Environmental Assessment Report Project Application: White Bay Cruise Passenger Terminal
Environmental Assessment Report Project Application: White Bay Cruise Passenger Terminal
Project Application
Submitted to
Department of Planning
On Behalf of Sydney Ports Corporation
Contents
Executive Summary vi
1.0 Introduction 1
1.1 Overview of Project Application Sought 1
1.2 Strategic Project Need 3
1.3 Existing Cruise Operations 5
1.4 Environmental Assessment and Approvals Process 6
1.5 Project Team 7
4.0 Consultation 31
4.1 Bays Precinct Consultation 33
Contents
8.0 Project Justification 108
Figures
1 Figure 1 – Inbound and outbound passenger process 5
2 Figure 2 – Locality Plan 8
3 Figure 3 – Land Title 9
4 Figure 4 – Aerial photograph of the site 11
5 Figure 5 – Photograph of WB5 taken from an elevated position south of White
Bay showing the context of the site and its proximity to the city 11
6 Figure 6 – Photograph of the site looking North West across White Bay from
Pyrmont Point Park 12
7 Figure 7 – Photograph of the site looking West across Darling Harbour from
Barangaroo 12
8 Figure 8 – Photograph of the large steel framed shed on site, taken from Grafton
Street 13
9 Figure 9 – Photograph of the service road on site located between existing
building and sites northern boundary. 13
10 Figure 10 – Photograph of WB4 taken from next to White Bay Park 14
11 Figure 11 – Photograph of the existing internal port road which connects to
Roberts Street 14
12 Figure 12 – Photograph of Grafton Street, looking north easterly from the corner
of Adolphus Street 15
13 Figure 13 – Photograph of Grafton Street, looking north-west 16
14 Figure 14 – Existing view south along Adolphus Street 16
15 Figure 15 – Residential development to the west of the site (setback from WB3).
17
16 Figure 16 – Location of Heritage Items in the vicinity (Source: City Plan Heritage)
18
17 Figure 17 – Site layout 40
18 Figure 18 – WB5 Vehicle Access Routes 43
19 Figure 19 – Photograph of a temporary terminal at DH5 46
20 Figure 20 – Illustration of the interior of the style of temporary terminal 46
21 Figure 21 – Residential noise receivers 50
22 Figure 22 – Existing view looking south along Adolphus Street, Balmain 71
23 Figure 23 – Montage view looking south along Adolphus Street, Balmain 71
24 Figure 24 – Montage view from Adolphus Street, Balmain (with cruise ship) 71
25 Figure 25 – Existing view looking south west along Grafton Street 72
26 Figure 26 – Montage view looking south west along Grafton Street 72
27 Figure 27 – Montage view looking south west along Grafton Street (with cruise
ship) 72
28 Figure 28 – Montage view looking south west along Grafton Street (with 2 cruise
ships) 72
Contents
29 Figure 29 – Existing view from White Bay Park 73
30 Figure 30 – Montage view from White Bay Park 73
31 Figure 31 – Montage view from White Bay Park (with cruise ship) 73
32 Figure 32 – Existing view from Pyrmont Park 74
33 Figure 33 – Montage view from Pyrmont Park 74
34 Figure 34 – Montage view from Pyrmont Park (with cruise ship) 75
35 Figure 35 – Montage view from Pyrmont Park (with 2 cruise ships) 75
36 Figure 36 – Existing view from Barangaroo 76
37 Figure 37 – Montage view from Barangaroo 76
38 Figure 38 – Montage view from Barangaroo (with cruise ship) 76
39 Figure 39 – Montage view from Barangaroo (with 2 cruise ships) 76
40 Figure 40 – Existing view from Anzac Bridge 77
41 Figure 41 – Montage view from Anzac Bridge (with cruise ship) 77
42 Figure 42 – Montage view from Anzac Bridge (with 2 cruise ships) 77
Tables
1 Table 1 – Forecast monthly cruise passenger ship arrivals for DH5, then White
Bay (between July 2010 and June 2012). 5
2 Table 2 – Relevant provisions Sydney Regional Environmental Plan No26 – City
West 9
3 Table 3 – Relevant Provisions of Sydney Regional Environmental Plan No.2626
4 Table 4 – SREP (Sydney Harbour Catchment) matters for consideration 27
5 Table 5 – Glebe Island/ White Bay Master Plan 28
6 Table 6 – Planning for Entertainment Guidelines 30
7 Table 7 – Authority Consultation Summary 31
8 Table 8 – WB5 Numeric Overview 39
9 Table 9 – Director General’s Environmental Assessment Requirements 48
10 Table 10 – Adopted RBL and LAeq (Source: Wilkinson Murray) 49
11 Table 11 – Operational Noise Criteria (Source: Wilkinson Murray) 50
12 Table 12 – Sound Power Levels (Source Wilkinson Murray) 51
13 Table 13 – Assessment against Intrusiveness Noise Criteria (Source Wilkinson
Murray) 52
14 Table 14 – Assessment against Amenity Noise Criteria (Source Wilkinson Murray)
53
15 Table 15 – Assessment against Intrusiveness Noise Criteria (Source Wilkinson
Murray) 55
16 Table 16 – Two Way Traffic Movements (6:30am to 4:30pm) associated with a
cruise ship visit at Darling Harbour 61
17 Table 17 – Intersection Analysis Results 63
18 Table 18 – Intersection Analysis Results from Cumulative traffic Assessment65
19 Table 19 – Intersection Analysis Results from Cumulative Traffic Assessment for
Functions 66
20 Table 20 – Summary of impacts on specific items 81
Contents
21 Table 21 – Maximum predicted ground level pollutant concentrations for
Scenarios 1 to 4. 86
22 Table 22 – Summary of Infrastructure and Utilities Provision 91
23 Table 23 – Environmental Risk Matrix 95
24 Table 24 – Environmental Risk Matrix 96
25 Table 25 – Environmental Management Commitments – Design and Construction
98
26 Table 26 – Environmental Management Measures - Operational 102
Appendices
A Director General’s Environmental Assessment Requirements
NSW Department of Planning
H Air Quality
Sinclair Knight Merz Pty Ltd
J Contamination
Consulting Earth Scientists
Statement of Validity
Prepared under Part 3A of the Environmental Planning and Assessment Act, 1979
(as amended)
Executive Summary
Purpose of this Report
This Project Application and Environmental Assessment Report is submitted to the
Minister for Planning to fulfil the Environmental Assessment Requirements issued
by the Director General for a Cruise Passenger Terminal (CPT) at Wharf No. 5
(WB5) White Bay, Sydney within the area shown in Figure 2.
The Proponent
The proponent of the development is Sydney Ports Corporation.
Background
Sydney Harbour currently has two dedicated passenger terminals; the Overseas
Passenger Terminal (OPT) at Circular Quay and the east Darling Harbour (now
known as Barangaroo) No. 5 Cruise Passenger Terminal which is currently located
at Wharf No. 5 but was until June 2010 located at Wharf No. 8. Occasionally,
other berths at east Darling Harbour, and berths at White Bay and Glebe Island
have been used to accommodate a third or fourth cruise vessel at a cargo wharf
when the need arose.
In April 2008 the NSW Government decided to temporarily relocate the Cruise
Passenger Terminal from Darling Harbour Wharf 8 to White Bay Wharf 4/5 for a
period of five years.
The PCT Steering Committee found that the Australian cruise industry grew by
18% per annum between 2002 and 2008, with growth forecast to continue over
the next 15 years. However, new passenger cruise ships are expected to increase
in size, so growth in the number of cruise ships visiting the proposed CPT at White
Bay is likely to be restricted in the longer term by the height limitation of the
Sydney Harbour Bridge. Based on the predicted growth forecasts and the height
limitation of the Sydney Harbour Bridge, it is expected that approximately 170
cruise ships per year could use the proposed CPT, approximately two-thirds of
these during the spring and summer months, with approximately one-third during
autumn and winter.
On 20 December 2009 the Premier announced that the NSW Government had
decided to permanently relocate the Darling Harbour No. 8 Cruise Passenger
Terminal to WB5, in accordance with the recommendation from the PCT Steering
Committee, subject to planning approval being obtained.
Project Overview
The proposal includes the construction of new purpose-built building(s), ancillary
site works, parking, and a new access road.
The Site
WB4 and WB5 in the main comprise the site and are located on the south eastern
arm of the Balmain Peninsula on the northern shore of White Bay. It is within a
broader area owned and controlled by Sydney Ports. The site is within the
Leichhardt LGA approximately 2.4km west of the Sydney CBD.
Planning Context
The construction and operation of the proposed CPT is subject to both
Commonwealth and NSW legislation. The proposed development is required to be
designed and operated in accordance with Maritime Transport and Offshore
Facilities Security Act 2003 and Customs Act 1901 (both Commonwealth
legislation).
The principal statutory planning instruments which apply to the site are
Sydney Regional Environmental Plan No 26 – City West (SREP 26) and
State Environmental Planning Policy – Major Development 2005
(Major Development SEPP).
Under SREP 26, the site is zoned ‘Port and Employment’. Uses that facilitate the
continuation of the commercial port uses, employment uses, port and maritime
uses are permissible.
The Glebe Island/ White Bay Master Plan was prepared to guide future
development at Glebe Island and White Bay. The Master Plan provides for the
continued use of Glebe Island and White Bay as a significant commercial port
facility in Sydney Harbour.
In addition, the Government has set up a long term planning process to provide
the planning framework for the future of the Bays Precinct, which includes White
Bay, as well as much of the surrounding land currently disused or used for
maritime purposes. In June 2009 the Minister for Planning established a public
consultation forum for the Bays Precinct, which included the formation of a Bays
Precinct Community Reference Group. Stage 1 of the Bays Precinct consultation
finished in early December 2009, gathering information and ideas from the
community, including the location of the Cruise Passenger Terminal west of the
Sydney Harbour Bridge. This consultation process developed a set of draft
planning principles for the consideration of the Bays Precinct Taskforce which ‘set
the scene’ for future planning and development in the area, and informed the
Government’s decision to permanently relocate the CPT to WB5. In stage 2 of the
consultation, expected to occur in the second half of 2010, the draft planning
principles will be exhibited for comment and feedback from the community will be
sought. This feedback will be used to finalise the planning principles, which will
guide all future planning processes for the precinct.
Environmental Impacts
The key environmental impacts identified for the proposed CPT are noise, air
quality, traffic and access, visual impact, and heritage.
The assessment concludes that these issues are all able to be managed and
mitigated through the design and through the implementation of construction and
operational management plans and other mitigation measures.
Conclusion
The continued provision of facilities that can cater for up to three passenger ships
at berth in Sydney at any one time provides a significant contribution to the NSW
economy. In 2007/2008 it was estimated to provide a total output expenditure
(direct and indirect expenditure) of $291 million in NSW and a total employment of
approximately 1,500 full-time equivalent jobs.
The proposed CPT will facilitate the continued economic investment by the cruise
shipping industry in a manner which is consistent with statutory planning
documents and strategic plans, and is of a high quality design, which will not have
a detrimental impact on the amenity or environment of the surrounding area.
1.0 Introduction
This Project Application and Environmental Assessment Report (EAR) is submitted
to the Minister for Planning pursuant to Part 3A of the Environmental Planning and
Assessment Act 1979 (EP&A Act). This is to fulfil the Environmental Assessment
Requirements issued by the Director General for the preparation of an
Environmental Assessment to support a Project Application for the construction
and operation of a Passenger Terminal at White Bay Wharf No. 5 (WB5), with
secondary berthing and cruise operations at White Bay No. 4 (WB4), Sydney. The
proposed Passenger Terminal is referred to hereinafter as the Cruise Passenger
Terminal (CPT).
Installation of services.
Refurbishment of existing office and amenities buildings.
A long term carpark with approximately 200 parking spaces in close proximity
to the WB5 CPT.
Works to provide public access to the WB5 CPT building surrounds and berth
face (e.g. stairs, fencing and gates) from either Stephen St or from White Bay
Park.
Use of the CPT facility at WB5 on non-ship days for a variety of functions
such as exhibitions and community and/or corporate events, including the
erection of temporary structures and signage.
This report has been prepared by JBA Urban Planning Consultants Pty Ltd, for the
proponent, Sydney Ports Corporation, and is based on design information provided
by Johnson Pilton Walker architects (JPW) and supporting technical documents
provided by the expert consultant team.
This EAR describes the site, its environs and the proposed development, and
includes an assessment of the proposal in accordance with the Director General’s
Environmental Assessment Requirements issued under Part 3A of the EP&A Act.
It should be read in conjunction with the information contained within and
appended to this report.
Section 3: The current strategic and statutory planning framework and context
applying to the site.
Section 9: Conclusion
The PCT Steering Committee reported in November 2009 that Sydney requires
three (3) Cruise Passenger Terminals to ensure transport growth in the industry,
and that one of these terminals will be a replacement terminal for the existing
Darling Harbour No. 8 (Barangaroo) Cruise Passenger Terminal west of Sydney
Harbour Bridge. The Committee’s studies included a detailed options analysis for
a new Cruise Passenger Terminal west of the Sydney Harbour Bridge, concluding
that the preferred option was the construction of a new purpose built Cruise
Passenger Terminal facility at WB5 with secondary berthing at WB4. It was also
recommended that the new Terminal at WB5 implement a traffic management
solution for passenger vehicle access using James Craig Road to protect local
residents’ amenity.
On 20 December 2009 the Premier announced that the NSW Government had
decided to permanently relocate the Darling Harbour No. 8 Cruise Passenger
Terminal to WB5, in accordance with the recommendation from the PCT Steering
Committee, subject to planning approval being obtained.
Wharf No.5 at White Bay is the preferred location for a replacement CPT in
Sydney Harbour for the following reasons:
the facility would be contained within an existing port precinct;
the site provides a high level of control which will assist in enforcing maritime
security legislative requirements, particularly during instances of heightened
levels of threat;
two cruise passenger ships can be berthed at the same time with the use of
the adjacent berth at WB4, which allows Sydney to continue to provide berths
for up to three passenger ships in port at any one time;
the site includes adequate space for staging and servicing of the CPT;
the site allows flexibility to meet operators space and facility requirements;
the site will be easily accessible prior to cruise ship visits by Shipping Agents
and operators for deliveries; and
the site enables the provision of adequate storage facilities in a secured area.
The domestic (home port) segment of the cruise industry is based at the East
Darling Harbour Passenger Terminal which currently provides adequate space and
facilities for a full exchange of passengers and associated servicing of the ship.
The Overseas Passenger Terminal at Circular Quay is the base for regional and
round the world cruises which occasionally accepts the domestic segment cruises
if the East Darling Harbour Passenger Terminal is unavailable. The East Darling
Harbour Passenger Terminal also accepts a small portion of the regional and round
the world segment cruises subject to the ship being able to meet the height
clearance requirements to pass under the Sydney Harbour Bridge.
The Passenger Cruise Terminal Steering Committee (PCTSC) found that the
Australian cruise industry grew by 18% per annum between 2002 and 2008, with
growth forecast to continue over the next 15 years. In assessing potential
location options for a Cruise Passenger Terminal west of the Sydney Harbour
Bridge, the PCTSC considered forecast cruise ship arrival data based on the
estimated 7% global growth trend and the cruise industry’s forecast. The global
growth forecast estimates approximately 173 cruise ships berthing on the western
side of the Harbour Bridge in 2021/22 while the cruise industry estimates the peak
cruise ship numbers being 157 in 2014/15 and then reducing to 103 cruise ships
in 2021/22. The cruise industry forecast takes into consideration the changing
ship sizes over time as there is an expectation that the existing fleet servicing the
local domestic segment will be replaced by larger (in height) ships. Whilst there is
a need for a cruise terminal west of the Sydney Harbour Bridge it is anticipated
that the number of cruise ships berthing at White Bay could be restricted in the
longer term by the height limitation of the Sydney Harbour Bridge (i.e. the air draft
restriction on ships berthing west of the Bridge).
The forecast cruise ship schedule for the next two years has been obtained from
the Sydney Ports Corporation. The number of cruise ships scheduled to arrive at
Wharf No. 5 – Barangaroo, the interim CPT until a permanent replacement
terminal is built is summarised in Table 1.
Table 1 indicates that over the next 2 years, up to 120 ships per year will use the
CPT, approximately two-thirds of these during the spring and summer months,
with approximately one-third during autumn and winter. Given this and the
forecast cruise ship arrival data growth presented to the PCTSC in November
2009, it is expected that approximately 170 cruise ships per year could use the
proposed CPT.
Table 1 – Forecast monthly cruise passenger ship arrivals for DH5, then White Bay (between July
2010 and June 2012).
Year/Month J A S O N D J F M A M J Total
2010/11 5 8 4 7 11 12 9 16 13 8 5 4 102
2011/12 9 6 8 8 14 17 13 15 11 8 5 3 117
During a typical domestic cruise ship visit, approximately 4,800 passengers and
crew will exchange. A diagrammatic illustration of the inbound and outbound and
passenger process for a typical one day ship visit is provided at Figure 1.
Once passengers are through the Customs, Immigration and Quarantine process,
they proceed to the Arrivals Hall which is accessible to greeting friends, family,
tour operators etc.
Typically, the disembarking process takes place from around 7:30am until
around 11:00am.
From the Baggage Hall, passengers travel via the mezzanine to the gangways
connecting the CPT building to the ship or via the ship’s gangways.
Hours of Operation
The East Darling Harbour CPT facility is permitted to operate on a 24 hour, 7 days
a week basis. The domestic cruise ships typically have a turnaround period of 10-
12hrs, berthing around 6.30am and sailing generally by 6pm. International cruise
ships could berth for up to 72 hours in accordance with Sydney Ports’ protocols.
Ships which berth for more than a day generally only account for around 10% of
the ships berthing on the western side of the Sydney Harbour Bridge.
Vehicle Movements
During a typical domestic cruise ship arrival and departure at East Darling Harbour,
the two way traffic movements are generally from 6:30am to 4:30pm. Within
this period, the traffic generation rates fluctuate. Whilst a domestic cruise ship is
generally berthed by approximately 7.00am, traffic movements in the morning
(resulting from the inbound ships) can be characterised as follows:
“early morning” truck traffic before and after 7:00am;
significant car traffic movements do not occur until after 9:00am; and
peak traffic activity typically occurs between 9:45am and 10:45am.
Peak (ship arrival) traffic generation therefore occurs after the main morning
commuter peak.
A domestic cruise ship generally departs the berth by 6.00pm. Traffic movements
in the afternoon (resulting from the outbound ship) generally occur in the early
afternoon and are generally complete (or minimal) from 3.00pm. Peak (ship
departure) traffic generation therefore occurs prior to the main afternoon
commuter peak.
The international cruise ship arrival and departure times vary however, the vehicle
movements generated are significantly less than the domestic cruise ships due to
the fact that these ships do not undertake a full passenger exchange in Sydney.
Traffic associated with the international vessels is significantly less than traffic
associated with domestic cruise ships with traffic spread out throughout the day
and evenings.
Clause 6 of the Major Development SEPP states that development, which in the
opinion of the Minister is development of a kind referred to in Schedule 1 (Classes
Clause 7 of Schedule 2 of the Major Development SEPP identifies the whole of the
area identified as Glebe Island, White Bay, Rozelle Bay and Blackwattle Bay as a
specified site (as identified on Map 6B of the SEPP) if a proposal has a capital
investment value of more than $5 million.
The proposal will have a capital investment value of more than $30 million, so on
14 May 2010, a delegate for the Minister formed the opinion that the proposed
CPT is a “Major Project” to which Part 3A of the EP&A Act applies.
In accordance with Section 75B of the EP&A Act, and Clause 6 of the Major
Development SEPP, on 4 May 2010 JBA Urban Planning Consultants, on behalf of
Sydney Ports Corporation, requested that the Director-General of the Department
of Planning issue the requirements for the preparation of an Environmental
Assessment Report (EAR) to accompany the Project Application for the proposed
development.
On 7 June 2010, in accordance with Section 75F of the EP&A Act, the
Director-General of the Department of Planning issued the requirements for the
preparation of an Environmental Assessment to accompany a Project Application
for the project.
Table 2 – Relevant provisions Sydney Regional Environmental Plan No26 – City West
Issue Standard
Zone Port and Employment
Permissible uses Uses that facilitate the continuation of the commercial port
uses, employment uses, port and maritime uses
Prohibited uses All uses which do not comply with the objectives of the zone
Initially, the White Bay terminal was used mainly for container traffic, however,
the construction of a dedicated container terminal at Port Botany in the early
1980s saw much of the container trade relocate there. From that time the White
Bay terminal was used for containers and mixed general cargo until late 2004,
when the general cargo operations were consolidated to Darling Harbour.
From 2004 to the present day, the site has been utilised for other port uses such
as the import and exportation of bulk liquids, ship maintenance and lay-up,
temporary car storage and harbour construction activities. Other port uses will
continue at White Bay.
Existing Development
The site is largely reclaimed land and is bounded on the south by an existing
caisson wharf and retaining structure.
Two rows of 35 free-standing trussed columns run towards the east, which
supported an overhead travelling crane (removed circa 1984).
There are a number of ancillary buildings on the site. To the west are:
a small gatehouse;
a small complex with a Sydney Water sewer pumping station, a small two
storey substation and switch room building, a single storey staff canteen and
a single storey fuel tank; and
three small additions attached to the building on its western face – a storage
facility covering approximately 220m2, a 7 metre wide carport and a portable
shed used as an office.
To the north, adjacent the cliff under Grafton Street, are:
a two-storey office building;
a single storey substation building; and
a covered parking area (78 metres long).
To the immediate east of the shed are two water tanks and a pump room. Along
the southern facade are a toilet block (which is to be demolished) and two
substations which are to be retained.
It should be noted that existing port activities and uses at White Bay No.5 will
continue when the WB5 CPT is not in use. Port activities at other White Bay
wharves will continue to occur. In particular WB4 and Glebe Island Wharf 1 will
continue to be used for unloading bulk liquids. Where there is a shipping schedule
conflict between a bulk liquids ship and a cruise passenger ship then the cruise
passenger ship will have preference at WB4.
Figure 5 – Photograph of WB5 taken from an elevated position south of White Bay showing the
context of the site and its proximity to the city
Figure 6 – Photograph of the site looking North West across White Bay from Pyrmont Point Park
Figure 7 – Photograph of the site looking West across Darling Harbour from Barangaroo
Figure 8 – Photograph of the large steel framed shed on site, taken from Grafton Street
Figure 9 – Photograph of the service road on site located between existing building and sites
northern boundary.
Site Access
The site is currently accessed via an internal private road which connects through
to Robert Street (refer to Figure 11). The internal access road is accessed from
Victoria Road via Mullins and Roberts Streets. Victoria Road provides direct
access to the Sydney CBD and the eastern suburbs via the Anzac Bridge to the
east, and direct access to the City West Link, which provides access to the Great
Western Highway and the western suburbs. Victoria Road also provides a link
over the harbour to the north western suburbs.
Figure 11 – Photograph of the existing internal port road which connects to Roberts Street
To the north west of the site, at the top of the cliff is White Bay Park and
Donnelly Street. The residences located along these streets are typically two
storeys, inter-dispersed with single or three storey dwellings.
Figure 12 – Photograph of Grafton Street, looking north easterly from the corner of
Adolphus Street
To the south of the site across White Bay is Glebe Island which was until recently
occupied by Australian Amalgamated Terminals (AAT), as an automotive import
terminal. Automotive imports at Glebe Island ceased in November 2008, due to
the relocation of AAT’s operations to Port Kembla.
Also Glebe Island Wharves 6, 7 and 8 are occupied by dry bulk terminals for
gypsum, cement & sugar which have long term leases on the adjacent sites.
Beyond WB6 to the south east (approximately 400m at the closest point across
the water of White Bay/Johnston’s Bay) is the suburb of Pyrmont. Pyrmont
comprises a range of typically high rise residential/mixed use development.
To the east of the site is WB6, which was subject to a Project Approval for
Baileys Marine Fuels Australia (BMFA) to construct and operate a marine fuelling
facility and marine depot. Sydney Ports considers that a CPT at WB5 would not
be inconsistent with the proposed land use of WB6 as a marine fuelling facility and
maritime depot.
Beyond WB6, across Darling Harbour (approximately 1km), is the development site
of Barangaroo (East Darling Harbour).
To the immediate west of the site is White Bay Wharf No.3 (WB3) which also
remains in port use and is partly subject to this application. Beyond WB3 is the
typically four storey residential flat building development, known as Somerset
Mews (refer to Figure 14), bound by Buchanan Street, Hyan, Palmer and
Booth Street.
Figure 15 – Residential development to the west of the site (setback from WB3).
Heritage Items
There are no listed heritage items at WB5, however the proposed access road will
cross one heritage item, being the Beattie Street Stormwater Channel No. 15
listed on Sydney Water’s Section 170 Heritage Register as being of local
significance (refer to item H10 in Figure 16).
There are a number of heritage items located in the immediate vicinity of the site
(refer to Figure 16), principally along the residential streets located to the north of
the site. In addition to the item described above, prominent identified heritage
items located adjacent to the site are:
H1: Dwellings 3-33 Adolphus Street, Balmain (listed in Leichhardt LEP 2000);
H2: White Bay Park (listed in Leichhardt LEP 2000);
H3: The Grange, 7 Vincent Street, Balmain (listed in Leichhardt LEP 2000);
H4: Ardenlea, 14 Vincent Street, Balmain (listed in Leichhardt LEP 2000);
H5: the sandstone rock cliff (indicated as a landscape heritage item on the
Heritage Conservation Map of the LEP)
H6: White Bay Power Station (listed in State Heritage Register);
H7: Glebe Island Silos (listed in City West REP No. 26 - Sch. 4, SPC S.170
Register);
H8: Sewerage Pumping Station No 7, Robert Street (REP listing & Sydney
Water S.170 Register listing);
H9: Old Glebe Island Bridge, abutments and approach (listed in Leichhardt LEP
2000, RTA S. 170 Register, SPC S.170 Register); and
H11: Hampton Villa, 12B Grafton Street, Balmain (listed in Leichhardt LEP
2000, State Heritage Register and National Trust).
H 12: White Bay Power Station Canal (listed on SPC’s S. 170 Heritage
Register).
Those heritage items located in the vicinity of the site are considered further as
part of the Statement of Heritage Impact prepared by City Plan Heritage, provided
at Appendix G and are identified in Figure 16. Assessment of the heritage impact
of the proposed development is provided at Section 6.6.
H1
H3
H4 H11
H5
H2
H10
H10
H8
H6 H7
H12
H9
Figure 16 – Location of Heritage Items in the vicinity (Source: City Plan Heritage)
In terms of NSW, the following NSW Legislation and strategic policy documents
are of key relevance to the proposed development:
Environmental Planning and Assessment Act 1979 (EP&A Act 1979);
Protection of the Environment Operations Act 1997 (POEO Act);
Threatened Species Conservation Act 1995;
Environmental Planning and Assessment Regulation 2000 (EP&A Regulation);
NSW State Plan;
Sydney Metropolitan Strategy; and
Inner West Subregion, Draft Subregional Strategy.
NSW Sea Level Rise Policy Statement 2009
Action for Air
The following statutory planning instruments and policy documents are of key
relevance to the proposed development:
State Environmental Planning Policy (Major Development) 2005;
State Environmental Planning Policy (Infrastructure) 2007;
State Environmental Planning Policy (Temporary Structures) 2007;
State Environmental Planning Policy No.55 – Remediation of Land;
Sydney Regional Environmental Plan No 26 – City West;
Sydney Regional Environmental Plan (Sydney Harbour Catchment) 2005; and
Glebe Island/ White Bay Masterplan.
Planning for Entertainment Guidelines (Department of Planning, October 2009)
The proposed development has been located and designed to ensure compliance
with the provisions of the Act, particularly with regard to security planning and the
provision of a Land Side Restricted Zone extending 30 metres from the wharf face
and including the Customs and storage and amenities area within the terminal.
All the wharves at White Bay are “Customs Areas” under Section 15 of the
Customs Act 1901. The design of the CPT includes a Cleared Zone which is
physically isolated from all other areas, with access and egress from this zone
through clearly defined control and screening points. Within this zone is the
Baggage Hall which is maintained and managed in accordance with this Act.
The objects of the EP&A Act are listed below, together with consideration of how
the proposed development relates to each of the objects. :
(a) to encourage:
(i) the proper management, development and conservation of
natural and artificial resources, including agricultural land,
natural areas, forests, minerals, water, cities, towns and
villages for the purpose of promoting the social and economic
welfare of the community and a better environment,
The proposal is for the orderly and economic use and development of
land.
The proposal takes into account the protection and provision of utility
services.
The proposal is not for the purpose of providing land for public
purposes, however public access to some parts of the land may
be facilitated at certain times or for certain functions or events.
Under Section 75A of the EP&A Act, a number of authorisations under other NSW
Legislation are not required. These include:
Heritage Act 1977 (Part 4 & s139); and
Water Management Act 2000 (ss89, 90 & 91)
An Environmental Protection Licence exists for operations at WB4 and in the future
a licence may be required for operations at WB6.
The operation of the CPT at WB5 will require ships to be secured with ropes to a
small part of WB6 immediately adjacent to WB5 on the wharf edge. The operation
of the proposed CPT will not require any activities to occur at WB6 which would:
be affected by any Environment Protection Licence for WB6,
impact on the ability of the licence holder at WB6 to comply with its licence
conditions.
In terms of the use of the CPT at WB5 as a function venue, the safety of persons
on site is addressed through Sydney Ports Corporation’s site security and
management procedures and Security Management Plan. Sydney Ports
Corporation will review their Security Management Plan to incorporate function
activities at White Bay.
The draft Strategy also refers to the establishment by the NSW Government of a
Task Force to investigate options for the long-term use of the area, including a
range of wider employment uses. The proposed CPT is not inconsistent with this
draft strategy as it makes use of the deep water commercial berth attributes of
the site. The Government also created the Bays Precinct Community Reference
Group in parallel with the Task Force.
The document doesn't contain any aims and objectives as such, however it
provides an overview of Sydney's current transport issues and outlines a number
of key infrastructure proposals to be implemented over the next decade. The
proposed CPT is not directly addressed in the document nor connected to or
reliant on any of the projects proposed. The CPT would not compromise the
implementation of the plan.
Few of the specific objectives or actions within Action for Air are relevant to the
proposed development. Those that are considered to be relevant relate to
Objective 1, which is to reduce motor vehicle emissions, in part through reducing
vehicle use and through improving and influencing transport choice. Specific
actions include:
These two actions highlight the importance of locating people’s home, jobs and
recreational areas by public transport to reduce car trips. In particular, Action
1.13 notes that the Sydney Metro (Stage 1 – Rozelle to Central) will be the spine
of a new public transport network for Sydney. The proposed CPT has been
designed to protect the route and potential station site for the Central to Rozelle
Metro railway line. The site will also have pedestrian and bicycle connections to
the surrounding area. It is highlighted that because of the nature of cruise
passenger travel, it would not be justified to divert bus routes closer to the site as
the amount of bus patronage would not warrant it.
Further, the location of the cruise passenger facility at WB5 permits the
development of Barangaroo for higher density uses, including residential and
commercial development, which makes better use of the public transport
attributes of that site.
The proposed CPT is development for the purposes of the port facilities, shipping
berths or terminals that has a capital investment value of more than $30 million,
being development that is identified in clause 22 of Schedule 1 of the Major
Development SEPP.
Additionally, under the Major Development SEPP the site is located within the area
identified on Map 6B ‘Port and Related Employment Lands’ under Schedule 2,
‘Part 3A projects – specified sites’, Part 7 ‘Port and Related Employment Lands’
and being a development with a capital investment value of more than $5 million.
Development for a CPT on the proposed site therefore meets the Major
Development SEPP criteria as a major project and as such, on 14 May 2010 a
delegate for the Minister for Planning declared the project a Major Project, and
subject to assessment under Part 3A of the EP&A Act.
The provisions of the Major Development SEPP prevail over the Infrastructure
SEPP to the extent of any inconsistency between the two policies. Therefore,
notwithstanding that the Infrastructure SEPP (Division 13) would permit
development of Port Facilities without the need for development consent, the
assessment regime applicable to the CPT is dictated by the Major Development
SEPP and the proposal is subject to assessment and approval under Part 3A of the
EP&A Act.
As the proposal will have the capacity for 200 or more motor vehicles, the
Infrastructure SEPP (Clause 104) requires that the Project Application be referred to
the Roads and Traffic Authority for comment during the assessment process. The
RTA has been consulted during the preparation of the Project Application and a
traffic impact assessment is discussed in Section 6.4 of this Report and included in
Appendix F. The report concludes that the site is appropriate for its intended uses.
The relevant aims of the SEPP are to ensure that suitable provision is made
to manage matters including noise, parking and traffic impacts and ensuring
heritage protection.
The proposed CPT development includes the installation and use of temporary
terminal structures (i.e. marquee) at WB4, and the relevant matters of
consideration relating to the potential environmental impacts from the operation of
the temporary terminal facility, such as noise, parking and traffic impacts and
ensuring heritage protection have been considered in Section 6 of the report.
The proposed development is consistent with the objectives of the Port and
Employment zone and is therefore permissible with consent.
The proposed CPT will exceed the 12 m height level established by the Glebe and
White Bay Masterplan. However, the proposed CPT will be lower than the height
of the existing high bay structure that it will replace. It is therefore deemed
appropriate for the site.
Sydney Harbour Catchment SREP lists several matters under Division 2 of Part 3
that must be considered during the assessment of an application, these are listed
and considered in Table 4 below.
The Master Plan provides for the continued use of Glebe Island and White Bay as a
significant commercial port facility in Sydney Harbour. The Master Plan sets out
the vision for the future development of Glebe Island and White Bay and a series
of principles and actions in relation to land uses, road and rail infrastructure,
views, building heights and building zones, build quality, environmental controls,
landscaping, pedestrian and cycle links and heritage conservation.
For development at Glebe Island/ White Bay, the Master Plan provides objectives
and guidelines. The relevant principles are considered in Table 5 below.
The proposed development includes the use of WB5 as a function centre on non-
ship days. A ‘function centre’ is defined as follows under the Standard Instrument
– Principal Local Environmental Plan:
a theatre, cinema, music hall, concert hall, dance hall and the like, but
does not include a pub or registered club.
The issues associated with the use of the proposed CPT as a function centre need
to be considered as part of this Part 3A Project Application. The Planning for
The key issues associated with the use of the proposed CPT as a function centre
have been addressed in the relevant section of this EAR. A summary is provided
in Table 6 below.
4.0 Consultation
In accordance with Part 3A of the EP&A Act consultation is required to occur at
the following stages:
the Director General of the Department of Planning is required to consult with
relevant public authorities in preparing the Environmental Assessment
requirements for the Project Application; and
the Director-General is required to advertise and exhibit the Environmental
Assessment and appended reports and documentation.
Sydney Ports Corporation has also consulted with cruise industry representatives
with regard to their operational requirements for the terminal based on
international experience and the existing operations at the Darling Harbour No. 8
(DH8) CPT. Where appropriate, these requirements have been addressed in the
terminal design.
In June 2009 the Minister for Planning established a public consultation forum for
the Bays Precinct, which included the formation of a Bays Precinct Community
Reference Group. Stage 1 of the Bays Precinct consultation was scheduled to
finish in early December 2009 but was extended to the end of March 2010 at the
community’s request. Amongst other things, it gathered information and ideas
from the community, including representatives from Leichhardt Council, in relation
to the location of the Cruise Passenger Terminal west of the Sydney Harbour
Bridge. This consultation process developed a set of draft planning principles for
the consideration of the Bays Precinct Taskforce which ‘set the scene’ for future
planning and development in the area, and informed the Government’s decision to
permanently relocate the CPT to WB5.
In stage 2 of the consultation, expected to occur in the second half of 2010, the
draft planning principles will be exhibited for comment and feedback from the
community will be sought. This feedback will be used to finalise the planning
principles, which will guide all future planning processes for the precinct.
Use of the CPT facility at WB5 on non-ship days for a variety of functions
such as exhibitions and community and / or corporate events, including the
erection of temporary structures and signage.
The design takes advantage of the high-visibility of the site and iconographic
nature of the arrival and departure procession. It invites the opportunity to
welcome and excite visitors with a unique and expressive building. The building
orientates to the significant landmarks of Sydney Harbour and references
significant aspects of site history to create a distinctive sense of place for
the visitor.
The iconographic element of the project is envisaged as a floating roof canopy that
strongly expresses ESD principles including natural ventilation and lighting.
Functional spaces are inserted beneath the roof canopy and within a transparent
pavilion between the rows of existing columns. During the daytime, the dramatic
roof gesture would be visible on approach from the Inner Harbour. During the
night-time, the underside would glow softly.
The existing trussed columns (i.e. the former gantry crane support structure) are
to be retained. Exposure of the trussed columns will create a simple building form,
enclosed within the strong line of trussed columns marching in two continuous
lines from west to east. Where the existing building partially conceals these
columns, the proposed design will expose the full height of each column by
relocating the new walls to the inside line of the columns. Reuse of the trussed
columns also interprets the previous port uses at the site, providing visitors with
an understanding of the nature and scale of port uses and activities.
The general appearance of the columns will remain unaltered, apart from essential
patching, repairs and painting as required.
The columns perform an integral structural role and act as an ordering device
across the site upon which the various new building elements interact and
are supported.
Within the existing framework, a corrugated metal roof is draped from a series of
trusses above, extending across 17 column bays.
The roof form varies in height in response to view considerations of overlooking
residents and internal functional requirements. It generally remains at or below the
height of the existing low bay shed. This variation in pitch heights minimises the
roof reflectance.
Beneath the roof, the arrivals hall and baggage hall areas are clad in clear glass
that wraps continuously around all sides. Two passenger gangways punctuate
the facade, which provide access directly to the ship.
Concentration of lighting on the harbourside and location of building mass on the
northern side minimises light spillage to neighbouring Balmain residents.
The key components of the CPT building and its immediate surrounds are:
Short Term Car Park;
Forecourt;
Arrivals Hall;
Baggage Hall;
Gangway Structure;
Storage and amenities area; and
Ancillary offices, staff and passenger amenities, storage rooms etc.
A landscape zone to the west acts as a visual as well as spatial buffer between
the car park and waiting area. A series of bollards line the edge of the drop
off/pick up area. These provide security from vehicle intrusion and also provide a
transition to the pedestrian zone. A clearance space between the bollards and the
vehicle drop off/ pick up allows adequate space for the movement of people
and luggage.
Arrivals Hall
A broad hall space forms the entrance to the Cruise Passenger Terminal. All
passengers and non-travelling visitors access this space directly from the
forecourt, moving through from west to east. The hall consists of a glazed, open
space that sits within the existing trussed columns with views over White Bay and
to the city beyond. In this expansive hall, a diverse range of uses can be
accommodated. Internal functions will generally match those previously
undertaken at Darling Harbour Wharf No.8. These primarily include processing
cruise passengers and serving as an adaptable space for functions and events.
Along the northern facade, amenities including toilets and plant areas are
contained within a series of highly-finished boxes, inserted between the existing
columns. This rhythm of boxes recalls the historic stacking of shipping containers
along a similar line in the original shed structure. A kiosk is situated along the
southern facade, with seating available both within the hall interior and outside on
an external deck. These are positioned to take advantage of panoramic views of
White Bay and the city.
Baggage Hall
The Baggage Hall adjoins the Arrivals Hall and it similarly consists of a large, open
hall that is glazed along the southern facade to permit views of White Bay and the
city. During ship days, only passengers may proceed to this space from the
Arrivals Hall. Upon departure, ticket processing and Customs checks occur here.
On arrival, this hall is used for bag pick up prior to screening by Australian
Customs. As an uninterrupted space of grand scale, the Baggage Hall also has the
capacity for flexible arrangements tailored to the requirements of specific events
and functions.
A series of boxes contain amenities including toilets and plant areas, as well as a
separate Customs office and AQIS washroom facility for the treatment of potentially
contaminated articles brought by passengers on arriving passenger ships.
A mezzanine is located along the southern face of the Baggage Hall, which leads
into to the main departure areas. This level is accessed by escalator, stairs and a
lift. It can also be used as an elevated function space.
Gangway Structure
Two airport style gangways provide access directly from the mezzanine level of
the Cruise Passenger Terminal to the ship. Two airport style retractable gangways
will be utilised between the CPT and the docked cruise ships. On occasions when
the terminal gangways cannot be used the ship’s gangways will be utilised.
Support Facilities
In addition to the main passenger processing halls and the storage and amenities
area, the CPT includes a number of areas which house ancillary functions,
including:
Australian Customs and Immigration interview rooms;
storage space for shipping service providers and Sydney Ports Corporation;
AQIS wash station (a room) accessible from the Baggage Hall to provide
washroom facilities for the treatment of potentially contaminated articles
brought in by passengers on arriving passenger ships;
public/passenger toilets;
staff facilities, including a meal room and toilet/shower rooms;
Long term car parking providing approximately 200 car park spaces may also be
provided for at the site. These car parking spaces would be used by ship
passengers who chose to drive to the CPT and leave their car while they are away
on the ship, normally about 9-10 days. As such, these car parking spaces would
not be available for any short term car parking use, including for functions, as they
may be occupied by ship passenger’s vehicles.
Figure 17 shows the layout of the terminal building and the key components.
The intent of the area surrounding the CPT is to create a functional landscape that
links the arrival and departure experience between land transport and ship and to
cater for the movement of both large pedestrian groups and small informal
gatherings. The areas surrounding the CPT will mostly be hard landscaped,
consisting of hard, functional surfaces (such as concrete, bitumen or paving), with
components including seating and infrastructure for pedestrian movements. There
will be minimal amounts of soft landscaping, however, where plant material is
proposed it will be low maintenance and distinctive to the Sydney region.
Where the new access road runs parallel close to Robert Street landscaping and a
footpath along Robert St will be provided consistent with the Glebe Island and
White Bay Master Plan and Ports Improvement Program.
A landscape plan for the site will be prepared as part of the detailed design of
the CPT.
In order to provide this new access road Sydney Ports are proposing to move the
existing fence line to the west to align with the Sydney Ports property boundary.
This is required to provide sufficient space within the port area for passenger
vehicle access via James Craig Road. The relocation of the fence will result in the
narrowing of Robert St, south-west of Buchanan Street, as well as the loss of
some on street parking to the south of Buchanan Street being removed. A new
security gate and check point will be provided at the Robert Street entry to the
Port.
Taxis, coaches and cars will access the terminal using the new access road via
James Craig Road. Security checks of service vehicles are performed in the area
of the existing security checkpoint near the Robert St entrance to the site.
Generally, the vehicular circulation has been designed to segregate traffic,
specifically private vehicles, taxis, buses, and service vehicles. Figure 18
illustrates the access routes for each mode of transport.
A full assessment of the impact of the proposed CPT operation on the surrounding
road network is at Section 6.4.
Private Cars
The short term car park including the drop off spaces would be located to the
immediate west of the main terminal building. The access to the short term car
would be located approximately 130m to the west of the terminal building. It
would provide access to the short term car park, as well as the coach drop off
spaces and general public drop off spaces adjacent to the terminal building.
A separate secured area would be available for large trucks (up to 19m semi-
trailers). This area would be located adjacent to the short term car park, and
south of the overflow coach parking area. This area would have six truck bays.
For WB5 new accessible toilets will be located on the ground floor, enabling wheel
chair or others with disabilities to make use of all facilities within the building. For
WB4 accessible toilets will be provided, enabling wheel chair or others with
disabilities to make use of all facilities within the building. Access will also be
provided at wharf level to the terminal building when ship gangways are utilised.
Waste from the cruise ships can be separated between quarantine waste and non-
quarantine waste. Non-quarantine waste will be taken off the ship by regular
waste contractors for disposal at a suitably licensed facility. Quarantine waste
will have different requirements for storage, treatment and disposal and will be
dealt with separately in accordance with those requirements.
5.2.11 Functions
On non ship days, the CPT facility at WB5 will be able to be used for a variety of
functions, with Arrival and Baggage halls within the building having the capacity to
be adapted for functions/events (providing for functions of up to 2,500 persons).
It is also intended to use external areas to the CPT for temporary structures
associated with events including but not limited to stalls, marquees, signage,
temporary toilets and amusement rides. As with the DH8 CPT, it is proposed that
the site be used as a venue for a range of activities when it is not being utilised as
a passenger terminal. The types of functions/events that will make use of WB5
may include:
community and / or corporate events;
exhibitions and conventions;
food and beverage festivals;
film shoots;
product launches;
charity and fundraising functions;
For functions and events, the main elements for which consent is sought for are:
use of the site for functions / events when the site is not being used as a
passenger terminal;
use of internal and external areas of the site from 7am until 11:30pm;
use of internal and external areas for amusement rides no more than 5 times a
year; and
temporary structures and signage for functions / events as required.
Approval is also sought to undertake functions / events outside the above stated
hours of operation for special events (e.g. New Years Eve, Australia Day, etc)
subject to approval by the Director-General of the Department of Planning.
The short term car park will be used for parking associated with events.
Corporate functions would be encouraged to transport patrons via organised
buses/coaches.
The facility will be housed in a marquee or similar structure that would be erected
prior to the arrival of the ship and removed following departure of the ship. The
temporary structure however, may remain erected after a cruise ship departs
should it be required for another cruise ship within the ensuing weeks.
Similar to the WB5 CPT, the WB4 temporary terminal will include:
Arrivals Hall;
Baggage Hall;
Cargo handling area;
Customs and AQIS facilities;
Amenities; and
Storage facilities.
The height (at the apex) of the temporary marquee is approximately 8 m, and it would
be approximately 25m wide. The WB4 temporary terminal will not include gangways
for passenger access to ships. Passengers will access ships directly from the wharf
side using ship gangways.
The approximate location and ship berthing at WB4 are shown in the White Bay
Site Diagram in Appendix B.
The WB4 temporary terminal will accommodate largely the same ship-day
activities as the WB5 CPT (i.e. arrivals, customs and cargo handling) and be
designed to meet the same customs, immigration and quarantine requirements as
the WB5 CPT with regard to Land Side Restricted Zones and Cleared Zones. As
with the security management of WB5, a network of fencing will be installed
around WB4 terminal to meet Port security requirements. Where existing security
fencing at White Bay is of an appropriate standard, reuse of such fencing for the
temporary terminal will be considered.
The WB4 temporary terminal will be accessed via the new access road connecting
to James Craig Road for private vehicles, taxis and buses / coaches.
A Noise and Vibration Assessment of the port activities and traffic was
undertaken by Wilkinson Murray and is included at Appendix D.
A further noise impact assessment has been undertaken by Renzo Tonin &
Associates (provided at Appendix E) for functions/events undertaken in the CPT
and external areas at WB5 and the building’s required acoustic treatment.
To establish a Rating Background Level (RBLs) for the project, the historical noise
data along with data for ambient LAeq has been used. Prevailing industrial LAeq
levels have also been estimated from historical data. Table 10, presents the levels
used to set intrusive and amenity criteria for the proposed development from a
number of locations (refer to Figure 21).
2
1
6
3
5 – off map
Table 11 provides a summary of the project specific noise criteria for the existing
residential receivers surrounding the site. The INP discusses setting a “project
specific noise criteria” that is the intrusive or amenity criterion that is most limiting
on operations.
Locations 1 and 2 would be limited by the night time intrusive criteria. The other
locations would be limited by the night time amenity criteria.
Note: At Locations 1 and 2 it is assumed that this proposal would be the dominant source of
ambient noise. Therefore, the amenity criteria are set at the unadjusted acceptable
levels at those locations. At other locations, the amenity criteria have been adjusted
according to the scale published in the INP to account for the existing ambient noise
(which comes from industrial sources other than the area proposed for the CPT). The
amenity criteria are based on the Urban/Industrial Interface categorisation of the closest
residences facing the port.
Location LAeq
Cruise Ship 107
Large Forklift (diesel, no noise control) 106
Large Forklift (electric, gas, or diesel, no noise control) 95
Gas powered forklift 93
Refrigerated Trucks 103
Car park acoustic centre* 92
Bus acoustic centre (at 30 to 40 kmph) 105
Car (at 40 kmph) 90
*The car park noise was based on the CPT peak traffic generation of 57 cars arriving and leaving
within a typical 15 minute period.
The extent of noise generated by the operation of a CPT, based on the Sound
Power Levels detailed above, will vary over a large range and are dependent on
the receiver’s location and on the activity at the port.
The assessment of the operational noise from the CPT facility considers:
intrusiveness criteria assessment;
amenity criteria assessment; and
cumulative noise with Bailey’s proposal at WB6.
Sleep disturbance impacts were also assessed, and details of this assessment are
provided in Appendix D.
Previously it was discussed that background noise levels in the area are variable.
Hence while intrusiveness assessment is necessary for a complete understanding
of noise emissions, it is considered that the long-term noise impact of the site is
best predicted by assessment against the amenity criteria.
Noise was predicted from ships at berth, miscellaneous sources (car park,
refrigerated trucks and forklifts) and internal roads (including the access road
connecting to James Craig Road).
The extent of the noise from these noise sources has been assessed for still
conditions and with a 3m/s westerly wind. Predicted noise was calculated at the
six assessment locations, and the results are shown in Table 13.
The assessment concludes that at the location closest to the site (Grafton Street),
there would be an excceedance of the intrusiveness criterion of up to 7 dBA
Scenario 1 (Typical Daytime) and up to an 8 dBA exceedance during Typical
Worst Case Daytime and Evening Scenarios (Scenarios 2-4), and 4 dBA for
Scenario 5 (Typical Worst Case Night time). At Donnelly Street there would be
exceedances of up to 3 dBA during the Typical Worst Case Daytime Scenarios 2
and 3. Predicted noise levels for all other scenarios comply with the intrusiveness
criteria at all other locations.
To predict the overall LAeq in these periods the following assumptions were made:
Daytime (an 11 hour period): using the daily traffic profile from the traffic
report, it is predicted that the LAeq,11hour (that is the daytime noise) from internal
traffic alone would be 4dBA less than the LAeq,15min during the busiest hour of
the day. The daytime LAeq is therefore calculated by reducing the noise level
of internal roads and carpark sources by 4dBA. It was assumed that forklifts
and refrigerated trucks would operate till approximately 4.00pm, so their
LAeq,11hr contribution would be 2dBA quieter than the noisiest hour. Ships
would operate continuously throughout the period.
Evening (a 4 hour period): ship operates continuously. In the event that
Providoring needed to continue into the evening period it was assumed that
Providoring would finish by approximately 8.30pm, corresponding to a noise
level contribution 2dBA less than the noisiest hour.
Night time (a 9 hour period): ship operates continuously through the night.
The results of this amenity assessment are provided in full in Appendix D, which
also includes the noise contour maps. Grafton Street (Location 1) was identified
as the critical receptor location in the Intrusiveness Assessment and so the
Amenity Assessment results for Grafton Street are summarised In Table 14 below.
The assessment concluded that there are no predicted exceedances of the
amenity criteria for all six (6) scenarios modelled.
Amenity
Criteria
Analysis of the noise benefits from the above options at Grafton Street concluded
the following:
The 3.5m wall on the northern side of the providoring storage area reduces
noise levels at the most-affected residence by 1 dBA.
Reducing the noise of the large forklift is predicted to reduce overall noise
level by 1dBA;
The sea side barrier on the high bay columns reduces overall noise levels by
less than 0.5dBA (though the difference is less than 0.5dBA, rounding it
shows as 1dBA in the table due to rounding effects);
The land side barrier on the high bay columns provides 2 dBA mitigation to
Location 1; and
The 3 m high Grafton Street clifftop barrier provides at most 1dBA reduction
in the overall noise level.
The preferred suite of noise mitigation measures includes:
A wall on the northern side of the Providoring storage area, forming a 3.5m
high noise barrier;
Maximum sound power level of large forklifts to be 95dBA; and
Only one large forklift in operation at any time.
While the acoustic ‘land-side’ and ‘sea-side’ acoustic barriers would provide some
noise mitigation they would undermine the improvements made to the visual
amenity at the site with removal of the high bay shed and would diminish the
overall quality of the architectural design for the CPT.
For the Typical Worst Case Daytime Scenarios there is predicted to be a small
1 dBA exceedance at Donnelly Street. Predicted noise levels for all scenarios
comply with the intrusiveness criteria at all other locations.
The importance of this proposal is that it could impact on the cumulative industrial
noise level at these residences, as assessed under the amenity criterion in the
Industrial Noise Policy. The inclusion of noise from operations by Bailey’s Marine
Fuels Australia at WB6 would affect the amenity criteria that would be applied to
the White Bay CPT.
During the daytime and evening there would be no affect to the amenity criteria.
If Bailey’s operated at its limit then it would cause the amenity criteria at Location
1 to be reduced by 1 dBA to 49 dBA and at Location 6 to be increased by 1 dBA
to 43 dBA. This would not have any affect on the assessment of the White Bay
CPT in regards to complying with the amenity criteria under the Industrial Noise
Policy.
Based on the traffic generation data prepared by Halcrow (Refer to Section 6.4
and Appendix F) traffic noise has been calculated. The predicted traffic noise level
increase is based on the additional traffic flow on the affected roads, being:
City West Link Rd, West Of The Crescent
The Crescent, South of City West Link Rd
At Anzac Bridge
Victoria Rd, South of Robert St
Because of the very large amount of traffic currently on these roads, the predicted
noise increase from the additional traffic would not be measureable or perceptible
(the theretical increase is less than 0.1 dBA).
The predicted contributed levels from the CPT are at least 12dBA below the
relevant criterion, therefore the predicted traffic noise from the CPT would not
increase the existing noise. If the existing noise were above the criterion, the
contribution of the CPT would increase the noise by less than the 2dBA allowed
by the ECRTN (in fact the increase would be 0dBA). Hence no traffic noise impact
is predicted.
The assessment concludes that the construction noise will comply with the noise
criteria at most times, except during certain stages of the construction works such
as rock breaking and piling activities (which will be minimal), for receptor locations
1,2 and 6.
The Noise Impact Assessment recommends a Construction Noise Management
Plan be developed to minimise noise construction impacts. Measures which will
be adopted to mitigate against the impact of construction activities on site include:
selection of quiet plant and processes;
retrofitting reversing alarms that are quieter and display less annoying
characteristics, such alarms could include “smart alarms” and
“quacker alarms”;
ensuring plant is well maintained and operated;
use of temporary barriers;
positioning of plant / processes; and
limiting the “cluster” of plant / processes.
The DECCW publication Assessing Vibration: a technical guideline (February 2006)
considers impacts from vibration in terms of effects on building occupants (human
comfort) and the effects on the building structure (building damage).
The Noise Impact Assessment in Appendix D estimates, from specified
construction activities, vibration levels at a range of distances from the various
construction activities, based on indicative levels of attenuation. It compares the
predicted levels of vibration against the DECCW guidelines, indentifying that there
could be brief exceedances of the residential goals for human comfort if rock
breaking had to be done at the nearest point to the houses on Grafton Street.
The noise assessment provides an assessment against the relevant noise criteria
set by the NSW Office of Liquor, Gaming and Racing (OLGR) and the NSW
Department of Environment, Climate Change and Water (DECCW.
When the CPT is operating as a function venue, it is anticipated that noise will
essentially emanate from the following sources:
music noise emission from within the terminal building;
patron noise from internal and external areas;
noise from vehicle movement and carpark activities on site;
noise from mechanical plant;
noise from outdoor activities; and
traffic noise.
In particular the OLGR criteria has been applied for event noise associated with
internal building activities and amplified music. Outdoor activities, including traffic
accessing the site via the internal road, have been assessed with consideration to
DECCW’s Industrial Noise Policy.
The noise impact assessment prepared by Renzo Tonin & Associates compares
the predicted noise generated by different noise sources generated by a function
and compares these noise levels against the criteria established by OLGR.
Renzo Tonin modeled various building envelope constructions for different types of
music source, and through an iterative process, identified the required building
envelope construction for the CPT.
The noise impact assessment concludes that double glazed finishes are required to
control music noise breakout from the facility during typical loud events, with the
aim of complying with the standard noise criteria set by OLGR. Double glazing of
the western and northern façade has been incorporated into the CPT building
design as .
During the first outdoor event with significant noise generation, noise testing
should be conducted to confirm noise levels at residences. Noisy activities can be
located strategically to minimise impacts.
The Renzo Tonin & Associates report also recommends that further analysis of
acoustic quality, reverberation control, speech intelligibility, mechanical services
noise, hydraulic services noise, and the like should be conducted during the
detailed design of the development.
Noise levels from car park activities and vehicles travelling on the private port
access road are predicted to comply easily with the day, evening and to just
comply with the night time criteria. This is based on an estimated maximum
traffic flow of 400 vehicle movements per hour based on an event for 500
attendees, assuming all attendees arrive by private vehicle. Where a function
larger than 500 people is proposed, or where a significant number of buses may
be used, the operational times of the function and the staging of vehicle arrivals
would determine whether traffic noise would exceed the criteria. Further
consideration of traffic noise management will be carried out as part of the Traffic
Management Plan for functions of greater than 500 people.
Renoz Tonin has assessed a range of amusement rides and outdoor music
scenarios. This assessment shows that some amusement rides and low level
background music could be acceptable as long as they are strategically located.
Because noise from car park activities is expected to easily comply with the INP
criteria during the day and evening periods up to 10pm, it would be possible to
add noise from several amusement rides to car park noise and still comply with the
INP criteria up to 10pm.
Based on the previous usage of the Wharf 8 Darling Harbour site, amusement
rides are proposed to operate up until 11pm on occasions, up to 5 times per year.
The background noise levels at Grafton and Donnelly Streets between 10pm and
midnight are only 1dB(A) lower than the evening background noise levels and
therefore in terms of the INP assessment, noise impacts would not increase
significantly between 10 pm and 11pm. However, to avoid sleep disturbance
issues where amusement rides will operate after 10pm, they will only be located
between the terminal building and the water.
Due to the strategic location of mechanical plant at ground level on the south side
of the storage and amenities area, and since it is well removed from the car park,
plant noise is not expected to significantly add to the total site noise at residences.
In any case, if noise reduction was required to prevent cumulative impacts, this
reduction could be readily achieved using standard noise control treatments and
commonly available building materials.
The PCT Steering Committee Part A Report (November 2009) recommended the
permanent CPT proposed for the western side of the Sydney Harbour Bridge be
located at WB5 based on, among other reasons, that access to the new facility
could be provided via James Craig Road. This Report also identified the potential
for some traffic access to the WB5 CPT to be provided via Robert Street subject
to a traffic impact assessment being undertaken.
Hence, this EAR assesses the impact of constructing a new access road via James
Craig Road to provide passenger access (i.e. private vehicles, taxis and buses /
coaches) to the new CPT with service vehicles (i.e. providoring trucks, staff
vehicles, etc) accessing the new facility via Robert Street. In order to provide this
new access road Sydney Ports are proposing to move the existing fence line to the
west to align with the Sydney Ports property boundary. This is required to provide
sufficient space within the port area for passenger vehicle access via James Craig
Road. The relocation of the fence will result in the narrowing of Robert St, south-
west of Buchanan Street, as well as the loss of some on street parking to the south
of Buchanan Street being removed. A new security gate and check point will be
provided at the Robert Street entry to the Port.
Table 16 – Two Way Traffic Movements (6:30am to 4:30pm) associated with a cruise ship visit at
Darling Harbour
During a typical cruise ship arrival and departure, the two way traffic movements
are from 6:30am to 4:30pm. Within this period, the traffic generation rates
fluctuate. Whilst a cruise ship is generally berthed by 7.00am, traffic movements
in the morning (resulting from the inbound ship) can be characterised as follows:
Taking into account the additional allowance of 20 per cent applied to the above
peak hour terminal traffic on a typical ship day, the proposed CPT would generate
some 205 vph during the morning peak period and about 36 vph in the evening
commuter peak period.
Cruise ship visits are envisaged to amount to approximately 170 visits per year,
with more frequent cruise ship visits occurring around the summer months. This
corresponds to the period of the year where overall traffic volumes are generally
lower due to school, university and work holidays.
On days when the CPT is not required for cruise ships, it is intended to be made
available for a range of other activities and functions. The traffic associated with
“events usage” is dependent on the activities and functions that are undertaken.
This is discussed further in Section 6.4.4 below.
The future traffic impacts have primarily been assessed in terms of the likely
future traffic flow and the impact of the level of service (LoS) of local
intersections.
The peak hourly flow on James Craig Road are expected to increase by 176 vph,
during the morning peak and 29 vehicles during the evening peak because of the
proposed CPT. The balance of the vehicles associated with the WB5 CPT,
approximately 29 during the morning peak and 7 during the evening peak, would
be providoring vehicles which would continue to use Robert Street.
The intersection analysis results for the current operation of the intersections
indicate that the nearby assessed intersections currently operate satisfactorily at
LoS D or better during the peak periods except for the Victoria Road-Robert Street
intersection which operates at LOS F during the morning peak. These results are
shown in Table 17 and are generally consistent with observations made on site for
both peak periods.
The intersections were then analysed with traffic from the subject proposed
development added to surveyed intersection flows. All the assessed intersections
would continue to operate with the same level of service, which is also shown in
Table 17.
Table 17 – Intersection Analysis Results
There may be instances when cruise ships are berthed at both WB4 and WB5
however their arrival and departure times will not coincide because of logistics
around berthing two ships in adjacent berths in a relatively confined area of the
harbour. Given this, having two cruise ships berthed at White Bay is unlikely to
create a cumulative traffic issue and has not been considered further.
The cumulative development traffic is expected to be about 440 vph and 270 vph
during the morning and evening peak periods respectively. Of this traffic around
375 vph and 225 vph (in the morning and evening peak periods respectively)
would be restricted to James Craig Road. The balance of 65 vph and 45 vph
(in the morning and evening peak periods respectively) would comprise providoring
vehicles and the traffic from the Baileys Marine depot, and these would use
Robert Street.
These results are presented in Table 18 below, and are summarised as follows:
Under the cumulative future traffic conditions, the James Craig Road
intersection would continue to operate satisfactorily at LoS D during the
morning peak, but it would operate at LoS F during the evening peak period.
The Victoria Road-Robert Street intersection would operate at similar
intersection levels to those that currently occur.
The two The Crescent intersections would operate at LoS E (with average
intersection delays close to LoS D) during the morning peak period and LoS
C/D during the evening peak period. The RTA defines LoS E operation as
being at capacity for signalised intersections without requiring intersection
capacity upgrade until the performance worsened to LoS F.
The Mullens Street-Robert Street intersection would continue to operate
satisfactorily with LoS D or better.
The upgrade to James Craig Road would require turn lines on the intersection
pavement, overhead lane direction plus signage and advanced lane direction
signage in James Craig Road. It would also require The Crescent, directly
opposite to James Craig Road, to be widened into the disused goods railway yard
by about 2m with an additional pavement area of about 50m2. The stop line
facing eastbound traffic on The Crescent would also need to be relocated by
about 2.0m to the west. This would result in the intersection performance
improving back to LoS D or better. The proposed improvement work at the
Victoria Road-Robert Street intersection would result in the intersection
maintaining similar level of service to existing conditions.
The results for the analysis incorporating the above proposed improvements are
presented in Table 18 below.
The above improved level of service assumes retention of the existing signal
timing for the James Craig Road intersection. However, the operation of James
Craig Road approach would be improved further (in the evening peak period) if it
was to receive slightly more green time. This is a matter for the RTA in managing
overall traffic flows.
The Consent Conditions for the function use at the DH8 required quarterly
Compliance Summary Reports to be submitted to the Department of Planning
summarising the events held for the quarter. The summary reports were required
to provide information relating to the number of patrons permitted, results of noise
level measurements and the traffic impacts to the surrounding area. Appendix F
includes a summary of events held at the DH8 Passenger Terminal facility for the
12 month period ending March 2009. There were 29 events held during this
period. The majority of these related to conference or dinner/cocktail party type
events. Of the 29 events, a total 14 events started or finished during the
commuter peak periods. Of these 14 peak period events, nine events had
attendances of 400 persons or less.
As on ship days, James Craig Road would be used to provide access when the
White Bay CPT was used for an event (excluding bump-in and bump-out related
traffic). On some occasions, event traffic may enter and/or exit the White Bay
CPT via Robert Street. This will be determined on a case by case basis and is only
likely to occur when an event finishes outside the commuter peak period or when
it is a very small event (e.g. a film shoot). This will be addressed in the Traffic
Management Plan to be prepared for functions held at the site.
For traffic analytical purposes, a daytime event (e.g. conference) with 500
attendees starting and finishing during the commuter peak periods was assumed
to undertake capacity analysis of the surrounding intersections. Modal splits were
estimated to predict traffic flow of approximately 180 car movements per hour
plus 215 drop-off movements (private vehicles and taxis). This is equates to
approximately 290 vph arrivals and 110 vph departures in the morning period. In
the evening the arrivals and departures were predicted to be reversed.
The proposed 200 space car park would be sufficient to accommodate parking
demand arising from a 500 person event.
Intersection analysis was repeated for the three intersections along The Crescent,
taking into account the cumulative traffic impacts from other developments, with
the results shown in Table 19.
Table 19 – Intersection Analysis Results from Cumulative Traffic Assessment for Functions
The results indicate that the City West Link Road and Victoria Road intersections
with The Crescent would operate with LoS E in the morning peak period and LoS
D or better in the evening peak period. The James Craig Road intersection would
operate with LoS D or better in the morning peak and LoS E during the evening
peak period.
As stated above the site will have limited onsite parking and this would need to be
considered for all events with more than 500 attendees. Should functions /
events with more than 500 attendees be proposed to start of finish during the
morning or evening peak traffic periods (i.e. 8am – 9am or 5pm – 6pm; Monday
to Friday) a further traffic impact assessment will be undertaken and
recommendations incorporated into the Operational Environmental Management
Plan.
For events with more than 500 attendees at any one point in time, a separate
transport management plan will be prepared given there are limitations on parking
on the site which would necessitate the need for special transport arrangements
to be made. The transport management plan will have regard to:
start and finish time;
day of the week;
expected arrival and departure pattern of patrons/visitors;
the need for shuttle services to/from public transport nodes or remote parking
areas; and
limit parking on site to pre-booked patrons only.
Sydney Ports has committed to ensuring no more than 20 events in any calendar
year would have more than 1500 attendees on site at any one point in time. It is
also estimated that the facility could be used for up to 50 functions / events a
year subject to the facility not being required for port operational purposes (e.g.
cruise ship processing).
Construction traffic would access the site via Robert Street from Victoria Road,
and it is expected that the Baileys Marine depot would be operational by the time
construction activities start on the White Bay CPT site.
Intersection capacity analysis was repeated for the Victoria Road and Mullens
Street intersections with Robert Street operating during the construction phase,
indicating that construction traffic would only marginally affect the Robert Street-
Mullens Street intersection during the construction phase.
Cruise passengers are unlikely to make significant use of public transport because
of their need to carry luggage. Some employees working in the terminal would
use public transport. This number would be relatively small and would not
generate a need for enhanced public transport in the area.
The route and potential station site for the now deferred Central to Rozelle Metro
railway line have been protected. The proposed development would not inhibit
this system in anyway.
On non ship days, the terminal would be available for other uses such as film
shoots, community events, conferences or functions. The impact of these on the
local road system would depend on starting or finishing times. Transport
management plans will be prepared for any uses with simultaneous attendances of
more than 500 persons.
The overall traffic and transport aspects of the proposal are considered to
be satisfactory.
Public access to the CPT building surrounds and the berth face would be made
available on non-ship days during daylight hours. Public access to the WB5 site
during a function which is not a public or community event would be with the
agreement of the individual hirer / lessee. Public access to the WB5 site would be
provided once the terminal was operational.
In the 2007/08 year a total of 356 ship calls occurred at Glebe Island / White Bay.
Of these, 261 ship calls related to vehicle carriers, and this trade relocated to Port
Kembla in late 2008. With the relocation of vehicle carriers to Port Kembla, the
number of vessels using the berths has increased. In 2008/09 a total of 673 ship
calls occurred at Glebe Island / White Bay and in 2009/10 there were a total of
591 ship calls.
Sydney Ports’ Harbour Control is responsible for managing the safe movement of
all commercial ships visiting the ports of Sydney Harbour and Botany Bay.
Harbour Control closely monitors the movement of all commercial ships within the
ports using radar, Automatic Identification System (AIS), CCTV and VHF radio in
order to avoid any adverse interaction between commercial ships, including cruise
ships and other ships (e.g. recreational boats) on the harbour.
All cruise ships visiting the CPT will also have a Sydney marine pilot onboard for both
the inward and outward movement. The Sydney marine pilot uses his / her local
knowledge and experience to advise the Master of the cruise ship on the appropriate
course, speed and tug positions throughout the movement. This is consistent with
all other movements of commercial ships of this size in Sydney Harbour.
The existing aids to navigation are adequate for the proposed cruise ships and no
additional aids are required.
Robert Street would have a carriageway width of 10.3 metres which would allow
for two way traffic and bicycle movement as well as the potential to provide
approximately 25 car spaces parked parallel to the kerb.
There is also the potential to park approximately 50 cars on Robert Street north of
Buchanan Street. These appear to be used by local residents living in adjoining
buildings who use it as overflow parking. This parking, which is on Sydney Ports
land, is only available because the property security gate is located 50 metres
north of its property boundary at Buchanan Street. These spaces will not be
available under the proposed arrangement.
The impact from the proposed development will significantly improve views as
illustrated in the Built Form Statement provided at Appendix C and reproduced in
Figures 21 to 30 below. In some of the montage views, examples of ship types
that are expected to berth at the CPT under a range of berthing scenarios (i.e. 0, 1
2 cruise ships) have been included. The impact that a cruise ship has on views is
however, limited to times when the ship is berthed at White Bay.
To address each of these views and vistas montages have been developed for the
following views:
Views down Adolphus Street and Grafton Street to demonstrate the impact
of the development on views from residential streets in Balmain looking
towards Pyrmont and Anzac Bridge. These address view corridors 3 and 4
above.
Views from White Bay Park towards Pyrmont and the city skyline have been
provided to address view corridors 1 and 2 above.
A view from Pyrmont Park has been provided to address view corridor 6
above.
A view from the Anzac Bridge has been provided to address view corridor 5
above.
A view from Barangaroo has been provided to illustrate the views across the
water towards White Bay as well as to demonstrate the impact to views from
the city towards White Bay, showing the context of the Anzac Bridge, the
White Bay Power Station and the Heritage Silos. This view has been
provided to address view corridor 7 above.
The impact of a ship berthed at WB5 will be similar to the impact of the high bay
shed in restricting views, however this impact will be limited to times when the
ship is berthed at White Bay 5.
The presence of a cruise ship at WB5 would periodically block the views from
Grafton Street towards Glebe Island and the Anzac Bridge, however this impact
will be limited to times when the ship is berthed at White Bay 5. A ship at WB5
would not block the more regional views towards the southwest.
The presence of a second cruise ship at WB4 would infrequently block the views
from Grafton Street towards the White Bay Power Station and regional views to
the southwest, however this impact will be limited to the infrequent occasions
when the ship is berthed at White Bay 4.
No montage has been provided, however views from White Bay Park southwards
towards Glebe Island and Anzac Bridge would be blocked by the infrequent
berthing of a cruise ship at WB4.
Figure 24 – Montage view from Adolphus Street, Balmain (with cruise ship)
Figure 27 – Montage view looking south west along Grafton Street (with cruise ship)
Figure 28 – Montage view looking south west along Grafton Street (with 2 cruise ships)
Figure 31 – Montage view from White Bay Park (with cruise ship)
Pyrmont
Figures 32 to 35 show the impact to views looking from Pyrmont Park towards
the Balmain skyline. The removal of part of the high bay shed structure reduces
the bulk and scale of the development and allows the development to sit below
the skyline. The retention and reuse of the trusses emphasise the historical
attributes of the site, adding interest to the view.
Cruise ships would periodically hinder the view between Pyrmont and parts of the
Balmain skyline, however this impact will be limited to times when a ship is
berthed at White Bay 5 and/or White Bay 4.
Barangaroo
Figures 36 to 39 show the impact to views looking from Barangaroo towards the
Anzac Bridge, Balmain and beyond. The removal of part of the high bay shed
structure reduces the bulk and scale of the development and allows the
development to sit below the skyline.
The presence of one or two cruise ships would periodically hinder the view of the
westerly skyline from Barangaroo and the city, however this impact will be limited
to times when the ship is berthed at White Bay 5.
Neither the berthing of one or two cruise ships at WB5 and WB4 would affect
views from the city and Barangaroo towards the Anzac Bridge, the Glebe Island
Grain Silos or the White Bay Power Station.
Anzac Bridge
Figures 40 to 42 show the impact to views looking from the western end of
Anzac Bridge towards White Bay and Balmain. Because of the height of the
bridge, the high bay shed structure currently sits below the skyline formed by the
Balmain peninsula.
The berthing of cruise ships at White Bay will affect the view corridor between
Balmain and the Anzac Bridge, but will not affect views between the Anzac Bridge
and the Sydney Harbour Bridge, the City, Barangaroo and Pyrmont.
6.5.3 Lighting
The majority of ship visits will occur during daylight hours. However, lighting will
be required for the operation of the CPT during cruise ship visits and the operation
of the CPT building for functions / events. Light fittings for the subject
development will be designed to prevent obtrusive and upward spill light being
seen directly from the vantage points identified above (Adolphus Street, Grafton
Street and White Bay Park). This will apply to internal lighting, external lighting of
the buildings and general external lighting of public spaces, roads and car parking.
Existing light fittings and towers will remain unaltered (other than those being
removed). For all new works, no internal light fittings will be directly visible from
outside. Whilst lit surfaces will be visible through glazed portions of external
walling, the extent of this light will be such that it does not constitute an adverse
impact, particularly on nearby residences as the lighting will be below the street
level of Grafton Street.
Selected portions of the external structure may be floodlit for emphasis and to
assist way-finding for patrons. Unobtrusive feature lighting of the cliff face will be
provided to highlight this natural attribute of the site.
New lighting to general external areas, such as public spaces and car parking, will
have fittings which minimise the possible viewing of the lamps from outside the
site. The design of lighting will comply with relevant Australian Standards for the
control of the obtrusive effects of outdoor lighting and other relevant standards.
6.5.5 Conclusion
From every vantage point, the proposed terminal will improve the visual amenity
of WB5. The reduction in the built form and removal of the cladding of the high
bay shed, results in the new terminal sitting almost entirely within the outline of
the existing low bay shed and below the skyline when viewed from the water.
The proposed development improves the views across the site from the
surrounding areas. In particular, the improved view afforded to the public from
White Bay Park, will allow visitors to the park to be able to enjoy greater views
towards the water and city beyond. From this vantage point, the western elevation
of the new terminal presents a different perspective of a working harbour.
From certain vantage points, in particular public areas, the presence of a cruise
ship on occasions will add visual interest and reinforce the maritime role of
Sydney Harbour.
The statement of heritage impact also considered the potential for archaeological
remains on the site. However, given the majority of the site is comprised of
reclaimed land, the assessment report concluded that the potential for
archaeological remains is generally low and therefore no further investigations will
be undertaken for the proposed development.
The White Bay Port area is historically significant as a site of continuous maritime
industry since the middle of the 19th century. Construction of the container
terminal to accommodate containerisation, then considered to be a revolution in
shipping industry, marked the beginning of the first regular international container
shipping service in the world.
The site is also historically significant for its contribution to the development of
worker’s housing around the White Bay foreshores of Balmain.
international containerised shipping service in the world. The site demonstrates all
phases of use and change relevant to shipping and transport since its construction
and has historical importance in the late 20th century for the shipping industry
of Sydney.”
The proposed development will not impact on any jetties, seawalls, slipways or
potential marine archaeological sites and therefore no further assessment has been
undertaken.
Indirect Impacts
The heritage assessment identifies that the most important aspect of the site is
the views and vistas including panoramic view corridors across the site that are
enjoyed by the adjoining residential neighbourhood, the White Bay Power Station
and Glebe Island. The reduced height of the proposed CPT building will
reintroduce city views currently obstructed by the existing high bay area of the
cargo shed (refer to Section 6.5) and increase the extent of views to and from
significant buildings within the vicinity, such as the heritage listed terraces along
Adolphus Street, which will have a positive impact. When a cruise ship is docked
at WB4 and / or WB5, the taller ships may obscure views to and from heritage
items within the site’s vicinity however, this impact will be temporary. It should
also be noted that other commercial ships will continue to berth at White Bay,
which includes White Bay Wharves No. 4 and 5, and other port activities will also
continue to be undertaken even with the proposed CPT in operation.
The assessment concludes that the proposed redevelopment of the site will have
no adverse impact on significant cultural values associated with the place and the
surrounding area. The assessment of significance demonstrates that the existing
structures have no significant cultural values worthy of conservation. Their
demolition will not erode the potential to maintain the historical importance of the
site within the shipping industry of Sydney or Australia, as well as nearby heritage
items or the interpretation of the intangible historic associations of the site.
Heritage Interpretation
The proposed WB5 CPT has been designed to interpret the previous port uses at
the site by:
incorporating and utilising the former gantry crane support structure (i.e.
trussed columns);
maintaining existing operational structures/markings along the southern edge
of the Wharf and the railway tracks from White Bay (where possible); and
incorporating container like design features within the terminal building.
H3 The Grange, 7 Vincent Street, Views from the end of the street will
Balmain be improved.
H4 Ardenlea, 14 Vincent Street, Views from the end of the street will
Balmain be improved.
H8 Sewerage Pumping Station No The new road will not restrict views to
7, Robert Street the Sewerage Pumping Station
H9 Old Glebe Island Bridge, The proposed road works at the top of
abutments and approach road Sommerville Road will be carried out
adjacent to the Bridge approach,
however there is already a road in
existence at the same location and any
further impact to the Bridge is
negligible.
H10 Beattie St Stormwater Channel While the channel is currently crossed
No.15 by several roads and concrete slabs
along its route, the new access road
will cross the stormwater channel at a
location where the channel is exposed.
The details of the crossing of the
stormwater channel will be agreed with
Sydney Water during the detailed
design of the road.
H11 Hampton Villa Proposal will slightly improve Hampton
Villa’s visual relationship with the
harbour and is therefore a positive
measure.
H12 White Bay Power Station Canal The new road will not physically
impact or restrict views to the Power
Station Canal.
6.6.3 Conclusions
The conclusions of the assessment of heritage significance are that the proposal
will have a positive impact on places of heritage significance in the vicinity of the
White Bay Port Precinct because it will:
Enhance the harbour foreshore and provide the required cruise facilities;
Allow for the appreciation of significant places and views from public places
to the harbour foreshore;
Maintain and further improve the key attributes of views from the surrounding
neighbourhood including but not limited to Balmain Peninsula, White Bay
Power Station, Glebe Island and Old Glebe Island Bridge;
Retain some historically significant features at the site that relate to the former
container terminal activities (primarily the gantry crane support columns); and
Interpret the significant historical and natural qualities of the site by continuing
the long-standing maritime use of the site.
The heritage impact assessment recommends that the site be subject of
a photographic archival recording prior to demolition or the removal of
structures occurring.
Modelling Scenarios
The modelling scenarios undertaken as part of the Air Quality assessment are
as follows:
A large passenger ship at berth at Wharf No. 5 for 12 hours per day (6 am –
6 pm) for up to 170 days per year, plus a medium passenger ship at Wharf
No. 5 for 72 hours on 3 occasions per year (ships not at berth at the same
time); and
A large passenger ship at berth at Wharf No. 5 for 12 hours per day (6 am –
6 pm) for up to 170 days per year, plus a medium passenger ship at berth at
Wharf No. 4 for 12 hours (6 am – 6 pm) for 10 days per year (ships at berth
concurrently).
A large passenger ship at berth at Wharf No. 5 for 12 hours per day (6 am –
6 pm) for up to approximately 170 days per year, plus a large passenger ship
at Wharf No. 5 for 72 hours on 3 occasions per year (ships not at berth at the
same time).
No scenario has been modelled where two ships are concurrently berthed at WB5
and WB4 outside of the hours of 6am to 6pm as this will not be a normal or likely
operating scenario. There are however circumstances when it would be possible
that two cruise ships would be concurrently berthed outside of the hours of 6am
to 6pm. These circumstances include when:
There is one international ship staying overnight and one domestic ship which
is delayed in arriving in port (and therefore delayed in departing the port)
which extends its occupation of a berth at White Bay beyond 6pm. This
situation would only occur if the domestic ship was subject to adverse
weather conditions or mechanical difficulties, leading to a second ship in port
outside of the hours 6am-6pm. However, in this situation the ship would still
only be in berth for up to 12 hours.
There is one international ship staying overnight and one domestic ship which
is required to stay overnight. This would only occur in exceptional
circumstances due to major mechanical failure, quarantine or immigration
requirements.
There are two international ships which require overnight berthing at White
Bay. This is considered highly unlikely situation as it would mean that there
was no domestic cruise ship berthed at WB5 and that the 2 international
cruise ships were capable of fitting underneath the Sydney Harbour Bridge.
There is also the possibility of a bulk liquids vessel being berthed at WB4
concurrently with a cruise passenger ship being berthed at WB5. The concurrent
berthing during the day is not considered to be significantly different from
Scenario 3. The concurrent berthing of a bulk liquids vessel and a cruise
passenger vessel at White Bay over a 24 hour period or longer is not expected to
occur due to the preference, in the event of a shipping conflict, that Sydney Ports
will give to cruise passenger vessels at WB4.
The Pacific Dawn was used as an example of a large passenger ship, and the
Nautica was used for a medium passenger ship.
Emission Rate
Ship emissions for existing and future scenarios were determined using the National
Pollutant Inventory Emission Estimation Technique Manual for Maritime Operations
Version 2.0 (2008). The emission factors (NOx, PM10 and SO2) relate to emissions
from auxiliary engines. The ships modelled in the air quality assessment, however,
run a single main engine while at berth. Emisisons were estimated by multiplying
emission factors by the engine power operating while at berth.
It is noted that emissions of SO2 are a function of the fuel sulphur content.The
weighted average fuel burn emission factor assumes a sulphur content of 2.4 %.
Fuel consumption data have also been obtained from Carnival and Oceania
Cruises. At idle, the average fuel consumption of cruise passenger ships has been
stated at approximately:
1.8 tonnes per hour for ships equivalent to the Pacific Dawn; and
0.9 tonnes per hour for ships equivalent to the Nautica.
On the basis of 2.4% sulphur content in the fuel, the SO2 mass emission rates
are calculated to be 24 g/s and 12 g/s for the Pacific Dawn and Nautica
respectively. These results are reasonably consistent with the results determined
using the NPI method.
Note 1: Background concentrations were determined using the Ozone Limiting Method which
uses background levels of ozone (O3) and NO2 to estimate the conversion of NOx to
NO2. The background concentrations of NO2 vary across a broad range, and were
reported within the Sinclair Knight Merz report between 15 µg/m3 and 162 µg/m3.
The focus of the air quality assessment relates to the operation of the auxiliary
engines to provide power to the ship while it is berthed. Compliance with the
DECCW air quality goals would also meet odour impacts in relation to ship
emissions, and there are no other activities which would generate odour.
Air emissions from up to 150 trucks per day are not expected to cause significant
air quality impacts in the context of daily traffic movements across Anzac Bridge
of more than 130,000 vehicles, and daily traffic movements on the City West Link
of more than 65,000 vehicles. As such emissions from vehicles for the CPT have
not been assessed further. There are no ship board generators or onboard waste
incineration while at port and so these have not been included in the air quality
assessment.
Construction of the proposed CPT is not expected to result in adverse air quality
provided the recommended mitigation measures are implemented.
6.8 Contamination
It is not anticipated that there will be extensive excavations proposed as part of
the construction of the CPT, since the majority of the support structures and
footings are already in place and will be reused to support the new CPT building.
However there will be some piling and excavation required to provide additional
support for certain elements of the terminal e.g. gangway and mezzanine level.
Due to these data gaps the following is proposed for the portion of the site west
of White Bay 3 (Buchanan Street) to Glebe Island Wharf No.8 (in front of the
Glebe Island Silos);
• A limited intrusive contamination assessment will be undertaken for any
excavations 1 metre below the existing ground level in this portion of the
site. This depth takes into account the depth of the hardstand on this
portion of the site. The limited intrusive contamination investigations
would be carried out prior to the commencement of the relevant
excavations.
• Given the high variability in groundwater conditions across the site, it is
proposed that should groundwater be encountered in this portion of the site
during construction and dewatering is required, a groundwater assessment
will be undertaken. The groundwater assessment would be carried out prior
to any dewatering taking place.
Taking into consideration the surface is to remain as hard standing and the lack of
extensive excavations proposed as part of the development the site is likely to be
deemed suitable for the proposed development (with respect of contamination).
Considering this CES do not feel that the Stage 2 Detailed Site Investigation would
be required.
6.9 Stormwater
There are currently two stormwater pipes that cross the WB5 site, conveying
stormwater from Balmain to the harbour. These existing pipe systems running
north to south on the site will be protected during construction of the proposed
development. Soil and water management measures will be implemented to avoid
runoff into the harbour during construction works. These measures will be
provided in the Construction Environmental Management Plan, and will include:
Measures to control erosion of soil and sedimentation in accordance with the
principles and practices in Soils and Construction (Landcom, 2004).
Measures to prevent spillage of any substances, and appropriate
clean-up measures.
The majority of the site is very flat and it is perceived that most drainage occurs
via sheet flow to White Bay with areas of undrained ponding and some areas
picked up by minor drainage linking to the existing main pipe systems. In addition
to the two Council stormwater pipe systems that convey water from upstream,
there are also 3 existing 600mm stormwater pipes which convey stormwater from
the site to the harbour.
Run-off from the roof of the proposed CPT Building will be directed into rainwater
tanks and then re-used for toilet flushing and irrigation for landscaping on site.
In addition, stormwater flows from minor storms up to the 3 month ARI storm
event will be collected and directed to bioremediation swales located within the
landscaped areas adjacent the proposed carpark.
Similarly, for the coach parking area, suitable gross pollutant traps will be retro-
fitted to the existing stormwater system to treat run-off from this area prior to
discharge to White Bay.
Stormwater overland flows from the Stephen Street and Grafton Street
catchments currently flow around the eastern and western ends of the existing
building on the site. For the proposed CPT and carpark it is intended largely to
maintain this arrangement, so it is expected that that the overland flow situation
will be similar to pre-development conditions.
Hazardous Materials
Asbestos is known to have been used in a number of the buildings on site. As
part of on going health and safety site management undertaken by Sydney Ports,
Noel Arnold and Associates have prepared an Asbestos Management Plan.
The Management Plan, prepared for WB3-6, documents the location of asbestos
and provides management and emergency procedures which are to be followed
when dealing with the material.
In carrying out any works in locations where asbestos is known to have been used
(including works proposed under this Project Application), the appropriate
procedures, as detailed in the Asbestos Management Plan will be followed.
As part of the bunkering process, Sydney Ports staff ensure a safety checklist is
completed by the cruise ship and barge prior to the start of the transfer operation.
This is to address safety issues (for example protocols concerning pump rates,
communications, emergency shutdown, etc). Random audits are also conducted
by Sydney Ports on the transfer operation.
1
Source: ‘Economic Impact of the Cruise Shipping Industry in Australia, 2007‐08’, conducted by the AEC
Group on behalf of Cruise Down Under and the Commonwealth Department of Industry, Tourism &
Resources.
Overall there may be minor changes to the greenhouse gas footprint of the CPT as
a result of the relocation of the facility, particularly associated with vehicle
movements journeying to and from the facility. As discussed in Section 6.4,
public transport is less accessible at the proposed White Bay location and
therefore it is anticipated that there would be an increase in private car usage to
the facility. Notwithstanding this, a number of elements of the proposed White
Bay CPT will assist in managing the greenhouse gas footprint of the facility when
compared with the previous operational DH8 facility. These include the provision
of approximately 200 long term car parking spaces on the site which will reduce
the number of overall vehicle trips to the CPT associated with picking up and
dropping off passengers, as well as the incorporation of the ESD initiatives in the
terminal design, as outlined in Section 6.12.
During the detailed design of the project, an assessment of the inclusion of further
sustainability initiatives such as further energy efficiencies and water reduction will
be undertaken and incorporated into the facility. The design will achieve the
equivalent of a minimum green star rating of 4.5 star.
The proposal is located within an existing port area, providing for the continuing
use of the port for maritime purposes. The site and its surroundings have been
heavily modified from their natural state to accommodate existing ports and
surrounding urban and industrial uses. The proposal will not result in serious or
irreversible damage to the environment.
The proposal is for the continuing maritime uses of the port and will not affect the
future health, diversity or productivity of the environment. Reuse of an existing
port site will avoid the need to impact an undeveloped harbour foreshore site for
the proposal.
The proposal will not affect biological diversity and ecological integrity of the site
and its surrounds. Reuse of an existing port site will avoid the need to impact an
undeveloped harbour foreshore site for the proposal.
Environmental factors have been considered in the strategic planning for the
proposed development. Reuse of an existing port site will avoid the need to
impact an undeveloped harbour foreshore site for the proposal and will allow the
Barangaroo site, which is located closer to employment and public transport, to be
used for higher density residential and commercial purposes.
Visual O Visual impact from local From the vantage points which overlook the site, the proposed terminal will 4 1 5
residences, public open improve the visual amenity of WB5. The reduction in the built form and (low/medium)
spaces and waterways removal of the cladding of the high bay area of the cargo shed, results in the
new terminal sitting almost entirely within the outline of the low bay shed
and below the skyline when viewed from the water.
Heritage C+O Impact on heritage items The details of the design for the crossing of the Beattie Street Stormwater 1 2 3
crossed by the new access Channel by the new access road will be agreed with Sydney Water. (Low)
road Retention of features of the former container terminal.
Impact on heritage items in The proposed development represents a continuation of the long-standing
the vicinity. maritime use of the site.
Heritage significance of
the site
Air Quality C+O Decrease in air quality The proposed development is not expected to significantly change pollution 1 4 5
levels in the area. (Low/medium)
Biodiversity C+O No significant impact Given the developed nature of the site and current and historical uses, there 1 1 2 (Low)
identified are not likely to be any significant impacts on any threatened species,
populations or ecological communities or their habitats.
Contamination C Exposure of contamination Contamination levels have been assessed as being likely to be below those 1 2 3 (Low)
or hazardous materials considered to be a risk for commercial and industrial purposes.
during construction Procedures for management of any contaminated or hazardous materials will
be addressed as part of the construction management plan if contamination
is identified during construction.
Water Quality C+O Deterioration in water During construction, erosion and sediment controls will be undertaken in 1 2 3 (Low)
quality in White Bay accordance with the construction management plan.
Stormwater from the car, bus and taxi parking areas will be collected and
treated prior to discharge into the Harbour.
Cruise ship operations while at port will be subject to standard SPC
requirements.
Discharge of any ballast water will be as per standard AQIS requirements.
Waste C+O Generation of waste Waste management would be addressed as part of the Construction and 1 1 3 (Low)
Operational Environmental Management Plans. This would include initiatives
such as:
Investigate the use of recycled materials in construction materials;
Maximisation of the recycling of wastes where possible; and
All waste for disposal would be removed by a licensed waste contractor
and disposed of at a licensed landfill facility.
Greenhouse C+O Potential increase in Provision of approximately 200 long term car spaces to reduce vehicle tip 1 1 2 (Low)
emissions numbers
Incorporation of ESD principles in the design of the CPT.
Key: C – Construction, O: Operation
Development will be carried out generally as described in the White Bay Cruise
Passenger Terminal, Environmental Assessment Report, prepared by JBA Urban
Planning and dated September 2010.
Objective Action
Environmental Management
Manage hours of Standard hours of construction are 7.00am –
construction work to 6.00pm Monday to Friday and 8am to 1pm on
minimise impacts on the Saturdays, with no work on Sundays or public
community holidays. Works which are not audible at the
nearest residence could be undertaken at any
other time, e.g. to minimise impacts on existing
traffic. For any construction works outside of
standard hours which are audible at residences,
approval would be sought from the Director
General.
The Construction Environmental Management
Plan (CEMP) will outline protocols for notifying
local residents prior to any works audible at
residences occurring out of standard
construction hours should such works be
required.
Minimise impacts of CPT A CEMP will be prepared and implemented to
construction on amenity guide construction activities as outlined below in
in surrounding areas the following areas:
Traffic & Pedestrian Management
Dust
Air Quality
Soils & Contamination
Water Quality
Noise & Vibration
Heritage
Landscape & Visual
Hazardous Materials
Waste Management
Energy and Water
Consultation
Objective Action
All plans and strategies would be developed as
part of the CEMP, in consultation with the relevant
agencies.
Objective Action
Soils and Contamination
Prevent exposure to A management plan for dealing with any
contaminated soils unforseen contamination, which may arise
during construction, will be prepared as part of
the CEMP prior to the invasive works or
excavations being carried out.
A limited intrusive contamination assessment
will be undertaken for any excavations 1 metre
below existing ground level in the western
portion of the site (i.e. between Buchanan Street
and Glebe Island Wharf No. 8). The intrusive
contamination assessment will take place prior
to the commencement of the relevant
excavations.
If groundwater is encountered during
construction in the western portion of the site
and dewatering is required, a groundwater
assessment will be undertaken. The
groundwater assessment would be carried out
prior to any dewatering taking place.
Water Quality
Prevent any water Soil and water management measures will be
pollution of White Bay detailed in the CEMP and implemented to reduce
the potential water quality impacts from site
works during construction.
Measures to control erosion of soil and
sedimentation will be implemented prior to
construction works. These measures will be
prepared in accordance with the principles and
practices in Soils and Construction (Landcom,
2004) and will be maintained and monitored
during the construction phase.
Measures to prevent spillage of any substances,
and appropriate clean-up measures will also be
outlined in the CEMP.
Separate OEMP’s may be prepared for the CPT at WB5, the temporary CPT’s at
WB4 and the function and event operations.
Table 26 – Environmental Management Measures - Operational
Objective Action
Environmental Management
Minimise impact of the Separate Operational Environmental
Cruise Passenger Terminal Management Plans (OEMP) will be prepared and
operations on surrounding implemented for WB4 and WB5 to guide
area operational activities. They will include:
Environmental Management
Traffic, Transport & Pedestrian Movement
Air Quality
Water Quality
Noise & Vibration
Heritage
Landscape & Visual
Objective Action
Waste Management
Energy & Water Consumption, and Greenhouse
Emergency Response
Security and access control
Community Consultation
Objective Action
proposed CPT; and
Manage long term parking arrangements
which will need to be implemented prior to the
operation of the long term car park.
The TMP will be prepared in accordance with
SPC’s TMP Guideline (2007).
Objective Action
Use of quieter or alternative reversing alarms
on mobile plant and equipment permanently
on the site;
Appropriate training of all staff in relation to
noise issues;
Maintenance of internal roads;
Community consultation program, including
24 hour hotline number for complaints;
Procedures for responding to complaints; and
Nominated responsibilities for noise control
during operation, and response to complaints.
Objective Action
Objective Action
provisions of the Maritime Transport and
Offshore Facilities Security Act 2003 and
Customs Act 1901.
A security management plan will be prepared
and implemented prior to functions being held
at WB5, which will include general security
procedures, management of unacceptable
patron behaviour, responsible service of
alcohol, security guard personnel requirements
and evacuation procedures in the event of an
emergency (such as a fire).
Consultation
Effective consultation with The OEMP will outline measures for effective
the community consultation with the local community and
will include:
Use of the existing Glebe Island and White
Bay Community Liaison Group to discuss CPT
related issues;
Ongoing maintenance of phone line to provide
opportunity for community input;
A complaints handling procedure to address
and respond to issues raised by the
community.
Use of Sydney Ports’ website for the provision
of public information.
9.0 Conclusion
The proposed CPT facilitates the ongoing servicing of the cruise ship industry in
Sydney by maintaining facilities to accommodate three passenger cruise ships in
port at any one time.
The proposed CPT is consistent with the statutory instruments, continuing the
maritime and port operations on the site and related activities, as well as providing
jobs and direct investment in NSW.