Automation of 11kv Substation Using PLC and Scada at Gndec Ludhiana A Case Study IJERTV3IS110830
Automation of 11kv Substation Using PLC and Scada at Gndec Ludhiana A Case Study IJERTV3IS110830
Automation of 11kv Substation Using PLC and Scada at Gndec Ludhiana A Case Study IJERTV3IS110830
ISSN: 2278-0181
Vol. 3 Issue 11, November-2014
Abstract-. The paper presents the use of SCADA (Supervisory Automation at the substation is done by the use of
Control and Data Acquisition) and PLC (programmable logic programmable logic controller (PLC) and supervisory control
controller) in substation for the purpose of automation. At the and data acquisition (SCADA) instead of electromechanical
substation the power is managed between the generator set and devices. As the technology advances the human involvement
the main incomer supply. In the power management, the control
become less and degree of automation will correspondingly
of low voltage and turn on the generator set automatically which
is installed at the substation in case of low voltage and monitors get greater. Now, in global economy automation employs an
all electrical parameters on PC by using SCADA is done. PLC increasing important role in our daily life.
is a programmable logic controller which controls the voltage in
substation. SCADA define as a centralized system that control II. PLC AND SCADA
and monitor the whole substation. SCADA system interact with
PLC for the implementation of whole process. The application PLC is a solid state device stands for Programmable Logic
implemented in PLC is on ladder logic using unity pro software Control. The function of the PLC is to performs the various
RT
and SCADA software used is vijeo citect . logic function previously accomplished by the devices such
as electromechanical relays, switches for the control and
Keywords— SCADA and PLC.
operation of equipment. It is control system designed for the
automation. The PLC is real computer in which it is capable
IJE
I. INTRODUCTION
of receiving data via inputs their sending commands by its
Substations forms a very important node in the transmission output Even though the electromechanical relay have served
and the distribution of electrical power system. Substation is good for many generation, often under adverse condition, but
the most important part of the power system, also needs the devolpment of modern technology equipments requires
automation. The main function of substation is to receive faster response, which electromechanical relays cannot offer.
energy transmitted at high voltage from the generating station Most of the PLC programmed works on the “on” and “off”
to a value appropriate for local distribution and provide state and these corresponds to true or false in logical form
facilities for switching. A substation is the convenient place and 0 and 1 in binary form. There are different types of PLC
for setting up the synchronous condenser at the end of available in market such as Siemens, Schneider, Omron etc.
transmission line for the purpose of power factor we are using the Schneider PLC for the automation purposes
improvement. The combination of all the equipments which because the simulation can be done without connecting the
are used to change the characteristics (e.g. voltage, frequency, PLC but this is not possible in case of Siemens. PLC can
p.f, etc.) of electrical supply is known as substation. transfer collected data to other devices and receive data and
Automation is the process of automatically controlling the control commands from various devices by a serial port.
process parameters in the plant with the help of automation There are also different types of the Schneider PLC which are
devices. In the beginning, process at the plants was as under:
supervised manually based on the instrument installed in a. Twido PLC
fields. This requires the plant supervisor to be placed in plant b. ZELIO PLC
at all time. But the automation has helped to overcome this c. M340 PLC
problem. Now, in global economy automation plays
increasingly important role. Automation doesn’t necessarily Among the different types of PLC we are using M340 PLC as
imply computerization, it can be pneumatic, mechanical, it has many advantages over the Twido and ZELIO PLC. In
electronic or combination of all these. It is not only a part of the M340 PLC we can increase the number of input and
industry today. The process in the substation includes the data output by increasing the number of racks. A PLC can be
acquisition, supervision of power system, and control of programmed to sense, control and activate various
power system equipments. All these processes work equipments. Thus, PLC includes a number of input output
collectively in a coordinated automatic mode. The signals or points which allow interfacing of electrical signals. First the
the message is produced automatically and then delivered in input and output components are connected to PLC and then
the same manner as the field supervisor provided commands. the control program is loaded onto PLC memory.
In the figure (a) the programming is done to compare the Animation Tables
voltage between the different phases. The animation table is used to display the values of the
variables used in the programming. To run the program
without connecting the PLC, the values of various parameters
are forced into the animation table. With the help of these
values we can run the project in the software part. The values
of all the variables or the parameters are of integer type or
bool type values.
b. SCADA SCREEN
Vijeo citect software of SCADA is used for the online
monitoring and control of various electrical parameters.
Window overview of SCADA Software:
RT
IJE
ACKNOWLEDGEMENT
RT
The author is thankful to Harmeet singh Gill , Assistant
Professor at Guru Nanak Dev Engineering College, Ludhiana
for giving good suggestions during our work that enable us
IJE
REFERENCES
1. Mladen Kezunovic, “Developing future substation automation
strategies: selecting appropriate IEDs and developing new
Figure(f) SCADA screen of incoming supply voltage applications”.IEEE Conference, Page 1-8,1995.
2. David j.dolezilek, “Power System Automation”, IEEE transaction on
industrial electronic,vol.53 no.4 page(s) 1066-1073, August 2006.
In figure (f) the readings of the meters like phase to phase 3. R. P. Gupta, “Substation Automation Using IEC61850 Standard”,
voltage, cureent values ,kwh consumption are shown on Fifteenth National Power Systems Conference (NPSC), IIT Bombay,
SCADA screen. December 2008.page 462-466.
4. Dr. Salih Mohammed Salih IEEE Member , “Practical Implementation
of SCADA System for Falluja Substation” AJES-2009, Vol. 2, No. 2
pages 29-46.
5. Roshan Bhaiswar Ambarish A. Salodkar Pravin Kshirasagar,“Power
Management using PLC and SCADA” International Journal of
Engineering Innovation & Research Volume 1, Issue 1, ISSN : 2277 –
5668.
6. Solomon Nunoo., Joseph C. Attachie, “An Investigation into the
Causes and Effects of Voltage Drops on an 11 kV Feeder”,Canadian
Journal on Electrical and Electronics Engineering Vol. 3, No. 1,
January 2012.
7. Julio GONZALO GARCÍA Mariano GAUDÓ NAVARRO Javier
COCA ALONSO, “Smart Secondary Substation Management
Device”,22nd International Conference on Electricity Distribution,
Pages(s): 2530-2535, June 2013.