Drainage Report: For: The Old Surgery, Sarn Bach Road, Abersoch, Pwllheli, Gwynedd. LL53 7EH
Drainage Report: For: The Old Surgery, Sarn Bach Road, Abersoch, Pwllheli, Gwynedd. LL53 7EH
Drainage Report: For: The Old Surgery, Sarn Bach Road, Abersoch, Pwllheli, Gwynedd. LL53 7EH
2016
DRAINAGE REPORT
For:
The Old Surgery, Sarn Bach Road, Abersoch,
Pwllheli, Gwynedd. LL53 7EH
Alan Owen
A.L.I. BUILDING DESIGN LTD
Glasdy, Station Road, Llanrug, Caernarfon, Gwynedd. LL55 4AG
01286 238297
A.L.I. BUILDING DESIGN LTD
Contents
1.0 General Overview ...................................................................................................... 2
Appendices
E Soakaway Calculations
1
A.L.I. BUILDING DESIGN LTD
Tial Pits:
On the 17th September 2016, two trial pits were excavated.
TP1 was excavated to a depth of 1350mm below ground level.
TP2 was excavated to a depth of 1300mm below ground level.
The depth of the trial pit included a hole at the base 300 x 300 x 300mm depth.
See Appendix (B) for position of trial pits.
2
A.L.I. BUILDING DESIGN LTD
Ref Total Depth of pit Ground Water Depth Soil Infiltration Rate
The data from the soakaway trial pits can be found in Appendix (D&E)
TP1 : Average 350mm thick topsoil with a stone/light clay mix layer beneath, which
continued beyond the base of the excavation.
TP2 : Average 300mm thick topsoil with a stone/light clay mix layer beneath, which
continued beyond the base of the excavation.
No groundwater was encountered.
4.0 Conclusions
Surface Water:
The findings indicated that the infiltration value of the ground was adequate to accept a
soakaway as a medium for discharging surface water run-off from the proposed dwelling and
drive.
See Appendix (D) for infiltration calculation data.
See Appendix (E) for soakaway calculation data
The calculations are based on 1 in 100 year return storm with 30% CCF.
The result for the worst case infiltration result (TP2) has been taken for the calculations.
Areas:
Drive catchment area of 93m2.
Roof catchment area 100m2.
The calculations show that a blanket soakaway 7.5m x 7.5m x 0.20m depth is sufficient to
accommodate surface water run-off from the drive and the dwelling.
It is recommended however, that the entire drive area be utilised as a blanket soakaway.
This will provide greater storage over and above that required by calculation.
3
A.L.I. BUILDING DESIGN LTD
Terram (or other approved geotextile) to be placed over the base of the excavated soakaway
area and taken up the side of the pit and then lapped over the clean stone after placement.
The porous pavior finish can then be constructed over the soakaway (to manufacturer’s
instructions).
The pipework leading to the soakaway will be solid 110mm dia. underground pipework with
110mm dia. perforated underground pipework laid within the blanket soakaway.
The perforated pipework will allow for an even distribution of the surface water through the
soakaway.
The surface water run-off from the roof of the dwelling will be discharged into a manhole
soakaway located between the dwelling and the access road.
Care to be taken that no tree roots are damaged in the excavation.
See Appendix (F) for indicative drainage layout.
See Appendix (G) for typical porous paviors soakaway cross section.
4
A.L.I. BUILDING DESIGN LTD
APPENDICES
5
A.L.I. BUILDING DESIGN LTD
Appendix (A)
6
A.L.I. BUILDING DESIGN LTD
Appendix (B)
7
A.L.I. BUILDING DESIGN LTD
Appendix (C)
8
A.L.I. BUILDING DESIGN LTD
A. L. I. Building Design Ltd
Appendix (D) Glasdy
Station Road
Llanrug
Caernarfon
Gwynedd
LL55 4AG
01286 238297
18th September 2016
Percolation Test
Re:- Porosity tests on land at The Old Surgery, Sarn Bach Road, Abersoch, Pwllheli,
Gwynedd LL53 7EH
Trial holes excavated 300mm square and 300mm deep as stipulated in Approved Documents
Part H 2000
9
A.L.I. BUILDING DESIGN LTD
Appendix (D)
01286 238297
18th September 2016
Percolation Test
Re:- Porosity tests on land at The Old Surgery, Sarn Bach Road, Abersoch, Pwllheli,
Gwynedd LL53 7EH
Trial holes excavated 300mm square and 300mm deep as stipulated in Approved Documents
Part H 2000
Data:
Calculations :
Results :
Emptying time to 50% volume = 0:19 (hr:min)
hMax (Depth) = 0.2 metres
Time to maximum = 0:01 hr:min
Rainfall at maximum = 71.72mm/hr
Width (m) = 7.5
Length (m) = 7.5
Total Infiltration area = 62.3m² (base area + sidewall area).
Total available volume = 3.98m³
N.B. The rainfall rates are calculated using the location specific
values above in accordance with the Wallingford procedure.
11
A.L.I. BUILDING DESIGN LTD
Appendix (F)
12
A.L.I. BUILDING DESIGN LTD
Appendix (G)
Terram 1000 (or other approved geotextile) to be fixed to the perimeter walls of the pit prior
to placing granular stone backfill
Typical Soakaway:
13
A.L.I. BUILDING DESIGN LTD
NOTES:
14