Commissioning Generator AVR, PSS and Model Validation: Wenyan Gu, Member, IEEE
Commissioning Generator AVR, PSS and Model Validation: Wenyan Gu, Member, IEEE
Commissioning Generator AVR, PSS and Model Validation: Wenyan Gu, Member, IEEE
Abstract - This paper outlines procedures and experience the response time and better steady state error; but it may also
author had on commissioning and field tuning ABB Unitrol P result in higher overshoot and longer settling time.
AVR and PSS of a 160 MW steam turbine. Field measurements
are provided in the paper for demonstration of transient
responses. In addition, UEL verification test was conducted and
test method is described in this paper.
The AVR tuning included two fold tests: off-line (or open-loop)
Figure 1. Unitrol P AVR block diagram step response and on-line (or closed-loop) step response. In
addition, UEL (under excitation limiter) and/or OEL (over
excitation limiter) shall be set during AVR field commissioning.
This AVR is a proportional (P) type controller, so steady
state error in regulation is expected. It features with two Off-line step response
lead-lag elements for flexibility in arranging zeros and poles.
Prior to the field commissioning, PSSE dynamic studies were
Adjusting time constants Tc1/Tb1 and Tc2/Tb2 will let the conducted for pre-settings of AVR. On site, AVR parameters such
engineer to gain proper phase angles of the regulator. Kr is as time constants and gain were set to the values identified from
the gain of the AVR. A larger gain Kr will result in fast simulation studies.
Manuscript received Nov 12, 2014. AVR tuning always starts with off-line step response test. To
Wenyan Gu is with ATCO Electric, Edmonton, Alberta, Canada. conduct such test, the generator should operate at rated speed
[email protected]. (3,600 rpm for this case) with the unit breaker open and PSS
669
978-1-4799-5829-0/15/$31.00 ©2015 IEEE
blocked. A 3~5% step ΔVref signal was then applied to the AVR, field current, and field voltage are provided in Figure 4. The test
and the unit terminal voltage, field voltage, field current and other was conducted with stabilizer blocked as well.
signals were recorded. The recorded traces were to be used for
evaluation of the AVR settings on the base of its response time, A -/+5% step was applied to the AVR when the unit was operated
oscillation pattern, overshoot, and steady state accuracy. Final at 160 MW/0 MVAR (PSS off), i.e. at full load and 1.0 power
setting of the AVR was made after all the quantities were within factor.
the acceptable level.
As expected, the terminal voltage step responses (in kV) showed
Adjusting Kr would result in fast response and larger overshoot or slower response time (about 2 seconds) comparing to that of the
oscillations, and it was continuously adjusted until satisfactory off-line step response. The field current showed a damped
response reached. response, but oscillations were observed comparing to the off-line
step response. The oscillations were due to the induced active
Figure 3 shows a group of traces recorded from the final AVR power swings.
settings. A -/+5% step signal was applied to the AVR. Vt is the unit
terminal phase voltage (in volt), Ifield is the field current (in
ampere), and Vfield is the field voltage (in volt).
The terminal voltage responded to the step signal in less than 300
ms with minimum overshoot, and there was no obvious oscillation.
The field voltage was at 89.2 V before the step changes, and it
stayed at 83.2 V when the –5% step was applied during the time of
t=8~22 sec. It returned to 89.2 V after the step signal was removed
at t=22 sec.
It is clear that all the responses were well damped, and therefore,
stable.
Figure 4. On-line -/+5% step response
The field voltage had a –100 V drop in responding to the –5% step,
and it reached the ceiling voltage (400 V) when +5% step was
applied.
This application did not include OEL, so only UEL was tested and
set. It was done by continuously manually lowering the terminal
voltage until the limiter picked up. The test was conducted when
the generator was operated at 150 MW/-20 MVAR generation
level. The terminal phase voltage started at 9.03 kV. When it
reached 8.7 kV, where the var reached –47 MVAR, the limiter
brought the terminal voltage back to 8.83 kV. The UEL stabilized
the reactive power at – 37 MVAR.
670
Most importantly, the applied disturbance level is too small to
trigger area oscillation mode (~0.4 Hz). Therefore, the PSS was
mainly tunned to damp local oscillation mode (~1.6 Hz).
PSS tuning
671
IV. SIMULATION STUDIES
Prior to the field tuning, PSSE simulations were conducted for
AVR and PSS parameter settings to assist the commissioning. After
the field commissioning, simulation studies were also conducted to
verify and to validate PSSE model. It also serves the purpose of
providing validated model to WECC and local Independent System
Operator (ISO).
A. Simulations
The AVR and PSS models were chosen to represent the physical
installations as closely as possible, and the parameters were set at
the values from commissioning.
Off-line step response Figure 9. On-line step response: -/+5% step on AVR.
Traces shown in Figure 8 are the terminal voltage and field voltage The well matched terminal voltage and the field voltage between
of the measured and simulated. The plots show a –5% step change the field measurement and the simulation further confirmed that the
on AVR reference. Although the simulated response of the terminal AVR model used in the simulation is accurate.
voltage was a little slower than the measured correspondence, it is
considered acceptable from an engineering point of view. The next PSS damping
simulation of on-line step response will further confirm the
accuracy of the model used in the simulation. Simulation for the PSS effect is presented in Figure 10, where the
field measured MW and the simulated MW responses subject to a -
/+5% AVR step were plotted. The unit was operated at 160 MW/-2
MVAR production. The mismatch of the MW swings between the
field measurement and the simulation is about 2 MW. But the
damping time and the oscillation pattern are very close. Therefore,
the PSS parameters used in the simulation are considered accurate.
672
AVR parameters: in the range of 10~20 db, and it attenuates sharply for higher
frequencies. For a 45 degree for stability margin, the tunned PSS
TC1= 0.01 TB1=0.007 TC2=1.6 TB2=9.85 Kr=400 has approximately 3 dB of amplitude margin.
Ts=0.003
Input #2 reduced the bandwidth of PSS from above 100 Hz to 30
PSS parameters: Hz. This is likely to improve noise resistance to higher frequency
signals.
TW1=2.0 TW2=2.0 T6=0.0 TW3=2.0 TW4=2.0 T7=2.0
Ks2=0.2 KS3=1 T8=0.0 T9=0.1 KS1=5.0 T1=0.2 The known WECC inter area mode is approximately at 0.4 Hz.
T2=0.04 T3=0.36 T4=0.12 USTMAX=0.1 USTMIN=-0.1 Although the inter area model was not observed from the applied
The PSS employed two input signals: input signal #1 is the bus 5% step voltage reference, the Bode Plot shown in Figure 12 a 16
frequency deviation; input signal #2 is generator electrical power. dB magnitude at 0.4 Hz with a 40 degree leading angle. So the
tunned PSS shall provide damping to this inter area mode.
25
10
Amplitude (dB)
20
35
50
65
80
0.01 0.1 1 10 100
Frequency (Hz)
trace 1
trace 2
trace 3
180
135
90
Phase (Degree)
45
45
90
135
180
0.01 0.1 1 10 100
Frequency (Hz)
trace 1
trace 2
trace 3
Comparing trace 1 and trace 3 we see that they are very closely
matched each other. This means that input #1 dominates the
functionality of the tunned PSS up to the frequency range of 30 Hz.
In the frequency range of 0.1~9.0 Hz, the PSS gain (amplitude) is
673