Method of Measurements
Method of Measurements
(PICCSMM1)
(First Edition)
AUGUST 2010
TABLE OF CONTENTS
i
Sr. No. DESCRIPTION PAGE NO.
ii
1.0 DOCUMENT TITLE
The title of this document is PICC Standard Method of Measurement, First Edition
(May, 2010), which is abbreviated to PICCSMM1. PICCSMM1 is intended to be
utilized in conjunction with the General Conditions of Contract, PICC General
Specifications or any other relevant provisions provided elsewhere in the Contract
Documents.
The Works shall be itemized and described in Bill of Quantities in sufficient details to
enables Bidders / Tenderers to price it adequately and the method of measurement shall
be stated in the Preamble to the Bills of Quantities. The Preamble shall state the methods
of measurement other than PICCSMM1, if any, which are adopted while preparing the
Bill of Quantities and to be used for measurement of completed parts of Works. Such
methods of measurement shall comprise those not covered by the PICCSMM1.
2.0 OBJECTIVE
The objective of PICCSMM1 is to set forth the procedure according to which the Bills
of quantities shall be prepared, priced and the quantities expressed and measured.
3.0 DEFINITIONS
3.1 In this document and in Bills of Quantities prepared according to the procedure set forth
herein the following words and expressions have the meanings hereby assigned to them,
except where the context otherwise requires.
3.2 “Conditions of Contract” means the “General Conditions of Contract” as provided in the
Bidding/Contract Documents prepared by the Pakistan Engineering Council (PEC).
3.3 Words and expressions defined in the Conditions of Contract have the same meanings
herein.
3.4 All references to clauses are references to clauses numbered in the Conditions of Contract
and reference to paragraphs are references to paragraphs numbered herein.
3.5 The word ‘Work’ includes work to be carried out, goods, materials and services to be
supplied, and the liabilities, obligations and risks to be undertaken by the Contractor
under the Contract.
1
3.6 The expression ‘expressly required’ means as shown on the Drawings or as described in
the Specifications or as instructed by the Engineer pursuant to the relevant provisions of
Conditions of Contract.
3.7 ‘Day work’ means the method of valuing work on the basis of time spent by the
workmen, the materials used and the plant employed.
3.8 ‘Original Ground Surface’ means the surface of ground before any work has been carried
out.
3.9 ‘Final Excavated Surface’ means the surface indicated on the Drawings to which
excavation is to be carried out.
3.10 ‘Commencing Ground Surface’ for an item in a Bill of Quantities means, the surface of
the ground from where that particular item of work has commenced.
3.11 ‘Excavated Ground Surface’ for an item in a Bill of Quantities means, the surface to
which excavation included in that particular item of work is to be carried out.
3.12 A hyphen between two dimensions means a range of dimensions which includes all
dimensions exceeding that preceding the hyphen but not exceeding that following the
hyphen.
The unit of measurement for each item shall be that stated for the item in the
PICCSMM1. The unit of measurement stated against a descriptive feature in the
PICCSMM1 shall apply to all items to which that descriptive feature applies. Meter,
Kilogram, Second (MKS) system of units has been adopted everywhere.
Works are classified into various “Sections”. Unique code has been allocated to each
item of Work for its identification and presentation in the PICCSMM1, Bill of Quantities
and elsewhere. Coding arrangement is as given hereunder:
First two digits represent the “Section”
Next two digits represent the “Part of Section”
2
Next digits represent the subsequent levels
Method of measurement has been defined for each part of the Section to be executed and
measured for payment.
Measurement rules set out the conditions under which work shall be measured and the
method by which the quantities shall be computed. In addition to measurement rules,
following general conditions shall also apply:
Definition rules define the extent and limits of the item of work represented by a word or
expression used in the work classification and in the Bill of Quantities prepared in
accordance with PICCSMM1.
Coverage rules provide that the work stated is deemed to be included in the appropriate
items to the extent that such work is included in the Contract. In addition to coverage
rules, following general conditions shall also apply:
3
b. All the items and activities in PICCSMM1 shall deem to be included all
operations required to perform the work as per Contract Documents.
c. Additional coverage rule which are necessary for complete understanding of
method of measurement are given against relevant item or activity.
Unit Abbreviation
Millimeter mm
Meter M
Square millimeter mm2 or mm2
Square meter M2 or M2
Hectare Ha
Cubic meter M3 or M3
Kilogram Kg
Tone Ton
Metric Tone M. Ton
Sum sum
Number No.
Hour Hr
Horse Power Hp
Week Wk
Litre Ltr
4
6.0 CONVERSION TABLE
For converting unit from MKS unit system to FPS unit system and vice versa following
conversion table shall be used:
CONVERSION TABLE
LENGTH
Millimeter Inch 0.03937
Inch Millimeter 25.40005
Meter Foot 3.28084
Foot Meter 0.3048
Meter Yard 1.09361
Yard Meter 0.9144
Kilometer Mile 0.62137
Mile Kilometer 1.60935
MASS WEIGHT
Kilogram Pound 2.20462
Pound Kilogram 0.45359
Gram Ounce 0.03527
Ounce Gram 28.34949
Kilogram Quintal 0.01
Milligram Grain 0.01543
Kilogram Hundred Weight 0.01968
Hundred Weight Tone 0.0508
Kilogram Tone 0.001
Kilogram Ton 0.00098
Pound Ton 0.00045
VOLUME
Litre Pint (U.K) 1.75975
Litre Gallon (Imperial) 0.21997
Litre Gallon (US) 0.26417
Litre Cubic foot 0.03531
Litre Cubic meter 0.001
Cubic foot Litre 28.31682
Milliliter Fluid ounce 0.0352
Gallon (Imperial) Litre 4.5461
Gallon (US) Litre 3.78541
Gallon (Imperial) Gallon (US) 1.20095
Cubic millimeter Cubic inch 0.00006
Cubic meter Cubic foot 35.31472
Cubic foot Cubic meter 0.02832
Cubic meter Cubic yard 1.30795
Cubic yard Cubic meter 0.76456
5
To Convert Into Multiply
AREA
Square millimeter Square inch 0.00155
Square inch Square millimeter 645.1613
Square meter Square foot 10.76392
Square foot Square meter 0.0929
Square meter Square yard 1.19599
Square yard Square meter 0.83613
Square meter Acre 0.00025
Hectare Acre 2.47105
Acre Hectare 0.40469
Square meter Hectare 0.0001
Square kilometer Square mile 0.3861
Square mile Square kilometer 2.58999
Hectare Square mile 0.00386
Square mile Hectare 258.9989
While converting unit from one system to other system the measurement shall be taken
nearest to 3 digits for MKS system and nearest to 2 digits for FPS system.
6
Section 05: Metals
7
PICC Standard Method of Measurements (PICCSMM1) Section -01: General and Preliminaries
Items
Section-01
GENERAL
AND
PRELIMINARIES ITEMS
8
PICC Standard Method of Measurements (PICCSMM1) Section -01: General and Preliminaries
Items
PICC PART
DEFINITION RULES MEASUREMENT RULES COVERAGE RULES
CODE NAME
011000 Contractual 1. The work/item under this section shall 1. All the items and activities under this
Requirements be measured as fixed and/or time
related in accordance with the unit as section shall deem to be included all
012000 Specified All work other than specified in bill of quantity. operations and provisions required to
Requirement permanent works
which is expressly 2. Method of measurements of items for perform/provide the work/item complete
stated in the contract method related charges, if any, shall be
to be carried out by stated by the tenderer in accordance as per requirement of Contract
the contractor and of with nature of work. Documents.
which the nature and
extent is expressly
stated in the contract
shall be classified as
specified
requirement.
013000 Method Related Method related charges
Charges means the sum of
items inserted in the
bill of quantity, by
the tenderer, to cover
such items of work,
the cost of which are
not to be considered
as some proportional
to the quantities of
other permanent
work items.
9
PICC Standard Method of Measurements (PICCSMM1) Section -03: Concrete
Section-03
CONCRETE
10
PICC Standard Method of Measurements (PICCSMM1) Section -03: Concrete
PICC PART
DEFINITION RULES MEASUREMENT RULES COVERAGE RULES
CODE NAME
031000 Form Work 1. The area of formwork shall be measured as 1. End support of blinding/lean concrete not
surface area in contact with acceptable exceeding 200mm in depth.
completed work of concrete as per 2. Joints and associated rebates and grooves
drawing. 3. Temporary surfaces formed at the discretion of
2. No deduction shall be made for opening in the Contractor.
concrete having area less than 0.01 M2 (1.0
Ft2). Openings with area larger than 0.01
M (1.0 Ft ) shall be deducted.
032000 Placing of Steel 1. Steel Reinforcement shall be classified and 1. Cover blocks, chairs, supports, hooks, spacers,
Reinforcement measured separately as listed under items 2. Binding wires, and laps not shown on drawings
of Bills of Quantities.
2. Measurement for steel reinforcement shall
be according to bar bending schedules
approved by the Engineer.
3. The nominal weight of steel reinforcement
shall be taken as 7.85 ton/M3 (490 lbs/ft3)
or as given in specification.
4. Laps shown on the drawing and/or laps
caused due to commercial length of 12mm
(40ft) bar shall be payable.
033000 Cast in Place 1. When longer dimension 1. The net Volume of Concrete shall be
Concrete of any structural measured as per drawing but no deduction
member is in horizontal shall be made for following:
direction (parallel to i. Volume of any steel reinforcement
surface of earth) then embedded in the concrete.
the component will be ii. Volume occupied by water pipes,
considered as conduits etc. not exceeding 0.0065 m2
horizontal member, (10 in2 ) each in cross-sectional area
and/or iii. Voids or opening not exceeding 0.1
2. When the ratio of m2 (1.07 ft2) in cross sectional area.
height/depth and iv. Rebates, grooves, throats, fillets and
width/breadth of any chamfers each not exceeding 0.01 m2
structural member is (0.107 ft2) in cross sectional area.
11
PICC Standard Method of Measurements (PICCSMM1) Section -03: Concrete
12
PICC Standard Method of Measurements (PICCSMM1) Section -03: Concrete
13
PICC Standard Method of Measurements (PICCSMM1) Section -04: Masonry
Section-04
MASONRY
14
PICC Standard Method of Measurements (PICCSMM1) Section -04: Masonry
15
PICC Standard Method of Measurements (PICCSMM1) Section -04: Masonry
16
PICC Standard Method of Measurements (PICCSMM1) Section -08: Opening
Section-08
OPENING
17
PICC Standard Method of Measurements (PICCSMM1) Section -08: Opening
PICC PART
DEFINITION RULES MEASUREMENT RULES COVERAGE RULES
CODE NAME
081000 Wooden Door,
Windows and
Ventilator
Door Frame 1. Measurement of acceptably Except otherwise specified herein or elsewhere
completed works of all types of in the Contract Documents, no measurement and
wooden door frames will be made payment will be made for the under mentioned
on the basis of net actual area in specified works related to the relevant items of
square meter fabricated and the Bill of Quantities. The cost thereof shall be
installed in position as shown on deemed to have been included in the quoted unit
the Drawings. rate of the respective/items of the Bills of
2. Net area will be measured in Quantities.
accordance with plastered 1. Nails and screws wedging, welding,
masonry opening in between concrete and all other such arrangements
jambs and plastered head and top those are required for complete fabrication
of floor surface as per drawing. and installation.
3. No allowance shall be made for 2. Making rebates, groves, lines, shape and
joints or overlaps. design as per drawing and specification
4. Cost of hold fast and arrangement 3. Fixing, boring, cutting, jointing, drilling and
for fixing hold fast is not included all associated work for complete
in the unit rate of door frame and installation.
shall be paid separately in the 4. Anti termite treatment to wood works and
relevant item of BOQ adhesives
5. Execution of work at any floor and at height
except otherwise mentioned in BOQ or else
in contract document.
Door Shutter 1. Measurement of acceptably Except otherwise specified herein or elsewhere
completed works of all types of in the Contract Documents, no measurement and
wooden door shutter will be made payment will be made for the under mentioned
on the basis of net actual area in specified works related to the relevant items of
square meter fabricated and the Bill of Quantities. The cost thereof shall be
installed in position as shown on deemed to have been included in the quoted unit
the Drawings. rate of the respective/items of the Bills of
2. Net area of door shutter will be Quantities.
measured as per Drawing after 1. Nails and screws wedging, hard wood or
18
PICC Standard Method of Measurements (PICCSMM1) Section -08: Opening
deduction of door frame size/ bamboo pins for frame joints and all other
dimension. such arrangements those are required for
3. No deduction will be made for complete fabrication and installation.
opening for glazing in case of 2. Making rebates in meeting style, groves,
glazed door shutter lines, shape, chamfers and design as per
4. Cost of ironmongery (like hinges, drawing and specification
handles, locks etc.) and glazing 3. Fixing, boring, cutting, jointing, drilling and
are not included in the unit rate of all associated work for complete
door shutter and shall be paid installation.
separately in the relevant item of 4. Anti termite treatment to wood works and
BOQ adhesives
5. Execution of work at any floor and at height
except otherwise mentioned in BOQ or else
in contract document
19
PICC Standard Method of Measurements (PICCSMM1) Section -09: Finishes
Section-09
FINISHES
20
PICC Standard Method of Measurements (PICCSMM1) Section -09: Finishes
PICC PART
DEFINITION RULES MEASUREMENT RULES COVERAGE RULES
CODE NAME
092400 Cement 1. Surfaces that make an angle 5. Measurement of acceptably 1. Metal lath over reinforced concrete and masonry
Plaster of 15⁰-90⁰ with vertical shall completed works of respective joint.
be classified as soffits. type of plaster will be made on 2. Joints, junctions, corners, beads, drip course edge,
2. Surfaces that make an angle the basis of number of square rounding, and aluminum U/Y channels in groves
less than 15⁰ with vertical Meter of the surface area plaster wherever required/ specified.
shall be classified as Walls. as shown on the Drawings. 3. More than one layer due to any unevenness in the
3. Surface of column exceeding 6. No deduction form the area shall finished works and base coat plaster in stucco
1m shall be classified as be made for opening each not plaster including marble chips/color pigments.
wall. exceeding 0.5 M2 and no addition 4. Cutting & patching of all defective works.
4. Surface of Beams Exceeding shall be made for reveals, jambs, 5. Surface preparation, cleaning and protection as
1m shall be classified as soffits, sills, etc., of these specified.
Soffits. openings. 6. Approved waterproofing agent.
7. In case of opening of area 7. Polypropylene Fibers in plaster work.
exceeding 0.5 squares Meter each,
deduction shall be made for the
openings and addition shall be
made for reveals, jambs, soffits,
sills, etc., of these openings.
21
PICC Standard Method of Measurements (PICCSMM1) Section -22: Water Supply and
Sanitation
Section-22
WATER SUPPLY
AND
SANITATION
22
PICC Standard Method of Measurements (PICCSMM1) Section -22: Water Supply and
Sanitation
PICC
PART NAME DEFINITION RULES MEASUREMENT RULES COVERAGE RULES
CODE
221113 Water Distribution
System
1. Pipes and their 1. The diameter of pipe as 1. All Pipes shall be measured along 1. Laying, jointing, cutting, threading
Fittings described means the nominal the centerline of the pipe in linear and insulation of any type of pipes
diameter. meters net as laid or fixed and shall and fittings up to 3" diameter shall
include the lengths occupied by pipe be included in unit rate of pipe.
2. Pipe Fittings means the fittings and valves. 2. Testing of pipelines as per
accessories used for jointing of specification.
pipes like elbows, bends, tees, 2. Measurement of all fittings above 3. Cutting through walls, floors etc.
unions, sockets, nipples etc. 3" diameter shall be made in No. as and making good shall be included
3. All pipes and their fittings actually installed and accepted. within the item.
shall be classified according to 3. Payment for pipe and pipefitting 4. Jointing of pipe fitting above 3"
their types, diameters, method shall be made as measured above in diameter shall be included in the
of jointing and fixing. unit rate as per relevant BOQ item. unit rate of pipe fittings.
23
PICC Standard Method of Measurements (PICCSMM1) Section -32: Earth Work
Section-31
EARTH WORK
24
PICC Standard Method of Measurements (PICCSMM1) Section -32: Earth Work
PICC
PART NAME DEFINITION RULES MEASUREMENT RULES COVERAGE RULES
CODE
311000 Site Clearance
a. Clearing and 1. Clearing and Grubbing consist 1. The quantity of acceptable completed 1. Removal of all surface objects or any
Grubbing of removal to the specified work under this part shall be computed in object to the depth of 30 cm such as
depth and disposal of all Square meter using dimensions from the stumps, roots, vegetation, bushes, logs,
surface objects including construction drawing and/or shop rubbish etc.
stumps, roots, bushes, drawings, and joint survey data approved 2. Removals of trees having girth of less
vegetation, logs, and other by the Engineer. than 150 mm (measured 600 mm
objectionable material except 2. No measurement will be made for area above ground level) shall not be
such objects as are designated outside the theoretical limits as shown on measured separately and deemed to be
to remain or are to be removed the drawings or clearing and grubbing included under this item.
in accordance with other carried out by the contractor in roadway
section of specifications. cut areas and for borrows pits.
3. Trial sections, if any, shall not be
measured separately but shall be included
in the quantities
4. The accepted quantities measured as
provided above shall be paid for relevant
pay item as per Bills of Quantities.
b. Bed Clearance 1. The quantity of acceptable completed 1. Removal of all surface objects or any
work under this part shall be computed in object to the depth of required level as
cubic meter using dimensions from the per drawing such as stumps, roots,
construction drawing and/or shop vegetation, bushes, logs, rubbish etc.
drawings, and joint survey data approved 2. Making and maintain of cross slope
by the Engineer. and longitudinal profile as per drawing
2. No measurement will be made for area and specifications.
outside the theoretical limits as shown on
the drawings
3. Trial sections, if any, shall not be
measured separately but shall be included
in the quantities
4. The accepted quantities measured as
provided above shall be paid for relevant
pay item as per Bills of Quantities
25
PICC Standard Method of Measurements (PICCSMM1) Section -32: Earth Work
c. Stripping/ 1. Stripping or removal of 1. The quantity of acceptable completed 1. Removal of unsuitable material to
removal of unsuitable material consist of work under this part shall be computed in required section, disposal in stock pile
unsuitable removal of un suitable top soil cubic meter using dimensions from the and/or spreading in layers at designated
material to required depth and/or construction drawing and/or shop area.
unsuitable material from any drawings, and joint survey data approved
depth and disposal of material by the Engineer.
in stock pile and/or spreading 2. No measurement will be made for area
at designated area. outside the theoretical limits as shown on
the drawings
3. The accepted quantities measured as
provided above shall be paid for relevant
pay item as per Bills of Quantities
d. Cutting of 1. The quantity of acceptable completed 1. If required cutting of trees from top to
Trees work under this part shall be computed in bottom to prevent traffic, structures
No. base on joint survey approved by the and trees not to be cut.
Engineer. 2. Back filling of holes resulted from
2. The Engineer and Contractor jointly removal of stumps and roots with
measure the girth and count the No. of excavated material and/or borrow
trees of respective girth to be removed material.
under this part 3. Compaction of back filling and loose
3. No measurement shall be made for trees soil resulting from removal of trees to
less than 150 mm girth as the same shall required degree of compaction of
be paid under sub part “clearing and adjoining area.
grubbing”. 4. Cutting of stumps, braches and roots in
4. The accepted quantities measured as required section and disposal in
provided above shall be paid for relevant specified lead.
pay item as per Bills of Quantities.
e. Removal of 1. The quantity of acceptable completed 1. Cutting of trees having girth of less
bush /shrubs / work under this part shall be computed in than 150 mm (measured 600 mm
sarkanda etc. Square meter using dimensions from the above ground level), if any.
construction drawing and/or shop 2. Disposal of garbage, bush, vegetation
drawings, and joint survey data approved and sarkanda within specified lead.
by the Engineer
2. The accepted quantities measured as
provided above shall be paid for relevant
pay item as per Bills of Quantities
26
PICC Standard Method of Measurements (PICCSMM1) Section -32: Earth Work
PICC
PART NAME DEFINITION RULES MEASUREMENT RULES COVERAGE RULES
CODE
312000 Excavation and 1. When the top width of the 1. The quantity of acceptable completed 1. An isolated volume of artificial hard
Backfilling excavation is up to 4.5 m, then work will be computed in Cubic meter material or rock occurring within other
the excavation will be and shall be classified and measured material to be excavated shall not be
classified as trench excavation. separately as listed under relevant items measured separately unless its volume
2. Excavation for foundation of of Bills of Quantities. exceeds 1 M3 for bulk excavation and
buildings, bridges, culverts, 2. The Quantity of work for any item of 0.25 M3 for trench and structural
walls, hydraulic structure, Bills of Quantity under this part shall be excavation.
inlets, out lets and any other computed by average end area method 2. Furnishing all relevant activities,
structure shall be classified as based on construction drawing and/or hauling as described, placing, watering,
structural excavation. shop drawing, cross-sections and joint rolling, if any, labor, equipment, tools
3. All other excavation work that survey data approved by the Engineer. and incidentals necessary to complete
is neither trench excavation 3. Any area over excavated beyond the the item
nor structural excavation shall required line and grades shall be
be classifies as bulk reinstated at the cost of contractor.
excavation. 4. The accepted quantities measured as
4. The type of soil shall be provided above shall be paid for relevant
classified as per specification pay item as per Bills of Quantities.
and/or as determined by the
Engineer.
313000 Formation of 1. The quantity of acceptable completed 1. Furnishing all materials, hauling,
Embankment work will be computed in Cubic meter placing, watering, rolling, labor,
and shall be classified and measured equipment, tools and incidentals
separately as listed under relevant items necessary to complete the item.
of Bills of Quantities. .
2. The Quantity of work for any item of
Bills of Quantity under this part shall be
computed by average end area method
based on construction drawing and/or
shop drawing, cross-sections and joint
survey data approved by the Engineer
27
PICC Standard Method of Measurements (PICCSMM1) Section -32: Earth Work
28
PICC Standard Method of Measurements (PICCSMM1) Section -32: Road Work
Section-32
ROAD WORK
29
PICC Standard Method of Measurements (PICCSMM1) Section -32: Road Work
PICC
PART NAME DEFINITION RULES MEASUREMENT RULES COVERAGE RULES
CODE
320600 Preparation of 1. Existing ground means 1. The quantity of acceptable sub grade work 1. Furnishing all materials, hauling,
Sub Grade when the design level of shall be computed in Square meter using placing, watering, rolling, labor,
sub grade is within 30 cm dimension from the construction drawing equipment, tools and incidentals
of the existing ground/road and/or shop drawing, cross-section and necessary to complete the item.
joint survey data approved by the
Engineer.
2. No allowance will be made for materials
placed outside the theoretical limits as
shown on the drawing.
3. Sub grade payment will be made in
following cases;
i. Sub grade prepared on existing ground
ii. Sub grade prepared in Earth cut.
4. In case unsuitable material found, the
contractor shall be paid for removal of
same material and replacement of suitable
material as per provision of relevant BOQ
item.
5. Sub grade in rock cuts and on
embankment, not consisting of the
existing road surface in fill area, shall not
be measured for payment. Performance of
this item of work shall be deemed to be
covered through in rock cutting and
Formation of Embankment respectively.
6. Trial sections shall not be measured
separately but shall be included in the
quantities
7. The accepted quantities measured as
provided above shall be paid for relevant
pay item as per Bill of Quantities.
30
PICC Standard Method of Measurements (PICCSMM1) Section -32: Road Work
PICC
PART NAME DEFINITION RULES MEASUREMENT RULES COVERAGE RULES
CODE
320700 Improvement of 1. The quantity of acceptable sub grade 1. Furnishing all materials, hauling,
Sub Grade improvement work shall be computed in placing, watering, rolling, labor,
Square meter using dimension from the equipment, tools and incidentals
construction drawing and/or shop necessary to complete the item.
drawing, cross-section and joint survey
data approved by the Engineer.
2. No allowance will be made for materials
placed outside the theoretical limits as per
drawing and/or shop drawing, cross-
section and joint survey data.
3. Trial sections shall not be measured
separately but shall be included in the
quantities.
4. The accepted quantities measured as
provided above shall be paid for relevant
pay item as per Bill of Quantities.
321000 Sub Base and 1. The quantity of acceptable sub base and 1. Furnishing all materials, hauling,
Base Courses base work shall be computed in cubic placing, watering, rolling, labor,
meter using dimension from the equipment, tools and incidentals
construction drawing and/or shop necessary to complete the item.
drawing, cross-section and joint survey .
data approved by the Engineer.
2. No allowance will be made for materials
placed outside the theoretical limits as
shown on the drawing and/or shop
drawing, cross-section and joint survey
data.
3. Trial sections shall not be measured
separately but shall be included in the
quantities.
4. The accepted quantities measured as
provided above shall be paid for relevant
pay item as per Bill of Quantities.
31
PICC Standard Method of Measurements (PICCSMM1) Section -32: Road Work
PICC
PART NAME DEFINITION RULES MEASUREMENT RULES COVERAGE RULES
CODE
321200 Flexible 1. The quantity of acceptable Flexible 1. Furnishing all materials, hauling,
Pavements Pavement work shall be computed in placing, watering, rolling, labor,
cubic meter using dimension from the equipment, tools and incidentals
construction drawing and/or shop necessary to complete the item.
drawing, cross-section and joint survey as
data approved by the Engineer.
2. No allowance will be made for materials
placed outside the theoretical limits as
shown on the drawing and/or shop
drawing, cross-section and joint survey
data.
3. Trial sections shall not be measured
separately but shall be included in the
quantities.
4. The accepted quantities measured as
provided above shall be paid for relevant
pay item as per Bill of Quantities.
32
PICC Standard Method of Measurements (PICCSMM1) Section -36: Pile Work
Section-36
PILE WORK
33
PICC Standard Method of Measurements (PICCSMM1) Section -36: Pile Work
PICC
PART NAME DEFINITION RULES MEASUREMENT RULES COVERAGE RULES
CODE
361000 Bored & Cast In-Situ
R.C Piles
1. Drilling and Boring 1. Commencing surface is 1. Drilling and Boring of hole of specified 1. Preparation of boring site,
the surface of the ground diameter for piles shall be measured in arrangement of requisite
at which any activity linear meters of the hole from materials such as bentonite
started. commencing surface of hole to pile tip etc. and disposal of excavated
2. Cutoff level is top level of level as shown on the drawings. material.
pile at which pile cap rests
or bottom of pile cap, as 2. Payment for drilling and boring shall be
per drawing. made at the unit rate as quoted in bill of
3. Pile toe level is the bottom quantities for linear meter of drilled hole
level of pile as per as measured above.
drawings.
2. Steel Reinforcement
and Concrete The measurement of steel reinforcement and concrete shall be in accordance with the methods of
measurement and rules as prescribed in the relevant Sections.
3. Pile Load Test 1. Measurement for pile load tests shall be 1. Unit Rate per number of load
made for the number of tests actually test includes all costs and
performed and accepted in accordance expenses for the equipment,
with the specifications. accessories, loading and
2. Payment for load test on test piles will unloading arrangement,
be made at the unit rate per number of providing measuring devices,
tests performed. preparing reports, clearing
site and all other operations
required for the completion of
the test as per specification.
34
PICC Standard Method of Measurements (PICCSMM1) Section -36: Pile Work
PICC
PART NAME DEFINITION RULES MEASUREMENT RULES COVERAGE RULES
CODE
1. Permanently placed pile casing of
4. Pile Casing specified diameter and length as shown
on drawings, if used shall be measured
in linear meters.
2. Payment for the pile casing will be made
at unit price per linear meter for pile
casing.
35
PICC Standard Method of Measurements (PICCSMM1) Misc. Items: Day Work
Miscellaneous Items
DAY WORK
36
PICC Standard Method of Measurements (PICCSMM1) Misc. Items: Day Work
PART
Sr. No. DEFINITION RULES MEASUREMENT RULES COVERAGE RULES
NAME
1 LABOR Varied work inputs subject 1 In calculating payments due to the Contractor for 1. The basic rates for labor shall cover all
to payment on “an hourly the execution of Daywork, the actual time of direct costs to the Contractor,
basis for the Contractor's various classes of labor directly doing the Daywork including (but not limited to) the
employees, plants & ordered by the Engineer and for which they are amount of wages paid to such labor,
quantity basis for competent to perform will be measured Per hour transportation time, overtime,
materials”. for “Actual working hours”, Excluding meal breaks subsistence allowances and any sums
and rest periods. paid to or on behalf of such labor for
2 The Contractor shall be entitled to payment in social benefits in accordance with
respect of the total time that labor is employed on Pakistan law.
Daywork, calculated at the basic rates entered by 2. The additional percentage payment to
him in the Schedule of Daywork Rates for labor be quoted by the Bidder and applied to
together with an additional percentage, payment on costs incurred under (1) in
basic rates representing the Contractor’s profit, Measurement Rule shall be deemed to
overheads, etc as described in Coverage Rule Sr. 1 cover the Contractor’s profit,
(Labor). overheads, superintendence, liabilities
and insurances and allowances to labor
3. timekeeping and clerical and office
work; the use of consumable stores,
water, lighting and power; the use and
repair of staging’s, scaffolding,
workshops and stores, portable power
tools, manual plant and tools;
supervision by the Contractor’s staff,
foremen and other supervisory
personnel; and charges incidental to
the foregoing.
2 MATERIALS 1 In calculating payments due to the Contractor for 1. The cost of hauling materials used on
the consumption of Material, the actual Quantity of work ordered to be carried out as
material directly consumed on the Daywork Daywork from the store or stockpile on
ordered by the Engineer and material will be the site to the place where it is to be
measured “Actual Material Consumed at site”. used.
Excluding wastage and all other charges as 2. The material handling, storing,
mentioned in Sr.1 Coverage rule (Materials). I.e.: delivery, wastage and related
a. Cement Bags will be count in no. of Bags expenditures including in material
as actually consumed at site Daywork rates as mentioned in Sr.1
37
PICC Standard Method of Measurements (PICCSMM1) Misc. Items: Day Work
38