An Overview of Protection System Analysis 1 PDF
An Overview of Protection System Analysis 1 PDF
Training Programme on
“ An Overview of Protection System Analysis”
for ER Utilities
1
Copyright @ Power Research & Development Consultants Pvt. Ltd
Topics
1. Understanding Power System Protection through
Simulations
2. Power Flow Solution Practical considerations
3. Short Circuit Studies
4. Transient Stability Studies
5. Introduction to Power System Protection
6. Protection Case Studies
7. Principles of Unit Protection
8. Generator Protection
9. Frequency Relays
10. Electromagnetic Transient analysis & Overvoltage
Studies
11. COMTRADE
12. Tripping Analysis - Methodoloy
1
Copyright @ Power Research & Development Consultants Pvt. Ltd
Understanding Power
System Protection through
Simulation
6
Copyright @ Power Research & Development Consultants Pvt. Ltd
Organization of the Lecture
Introduction
Recent Trends
Simulation Tools
Simulation Cases
Economics ?
Record keeping
6. Frequent surveys as system changes or additions
are made, to be sure that the fore going features are
still adequate
PROTECTION
– Online activity
– Modifies preferred protective response to a
change in system conditions or requirements.
– Special application in case of -
* Multi terminal lines.
* Out of step protection.
* Back up protection of distance relays.
Finance
Planning/
Design Manufacturer
/supplier
Protection
Engineer
Operational Field
Load Despatch Engineer
Analysis Tools
System Loadflow
Operational Short Circuit
Relay Relay Co-ordination
RESULTS Transient Stability
Over voltage
Database
SLD
Zooming Degitizer
Windowing Mouse
Reports Printer
Graphs Plotter
Peripheral support
GUI (Graphic User Interface)
system
Fault
Transients
Surge period
Dynamic period
Steady State period
32
Copyright @ Power Research & Development Consultants Pvt. Ltd
Why Load flow study for protection
Engineer?
33
Copyright @ Power Research & Development Consultants Pvt. Ltd
Copyright @ Power Research & Development Consultants Pvt. Ltd 34
Fault Simulation to Aid Protection
Engineer
35
Copyright @ Power Research & Development Consultants Pvt. Ltd
Fault calculation to determine
1. Fault current from various sources
2. Post fault voltage
3. Earth fault current
4. Primary and back up relay current
5. Temporary over voltage (during
single line to ground fault)
1. Symmetrical AC current
2. DC off set current
3. Asymmetrical AC current
40
Copyright @ Power Research & Development Consultants Pvt. Ltd
41
Copyright @ Power Research & Development Consultants Pvt. Ltd
Stability study simulation and its
importance
42
Copyright @ Power Research & Development Consultants Pvt. Ltd
Sustained fault at the machine terminal
1. Initial Sub-transient current.
2. Intermediate transient current.
3. Final steady state current.
43
Copyright @ Power Research & Development Consultants Pvt. Ltd
Frequency plot
44
Copyright @ Power Research & Development Consultants Pvt. Ltd
Parallel line, one line trips
45
Copyright @ Power Research & Development Consultants Pvt. Ltd
Initial point
Final point
Terminologies
1. Load encroachment
2. Power swing
46
Copyright @ Power Research & Development Consultants Pvt. Ltd
Impedance seen by the distance relay
47
Copyright @ Power Research & Development Consultants Pvt. Ltd
Fault cleared in 0.1 seconds
48
Copyright @ Power Research & Development Consultants Pvt. Ltd
Fault cleared in 0.3 seconds
49
Copyright @ Power Research & Development Consultants Pvt. Ltd
Fault cleared in 0.5 seconds
50
Copyright @ Power Research & Development Consultants Pvt. Ltd
Out of step detected
and generator tripped
51
Copyright @ Power Research & Development Consultants Pvt. Ltd
Power reversal in the line
And the system is saved.
52
Copyright @ Power Research & Development Consultants Pvt. Ltd
Understanding single pole auto re-closing facility
53
Copyright @ Power Research & Development Consultants Pvt. Ltd
Out of step operation
1. Out of step protection for the machine
2. Pole slipping relay
54
Copyright @ Power Research & Development Consultants Pvt. Ltd
Protection Engineer designs the relay,
based on system behavior
55
Copyright @ Power Research & Development Consultants Pvt. Ltd
Loss of excitation
1. Machine draws very large reactive power
2. Over heating of stator
3. If not protected, burning out of stator
56
Copyright @ Power Research & Development Consultants Pvt. Ltd
Loss of excitation
1. Impedance moves from the first
quadrant
2. Settles in a circle with dia xd and
off set xd’/2
3. Off set mho relay detects the fault
57
Copyright @ Power Research & Development Consultants Pvt. Ltd
Loss of excitation relay
1. Off set mho relay
2. Off set of xd’/2
3. Diameter of xd
58
Copyright @ Power Research & Development Consultants Pvt. Ltd
Why current limiting reactor for
capacitor banks?
MVA x1000
Current base =
3VLL
kV
2
Z base 2
kVb 2
2
MVAb1 MVAb 2
Z act Z base1.Z pu1 Z act Z base 2.Z pu 2
Z base1.Z pu1Z base 2.Z pu 2
Z pu 2
Z base1.Z pu1
Z pu1
kVb1 MVAb 2
2
.
Z base 2 MVAb1 kVb 2 2
5 MVA, 8% impedance
On 100 MVA, it is 0.08*100/5 = 1.6 pu
2. Balanced operation
No zero sequence.
No mutual.
Perfectly transposed.
3. Series compensation
Series compensation factor Xc/XL
4. Shunt compensation
Shunt compensation factor BL /Bc
Line reactor
Bus reactor
BC /2 BC /2
R XL
57.5 57.5
BC /2 MVAR BC /2 MVAR
Ypq/a q
p
1/a(1/a-1).Ypq (1-1/a).Ypq
IX = 0.1 pu
E = 1+0.1 = 1.1 pu
I= 1pu V = 1 pu
VR = (1.1-1)/1 = 0.1=10%
1 pu
1 pu
current
220/132 kV
Z=8%
s p-s - t
p H-M-L
Zp
Zs Zt
s
P 220 kV
2.5%
7.5% 7.5%
S
t 11 kV 11 kV
80
Z st 16.5 22%
60
1
Zp 9.5 115
. 22 0.5%
2
1
Z s 22 9.5 115 . 10%
2
1
Z t 115 . 22 9.5 12%
2
on primary rating
Copyright @ Power Research & Development Consultants Pvt. Ltd
Example 2 : Equivalent Circuit
P 220 kV
-0.5%
10% 12%
S
t 132 kV 11 kV
P, Q
Initial
V
P, V Q
Qmax, V, Vspec
Qmin, V, Vspec
S P Q 2 2
Rotor heating
Stability limit limit
52
50
48
P
Rated
G 10+j0
11kV 10% 220kV
100MVA
Pmin = 0
Pmax = 100 MW
Prated = 100 MW
Pscheduled = ? = X {Flat tie line control}
Droop = 5%
60+j0
G
11kV 10% 220kV
100MVA
Pmin=0
Pmax=100MW Droop=5%
Prated=100MW
Pscheduled=X
C0
P operating P
Copyright @ Power Research & Development Consultants Pvt. Ltd
Load Modelling
PL=PL0(1+Cpf . f) * (Cpp+CpiV+CpzV2)
PL0 : Base load (Nominal load)
Cpf : Frequency dependence factor
f : Change in frequency
Cpp : Constant power factor
Cpi : Constant current factor
Cpz : Constant impedance factor
Static Dynamic
Induction Motor
Synchronous Motor
P 1 p
P0 CP p
C I .V p
CZ .V 2
K f . f
p
Q Q C C .V C .V 1 K .f
0
q
P
q
I
q
Z
2 q
f
P P0 C Pp CIp .V CZp .V 2 1 f . C fp
Q Q C 0
q
P CIq .V CZq .V 2 1 f . C
q
f
Cp
Voltage
P yp1
Ip V1
Ip1
yp2 2
yp0 Ip2
V2
n
Ip0 ypn
Ipn
Vn
Vp
Vp . y p 0 Vp V1 . y p1 Vp V2 y p 2 Vp Vn y pn
I p y p 0 y p1 y p 2 y pn V y . V y V y . V
p p1 1 p2 2 pn n
x k Yk f k' x1 , x 2 , , x k 1 , x k 2 , , x n 1 , x n
Gauss
x ki Yk f k1 x1i 1 , x 2i 1 , , x ki11 , x ki12 , , x ni11 , x ni1
Gauss Seidel
xki Yk f k1 x1i , x2i ,, xki 1, xki 12 ,, xni 11, xni 1
n
1 I p
Vp Ypq Vq
Ypp
q 1
qp
P jQ n
1 Ypq Vq
p p
Vp
Ypp *
Vp
q 1
qp
p 1
1 Pp jQ p
n
V pi
Y pp V p* i 1
Y pq V q
i
Y pq V q
i 1
q 1 q p 1
fk fk fk fk
yk f k x , x ,....x ,.....x x1
i 1 i 1 i 1 i 1
x2 ...... xk ........ xn
x1 i1 x2 i1 xk i1 xn i1
1 2 k n
f k f k f k f k
y k x1 x 2 ...... x k ........ x n
x1 i 1
x 2 i 1
x k i 1
x n i 1
Vk V
m 1
m Ykm
n
Vk k . V
m 1
m m . Ykm km
Whenthesolutionisobtained
n
k m km
V '
V
m 1
'
Y cos '
k m km Ps pec
'
Pspec = PG-PC-PL
PG : After generator regulation characteristic
PL : After load modelling
Pk = Pspec - Pk
n
m1
Vk' Vm' Ykm sin 'k 'm km Q s pec
QC
QL
QComp
Qspec = QG - Qc - QL + Qcomp
QG = After Q checking
QL = After load modelling
Qcomp = Fixed compensation given along with load data.
Qk = Qspec - Qk
n
Pk V V Y
m1
k m km cos k m km
1. HVDC converters
2. Harmonic elimination
3. Industrial plants
AC Bus
1
1 4 7 10 13
2 4 6 8
10
2 5 8 11
3 5 7 9
14 15
3 6 9 12
1
R j0
R
1
0 j 2 f L
L
C 0 j 2 fC
R = 1, L = 2, C = 3
XL = 2fL and XC = 1/2 fC
f : system frequency
R +jX
G+jB
Filter B +ve for C
B -ve for L
B2
L2
L1
where,
nl : Total number of series elements.
Wi : Line weightage for ith line
Pinew : New real power flow in the line
Pilimit : Real power flow limit on the line
Features added:
Multiple contingencies
Subject to:
Voltage is within the specified limits.
Tap is within the limits.
Compensation is within the limits
Program termination:
Voltages are within the limits
No more VAR source is available
where,
X is the annual expenditure / income.
i : interest rate per annum.
n : Scheme period in years.
Annual expenditure :
Capital investment * (O & M)
Annual benefit :
Reduced loss(in MW)*loss load factor * 8760*1000 *
Unit charge in Rs. (kwhr)
2 Methodology:
Minimize: The total cost (generation + cost).
Subject to: Generation schedule being within minimum
& maximum limits.
3 Technique :
Linear Programming technique
Minimize the objective function (total cost)
Subject to equality and inequality constraints
50%
25%
47 48 49 50
Hz
PTn Tie-line
PT2 Area -x
Area -1
PT1
No. of poles = 2
3 XC
Rc
No. of bridges = 2
Xc = Transformer reactance on own
Rdc MVA rating
Vac Idc
Pac
I ac base A base
3Vac base
RC X C .
baseMVA
x
1
nbnp
6 T .MVA
r
Vdc1 Vdc2
Idc
Pdc = Vdc * Idc ,When Vdc is less Idc has to be more for
same Pdc . Idc2Rdc is the loss
V1 V2
3
V3
I3
Vdc1 Vdc2
Steady state operation : R alone L & C not considered
I dc
Vdc1 Vdc2
Rdc
Pdc1 Vdc1 * I dc
Pdc2 Vdc2 * I dc
our approachPdc, I dc ve for rectifier , ve for inverter ,Vdc:always ve
Rdc is accepted in ohms
Rdc ohm
Rdc pu
Z dc base
Copyright @ Power Research & Development Consultants Pvt. Ltd
Modelling of DC Link:
Line Reactors:
17
Copyright @ Power Research & Development Consultants Pvt. Ltd 1
Typical data for a
Transformer
• MVA rating : 145
• Voltage rating : 132kV/66kV
• Number of taps : 6
• Minimum tap voltage : 122.1 kV
• Maximum tap voltage : 138.6 kV
• Impedance on own rating : 11%
• Type of tap change : OLTC
17
Copyright @ Power Research & Development Consultants Pvt. Ltd 2
Line or Cable details
• Number of circuits
• Positive sequence resistance - ohms/km
• Positive sequence reactance - ohms/km
• Positive sequence susceptance - mho/km
• Line length
• Loading capability
17
Copyright @ Power Research & Development Consultants Pvt. Ltd 3
Typical values for line
Voltage R X B Bp
KV ohm/km ohm/km mho/km 100 km
400 0.02640 0.329440 3.365e-6 0.5384
220 0.07986 0.399784 2.867e-6 0.1388
132 0.102 0.401 1.46e-6 0.0254
110 0.18906 0.398961 2.834e-6 0.0343
66 0.31882 0.466684 2.892e-6 0.0127
33 0.201 0.395 2.72 e-6 0.0029
17
Copyright @ Power Research & Development Consultants Pvt. Ltd 4
Load data
17
Copyright @ Power Research & Development Consultants Pvt. Ltd 5
Shunt Reactor and Capacitor
Data
Rated kV and MVAR at rated kV
17
Copyright @ Power Research & Development Consultants Pvt. Ltd 6
Generator Data
Capability curve
17
Copyright @ Power Research & Development Consultants Pvt. Ltd 7
Node Numbering and Naming
17
Copyright @ Power Research & Development Consultants Pvt. Ltd 8
Node Numbering and Naming
Further,
1 - 1000 : Area 1 buses
1001 - 2000 : Area 2 buses
2001 - 3000 : Area 3 buses
3001- 4000 : Area 4 buses
17
Copyright @ Power Research & Development Consultants Pvt. Ltd 9
Naming
Close to the user
Last digit to indicate the voltage level
Say,
NLMG400 - Nelamangala 400 kV
NLMG220 - Nelamangala 220 kV
NLMG66 - Nelamangala 66 kV
RAWI132 - Rarawai 132 kV
18
Copyright @ Power Research & Development Consultants Pvt. Ltd 0
New substation arrangement
Tap or T-off
105
Dummy node
108 107
106
18
Copyright @ Power Research & Development Consultants Pvt. Ltd 1
New substation arrangement
Loop in and Loop out (LILO)
105
107
106
18
Copyright @ Power Research & Development Consultants Pvt. Ltd 2
Generator Arrangement
18
Copyright @ Power Research & Development Consultants Pvt. Ltd 3
Shunt Arrangement
18
Copyright @ Power Research & Development Consultants Pvt. Ltd 4
Selection of base MVA
• For utility networks : 100 MVA
18
Copyright @ Power Research & Development Consultants Pvt. Ltd 5
Per Unit calculation
Most of the packages convert the name
plate
details to PU internally. No additional
calculations are involved by the user
Z base = (kV)2/MVA
Zpu(new)=Zpu(old)*[MVA(new)/MVA(old)]
18
Copyright @ Power Research & Development Consultants Pvt. Ltd 6
Per Unit calculation
Thumb Rule
Conversion from smaller MVA base to larger
MVA base : Zpu_new increases
18
Copyright @ Power Research & Development Consultants Pvt. Ltd 7
Special Consideration
for Transformer
kV rating : 220/34.5
18
Copyright @ Power Research & Development Consultants Pvt. Ltd 8
Basic Checks for Load
Flow Analysis
1. Load and generation balance
18
Copyright @ Power Research & Development Consultants Pvt. Ltd 9
Basic Checks for Load
Flow Analysis
2. Line charging susceptance
19
Copyright @ Power Research & Development Consultants Pvt. Ltd 0
Basic Checks for Load
Flow Analysis
5. MVAR limits on generators
19
Copyright @ Power Research & Development Consultants Pvt. Ltd 1
Convergence
1. Validity of the data
19
Copyright @ Power Research & Development Consultants Pvt. Ltd 2
Convergence
Model reactive power load as a function of
voltage
19
Copyright @ Power Research & Development Consultants Pvt. Ltd 3
Convergence
Over voltage in some pockets :
19
Copyright @ Power Research & Development Consultants Pvt. Ltd 4
Convergence
Low voltage in some pockets :
19
Copyright @ Power Research & Development Consultants Pvt. Ltd 5
Convergence
Every thing perfect, but unable to converge
19
Copyright @ Power Research & Development Consultants Pvt. Ltd 6
Convergence
Tolerance value for convergence
19
Copyright @ Power Research & Development Consultants Pvt. Ltd 7
Convergence
Tolerance value for convergence
19
Copyright @ Power Research & Development Consultants Pvt. Ltd 8
Convergence
Select the tolerance based on smallest real and
reactive power loads.
19
Copyright @ Power Research & Development Consultants Pvt. Ltd 9
Analysis of Results
• Voltage should be within the acceptable limits
20
Copyright @ Power Research & Development Consultants Pvt. Ltd 0
Analysis of Results
Generator Q limits
20
Copyright @ Power Research & Development Consultants Pvt. Ltd 1
Analysis of Results
20
Copyright @ Power Research & Development Consultants Pvt. Ltd 2
Analysis of Results
Line loading
Permissible line loading depends on
•Voltage regulation
•Stability
•Thermal (current carrying) capacity
Voltage regulation : 5% and phase angle
difference less than 30 degrees
20
Copyright @ Power Research & Development Consultants Pvt. Ltd 3
Analysis of Results
• Thermal capacity
• Design practice
• Ambient temperature
• Maximum permissible conductor temperature
• Wind velocity
20
Copyright @ Power Research & Development Consultants Pvt. Ltd 4
Analysis of Results
•Short lines can be loaded above SIL and long lines
should be loaded less than SIL because of stability
limitations.
20
Copyright @ Power Research & Development Consultants Pvt. Ltd 5
Queries & Discussions
20
Copyright @ Power Research & Development Consultants Pvt. Ltd 6
Thank You
20
Copyright @ Power Research & Development Consultants Pvt. Ltd 7