Ashwani Report
Ashwani Report
Ashwani Report
COMMERCIAL BUILDING
B.Tech. Report
RRRRAJT
ASHWANI KUMAR
By
ASHWANI KUMAR RAJTU
(Registration Number: 15000936)
JULY-AUG 2018
1
INDUSTRIAL TRAINING REPORT ON
COMMERCIAL BUILDING
A Report
BACHELOR OF TECHNOLOGY
By
ASHWANI KUMAR RAJTU
(Registration Number: 15000936)
July-Aug 2018
2
Copyright © AP GOYAL SHIMLA UNIVERSITY
SHIMLA, (HP), INDIA, Year
3
AP GOYAL SHIMLA UNIVERSITY
DECLARATION
I hereby certify that the work which is being presented in the project titled
“COMMERCIAL BUILDING” in partial fulfillment of the requirements for the award
of the Degree of Bachelor of Te chn ol o g y an d submitted in the Civil Engineering
Department, AP Goyal shimla university , is an authentic record of my own work carried out
during a period from JULY 2018 to AUG 2018 under the supervision of Er. Parveen Talwar,
Rampur .
The matter presented in this project report has not been submitted by me for the award of any
other degree of this or any other Institute/University.
This is to certify that the above statement made by the me is correct to the best of my
knowledge.
Date:
(Er. Parveen Talwar)
The Industrial training report Viva-Voce Examination of Ashwani Kumar Rajtu, has been
held on
4
TRAINING CERTIFICATE
5
ACKNOWLEDGEMENT
I would like to express my gratitude to all those who gave me the possibility to complete this
project. I want to thank the Department of Civil Engineering and construction and maintenance
section of “AP GOYAL SHIMLA” for giving me such a golden opportunity to commence this
project In the first instance. I have furthermore to thank the “J. Er. PRAVEEN TALWAR” who
encouraged me to go ahead with my project
I am deeply indebted to our training in-charge at sight engineer who help, stimulating suggestions
and encouragement helped me in all the time at the training site and also for writing this report.
Also I am thankful to site engineer for helping me understanding the process of construction.
My colleagues from the Civil Engineering Department supported in my project work. I want to
thank them for all their help, support, interest, valuable hints
Especially, I would like to give my specially thanks to my parents whose patience love enabled
me to complete this work. And at last but not the least I would like thank God for the successful
completion of my project.
6
ABSTRACT
7
LIST OF FIGURES
1 Concrete mixture 17
2 Reinforcement bars 26
3 Column reinforcement 28
4 Column formwork 29
6 Rectangular columns 31
10 Chairs 35
11 Coarse aggregate 36
12 Concrete cover 37
13 Vibrator 38
14 Ducts 38
8
LIST OF TABLE
3 Column dimensions 31
9
TABLE OF CONTENTS
1 Introduction 12
2 Aim 14
4.3 Excavation 20
4.5 Footing 22
10
4.5.6 Steel form work 30
5 Column 30
6.2 Spacer 33
7 Slabs 33
7.2 Chairs 35
7.3 Cement 35
7.3.1 Aggregate 36
8 Vibrators 37
9 Ducts 38
10 Expansion joints 39
11 Brick work 39
12 Conclusion 41
13 Reference 42
11
INTRODUCTION
Building construction is the process of adding structure to real property. The vast majority
of building construction projects are small renovations, such as addition of a room, or
renovation of a bathroom. Often, the owner of the property acts as laborer, paymaster, and
design team for the entire project. However, all building construction projects include
some elements in common - design, financial, and legal considerations. Many projects of
varying sizes reach undesirable end results, such as structure collapse, cost overruns,
and/or litigation. For this reason, those with experience in the field make detailed plans
and maintain careful oversight during the project to ensure a positive outcome.
The most popular method of residential construction in the United States is wood framed
construction. As efficiency codes have come into effect in recent years, new construction
technologies and methods have emerged. University Construction Management
departments are on the cutting edge of the newest methods of construction intended to
improve efficiency, performance and reduce construction waste.
TYPE I
– This concrete and steel structure, called fire resistive when first built at the turn of the
century, is supposed to confine a fire by its construction. This type of construction in
which the building elements listed in IBC Table 601 are of non-combustible materials,
such as concrete and steel. The roof is also of non-combustible material, such as concrete
or steel.
TYPE II
– This type of building has steel or concrete walls, floors, and structural framework
similar to type I construction; however, the roof covering material is combustible. The
roof covering of a type II building can be a layer of asphalt waterproofing, with a
combustible felt paper covering. Another layer of asphalt may be mopped over the felt
paper.
TYPE III
– This type of constructed building is also called a brick-and-joist structure by some. It has
masonry-bearing walls but the floors, structural framework, and roof are made of wood or
other combustible material; for example, a concrete-block building with wood roof and
floor trusses. Fire-retardant-treated wood framing complying with IBC Sec. 2303.2 shall
be permitted within exterior wall assemblies of a two-hour rating or less.
TYPE IV
– These buildings have masonry walls like type III buildings but the interior wood consists
of heavy timber. In a heavy-timber building, a wood column cannot be less than 8′′thick in
any dimension and a wood girder cannot be less than 6′′thick. The floor and roof are plank
board. One difference between a heavy timber type IV building and type III construction
is that a heavy-timber type IV building does not have plaster walls and ceilings covering
the interior wood framework. The details of type IV construction shall comply with the
provisions of 602.4.1 through 602.4.7. Fire-retardant-treated wood framing complying
with IBC Section 2303.2 shall be permitted within exterior wall assemblies with a two-
hour rating or less.
TYPE V
– Wood-frame construction is the most combustible of the five building types. The interior
framing and exterior walls may be wood. A wood-frame building is the only one of the
five types of construction that has combustible exterior walls. This is the typical single-
family home construction method. These buildings are built with 2 x 4 or 2 x 6 studs and
load-bearing walls, wood floor trusses, or wood floor joist and wood roof framing.
13
2. Aim
The aim of this report is to apprise you about the practical experience gained by us from
on going project activities during the package of CESIP(Civil Engineering students
internship Program)
15
vii.Unconfined compression test.
viii.Consolidation test
b) Timber formwork
c) Polly wood formwork
2. Steel formwork
28,25,20,16,12,10,8 Mm
3. Proportioning concrete
Concrete mix design are often given by a ratio:
16
1. 8 bags of cement
2. 0.445m3 sand
3. 0.67m3 (20mm) stone aggregate
Part of our design for this project is to develop mix ratios that led to high compression
stresses at failure.
The two criteria for a successful mix ratios are:-
17
4.0 PROCEDURES FOLLOWED DURING CONSTRUCTION OF
BUILDING
Below are the step by step processes which are performed during different phases of
construction.
The site needs to be cleaned and levelled before further processes. Sometimes the site may
not need levelling. All of this depends on the planning of construction.
Excavation is the digging of trenches in the ground for making it ready for the foundation
substructure of the building. After excavating the ground, a layer of PCC (Plain cement
concrete) is laid in the dug portion before placing the reinforcements for foundation.
Foundation
Foundation is the lowermost part of the building that is contact with the soil. It transfers
the load on the building from the superstructure to the soil and needs to be extremely
strong to handle the load. The reinforcement for the foundation is then prepared after
excavation and concreting is done. The level of base of foundations should be checked
before pouring the concrete. The earth filling is done in the excavated portions after the
concrete foundations stabilize.
Once the foundation is built, the ground beam reinforcements are prepared and then
concreting is done. Later masonry is done above the ground beam and concreting of plinth
beam is done above that. The void between the foundation and plinth level is filled with
compacted soil.
Superstructure – Column
After the plinth slab is cured then the main structure for the house is started. The columns
are brought up and the frame for further construction is prepared.
Masonry
The walls are later prepared with different materials such as bricks, concrete blocks, fly
ash bricks etc. according to the prepared drawing. Masonry work is carried out with
18
cement mortar. Cement mortar is a mixture of cement & sand. Then gaps are laid for
doors and windows during the masonry work.
Lintels are prepared with reinforcement and concreting to support the masonry work over
the doors and windows.
The masonry work is completed. Then the slab for upper floor is prepared with the beams
resting on the concrete columns. The reinforcements for beams and slabs are assembled
and then in a single day the concrete is poured. Later curing is done.
Once, the covering is prepared with walls and structure, the door and window frames are
installed. Later the doors and window panels are fixed without finishes.
Rough ins
The electric and plumbing cables and pipes are installed in the walls and slabs such that
they are concealed and not visible after the finishing work is done. The cables and pipes
are left out protruding such that later they can be finished with the electric fitting and
plumbing fixtures.
Exterior finishing
The exterior plastering and painting is also started once the superstructure is ready. Water
proofing is also done to prevent weather effect. Cladding can also be done to enhance the
elevation of the house.
Water proofing is done on the terrace and usually terrazzo tiles are applied on the slabs to
keep prevent passage of heat.
Internal finishing
The walls are plastered and the flooring is levelled and tiling is done. Later on the walls
are painted and tiled.
19
Wood work and Fixture fittings
Once the construction process is done. The furniture work is started. Side by side, electric
lights, switch boards and other electric fixtures are fitted. And plumbing fittings are
complete in the bathrooms and kitchen areas too.
Interior decoration is the last step in completing the house with proper furnishing and
fabric use.
A string line is used is used to distinguish the dimension of the building layout
A sledgehammer is used to sink corner stakes or batter boards and posts.
A posthole auger is used to dig the holes required to set posts properly in some soils.
A chalk line is used to deposit chalk on the surface in order to make a straight line.
A plumbing bob is used to locate the corners of the building dimensions.
A line level has a sprit bubble to show levelness. The level is huge from a Taut Line. A
100-foot/30-meter tape is used for measuring diagonally (usually in a 100foot length) and
for laying out excavation or foundation lines.
4.3 EXCAVATION:
Excavation is the process of moving earth, rock or other materials with tools, equipment
or explosives. It includes earthwork, trenches, wall, shafts, tunnel-ling and underground.
Excavation has a number of important applications including exploration, environmental
restoration, mining and construction. Among these, construction is one of the most
common application for excavation. Among these, construction is one of the most
common application for excavation. Excavation is used in construction to create building
foundations, reservoirs and roads. Some of different processes used in excavation include
20
trenching, digging, dredging , and site development. Each of these processes requires
unique techniques, tools machinery o get the job done right. The processes used will
depend upon the structure that will result from the construction process.
Mechanical: This method employs the use of mechanical like hydraulic excavation like
JCB 3CX & L&T Komatsu for the purpose of excavation.
Manual: In this method the manpower is used for the purpose of excavation using various
instruments like towel etc. It preferred only in the case where mechanical excavation
cannot be carried out since it is time consuming.
Measure out one side. Place stakes at each end, oriented as desired. It is important that the
stakes lie among the same edge, namely, corners 1 & 2, not corners 1 & 4. Bang in the
stakes using hammer or equivalent tool.
Use the Pythagorean Theorem to determine where to place the last two stakes for a 90
degree triangle, a^2+b^2=c^2 where c is the hypotenuse.
4.5 FOOTING
In simple terms the bottom most part of a vertical structure (column) which ultimately
transfers the weight from walls and columns to the soil or bedrock is referred as footing.
This is a part of foundation of any modern structure. Depending on the type of element to
be supported and total designed load soil bearing capacity, footings are divided in several
types.
Below is an image of typical footing of column:
22
Another footing of a typical load bearing wall
Soil type
Site condition (topography/slope, water content/food plain)
Type of construction
Magnitude of the load and intensity
Economic and other construction considerations
Type of building
The possible effect of whether element e.g. rain, snow
23
4.5.2 Types of footing used
1. Spread or isolated footing
2. Combined footing
The isolated footing is one of the most popular and simplest types of foundation used
worldwide. An isolated footing is used to support a single column. Isolated footings are
independent footings which are provided for each column.
The Isolated footings essentially consist of a bottom slab. There are three basic types
of bottom slabs are:
24
Isolated footings can have different shapes in plan, generally, it depends upon the shape of
cross section of the column.
Square footing
Rectangular footing
Circular footing
2. Combined footing
Whenever two or more columns in a straight line are carried on a single spread footing, it
is called a combined footing. Isolated footings for each column are generally the
economical.
Combined footings are provided only when it is absolutely necessary, as When two
columns are close together, causing overlap of adjacent isolated footings Where soil
bearing capacity is low, causing overlap of adjacent isolated footings Proximity of
building line or existing building or sewer, adjacent to a building column.
1. When two columns closely spaced that separate footings overlap or are of uneconomic
proportions.
25
2. An exterior column footing that cannot be made symmetrical because of property line
limitations or other restrictions in these situations, the area required to provide isolated
footings for the columns generally overlap. Hence, it is advantageous to provide single
combined footing; in some cases the columns are located on or close to property line . In
such cases footing cannot be explained on one side. Here the footings of exterior and
interior columns are connected by the combined footings. Combined footing essentially
consists of a common slab for the column it is supporting. These slabs are generally
rectangular in plan. Sometimes they can also trapezoidal in plan. Combined footings can
also have a connecting beam and arrangement, which is similar to an inverted T-beam
slab.
26
Reinforcing steel bar specification and theoretical weight
A Ton
Cross Weight
Theoretical Contains
Diameter Sectional of 12m
Item Weight 12m
(mm) Area Bar
(kg/m) Bars
(mm2) (kg)
(pcs)
RSB-
6 28.27 0.222 2.664 375.38
6
RSB-
8 50.27 0.395 4.74 210.97
8
RSB-
10 78.54 0.617 7.404 135.06
10
RSB-
12 113.1 0.888 10.656 93.84
12
RSB-
14 153.9 1.21 14.52 68.87
14
RSB-
16 201.1 1.58 18.96 52.74
16
RSB-
18 254.5 2 24 41.67
18
RSB-
20 314.2 2.47 29.64 33.74
20
RSB-
22 380.1 2.98 35.76 27.96
22
RSB-
25 490.9 3.85 46.2 21.65
25
RSB-
28 615.8 4.83 57.96 17.25
28
RSB-
32 804.2 6.31 75.72 13.21
32
RSB-
36 1018 7.99 98.88 10.43
36
RSB-
40 1257 9.87 118.44 8.44
40
Features
Reinforcing steel bars are mainly used in construction industry, manufacture of anchor
bolts, masonry structures and so On.
After the PCC is laid the layout for lying reinforcement is made using cement mortar
subsequently, reinforcement is laid for the foundation and the column which is connected
by by a beam in case of combined footing.
This consist of panels fabricated out of thin steel plates stiffened along the edges by
small steel angles. The panel units cab be held together through the use of suitable clamps
or bolts and nuts. The panels can be fabricated in large number in any desired modular
shape or size . Steel forms are largely used in large projects or in situation where large
number reuses of the shuttering is possible. This type of shuttering is considered most
suitable for circular or curved structures.
The joints in the formwork should be tight against leakage of cement grout.
The formwork should be set accurately to the desired line and levels should have plane
surface.
The material of the formwork should be cheap, easily available and should be suitable
for reuse.
Propping and centering
Shuttering
Cleaning and surface treatment
29
Small Steel plates:
5. Columns:
Columns support vertical loads from the floor and roofs slabs and transfer these loads to
the footings. Columns usually support compressive loads with or without bending.
Depending on the magnitude of the bending moment and the axial force column behavior
will vary from pure beams action to pure column action. Column are classified as short or
long depending on their slenderness ratio. Short columns usually fail when their materials
are overstressed and long columns usually fail due to buckling which produces secondary
moments resulting from the P –D effect. Columns are classified according to the way they
are reinforced into tied and spirally reinforced columns. Columns are usually reinforced
with longitudinal and transverse reinforcement. When this transverse reinforcement is in
the form of ties. The columns is called “tied”. If the transverse reinforcement is in the
form of helical hoops, the column is called “spirally reinforced”.
Since failure of column often cause extensive damage, they are designed with a higher
factor of safety than beams.
30
5.1 Types of columns :
Long column or slender
Short column
Intermediate column
A column may rectangular, square, circular, or polygon in cross – section
Here, in this project we have used one type of column which is rectangular further details
are provided in the table as follows:-
Beams are horizontal members above which the slabs are provided. The beams are
supported on wall and columns. The M20(1:1.5:3) grade concrete is used in beams with a
clear cover of 25mm on each side. Different sizes of beams are used in the buildings.
a. DESIGN OF BEAM:
Beams is a member which transfer the loads from slab to columns and then foundation to
soil.
Beams is a tension member.
Span of slabs , which decide the spacing of beams.
b. SIZE OF BEAM
40x60
35*50
That’s for resist diagonal tension stress and in order to prevent inclined cracks to occur by
action of maximum shear stresses which concrete fails to resist.
32
6.2 SPACER:
To provided cover at the bottom of the beams they are rested on small pieces of different
dia bars such as 20mm and 25mm with maintains the spaces between formwork and
beam, and thus a clear cover is provided at the bottom of beams, these small pieces of
different dia bars are known as spacers.
7. SLABS:
A concrete slab is a common structural element of modern buildings. Horizontal slabs
of steel reinforced concrete, typically between 4 and 20 inches (100 and 500 millimeters)
thick, are most often used to construct floors and ceilings, while thinner slabs are also
used for exterior paving. Sometimes these thinner slabs, ranging from 2 inches (51 mm) to
33
6 inches (150 mm) thick, are called mud slabs, particularly when used under the main
floor slabs or in crawl spaces. In many domestic and industrial buildings a
thick concrete slab, supported on foundations or directly on the subsoil, is used to
construct the ground floor of a building. These can either be "ground-bearing" or
"suspended" slabs. The slab is "ground-bearing" if it rests directly on the foundation,
otherwise the slab is "suspended". For double-storey or multi-storey buildings.
Slab in this project is 15cm thick in which M20 (1:1.5:3) grade concrete is used. A clear
of 20mm is given to main reinforcement
Two way slab is used in this project. In this project main reinforcement is used is 10mm
dia. Bars and Distributions bars of 8mm dia.
34
Bent up bars:
The additional length for one bent up to be taken=0.6D Where D=total depth of beam or
slab –bottom and top cover
EXTRA BARS
Extra bars of 8mm diameter are also provided. Length of bars is 1.60m
7.2 CHAIRS:
7.3 CEMENT:
A cement is a binder a substance used for construction that sets, hardens, and adheres to
other materials to bind them together. Cement is seldom used on its own, but rather to
bind sand and gravel (aggregate) together. Cement mixed with fine aggregate
produces mortar for masonry, or with sand and gravel, produces concrete. Quality of
cement is based on grade of cement. The grade of cement are as-
33 grades
43 grades
53 grades
Aggregate are small pieces of broken stones in irregular size and shapes. Neat cement is
very rarely used in construction works since it is liable to shrink too much and becomes
cracks on setting. More over,it will be costly to use neat cement in construction work.
Therefore cement is mixed with some inert strong & durable hard materials. They also
reduce the cost of concrete because they are comparative much cheaper as cement.
TYPES OF AGGREGATES:
1. Fine Aggregate
2. Coarse Aggregate
1. FINE OF AGGREGATES (SAND):
The aggregate, which pass through 4.75 mm, I.S. Sieve and entirely retain on 75 micron
(0.75mm) I.S. Sieve is known as fine aggregate.
2. COARSE AGGREGATE:
The aggregate, which pass through 75mm I.S. Sieve and entirely retain on 4.75 I.S. Sieve
is known as coarse aggregates. At the site the coarse aggregate was 10mm &20mm
(graded).
Upon contact with each other, the cement paste and steel rebar form a non- reactive
surface film preventing corrosion.
Reinforcement bars or beams can be strategically set throughout the concrete to achieve
the required system.
The bond created by utilizing rebar and concrete can also be attributed to the ridged rebar
surface. The allows stresses to transfer from the concrete to the steel, and from the steel to
concrete.
Concrete and steel have similar thermal expansion coefficients. Upon freezing or heating,
they contract and expand in a similar manner, maintaining the structure needed.
Slab is curved with water by forming blocks with sand and filling them by water on slab,
for minimum 25 days.
8. VIBRATORS:
37
(Fig 13.) : VIBRATORS
9. DUCT:
In this project duct used to throughout the pipes, cables, sewer pipes etc.
38
10. EXPANSION JOINTS:
Joints provided to accommodate the expansion of adjacent building parts and relieve
compressive stresses that may otherwise develop. Expansion joints essentially provide a
space between the parts and may sometimes be provided with the load transmitting
devices between the parts and generally filled with expansion of adjacent parts, and
having ability to regain 75 percent of the original thickness, when pressure is released.
Brick work above plinth level is called brick work in super structure. Brick work in super
structure transfer the loads of RCC beam and slabs to the foundation of the walls. Doors,
Windows and ventilators are accommodated in this part of brick work. This part of the
39
building is used to divide the space into required room etc. outer walls may be used for
ornamental design of the building.
11.2 BRICK WORK ACCORDING TO CEMENT MORTAR
RATIO:
Brick walls constructed with cement sand mortar 1:4 ratio 1 part of cement and 4 part of
sand. This mortar is of high strength and is recommended for following constructions
works.
Multi storey buildings
Heavy weight/load bearing walls
In earth quake zones
Brick walls constructed with cement sand mortar 1:6 ratio means 1 part of cement and 6
parts of sand. This mortar is of medium strength and is recommended for following
construction works.
Brick walls constructed with cement sand mortar in the ratio of 1:7 means 1 part of
cement and 7 parts of sand. This mortar is low in strength and is recommended for
following works.
Toe walls
Single storey buildings
Temporary structures
Light weight wall having no load of beams etc.
40
CONCLUSION
The internship is a building between the theoretical and the practical knowledge in the
field of construction in the civil engineering work. We all who take the internship class go
to companies that already working either as a consultant or a contractor. The
responsibilities of the hosting company are to teach student and shape them in the four
month as a real site workers. My hosting company is a consultant team and they help
different knowledge in different positions. They collaborate with the contractors to teach
us in that section and believe that the civil engineer work is more important for us than the
consulting office.
This program played an important role to break the conventional thought that field work
can only be implemented by the students who hold a degree or people who have an
experience in building construction. We were able to acquire a high level of confidence to
deal with problems that arise in a building construction. I took my internship session in the
consulting site HPPWD construction under the total guidance of Er. Parveen Talwar
which help me to gain more knowledge by seeing what they work in their own office and
what is their main responsibilities to the client and also each other.
They help me to understand what is going to be when I work in the consultant office. The
contractor also avail practical knowledge for us to improve our practical knowledge status
in the field and also the contractor make us more familiar with the site works starting from
communication skills ; handling of different site works equipment utilization of man
power control to finishing of work within the time scheduled by the client.
41
REFERENCE
www.hppwdgovt.in
www.wikipidia.in
www.google.in
Building construction by S K DUGGAL
42