electric 3 50 60 40 48 67 80.4 67 80.4
Heating systems 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Hose reels, fire 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Incinerators 8 22 26.4 15.5 18.6 25 30 17.5 21
Incinerators, rubbish 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Tax
2008
Tax Depreciation—Buildings
Building Fit-Out (when in books separately from building
cost)
Page 13-629
Building Fit-Out (when in books separately from building cost).
Use the “Old Rates” column for assets acquired before 1 Life Asset Acquired from
April 2005. (Yrs) 1 April 1993 1 April 2005
“Old Rates” “New Rates”
Use the “New Rates” column for assets (other than
buildings) acquired on or after 1 April 2005. DV SL DV SL
(Note: 20% loading may apply) % 20% % 20% % 20% % 20%
Lifts 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Light fittings 10 18 21.6 12.5 15 20 24 13.5 16.2
Lighting controllers, emergency 12.5 15 18 10 12 16 19.2 10.5 12.6
Mailboxes 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Maintenance units, for buildings 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Metal speed bumps 5 33 39.6 24 28.8 40 48 30 36
Meters, gas 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Meters, water 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Monitoring systems 10 18 21.6 12.5 15 20 24 13.5 16.2
Motors, roller doors 10 18 21.6 12.5 15 20 24 13.5 16.2
Paper towel dispensers 2 63.5 76.2 63.5 76.2 100 100 100 100
Partitions, demountable 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Partitions, non-load bearing 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Plumbing 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Plumbing fixtures 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Pumps, heat 10 18 21.6 12.5 15 20 24 13.5 16.2
Railings 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Runway beams 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Sanitary appliances 8 22 26.4 15.5 18.6 25 30 17.5 21
Saunas 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Security systems 10 18 21.6 12.5 15 20 24 13.5 16.2
Signs, electric 10 18 21.6 12.5 15 20 24 13.5 16.2
Signs, other than electric 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Smoke detectors 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Spa pools 12.5 15 18 10 12 16 19.2 10.5 12.6
Sprinkler systems 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Strong boxes 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Toilet roll dispensers 2 63.5 76.2 63.5 76.2 100 100 100 100
Towel cabinets 3 50 60 40 48 67 80.4 67 80.4
Ventilating fans 10 18 21.6 12.5 15 20 24 13.5 16.2
Ventilating fans, ducted 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Ventilating fans, roof mounted 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Vinyl flooring 10 18 21.6 12.5 15 20 24 13.5 16.2
Walkways 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Walkways, moving 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Water heaters, not over-sink type 12.5 15 18 10 12 16 19.2 10.5 12.6
Water heaters, over-sink 10 18 21.6 12.5 15 20 24 13.5 16.2
Water savers 3 50 60 40 48 67 80.4 67 80.4
Watering systems 3 50 60 40 48 67 80.4 67 80.4
Tax
2008
Tax Depreciation—Buildings
Contractors, Builders and Quarrying
Page 13-630
2008
Tax Depreciation—Buildings
Office Equipment and Furniture
Page 13-631
2008
Tax Depreciation—Buildings
Office Equipment and Furniture
Page 13-632
2008
Tax Depreciation—Buildings
Tanks, Vats and Reservoirs (where not industry speci-
fied)
Page 13-633
Office Equipment and Furniture.
Use the “Old Rates” column for assets acquired before 1 Life Asset Acquired from
April 2005. (Yrs) 1 April 1993 1 April 2005
“Old Rates” “New Rates”
Use the “New Rates” column for assets (other than
buildings) acquired on or after 1 April 2005. DV SL DV SL
Note: 20% loading may apply % 20% % 20% % 20% % 20%
Stationery expense expense
Tables 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Telephone systems 6.66 26 31.2 18 21.6 30 36 21 25.2
Telephones (mobile) 3 50 60 40 48 67 80.4 67 80.4
Telephones (portable) 3 50 60 40 48 67 80.4 67 80.4
Time recorders 10 18 21.6 12.5 15 20 24 13.5 16.2
Transcribing machines 3 50 60 40 48 67 80.4 67 80.4
Typewriters 5 33 39.6 24 28.8 40 48 30 36
Water coolers 8 22 26.4 15.5 18.6 25 30 17.5 21
Whiteboards (electronic) 5 33 39.6 24 28.8 40 48 30 36
Word processors 5 33 39.6 24 28.8 40 48 30 36
2008
Tax Depreciation—Buildings
Computers
Page 13-634
Computers.
Use the “Old Rates” column for assets acquired before 1 Life Asset Acquired from
April 2005. (Yrs) 1 April 1993 1 April 2005
“Old Rates” “New Rates”
Use the “New Rates” column for assets (other than
buildings) acquired on or after 1 April 2005. DV SL DV SL
Note: 20% loading may apply % 20% % 20% % 20% % 20%
Computer equipment (default class) 4 40 48 30 36 50 60 40 48
Backup units (tape type) 4 40 48 30 36 50 60 40 48
Banknote dispensers 6.66 26 31.2 18 21.6 30 36 21 25.2
Bridges 4 40 48 30 36 50 60 40 48
Cabling 6.66 26 31.2 18 21.6 30 36 21 25.2
CAD/CAM equipment 4 40 48 30 36 50 60 40 48
Communications controllers 4 40 48 30 36 50 60 40 48
Computer and associated equipment (for 5 33 39.6 24 28.8 40 48 30 36
typesetting)
Control equipment (process, computer, if separately 8 22 26.4 15.5 18.6 25 30 17.5 21
identified)
Data concentrators 4 40 48 30 36 50 60 40 48
Digitisers 4 40 48 30 36 50 60 40 48
Disk drives (for use with mini computers) 4 40 48 30 36 50 60 40 48
Disk drives (for use with personal computers) 4 40 48 30 36 50 60 40 48
Disks expense expense
EFTPOS terminals 4 40 48 30 36 50 60 40 48
Floors (for computer rooms) 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Gas dowsing systems 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Laptop computers 4 40 48 30 36 50 60 40 48
Mainframe computers 6.66 26 31.2 18 21.6 30 36 21 25.2
Mini computers 4 40 48 30 36 50 60 40 48
Modems 4 40 48 30 36 50 60 40 48
Multiplexers 4 40 48 30 36 50 60 40 48
Network servers 4 40 48 30 36 50 60 40 48
Notebook computers 4 40 48 30 36 50 60 40 48
Personal computers 4 40 48 30 36 50 60 40 48
Plotters 5 33 39.6 24 28.8 40 48 30 36
Power conditioners 6.66 26 31.2 18 21.6 30 36 21 25.2
Power supplies (uninterruptable) 6.66 26 31.2 18 21.6 30 36 21 25.2
Printers 5 33 39.6 24 28.8 40 48 30 36
Routers 4 40 48 30 36 50 60 40 48
Scanners 4 40 48 30 36 50 60 40 48
Tapes expense expense
Terminals (without capability of local storage 6.66 26 31.2 18 21.6 30 36 21 25.2
capacity)
Voice mail equipment 4 40 48 30 36 50 60 40 48
Tax
2008
Tax Depreciation—Buildings
Shops
Page 13-635
Shops.
Use the “Old Rates” column for assets acquired before 1 Life Asset Acquired from
April 2005. (Yrs) 1 April 1993 1 April 2005
“Old Rates” “New Rates”
Use the “New Rates” column for assets (other than
buildings) acquired on or after 1 April 2005. DV SL DV SL
Note: 20% loading may apply % 20% % 20% % 20% % 20%
Shop plant and equipment (default class) 12.5 15 18 10 12 16 19.2 10.5 12.6
Appliances (domestic) 6.66 26 31.2 18 21.6 30 36 21 25.2
Bandsaws (for meat) 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Barbers chairs 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Barriers 10 18 21.6 12.5 15 20 24 13.5 16.2
Baskets (for shopping) 5 33 39.6 24 28.8 40 48 30 36
Benches (fitted) 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Benches (loose) 10 18 21.6 12.5 15 20 24 13.5 16.2
Blenders 6.66 26 31.2 18 21.6 30 36 21 25.2
Bowl choppers 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Brakes (for pastry) 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Carpets (modular nylon tile construction) 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Carpets (other than modular nylon tile construction) 5 33 39.6 24 28.8 40 48 30 36
Cash registers 5 33 39.6 24 28.8 40 48 30 36
Check-out systems 5 33 39.6 24 28.8 40 48 30 36
Cobblers, equipment 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Coffee grinders 8 22 26.4 15.5 18.6 25 30 17.5 21
Coffee makers 6.66 26 31.2 18 21.6 30 36 21 25.2
Comparators (consumer electronic comparative 3 50 60 40 48 67 80.4 67 80.4
display units)
Compressors 12.5 15 18 10 12 16 19.2 10.5 12.6
Cookers 12.5 15 18 10 12 16 19.2 10.5 12.6
Coolrooms 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Counters (for check-out, loose) 10 18 21.6 12.5 15 20 24 13.5 16.2
Croissant makers 12.5 15 18 10 12 16 19.2 10.5 12.6
Dishwashers 10 18 21.6 12.5 15 20 24 13.5 16.2
Display cabinets 12.5 15 18 10 12 16 19.2 10.5 12.6
Doors (roller) 12.5 15 18 10 12 16 19.2 10.5 12.6
Drinks dispensers 12.5 15 18 10 12 16 19.2 10.5 12.6
Electronic article surveillance systems 5 33 39.6 24 28.8 40 48 30 36
Evaporators 12.5 15 18 10 12 16 19.2 10.5 12.6
Fillers (for sausages) 12.5 15 18 10 12 16 19.2 10.5 12.6
Fittings (in shop, loose) 10 18 21.6 12.5 15 20 24 13.5 16.2
Food processors 6.66 26 31.2 18 21.6 30 36 21 25.2
Formers (for sausages) 12.5 15 18 10 12 16 19.2 10.5 12.6
Freezer cabinets 12.5 15 18 10 12 16 19.2 10.5 12.6
Fume hoods (other than stainless steel) 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Fume hoods (stainless steel, fitted) 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Furniture (fitted) 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Furniture (loose) 10 18 21.6 12.5 15 20 24 13.5 16.2
Grills (roller) 12.5 15 18 10 12 16 19.2 10.5 12.6
Tax
2008
Tax Depreciation—Buildings
Shops
Page 13-636
Shops.
Use the “Old Rates” column for assets acquired before 1 Life Asset Acquired from
April 2005. (Yrs) 1 April 1993 1 April 2005
“Old Rates” “New Rates”
Use the “New Rates” column for assets (other than
buildings) acquired on or after 1 April 2005. DV SL DV SL
Note: 20% loading may apply % 20% % 20% % 20% % 20%
Hairdressers’ equipment 5 33 39.6 24 28.8 40 48 30 36
Ice-cream dispensers 12.5 15 18 10 12 16 19.2 10.5 12.6
Ice making machines 12.5 15 18 10 12 16 19.2 10.5 12.6
Insect exterminators 6.66 26 31.2 18 21.6 30 36 21 25.2
Jewellers’ manufacturing equipment 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Key cutting machines 5 33 39.6 24 28.8 40 48 30 36
Kitchen appliances (miscellaneous) 6.66 26 31.2 18 21.6 30 36 21 25.2
Mannequins 8 22 26.4 15.5 18.6 25 30 17.5 21
Milkshake mixers 8 22 26.4 15.5 18.6 25 30 17.5 21
Mincers 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Mixers 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Moulders (French stick) 12.5 15 18 10 12 16 19.2 10.5 12.6
Music systems (in-house) 10 18 21.6 12.5 15 20 24 13.5 16.2
Ovens 12.5 15 18 10 12 16 19.2 10.5 12.6
PA systems 10 18 21.6 12.5 15 20 24 13.5 16.2
Packing machines (shrink wrap) 8 22 26.4 15.5 18.6 25 30 17.5 21
Packing machines (vacuum) 10 18 21.6 12.5 15 20 24 13.5 16.2
Paintings and drawings, in either case being 20 9.5 11.4 6.5 7.8 10 12 7 8.4
property the value of which might reasonably be
expected in normal circumstances to decline in value
Paint shakers 10 18 21.6 12.5 15 20 24 13.5 16.2
Peelers (for vegetables) 12.5 15 18 10 12 16 19.2 10.5 12.6
Prints (including limited edition prints) 10 18 21.6 12.5 15 20 24 13.5 16.2
Racks (loose) 10 18 21.6 12.5 15 20 24 13.5 16.2
Rails (for carcass) 25 7.5 9 5.5 6.6 8 9.6 6 7.2
Ranges 12.5 15 18 10 12 16 19.2 10.5 12.6
Readers (bar code) 5 33 39.6 24 28.8 40 48 30 36
Refrigerated cabinets 12.5 15 18 10 12 16 19.2 10.5 12.6
Rotisseries 12.5 15 18 10 12 16 19.2 10.5 12.6
Scales 8 22 26.4 15.5 18.6 25 30 17.5 21
Scanners (bar code) 5 33 39.6 24 28.8 40 48 30 36
Shelving (loose) 10 18 21.6 12.5 15 20 24 13.5 16.2
Signs (electric) 10 18 21.6 12.5 15 20 24 13.5 16.2
Signs (other than electric) 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Signs (portable, electric) 5 33 39.6 24 28.8 40 48 30 36
Sinks (fitted) 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Slicers 12.5 15 18 10 12 16 19.2 10.5 12.6
Tags (security) 3 50 60 40 48 67 80.4 67 80.4
Tailors’ dummies 8 22 26.4 15.5 18.6 25 30 17.5 21
Tenderisers 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Tax
2008
Tax Depreciation—Buildings
Laundry
Page 13-637
Shops.
Use the “Old Rates” column for assets acquired before 1 Life Asset Acquired from
April 2005. (Yrs) 1 April 1993 1 April 2005
“Old Rates” “New Rates”
Use the “New Rates” column for assets (other than
buildings) acquired on or after 1 April 2005. DV SL DV SL
Note: 20% loading may apply % 20% % 20% % 20% % 20%
Trolleys (in supermarkets) 5 33 39.6 24 28.8 40 48 30 36
Utensils (including pots and pans) 3 50 60 40 48 67 80.4 67 80.4
Utensils (kitchen) up to 1997 5 33 39.6 24 28.8 40 48 30 36
Vinyl flooring 10 18 21.6 12.5 15 20 24 13.5 16.2
Warming cabinets 12.5 15 18 10 12 16 19.2 10.5 12.6
Waste disposal units 10 18 21.6 12.5 15 20 24 13.5 16.2
Wrap sealers 8 22 26.4 15.5 18.6 25 30 17.5 21
Laundry.
Use the “Old Rates” column for assets acquired before 1 Life Asset Acquired from
April 2005. (Yrs) 1 April 1993 1 April 2005
“Old Rates” “New Rates”
Use the “New Rates” column for assets (other than
buildings) acquired on or after 1 April 2005. DV SL DV SL
Note: 20% loading may apply % 20% % 20% % 20% % 20%
Laundry plant and equipment (default class) 8 22 26.4 15.5 18.6 25 30 17.5 21
Clothes markers 8 22 26.4 15.5 18.6 25 30 17.5 21
Continuous towels 6.66 26 31.2 18 21.6 30 36 21 25.2
Detergent dispensers 3 50 60 40 48 67 80.4 67 80.4
Dry-cleaning plant 8 22 26.4 15.5 18.6 25 30 17.5 21
Dryers 8 22 26.4 15.5 18.6 25 30 17.5 21
Floor mats 3 50 60 40 48 67 80.4 67 80.4
Folding machines (commercial type) 12.5 15 18 10 12 16 19.2 10.5 12.6
Folding machines (domestic type) 3 50 60 40 48 67 80.4 67 80.4
Hand driers (air type) 3 50 60 40 48 67 80.4 67 80.4
Hydro extractors 12.5 15 18 10 12 16 19.2 10.5 12.6
Ironing boards (domestic type) 3 50 60 40 48 67 80.4 67 80.4
Ironing machines (commercial type) 12.5 15 18 10 12 16 19.2 10.5 12.6
Ironing machines (domestic type) 3 50 60 40 48 67 80.4 67 80.4
Irons (commercial type) 8 22 26.4 15.5 18.6 25 30 17.5 21
Irons (domestic type) 3 50 60 40 48 67 80.4 67 80.4
Linen (for hire) 3 50 60 40 48 67 80.4 67 80.4
Pressing machines (commercial type) 12.5 15 18 10 12 16 19.2 10.5 12.6
Pressing machines (domestic type) 3 50 60 40 48 67 80.4 67 80.4
Spotting tables 12.5 15 18 10 12 16 19.2 10.5 12.6
Towel cabinets (continuous) 6.66 26 31.2 18 21.6 30 36 21 25.2
Washing machines 8 22 26.4 15.5 18.6 25 30 17.5 21
Tax
2008
Tax Depreciation—Buildings
Hotels, Motels, Restaurants, Cafes, Taverns, Takeaway
Bars
Page 13-638
Hotels, Motels, Restaurants, Cafes, Taverns, Takeaway Bars.
Use the “Old Rates” column for assets acquired before 1 Life Asset Acquired from
April 2005. (Yrs) 1 April 1993 1 April 2005
“Old Rates” “New Rates”
Use the “New Rates” column for assets (other than
buildings) acquired on or after 1 April 2005. DV SL DV SL
Note: 20% loading may apply % 20% % 20% % 20% % 20%
Hotel, motel, restaurant, cafe, tavern and takeaway 12.5 15 18 10 12 16 19.2 10.5 12.6
bar equipment and machinery (default class)
Appliances (domestic type) 6.66 26 31.2 18 21.6 30 36 21 25.2
Bains-marie 12.5 15 18 10 12 16 19.2 10.5 12.6
Bedding 3 50 60 40 48 67 80.4 67 80.4
Beds 10 18 21.6 12.5 15 20 24 13.5 16.2
Beer systems 12.5 15 18 10 12 16 19.2 10.5 12.6
Beer tanks 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Benches 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Blankets 5 33 39.6 24 28.8 40 48 30 36
Blenders 6.66 26 31.2 18 21.6 30 36 21 25.2
Blinds 8 22 26.4 15.5 18.6 25 30 17.5 21
Boiling pans 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Carpets (modular nylon tile construction) 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Carpets (other than modular nylon tile construction) 5 33 39.6 24 28.8 40 48 30 36
Cash register systems 5 33 39.6 24 28.8 40 48 30 36
Cash registers 5 33 39.6 24 28.8 40 48 30 36
Chairs 10 18 21.6 12.5 15 20 24 13.5 16.2
Coffee makers 6.66 26 31.2 18 21.6 30 36 21 25.2
Compact disc players 5 33 39.6 24 28.8 40 48 30 36
Compact discs 1 100 100 100 100 100 100 100 100
Compressors 12.5 15 18 10 12 16 19.2 10.5 12.6
Cookers 12.5 15 18 10 12 16 19.2 10.5 12.6
Coolrooms 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Crockery 3 50 60 40 48 67 80.4 67 80.4
Curtains 8 22 26.4 15.5 18.6 25 30 17.5 21
Cutlery 3 50 60 40 48 67 80.4 67 80.4
Dance floor 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Decorative articles 10 18 21.6 12.5 15 20 24 13.5 16.2
Digital versatile disc players (DVD players) 5 33 39.6 24 28.8 40 48 30 36
Digital versatile discs (DVDs) 2 63.5 76.2 63.5 76.2 100 100 100 100
Dishwashers 10 18 21.6 12.5 15 20 24 13.5 16.2
Display cabinets 12.5 15 18 10 12 16 19.2 10.5 12.6
Drapes 8 22 26.4 15.5 18.6 25 30 17.5 21
Drinks dispensers 12.5 15 18 10 12 16 19.2 10.5 12.6
Electric blankets 3 50 60 40 48 67 80.4 67 80.4
Evaporators 12.5 15 18 10 12 16 19.2 10.5 12.6
Flagon fillers 8 22 26.4 15.5 18.6 25 30 17.5 21
Food processors 6.66 26 31.2 18 21.6 30 36 21 25.2
Freezer cabinets 12.5 15 18 10 12 16 19.2 10.5 12.6
Fryers 12.5 15 18 10 12 16 19.2 10.5 12.6
Tax
2008
Tax Depreciation—Buildings
Hotels, Motels, Restaurants, Cafes, Taverns, Takeaway
Bars
Page 13-639
Hotels, Motels, Restaurants, Cafes, Taverns, Takeaway Bars.
Use the “Old Rates” column for assets acquired before 1 Life Asset Acquired from
April 2005. (Yrs) 1 April 1993 1 April 2005
“Old Rates” “New Rates”
Use the “New Rates” column for assets (other than
buildings) acquired on or after 1 April 2005. DV SL DV SL
Note: 20% loading may apply % 20% % 20% % 20% % 20%
Fume hoods (other than stainless steel) 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Fume hoods (stainless steel) 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Furniture (fitted) 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Furniture (loose) 10 18 21.6 12.5 15 20 24 13.5 16.2
Gas cylinders–LPG, including propane and butane 8 22 26.4 15.5 18.6 25 30 17.5 21
(these rates apply to cylinders acquired on or after 1
Oct 1996)
Gas cylinders–others (these rates apply to cylinders 12.5 15 18 10 12 16 19.2 10.5 12.6
acquired on or after 1 Oct 1996)
Gas cylinders (acquired before 1 Oct 1996) 5 33 39.6 24 28.8 40 48 30 36
Glassware 3 50 60 40 48 67 80.4 67 80.4
Glass washers 8 22 26.4 15.5 18.6 25 30 17.5 21
Griddles 12.5 15 18 10 12 16 19.2 10.5 12.6
Hand driers (air type) 3 50 60 40 48 67 80.4 67 80.4
Ice-cream dispensers 12.5 15 18 10 12 16 19.2 10.5 12.6
Ice making machines 12.5 15 18 10 12 16 19.2 10.5 12.6
Insect exterminators 6.66 26 31.2 18 21.6 30 36 21 25.2
Keg fittings 12.5 15 18 10 12 16 19.2 10.5 12.6
Kitchen appliances (miscellaneous) 6.66 26 31.2 18 21.6 30 36 21 25.2
Linen 3 50 60 40 48 67 80.4 67 80.4
Lowerators 12.5 15 18 10 12 16 19.2 10.5 12.6
Milkshake mixers 8 22 26.4 15.5 18.6 25 30 17.5 21
Mixers 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Nip pourers 3 50 60 40 48 67 80.4 67 80.4
Ornaments 10 18 21.6 12.5 15 20 24 13.5 16.2
Paintings and drawings, in either case being 20 9.5 11.4 6.5 7.8 10 12 7 8.4
property the value of which might reasonably be
expected in normal circumstances to decline in value
Peelers (vegetables) 12.5 15 18 10 12 16 19.2 10.5 12.6
Pillows 3 50 60 40 48 67 80.4 67 80.4
Prints (including limited edition prints) 10 18 21.6 12.5 15 20 24 13.5 16.2
Ranges 12.5 15 18 10 12 16 19.2 10.5 12.6
Refrigerated cabinets 12.5 15 18 10 12 16 19.2 10.5 12.6
Rotisseries 12.5 15 18 10 12 16 19.2 10.5 12.6
Sandwich makers 8 22 26.4 15.5 18.6 25 30 17.5 21
Satellite dishes 12.5 15 18 10 12 16 19.2 10.5 12.6
Saunas 15.5 12 14.4 8 9.6 13 15.6 8.5 10.2
Sinks 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Slicers 12.5 15 18 10 12 16 19.2 10.5 12.6
Spa pools 12.5 15 18 10 12 16 19.2 10.5 12.6
Stage 20 9.5 11.4 6.5 7.8 10 12 7 8.4
Tax
2008
Tax Depreciation—Buildings
Residential Rental Property Chattels
Page 13-640
2008
Tax Depreciation—Buildings
IRD Stand: Residential Rental Chattels
Page 13-641
2008
Glossary of Terms
Page 14-643
1 Glossary of Terms
baluster ....................... post forming part of balustrade
balustrade ................... collective term for the handrail and balusters forming the infilling to the side of a
stair or walkway
barge board................. sloping board along a gable end, covering ends of roof timbers
blinding........................ a sand or weak concrete mix layer on top of hardfill, to provide a smooth puncture-
free surface for placing of damp course layer
brick veneer................. outer skin of bricks over a timber frame
brise-soleil ................... vertical or horizontal sun shading on exterior of building
crs ............................... see centres
centres ........................ centres—distance at which an item repeats, e.g., studs at 600mm centres
contingency sum ......... allowance for unforeseen work
dpc .............................. damp proof course, layer of impervious material laid under concrete slabs on
ground, or between concrete surfaces and timber members, to exclude water
dunnage ...................... waste timber used for packing, particularly to keep materials off the ground, and
separated in layers
dwangs........................ see nogs
element ....................... “An element is a component part of a building or a development which,
irrespective of design or method of construction, tends to perform the same
function.”1
fascia board................. board fixed to rafter ends at eaves, to carry gutter
girt ............................... timber or steel rail attached to wall framing, generally used for larger sizes of
framing
going ........................... horizontal distance from stair riser to stair riser. Total going for going
flight of stairs is the sum of the goings tread riser
green ........................... unseasoned timber, or concrete or cement mortar after it has
set initially, and before gaining full strength
in situ........................... work done on site or in place, rather than pre-fabricated, most commonly used for
concrete poured in place versus pre-cast
jointing......................... working up brick or block mortar joints to give a finished surface while the mortar is
green, rather than raking out and refilling them, as in pointing
labours ........................ additional items of work, such as pointing to bricks. Not to be confused with the
labour to install materials. A bit of quantity surveying jargon.
lintel............................. beam over an opening, window or door
mortice ........................ slot cut into timber, into which a tenon from another members is glued or pinned.
Method of jointing timbers. Also used referring to locks morticed into door
newel post ................... post in flight of stairs, carrying the ends of outer string and handrail, and
supporting them at an end or corner
nogs, nogging} ............ horizontal short timbers which stiffen the studs of a framed partition
plumb bob ................... a weight hanging on a string (the plumb line) to show the direction of the vertical
plumbing of angles ...... transferring a point to one vertically above or below it, usually with a plumb bob or
plumb rule
pointing........................ raking out mortar joints 20mm deep and pressing a surface mortar into them.
Allows use of different colour mortar. May not bond to bedding mortar. See jointing
1. p1, Elemental Analysis of Costs of Building Projects, published by the New Zealand Institute of Quantity Surveyors Inc
Weights, Measures and Charts
2008
Abbreviations
Page 14-644
preliminaries, P&G ...... preliminary and general costs, includes those items of temporary establishment,
notices and fees, builders’ power, phone and water, scaffolding, security, plant
hire, insurances, supervision and the like, that cannot be seen in the finished
building, but which must be allowed in the budget of any building project
profiles......................... timber framework at corners of a building, to aid in establishing levels and position
purlins.......................... roof framing, generally on top of and at right angles to rafters, the roofing materials
are fixed to the purlins
quantity surveyor......... a person trained in construction costs and contract procedures.
rail ............................... horizontal secondary framing member, part of window or door, also, fence rail
rake, raking ................. an angle of inclination to the vertical
raking cutting............... cutting not at right angles
raking out .................... cleaning out mortar joints before pointing
rebar or reo ................. reinforcing steel
rebate .......................... rectangular recess cut in the edge of a piece of timber
riser ............................. the upright face of a step
string or stringer .......... sloping member at each end of the treads, cut to carry the treads and risers of a
stair
stile.............................. vertical end framing member of window or door
studs............................ vertical steel or timber framing members
tenon ........................... end of a rail, placed into a mortice in another member, forming a joint
tread ............................ the level part of a step
2 Abbreviations
A/C .............................. air-conditioning
b/w............................... both ways, as in battens at 600 centres both ways–vertical and horizontal
dia ............................... diameter
FECA........................... fully enclosed covered area—see UCA below
FF&E ........................... fittings, furniture and equipment—usually excluded from building budgets, or
shown separately
GFA............................. Gross Floor Area
HVAC .......................... heating, ventilating and air-conditioning
LPG ............................. liquid petroleum gas
SED............................. small end diameter (referring to timber pile sizes)
UCA............................. unenclosed covered area—i.e., no walls—see FECA above
3 Working Space
• Refer NZS4202:1995, Standard Method of Measurement of Building Works
• Minimum allowance for working space from wall or projecting footing face
Depth of excavation from commencing level Working space
Depth not exceeding 0.5m 0.2m
0.5m to 1.0m 0.4m
1.0m to 2.0m 0.6m
2.0m to 3.0m 1.0m
Depth exceeding 3.0m 1.3m
Weights, Measures and Charts
2008
Structural Steel Weights
UB’s, UC’s, H Piles, RSJ’s
Page 14-645
4.1 UB’s, UC’s, H Piles, RSJ’s Rolled Steel Joists—Taper Flange Beams
Universal Beams 100 x 45 x 7 7.2 134.4
150 UB14 14.0 71.4 0.590 125 x 65 x 13 13.1 74.6
150 UB18 18.0 55.6 0.600
180 UB16 16.1 62.1 0.700 4.2 Channels
180 UB18 18.1 55.2 0.700 Taper Flange
200 UB18 18.2 54.9 0.780 TF75 x 40 x 5mm 6.92 144.5
200 UB25 25.4 39.4 0.915 TF100 x 50 x 5mm 9.35 107.0
200 UB30 29.8 33.6 0.923
250 UB31 31.4 31.8 1.060 Parallel Flange
250 UB37 37.3 26.8 1.070 PF75 x 40 x 6.1mm 5.92 168.9
310 UB32 32.0 31.3 1.240 PF100 x 50 x 6.7mm 8.33 120.3
310 UB40 40.4 24.8 1.240 PF125 x 65 x 7.5mm 11.90 84.0
360 UB45 44.7 22.4 1.360 PF150 x 75 x 9.5mm 17.70 56.5
360 UB51 50.7 19.7 1.370 PF180 x 75 x 11.0mm 20.90 47.9
410 UB54 53.7 18.6 1.480 PF200 x 75 x 12.0mm 22.90 43.7
410 UB60 59.7 16.8 1.490 PF230 x 75 x 12.0mm 25.10 39.8
460 UB67 67.1 14.9 1.650 PF250 x 90 x 15.0mm 35.50 28.0
460 UB75 74.6 13.4 1.660 PF300 x 90 x 16.0mm 40.10 25.0
460 UB82 82.1 12.2 1.690 PF380 x 100 x 17.5mm 55.00 18.1
530 UB82 82.0 12.2 1.850
610 UB101 101.0 9.9 2.070 4.3 Round and Square Bars
610 UB125 125.0 8.0 2.090 Round Bars
6mm diameter 0.222 4,505.0
Universal Columns 10mm diameter 0.616 1,622.0
100 UC15 14.8 67.5 0.576 12mm diameter 0.887 1,126.0
150 UC23 23.4 42.7 0.889 16mm diameter 1.580 633.6
150 UC30 30.0 33.3 0.900 20mm diameter 2.460 405.5
150 UC37 37.2 26.9 0.924 24mm diameter 3.550 281.6
200 UC46 46.2 21.6 1.190 28mm diameter 4.840 206.9
200 UC52 52.2 19.2 1.212 32mm diameter 6.310 158.4
200 UC60 59.5 16.8 1.221 40mm diameter 9.865 101.4
250 UC73 72.9 13.7 1.480
250 UC89 89.5 11.2 1.523 Square Bars
310 UC97 96.8 10.3 1.790 6mm x 6mm 0.283 3,539.0
310 UC118 118.0 8.5 1.810 10mm x 10mm 0.785 1,274.0
310 UC137 137.0 7.3 1.830 12mm x 12mm 1.130 884.6
310 UC158 158.0 6.3 1.850 16mm x 16mm 2.010 497.6
20mm x 20mm 3.140 318.5
H Bearing Piles (other sizes available) 32mm x 32mm 8.040 124.4
HP1010x10, 250 x 250 62.5 38mm x 38mm 11.300 88.5
HP1212x12, 300 x 300 110.1 40mm x 40mm 12.600 79.3
HP1313x13, 325 x 325 129.5 45mm x 45mm 15.900 62.9
HP1414x14, 350 x 375 174.1 50mm x 50mm 19.600 51.0
Weights, Measures and Charts
2008
Structural Steel Weights
Mild Steel Angles
Page 14-646
2008
Structural Steel Weights
Hollow Sections
Page 14-647
2008
Structural Steel Weights
Flat Plate Sections
Page 14-648
Thickness Width
10mm 20mm 30mm 40mm 50mm 60mm 70mm 80mm
kg/m kg/m kg/m kg/m kg/m kg/m kg/m kg/m
2008
Reinforcing Steel
Weights of Reinforcing Rod
Page 14-649
5 Reinforcing Steel
Diameter Kg per metre metres per tonne Mesh Code Rod size in Rod centres in mm
mm
2008
Framing and Plywood
Plywood Grades
Page 14-650
2008
Retention Formula
Acceptable Solutions, Timber Durability
Page 14-651
7 Retention Formula
A spreadsheet formula can be used to calculate retention values. The formulae shown in cells A2
and A3 of the simulated spreadsheet below use the ‘IF’ worksheet function and are nested to 3
levels. The version in A2 has hard-typed values for the percentages and maximum values,
whereas the version in A3 has cell references (B1, C2, etc.), which can be edited for different
Conditions of Contract. Note: answer is negative.
• A1 = the cell reference for the progress claim valuation from which retentions are to be
deducted.
• B1 = 10% retention (on first $200,000)
• B2 = 5% retention (on the next $800,000, i.e., up to $1,000,000)
• B3 = 1.75% retention on the balance, to a maximum of $200,000 retained, or a progress
claim valuation of $9,000,000.
• Formulae shown in A2 or A3 (copy exactly) will return the retention value.
• Columns C and D contain the fixed values applying when SCC1 is used.
A B C D
1 enter valuation amount here 10.00% 200,000 20,000
2 =IF(A1>9000000,200000,IF(A1<200000,A1*0.1,IF(A1<1000000, 5.00% 1,000,000 60,000
(A1-200000)*B2+20000,(A1-1000000)*B3+60000)))*-1
3 =IF(A1>C3,-D3,IF(A1<C1,A1*B1,IF(A1<C2,(A1-C1)*B2+D1, 1.75% 9,000,000 200,000
(A1-C2)*B3+D2)))*-1
Weights, Measures and Charts
2008
Mensuration
Acceptable Solutions, Timber Durability
Page 14-652
8 Mensuration
Figure Description Perimeter Surface Area
A
Arc radius r, subtended angle A π r ---------
180
2 2
Helix number of turns n, pitch p, radius r n × [ p + ( 2πr ) ]
2 A
Sector arc a, radius r, subtended angle A 1
--- ar
2
or π r ---------
360
3
Segment chord a, altitude h h - + ⎛ 2--- a × h⎞
-----
2a ⎝ 3 ⎠
1
--- ( a
Trapezoid parallel sides a, b; altitude h 2
+ b )h
2
Circle radius r 2πr πr
--- π ( a --- π ab
1 1
Ellipse axes a,b 2
+ b) 4
2
2 π r ( h + r ) (total surface) πr h
1--- 2
slant height l π r ( l + r ) (total surface) πr h
2
1---
Pyramid, base perimeter a, base area A, height ½ al + A 3
Ah
rectangular or h, slant height l
triangular
2 4--- 3
Sphere (radius r) 4πr 3
πr
Weights, Measures and Charts
2008
Irregular Areas and Volumes
Trapezoidal Rule
Page 14-653
10 Measures
10.1 Linear
1,000 mm = 1 metre
100 cm = 1 metre
1,000 m = 1 kilometre
10.2 Square
1,000,000 mm2 = 1 square metre
10,000 cm2 = 1 square metre
10,000 m2 = 1 hectare
1,000,000 m2 = 1 square kilometre
10.3 Cubic
1,000,000,000 mm3 = 1 cubic metre
1,000,000 cm3 = 1 cubic metre
10.4 Weight
1 kl = 1 cubic metre
1,000 g = 1 kilogram
1,000 kg = 1 tonne
10.5 Liquid
1,000 ml = 1 litre
1,000 litres = 1 cubic metre
1,000 litres = 1 kilolitre
Weights, Measures and Charts
2008
Conversion Factors
Liquid
Page 14-654
11 Conversion Factors
Category Metric to Imperial Imperial to Metric
Length
1 km = 0.621371 mile 1 mile = 1.609344 km
= 49.7097 chain 1 chain = 20.1168 m
1m = 1.09361 yd 1 yd = 0.9144 m
= 3.28084 ft 1 ft = 0.3048 m
= 4.97097 links = 304.8 mm
1 link = 201.168 mm
1 in = 25.4 mm
Mass
1 tonne = 0.984 207 ton 1 ton = 1.016 05 tonne
= 19.684 1 cwt. 1 cwt = 50.802 3 kg
1 kg = 2.204 62 lb. 1 lb = 0.456 592 kg
1g = 0.035 274 0 oz. 1 oz = 28.349 5 g
Area
1 km2 = 0.386 102 mile2 1 mile2 = 2.589 99 km2
1 ha = 2.471 05 acre 1 acre = 0.404 686 ha
= 395.369 perch = 4,046.86 m2
1 m2 = 1.195 99 yd2 1 perch = 25.292 85 m2
= 10.764 ft2 1 yd2 = 0.836 127 m2
1 ft2 = 0.092 903 04 m2
1 in2 = 645.16 mm2
Volume/Capacity
1 m3 = 1.307 95 yrd3 1 yd3 = 0.764555 m3
= 35.314 ft3 100 board ft = 0.235973 m3
= 423.776 board feet 1 ft3 = 0.028316 8 m3
1 litre = 0.035314 7 ft3 1 in3 = 1,6387.1 mm3
= 0.219969 gal = 16.3871 ml
= 1.75976 pt 1 gal (Imp) = 4.54609 litre
1 gal (U.S.) = 3.785 41 litre
1 pt = 568.261 ml
1 fl oz = 28.413 ml
Velocity/Speed
1 km/h = 0.621371 mile/h 1 ft/s = 0.304 8 m/s
1 mile/h = 1.609344 km/h
Volume Rate of Flow
1 m3/s = 35.314 ft3/s 1 gal/min = 0.075 5682 litre/s
1 litre/s = 13.1982 gal/min.
Temperature
degrees
= ° C = 5--- ( ° F – 32 )
Celsius 9
degrees °F= × °C
⎛ 9--------------- ⎞
Fahrenheit
= ⎝ 5 - + 32⎠
Weights, Measures and Charts
2008
Conversion Factors
Liquid
Page 14-655
2008
Blockfill Volume
Liquid
Page 14-656
12 Blockfill Volume
750 300
725 290
ks
ks
ks
Bloc
Bloc
700 280
loc
mB
mm
Fire
675 270
d
on
m
150
200
650 260
am B
200m
B e mm
625 250
0
20
600 240
575 230
ks
oc
Bl
550 220
m
Number of blocks to be filled.
0m
525 210
Intermittent Filling
500 200
nd
475 190
Bo
Solid Filling
am m
450 180
Be 0m
425
25 170
400 160
375 150
350 140
325 130
300 120
275 110
250 100
225 90
200 80
175 70
150 60
125 50
100 40
75 30
50 20
25 10
0 0
1 2 3 4 5 6
Estimated cubic metres of blockfill required
Weights, Measures and Charts
2008
Weather Tables
30 Year Cycle, Period: 1971–2000
Page 14-657
13 Weather Tables
These are monthly climatological statistics for New Zealand main centres, based on historical
observations from several stations. Table 12.1 is the updated cycle, for 1971–2000, table 12.2 is
the original cycle, for 1961–1990, given for comparison purposes. The information is provided by
National Institute of Water and Atmospheric Research (NIWA).
13.1 30 Year Cycle, Period: 1971–2000
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Year
Auckland
Rainfall, average in mm 75 65 94 105 103 139 146 121 116 91 93 91 1240
Rainfall, average no of rain days 8 7 9 11 12 15 16 15 14 12 11 9 139
Temperature, max recorded C 28.7 30.5 27.3 26.7 22.6 21.1 20.0 20.0 21.0 23.0 25.3 27.1 30.5
Temperature, average C 19.4 19.8 18.5 16.2 13.7 11.6 10.8 11.3 12.6 14.1 15.8 17.7 15.1
Temperature, min recorded C 8.6 7.9 5.3 2.5 1.0 -2.5 -2.0 0 0.3 3.0 5.3 5.2 -2.5
Sunshine, average no of hours 231 198 184 157 138 111 130 141 147 178 191 209 2013
Windspeed, average days of gusts over 63km/hr 4 2 3 4 5 5 7 7 7 7 5 4 60
Ground Frost, average no of days 0.1 0.6 2.7 3.7 2.0 0.8 0.2 9.5
Snow, average no of days 0.04 0.04
Wellington
Rainfall, average in mm 72 62 92 100 117 147 137 123 100 115 99 86 1249
Rainfall, average no of rain days 7 7 8 9 11 14 13 13 12 12 10 8 124
Temperature, max recorded C 30.1 30.1 26.6 24.7 22.0 18.3 17.6 18.0 21.9 21.5 24.3 27.6 30.1
Temperature, average C 16.9 17.1 15.8 13.8 11.5 9.5 8.8 9.2 10.6 12.0 13.4 15.3 12.8
Temperature, min recorded C 5.8 5.3 4.6 3.7 1.0 0.2 0.2 0.1 1.3 1.2 2.1 4.8 0.1
Sunshine, average no of hours 246 209 191 155 128 98 117 136 156 194 210 226 2064
Windspeed, average days of gusts over 63km/hr 18 14 16 15 17 16 16 16 18 21 19 19 205
Ground Frost, average no of days 0.1 0.6 2.1 3.0 3.1 1.1 0.3 0.1 10.0
Snow, average no of days 0.03 0.20 0.17 0.10 0.10 0.10 0.62
Christchurch
Rainfall, average in mm 43 41 56 51 52 62 72 66 46 49 46 47 630
Rainfall, average no of rain days 6 5 6 7 7 9 8 8 6 7 7 7 83
Temperature, max recorded C 35.9 40.0 35.9 29.9 27.3 22.5 21.7 21.5 26.2 30.1 31.2 35.4 40.0
Temperature, average C 17.1 16.8 15.1 12.1 8.9 6.2 5.8 7.0 9.3 11.7 13.5 15.8 11.6
Temperature, min recorded C 3.0 2.5 -0.2 -4.0 -4.7 -7.2 -6.8 -6.7 -4.2 -4.2 -1.7 1.5 -7.2
Sunshine, average no of hours 230 196 183 161 142 119 124 148 165 198 215 221 2100
Windspeed, average days of gusts over 63km/hr 6 4 5 4 4 3 3 4 5 6 6 6 56
Ground Frost, average no of days 0.2 1.1 4.0 11.5 18.2 18.1 15.6 10.7 6.2 2.1 0.4 87.6
Snow, average no of days 0.09 0.13 0.96 0.70 1.05 0.36 0.09 0.05 3.41
Dunedin
Rainfall, average in mm 72 62 70 58 70 71 67 66 53 71 64 81 805
Rainfall, average no of rain days 10 8 10 9 11 10 11 11 10 11 11 12 124
Temperature, max recorded C 35.7 34.6 30.0 26.4 23.6 20.6 20.0 20.2 25.0 31.0 31.3 31.5 35.7
Temperature, average C 15.2 15.2 13.8 11.9 9.3 7.1 6.6 7.6 9.3 11.0 12.3 13.9 11.1
Temperature, min recorded C 5.2 2.0 1.0 1.0 -4.5 -8.0 -2.7 -2.5 -6.5 0.0 1.8 4.5 -8.0
Sunshine, average no of hours 178 152 139 121 100 86 101 113 128 146 161 167 1592
Windspeed, average days of gusts over 63km/hr 10 8 10 8 10 9 8 10 10 11 11 10 115
Ground Frost, average no of days 0.1 0.3 1.7 6.1 12.6 15.6 12.3 7.3 3.1 0.9 0.1 58.1
Snow, average no of days 0.05 0.10 0.50 1.00 0.65 1.00 0.20 0.30 0.21 4.28
Weights, Measures and Charts
2008
Weather Tables
30 Year Cycle, Period: 1961–1990
Page 14-658
Information for other centres is available from NIWA on a user pays basis.
See also www.niwa.co.nz, where some monthly information is available to download at no charge.
13.2 30 Year Cycle, Period: 1961–1990
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Year
Auckland
Rainfall, average in mm 70 87 79 98 118 130 135 115 96 96 84 77 1185
Rainfall, average no of rain days 8 8 9 11 14 15 15 15 13 12 11 9 140
Temperature, max recorded C 32.2 32.4 29.9 27.2 23.6 21.2 19.2 19.6 22.2 23.9 27.2 31.8 32.4
Temperature, average C 19.4 19.7 18.7 16.5 13.9 11.9 10.9 11.5 12.8 14.4 16.1 17.9 15.3
Temperature, min recorded C 7.3 8.6 5.6 4.1 2.0 -0.1 0.7 1.1 1.2 2.3 5.0 6.1 -0.1
Sunshine, average no of hours 235 194 191 152 141 126 129 149 169 181 208 227 2102
Windspeed, average days of gusts over 63km/hr 3.3 2.4 3.3 4.2 6.3 6.1 6.4 6.0 6.6 6.6 5.1 4.8 61.2
Ground Frost, average no of days 0.2 1.0 1.9 0.9 0.2 4.2
Snow, average no of days 0.1 0.1
Wellington
Rainfall, average in mm 81 81 85 100 122 125 139 122 100 106 88 91 1240
Rainfall, average no of rain days 7 7 8 10 12 13 14 13 11 11 10 9 125
Temperature, max recorded C 30.1 31.1 28.3 27.3 21.7 20.6 17.2 18.9 20.6 25.1 26.9 29.1 31.1
Temperature, average C 16.4 16.6 15.6 13.6 11.0 8.9 8.2 8.98 10.2 11.8 13.4 15.2 12.5
Temperature, min recorded C 4.1 4.7 3.9 2.1 -0.7 -1.2 -1.9 -1.6 -0.6 1.1 1.7 3.4 -1.9
Sunshine, average no of hours 236 201 186 151 118 104 107 132 162 190 208 224 2019
Windspeed, average days of gusts over 63km/hr 17.9 15.2 16.1 16.8 18.1 16.7 16.3 17.0 20.0 20.2 19.8 19.2 213.3
Ground Frost, average no of days 0.1 1.0 3.2 4.7 3.6 1.7 0.5 0.2 15.0
Snow, average no of days 0.1 0.1 0.4 .02 0.3 0.1 1.2
Christchurch
Rainfall, average in mm 55 42 54 56 75 62 71 53 47 47 46 58 666
Rainfall, average no of rain days 7 5 7 7 8 9 9 7 7 7 7 7 87
Temperature, max recorded C 36.2 41.6 33.4 30.1 27.0 22.5 22.8 23.2 27.3 31.4 32.2 35.0 41.6
Temperature, average C 16.6 16.3 14.8 12.1 8.9 6.3 5.9 7.0 9.5 11.9 13.7 15.6 11.6
Temperature, min recorded C 1.1 1.2 -0.9 -3.6 -5.9 -5.8 -7.1 -5.0 -4.8 -3.3 -1.5 -0.6 -7.1
Sunshine, average no of hours 211 183 180 139 126 114 127 145 164 185 205 195 1974
Windspeed, average days of gusts over 63km/hr 3.3 3.1 1.9 2.8 3.7 3.2 3.8 4.0 2.6 4.3 4.1 3.9 40.7
Ground Frost, average no of days 0.2 0.2 1.1 4.5 11.2 17.8 18.8 16.8 10.0 5.2 2.4 0.5 88.7
Snow, average no of days 0.2 0.5 0.8 0.4 0.3 0.2 2.4
Dunedin
Rainfall, average in mm 86 69 78 74 83 83 79 74 67 75 81 89 938
Rainfall, average no of rain days 11 9 10 10 11 10 10 10 10 11 12 12 126
Temperature, max recorded C 34.4 32.2 28.9 28.9 22.2 20.0 18.9 21.1 25.0 28.3 28.9 28.9 34.4
Temperature, average C 14.8 14.6 13.4 11.5 8.7 6.8 6.3 7.4 9.3 11.1 12.1 13.6 10.8
Temperature, min recorded C -0.2 -0.8 -2.0 -4.8 -7.7 -8.2 -8.1 -7.3 -5.1 -3.7 -2.1 -0.8 -8.2
Sunshine, average no of hours 174 185 143 128 99 98 100 122 134 162 169 182 1676
Windspeed, average days of gusts over 63km/hr 6.5 4.2 5.4 5.3 6.6 5.3 3.9 4.8 6.1 7.8 7.2 4.9 68.0
Ground Frost, average no of days 0.1 0.6 3.9 8.4 11.0 8.3 3.5 1.1 0.3 0.1 37.3
Snow, average no of days 0.1 0.7 1.1 1.5 1.6 0.9 0.5 0.2 0.1 6.7
Weights, Measures and Charts
2008
Exchange Rate Fluctuations
Overseas Trade Indexes (Prices)
Page 14-659
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
2008
B
Page 15-661
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Avenue seat 4-429 Laminate 4-248 Flush 4-232
Awnings 4-187 Laminated Rimu 4-248 Galvanised Mild Steel 4-169
Axon Panel 4-208 Marble 4-248 Galvanised, with insert 4-198
Polyceramic 4-248 Hardware 4-231
B Polypropylene 4-248 High Strength Steel 4-169
Baby Changing Station 4-236 Stainless Steel 4-248 Holding Down 4-170
Backbar chillers 4-437 Benches 4-429 Indicator 4-231
Backfill Benchsaw, hire rates 4-454 Necked 4-231
Drainage 4-318 Bentonite 4-173 Panic 4-230
Excavation 4-135 Diaphragm wall 4-156 Socket 4-231
Baffle Block 4-203 Bevelback weatherboards 4-216 Stainless Steel 4-169
Bagging 4-176 Bevels, glass 4-416 Bond beam 4-180
Balau decking 4-205 Bidets 4-298 Bonding Agents 4-144
Balustrade Bins, litter 4-429 Bondor insulated panels 4-278
Aluminium 4-188 Bitumen Bondor Polyrock 4-135
Brass 4-188 Break up and remove 4-133 Bottle Store 4-440
Comparative Costs 3-82 Paving 4-422 Bowmac 4-199
Stainless Steel 4-188 Bituminous Box Gutters
Steel 4-188 Coating 4-173 Butyl Rubber 4-285
Timber 4-244 Membranes, Roofing 4-286 Copper 4-292
Balustrades 4-188 Bituproof 4-173 Polibit 4-292
Banks Bituthene 4-174 Zincalume 4-292
Building Costs/m2 1-13 Blanket BPB Plasterboard 4-388
Elemental Costs 2-41 Fibreglass, Bradford Gold 4-204 Bracing 4-193
Fit-Out 4-438 Fire 4-421 Plywood 4-217
Barge Boards 4-220 Blinds 4-256 Brackets, Steel 4-189
Bark mulch 4-425 Blockfill Volume 14-656 Bradford Gold 4-204
Basecourse 3-66, 4-135, 4-422, 4-431 Blocks Brass
Basins 4-302 Glass 4-178 Angle 4-399
Pedestal 4-302 Polycarbonate 4-178 Division Strip 4-399
Wall 4-302 Blockwork 4-179 Handrail 4-189
Baths 4-300 Bond beam 4-180 Breather Type Building Paper 4-202
Hospital 4-444 Coping Blocks 4-180 Brick
Spa 4-301 Cutting 4-180 Pavers 4-423
Battens 4-197 DryBlock 4-180 Walls 3-77
Batter Excavation 4-136, 4-431 Filling 4-180 Bricks
Beams FormBlock 4-180 Concrete 4-175
Comparative Costs 3-65 Grouting 4-180 Monier 4-175
Composite 4-201 Insulated 4-179 Brickwork 4-175
Concrete 4-143 Labour constants 5-462 Bagging 4-176
Laminated Timber 4-239 Labours 4-180 Cavities 4-175–4-176
Pergola 4-197 Lightweight 4-179 Cavities, filling 4-176
Posi-Strut 4-201 Lintels 4-180 Coloured mortar 4-176
Twinaplate 4-201 Reinforcement 4-180 Copings 4-177
Bearers Board and Batten 4-216 Cutting 4-176
Eaves 4-196 Boiler Firebricks 4-178
Floor 4-193 Gas Fired 4-335 Forming angles 4-175
Bed Screen 4-438 Oil Fired 4-335 Glass Blocks 4-178
Beds Bollard lighting 4-369 Hinuera Stone 4-175–4-176
Hospital 4-443 Bolts 4-169 Labour constants 5-462
Hotel 4-440 Black Mild Steel 4-169 Lintels 4-177
Student 4-438 Coach 4-198 Polycarbonate 4-178
Bench Supports 4-189 Dust 4-232 Reinforcement 4-177
Bench Tops 4-248 Dynabolt 4-170 Sills 4-177
Granite 4-248 Exit Devices 4-230 Stack bond 4-176
Index
2008
C
Page 15-662
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Ties 4-177 Bolts 4-198 Tiles 4-401
Veneer ties 4-177 Bracing, metal 4-199 Tufted 4-400
Broadband connection 4-121 Building Papers 4-202 Underlay 4-400
Broom Cupboard 4-247 Ceiling Linings 4-219 Wilton 4-400
Brownbuilt 900 4-282 Wood Fibre Panels 4-219 Woven 4-400
Budgets 11-539 Damp Proof Courses 4-192 Carport, Building Costs/m2 1-28
Building Decking 4-205 Cartage 4-430
Levy 4-125 Finishings Cash flow 11-564
Papers 4-202 Barge Boards 4-220 Catering Facilities 4-434
Research Levy 4-110, 4-125 Fascia 4-220 Cavities
Building Act 12-590 Fixings 4-198 Brickwork 4-175–4-176
Exemptions 12-593 Floor Cavity
Built Up Sections, Steel 4-164 Sanding 4-207 Sliding Doors 4-260
Bulk Excavate 4-133, 4-430 Sealing 4-207 Ties 4-177
Bulkhead, fire resistant 4-420 Flooring 4-205 Cavity battens 4-197
Bulking factors 4-133 Decking 4-205 CBI—MasterSpec® 11-547
Bus Lane Surfacing 4-422 Hardwood 4-206 CCI
Butyl Rubber Kopine 4-205 Description 6-493
Box Gutters 4-285 Parquet 4-206 Tables 6-494, 6-496
Comparative Costs 3-76 Plywood 4-205 Cedar
Eaves Gutter 4-285 Premafloor 4-205 Ply 4-217
Membrane Roofing 4-285 Pynefloor 4-205 Shingles 3-76
Valley Gutters 4-292 T&G 4-206 Ceiling
Butynol Rubber Framing 4-193 Access Ladders 4-234
Roofing 4-284 Ceiling 4-194 Battens 4-195
Kiln dried 4-196 Finishes 3-91
C Pergola 4-197 Hangers 4-194
Cabin Hook 4-232 Posts 4-197 Joists 4-194
Cable Roof 4-195 Linings 4-219
Aluminium 4-362 Steps 4-197 Wood Fibre Panels 4-219
Carriers 4-360 Stress Grading 14-649 Panels, Heating 4-393
Copper 4-356–4-357, 4-362 Wall 4-194 Runners 4-195
High Voltage 4-356 Insulation 4-203 Suspended Grid 4-394
Service Mains 4-356 Labour constants 5-467 Sweep fan 4-375
Calculation Lintels Ceiling Tiles
Areas 14-653 LVL 4-202 Fibre Cement 4-395
Volumes 14-653 Nail Plates 4-198 Gib Tone 4-394
Canopies 4-113 Particle Board 4-205 Mineral fibre 4-394
Capital Goods Price Index 6-493 Pile Connectors 4-199 Ceilings
CAR Insurance. See Insurance Roof Trusses 4-200 Coatings 4-411
Car’ousel vehicle turntable 4-433 Soffit Fire Rated 3-72
Carborundum slip strips 4-181 Bearers 4-196 Leaf, suspended 4-396
Caroma Linings 4-219 Linear 4-396
Basins 4-302 Trusses 4-200 Metal Strip 4-396
Baths 4-301 Wall Linings Open Cell 4-395
Caroma fittings 4-297–4-298 Plywood 4-217 Screen 4-396
Cisterns 4-299 Timber Boarding 4-217 Stainless Steel panel 4-396
Leda 4-298 Weatherboards 4-215–4-216 Cement Plaster 3-90, 4-384–4-385
Urinals 4-299 Carpet 3-88, 4-400 Comparative Costs 3-77
Carpark Membranes 4-286 Axminster 4-400 Cemix 4-144
Carpentry 4-192 Cut pile 4-400 Easy Flor 4-399
Beams Loop pile 4-400 Pro Flor 4-399
LVL 4-202 Mitech film 4-130 Centrifugal fans 4-375
Posi-Strut 4-201 Protection 4-130 Cesspit, Drainage 4-325
Twinaplate 4-201 Skirting 4-403 CGPI
Index
2008
C
Page 15-663
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Description 6-493 Vanities 4-303 Concept Design 11-543
Tables 6-494, 6-497 Clearspan Shutters 4-265 Concrete
Chainsaw, hire rates 4-454 Clearview Squash Court 4-254 Additives 4-144
Chairs, office 4-447–4-448 Cleats, roof framing 4-195 basecourse 4-422
Changing Rooms Climatherm pipe 4-339 Beams 3-68, 4-143
Building Costs/m2 1-24 Clinic, Building Costs/m2 1-17 Blockwork 4-179
Elemental Costs 2-56 Clocks 4-380 Blockwork, DryBlock 4-180
Channel Drains 4-328 Closed Circuit Television 4-383 Blockwork, FormBlock 4-180
Channels 4-424, 14-645 Closers, Door 4-230 Blockwork, insulated 4-179
Chapel, Building Costs/m2 1-28 Clubhouse Break up and remove 4-133
Charge Out Rates 7-503 Building Costs/m2 1-24 Bricks 4-175
Charges, P&G Check List 4-110 Elemental Costs 2-56 Bush hammer finish 4-145
Chemical Resistant Coatings 4-410 Coach Bolts 4-198 Channel Drain 4-328
Chequer Plate 4-172 Coat Hook 4-232 Channels 4-424
Cherry Picker, Hire 4-123 Cocks 4-305 Columns 3-67, 4-143
Chillers, Water 4-333 Coir Mat 4-404 Comparative Costs
Chilllers 4-437 Cold Store Beams 3-68
Chip Seal 4-422, 4-431 Doors 4-278 Column Pads 3-66
Church, Building Costs/m2 1-28 Shelving 4-277 Columns 3-67
Chutes, Disposal 4-450 Collar Roof 3-76
Cinemas, Building Costs/m2 1-16 Fire stop 4-420 Roof tiles 3-76
Circuits Ties 4-195 Suspended Slab 3-73
Heating 4-367 Colorcote Walls 3-71
Lighting 4-365–4-366 Wall Cladding 4-287 Crib Wall 4-428
Power 4-366–4-367 Colorsteel Culvert 4-432
Telephone 4-378 Roofing 4-281–4-282 Cutting and drilling 4-147
Cisterns 4-299 Wall Cladding 4-287 Detailed prices 4-142
Urinal 4-299 Column Diaphragm walling 4-156
Civic Buildings Formers 4-155 Drilling 4-147
Building Costs/m2 1-11 Guards 4-187 Expansion joints 4-147
Elemental Costs 2-38 Pads, Comparative Costs 3-66 Filling 4-143
Civic Centre Columns Finishes 4-143
Building Costs/m2 1-11 Comparative Costs 3-67 Floors 3-73
Elemental Costs 2-38 Concrete 4-143 Foundations 4-142
Civil Engineering Combination Locks 4-224–4-225 Grinding floors 4-143
Culverts 4-432 Combustion Heaters 4-435 Labour constants 5-460
Excavation 4-430 ComFlor 210 3-73 Masonry
Plant constants 5-484 Detailed Prices 4-153 Comparative Costs 3-71
Roadworks 4-431 ComFlor 80 Walls 3-71
Cladding Comparative Costs 3-73 Mixer, hire rates 4-453
Comparative Costs 3-78 Detailed Prices 4-153 Pavers 4-423
Perforated 4-190 Compaction 4-430 Paving
Sheetmetal 4-190 Compactors insitu 4-423
Transparent 4-284 Garbage 4-450 road 4-432
Wall 4-287 Comparative Costs slabs 4-423
Classification Exclusions 3-63 Piles, insitu 4-139
work sections 11-547 Explanatory Notes 3-63 Piles, precast 4-139
Clay Roof Tiles 4-283 Purpose 3-63 Pipework
CLD panel 4-208 Composite steel permanent Drain 4-322
Cleaners Sink 4-303 formwork 4-153 Sewer 4-321–4-322
Clean-Off Zone 4-404 Compressors, Hire rates 4-453 Precast 4-157
Clearlite Computer Beams 4-158
Basins 4-302 Flooring, Cemac 4-190 Floors 4-157
Baths 4-300 Workstation 4-448 Freezer/chiller panels 4-159
Shower bases 4-301 Concealed Gutter 4-291 Nirvana 4-159
Index
2008
D
Page 15-664
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Panels 4-159 Cool/Cold Store Bradford Glasswool 4-204
Stairs 4-158 Building Costs/m2 1-21 Bradford Gold 4-204
Thermomass 4-159 Cooling Culverts 4-432
Tilt-Up 4-160 Coils 4-334 Curing Compounds 4-144
Pumping 4-143 Load 4-329 Curtain
Roof Shingles 4-283 Towers 4-333 Air 4-268
Roof Tiles 4-283 Coordinated Rails 4-237
Shingles 3-76 Building Information 11-547 Tracks 4-438
Shingles, roofing 4-283 Coping Walling 4-253
Slabs 4-142 Blocks 4-180 Walls, Comparative Costs 3-81
Spacers, PCP 4-162 Bricks 4-177 Cut To Fill 4-136, 4-430
Sprayed 4-156 Copper Cutting
Stairs 4-143 Box Gutters 4-292 Blocks 4-180
Steel encasing 4-143 Cable 4-356–4-357, 4-362 Bricks 4-176
Supply & place 4-142 Downpipes 4-294 Chase 4-148
Supply prices 4-142, 4-156 Flashings 4-295 Concrete 4-147
Surrounds, pipe 4-325 Pipework Cycle Racks 4-187
Tanks 4-313 Mechanical 4-339 Cygnus 4-280
Testing 4-143 Soil 4-308 Cylinder Deadbolts 4-226
Tiles, roofing 4-283 Water 4-310 Cylindrical Locks 4-226
Treatments 4-144 Rainwater Heads 4-291
Walls 3-71, 3-77, 4-143 Traps 4-307 D
Waterstops 4-145 Valley Gutters 4-292 Dairy shed 1-30
Concrete Masonry Coral-Tread 4-404 Damp Proof Courses 4-192
Blockfill volumes 14-656 Core Filling 4-180 To brickwork 4-178
Conditions of Contract 11-557 Cork Tiles 4-401 Damper, Fire 4-342
Conduits 4-361 Cornice Dampstop 4-144
Consents Ornamental, fibrous plaster 4-393 Danpalon 4-284
Resource Management 12-600 Corus 3-73 Daywork or Charge Out Hourly
Construction Cost Rates 7-505
Design 11-543 control 11-544 DCF. See Discounted cash flow
Keying 4-226 definition 11-539 Deadlocks 4-224
Management 11-555–11-556 life cycle 11-571–11-575 Deck Membranes 4-286
Periods 11-562 management 11-544 Decking
Construction Contracts Act 12-603 operating 11-569 balau 4-205
Construction Indices 6-494, 6-496 planning 11-539, 11-544 Fibre cement 4-205
Consumer Price Index 6-493 plus 11-555 kwila 4-205
Contactors 4-375 reimbursement 11-553, 11-555 Steel 4-172
Contract Council Connections Timber 4-205
Administration 11-544 Drainage 4-325 Decorating 4-406
Conditions 11-557 Court Buildings Paper Hanging 4-409
Duration 11-562 Building Costs/m2 1-12 Wall Fabrics 4-409
Length of 11-562 Elemental Costs 2-40 Dee litter bin 4-429
Retentions 11-559 Covers Deep Freezers 4-436
Contractual Systems 11-553 Manhole 4-326 Definitions
Control equipment, electrical 4-375 CPI construction management 11-556
Controlled activities Description 6-493 Design stages 11-543
Resource Management 12-600 Tables 6-494, 6-497 project management 11-556
Conversion Factors 14-654 Crane Demolition 4-128
Cooking Equipment Inspections 4-125 Alterations 4-129
Electric 4-436 Mobile 4-119 Comparative Costs 3-64
Gas 4-436 Tower 4-120 Concrete paving 4-133
Cool Rooms 4-277 Crib Wall Electrical fittings 4-132
Doors 4-278 Concrete 4-428 Entire structures 4-128
Shelving 4-277 CSR Forming openings 4-130
Index
2008
D
Page 15-665
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Labour constants 5-458 Discretionary activities Glazing Beads 4-258
Partial 4-130 Resource Management 12-600 Hollow Core 4-259
Preparatory work 4-131 Dishwasher 4-437 Insect 4-268
Refurbishment 4-129 Dispenser Interlocking Slat 4-263
Repairs 4-131 Paper Towel 4-237 Louvre 4-260
Sanitary fittings 4-132 Soap 4-237 Panelled 4-259
Services 4-132 Toilet Roll 4-236 PVC Strip 4-265
Depreciable Improvements 13-620 Disposal Retractable Grilles 4-264
Depreciation Bins 4-237 Revolving 4-261
Rate Finder 13-620 Chutes 4-450 Roller
Depreciation Schedules 13-621 Excavated material 4-135 Domestic 4-262
Building fitout 13-627 Incinerator 4-450 Industrial 4-263
Buildings and Structures 13-626 Waste 4-450 Shutter 4-263
Computers 13-634 District Hospital Rolling Grilles 4-264
Contractors, Builders and Building Costs/m2 1-17 Safety Swing 4-265
Quarrying 13-630 Divers 4-124 Sectional Overhead 4-264
Furniture 13-631 Document Security 4-268
Hotels, motels, cafes 13-638 Lift 4-433 Slide Over 4-264
Laundry 13-637 Transport Systems 4-433 Sliding 4-261
Office Equipment 13-631 Trough Conveyor 4-433 Solid Core 4-259
Residential Rental Property Domestic Roller Doors 4-262 Strongroom 4-445
Chattels 13-640 Door Swing 4-265
Shops 13-635 Closers 4-230 Tilting 4-262
Tanks and Vats 13-633 Frames 4-257 Timber 4-259
Design Aluminium 4-258 Comparative Costs 3-85
and Build 11-555 Timber 4-257 Dormitory Fit-Out 4-438
Concept 11-543 Furniture Supply Prices 4-227 Double
Construction 11-543 Seals 4-233 Glazing 4-413
Detailed 11-543 Sliding Track 4-229 Leaf Overhead Doors 4-264
Developed 11-543 Stops 4-229 Tee
Documentation guidelines 11-541 Track 4-229 Comparative Costs 3-75
documentation guidelines 11-541 Doors Downpipes 4-294
Preliminary 11-543 Accordion 4-266 Labour constants 5-472
Detailed Design 11-543 Acoustic 4-267 Drainage
Detailed Prices Air Curtains 4-268 Backfill 4-318
Exclusions 4-109 Aluminium 4-261 Cesspits 4-325
Inclusions 4-109 Automatic 4-261 Channel 4-328
Detector Cavity Sliding 4-260 Comparative Costs 3-100
Fire 4-351 Clearspan Shutters 4-265 Concrete Pipe Surrounds 4-325
Traffic 4-433 Cold Store 4-278 Connect to existing 4-325
Developed Design 11-543 Comparative Costs 3-81, 3-85 Directional Drilling 4-318
Devotional Buildings Fire 3-86 Labour constants 5-477
Building Costs/m2 1-28 Hollow Core Flush 3-85 Manhole Covers 4-326
Diaper Changing Table 4-236 Solid Core Flush 3-85 Manholes 4-326
Diaphragm Walling 4-156 Door Frames 4-257 Micro-Tunnelling 4-318
Diffusers 4-344 Aluminium 4-258 Pipework
Acrylic Light 4-395 Timber 4-257 Concrete 4-321
Dimond Hi Span Purlins 4-168 Door Stop 4-258 Earthenware 4-320
Dimondek 300 trough roofing 4-282 Double Leaf Overhead 4-264 PVC 4-318
Dimondek 400 trough roofing 4-282 Entrance 4-260 Sewer 4-318–4-323
DimondShake Fire 4-267 Slotted PVC 4-324
Comparative Costs 3-76 Folding Septic Tanks 4-327
DimondTile 4-283 Industrial 4-264, 4-266 Subsoil 4-324
Directional Drilling 4-318 Framed 4-260 Sumps 4-325
Discounted cash flow 11-572 Garage 4-262 Traps 4-327
Index
2008
E
Page 15-666
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Trench Excavation 4-316–4-317 motor starters 4-375 Stockpile Material 4-430
Wing Walls 4-328 Residual Current Device 4-376 Surface treatments 4-136
Drains, Roof 4-293 Services Top soil, stripping 4-133
Draw-downs 11-564 Comparative Costs 3-97 Tree removal 4-133
Drawer Units 4-245 Submains Sizing 3-98 Trench
Driers Temporary 4-121 Backfill 4-318
Hair 4-236 Electromagnetic Locks 4-228 Drainage 4-316–4-317
Hand 4-236 Elements 3-63 Working Space 14-644
Drill, hire rates 4-453 Definition 2-36 Excavators, hire rates 4-452
Drilling Emergency Exchange Rate Fluctuations 14-659
Concrete 4-147 Lighting 4-372 Exhaust
Directional 4-318 Luminaire 4-372 Fans 4-374
Drinking Fountains 4-304 Power Supply 4-372 Grilles 4-345
DryBlock® Concrete Blocks 4-180 Warning System 4-380 Exit Sign 4-372
Dryer, Commercial 4-435 Employer Expansion
Dryvit Outsulation 3-80, 4-279 Levy Rates 7-512 Joint covers 4-149
Ductwork 4-342–4-344 Historic 7-513 Joints 4-147
Dumbwaiter 4-353 Premium 7-512–7-513 External Works 3-101
Dumpy Level, hire rates 4-454 Employment Artificial Surfaces 4-424
Durolite 4-284 Contracts 7-503 Asphalt Paving 4-422
Durolite HeatGuard 4-284 Relations Act 12-596 Channels 4-424
Dust Proofers 4-144 Endura Fences 4-427
Dux Roofing 4-281–4-282 Grassing 4-425
Centreflush 4-299 Englefield Paving 4-423
Cistermiser 4-300 Baths 4-300 Retaining Walls 4-428
Twinline 4-299 Shower enclosures 4-301 Road Marking 4-422
Dycore, Comparative Costs 3-75 Spa baths 4-301 Sand Bedding 4-422
Dynabolt 4-170 Entrance Doors 4-260 Soil Control Fabrics 4-426
Enviromix 4-422 Top Soil 4-425
E Epoxy Floor Coating 4-410 Trees and Shrubs 4-425
Earner Levy 7-511 EPS40CavityPlus 3-80, 4-279 Underlay 4-422
Earthenware Equipment Extinguishing Systems 4-350
Pipework, Sewer 4-320 Lighting 4-367, 4-369 Extruded Polystyrene 4-152, 4-203
Eaves Power 4-372–4-377
Bearers 4-196 Usage factors 5-484 F
Gutter 4-292–4-293 Ergonomic Furniture 4-448 Fabric Mesh 14-649
Butyl Rubber 4-285 Escalators 3-99, 4-354 Fabric Wall Coverings 4-409
Mould 4-220 Eulux Flooring 4-206 Factories
Eco skylight 4-289 Euro Fibre Slates 4-284 Building Costs/m2 1-20
Economesh 4-162 Excavation 4-133 Falling butt hinge 4-223
Ecotanks 4-327 Bulk excavate 4-133, 4-430 Fan Coil Units 4-331
Educational Buildings Bulking factors 4-133 Fanlight stay 4-232
Elemental Costs 2-42 Cartage 4-430 Fans
EIFS cladding systems 3-80, 4-279 Civil Engineering 4-430 Air Conditioning 4-331
Elasto-Deck 5000 HT 4-286 Compaction 4-430 Axial Flow 4-332
Elderly Persons Home Comparative Costs 3-64 Ceiling sweep type 4-374
Building Costs/m2 1-27 Cut to fill 4-136, 4-430 Centrifugal 4-331
Elemental Costs 2-58 Disposal 4-135 In-line 4-374–4-375
Electric leads, hire 4-453 Excavate in Rock 4-431 Exhaust 4-374
Electrical Fill 4-431 Hire rates 4-454
contactors 4-375 Filling 4-135 Farm Buildings
control equipment 4-375 Labour constants 5-459 Building Costs/m2 1-30
hospital equipment 4-376 Planking & strutting 4-136 Fascias 4-220
Labour constants 5-478 Plant constants 5-484 Fast tracking 11-563
MCB’s 4-376 Site preparation 4-133 Fasteners
Index
2008
F
Page 15-667
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Tylok 4-198 Resistant Cabinet 4-445 Green Tongue 4-205
FBT 13-617 Retardant Building Papers 4-202 Pynefloor 4-205
Feasibility studies 11-550 Services SuperBrace 4-217
Fees Comparative Costs 3-96 Flexicote 4-412
architects 11-576 Sprinkler Systems 4-350–4-351 Flintkote 4-173
commercial property 8-517 Fire Proofing 4-421 Floor
land agents 8-517 Acrylic 4-421 Area
professional 11-576 Cementitious Sprayed 4-418 Gross 11-548
Feltonmix 4-306 Ceramic Fibre Blanket 4-421 Rentable 11-548
Fences 4-427 Dry Board Systems 4-419 Coatings 4-410
Pool Safety 4-427 Fire Resistant Bulkhead 4-420 Computer 4-190
Fibre Cement 4-427 Fire Resistant Pillows 4-420 Joists 4-193
Axon Panel 4-208 Fire Stop Collars 4-420 Levelling Compound 4-399
Ceiling Tiles 4-395 Floor/Wall Joints 4-421 Mats 4-404
CLD Panel 4-208 Intumescent Coatings 4-419 Plate Sections 14-646
Fences 4-427 Monokote 4-418 Plates 4-194, 4-196
Hardibacker 4-207 Seismic Floor Joints 4-421 Sanding 4-207
Hardies Weatherboards 4-215 Fire Station Screed 4-399
Hardiflex 4-207 Building Costs/m2 1-12 Screeds 4-398
HardiGroove™ 4-207 Elemental Costs 2-40 Sealing 4-207
Hardipanels 4-207 Firemaster Felt 4-421 Springs 4-229
Inseal jointer 4-207 Firth Storage Heating 4-374
Villaboard 4-207 Concrete bricks 4-175 Systems, Precast 4-157
Weatherboards 4-215 Ribraft floor system 3-66, 4-152 Floor Coatings
Fibreclene 4-411 Fit-Out Acid Resistant 4-410
Fibreglass Bar 4-439 Anti-Dusting 4-410
Wall Coverings 4-409 Bedrooms, hotel 4-440 Chemical Resistant 4-410
Fibrerock 4-391 Bottle Store 4-440 Slip Resistant 4-410
Fibrous Plaster 3-91, 4-393 Building Costs/m2 1-22 Floor Coverings
Comparative Costs 3-89 Hospital 4-443 Anti-Static 4-401–4-402
Filling 4-180 Kitchen Equipment 4-441 Carpet 4-400
Brick cavities 4-176 Laboratory 4-438 Carpet Tiles 4-401
Comparative Costs 3-66 Office 4-447–4-448 Cork Tiles 4-401
Concrete 4-143 Restaurants 4-439 Labour constants 5-473
Excavation 4-135 Retail 4-446 Linoleum 4-401
Imported 4-431 Servery 4-439 Mats 4-404
Filters Shop 4-446 Rubber 4-403
Air 4-332 Fixings Sports 4-402–4-403
Dry Arrestance 4-332 Carpentry 4-198 Vinyl Sheet 4-402
Finishes Flagpoles 4-190 Vinyl Tiles 4-401
Concrete 4-143 Flair furniture 4-226 Flooring
Finishings, Carpentry 4-220 Flashings Carpet 3-88
Fire Aluminium 4-295 Comparative Costs 3-72
Alarm 4-351 Copper 4-295 Computer 4-190
Bricks 4-178 Labour constants 5-472 Eulux Timber 4-206
Damper 4-342 Lead 4-296 Granite 3-87
Detector 4-351 Prefinished Steel 4-296 Hardwood 4-206
Doors 4-267 Roof 4-295 Kopine 4-205
Extinguishers 4-349 Stainless Steel 4-295 Laminated Timber 4-241
Hose Reels 4-349 Zincalume Steel 4-295 Linoleum 3-88
Rated Flat Plate Sections 14-648 Marble 3-87
Floor/Ceiling Systems 3-72 Flat Slab 4-157 Parquet 3-88, 4-206
Partitions 4-272–4-274 Comparative Costs 3-75 Particle Board 3-72, 4-205
Performance Systems 3-79 FLC 4-399 Premafloor 4-205
Windows 4-255 Fletcher Wood Panels Pynefloor 3-72, 4-205
Index
2008
G
Page 15-668
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Slate 3-87 Frames, Door 4-257–4-258 Solutions 4-269–4-274, 4-387–4-388
Vinyl 3-88 Framing 4-193 Acoustic Resilient Mount 4-271
Floors Ceiling 4-194 Fire-Rated 4-272–4-274
Comparative Costs 3-72, 3-87 Pergola 4-197 Gib-Rail 4-271–4-272
Fire Rated 3-72 Posts 4-197 Inter-tenancy 4-271
Flues 4-336 Roof 4-195 Sound Barrier 4-391
Flushing Valves 4-300 Studs 4-194, 4-196 -Tone ceiling tiles 4-394
Folding Doors 4-264, 4-266 Wall 4-194 Toughrock 4-391
Folding Shower Seat 4-236 Kiln dried 4-196 Glass
Footings, Comparative Costs 3-65 Freezers 4-436–4-437 Blocks 4-178
Formatube 4-155 Front End Loaders, hire rates 4-451 Reinforced Acrylic Membrane
Formavoid 4-155 Fuel Depot Roofing 4-286
FormBlock® Concrete Blocks 4-180 Building Costs/m2 1-21 Glass. See Glazing
Formceal 4-173 Elemental Costs 2-52 Glasswall, squash 4-254
Form-Flow 4-173 Fume Cupboards 4-438 Glasswool, Bradford 4-204
Formula Funding 4-111 Glazing
Cost indexation 6-499 Furniture Abrasion Resistant 4-415
Prismoidal 14-653 Computer Workstation 4-448 Acrylic 4-416
Formwork 4-150 Ergonomic 4-448 Anti-Bandit 4-414
Ambionse 4-152 Office 4-447–4-448 Bars 4-254
Beams 4-150 Street 4-429 Beads 4-258
Column formers 4-155 Fusiotherm pipe 4-312–4-313 Clear Float Glass 4-413
Columns 4-151 Futurebuild Double 4-413
composite steel permanent 4-153 Hybeam 4-202 Edge Processing 4-416
Formatube 4-155 Hyspan 3-69, 4-202 Figured Glass 4-414
Formavoid 4-155 LVL 4-202 Frameless 4-253
Grooves, rebates 4-151 Portal Frames 3-69, 4-242 Georgian Wired 4-414
Insulform 3-71, 4-152 Insulation 4-416
Labour constants 5-461 G Labour constants 5-474
Metal Tray 4-153 Gables 3-78 Laminated 4-414
Openings 4-155 Galvanising 4-172 Louvres 4-415
Permanent 4-153 Gantry 4-113 Mirrors 4-415
Plywood 4-217 Garage Doors 4-262 Polycarbonate 4-415
Polystyrene 4-152 Garages Safety 4-414
polystyrene 4-152 Building Costs/m2 1-28 Security 4-414
Retarding agent 4-151 Garbage Disposal Unit 4-437 Solar Control 4-414
Ribraft floor system 3-66, 4-152 Gates Toughened 4-414
Slabs 4-151 Automatic 4-433 Glazing Bar System 4-254
Soffits 4-151 General Hospital Glulam
Speedfloor 4-152 Building Costs/m2 1-17 Portal Frames 3-69
Stairs 4-150–4-151 Elemental Costs 2-47 Gobiblock 4-423
Steel Tray 3-73 Genie Hoist, hire rates 4-453 Goods & Services Tax 13-608–13-
Sundries 4-151 Georgian furniture 4-226 614
Superform 3-71, 4-152, 4-276 Geotextile Fabric 4-426 Grab Rails 4-235
Truss 4-152 GFA. See Gross floor area Grades
Types 4-150 Giant Dome acrylic skylight 4-289 of plywood 14-650
Walls 4-150 Gib of timber 14-649
Foundations Ceiling Battens 4-195 Graffiti Protection 4-144
Concrete 4-142 Fibrerock 4-391 Grandstands
Fowler Perimeter Channel 4-195 Building Costs/m2 1-16
WC Pan 4-297 Plasterboard Linings 4-387 Granite 4-182
Fowler fittings 4-298 Acoustic 4-388 Comparative Costs 3-87
Fox Water Diversion Systems 4-327 Double Layer 4-387 Facing 4-182
Framed Doors 4-260 Fire-Rated 4-389, 4-391 Paving 4-182
Frameless Glazing 4-253 -Rail 4-271–4-272 Slab 3-87, 3-90
Index
2008
H
Page 15-669
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Tiles 3-87, 3-90, 4-182 Hardwall Plaster 3-90, 4-386 Hire rates 4-454
Grassing 4-425 Hardware Hot Water 4-314
Grasspaver 4-423 Bolts 4-231 Heating
Grease Ceiling Access Ladders 4-234 Circuits 4-367
Trap 4-327 Curtain Rails 4-237 Coils 4-334
Greens Cylindrical Locks 4-226 Underfloor 4-374
Mixers 4-306 Disposal Bins 4-237 Hebel
Tapware 4-305 Domestic locks 4-226 blocks 4-179
GreenStuf 4-203 Door Closers 4-230 Panel Cladding 4-160
Grilles Door furniture Soundfloor 4-160
Amplimesh 4-191 Flair 4-226 Helicopter Hire 4-124
Louvre 4-191, 4-256 Georgian 4-226 HERA Costing, Steel 4-165
Mechanical Services 4-344 Neptune 4-226 Herring Bone Strutting 4-194
Retractable 4-264 Orbit 4-226 Hi Flo skylight 4-288–4-289
Rolling 4-264 Plymouth 4-226 High Build Acrylic Coating 4-412
Security 4-191 Supply Prices 4-227 Hinges, Supply Prices 4-223
GripBlock 4-428 Door Seals 4-233 Hinuera Stone 4-175–4-176, 4-183
Gross floor area 11-548 Door Stops 4-229 Hippolon 4-218
Ground Slabs Driers Hire
Comparative Costs 3-66 Hair 4-236 Cherry pickers 4-123
Grout 4-180 Hand 4-236 Helicopter 4-124
Steel 4-168 Floor Springs 4-229 Mobile scaffolds 4-123
GST 13-608–13-614 Heated Towel Rails 4-236 Scaffolding 4-123
Gutters Hooks 4-232 Scissor platform 4-123
Labour constants 5-472 Illuminated Signs 4-234 Swinging stage, hire 4-123
Gymnasium Keying 4-226 Historic Places Act 12-599
Building Costs/m2 1-24 Latchsets 4-223, 4-225 Hitex Diamond Cavity 4-279
Elemental Costs 2-56 Locks 4-223, 4-225 Hoardings 4-113, 4-122
Flooring 4-403 Combination 4-224–4-225 Hob
Cylinder Deadbolts 4-226 Electric 4-436
H Cylindrical 4-226 Gas 4-436
H Piles 4-141, 14-645 Deadlocks 4-224 Holding Down Bolts 4-170
Hair Driers 4-236 Electromagnetic 4-228 Holidays and Sick Leave 7-507
Halls of Residence Sliding Door 4-225 Hollow Core Doors 4-259
Building Costs/m2 1-15 Vestibule 4-223, 4-225 Hollow Sections 14-646–14-647
Elemental Costs 2-45 Mortice Hooks 4-232
Hand Driers 4-236 Locks 4-223, 4-225 Horizon seat 4-429
Handles Panic Bolts 4-230 Horizon table 4-429
Pull 4-231 Paper Towel Dispensers 4-237 Hose Reels 4-349
Handrail Pull Handles 4-231 Hospital
Aluminium 4-189 Push Plates 4-231 Call Stations 4-377
Brass 4-189 Safety Rails 4-235 Equipment 4-376, 4-443
Stainless Steel 4-189 Seats 4-236 Hospitals
Steel 4-189 Shower Curtains 4-237 Building Costs/m2 1-17
Timber 4-244 Signs 4-233 Elemental Costs
Tubular 4-189 Soap Dispenser 4-237 District 2-47
Handrails 3-83 Toilet Roll Holders 4-236 Elderly, Critical Care 2-48
Hardboard 3-88 Towel Rails 4-236 General 2-47
Hardibacker 4-207 Window Winding Equipment 4-233 Private 2-47
Hardiflex 4-207 Hardwood Hot
Soffit linings 4-219 Flooring 4-206 Dip Galvanising 4-172
Waterproofing Protection 4-173 Hauling Times 5-490 Water Heaters 4-314
Hardiglaze 4-218 Heat Pump Water Heater 4-315 Water Heating Coils 4-334
HardiGroove™ 4-207 Heated Towel Rails 4-236 Hotbloc 4-179
Hardipanels 4-207 Heaters 4-373, 4-435 Hotel Fit-Out 4-439–4-442
Index
2008
I
Page 15-670
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Hotels Insulated Reception Desk 4-250
Building Costs/m2 1-18 Panel Systems 4-277 Shaving Cabinet 4-249
Elemental Costs 2-50 Panel Walls 4-278 Timber Stairs 4-243
Hourly Insulating Plaster 3-80, 4-279, 4-386 Vanity unit
Paid wage rates 7-504 Insulation Athena 4-302
Rate calculations 7-504 Baffle Block 4-203 Clearlite 4-303
Houses Bradford Gold 4-204 Vanity Units 4-249
Building Costs/m2 1-26 Ceiling 4-203 Whiteboards 4-250
Elemental Costs 2-57 Foil 4-202 Joints
HWC GreenStuf 4-203 Floor/Wall, Fire Resistant 4-421
Solar 4-314 Pipe 4-341 Seismic Fire Resistant 4-421
Wetback 4-314 Wall 4-203 Joists
Hybeam 4-202 Window 4-416 Ceiling 4-194
Hydrant Point 4-349 Insulclad 3-80, 4-279 Floor 4-193
Hydrotap 4-315 Insulform 3-71, 4-152 Hangers 4-201
Hyspan 4-242 Insurance Pergola 4-197
Portal Frames, m2 cost 3-69 Check list 4-110
Contractors All Risk 4-127 K
I indemnity 11-567 Kaimai Stone 4-183
Illuminated Signs 4-234 property 11-567 Kaowool Firemaster 4-421
Imputation credits, tax 13-618 Public Liability 4-127 Keying 4-226
Incinerator 4-450 Rates 4-127 Keystone 4-428
Income Tax 13-608 replacement 11-567 Kilometre rates 4-456
Indemnity insurance 11-567 valuations 11-568 Kitchen
Indexation Formula 6-499 Insurances and Levies 7-507 Equipment 4-441
Indices Interlocking Slat Doors 4-263 Joinery 4-245, 4-247
Adjustment formula 6-499 International costs 9-521–9-535 Sinks 4-303
Base date changes 6-500 estimating rates 9-524–9-535 Kleentech 4-435
Description of per square metre 9-521–9-523 Kopine 4-205
CGPI 6-493 Intumescent Coatings 4-419 Kwila decking 4-205
CPI 6-493 Intumex Supalux board 4-419
LCI 6-493 Invoicing for Levies 7-511 L
PPI 6-493 Ironing Centre 4-247, 4-435 Laboratories
Quarterly, Construction 6-493–6- IRPC Act 2001 7-511 Building Costs/m2 1-24
494, 6-496 Irregular Areas and Volumes 14-653 Elemental Costs 2-55
Recalibrated 6-500 Fit-Out 4-438
Regional 6-501 J Labour
Release dates 6-500 Jack Constants
Tables Rafters 4-195 Blockwork 5-462
CCI 6-494, 6-496 Studs 4-194, 4-196 Brickwork 5-462
CGPI 6-494, 6-497 Studs, sub-floor 4-193 Carpentry 5-467
CPI 6-494, 6-497 James Hardie Concrete 5-460
LCI 6-494, 6-496 Fire and Acoustic Systems 3-72, 4- Demolition 5-458
PPI 6-494, 6-497 274 Downpipes 5-472
Update Service 6-495 Joinery Drainage 5-477
Industrial Roller Doors 4-263 Balustrades 4-244 Electrical 5-478
Injection Anchor 4-141 Bench Tops 4-248 Excavation 5-459
Inseal jointer 4-207 Benches 4-245, 4-247 Flashings 5-472
Insect Fittings Floor Coverings 5-473
Doors 4-268 Demolition 4-131 Formwork 5-461
Screen 4-268 Handrails 4-244 Glazing 5-474
Insol Architectural Louvres 4-255 Kitchen Cupboards 4-245, 4-247 Gutters 5-472
Inspections Labour constants 5-472 Joinery 5-472
Crane 4-125 Notice Boards 4-250 Mechanical Services 5-479
Lift 4-125 Pinboard 4-250 Metalwork 5-466
Index
2008
M
Page 15-671
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Painting 5-474 Goods 4-353 Beams 4-202
Paperhanging 5-474 Handling Capacity 3-99 Floor Joists 4-202
Plumbing 5-474 Passenger 4-352 Lintels 4-202
Reinforcement 5-462 Waiting Interval 3-99 Portal Frames 3-69, 4-242
Roof Coverings 5-472 Lighting 4-365–4-366
Roofing 5-472 Area 4-369 M
Solid Plaster 5-473 Bollards 4-369 Magnagrid 4-395
Steelwork 5-463 Columns 4-371 Management
Suspended ceilings 5-473 Emergency 4-372 Construction 11-556
Tiling 5-473 Luminaires 4-370 Project 11-556
Cost Index, LCI 6-493 Street 4-370 Value 11-577
Rate build up 7-506 Lighting Track 4-369 Manhole Covers 4-326
Labour only Lightweight masonry 4-160, 4-179 Manholes 4-326
Hourly rates 7-504 Linear Manlift 4-453
Square metre rates 7-508 Ceilings 4-396 Marble 4-181
Lacquer Spray Finish 4-406 Diffuser 4-344 Facing 3-90, 4-181
Ladders 4-191 Linoleum 4-401 Paving 4-181
Laminated Comparative Costs 3-88 Slab 3-87, 3-90
Glass 4-414 Lintels Tiles 3-87, 3-90, 4-181
Timber 4-239 Blockwork 4-180 Masonry 4-181
Latchsets 4-223, 4-225 LVL 4-202 Granite 4-182
Lath 4-386 Steel, to brickwork 4-177 Hinuera Stone 4-183
Laundry Equipment 4-435 Timber 4-194 Kaimai Stone 4-183
Lawn 4-425 Liquor Outlets Marble 4-181
Instant 4-425 Building Costs/m2 1-18 Moss Rock 4-184
Lazy ”S” 11-566 Elemental Costs 2-49 Oamaru Stone 4-183
LCC analysis 11-571–11-575 Literock 3-80, 4-386 Paradise Stone 4-183
LCI Litter Bins 4-429 Schist 4-183
Description 6-493 Locker Slate 4-183
Tables 6-494, 6-496 Bedside 4-444 Terrazzo 4-184
Lead Flashings 4-296 Changing Room 4-191 Master keying 4-226
Legge Pacific locks 4-223, 4-225 Lockfast FLC 4-399 MasterSpec® Systems 11-546
Legislation Locks Mastic Asphalt
Acts of Parliament 12-579 Cylinder Deadbolts 4-226 Roofing 4-285
Arbitration Act 12-587 Cylindrical, Domestic 4-226 Mats 3-88, 4-404
Building Act 12-590 Electromagnetic 4-228 Coir 4-404
Construction Contracts Act 12-603 Mortice, Commercial 4-223, 4-225 Rubber 4-404
Employment Relations Act 12-596 Vestibule 4-223, 4-225 Mattresses, hospital 4-443
Historic Places Act 12-599 Loft Ladder 4-234 MATV 4-379
Resource Management 12-600 Louvre Matwell Frames 4-404
Levies 4-110 Blades, glass 4-415 Matwells 3-88
Building 4-125 Doors 4-260 Maxilite 4-284
Building Research 4-125 Grilles 4-191, 4-256 MCB’s 4-376
Reserves Contribution 4-125 Inlet 4-345 MDF
Levy Year 7-511 Sun shades 4-255 Comparative Costs 3-89
Library Windows 4-256 Measurement
Building Costs/m2 1-11 Lumberlok 4-198 methods of 11-548
Elemental Costs Luminaires Measures 14-653
Public 2-39 Emergency 4-372 Meatworks
Tertiary 2-45 Fluorescent 4-367 Building Costs/m2 1-24
Life cycle costing 11-571–11-575 Industrial 4-369 Mechanical Services 4-342–4-344
Lift Wide Beam 4-369 Air Filters 4-332
Inspections 4-125 Lump sum tender 11-553 Air Handling Unit 4-331
Lifts Luxalon ceilings 4-396 Console Units 4-329
Comparative Costs 3-99 LVL Cooling Coils 4-334
Index
2008
N
Page 15-672
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Cooling Load 4-329 Labour constants 5-466 Building Costs/m2 1-11
Cooling Towers 4-333 Ladders 4-191 Elemental Costs 2-39
Diffusers 4-344 Lockers 4-191 Music System 4-380
Ducted Split System 4-330 Stairs 4-189
External Units 4-329 Sunscreens 4-191 N
Fan Coil Units 4-331 Meter Nail Plates 4-198
Fans 4-331 control equipment 4-375 Negotiation
Flues 4-336 Methven competitive 11-554
Grilles 4-344 Mixers 4-306 direct 11-553, 11-555
Heating Coils 4-334 Tapware 4-305 Neptune door furniture 4-226
Hot Water Boilers 4-335 Micro-Tunnelling Nirvana 4-159
Hydronic Air Conditioning Systems Drainage 4-318 Nogging
4-330 Mild Steel Floor 4-193
Labour constants 5-479 Angles, weights 14-646 Herring Bone 4-194
Non Ducted Split System 4-329 Bolts 4-169 Wall 4-194, 4-196
Pipe Insulation 4-341 Mileage rates 4-456 Non-complying activities
Pipework 4-338 Miniature Circuit Breakers 4-376 Resource Management 12-600
Pumps 4-336 Mirror Tiles 4-415 Notice Boards 4-250
Room Air Conditioners 4-329 Mitech Nova membrane
Split System 4-329 Carpet film 4-130 Comparative Costs 3-76
Three Phase Split System 4-330 Window film 4-130 Nova Metal Coated Membranes
Valves 4-340 Mixers 4-306 Roofing 4-286
Water Chillers 4-333 Feltonmix 4-306 Novabit
Medium Density Fibre Board 3-89 Greens 4-306 Comparative Costs 3-76
Membrane Methven 4-306 Novabond 4-286
Box Gutters 4-292 Mobile Novalok 4-277
Roofing 4-286 Cranes 4-119 Novater 200 4-174
Mensuration 14-652 Scaffolds 4-123 Nuplex
Mercer Mondo Volley 4-403 Lockfast FLC 4-399
Shower bases 4-302 Mondoflex 4-403 Supascreed 4-410
Mesh Mondosport 4-403 Sureshield 4-410
Reinforcing 4-162 Monier bricks 4-175 Terratuff 4-410
Mesh/Rod Equivalents 14-649 Monokote 4-418 Nurse Call Button 4-377
Metal Mortar Nuthane floor finish 4-410
Bracing 4-199 Cavity filling 4-176 Nu-Wall aluminum cladding 4-216
Lath 4-386 Coloured 4-176 NZS3910
Roof Tiles 4-283 Mortice Indexation formula 6-499
Strip Ceilings 4-396 Locks 4-223, 4-225
Tiles, roofing 4-283 Mosaic Tiling 4-398 O
Metalspray 4-171 Moss Rock 4-184 Oamaru Stone 4-183
Metalwork Motels Office
Access Floors 4-190 Building Costs/m2 1-19 Fitout, Reception Desk 4-250
Amplimesh 4-191 Elemental Costs 2-50 Storage Systems 4-449
Angles 4-187 Motor Starters 4-375 Office Building
Awnings 4-187 Motor vehicle Building Costs/m2 1-22
Bed Screens 4-438 Reimbursement rates 4-456 Elemental Costs 2-35, 2-53
Bench Supports 4-189 Mouldings Open Cell Ceilings 4-395
Brackets 4-189 Eaves 4-220 Openings
Cladding 4-190 Scriber 4-220 Cutting 4-130
Column Guards 4-187 Timber, exterior 4-220 Forming 4-130
Computer Flooring 4-190 Mudstop 4-426 Operable
Curtain Tracks 4-438 Mulch 4-425 Doors 4-266
Cycle Racks 4-187 Mulseal 4-173 Wall 4-266
Flagpoles 4-190 Multitone 4-411 Operating costs 11-569
Grilles 4-191 Museum Opus CCI (discontinued) 6-493
Index
2008
P
Page 15-673
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Orbit furniture 4-226 Fire Rated 4-272–4-274 Timber 4-137
Oven 4-436 Folding Operable Bored 4-138
Overseas Trade Indexes 14-659 Wall 4-266 Driven 4-137
Gib 4-269–4-274, 4-387–4-388 Pillows, fire resistant 4-420
P Acoustic Resilient Mount 4-271 Pinboard 4-250
Paging 4-379 Fire-Rated 4-272–4-274 Pipework
Painting 3-89 Gib-Rail 4-271–4-272 Aluminium, culvert 4-432
Acrylic 4-406–4-408 Inter-tenancy 4-271 Climatherm 4-339
Bus lane surfaces 4-422 Toilet 3-84, 4-276 Concrete
Ceilings 4-407 Resco 4-276 RRJ 4-322
Enamel 4-406–4-407 Patient Trolleys 4-444 Sewer 4-321–4-322
Exterior 4-408 Pavers Copper
Interior 4-406–4-407 Brick 4-423 Mechanical 4-339
Labour constants 5-474 Concrete 4-423 Culvert 4-432
Lacquer Spray 4-406 Paving 3-101 Earthenware
Metal Roofing 4-408 Break up and remove 4-133 Sewer 4-320
Metalwork 4-407 concrete sub-base 4-422 Fusiotherm 4-312–4-313
Paper Hanging 4-409 Granite 4-182 HVAC, Climatherm 4-339
Polyurethane 4-406 Grasspavers 4-423 Insulation 4-341
Preparation 4-408 Marble 4-181 Mechanical Services 4-338
Silicone Water Repellent 4-407 Slate 4-183 Polyethylene
Specialist Finishes 4-410 PAYE tax 13-617 Drawn 4-318
Stain 4-406, 4-408 PCP Concrete Spacers 4-162 PVC
Timber 4-406 Pegboard Sewer 4-318
Walls 4-407 Wall Linings, Carpentry 4-218 Stormwater 4-323
Weather Boards 4-408 Perforated Soil
Palliside Weatherboards 4-216 Cladding 4-190 Copper 4-308
Panectric Heating Panels 4-393 Foil 4-202 PVC 4-309
Panelled Doors 4-259 Performance Bond 4-110 Steel
Panic Bolts 4-230 Permaliner 4-173 Mechanical 4-338
Pantry Unit 4-246 Permanent Formwork 4-153 Sprinkler 4-350
Paper Hanging 4-409 Permitted activities Water 4-311
Comparative Costs 3-90 Resource Management 12-600 Water
Paper Towel Dispensers 4-237 Petrol station Agricultural 4-312
Paperhanging Building Costs/m2 1-30 Copper 4-310
Labour constants 5-474 Photographs 4-113 Fusiotherm 4-312–4-313
Paradise Stone 4-183 Picnic seat 4-429 Polybutylene 4-311
Parapet Walls 3-78 Piers, Blockwork 4-180 Steel 4-311
Parex flushing valve 4-300 Pilasters 4-180 Planking, Strutting 4-136
Parking Pile Connectors 4-199 Plant
Building Costs/m2 1-23 Piles, H, weights of 14-645 Usage factors 5-484
Elemental Costs 2-54 Piles. See Piling Plant Hire Calculation 4-455
Equipment 4-433 Piling Plant Hire Rates 4-451
Vertical stack 4-433 Concrete 4-139 Front End Loaders 4-451
Parking Buildings Concrete, driven 4-139 Rollers 4-451–4-452
Building Costs/m2 1-23 Concrete, insitu, bored 4-139 Planting 4-425
Parquet Flooring 3-88, 4-206 Drilling 4-137 Plaster 3-91
Particle Board 3-72, 3-88 H piles 4-141 Cement 3-90, 4-384
Comparative Costs 3-72 Injection anchor 4-141 Comparative Costs 3-90
Flooring 4-205 Pre-stressed 4-139 Dryvit 3-80, 4-279
Kopine 4-205 Sheet Fibrous 3-89, 4-393
Pynefloor 3-72, 4-205 Comparative Costs 3-64 Finishing 3-80, 4-279
Partitions Soil nails 4-141 Hardwall 3-90, 4-386
Acoustic 4-270–4-271, 4-276 Steel sheet 4-140 Hitex 4-279
Comparative Costs 3-84 Steel, driven 4-141 Insulating 3-80, 4-279, 4-386
Index
2008
P
Page 15-674
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Insulclad 3-80, 4-279 Urinal To floors 4-207, 4-401
Proprietary systems 4-386 Cisterns 4-299 Pool Safety Fences 4-427
Rockcote 3-80, 4-279, 4-386 Flushing valve 4-300 Portal Frames
Thermaclad 3-80, 4-279 Urinals 4-299 Comparative Costs 3-69
Thermaplast 4-386 Valves, flushing 4-300 GluLam 3-69
Tyrolean 3-90, 4-385 W.C. Laminated Timber 4-242
Plasterboard 4-387 Pans 4-297 LVL 3-69, 4-242
BPB 4-388 Slop Hopper 4-297 Posi-Strut Trusses 4-201
Comparative Costs 3-89 Suites 4-298 Post
Gib 4-387–4-389, 4-391 Water Tanks 4-313 Anchor Base 4-199
Gib Solutions 4-269–4-274, 4-387– Plymouth furniture 4-226 Bracket 4-199
4-388 Plywood 3-88, 4-217 Post Offices
Acoustic Resilient Mount 4-271 Cedar Ply 4-217 Building Costs/m2 1-12
Fire-Rated 4-272–4-274 Comparative Costs 3-89 Posts
Gib Rail 4-271–4-272 Decorative 4-217 Laminated Timber 4-241
Inter-tenancy 4-271 Exterior Grade, H3 4-217 Pergola 4-197
Plate Flooring 4-205 Timber 4-197
Connections 4-165 Formwork 4-217 Poultry shed 1-30
Wall 4-194, 4-196 Grades, explained 14-650 Power circuits 4-366–4-367
Plumbing Interior Grade 4-217 PPI
Basins 4-302 Shadow Clad 4-217 Description 6-493
Baths 4-300 V-Grooved 4-217 Tables 6-494, 6-497
Bidets 4-298 Pneumatic Tube System 4-433 Precast Concrete 4-157
Caroma fittings 4-297–4-299 Poles, timber 4-138 Beams 4-158
Cisterns 4-299 Polibit Flat Slab 4-157
Cleaners Sink 4-303 Box Gutters 4-292 Floors 4-157
Cocks 4-305 Roofing 4-286 Freezer/chiller panels 4-159
Comparative Costs 3-92 Police Station Nirvana 4-159
Disposal Units Building Costs/m2 1-12 Prestressed Floor 4-157
Diaper 4-304 Elemental Costs 2-40 Stair Treads 4-159
Sanitary 4-304 Polybutylene Pipework, Water 4-311 Stairs 4-158
Drinking Fountain 4-304 Polycarbonate Thermomass 4-159
Dux fittings 4-299 Blocks 4-178 Tilt-Up 4-160
Flushing Valves 4-300 Glazing 4-415 Wall Panels 4-159
Fowler fittings 4-298 Polyethylene Pipework 4-318 Prefinished Steel
Hot Water Heaters Polyflow® 4-173 Cladding 4-287
Electric 4-314 Polyfoam S 4-203 Flashings 4-295
Gas 4-314 Polygum 3mm 4-174 Rainwater Heads 4-287
Kitchen Sinks 4-303 Polyjute 4-426 Valley Gutters 4-292
Labour constants 5-474 Polypropylene Preliminaries 3-102
Mixers 4-306 Hippolon lining 4-218 ACC Premiums 7-511
Pumped Waste System 4-300 Tanking Membrane 4-173 Building Levy 4-125
Sanitary Disposal Units 4-304 Polyrock 4-135 Building Research Levy 4-125
Saunas 4-304 Polystyrene Check list 4-110
Shower Bases 4-301 Ceiling Finish 4-411 Crane hire 4-119
Sink Extruded 4-152, 4-203 Divers 4-124
Cleaner 4-303 Fill 4-135 Helicopter hire 4-124
Kitchen 4-303 Formwork 4-152 Hoardings 4-122
Spa Insulform 3-71 Inspections, crane 4-125
Baths 4-301 Superform 3-71, 4-276 Inspections, lift 4-125
Pool 4-304 Ribraft floor system 3-66, 4-152 Insurance 4-127
Taps 4-305 Waterproofing Protection 4-173 Reserves Contribution 4-125
Toilets 4-297 Polystyrene block formwork 4-152 Scaffolding 4-123
Traps 4-307 Polyurethane Site accommodation 4-122
Tubs 4-303 Finish 4-406 Temporary power 4-121
Index
2008
Q
Page 15-675
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Temporary services 4-121 PVC Labour constants 5-462
Preliminary Design 11-543 Conduit 4-361 Lattice 4-177
Preparation, Painting 4-408 Downpipes 4-294 To blocks 4-180
Preparatory Work 4-131 Pipework To brickwork 4-177
Pressed Steel Tiles 4-283 Sewer 4-318 Reinforcing Steel 4-161, 14-649
Pressurisation, Stairs 3-94 Soil 4-309 Supply Prices 4-161
Prestressed Flooring 4-157 Stormwater 4-323 Weights 14-649
Primary Industry Slotted Drains 4-324 Release dates, indices 6-500
Building Costs/m2 1-24 Strip Doors 4-265 Renovations
Elemental Costs 2-55 Tanks 4-313 Building Costs/m2 1-22
Primary School Traps 4-307 Rentable floor area 11-548
Building Costs/m2 1-14 Waterstop 4-145 Rental values 8-515
Elemental Costs 2-42 Pynefloor 4-205 carparks 8-515
Priming Comparative Costs 3-72 industrial 8-516
Steel 4-171 Pyramid acrylic skylight 4-288 offices 8-516
Prismoidal Formula 14-653 Pyrosleeve fire collars 4-420 residential 8-515
Producers Price Index 6-493 retail 8-516
Production Facilities Q Replacement insurance 11-567
Building Costs/m2 1-16 Quadrant stay 4-232 Resco Toilet Partitions 4-276
Productive Hours 7-505 Quarterly Construction Indices 6- Research Centre
Professional fees 11-576 494, 6-496 Building Costs/m2 1-24
Programming 4-110 Quartz Chip 4-286 Elemental Costs 2-55
Prohibited activities Quiet Stud 4-270 Reserves Contribution 4-110, 4-125
Resource Management 12-600 Residential
Project management 11-556 R Building Costs/m2 1-26
Promenade seat 4-429 Rafters 4-195 Elemental Costs 2-58
Property Council 11-548 Hip 4-195 Residual Current Device 4-376
Proprietary Wall Cladding 4-280 Jack 4-195 Resin Bonded Slate Roofing 4-284
Protection 4-130 Valley 4-195 Resource Management Act 12-600–
Cable 4-361 Rails 12-602
Carpet film 4-130 Curtain 4-237 Retail
Membrane Roofing 4-286 Grab 4-235 Building Costs/m2 1-29
Mitech film 4-130 Heated Towel 4-236 Elemental Costs 2-60
Waterproofing 4-173 Safety 4-235 Retail Fit-Out 4-446
Window film 4-130 Towel 4-236 Retaining Walls 4-428
Psychiatric Unit Rainwater Heads 4-291 Retarding Agent 4-151
Building Costs/m2 1-17 Range Hood 4-437 Retentions 11-559
Public toilets Rates Formula 14-651
Building Costs/m2 1-30 Charge out 7-503, 7-505 Retractable Grilles 4-264
Pull Handles 4-231 Contract 7-505 Revolving Doors 4-261
Pumped Waste System 4-300 Daywork 7-505 Reynobond 4-280
Pumping Labour build up 7-506 Ribraft floor system 3-66, 4-152
Concrete 4-143 Labour only 7-504 Ridge Beams 4-195
Pumps Tender 7-505 Ridge Board 4-195
Baseplate Centrifugal 4-337 Wage 7-503–7-504 Riotone 4-218
Glandless 4-336 Ratios, labour to material 5-491 Rising butt hinge 4-223
Hire rates 4-454 Raven door seals 4-233 River Gravel 4-286
Inline Centrifugal 4-337 Reception Desk 4-250 Road
Mechanical Services 4-336 Recreation Paving 4-432
Submersible Sump 4-337 Building Costs/m2 1-24 Road Marking 4-422
Purlins Refrigerant Cooling Coils 4-334 Roading 3-101
Dimond Hi Span 4-168 Refrigerators 4-436 Roadworks 4-431
Steel 4-168 Refurbishment 4-129 Rock Excavation 4-431
Timber 4-196 Regional indices 6-501 Rockcote 3-80, 4-279, 4-386
Push Plates 4-231 Reinforcement Rods, reinforcing 4-161–4-162
Index
2008
S
Page 15-676
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Roller Roofing Ceilings 4-396
Blinds 4-256 Labour constants 5-472 Screens
Doors Rooflights 4-290 Comparative Costs 3-84
Domestic 4-262 Acrylic 4-288–4-289 Insect 4-268
Industrial 4-263 Glass 4-290 Temporary 4-129
Shutter Doors 4-263 Rotary Hoeing 4-425 Scriber 4-220
Rollers, hire rates 4-451–4-452 Round and Square Bars 14-645 Seals
Rolling Grilles 4-264 Rubber Door 4-233
Rondo® Quiet Stud 4-270 Flooring 4-403 Seat
Roof Mats 4-404 Avenue 4-429
Comparative Costs 3-70 Slab Underlay 4-400 Horizon 4-429
Drains 4-293 Rubbish bins 4-429 Picnic 4-429
Painting 4-408 Rural Buildings Promenade 4-429
Trusses 4-200 Building Costs/m2 1-30 Strand 4-429
Steel 4-164 Dairy 1-30 Seats 4-236
Underlay 4-202 Poultry 1-30 Secondary School
Ventilators 4-293 Rusticated weatherboards 4-216 Building Costs/m2 1-14
Windows 4-288 RWT 13-618 Elemental Costs 2-42
Roof Coverings 4-291–4-292 Sectional Overhead Doors 4-264
Acrylic Membranes 4-286 S Security 4-445
Aluminium 4-281 S Curve 11-566 Disintegrator 4-450
Bituminous Membranes 4-286 Safes 4-445 Doors 4-268
Box Gutters 4-292 Fire Resistant 4-445 Glass 4-414
Butyl Rubber Membrane 4-285 Safety Grilles 4-191
Butynol Rubber 4-284 Glass 4-414 Screens 4-268
Concealed Gutter 4-291 Mirror 4-415 Store Anti-Theft Device 4-438
Concrete Tiles 4-283 Rails 4-235 Systems 4-381
Deck Membranes 4-286 Sample Calculations 7-504 Seismic
Downpipes 4-294 Sand Floor Joints, Fire Resistant 4-421
Eaves Gutters 4-292–4-293 Bedding 4-422 Joint covers 4-149
Flashings 4-295 Blinding 4-136 Self Employed Persons 7-511
Glass Reinforced Acrylic Filling 4-136 Self Seal 4-174
Membrane 4-286 Sanding Floors 4-207 Septic Tanks 4-327
Gutters 4-292–4-293 Sani-plus waste system 4-300 Service Mains 4-356
Labour constants 5-472 Sanitary Disposal Units 4-304 Services
Mastic Asphalt 4-285 Sani-top 4-300 Temporary 4-121
Metal Coated Membranes 4-286 Sani-Vite 4-300 Sewer Drains
Polibit 4-286 Sarking 4-217 Earthenware 4-320
Protection 4-286 Sashless Sliding Windows 4-252 PVC 4-318
Rainwater Heads 4-291 Saunas 4-304 Shadow Clad 4-217
Resin Bonded Slate 4-284 Scaffolding 4-123 Shakes 4-284
Shakes 4-284 Schedules of quantities 11-548 Shaving Cabinets 4-249
Shingles 4-284 Schist 4-183 Shear Connectors 4-153, 4-170, 4-
Cedar 4-284 Schlage 4-226 172
Certainteed 4-284 Schools Sheet Piling 4-140
Fibreglass 4-284 Building Costs/m2 1-14 Comparative Costs 3-64
Oberon 4-283 Elemental Costs Sheetmetal Cladding 4-190
Slate 4-284 Auditorium 2-43 Shell Beams 4-158
Steel 4-281 Classrooms 2-42 Shelterbit 4-174
Colorsteel 4-281–4-282 Dormitory 2-43 Shelterseal 4-174
Translucent 4-284 Gymnasium 2-43 Shelving
Trapezoidal 4-282 Laboratories 2-42 Cold Store 4-277
Trough 4-282 Scissor Platform Hire 4-123 Coolroom 4-277
Underlay 4-287 Screeds, floor 4-398 Office 4-449
Valley Gutters 4-292 Screen Storage 4-449
Index
2008
S
Page 15-677
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Shingles 4-284 Carpet 4-403 Anti-Dusting 4-410
Cedar 3-76, 4-284 Vinyl 4-403 Ceilings 4-411
Certainteed 4-284 Skylights Chemical Resistant 4-410
Concrete roof 4-283 Acrylic 4-288–4-290 Floors 4-410
Fibreglass 4-284 Acrydome 4-289 High Build Acrylic 4-411–4-412
Oberon Metal 4-283 Giant Dome 4-289 Modified Plaster 4-412
Roofing Hi Flo 4-288 Slip Resistant 4-410
Comparative Costs 3-76 Pyramid 4-288 Tridek 4-411
Shiplap weatherboards 4-216 Superdome 4-289 Vinyl emulsion 4-411
Shop Tubelight 4-289 Walls 4-411–4-412
Elemental Costs 2-60 Adlux 4-288–4-289 Whisper 4-411
Fronts 4-253 Glass 4-290 Zolatone 4-411
Comparative Costs 3-81 Velux 4-290 Specialist Fittings
Surveillance System 4-438 Slabs Appliances
Shopping Centre Concrete 4-142 Domestic 4-436
Building Costs/m2 1-29 Slate 4-183 Bank Fit-Out 4-438
Elemental Costs 2-60 Comparative Costs 3-87 Catering Facilities 4-434
Shops Paving 4-183 Chutes 4-450
Building Costs/m2 1-29 Roofing 4-284 Cleaning, Waste Disposal 4-450
Shoring 4-136 Tile, Comparative Costs 3-76 Combustion Heaters 4-435
Shower Slide Over Doors 4-264 Compactors 4-450
Bases 4-301 Sliding Document Transport 4-433
Curtains 4-237 Door Locks 4-225 Dormitory Fit-Out 4-438
Mixers 4-306 Door Track 4-229 Garbage Disposal Unit 4-437
Roses 4-306 Doors 4-261 Hospital 4-443
Sliding 4-306 Slip Resistant Floor Coatings 4-410 Hotel Fit-Out 4-439–4-442
Trolley 4-444 Smooth edge 4-400 Incinerator 4-450
Shrubs 4-425 Soap Dispenser 4-237 Laundry Equipment 4-435
Shugg Windows 4-252 Sockets 4-373 Nursing Home 4-443
Shutters Soffit Office Furniture 4-447–4-448
Clearspan 4-265 Bearers 4-196 Office Storage Systems 4-449
Industrial Roller 4-263 Linings 4-219 Parking Equipment 4-433
Interlocking Slat 4-263 Softboard Retail 4-446
Signboard 4-111 Waterproofing Protection 4-173 Safes 4-445
Signs 4-233 Soil Security 4-445
Illuminated 4-234 Control Fabrics 4-426 Security Disintegrator 4-450
Silicone Water Repellent 4-407 Stablisation 4-426 Specifications
Silkline soffit linings 4-219 Solar Water Heater 4-314 MasterSpec® 11-546
Sills Solid Core Doors 4-259 Spectator Stand
Blockwork 4-180 Solid Plaster Building Costs/m2 1-16
Brick 4-177 Labour constants 5-473 Speedfloor 4-152
Simpson's Rule 14-653 Sopralene Flam Unilay 4-286 Sportflex
Site Soprasun 4AR 4-286 Tennis 4-425
Buildings, temporary 4-122 Sound Barrier flooring underlay 4- Sports
Clearance 391 Flooring 4-402–4-403
Comparative Costs 3-64 Soundfloor, Hebel 4-160 Surfaces 4-424
Meetings 4-111 South Pacific Waterless 4-299 Sprayed
Offices 4-122 Spa Concrete 4-156
Preparation 3-64, 4-133 Baths 4-301 Finishes 4-410
Comparative Costs 3-64 Pool 4-304 Spraymix supply prices 4-156
Services 4-121 Spacers, reinforcing, PCP 4-162 Spring hinge 4-223
Situclad 4-411 Spandome, see Adlux 4-288–4-289 Springs, Floor 4-229
Situflex 4-411 Spandrel Panel, Window 4-253 Sprinkler Systems 4-350–4-351
Situglaze 4-411 Specialist Finishes 4-410 Spur fastener 4-232
Skirting Acid Resistant 4-410 Squash Court Glasswall 4-254
Index
2008
T
Page 15-678
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Squash Courts Strand seat 4-429 Metalwork 4-185
Building Costs/m2 1-25 Strapping 4-197 Reinforcing Steel 4-161
Squat style WC pan 4-297 Street Structural Steel 4-163
Stack bond 4-176 Lighting 4-370 Structural Steelwork 4-163
Stain Finish 4-406, 4-408 Lighting Columns 4-371 Timber 4-192
Stainless Steel Street Furniture Supply Register 4-345
Angle Guards 4-187 Litter bins 4-429 Surechem 4-410
Bolts 4-169 Seats 4-429 Surecoat 500AR 4-410
Ceiling tiles 4-396 Tables 4-429 Sureshield 4-410
Downpipes 4-294 Strongroom Door 4-445 Surface
Flashings 4-295 Structural Steelwork 4-163 Hardeners 4-144
Handrails 4-189 Abrasive Blast 4-171 Treatments
Stair Bolts 4-169 Structural Steel 4-171
Tread Nosings 4-405 Chequer Plate 4-172 Subgrade 4-431
Treads, Concrete 4-159 Connections 4-165 Surgery
Stairs 4-189 Decking 4-172 Building Costs/m2 1-17
Comparative Costs 3-82 Galvanising 4-172 Surveyor 4-111
Concrete 4-143 Grouting 4-168 Suspended
External, timber 4-197 HERA costing 4-165 Ceilings 4-394
Pressurisation 3-94 Metalspray 4-171 Labour constants 5-473
Pull Down 4-234 Priming 4-171 Slabs, concrete 4-142
Spiral 3-83 Purlins 4-168 Swelltite 4-173
Spiral, steel 4-189 Roof Trusses 4-164 Swimming Pools
Steel 4-164, 4-189 Stairs 4-164 Building Costs/m2 1-25
Terrazzo treads 3-82 Supply and Erect 4-164 Swing Doors 4-265
Starmix Tapware 4-306 Supply Prices 4-163 Swinging Stage 4-123
Steam Heating Coils 4-334 Surface Treatments 4-171 Switchboards 4-358–4-359
Steel Tie rods 4-168 Switchgear, high voltage 4-356
Angle Guards 4-187 Universal Beams 4-164 Synagogue
Box Gutters 4-292 Universal Columns 4-164 Building Costs/m2 1-28
Conduit 4-361 Weights 14-645 Syntex 4-426
Downpipes 4-294 Welded Sections 4-164 Synthetic Turf 4-424
Formwork 3-73 Welding 4-168
Pipework Structural Walls T
Mechanical 4-338 Comparative Costs 3-71 Table
Water 4-311 Stud welding 4-153, 4-170, 4-172 Diaper Changing 4-236
Reinforcing Studio Tables
Detailed Prices 4-161 Building Costs/m2 1-16 Street Furniture 4-429
Roof 4-281 Studs 4-194, 4-196 Tables, Bedside 4-444
Roofing Styrofoam 4-152, 4-203 Tanking 4-173
Colorsteel 4-281–4-282 Subgrade 4-135, 4-422 Comparative Costs 3-66
Comparative Costs 3-76 Submains Sizing 3-98 Tanks
Valley Gutters 4-292 Sumps, Drainage 4-325 Concrete 4-313
Wall Cladding, Colorsteel 4-287 Sunscreens 4-191, 4-255 PVC 4-313
Windows 4-254 SuperBrace 4-217 Septic 4-327
Steelspan 900 4-282 Superdome acrylic skylight 4-289 Water 4-313
Steelwork Superform 3-71, 4-152, 4-276 Taps 4-305
Labour constants 5-463 Supermarket boiling water 4-315
Stirrups 4-161 Building Costs/m2 1-29 Greens 4-305–4-306
Stockpile Excavated Material 4-430 Elemental Costs 2-60 Methven 4-305–4-306
Stone Walls 4-184 Supply Prices Tarpaulin, hire rates 4-454
Stone. See Masonry Concrete 4-142 Taverns
Storage Systems 4-277 spraymix 4-156 Building Costs/m2 1-18
Stove 4-436 Door Furniture 4-227 Elemental Costs 2-49
Stove Hood 4-437 Hinges 4-223 Tax
Index
2008
T
Page 15-679
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Capital Gains 13-618 Tender Rubber 4-403
Depreciation 13-621 competitive negotiation 11-554 Screeds 4-398
Building fitout 13-627 construction management 11-555 Slate 4-183
Buildings and Structures 13-626 design and build 11-555 Terrazzo 4-184
Computers 13-634 direct negotiation 11-555 Vinyl 4-401
Contractors, Builders and documentation 11-544 Wall 4-397
Quarrying 13-630 lump sum 11-553 Weather Bars 4-399
Furniture 13-631 open 11-553 Tiling
Hotels, motels, cafes 13-638 selected 11-553 Labour constants 5-473
Laundry 13-637 traditional system 11-553 Tilting Doors 4-262
Office Equipment 13-631 types of 11-544, 11-553 Timber 3-75
Residential Rental Property Tender or Contract Rate 7-505 Boarding 3-91, 4-217
Chattels 13-640 Tennis Courts Door Frames 4-257
Shops 13-635 Building Costs/m2 1-25 Doors 4-259
Tanks and Vats 13-633 Terraflake 4-410 Flooring 4-206
Dividend Imputation 13-618 Terraflex 4-286 Flooring, Eulux 4-206
FBT 13-617 Terratuff 4-410 Floors 3-72
Fringe Benefit 13-617 Terrazzite 4-410 Framed Roof
Goods & Services 13-608–13-614 Terrazzo 4-184 Comparative Costs 3-69
Income 13-608 Stair Treads 4-184 Infill Flooring 4-157
Land Sales 13-608 Terrier Insert 4-198 Laminated
PAYE 13-617 Tertiary Institutions Beams 4-239
Withholding 13-618 Building Costs/m2 1-15 Flooring 4-241
WoF’s, Buildings 13-616 Tertiary Lecture Theatre Portal Frames 4-242
Tecstop levelling plaster 4-386 Elemental Costs 2-44 Posts 4-241
Telephone Testing Piles 4-137
Circuits 4-378 Concrete 4-143 Bored 4-138
Connections 4-121 TG&V timber boarding 4-217 Driven 4-137
Rentals 4-121 Theatres Pole Retaining Wall 4-428
Temporary 4-121 Building Costs/m2 1-16 Stairs 4-243
Telephones Thermaclad 3-80, 4-279 Strapping 4-197
Broadband connection 4-121 Thermaplast insulating plaster 4-386 Stress Grading 14-649
Television Thermomass 4-159 Supply Prices 4-192
Antenna 4-379 Tie rods 4-168 Walls
Antenna Cable 4-379 Ties Framed 3-77
Closed Circuit 4-383 Cavity 4-177 Windows 4-251
Television studio Collar 4-195 Cedar 4-251
Building Costs/m2 1-16 To brickwork 4-177 Colonial Style 4-251
Tempaclad Glass 4-414 Veneer 4-177 Pine 4-251
Tempascreen Glass 4-414 Tiles Timber Infill Flooring
Temporary Anti-Static 4-401 Comparative Costs 3-75
Buildings 4-122 Carpet 4-401 Timberbond 4-241
Canopies 4-122 Clay roof 4-283 Time
Drainage 4-112 Concrete roof 4-283 switches 4-375
Electrical 4-121 Cork 4-401 Toilet
Fences 4-122 Division Strips 4-399 Pans 4-297
Plumbing 4-112 Floor 4-398 Partitions 3-84, 4-276
Power 4-112 Granite 4-182 Roll Holders 4-236
Protection 4-130 Marble 4-181 Screens
Roading 4-112 Metal roof 4-283 Comparative Costs 3-84
Screens 4-129 Mirror 4-415 Seats 4-298
Services 4-121 Mosaic 4-397–4-398 Site, temporary 4-123
Telephones 4-112, 4-121 Pressed Steel 4-283 Slop Hopper 4-297
Toilets 4-123 Roofing Suites 4-298
Water 4-112 Comparative Costs 3-76 Tongue And Groove Flooring 4-206
Index
2008
U
Page 15-680
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Top Soil 4-133, 4-425, 4-430 Twinaplate 4-201 Vertical Boarding 4-217
In layers 4-425 Tylok 4-198 Vertical Stack Parking 4-433
TorkT-Box Mini 4-236 Tyrolean Plaster 4-385 Vertiface 4-409
Toughrock 4-391 Comparative Costs 3-77, 3-90 Vestibule Locks 4-223, 4-225
Towel Rails 4-236 Villaboard 4-207
Heated 4-236 U Soffit linings 4-219
Tower Cranes 4-120 U Bolts 4-170 Villeroy & Boch 4-298
Town Hall UB’s, UC’s, H Piles, RSJ’s 14-645 Vinyl 3-88
Building Costs/m2 1-11 Underfloor Heating 4-374 Sheet 3-88, 3-90, 4-402
Elemental Costs 2-38 Underlay 4-287 Skirting 4-404
Townhouses Carpet 4-400 Tiles 4-401
Building Costs/m2 1-27 Gib Bedrock 4-391 Volclay 4-173
Trade Ratios 5-491 Paving 4-422 Voltex 4-173
Traffic Roof 4-202
Detector 4-433 Underpinning W
Transformers 4-356 Comparative Costs 3-64 W.C.
Hire Rates 4-453 Underpurlins 4-195 Pans 4-297
Translucent Universities Slop Hopper 4-297
Cladding 4-284 Building Costs/m2 1-15 Suites 4-298
Roofing 4-284 Updates, indices 6-495 Waffle back underlay 4-400
Trapezoidal Roofing 4-282 UPS 4-372 Wage Rates 7-503
Trapezoidal Rule 14-653 Urinal Wall
Traps 4-307 Cisterns 4-299 Claddings 4-287
Drainage 4-327 Flushing valves 4-300 Colorcote 4-287
Grease 4-327 Stainless Steel 4-299 Colorsteel 4-287
Grit 4-327 Vitreous China 4-299 Transparent 4-284
Oil 4-327 Waterless 4-299 Coatings 4-411–4-412
Traydek 3-73 Usage factors, plant 5-484 Hygiene Quality 4-411
Treatments Coverings 4-409
Concrete 4-144 V Fabrics 4-409
Structural Steel 4-171 Vacuum Cleaning System 4-450 Linings 3-89
Subgrade 4-431 Valley Boards 4-195 Papering 4-409
Tree Removal 4-133 Valley Gutters 4-292 Tiling 4-397
Trees 4-425 Value management 11-577 Wall Cladding
Trellis 4-427 Valves Colorcote 4-287
Trench Excavation Landing 4-349 Wall Linings
Drainage 4-316–4-317 Mechanical Services 4-340 Fibre Cement
Tridek 4-411 Sprinkler 4-351 Axon Panel 4-208
Trimmers, Carpentry 4-194 Urinal, flushing 4-300 CLD Panel 4-208
Trolleys, Patient 4-444 Vanity Units 4-249, 4-302–4-303 Hardibacker 4-207
Trough Melamine 4-249 Hardiflex 4-207
Conveyor, Document 4-433 Natural Timber Veneer 4-249 HardiGroove™ 4-207
Roofing 4-282 Vapour barrier 4-202 Hardipanels 4-207
Truck Capacity 5-490 Vehicle reimbursement 4-456 Inseal jointer 4-207
Trunking 4-360 Vehicle showroom Villaboard 4-207
Trusses Building Costs/m2 1-30 Weatherboards, Hardies 4-215
Carpentry 4-200 Vehicle turntable 4-433 Plywood 4-217
Posi-Strut 4-201 Velux roof windows 4-290 Timber Boarding 4-217
Roof 4-200 Veneer Ties 4-177 Weatherboards
Twinaplate 4-201 Venetian blinds 4-256 Aluminium 4-216
Tubelight acrylic skylight 4-289 Ventilation James Hardie 4-215
Tubs 4-303 Comparative Costs 3-94 PVC 4-215–4-216
Tuftiguard 4-404 Natural 4-348 Timber 4-216
Turf Reinforcement 4-426 Powered 4-346–4-347 Wall Oven 4-436
Turntable, vehicle 4-433 Ventilators, Roof 4-293 Bench Unit 4-247
Index
2008
X,Y,Z
Page 15-681
A B C D E F G H I J K L M
N O P Q R S T U V W X,Y,Z
Wallboard Seats 4-298 Pine 4-251
BPB Plasterboard 4-388 WC Pan Velux, roof 4-290
Gib Board 4-387 Squat style 4-297 Winding Equipment 4-233
Wallpaper 3-90 Weather Bars 4-399 Wing Walls 4-328
Walls Weather Tables 14-657 Won-Door 4-266
Concrete 4-143 Updated 14-657 Wood Fibre
Gables 3-78 Weatherboards Panels 4-219
Insulated 4-278 Aluminium 4-216 Work section codes 11-547
Parapet 3-78 Bevelback 4-216 Working Space 14-644
Retaining 4-428 Board and Batten 4-216 Workshops
Stone 4-184 Fibre Cement 4-215 Building Costs/m2 1-21
Timber Framed 3-77–3-78 PVC 4-215–4-216 Elemental Costs 2-52
Warehouses Rusticated 4-216 Workstation, office furniture 4-448
Building Costs/m2 1-20 Shiplap 4-216
Warrants of Fitness Timber 4-216 X,Y,Z
Tax Aspects 13-616 Wedge and Grout 4-168 XPS polystyrene 4-152, 4-203
Washing Machine Wedge fastener 4-232 Z nails 4-198
Commercial 4-435 Weights Zenith Hydrotap 4-315
Domestic 4-437 of Reinforcing Rod 14-649 Zinc
Water Weld 4-168 Metalspray 4-171
Boilers, HVAC 4-335 Welded Sections 4-164 Phosphate Paint 4-171
Chillers 4-333 Welder, hire rates 4-454 Silicate Paint 4-171
Cooler 4-304 Welding studs 4-153, 4-170, 4-172 Zincalume
Filter 4-304 Wetback HWC 4-314 Box Gutters 4-292
Heaters Whiteboards 4-250 Downpipes 4-294
Electric 4-314 Window Flashings 4-295
Gas 4-314 Catches 4-232 Valley Gutters 4-292
Heat Pump 4-315 Insulation 4-416 Zolatone 4-411
Low Pressure 4-314 Stays 4-232
Solar 4-314 Winding Equipment 4-233
Wetback 4-314 Windows
Tanks 4-313 Aluminium
Waterless Urinal 4-299 Commercial 4-252
Waterproofing Domestic 4-252
Bentonite 4-173 Double Glazed 4-252
Bituminous Coating 4-173 Blinds 4-256
Bituproof 4-173 Comparative Costs 3-81
Bituthene 4-174 Curtain Walling 4-253
Dampstop 4-144 Fire Rated 4-255
Flintkote 4-173 Frameless Glazing 4-253
Formceal 4-173 Glasswall 4-254
Mulseal 4-173 Glazing Bar 4-254
Novater 4-174 Louvres 4-256
Permaline 4-173 Mitech film 4-130
Polygum 4-174 Protective film 4-130
Polypropylene 4-173 Roof 4-288
Polythene 4-144 Sashless Sliding 4-252
Protection 4-173 Shop Fronts 4-253
Self Seal 4-174 Shugg 4-252
Shelterbit 4-174 Spandrel Panels 4-253
Shelterseal 4-174 Squash Courts 4-254
Underlay 4-144 Steel 4-254
Volclay 4-173 Timber 4-251
Waterstops 4-145 Cedar 4-251
WC Colonial Style 4-251